CONTENTS
• Training site and organization
• Bus Ducts
• Why bus ducts, why not cables
• Types of bus ducts
• Force acting on bus Bars
• Bus ducts accessories
• Ingress protection
• Test performed on bus ducts and their types
TRAINING SITE AND ORGANIZATION
• Bharat Heavy Electricals Ltd. (BHEL), Rudrapur, Uttrakhand
• Established in March 1983
• It’s a Component Fabrication Plant (CFP)
• Manufacturing Product is Bus Ducts ( All 3 Types)
• BHEL turn over: Rupees 10,341.58 Crores (2017-2018)
Rupees 10,476.28 Crore (2016-2017)
• Largest Plants: (1) Tiruchipalli (Tamil Nadu)
(2) Bhopal (MP)
• It also have International Customers: Malaysia, Oman, Iraq, UAE, Bhutan, Egypt, New Zealand
OTHER
BRANCHES
These are some of the
Manufacturing units(17),
Repair Units(02) and BHEL
Subsidiary(01).
BHEL Manufacturing Units Bangalore Electronics Division
Electronics Systems Division
Electro Porcelain Division
Bhopal Heavy Electrical Plant
Goindwal Industrial Valves Plant
Haridwar Heavy Electrical Equipment Plant
Central Foundry Forge Plant
Hydrabad Heavy Power Equipment Plant
Jagdishpur Insulator Plant
Centralized Stamping Unit
Jhansi Transformer Plant
Rudrapur Component Fabrication Plant
Ranipet Boiler Auxiliaries Plant
Tiruchirappalli High Pressure Boiler Plant
Seamless Steel Tube Plant
Thirumayam Power Plant Piping Unit
Visakhapatnam Heavy Plates and Vessels Plant
BHEL Repair Units Mumbai Electrical Machine Repair Plant
Varanasi Heavy Equipment Repair Plant
BHEL Subsidiary Kasaragod BHEL Electrical Machines
BUS DUCTS
J U S T A FA N C Y N A M E F O R C O N D U C TO R S
BUS DUCTS
• These are the hollow conductor, used to carry current from generator to transformer.
• These have High current and voltage handling capacity
• Material used may be Copper or Aluminium
• These materials are according to the demand of Customer
• Design either defined by the customer or suggested by Company
• These are according to the ISO standards
• Conductor Shape can be a Bar, Cubical or Cylindrical
• Magnetic field due to the conductor is reduced up to 95% due to this hollow design.
• There are two main part of the Duct which are the Enclosure and Conductor.
CONDUCTORS
• Thick and hollow
• Usually made up of Aluminium
• Ends of conductors are silver polished.
• There are some cutting on regular distance on it to make the heat escape.
• outside and inside of the conductor is painted with black color to minimize the heat
reflection.
• Ends of the conductor are angled just to make effective welding with another
conductor.
ENCLOSURE
• It is the outer part of the bus duct
• It is used for protection of humans and conductors.
• It also made up of Aluminum
• Aluminum is used because it is non-magnetic and light in weight and easier to
fabricate.
• It is made dust tight to protect the conductor from potential faults.
• It is also painted black from inside for the same purpose.
• Outer color is demanded by the customer.
WHY BUS DUCT
WHY NOT
CABLES????
Q U E S T I O N O F T H E E R A …
• Cables have very low short circuit current withstand capacity in comparison with Bus
ducts
• More material is used to make cable for such rating.
• Cables become Bulky
• Hard to install
• Repair and maintenance is not easy for cables
• Installation of cables is very difficult and may stress other equipment
• Current carrying capacity of bus duct is much higher than cables
• Voltage drop is bus ducts is much lower than cables
• Insulation is not practical or if possible it is not reliable.
• Connection to electrical equipment like Switch gear and transformers is not easy, its
more stressful.
T YPE OF BUS
DUCTS
There are 3 types of
bus ducts which are
also further divided
according to working
and construction.
The adjacent figure
shows the different
categories of Bus
Ducts.
Bus Ducts
Isolated Phase Bus
Ducts
Discontinuous Continuous
Natural Cooled Forced Cooled
Segregated Phase
Bus Ducts
Non-segregated
phase Bus Ducts
ISOLATED
PHASE BUS
DUCT
V E R Y H I G H C U R R E N T R AT I N G S
I S O L AT E D P H A S E
B U S D U C T
• Abbreviation: IPBD
• Connected between Generator and Generating
Transformer.
• Each phase is separated or isolated
• Thickness and diameter of conductor depend on the
current rating of Duct.
• Rating of the IPBD starts from 1200 Amp to 31000
Amps.
• Classified into three parts according to the connection
schemes: > Main run
> Delta Run
> Tap-off
DESIGN ASPECTS AND CRITERIA
• Rated Continuous Current for main bus: 19000 Amps
• Rated Continuous Current for Tap off bus: 1600 Amps
• Rated voltage 21KV
• Short time current for main bus 135 KA RMS for 3 sec
• Short timer current for tap off bus 254KA RMS for 1 sec
• Temperature rise allowed for bus enclosure 30 to 50° Celsius
• Temperature rise allowed for bus conductor 40° for plain bolt joint
50° to 55° for silver plated joint
These are the parameters for 2X500 MW plant at TUTICORIN, Tamil Nadu
CONSTRUCTIONAL ASPECTS
• Enclosure is made up of aluminum alloy, this is usually shorter than conductor.
• Additional channel rings are used to fill the gap between two enclosure.
• Conductors are not completely in cylindrical shape it have some cuttings to pass the
heat produced in internal portion.
• Conductor have some holes to mount insulators.
• Coloring schemes.
• Enclosure also have a inspection window for routine checkups.
• These sections also have a hot air blower or HAB.
• There are also some Seal-off bushings at the end of the sections.
SEGREGATED
PHASE BUS
DUCT
A L L T H R E E P H A S E I N O N E D U C T
S E G R E G AT E D P H A S E
B U S D U C T
• Abbreviation: SPBD
• Generally used for medium voltages.
• These are used to connect equipment like switch
gear from unit aux transformers
• It have common enclosure but separated by Al
sheet
• This provide non-magnitude barrier.
• Conductor may by copper of aluminum.
• Supporting insulators are made up of porcelain or
epoxy resin.
• It may be Bar, Cuboidal or cylindrical in shape.
• Can also be used to form link between LAVT, UAT,
NGC etc.
DESIGN ASPECT AND CRITERIAFollowing parameters are given for 500 MW Power Plant
CONSTRUCTIONAL ASPECTS
• Enclosure is made up of aluminum alloy, sheet provided is of length of 3.72 meters.
• Barrier plate is of thickness 2mm which provide complete phase segregation.
• Inspection windows are also provided near the joints where is High Resistance is used
to make duct air tight or weather proof.
• Space heater(HAB) are also used here for the same purpose.
• Thermistor is also used which keep track of temperature inside duct.
NON-SEGREGATED PHASE BUS DUCT
• The only difference between the SPBD and NSPBD is that there is no separation barrier
between the phases.
• Also the current rating is not so wide.
Difference in current rating of these 3 are given
below>>
INGRESS
PROTECTION
P R OT E C T I O N O F C U B I C L E S
DESIGN AND
SELECTION
CRITERIA
FA C TO R S D E C I D I N G D E S I G N A N D
S E L E C T I O N
DESIGN DEPEND UPON FOLLOWING
FACTORS
• The continuous current rating
• Maximum system voltage
• Maximum dynamic forces it may be subjected to during its life span
• The dielectric requirement of the system
• Climatic conditions
SELECTION CRITERIA
• Current carrying capability
• The resistivity required for permissible thermal limits
• Forces between the different conductors in short circuit condition
• Skin effects
• Proximity effects
• Effects of solar radiation on temperature rise
• Seismic condition
Shape and size of the bus ducts is selected considering the following aspects:
FORCES ACTING
ON BUS BAR
W H AT B U S D U C T S H AV E TO FA C E
• Weight :
Dusts are made from Aluminum, so it light in weight
It is also easier to support the main bus bar inside the enclosure.
Supported using insulators.
• Wind and ice
If bus ducts are outside, forces like wind and ice are also considered.
This is taken into account and the radial thickness should be 9.5 mm.
• Expansion forces
Due to the Temperature rise and fall the conductor, expends and contracts
respectively. So there will be relative motion between the two adjacent bars.
BUS DUCT
ACCESSORIES
A U X I L I A R Y PA R T O F B U S D U C T
CURRENT
TRANSFORMERS
• It is mounted within the enclosure, suitable for
operation at an ambient temperature.(90° to 100°)
• The CT secondary boxes are brought through the
marshalling boxes.
• Marshalling boxes have the terminal blocks
provide the facility of shorting and grounding.
L AV T CUBICLES• VT, SC and LA all three present in one cubicle
• Generally IP 52 protection is used
• Supplied from tap off bus duct.
• Fabricated from cold rolled sheet of Aluminum
(2mm)
• There is a automated shutter mechanism for isolation
when carriage is out.
• Generally the number of VTs are four but it depends
upon the customer.
NGT CUBICLES
• It consists of two parts which are NGT and NGR.
• Both are located in separated chambers of cubicle
• Painted with heat resistant paint.
• Lower IP (23)
• NGT is cast epoxy resin type, natural cooled, Single
phase
• Secondary is connected to the NGR.
• This is made from anti-aging, corrosion resistant
punched stainless steel grid.
• This is designed for indoors, for temperature rise as per
IEEE 32
OTHER AUXILIARY PARTS
• Seal off bushing: made up of cast resin and used at the equipment termination.
• Rubber Bellow: provided between the sections of the enclosure, provide discontinuous
path to the circulating current.
• Shorting plate: it’s a plate of Aluminum alloy, its used to make IPBD enclosure
continuous. It is used at generator end, GT ends, UT ends.
• Wall frame Assembly: These are the supporting plated used where Bus Ducts need to
penetrate the building walls, it make sure no loads are imposed
the building structure.
• Air pressurization system: Since Generator bus duct must be air tight, so the air
leakage rate shall be restricted to the minimum
ie 5% of total air volume per hour.
• HAB: It is used to maintain the moisture content inside the Bus Ducts.
• Silica gel breather: Provided in non-pressurized bus duct to keep it dry. It is used to
maintain the ingress of the duct.
TEST
PERFORMED
B E C A U S E Q U A L I T Y I S I M P O R TA N T
ROUTINE TEST
• Visual inspection
• Dry power frequency voltage withstand for 1 minute
• Milli-volt drop test
• Water-tightness test
• Insulation resistance
TYPE TEST
• Impulse voltage test
• Heat run test
• Milli-volt drop test
• Air leakage test
• Water tightness test
• Temperature rise test
ANY QUESTIONS
LEFT????
W H AT ’ S I N Y O U R M I N D
THANK
YOU
T H A N K S F O R L I S T E N I N G

More Related Content

What's hot

Esp rectifier transformer
Esp rectifier transformerEsp rectifier transformer
Esp rectifier transformer
Molla Morshad
 
132kv Substation
132kv Substation132kv Substation
132kv Substationguestecdd58
 
220 66 kv nrs sub report
220 66 kv nrs sub report220 66 kv nrs sub report
220 66 kv nrs sub report
Mayur Dhanaji Rane
 
BUSDUCT
BUSDUCTBUSDUCT
Different types of Transformers used in Generating Station
Different types of Transformers used in Generating StationDifferent types of Transformers used in Generating Station
Different types of Transformers used in Generating Station
Vasanthan Ravichandran
 
Switchgear
Switchgear Switchgear
Switchgear
dipak doud
 
Protection of three phase synchronous generator
Protection of three phase synchronous generatorProtection of three phase synchronous generator
Protection of three phase synchronous generator
Mohammad Abdullah
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
Nikhil Kachare
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Asha Anu Kurian
 
Transformer ppt
Transformer pptTransformer ppt
Transformer ppt
Rakesh Gurjar
 
Transformer Parts and functions
Transformer Parts and functionsTransformer Parts and functions
Transformer Parts and functions
Sourabh sharma
 
Magnetic contactors and magnetic starters ms-t series dienhathe.org
Magnetic contactors and magnetic starters ms-t series dienhathe.orgMagnetic contactors and magnetic starters ms-t series dienhathe.org
Magnetic contactors and magnetic starters ms-t series dienhathe.org
Dien Ha The
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 
Transformer Oil Testing
Transformer Oil TestingTransformer Oil Testing
Transformer Oil Testing
engrsurif
 
Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)
Sourabh sharma
 
armature Winding
armature Windingarmature Winding
armature Winding
vishalgohel12195
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
MANOJ KUMAR MAHARANA
 
Interlocking of motor
Interlocking of motorInterlocking of motor
Interlocking of motor
Dhiraj Sonawane
 

What's hot (20)

Esp rectifier transformer
Esp rectifier transformerEsp rectifier transformer
Esp rectifier transformer
 
132kv Substation
132kv Substation132kv Substation
132kv Substation
 
220 66 kv nrs sub report
220 66 kv nrs sub report220 66 kv nrs sub report
220 66 kv nrs sub report
 
BUSBAR PROTECTION
BUSBAR PROTECTIONBUSBAR PROTECTION
BUSBAR PROTECTION
 
BUSDUCT
BUSDUCTBUSDUCT
BUSDUCT
 
Different types of Transformers used in Generating Station
Different types of Transformers used in Generating StationDifferent types of Transformers used in Generating Station
Different types of Transformers used in Generating Station
 
Switchgear
Switchgear Switchgear
Switchgear
 
Protection of three phase synchronous generator
Protection of three phase synchronous generatorProtection of three phase synchronous generator
Protection of three phase synchronous generator
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
 
Transformer ppt
Transformer pptTransformer ppt
Transformer ppt
 
Transformer Parts and functions
Transformer Parts and functionsTransformer Parts and functions
Transformer Parts and functions
 
Magnetic contactors and magnetic starters ms-t series dienhathe.org
Magnetic contactors and magnetic starters ms-t series dienhathe.orgMagnetic contactors and magnetic starters ms-t series dienhathe.org
Magnetic contactors and magnetic starters ms-t series dienhathe.org
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
Transformer Oil Testing
Transformer Oil TestingTransformer Oil Testing
Transformer Oil Testing
 
Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)
 
Lightning arresters
Lightning arrestersLightning arresters
Lightning arresters
 
armature Winding
armature Windingarmature Winding
armature Winding
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
Interlocking of motor
Interlocking of motorInterlocking of motor
Interlocking of motor
 

Similar to Bus Ducts or Hollow conductors

Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing
Praveen Sharma
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmission
Rasika Ghongade
 
electrical materialsand accessories ch2.pptx
electrical materialsand accessories ch2.pptxelectrical materialsand accessories ch2.pptx
electrical materialsand accessories ch2.pptx
ethiouniverse
 
Electrical wiring system
Electrical wiring systemElectrical wiring system
Electrical wiring system
shweta saini
 
220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx
ssuser1b3e431
 
PPT ON CIM ,BHEL HARIDWAR
PPT ON CIM ,BHEL HARIDWARPPT ON CIM ,BHEL HARIDWAR
PPT ON CIM ,BHEL HARIDWAR
ABHISHEK SINGH
 
Fluid conductors: Design and selection criteria
Fluid conductors: Design and selection criteriaFluid conductors: Design and selection criteria
Fluid conductors: Design and selection criteria
Anand Prithviraj
 
EEE 233_Lecture-2 to 4.pptx
EEE 233_Lecture-2 to 4.pptxEEE 233_Lecture-2 to 4.pptx
EEE 233_Lecture-2 to 4.pptx
RubaiyatJaky
 
Harshitagarwal 111109034529-phpapp02
Harshitagarwal 111109034529-phpapp02Harshitagarwal 111109034529-phpapp02
Harshitagarwal 111109034529-phpapp02
k,l polytechnic roorkee
 
ELECTRICAL INSTALLATIONS PPT (1).pptx
ELECTRICAL INSTALLATIONS PPT (1).pptxELECTRICAL INSTALLATIONS PPT (1).pptx
ELECTRICAL INSTALLATIONS PPT (1).pptx
rajalakshmi769433
 
Presentation on Piping Familiarization.ppt
Presentation on Piping Familiarization.pptPresentation on Piping Familiarization.ppt
Presentation on Piping Familiarization.ppt
ashadiamir1
 
Residential wiring PPT.pptx
Residential wiring PPT.pptxResidential wiring PPT.pptx
Residential wiring PPT.pptx
vlkumashankardeekshi th
 
Underground Cables.pptx
Underground Cables.pptxUnderground Cables.pptx
Underground Cables.pptx
karthik prabhu
 
Electrical System Design
Electrical System Design Electrical System Design
Presentation-GEMCO
Presentation-GEMCOPresentation-GEMCO
Presentation-GEMCODipen Shome
 
Contactor generalizations
Contactor generalizationsContactor generalizations
Contactor generalizations
Michael O'Dell
 
Harshit agarwal
Harshit agarwalHarshit agarwal
Harshit agarwal
IIT Roorkee
 
500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPT500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPTMahadev Kovalli
 
Getting the Most out of your Electrical Room
Getting the Most out of your Electrical RoomGetting the Most out of your Electrical Room
Getting the Most out of your Electrical Room
michaeljmack
 

Similar to Bus Ducts or Hollow conductors (20)

Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmission
 
electrical materialsand accessories ch2.pptx
electrical materialsand accessories ch2.pptxelectrical materialsand accessories ch2.pptx
electrical materialsand accessories ch2.pptx
 
Electrical wiring system
Electrical wiring systemElectrical wiring system
Electrical wiring system
 
220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx
 
PPT ON CIM ,BHEL HARIDWAR
PPT ON CIM ,BHEL HARIDWARPPT ON CIM ,BHEL HARIDWAR
PPT ON CIM ,BHEL HARIDWAR
 
ALTERNATOR DESIGN
ALTERNATOR DESIGNALTERNATOR DESIGN
ALTERNATOR DESIGN
 
Fluid conductors: Design and selection criteria
Fluid conductors: Design and selection criteriaFluid conductors: Design and selection criteria
Fluid conductors: Design and selection criteria
 
EEE 233_Lecture-2 to 4.pptx
EEE 233_Lecture-2 to 4.pptxEEE 233_Lecture-2 to 4.pptx
EEE 233_Lecture-2 to 4.pptx
 
Harshitagarwal 111109034529-phpapp02
Harshitagarwal 111109034529-phpapp02Harshitagarwal 111109034529-phpapp02
Harshitagarwal 111109034529-phpapp02
 
ELECTRICAL INSTALLATIONS PPT (1).pptx
ELECTRICAL INSTALLATIONS PPT (1).pptxELECTRICAL INSTALLATIONS PPT (1).pptx
ELECTRICAL INSTALLATIONS PPT (1).pptx
 
Presentation on Piping Familiarization.ppt
Presentation on Piping Familiarization.pptPresentation on Piping Familiarization.ppt
Presentation on Piping Familiarization.ppt
 
Residential wiring PPT.pptx
Residential wiring PPT.pptxResidential wiring PPT.pptx
Residential wiring PPT.pptx
 
Underground Cables.pptx
Underground Cables.pptxUnderground Cables.pptx
Underground Cables.pptx
 
Electrical System Design
Electrical System Design Electrical System Design
Electrical System Design
 
Presentation-GEMCO
Presentation-GEMCOPresentation-GEMCO
Presentation-GEMCO
 
Contactor generalizations
Contactor generalizationsContactor generalizations
Contactor generalizations
 
Harshit agarwal
Harshit agarwalHarshit agarwal
Harshit agarwal
 
500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPT500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPT
 
Getting the Most out of your Electrical Room
Getting the Most out of your Electrical RoomGetting the Most out of your Electrical Room
Getting the Most out of your Electrical Room
 

Recently uploaded

Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 

Recently uploaded (20)

Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 

Bus Ducts or Hollow conductors

  • 1. A PRESENTATION ON BUS DUCTS P R E S E N T E D BY A J AY M E E N A
  • 2. CONTENTS • Training site and organization • Bus Ducts • Why bus ducts, why not cables • Types of bus ducts • Force acting on bus Bars • Bus ducts accessories • Ingress protection • Test performed on bus ducts and their types
  • 3. TRAINING SITE AND ORGANIZATION • Bharat Heavy Electricals Ltd. (BHEL), Rudrapur, Uttrakhand • Established in March 1983 • It’s a Component Fabrication Plant (CFP) • Manufacturing Product is Bus Ducts ( All 3 Types) • BHEL turn over: Rupees 10,341.58 Crores (2017-2018) Rupees 10,476.28 Crore (2016-2017) • Largest Plants: (1) Tiruchipalli (Tamil Nadu) (2) Bhopal (MP) • It also have International Customers: Malaysia, Oman, Iraq, UAE, Bhutan, Egypt, New Zealand
  • 4. OTHER BRANCHES These are some of the Manufacturing units(17), Repair Units(02) and BHEL Subsidiary(01). BHEL Manufacturing Units Bangalore Electronics Division Electronics Systems Division Electro Porcelain Division Bhopal Heavy Electrical Plant Goindwal Industrial Valves Plant Haridwar Heavy Electrical Equipment Plant Central Foundry Forge Plant Hydrabad Heavy Power Equipment Plant Jagdishpur Insulator Plant Centralized Stamping Unit Jhansi Transformer Plant Rudrapur Component Fabrication Plant Ranipet Boiler Auxiliaries Plant Tiruchirappalli High Pressure Boiler Plant Seamless Steel Tube Plant Thirumayam Power Plant Piping Unit Visakhapatnam Heavy Plates and Vessels Plant BHEL Repair Units Mumbai Electrical Machine Repair Plant Varanasi Heavy Equipment Repair Plant BHEL Subsidiary Kasaragod BHEL Electrical Machines
  • 5. BUS DUCTS J U S T A FA N C Y N A M E F O R C O N D U C TO R S
  • 6.
  • 7. BUS DUCTS • These are the hollow conductor, used to carry current from generator to transformer. • These have High current and voltage handling capacity • Material used may be Copper or Aluminium • These materials are according to the demand of Customer • Design either defined by the customer or suggested by Company • These are according to the ISO standards • Conductor Shape can be a Bar, Cubical or Cylindrical • Magnetic field due to the conductor is reduced up to 95% due to this hollow design. • There are two main part of the Duct which are the Enclosure and Conductor.
  • 8. CONDUCTORS • Thick and hollow • Usually made up of Aluminium • Ends of conductors are silver polished. • There are some cutting on regular distance on it to make the heat escape. • outside and inside of the conductor is painted with black color to minimize the heat reflection. • Ends of the conductor are angled just to make effective welding with another conductor.
  • 9. ENCLOSURE • It is the outer part of the bus duct • It is used for protection of humans and conductors. • It also made up of Aluminum • Aluminum is used because it is non-magnetic and light in weight and easier to fabricate. • It is made dust tight to protect the conductor from potential faults. • It is also painted black from inside for the same purpose. • Outer color is demanded by the customer.
  • 10. WHY BUS DUCT WHY NOT CABLES???? Q U E S T I O N O F T H E E R A …
  • 11. • Cables have very low short circuit current withstand capacity in comparison with Bus ducts • More material is used to make cable for such rating. • Cables become Bulky • Hard to install • Repair and maintenance is not easy for cables • Installation of cables is very difficult and may stress other equipment • Current carrying capacity of bus duct is much higher than cables • Voltage drop is bus ducts is much lower than cables • Insulation is not practical or if possible it is not reliable. • Connection to electrical equipment like Switch gear and transformers is not easy, its more stressful.
  • 12. T YPE OF BUS DUCTS There are 3 types of bus ducts which are also further divided according to working and construction. The adjacent figure shows the different categories of Bus Ducts. Bus Ducts Isolated Phase Bus Ducts Discontinuous Continuous Natural Cooled Forced Cooled Segregated Phase Bus Ducts Non-segregated phase Bus Ducts
  • 13. ISOLATED PHASE BUS DUCT V E R Y H I G H C U R R E N T R AT I N G S
  • 14. I S O L AT E D P H A S E B U S D U C T • Abbreviation: IPBD • Connected between Generator and Generating Transformer. • Each phase is separated or isolated • Thickness and diameter of conductor depend on the current rating of Duct. • Rating of the IPBD starts from 1200 Amp to 31000 Amps. • Classified into three parts according to the connection schemes: > Main run > Delta Run > Tap-off
  • 15. DESIGN ASPECTS AND CRITERIA • Rated Continuous Current for main bus: 19000 Amps • Rated Continuous Current for Tap off bus: 1600 Amps • Rated voltage 21KV • Short time current for main bus 135 KA RMS for 3 sec • Short timer current for tap off bus 254KA RMS for 1 sec • Temperature rise allowed for bus enclosure 30 to 50° Celsius • Temperature rise allowed for bus conductor 40° for plain bolt joint 50° to 55° for silver plated joint These are the parameters for 2X500 MW plant at TUTICORIN, Tamil Nadu
  • 16. CONSTRUCTIONAL ASPECTS • Enclosure is made up of aluminum alloy, this is usually shorter than conductor. • Additional channel rings are used to fill the gap between two enclosure. • Conductors are not completely in cylindrical shape it have some cuttings to pass the heat produced in internal portion. • Conductor have some holes to mount insulators. • Coloring schemes. • Enclosure also have a inspection window for routine checkups. • These sections also have a hot air blower or HAB. • There are also some Seal-off bushings at the end of the sections.
  • 17. SEGREGATED PHASE BUS DUCT A L L T H R E E P H A S E I N O N E D U C T
  • 18. S E G R E G AT E D P H A S E B U S D U C T • Abbreviation: SPBD • Generally used for medium voltages. • These are used to connect equipment like switch gear from unit aux transformers • It have common enclosure but separated by Al sheet • This provide non-magnitude barrier. • Conductor may by copper of aluminum. • Supporting insulators are made up of porcelain or epoxy resin. • It may be Bar, Cuboidal or cylindrical in shape. • Can also be used to form link between LAVT, UAT, NGC etc.
  • 19. DESIGN ASPECT AND CRITERIAFollowing parameters are given for 500 MW Power Plant
  • 20. CONSTRUCTIONAL ASPECTS • Enclosure is made up of aluminum alloy, sheet provided is of length of 3.72 meters. • Barrier plate is of thickness 2mm which provide complete phase segregation. • Inspection windows are also provided near the joints where is High Resistance is used to make duct air tight or weather proof. • Space heater(HAB) are also used here for the same purpose. • Thermistor is also used which keep track of temperature inside duct.
  • 21. NON-SEGREGATED PHASE BUS DUCT • The only difference between the SPBD and NSPBD is that there is no separation barrier between the phases. • Also the current rating is not so wide. Difference in current rating of these 3 are given below>>
  • 22. INGRESS PROTECTION P R OT E C T I O N O F C U B I C L E S
  • 23.
  • 24. DESIGN AND SELECTION CRITERIA FA C TO R S D E C I D I N G D E S I G N A N D S E L E C T I O N
  • 25. DESIGN DEPEND UPON FOLLOWING FACTORS • The continuous current rating • Maximum system voltage • Maximum dynamic forces it may be subjected to during its life span • The dielectric requirement of the system • Climatic conditions
  • 26. SELECTION CRITERIA • Current carrying capability • The resistivity required for permissible thermal limits • Forces between the different conductors in short circuit condition • Skin effects • Proximity effects • Effects of solar radiation on temperature rise • Seismic condition Shape and size of the bus ducts is selected considering the following aspects:
  • 27. FORCES ACTING ON BUS BAR W H AT B U S D U C T S H AV E TO FA C E
  • 28. • Weight : Dusts are made from Aluminum, so it light in weight It is also easier to support the main bus bar inside the enclosure. Supported using insulators. • Wind and ice If bus ducts are outside, forces like wind and ice are also considered. This is taken into account and the radial thickness should be 9.5 mm. • Expansion forces Due to the Temperature rise and fall the conductor, expends and contracts respectively. So there will be relative motion between the two adjacent bars.
  • 29. BUS DUCT ACCESSORIES A U X I L I A R Y PA R T O F B U S D U C T
  • 30. CURRENT TRANSFORMERS • It is mounted within the enclosure, suitable for operation at an ambient temperature.(90° to 100°) • The CT secondary boxes are brought through the marshalling boxes. • Marshalling boxes have the terminal blocks provide the facility of shorting and grounding.
  • 31. L AV T CUBICLES• VT, SC and LA all three present in one cubicle • Generally IP 52 protection is used • Supplied from tap off bus duct. • Fabricated from cold rolled sheet of Aluminum (2mm) • There is a automated shutter mechanism for isolation when carriage is out. • Generally the number of VTs are four but it depends upon the customer.
  • 32. NGT CUBICLES • It consists of two parts which are NGT and NGR. • Both are located in separated chambers of cubicle • Painted with heat resistant paint. • Lower IP (23) • NGT is cast epoxy resin type, natural cooled, Single phase • Secondary is connected to the NGR. • This is made from anti-aging, corrosion resistant punched stainless steel grid. • This is designed for indoors, for temperature rise as per IEEE 32
  • 33. OTHER AUXILIARY PARTS • Seal off bushing: made up of cast resin and used at the equipment termination. • Rubber Bellow: provided between the sections of the enclosure, provide discontinuous path to the circulating current. • Shorting plate: it’s a plate of Aluminum alloy, its used to make IPBD enclosure continuous. It is used at generator end, GT ends, UT ends. • Wall frame Assembly: These are the supporting plated used where Bus Ducts need to penetrate the building walls, it make sure no loads are imposed the building structure.
  • 34. • Air pressurization system: Since Generator bus duct must be air tight, so the air leakage rate shall be restricted to the minimum ie 5% of total air volume per hour. • HAB: It is used to maintain the moisture content inside the Bus Ducts. • Silica gel breather: Provided in non-pressurized bus duct to keep it dry. It is used to maintain the ingress of the duct.
  • 35. TEST PERFORMED B E C A U S E Q U A L I T Y I S I M P O R TA N T
  • 36. ROUTINE TEST • Visual inspection • Dry power frequency voltage withstand for 1 minute • Milli-volt drop test • Water-tightness test • Insulation resistance
  • 37. TYPE TEST • Impulse voltage test • Heat run test • Milli-volt drop test • Air leakage test • Water tightness test • Temperature rise test