SlideShare a Scribd company logo
1 of 29
Euro IV Tankages - CPCL Project Presentation 
Kamal Nayak B 
Lakshman L R 
Shanmukha Sreenivas P 
Shiriram Prabhu S 
21-11-2012
Project Overview 
This project involves the construction of six oil 
storage tankages for CPCL. It was part of the 
refinery expansion project in order to produce 
Euro IV grade of fuel. 
Client: Chennai Petroleum Corporation 
Limited (CPCL) 
Contractor: NR Patel & Co. (NRP) 
Project Management Consultant: 
TATA Consulting Engineers Limited (TCE)
Project Layout – (Top view) 
Naptha 
1 
Naptha 2 
Naptha 3 Naptha 4 
Diesel - 1 Diesel 2 
Gas Turbine Generator 
Input fuel from 
the above six 
tanks
SYSTEMS APPROACH
Systems Approach 
Primitive Need 
The basic need which the system has to meet is the construction of six oil storage 
(4 Naphtha, 2 diesels) tankages for CPCL. It was part of the refinery expansion 
project in order to produce Euro IV grade of fuel. 
Criteria for Evaluation 
• Budget overrun 
• Time overrun 
• Average Safety Index 
• Client performance appraisal 
• Community and Environmental impact 
• Economic and Regional development
Desired outputs 
Time : 12 Months 
Quality : API 650 Standards 
Budget: 38.4 crores 
Size (Volume): 200000 Litres (all 
6 Combined) 
Undesired outputs 
Project Overrun 
1) Cost <10 % of Budget 
2) Time < 30 days from 
Scheduled Completion 
Controllable Inputs 
Labour Costs 
Land 
Quality of Cement, Sand, Steel. 
Uncontrollable Inputs 
Labour Strikes 
Institutional Factors 
Socio Political Issues 
Environmental Inputs 
Rainfall < 2 cm/ day 
Temperature < 50 deg 
Design Parameters 
Size - 
Capacity: 200000 litres 
Operating Days 365 days 
Operating Costs 38.4 crores
General Systems model 
Land 
Labor 
Sand 
Steel 
Cement 
Money 
Time 
Quality 
Budget 
Size & Capacity 
Natural Calamities 
Socio Political 
Issues 
Construction 
of 6 storage 
tanks 
Inputs Outputs
Evaluation of alternatives 
Prefabricated knock-down 
Storage tanks 
Reinforced Stainless Steel 
tanks
Evaluation of alternatives – Contd. 
Double walled double deck 
storage tanks 
Underground Storage 
tanks(UST) 
Reinforced steel tanks meet all criteria !!!
Timeline
WBS 
• The project has been fragmented in to the following. 
o Design and detailed Engineering 
o Supply of materials 
o Civil works 
o Mechanical works
SCHEDULING
Scheduling 
• Scheduling done on MS-Project 
• Project duration – 480 days 
• PERT – One and three time estimate 
• Critical Path 
o Apart from structural work – foam and cooling system – everything else 
is on the critical path.
SCHEDULING 
• Project scheduling is the most important tool for determining how the 
available and relevant resources should be integrated so that synergy will 
be produced. 
• The estimated duration for the entire project is 375 days. 
• The schedule was prepared by a group of experts comprising of Project 
personnel from TCE, NR Patel Contractors and CPCL. 
• The ideal time of completion is estimated is based on the priority level of 
activities, estimated start and end point of each activity, followed 
by their interdependence.
PERT 
• Before the commencement of the project, a detailed PERT analysis was performed to 
analyse the critical paths and the expected time of completion of the different 
constituent paths. 
• Review meetings were conducted weekly to analyse the progress of the project. A 
monthly project review meeting happened where a detailed review was performed on 
the status of the project. 
• A bi-monthly review meeting attended by the Board members of CPCL, top 
management of CPCL, top managers from TCE, the CEO of N R Patel & Co., the PERT 
was modified. So every 2 months the PERT was modified with the consent of CPCL 
and TCE. 
• The PERT present is the modified PERT after eight months of commencement of the 
project. This approximately reflects the status of the project mid-way.
oCritical path hyperlink 
oThree time estimates
COSTING
Cost break up 
• Direct cost 
o Labor cost 
o Non labor cost 
• Indirect cost 
o Overheads 
o G & A expenses
• Rate of return: 
Rate of return = X 100 
Where, E = 794.63 crores ; C = 38.4 crores ; N = 50 years 
Rate of return = 39.2 % 
• Payback period: 
According to the calculations payback period = 16 years 4 months 
• Discounted cash flow and NPV: 
The net present value = Rs 1.13 crores. 
• Quantity of fuel in the tanks = 
200000 litres 
• Weighted average price of diesel 
and naphtha = Rs 50.5 
• Life time of the project post 
commissioning = 50 years.
Project Cost Accounting System (PCAS) 
• Activity-Based Costing (ABC) is used in our study project for PCAS. 
• ABC is used to identify, describe, assign costs to, and report on 
operational performance.
Tenrox project cost and billing software helped in 
• Set budgets for project cost and billing; setup notifications when certain milestones 
related to Civil, Mechanical work are reached. 
• Workflow-driven approval of pre-bills submitted by the contractor and appraisal reports 
by CPCL 
• CPCL online portal to view project status and pre-bill information for the project in 
question. 
• Define Purchase Orders (PO) associated with a project to generate pre-bills and track 
billable work against each PO.
• Indirect Cost = 2.8 crores + 0.12637 crores * Te 
( Te in weeks)
•HYPERLINK TO SPLIT UP 
Of costing
CRASHING 
• Objectives of Crashing : 
• To reduce the scheduled completion time to reap the results of the 
project sooner. 
• As project continue over time, the team consume indirect costs. 
• There may be direct financial penalties for not completing a project 
on time. 
Normal 
time 
Crash time Normal cost Crash cost 
480 days 470 days 38.4 crores 38.7 crores
Biz CMS (Construction Management System) – 
Integrated PMS Tool 
• Biz CMS is a comprehensive and computerized web based Project Management System tool for the 
construction sector. 
• This system is designed keeping in mind different functional areas of the industry like 
o Scheduling, 
o Budgeting, 
o Cost control, 
o Performance analysis, 
o Project Monitoring, 
o Control & Management 
• CMS is a powerful integrated platform that connects back office, estimation department, purchase 
department,project sites and vendors. 
• This system synergizes different processes from tendering, estimation, project management, sales and 
purchase in addition to inventory management with accounts.
Time 
Project 
Mangement 
System 
Diary 
Scheduling 
Budgeting& 
cost control 
Dash board 
Performance 
analysis
Some of the advantages of using a Computerized 
PMS: 
• It helps in reducing estimation time and improving accuracy. 
• The system carries out complete segregation of materials as per estimation on the basis of category, group 
and item. This also indicates preference of the brand given in the tender document which saves lot of 
time. 
• This software conducts daily update of Project Execution details in addition to Resource Utilization of 
both materials and labor. It helps improving project execution process in terms of time and money. 
• AUTOMATES 
• indent raising 
• segregation of material categories 
• request for quotation which saves lot of time.
LEARNING FROM MG 286 PROJECT MANAGEMENT 
• Define the various aspects of the project like nature, industry etc. 
• Apply the systems approach to any project and to develop a systems 
model. 
• To identify clear work definitions in a project and to build an apposite 
Work Breakdown Structure 
• Schedule projects using single time PERT, three time PERT and CPM 
• To do financial analysis and build cost estimates of project. 
• Controlling methods used in projects 
• MS Project 
• Idea about Project Costing and Accounting Software(PCAS) – Tenrox 
• Idea about Construction management software – Biz CMS
Construction of 6 CPCL Oil storage tankers - A critical Project Management perspective

More Related Content

What's hot

CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar BeheraTarun Behera
 
Kalyan Chunchu Resume
Kalyan Chunchu Resume Kalyan Chunchu Resume
Kalyan Chunchu Resume Kalyan Chunchu
 
Project cost management a simplified approach ppt - Oracle Primavera Collab...
Project cost management   a simplified approach ppt - Oracle Primavera Collab...Project cost management   a simplified approach ppt - Oracle Primavera Collab...
Project cost management a simplified approach ppt - Oracle Primavera Collab...p6academy
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy systempriyang2004
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Allan Leyte
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPSagar Kaptan
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management A Makwana
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
Detailed project schedule
Detailed project scheduleDetailed project schedule
Detailed project schedulePeica Ionela
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
05 Project Monitoring &amp; Cost Control
05 Project Monitoring &amp; Cost Control05 Project Monitoring &amp; Cost Control
05 Project Monitoring &amp; Cost Controlakashpadole
 
PMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPeter Mello
 
How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003bebocole
 

What's hot (20)

CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar Behera
 
Kalyan Chunchu Resume
Kalyan Chunchu Resume Kalyan Chunchu Resume
Kalyan Chunchu Resume
 
Project cost management a simplified approach ppt - Oracle Primavera Collab...
Project cost management   a simplified approach ppt - Oracle Primavera Collab...Project cost management   a simplified approach ppt - Oracle Primavera Collab...
Project cost management a simplified approach ppt - Oracle Primavera Collab...
 
Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
CV-Balamurugan.
CV-Balamurugan.CV-Balamurugan.
CV-Balamurugan.
 
Detailed project schedule
Detailed project scheduleDetailed project schedule
Detailed project schedule
 
Allwyn-PE-CV
Allwyn-PE-CVAllwyn-PE-CV
Allwyn-PE-CV
 
Allwyn Leo CV
Allwyn Leo CVAllwyn Leo CV
Allwyn Leo CV
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Resume of Hariom
Resume of HariomResume of Hariom
Resume of Hariom
 
05 Project Monitoring &amp; Cost Control
05 Project Monitoring &amp; Cost Control05 Project Monitoring &amp; Cost Control
05 Project Monitoring &amp; Cost Control
 
PMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/Manaus
 
How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003
 
Chap09
Chap09Chap09
Chap09
 

Viewers also liked

Industrial View of Crude-oil Scheduling Problems
Industrial View of Crude-oil Scheduling ProblemsIndustrial View of Crude-oil Scheduling Problems
Industrial View of Crude-oil Scheduling ProblemsBrenno Menezes
 
Oil 101: Introduction to Oil and Gas - Midstream
Oil 101:  Introduction to Oil and Gas - MidstreamOil 101:  Introduction to Oil and Gas - Midstream
Oil 101: Introduction to Oil and Gas - MidstreamEKT Interactive
 
Oil 101: Introduction to Oil and Gas - Downstream
Oil 101:  Introduction to Oil and Gas - DownstreamOil 101:  Introduction to Oil and Gas - Downstream
Oil 101: Introduction to Oil and Gas - DownstreamEKT Interactive
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
143137557 storage-tanks
143137557 storage-tanks143137557 storage-tanks
143137557 storage-tanksbernard347
 
Oil 101: Introduction to Oil and Gas - Upstream
Oil 101:  Introduction to Oil and Gas - UpstreamOil 101:  Introduction to Oil and Gas - Upstream
Oil 101: Introduction to Oil and Gas - UpstreamEKT Interactive
 
Storage tanks basic training (rev 2)
Storage tanks basic training (rev 2)Storage tanks basic training (rev 2)
Storage tanks basic training (rev 2)ledzung
 

Viewers also liked (10)

kabitaa tech neww PPT
kabitaa tech neww PPTkabitaa tech neww PPT
kabitaa tech neww PPT
 
Industrial View of Crude-oil Scheduling Problems
Industrial View of Crude-oil Scheduling ProblemsIndustrial View of Crude-oil Scheduling Problems
Industrial View of Crude-oil Scheduling Problems
 
Oil 101: Introduction to Oil and Gas - Midstream
Oil 101:  Introduction to Oil and Gas - MidstreamOil 101:  Introduction to Oil and Gas - Midstream
Oil 101: Introduction to Oil and Gas - Midstream
 
Oil and gas separators
Oil and gas separatorsOil and gas separators
Oil and gas separators
 
Oil 101: Introduction to Oil and Gas - Downstream
Oil 101:  Introduction to Oil and Gas - DownstreamOil 101:  Introduction to Oil and Gas - Downstream
Oil 101: Introduction to Oil and Gas - Downstream
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
143137557 storage-tanks
143137557 storage-tanks143137557 storage-tanks
143137557 storage-tanks
 
Tank design - word
Tank design - wordTank design - word
Tank design - word
 
Oil 101: Introduction to Oil and Gas - Upstream
Oil 101:  Introduction to Oil and Gas - UpstreamOil 101:  Introduction to Oil and Gas - Upstream
Oil 101: Introduction to Oil and Gas - Upstream
 
Storage tanks basic training (rev 2)
Storage tanks basic training (rev 2)Storage tanks basic training (rev 2)
Storage tanks basic training (rev 2)
 

Similar to Construction of 6 CPCL Oil storage tankers - A critical Project Management perspective

projectmanagement-123765482.pdf
projectmanagement-123765482.pdfprojectmanagement-123765482.pdf
projectmanagement-123765482.pdfAmarDeo7
 
Project management
Project managementProject management
Project managementtwilight89
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Ian Carr SCMP, MCIPS
 
Cost and time estimation methods pros and cons
Cost and time estimation methods pros and consCost and time estimation methods pros and cons
Cost and time estimation methods pros and consPragnendra Rahevar
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 ) SAJJAD KHUDHUR ABBAS
 
Presentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantPresentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantabhishekthakur309
 
Following the-EXEED-methodology: data centre design
Following the-EXEED-methodology: data centre designFollowing the-EXEED-methodology: data centre design
Following the-EXEED-methodology: data centre designSustainableEnergyAut
 
module 2 Lec 1 CEM Construction project planning.pdf
module 2 Lec 1 CEM Construction project planning.pdfmodule 2 Lec 1 CEM Construction project planning.pdf
module 2 Lec 1 CEM Construction project planning.pdfkeyurcha
 
Current Capabilities Presentation 050416
Current Capabilities Presentation 050416Current Capabilities Presentation 050416
Current Capabilities Presentation 050416Roger Boyette
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Chris Baichoo
 
CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)sundeep khare
 

Similar to Construction of 6 CPCL Oil storage tankers - A critical Project Management perspective (20)

projectmanagement-123765482.pdf
projectmanagement-123765482.pdfprojectmanagement-123765482.pdf
projectmanagement-123765482.pdf
 
Project management
Project managementProject management
Project management
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
sounder
soundersounder
sounder
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
 
Cost and time estimation methods pros and cons
Cost and time estimation methods pros and consCost and time estimation methods pros and cons
Cost and time estimation methods pros and cons
 
Sachin Mohelay
Sachin MohelaySachin Mohelay
Sachin Mohelay
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
Presentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantPresentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plant
 
Prashant Wani1
Prashant Wani1Prashant Wani1
Prashant Wani1
 
Manikandan Energy Engineer
Manikandan Energy EngineerManikandan Energy Engineer
Manikandan Energy Engineer
 
Varun Garg_CV
Varun Garg_CVVarun Garg_CV
Varun Garg_CV
 
Following the-EXEED-methodology: data centre design
Following the-EXEED-methodology: data centre designFollowing the-EXEED-methodology: data centre design
Following the-EXEED-methodology: data centre design
 
module 2 Lec 1 CEM Construction project planning.pdf
module 2 Lec 1 CEM Construction project planning.pdfmodule 2 Lec 1 CEM Construction project planning.pdf
module 2 Lec 1 CEM Construction project planning.pdf
 
Current Capabilities Presentation 050416
Current Capabilities Presentation 050416Current Capabilities Presentation 050416
Current Capabilities Presentation 050416
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
 
Sachin Mohelay
Sachin MohelaySachin Mohelay
Sachin Mohelay
 
CV-Sounder
CV-SounderCV-Sounder
CV-Sounder
 
CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)
 

More from Shanmukha S. Potti

Technology analysis using patent citation network of a seminal patent final
Technology analysis using patent citation network of a seminal patent finalTechnology analysis using patent citation network of a seminal patent final
Technology analysis using patent citation network of a seminal patent finalShanmukha S. Potti
 
Technology Analysis Using Patent Citation Network of a Seminal Patent
Technology Analysis Using Patent Citation Network of a Seminal PatentTechnology Analysis Using Patent Citation Network of a Seminal Patent
Technology Analysis Using Patent Citation Network of a Seminal PatentShanmukha S. Potti
 
A brief introduction to 'R' statistical package
A brief introduction to 'R' statistical packageA brief introduction to 'R' statistical package
A brief introduction to 'R' statistical packageShanmukha S. Potti
 
BIDIRECTIONAL SPEED CONTROL OF DC MOTOR USING 8051 MICROCONTROLLER
BIDIRECTIONAL SPEED CONTROL OF DC MOTOR USING 8051 MICROCONTROLLERBIDIRECTIONAL SPEED CONTROL OF DC MOTOR USING 8051 MICROCONTROLLER
BIDIRECTIONAL SPEED CONTROL OF DC MOTOR USING 8051 MICROCONTROLLERShanmukha S. Potti
 
Proactive planning for catastrophic events in supply chains
Proactive planning for catastrophic events in supply chainsProactive planning for catastrophic events in supply chains
Proactive planning for catastrophic events in supply chainsShanmukha S. Potti
 
Time series data mining techniques
Time series data mining techniquesTime series data mining techniques
Time series data mining techniquesShanmukha S. Potti
 
HR Analytics: New approaches, higher returns on human capital investment
HR Analytics: New approaches, higher returns on human capital investmentHR Analytics: New approaches, higher returns on human capital investment
HR Analytics: New approaches, higher returns on human capital investmentShanmukha S. Potti
 
Commercialization Options for a set of Wireless Patents
Commercialization Options for a set of Wireless PatentsCommercialization Options for a set of Wireless Patents
Commercialization Options for a set of Wireless PatentsShanmukha S. Potti
 
How NOT to make a presentation!!
How NOT to make a presentation!!How NOT to make a presentation!!
How NOT to make a presentation!!Shanmukha S. Potti
 

More from Shanmukha S. Potti (9)

Technology analysis using patent citation network of a seminal patent final
Technology analysis using patent citation network of a seminal patent finalTechnology analysis using patent citation network of a seminal patent final
Technology analysis using patent citation network of a seminal patent final
 
Technology Analysis Using Patent Citation Network of a Seminal Patent
Technology Analysis Using Patent Citation Network of a Seminal PatentTechnology Analysis Using Patent Citation Network of a Seminal Patent
Technology Analysis Using Patent Citation Network of a Seminal Patent
 
A brief introduction to 'R' statistical package
A brief introduction to 'R' statistical packageA brief introduction to 'R' statistical package
A brief introduction to 'R' statistical package
 
BIDIRECTIONAL SPEED CONTROL OF DC MOTOR USING 8051 MICROCONTROLLER
BIDIRECTIONAL SPEED CONTROL OF DC MOTOR USING 8051 MICROCONTROLLERBIDIRECTIONAL SPEED CONTROL OF DC MOTOR USING 8051 MICROCONTROLLER
BIDIRECTIONAL SPEED CONTROL OF DC MOTOR USING 8051 MICROCONTROLLER
 
Proactive planning for catastrophic events in supply chains
Proactive planning for catastrophic events in supply chainsProactive planning for catastrophic events in supply chains
Proactive planning for catastrophic events in supply chains
 
Time series data mining techniques
Time series data mining techniquesTime series data mining techniques
Time series data mining techniques
 
HR Analytics: New approaches, higher returns on human capital investment
HR Analytics: New approaches, higher returns on human capital investmentHR Analytics: New approaches, higher returns on human capital investment
HR Analytics: New approaches, higher returns on human capital investment
 
Commercialization Options for a set of Wireless Patents
Commercialization Options for a set of Wireless PatentsCommercialization Options for a set of Wireless Patents
Commercialization Options for a set of Wireless Patents
 
How NOT to make a presentation!!
How NOT to make a presentation!!How NOT to make a presentation!!
How NOT to make a presentation!!
 

Recently uploaded

Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
self respect is very important in this crual word where everyone in just thin...
self respect is very important in this crual word where everyone in just thin...self respect is very important in this crual word where everyone in just thin...
self respect is very important in this crual word where everyone in just thin...afaqsaeed463
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 

Recently uploaded (17)

Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
self respect is very important in this crual word where everyone in just thin...
self respect is very important in this crual word where everyone in just thin...self respect is very important in this crual word where everyone in just thin...
self respect is very important in this crual word where everyone in just thin...
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 

Construction of 6 CPCL Oil storage tankers - A critical Project Management perspective

  • 1. Euro IV Tankages - CPCL Project Presentation Kamal Nayak B Lakshman L R Shanmukha Sreenivas P Shiriram Prabhu S 21-11-2012
  • 2. Project Overview This project involves the construction of six oil storage tankages for CPCL. It was part of the refinery expansion project in order to produce Euro IV grade of fuel. Client: Chennai Petroleum Corporation Limited (CPCL) Contractor: NR Patel & Co. (NRP) Project Management Consultant: TATA Consulting Engineers Limited (TCE)
  • 3. Project Layout – (Top view) Naptha 1 Naptha 2 Naptha 3 Naptha 4 Diesel - 1 Diesel 2 Gas Turbine Generator Input fuel from the above six tanks
  • 5. Systems Approach Primitive Need The basic need which the system has to meet is the construction of six oil storage (4 Naphtha, 2 diesels) tankages for CPCL. It was part of the refinery expansion project in order to produce Euro IV grade of fuel. Criteria for Evaluation • Budget overrun • Time overrun • Average Safety Index • Client performance appraisal • Community and Environmental impact • Economic and Regional development
  • 6. Desired outputs Time : 12 Months Quality : API 650 Standards Budget: 38.4 crores Size (Volume): 200000 Litres (all 6 Combined) Undesired outputs Project Overrun 1) Cost <10 % of Budget 2) Time < 30 days from Scheduled Completion Controllable Inputs Labour Costs Land Quality of Cement, Sand, Steel. Uncontrollable Inputs Labour Strikes Institutional Factors Socio Political Issues Environmental Inputs Rainfall < 2 cm/ day Temperature < 50 deg Design Parameters Size - Capacity: 200000 litres Operating Days 365 days Operating Costs 38.4 crores
  • 7. General Systems model Land Labor Sand Steel Cement Money Time Quality Budget Size & Capacity Natural Calamities Socio Political Issues Construction of 6 storage tanks Inputs Outputs
  • 8. Evaluation of alternatives Prefabricated knock-down Storage tanks Reinforced Stainless Steel tanks
  • 9. Evaluation of alternatives – Contd. Double walled double deck storage tanks Underground Storage tanks(UST) Reinforced steel tanks meet all criteria !!!
  • 11. WBS • The project has been fragmented in to the following. o Design and detailed Engineering o Supply of materials o Civil works o Mechanical works
  • 13. Scheduling • Scheduling done on MS-Project • Project duration – 480 days • PERT – One and three time estimate • Critical Path o Apart from structural work – foam and cooling system – everything else is on the critical path.
  • 14. SCHEDULING • Project scheduling is the most important tool for determining how the available and relevant resources should be integrated so that synergy will be produced. • The estimated duration for the entire project is 375 days. • The schedule was prepared by a group of experts comprising of Project personnel from TCE, NR Patel Contractors and CPCL. • The ideal time of completion is estimated is based on the priority level of activities, estimated start and end point of each activity, followed by their interdependence.
  • 15. PERT • Before the commencement of the project, a detailed PERT analysis was performed to analyse the critical paths and the expected time of completion of the different constituent paths. • Review meetings were conducted weekly to analyse the progress of the project. A monthly project review meeting happened where a detailed review was performed on the status of the project. • A bi-monthly review meeting attended by the Board members of CPCL, top management of CPCL, top managers from TCE, the CEO of N R Patel & Co., the PERT was modified. So every 2 months the PERT was modified with the consent of CPCL and TCE. • The PERT present is the modified PERT after eight months of commencement of the project. This approximately reflects the status of the project mid-way.
  • 16. oCritical path hyperlink oThree time estimates
  • 18. Cost break up • Direct cost o Labor cost o Non labor cost • Indirect cost o Overheads o G & A expenses
  • 19. • Rate of return: Rate of return = X 100 Where, E = 794.63 crores ; C = 38.4 crores ; N = 50 years Rate of return = 39.2 % • Payback period: According to the calculations payback period = 16 years 4 months • Discounted cash flow and NPV: The net present value = Rs 1.13 crores. • Quantity of fuel in the tanks = 200000 litres • Weighted average price of diesel and naphtha = Rs 50.5 • Life time of the project post commissioning = 50 years.
  • 20. Project Cost Accounting System (PCAS) • Activity-Based Costing (ABC) is used in our study project for PCAS. • ABC is used to identify, describe, assign costs to, and report on operational performance.
  • 21. Tenrox project cost and billing software helped in • Set budgets for project cost and billing; setup notifications when certain milestones related to Civil, Mechanical work are reached. • Workflow-driven approval of pre-bills submitted by the contractor and appraisal reports by CPCL • CPCL online portal to view project status and pre-bill information for the project in question. • Define Purchase Orders (PO) associated with a project to generate pre-bills and track billable work against each PO.
  • 22. • Indirect Cost = 2.8 crores + 0.12637 crores * Te ( Te in weeks)
  • 23. •HYPERLINK TO SPLIT UP Of costing
  • 24. CRASHING • Objectives of Crashing : • To reduce the scheduled completion time to reap the results of the project sooner. • As project continue over time, the team consume indirect costs. • There may be direct financial penalties for not completing a project on time. Normal time Crash time Normal cost Crash cost 480 days 470 days 38.4 crores 38.7 crores
  • 25. Biz CMS (Construction Management System) – Integrated PMS Tool • Biz CMS is a comprehensive and computerized web based Project Management System tool for the construction sector. • This system is designed keeping in mind different functional areas of the industry like o Scheduling, o Budgeting, o Cost control, o Performance analysis, o Project Monitoring, o Control & Management • CMS is a powerful integrated platform that connects back office, estimation department, purchase department,project sites and vendors. • This system synergizes different processes from tendering, estimation, project management, sales and purchase in addition to inventory management with accounts.
  • 26. Time Project Mangement System Diary Scheduling Budgeting& cost control Dash board Performance analysis
  • 27. Some of the advantages of using a Computerized PMS: • It helps in reducing estimation time and improving accuracy. • The system carries out complete segregation of materials as per estimation on the basis of category, group and item. This also indicates preference of the brand given in the tender document which saves lot of time. • This software conducts daily update of Project Execution details in addition to Resource Utilization of both materials and labor. It helps improving project execution process in terms of time and money. • AUTOMATES • indent raising • segregation of material categories • request for quotation which saves lot of time.
  • 28. LEARNING FROM MG 286 PROJECT MANAGEMENT • Define the various aspects of the project like nature, industry etc. • Apply the systems approach to any project and to develop a systems model. • To identify clear work definitions in a project and to build an apposite Work Breakdown Structure • Schedule projects using single time PERT, three time PERT and CPM • To do financial analysis and build cost estimates of project. • Controlling methods used in projects • MS Project • Idea about Project Costing and Accounting Software(PCAS) – Tenrox • Idea about Construction management software – Biz CMS

Editor's Notes

  1. This template can be used as a starter file to give updates for project milestones. Sections Right-click on a slide to add sections. Sections can help to organize your slides or facilitate collaboration between multiple authors. Notes Use the Notes section for delivery notes or to provide additional details for the audience. View these notes in Presentation View during your presentation. Keep in mind the font size (important for accessibility, visibility, videotaping, and online production) Coordinated colors Pay particular attention to the graphs, charts, and text boxes. Consider that attendees will print in black and white or grayscale. Run a test print to make sure your colors work when printed in pure black and white and grayscale. Graphics, tables, and graphs Keep it simple: If possible, use consistent, non-distracting styles and colors. Label all graphs and tables.
  2. What is the project about? Define the goal of this project Is it similar to projects in the past or is it a new effort? Define the scope of this project Is it an independent project or is it related to other projects? * Note that this slide is not necessary for weekly status meetings
  3. * If any of these issues caused a schedule delay or need to be discussed further, include details in next slide.