This document discusses the structural health monitoring system installed on the Barddhaman cable-stayed bridge in India. The system monitors cable forces using electromagnetic sensors installed on 6 cables subjected to maximum loads. Data is acquired and presented in real-time on a web-based interface, allowing monitoring of forces and issuing alarms if thresholds are exceeded. A load test was also conducted on the bridge to measure deflections at various loading stages and confirm the design performed as expected.
The document provides guidance on loads and forces that should be considered when designing bridges, including:
1. Dead loads, live loads, dynamic loads, longitudinal forces, wind loads, centrifugal forces, horizontal water currents, buoyancy, earth pressures, temperature effects, and seismic loads.
2. It describes the various live load models (Class A, B, 70R, AA) and provides details on load intensity, wheel/track configuration, and load combinations.
3. Design recommendations are given for calculating impact factors, braking forces, wind loads, water current pressures, earth pressures, and seismic forces.
The document describes a topographic survey conducted for the construction of a new railway bridge. It discusses using a topographic map to identify potential alignment options for the railway track. A field survey was then carried out using a total station to determine the central line alignment and elevation levels at different points. Soil exploration work, including lab testing, was also performed. Following this, the land acquisition process began by contacting local authorities to purchase the necessary land from owners. Foundation excavation work then commenced based on the ground conditions. Piers were constructed using a total station to ensure proper alignment. Bed blocks were then marked for placing precast girders. Sleepers were later laid to allow for track alignment along the central line.
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABSila vamsi krishna
RESULT OF ANALYSIS:
https://www.slideshare.net/ilavamsikrishna/results-of-etabs-on-high-rise-residential-buildings
ANALYSIS AND DESIGN OF BUILDING BY USING STAAD PRO PPT link :
https://www.slideshare.net/ilavamsikrishna/analysis-and-design-of-mutistoried-residential-building-by-using-staad-pro
FOR FULL REPORT:
vamsiila@gmail.com
Concrete is the most widely used construction material in India with annual consumption exceeding 100 million cubic meters.
High performance concrete is a concrete in which certain characteristics are developed for a particular application and environment, so that it will give excellent performance in the structure in which it will be placed.
A high-strength concrete is always a high performance concrete, but a high-performance concrete is not always a high-strength concrete.
Structural Health Monitoring for Bridges are used for assessment as well as prioritizing which bridge needs repair or upgrade urgently. Dynamic Tests can be used to estimate the load carrying capacity of bridges
This document provides information on bridge planning, design, classification and components. It discusses:
1. The key steps in bridge planning including studying needs, alternatives, design and implementation.
2. Common bridge classifications including material (masonry, concrete, steel), structural type (slab, girder, truss), and purpose (road, rail).
3. The main components of a typical T-beam bridge including the deck slab, longitudinal girders, cross girders, abutments and foundations. Methods for designing the deck slab and cantilever portions are outlined.
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONSGirish Singh
The purpose of this investigation is mainly a brief explanation about the advantages of FRP over steel. The various uses and advantages of FRP are explained in this project. In this project, we have taken a section of 3m length, 200mm width and 300mm depth and using a parabolic tendon of eccentricity 100mm at the centre. We have design the section for FRP as well as steel with the above data. The final stresses obtained is being verified with the help of Ansys software. We have shown the result of steel straight tendon only in this mini project.
Anchorage and lap splicing Detailing of slabs, columns, beams, footingskarthickcivic
This document discusses Eurocode 2 and provides details on anchorage and lap splicing of reinforcement in slabs, columns, beams and footings according to Eurocode 2. It covers general provisions for anchorage length, including tables of minimum anchorage lengths for different bar diameters. It also discusses lap splicing requirements, including tables of minimum lap splice lengths. The document is intended to provide guidance on reinforcement detailing according to Eurocode 2.
The document provides guidance on loads and forces that should be considered when designing bridges, including:
1. Dead loads, live loads, dynamic loads, longitudinal forces, wind loads, centrifugal forces, horizontal water currents, buoyancy, earth pressures, temperature effects, and seismic loads.
2. It describes the various live load models (Class A, B, 70R, AA) and provides details on load intensity, wheel/track configuration, and load combinations.
3. Design recommendations are given for calculating impact factors, braking forces, wind loads, water current pressures, earth pressures, and seismic forces.
The document describes a topographic survey conducted for the construction of a new railway bridge. It discusses using a topographic map to identify potential alignment options for the railway track. A field survey was then carried out using a total station to determine the central line alignment and elevation levels at different points. Soil exploration work, including lab testing, was also performed. Following this, the land acquisition process began by contacting local authorities to purchase the necessary land from owners. Foundation excavation work then commenced based on the ground conditions. Piers were constructed using a total station to ensure proper alignment. Bed blocks were then marked for placing precast girders. Sleepers were later laid to allow for track alignment along the central line.
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABSila vamsi krishna
RESULT OF ANALYSIS:
https://www.slideshare.net/ilavamsikrishna/results-of-etabs-on-high-rise-residential-buildings
ANALYSIS AND DESIGN OF BUILDING BY USING STAAD PRO PPT link :
https://www.slideshare.net/ilavamsikrishna/analysis-and-design-of-mutistoried-residential-building-by-using-staad-pro
FOR FULL REPORT:
vamsiila@gmail.com
Concrete is the most widely used construction material in India with annual consumption exceeding 100 million cubic meters.
High performance concrete is a concrete in which certain characteristics are developed for a particular application and environment, so that it will give excellent performance in the structure in which it will be placed.
A high-strength concrete is always a high performance concrete, but a high-performance concrete is not always a high-strength concrete.
Structural Health Monitoring for Bridges are used for assessment as well as prioritizing which bridge needs repair or upgrade urgently. Dynamic Tests can be used to estimate the load carrying capacity of bridges
This document provides information on bridge planning, design, classification and components. It discusses:
1. The key steps in bridge planning including studying needs, alternatives, design and implementation.
2. Common bridge classifications including material (masonry, concrete, steel), structural type (slab, girder, truss), and purpose (road, rail).
3. The main components of a typical T-beam bridge including the deck slab, longitudinal girders, cross girders, abutments and foundations. Methods for designing the deck slab and cantilever portions are outlined.
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONSGirish Singh
The purpose of this investigation is mainly a brief explanation about the advantages of FRP over steel. The various uses and advantages of FRP are explained in this project. In this project, we have taken a section of 3m length, 200mm width and 300mm depth and using a parabolic tendon of eccentricity 100mm at the centre. We have design the section for FRP as well as steel with the above data. The final stresses obtained is being verified with the help of Ansys software. We have shown the result of steel straight tendon only in this mini project.
Anchorage and lap splicing Detailing of slabs, columns, beams, footingskarthickcivic
This document discusses Eurocode 2 and provides details on anchorage and lap splicing of reinforcement in slabs, columns, beams and footings according to Eurocode 2. It covers general provisions for anchorage length, including tables of minimum anchorage lengths for different bar diameters. It also discusses lap splicing requirements, including tables of minimum lap splice lengths. The document is intended to provide guidance on reinforcement detailing according to Eurocode 2.
The presentation summarizes the project work done on "Seismic Analysis of Elevated Water Tank". Elevated water tanks are important structures that serve the function of supplying municipal water to the civil community. The stability of such structure is highly uncertain in the eve of earthquake. This project analyses the performance of such a structure in the eve of earthquake.
The project is done as a course requirement for undergraduate degree in May 2013. The degree in pursuit was "Bachelor of Technology in Civil Engineering" in National Institute of Technology in Tiruchirappalli (INDIA). The authors were in final year of the study during the making of the project.
This document provides an introduction to prestressed concrete bridge design. It discusses how prestressing concrete induces compression to counteract tensile stresses from loading. Prestressed concrete allows for longer concrete bridge spans through precasting units that are lifted into place. The document covers methods of prestressing including pre-tensioning and post-tensioning. It also summarizes design considerations like serviceability limits, stress limitations, prestress losses, and establishes basic inequalities for prestress force and section properties. Magnel diagrams are introduced as a way to determine appropriate prestress force and eccentricity values.
Progressive collapse is the result of a localized failure of one or two structural elements that lead to a steady progression of load transfer that exceeds the capacity of other surrounding elements, thus initiating the progression that leads to a total or partial collapse of the structure. The present study is to evaluate the behavior of G+8 reinforced concrete building subjected to potential collapse. The reinforced concrete structure is analyzed by Pushover Analysis using ETABS Software. It shows the maximum storey displacement and a maximum storey drift values of the components are studied. And the potential of the progressive collapse is determined.
This document discusses shear wall analysis and design. It defines shear walls as structural elements used in buildings to resist lateral forces through cantilever action. The document classifies different types of shear walls and discusses their behavior under seismic loading. It outlines the steps for designing shear walls, including reviewing layout, analyzing structural systems, determining design forces, and detailing reinforcement. The document emphasizes the importance of properly locating shear walls in a building to resist seismic loads and minimize torsional effects.
Influence line diagram for model arch bridgekunalsahu9883
The Lupu Bridge in Shanghai, China is a steel box section tied arch bridge with a main span of 550m, making it the largest arch bridge in the world when it was completed. A tied arch bridge design was used because the ground conditions on either side of the river were unsuitable for the large forces from a normal arch bridge. The bridge was analyzed using structural analysis software to determine member forces and deformations under load. The bridge is an impressive engineering feat that helped advance Chinese bridge engineering.
This document discusses reinforced concrete (RC) girder bridges. It begins by defining girder bridges as the simplest bridge type, consisting of horizontal beams supported at each end. RC girder bridges are comprised of deck slabs that vehicles drive on, supported by main girders. There are three main types of girder bridges: box girders, which can handle twisting forces and are suitable for longer spans; concrete girders made of pre-stressed concrete; and I-beam girders made of steel. RC girder bridges must be designed to support dead loads from the structure itself, live loads from traffic, and dynamic loads from wind and weather.
This document outlines various load types that must be considered in bridge design, including:
1. Dead loads from structural components like deck slabs, girders, and railings.
2. Live loads according to Indian Road Congress (IRC) standards, including Class A and 70R loadings.
3. Impact allowance as a percentage of live load to account for dynamic effects, ranging from 10-25% depending on span length and vehicle type.
4. Other loads such as wind loads, which are dependent on average height and wind velocity, and seismic forces. A table provides wind pressure and velocity values.
This document summarizes techniques for earthquake resistant building construction. It discusses how earthquake resistant buildings differ from traditional buildings in their design. Some techniques discussed include using reinforced hollow concrete block masonry, which uses reinforced blocks as load-bearing walls and shear walls. Mid-level isolation is described as installing base isolation systems on intermediate floors of existing buildings. Slurry infiltrated mat concrete is presented as a new type of concrete being developed to prevent building collapse. Traditional earthquake resistant housing styles from various regions of India are also overviewed.
This document provides specifications for the manufacture, supply and testing of uncoated, stress relieved, low relaxation seven-wire steel strands for pre-stressed concrete. It includes specifications for the wire, strand construction, treatment process, joints, workmanship, testing procedures for properties like lay length, diameter, breaking load and elongation. Relaxation testing procedures are also defined to ensure the strands have low stress loss over time when loaded.
This document provides an overview of different seismic analysis methods for reinforced concrete buildings according to Indian code IS 1893-2002, including linear static, nonlinear static, linear dynamic, and nonlinear dynamic analysis. It describes the basic procedures for each analysis type and provides examples of how to calculate design seismic base shear, distribute seismic forces vertically and horizontally, and determine drift and overturning effects. Case studies are presented comparing the results of static and dynamic analysis for regular and irregular multi-storey buildings modeled in SAP2000.
This document discusses box culverts and their components and construction. It begins by defining a culvert as a cross-drainage structure less than 6 meters long. It then describes box culverts, noting they consist of rectangular or square openings constructed monolithically with abutments and piers. Box culverts are typically constructed where soil is soft to distribute load over a wider area. They are made of concrete and can redirect water flow. The document outlines the wet cast and dry cast construction methods and lists the typical components of a box culvert. It also discusses the loads box culverts are subject to and their applications, advantages, and thank you.
This document discusses structure control systems used to protect structures from vibrations during earthquakes or strong winds. It describes traditional seismic design approaches and modern structural control methods. Structural control systems can be passive, active, semi-active, or hybrid. Passive systems like base isolation and dampers dissipate energy without external power. Active systems precisely control structural response using external actuation, while semi-active systems adjust properties using small power inputs. The document provides examples of different control devices and their operating principles.
Following are some suggestions for future research. As GFRSCC technology is now being adopted in many countries throughout the world, in the absence of suitable
standardized test methods it is necessary to examine the existing test methods and identify or, when necessary, develop test methods suitable for acceptance as International Standards. Such test methods have to be capable of a rapid and reliable assessment of key
properties of fresh SCC on a construction site. At the same time, the testing equipment should be reliable, easily portable and inexpensive. The test procedure should be carried out by a single operator and the test results have to be interpreted with a minimum of training. Also, the results have to define and specify different GFRSCC mixes. One primary application of these test methods would be in verification of compliance on sites and in concrete production plants, if self- compacting concrete could be manufactured in large quantities..
This document discusses various concepts related to structural analysis of arches:
1. An arch is a curved girder supported at its ends, allowing only vertical and horizontal displacements for arch action.
2. The general cable theorem relates the horizontal tension and vertical distance from any cable point to the cable chord moment.
3. Arches are classified based on support conditions (3, 2, or 1 hinged) or shape (curved, parabolic, elliptical, polygonal).
4. Horizontal thrust in arches reduces the bending moment and is calculated differently for various arch types (e.g. parabolic) and loading (e.g. UDL).
This document provides design aids for reinforced concrete structures based on Indian Standard IS: 456-1978 Code of Practice for Plain and Reinforced Concrete.
The design aids cover material strength and stress-strain relationships, flexural members, compression members, shear and torsion, development length and anchorage, working stress design, deflection calculation, and general tables. Charts and tables are provided for preliminary and final design of beams, slabs, and columns. Assumptions made in developing the design aids are explained. An example illustrates the use of the design aids. Important points regarding the use and limitations of the charts and tables are noted.
The design aids were prepared based on examination of international handbooks and consultation with Indian
The document discusses various topics related to bridges including their purpose, importance, components, classifications, loadings, aesthetics, materials used such as steel and reinforced concrete, types of bridges like suspension bridges, causes of bridge failures, maintenance, and some landmark bridges in India. Bridges are structures built to provide passage over physical obstacles without closing the gap below and have been developing in sophistication since early human civilization. They are important for connecting difficult terrains, aiding trade and transportation, and reducing travel time.
This document discusses structural health monitoring (SHM). It defines SHM as using damage detection techniques to monitor critical structures like bridges and buildings. The purpose of SHM is to enhance performance, monitor structures affected by external factors, and provide feedback to improve future designs. The key steps of SHM involve visual inspections, non-destructive evaluation techniques, and vibration-based monitoring using various sensors. Challenges to SHM include developing reliable wireless sensor networks and smart control units to efficiently monitor large structures over long periods.
Cable Layout, Continuous Beam & Load Balancing MethodMd Tanvir Alam
This document provides information on cable layout and load balancing methods for prestressed concrete beams. It discusses layouts for simple, continuous, and cantilever beams. For simple beams, it describes layouts for pretensioned and post-tensioned beams, including straight, curved, and bent cable configurations. It also compares the load carrying capacities of simple and continuous beams. The document concludes by explaining the load balancing method for design, using examples of how to balance loads in simple, cantilever, and continuous beam configurations.
DESIGN OF BOX CULVERT AS PER IRC-112: 2011, INTERNSHIP PROJECT REPORT.
INCLUDES:
1) BASIC DETAILS
2) DESIGN OF 2 CELL BOX CULVERT
3) DESIGN OF WING WALLS (RETAINING WALLS) AS PER IRC
Detailed Power point presentation on Implementation of 4 lane Cable Stayed Road over bridge at Bardhman- a future fast track model for construction over busy and longer Railway yards in India
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Rajesh Prasad
For the construction of Cable Stayed Bridge at Bardhman, a simulation model was made using LARSA 4D and accordingly design were concluded considering all the possible situation. At the execution stage the profile/geometry control is very important. Accordingly construction stage analysis along with geometry control is being done using LUSAS software. These software are 4D and the fourth dimension is Time. The said presentation covers the LARSA, LUSAS and few pictures on execution at site along with sample of documentation.
The presentation summarizes the project work done on "Seismic Analysis of Elevated Water Tank". Elevated water tanks are important structures that serve the function of supplying municipal water to the civil community. The stability of such structure is highly uncertain in the eve of earthquake. This project analyses the performance of such a structure in the eve of earthquake.
The project is done as a course requirement for undergraduate degree in May 2013. The degree in pursuit was "Bachelor of Technology in Civil Engineering" in National Institute of Technology in Tiruchirappalli (INDIA). The authors were in final year of the study during the making of the project.
This document provides an introduction to prestressed concrete bridge design. It discusses how prestressing concrete induces compression to counteract tensile stresses from loading. Prestressed concrete allows for longer concrete bridge spans through precasting units that are lifted into place. The document covers methods of prestressing including pre-tensioning and post-tensioning. It also summarizes design considerations like serviceability limits, stress limitations, prestress losses, and establishes basic inequalities for prestress force and section properties. Magnel diagrams are introduced as a way to determine appropriate prestress force and eccentricity values.
Progressive collapse is the result of a localized failure of one or two structural elements that lead to a steady progression of load transfer that exceeds the capacity of other surrounding elements, thus initiating the progression that leads to a total or partial collapse of the structure. The present study is to evaluate the behavior of G+8 reinforced concrete building subjected to potential collapse. The reinforced concrete structure is analyzed by Pushover Analysis using ETABS Software. It shows the maximum storey displacement and a maximum storey drift values of the components are studied. And the potential of the progressive collapse is determined.
This document discusses shear wall analysis and design. It defines shear walls as structural elements used in buildings to resist lateral forces through cantilever action. The document classifies different types of shear walls and discusses their behavior under seismic loading. It outlines the steps for designing shear walls, including reviewing layout, analyzing structural systems, determining design forces, and detailing reinforcement. The document emphasizes the importance of properly locating shear walls in a building to resist seismic loads and minimize torsional effects.
Influence line diagram for model arch bridgekunalsahu9883
The Lupu Bridge in Shanghai, China is a steel box section tied arch bridge with a main span of 550m, making it the largest arch bridge in the world when it was completed. A tied arch bridge design was used because the ground conditions on either side of the river were unsuitable for the large forces from a normal arch bridge. The bridge was analyzed using structural analysis software to determine member forces and deformations under load. The bridge is an impressive engineering feat that helped advance Chinese bridge engineering.
This document discusses reinforced concrete (RC) girder bridges. It begins by defining girder bridges as the simplest bridge type, consisting of horizontal beams supported at each end. RC girder bridges are comprised of deck slabs that vehicles drive on, supported by main girders. There are three main types of girder bridges: box girders, which can handle twisting forces and are suitable for longer spans; concrete girders made of pre-stressed concrete; and I-beam girders made of steel. RC girder bridges must be designed to support dead loads from the structure itself, live loads from traffic, and dynamic loads from wind and weather.
This document outlines various load types that must be considered in bridge design, including:
1. Dead loads from structural components like deck slabs, girders, and railings.
2. Live loads according to Indian Road Congress (IRC) standards, including Class A and 70R loadings.
3. Impact allowance as a percentage of live load to account for dynamic effects, ranging from 10-25% depending on span length and vehicle type.
4. Other loads such as wind loads, which are dependent on average height and wind velocity, and seismic forces. A table provides wind pressure and velocity values.
This document summarizes techniques for earthquake resistant building construction. It discusses how earthquake resistant buildings differ from traditional buildings in their design. Some techniques discussed include using reinforced hollow concrete block masonry, which uses reinforced blocks as load-bearing walls and shear walls. Mid-level isolation is described as installing base isolation systems on intermediate floors of existing buildings. Slurry infiltrated mat concrete is presented as a new type of concrete being developed to prevent building collapse. Traditional earthquake resistant housing styles from various regions of India are also overviewed.
This document provides specifications for the manufacture, supply and testing of uncoated, stress relieved, low relaxation seven-wire steel strands for pre-stressed concrete. It includes specifications for the wire, strand construction, treatment process, joints, workmanship, testing procedures for properties like lay length, diameter, breaking load and elongation. Relaxation testing procedures are also defined to ensure the strands have low stress loss over time when loaded.
This document provides an overview of different seismic analysis methods for reinforced concrete buildings according to Indian code IS 1893-2002, including linear static, nonlinear static, linear dynamic, and nonlinear dynamic analysis. It describes the basic procedures for each analysis type and provides examples of how to calculate design seismic base shear, distribute seismic forces vertically and horizontally, and determine drift and overturning effects. Case studies are presented comparing the results of static and dynamic analysis for regular and irregular multi-storey buildings modeled in SAP2000.
This document discusses box culverts and their components and construction. It begins by defining a culvert as a cross-drainage structure less than 6 meters long. It then describes box culverts, noting they consist of rectangular or square openings constructed monolithically with abutments and piers. Box culverts are typically constructed where soil is soft to distribute load over a wider area. They are made of concrete and can redirect water flow. The document outlines the wet cast and dry cast construction methods and lists the typical components of a box culvert. It also discusses the loads box culverts are subject to and their applications, advantages, and thank you.
This document discusses structure control systems used to protect structures from vibrations during earthquakes or strong winds. It describes traditional seismic design approaches and modern structural control methods. Structural control systems can be passive, active, semi-active, or hybrid. Passive systems like base isolation and dampers dissipate energy without external power. Active systems precisely control structural response using external actuation, while semi-active systems adjust properties using small power inputs. The document provides examples of different control devices and their operating principles.
Following are some suggestions for future research. As GFRSCC technology is now being adopted in many countries throughout the world, in the absence of suitable
standardized test methods it is necessary to examine the existing test methods and identify or, when necessary, develop test methods suitable for acceptance as International Standards. Such test methods have to be capable of a rapid and reliable assessment of key
properties of fresh SCC on a construction site. At the same time, the testing equipment should be reliable, easily portable and inexpensive. The test procedure should be carried out by a single operator and the test results have to be interpreted with a minimum of training. Also, the results have to define and specify different GFRSCC mixes. One primary application of these test methods would be in verification of compliance on sites and in concrete production plants, if self- compacting concrete could be manufactured in large quantities..
This document discusses various concepts related to structural analysis of arches:
1. An arch is a curved girder supported at its ends, allowing only vertical and horizontal displacements for arch action.
2. The general cable theorem relates the horizontal tension and vertical distance from any cable point to the cable chord moment.
3. Arches are classified based on support conditions (3, 2, or 1 hinged) or shape (curved, parabolic, elliptical, polygonal).
4. Horizontal thrust in arches reduces the bending moment and is calculated differently for various arch types (e.g. parabolic) and loading (e.g. UDL).
This document provides design aids for reinforced concrete structures based on Indian Standard IS: 456-1978 Code of Practice for Plain and Reinforced Concrete.
The design aids cover material strength and stress-strain relationships, flexural members, compression members, shear and torsion, development length and anchorage, working stress design, deflection calculation, and general tables. Charts and tables are provided for preliminary and final design of beams, slabs, and columns. Assumptions made in developing the design aids are explained. An example illustrates the use of the design aids. Important points regarding the use and limitations of the charts and tables are noted.
The design aids were prepared based on examination of international handbooks and consultation with Indian
The document discusses various topics related to bridges including their purpose, importance, components, classifications, loadings, aesthetics, materials used such as steel and reinforced concrete, types of bridges like suspension bridges, causes of bridge failures, maintenance, and some landmark bridges in India. Bridges are structures built to provide passage over physical obstacles without closing the gap below and have been developing in sophistication since early human civilization. They are important for connecting difficult terrains, aiding trade and transportation, and reducing travel time.
This document discusses structural health monitoring (SHM). It defines SHM as using damage detection techniques to monitor critical structures like bridges and buildings. The purpose of SHM is to enhance performance, monitor structures affected by external factors, and provide feedback to improve future designs. The key steps of SHM involve visual inspections, non-destructive evaluation techniques, and vibration-based monitoring using various sensors. Challenges to SHM include developing reliable wireless sensor networks and smart control units to efficiently monitor large structures over long periods.
Cable Layout, Continuous Beam & Load Balancing MethodMd Tanvir Alam
This document provides information on cable layout and load balancing methods for prestressed concrete beams. It discusses layouts for simple, continuous, and cantilever beams. For simple beams, it describes layouts for pretensioned and post-tensioned beams, including straight, curved, and bent cable configurations. It also compares the load carrying capacities of simple and continuous beams. The document concludes by explaining the load balancing method for design, using examples of how to balance loads in simple, cantilever, and continuous beam configurations.
DESIGN OF BOX CULVERT AS PER IRC-112: 2011, INTERNSHIP PROJECT REPORT.
INCLUDES:
1) BASIC DETAILS
2) DESIGN OF 2 CELL BOX CULVERT
3) DESIGN OF WING WALLS (RETAINING WALLS) AS PER IRC
Detailed Power point presentation on Implementation of 4 lane Cable Stayed Road over bridge at Bardhman- a future fast track model for construction over busy and longer Railway yards in India
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Rajesh Prasad
For the construction of Cable Stayed Bridge at Bardhman, a simulation model was made using LARSA 4D and accordingly design were concluded considering all the possible situation. At the execution stage the profile/geometry control is very important. Accordingly construction stage analysis along with geometry control is being done using LUSAS software. These software are 4D and the fourth dimension is Time. The said presentation covers the LARSA, LUSAS and few pictures on execution at site along with sample of documentation.
Use of sensors in structural engineering by pirpasha ujedePirpasha Ujede
The document discusses different types of sensors used in structural health monitoring, including optical fiber sensors, fiber Bragg grating sensors, piezoelectric sensors, and humidity sensors. It provides details on how these sensors work and their advantages. Some examples of large-scale bridge monitoring projects around the world are also mentioned. The document aims to outline how sensors can be used to monitor structures for factors like stress, strain, damage, and corrosion in real-time to assess structural integrity and safety.
Structural health monitoring uses sensors and data collection techniques to monitor structures for damage or changes over time. This improves safety, reliability and reduces costs. The document discusses using P3HT, a conductive polymer, for sensors as it displays electro-chemical sensing abilities. SHM involves identifying critical damage types, data acquisition from sensors, signal processing, and statistical modeling to correlate responses to damage types.
Future fast track model for new road over bridge spanning over railway yard- ...Rajesh Prasad
Implementation of 4 lane cable stayed road over bridge is nearing completion. It is felt that it could be a future fast track model for construction of ROB over busy railway yard in India
Provision of dampers to reduce the fatigue in cables of a cable stayed bridge...Rajesh Prasad
The dampers are being provided at Cable Stayed Bridge site to reduce the effect of fatigue on the stay cables due to oscillations induced by wind or other external phenomena, stay cables of more than 80m lengths have been provided with Internal Radial Dampers (IRD).15 such dampers are being installed on the stays.
Innovative solution for crossing larger spaces like railway yardRajesh Prasad
This paper titled Innovative solution for crossing larger spaces like railway yard has been presented in a seminar organised by CEAI at Kolkata on 03.06.2016
Handbook cum coffee table book titled staying with cables a modern construct...Rajesh Prasad
In India constructions of cable stayed bridge are far less than the construction of such bridges in advanced countries. The concept and technical know how in India is relatively new but after execution over busy yard Barddhaman- a very busy station and yard, the construction of cable stayed bridges is going to play important role in time to come specially at stations where there is a need to use the yard and land mass for future yard remodeling and passenger amenities.This hand book cum coffee table book has been made by Rajesh Prasad to share his construction experience for education purpose. An interesting and amazing stuff....by Rajesh Prasad, Chief Project Manager(M) cum Group General Manager RVNL
Disputes and Arbitration- How to Avoid and ManageRajesh Prasad
The presentation deals with the management tool to avoid and manage Arbitration in view of the new act ( arbitration and conciliation amendment act) notified on 01.01.2016 The paper presented during an All India Seminar on “Law & Practice of Arbitration in India as per Amended Law” held on 09.12.2016
The document discusses the construction of the Millau viaduct in France, which is the highest bridge in the world. It required over 350,000 tons of concrete and 40,000 tons of steel. The bridge's seven huge pillars rise over 800 feet high and support a roadway that is over 1,100 feet above the ground, making it over 50 feet taller than the Eiffel Tower. The bridge shortened travel time between cities by connecting a major highway over the mountainous terrain of the Tarn river valley.
5th metro rail summit at shangri la, cp, new delhi on 11.03.2016Rajesh Prasad
RVNL is using various software tools and new technologies to optimize design and planning for passenger experience and efficient project management of metro construction projects. This includes 3D lighting software to design optimal light fixture placement and selection of reflective materials, AC tonnage software to accurately calculate heating and cooling loads, and Revit architectural software to simulate designs. RVNL is also implementing lightning protection per the latest IEC standard and designing earth mats using specialized software. Remote monitoring systems further aid construction management. These approaches help address challenges of building metro lines amid utilities and in constrained environments.
ELAAU, Dankuni executed on very fast track by RVNLRajesh Prasad
Electric Loco Assembly and Ancillary unit of CLW at Dankuni has been implemented on a very fast track by RVNL and the aim is to augument production capacity of Electric Locos in Indian Railways. The project was implemented by the team of CPM M RVNL Kolkata- Rajesh Prasad and this coffee table book has been conceived and concluded by him only.
Implementation of Structural Health Monitoring System for live monitoring of ...Rajesh Prasad
This document discusses the implementation of a structural health monitoring system for a cable-stayed bridge in Barddhaman, India. The monitoring system measures forces on six critical bridge cables using electromagnetic sensors. It provides real-time data on cable forces and temperatures. The system was load tested and found to accurately monitor cable forces. It will allow engineers to safely monitor the bridge's structural integrity over its lifespan.
High Speed Rail- Need, Challenges, Key Issues and Options: Indian PerspectiveRajesh Prasad
A Paper titled:
"High Speed Rail- Need, Challenges, Key Issues and Options: Indian Perspective"
was presented during the 4th Annual South Asia Transport Infrastructure Conference 2016 held at Shanri-La's- Eros Hotel, New Delhi on 19-20 th september 2016 by Rajesh Prasad, IRSE, Chief Project Manager & Group General Manager, Rail Vikas Nigam Ltd, Kolkata
Real Time Monitoring Systems for Tunnels & Deep Excavation ProjectsRekaNext Capital
Presented in Malaysian Geotechnical Conference 16 March 2004 and a month later on 20 April 2004, there was the Nicoll Highway Collapse ! This system, if it had been used could have provided early warning to the site supervisors. The system was developed in 2001/2002 and had been used in many projects in Singapore.
Structural Health Monitoring and Strengthening Of BridgesStructural Health Mo...Editor IJCATR
This paper presents one bridge which were either rehabilitated or strengthened by using FRP composites. The resulting
structure was then tested for the effect after using FRP composites for Rehabilitation and strengthening. In this paper, Structural
Health Monitoring basics are covered and need for SHM in future in or India scenario. Use of FRP composites in Rehabilitation
and Strengthening of structures is becoming increasingly popular and is opening new possibilities in construction and rehabilitation
of structures.
Focal Design Issues Affecting The Deployment Of Wireless Sensor Networks For ...Vinayak Kulkarni
This document discusses key design issues affecting the deployment of wireless sensor networks for pipeline monitoring. It identifies critical requirements such as the need for low-cost solutions to monitor long pipelines traversing remote areas. The document covers sensing modalities, power efficiency, energy harvesting, network reliability, and localization as major design categories. It emphasizes the need to consider these issues to facilitate effective pipeline monitoring using wireless sensor networks.
In operational tunnels, whenever there are excavations adjacent to the tunnels, tunnels must be monitored for movements and deflections to prevent permanent damage to the tunnel rings. Once these rings have micro cracks, water seepage occurs and this will lead to longer term issues
Optical fiber sensors can measure various physical parameters by converting them to optical signals. They have applications in structure health monitoring and use light transmitted through optical fibers. The document discusses different types of optical fiber sensors including intrinsic and extrinsic, and how they work based on intensity, phase, frequency and polarization. It also covers the basic components, principles, advantages and challenges of optical fiber sensor systems.
Pile foundations are required for large structures. Different pile types can be installed using various equipment, even in layered soils, making safe and economical installation difficult. Dynamic pile load testing methods like low-strain integrity testing and high-strain load testing provide alternatives to static pile load testing by being more economical and efficient while still providing pile capacity and integrity information. Dynamic testing has been used successfully on numerous infrastructure projects to test piles efficiently and help reduce costs and schedule.
A real time instrumentation approach for bridges and tunnelsDerya Dinçer
Among all civil engineering structures, bridges & tunnels are two of the leading types that should be monitored by sensors due to their critical fatigue and creep behavior. Especially natural events such as earthquakes, floods, storms increase the importance of monitoring. A number of different types of instruments and sensors should be combined in health monitoring of railway/highway bridges, tunnels, tube crossings and subways. Although customization has a big importance in a specific health monitoring instrumentation project of a bridge or tunnel, accelerometers, strain/crack gauges, tilt, wind and temperature sensors are the most generally preferred sensors.
This document discusses a study to develop a bridge weigh-in-motion (BWIM) system using a scaled model bridge. The objectives are to simulate and experimentally test a BWIM system to accurately calculate gross vehicle weight and velocity. Sensors will be installed on a 3m long model bridge to measure strain from passing model trucks of known weights and configurations. Preliminary testing of a piezoelectric sensor to estimate vehicle velocity was also conducted. Comparing simulated, field and experimental results will help validate the data processing algorithms used.
This document describes the design of an instrumented wheelchair wheel called a propulsiometer that measures forces during wheelchair propulsion. The propulsiometer consists of a data acquisition system, load cell, wireless transmitter, battery, and other components. It has 6 analog channels, 4 digital channels, and can sample at over 200 Hz while consuming around 5 watts of power. The design meets about 85% of requirements and successfully transfers data from the load cell and encoder to a computer. The goal is to further develop this affordable device to help assess wheelchair propulsion and reduce overuse injuries.
ASCE Pipelines 2017 MTA Pipe-Inspector paper presentationGordon Henrich
The document discusses a new technology for inspecting pipelines called the Multi-Sensor Inspection (MSI) platform. The MSI is an untethered, self-propelled robotic device that can inspect pipelines using multiple onboard sensors simultaneously, including video cameras, acoustic sensors for leak detection, and sensors for pressure, temperature, and location. It is designed to move with fluid flow inside pressure pipes or gravity pipes to inspect long sections of pipe with only one access point. The MSI provides advantages over traditional tethered inspection methods by not being limited by cable length or ability to navigate bends. It allows synchronized inspection and correlation of different sensor data during live operations with minimal disruptions.
The LaserSweep system is a portable laser scanning device that:
1. Uses a rugged PDA with built-in software to perform cable-free measurements on rail infrastructure like tunnels, bridges, and platforms.
2. Can capture full profiles, partial profiles, and single points to efficiently measure structures and ensure vehicle clearances.
3. Exports data directly to Balfour Beatty Rail's ClearRoute software for analysis and is approved for use on UK rail networks.
ROLE OF DIGITAL SIMULATION IN CONFIGURING NETWORK PARAMETERSDeepak Shankar
Selecting the right Ethernet standard and configuring all the network devices in the embedded systems accurately is an extremely hard and rigorous job. The configuration depends on the topology, workloads of the connected devices, processing overhead at the switches, and the external interfaces. Network calculus, mathematical models and analytical techniques provide worst case execution time (WCET), but their probability of activity is extremely wide. This leads to overdesign which leads to higher costs, power consumption, weight, and size. Simulating the network is the best way to measure the throughput of the entire system. Digital system simulation provides better latency and throughput accuracy, but the accuracy is still limited because it does not consider the latency associated with the network OS, cybersecurity processing and scheduling. In many cases, these factors can reduce the throughput by 20-40%.
In this paper, we will present our research on modeling the entire Ethernet network, including the workloads, network flow control, scheduling, switch hardware, and software. To substantially increase the coverage and compare topologies, we have developed a set of benchmarks that provides coverage for different combination of deterministic, rate-constrained, and best effort traffic. During the presentation, we will cover the benchmarks, the list of attributes required to accurately model the traffic, nodes, switches, and the scheduler settings. We will also look at the statistics and reports required to make the configuration decision. In addition, we will discuss how the model must be constructed to study the impact of future requirements, failures, network intrusions, and security detection schemes.
Key Takeaways:
1. Learn how to efficiently use network simulation to design Ethernet systems
2. Develop a reusable benchmark and associated statistics to test different configurations
3. The role and impact of the CDT slots, guard band, send slope, idle slope, shuffle scheduling, flow control and virtual channels
- Kanteti Amar is a semiconductor professional with over 1 year of experience in analog and mixed-signal design. He has worked on projects such as bandgaps, power-on resets, and time-interleaved flash ADCs using technologies like 28nm, 40nm, and 65nm CMOS.
- He has a M.Tech from IIT Bombay and a B.Tech from GITAM University. He has experience with design tools like Cadence, Verilog, and MATLAB.
- His experience includes designing low-power bandgap references and power-on resets in 40nm technology and a low-noise bandgap reference in 65nm technology.
This document analyzes the automation system of a substation based on IEC 61850 standards using TOPCAL software. It discusses the architecture, components, and functions of the substation automation system (SAS), including monitoring, control, protection, and communication. The document also covers commissioning of the SAS human-machine interface, functional configuration, redundancy implementation, and availability calculations considering different component failure rates and numbers of integrated electronic device features. The results show the SAS availability is highest when using fewer IED features and lowest when using more features.
This document provides details about innovative technologies used in the construction of special bridge structures. It summarizes the construction of a cable-stayed bridge in Bardhaman, India. Some key points:
- The bridge has a main span of 124 meters and uses precast concrete segments, steel pylons, and parallel strand cable-stay system for support.
- Advanced modeling software and wind tunnel testing were used in the design. Precast concrete slabs were used to avoid scaffolding.
- Construction involved erecting the steel pylons and deck segments, installing and stressing the 180 tons of stay cables to provide support.
- Monitoring sensors were installed to track the bridge's performance over its 100
This document discusses bridge security and health monitoring systems installed on the I-35W bridge in Minnesota. It provides an overview of the basic ITS elements including CCTV cameras, ramp meters, traffic sensors, and dynamic message signs. It then describes the unique elements installed on the bridge, such as forward looking infrared cameras, an anti-icing system, and sensors to monitor the bridge's structural behavior. The document discusses the design and installation of the conduit and fiber optic network supporting these technologies, and how the data is used to monitor the bridge's security and structural health in real-time.
This project aims to develop a wireless electric vehicle charging system with high efficiency (>85%), high power transfer (over 6.6 kW), and good position tolerance. The system achieved power transfer of 6.6 kW with 85% efficiency at a 20 cm coil gap in initial testing. Future work will reduce the coil size and increase power transfer capability to 19.2 kW while maintaining performance. Validation through building and testing 5 electric vehicles integrated with the wireless charging system is also planned.
There was a Bridge 2018 Conference on Innovative Technologies of Bridges organised by IIBE at Lucknow. During the conference held on 25.05.18 this paper was presented by Rajesh Prasad, ED Metro RVNL.
High speed-pcb-board-design-and-analysiscadence-130218085524-phpapp01khalid noman husainy
This document discusses Cadence's solutions for high speed PCB design challenges. It introduces SPECCTRAQuest, a suite of products for signal integrity, power integrity, and packaging analysis throughout the PCB design flow. Key aspects covered include constraint management, frequency-domain analysis for power delivery, and a new Model Integrity module for creating and validating models. A demonstration overview discusses using these capabilities for model development, topology planning, and system-level verification.
This document summarizes a student project to build a self-balancing robot controlled by a mobile phone using Bluetooth. A group of 6 students from ITM Vocational University developed the robot under faculty guidance. The robot uses an Arduino, gyroscope, accelerometer, motor driver and DC motors. It balances itself using PID control and can be operated remotely from a mobile app connected via Bluetooth. The presentation covers the objectives, components, circuit diagrams, software, advantages and applications of the self-balancing robot.
This project presents an overhead bridge electromagnetic crane that can automatically measure and place objects on a conveyor belt based on their length and height. The crane uses sensors to detect objects, a microcontroller to process the measurements and control the electromagnet and motors, and can operate either automatically or manually via joystick. It is intended to help automate material handling in industries like shipping, steel mills, and petroleum refineries.
Peak’s Synchrophasor Technology Implementation Progress and Roadmap Rick Estrada
- Peak Reliability has implemented synchrophasor technology including installing 584 PMUs and 77 PDCs to enhance situational awareness.
- Applications include the V&R Peak ROSE tool for online monitoring of IROLs based on voltage stability analysis and the WSU oscillation monitoring system tools.
- Peak is implementing online transient stability analysis with PowerTech TSAT using the West-wide System Model to assess stability limits and monitor frequency deviations during contingencies.
Warner Land Surveys Ltd provides industrial measurement and dimensional control services for major refinery shutdowns and plant replacements. They have over 18 years of experience helping engineers replace refinery equipment on a first time basis. Their precise dimensional solutions are fit for purpose and do not interrupt plant operations. They take pride in understanding client accuracy needs and providing dimensions to 1mm.
Amberg Rail provides comprehensive system solutions for surveying and data management in railway construction and maintenance. Their solutions allow for precise identification and inspection of track positions during slab track installation and identification of track position errors to support tamping. They also offer a solution for clearance profiling and analysis to document encroaching objects. Amberg Rail aims to increase efficiency and flexibility in surveying through specialized hardware and software.
This document contains a resume for Rabi Kumar Purohita. It summarizes his professional experience in railway and metro signaling projects over the past 11 years, including roles as a project warranty manager, team leader, and senior engineer. It also lists his educational qualifications and technical skills related to signaling systems, including interlocking, automatic train control, and data loggers.
Similar to Bridge Structure Health Monitoring system (20)
Opportunities in Railway construction- development operations of infrastructu...Rajesh Prasad
7th RaiIndia Conference and Expo 7th edition was held on 27th Oct 2023 and a presentation was made on "Opportunities in Railway Construction - development/operations of railway infrastructure. This was held at Shangri-La Eros New Delhi and the theme was Next Gen Railways: Smart, Safe and Sustainable....
This is Keynote Address by Rajesh Prasad, Director Operations, Rail Vikas Nigam Ltd dt 11.09.2023 during 20th Safety Convention- Back to Basics for Strengthening EHS and Sustainable Foundation at Hotel Le-Meridien New Delhi being held from 11th to 13th Sept 2023
The presentation on Cyber Security and Data Protection in RVNL is being made on 8th April 2022 before the Board of Directors of RVNL by Rajesh Prasad Director Operations RVNL
Management Development programme - 01.07.2022 .pdfRajesh Prasad
This document provides an overview of a management and leadership programme presented by Rajesh Prasad. Some key points:
- It discusses definitions of management vs leadership and quotes prominent thinkers on the topics.
- It provides an introduction to Rail Vikas Nigam Limited (RVNL), a public sector undertaking that has contributed significantly to railway infrastructure projects in India.
- Statistics are presented on RVNL's financial performance, projects commissioned, and rankings from the Department of Public Enterprises over the past years.
- The presentation covers topics like corporate governance practices at RVNL, motivation examples, and the company's response to the COVID-19 pandemic crisis.
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...Rajesh Prasad
The said paper presented as KEY NOTE ADDRESS presented by Rajesh Prasad during the 17th Safety Convention on theme- Safety in Mobility held on 17-18th March 2021 at Hotel Le Meridien New Delhi organised by Institution of Engineers (india)
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRajesh Prasad
Rajesh Prasad Director Operations RVNL participated as a speaker in 5th edition of 'Rail India Conference and Expo' organised under the aegis of MFI Safe Connect (Messe Frankfurt India) in Delhi on 11.03.2021
Motivation and Bounce Back after the crisis....Rajesh Prasad
This document provides motivational stories and advice on remaining motivated after a crisis. It discusses how the COVID-19 pandemic has impacted many areas, including the Indian railway system and RVNL share prices. It then summarizes motivational stories of individuals and organizations that faced challenges but were able to bounce back, including CSK winning the IPL after a two-year suspension, a pistol shooter who won two Olympic gold medals after losing his right hand, and a volleyball player who climbed Mount Everest with one leg. The document advocates that with motivation, Indian Railways and RVNL will continue to play important roles in developing infrastructure and the country.
During the present crisis the whole country is shut down and all the InfraStructure projects have been stopped. Wheels of the Indian Railways carrying passengers have also stopped moving after inception in April 1853. A small ppt has been prepared for the RVNL family.
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...Rajesh Prasad
A 4 lane cable stayed bridge with 4 approaches over a very busy yard at Bardhman of E. Rly is an iconic structure at Bardhman- a gift to the nation by RVNL opened for road traffic yesterday ie 27.09.19. Proud to be the part and head of the team from concept to completion to commissioning.
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019Rajesh Prasad
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019 by Rajesh Prasad, Executive Director RVNL organised by Institute of Engineers in Kolkata
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...Rajesh Prasad
The said paper was presented by Rajesh Prasad in IC TRAM 2018 (International Conference- Technological Advancement in Railways and Metro Projects at Manekshaw Centre New Delhi on 04.10.2018
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
The said technical paper was presented by Rajesh Prasad in IC TRAM 2018 (International Conference- Technological Advancement in Railways and Metro Projects at Manekshaw Centre New Delhi on 04.10.2018
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...Rajesh Prasad
There was a Bridge conference on Innovative Technologies on 25.05.18 and 26.05.18 at Lucknow. This presentation was made by Rajesh Prasad, ED RVNL during the panel discussion. This PPT contains a lot cartoons and images and conveys a big message on ensuring safety at construction worksites.
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...Rajesh Prasad
This is a Handbook cum Coffee Table Book on Bridging over River Bhagirathi (alias Ganges)- Concept to Completion by Rajesh Prasad, Executive Director, Rail Vikas Nigam Ltd (RVNL) depicting from the concept to completion of the Railway Bridge including cantilever launching of the open web girders with span size of 103 m.
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...Rajesh Prasad
The said paper by Rajesh Prasad Executive Director RVNL has been published in IPWE international seminar held on 23/24-02-2018. The power point presentation nicely explains about how the technical challenges and administrative challenges addressed in completion of the tunnel while constructing a tunnel by the side of a railway tunnel with train operation in place and the entire area is affected by LWE activities.
How to Build a Module in Odoo 17 Using the Scaffold MethodCeline George
Odoo provides an option for creating a module by using a single line command. By using this command the user can make a whole structure of a module. It is very easy for a beginner to make a module. There is no need to make each file manually. This slide will show how to create a module using the scaffold method.
Main Java[All of the Base Concepts}.docxadhitya5119
This is part 1 of my Java Learning Journey. This Contains Custom methods, classes, constructors, packages, multithreading , try- catch block, finally block and more.
This slide is special for master students (MIBS & MIFB) in UUM. Also useful for readers who are interested in the topic of contemporary Islamic banking.
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...PECB
Denis is a dynamic and results-driven Chief Information Officer (CIO) with a distinguished career spanning information systems analysis and technical project management. With a proven track record of spearheading the design and delivery of cutting-edge Information Management solutions, he has consistently elevated business operations, streamlined reporting functions, and maximized process efficiency.
Certified as an ISO/IEC 27001: Information Security Management Systems (ISMS) Lead Implementer, Data Protection Officer, and Cyber Risks Analyst, Denis brings a heightened focus on data security, privacy, and cyber resilience to every endeavor.
His expertise extends across a diverse spectrum of reporting, database, and web development applications, underpinned by an exceptional grasp of data storage and virtualization technologies. His proficiency in application testing, database administration, and data cleansing ensures seamless execution of complex projects.
What sets Denis apart is his comprehensive understanding of Business and Systems Analysis technologies, honed through involvement in all phases of the Software Development Lifecycle (SDLC). From meticulous requirements gathering to precise analysis, innovative design, rigorous development, thorough testing, and successful implementation, he has consistently delivered exceptional results.
Throughout his career, he has taken on multifaceted roles, from leading technical project management teams to owning solutions that drive operational excellence. His conscientious and proactive approach is unwavering, whether he is working independently or collaboratively within a team. His ability to connect with colleagues on a personal level underscores his commitment to fostering a harmonious and productive workplace environment.
Date: May 29, 2024
Tags: Information Security, ISO/IEC 27001, ISO/IEC 42001, Artificial Intelligence, GDPR
-------------------------------------------------------------------------------
Find out more about ISO training and certification services
Training: ISO/IEC 27001 Information Security Management System - EN | PECB
ISO/IEC 42001 Artificial Intelligence Management System - EN | PECB
General Data Protection Regulation (GDPR) - Training Courses - EN | PECB
Webinars: https://pecb.com/webinars
Article: https://pecb.com/article
-------------------------------------------------------------------------------
For more information about PECB:
Website: https://pecb.com/
LinkedIn: https://www.linkedin.com/company/pecb/
Facebook: https://www.facebook.com/PECBInternational/
Slideshare: http://www.slideshare.net/PECBCERTIFICATION
This presentation includes basic of PCOS their pathology and treatment and also Ayurveda correlation of PCOS and Ayurvedic line of treatment mentioned in classics.
हिंदी वर्णमाला पीपीटी, hindi alphabet PPT presentation, hindi varnamala PPT, Hindi Varnamala pdf, हिंदी स्वर, हिंदी व्यंजन, sikhiye hindi varnmala, dr. mulla adam ali, hindi language and literature, hindi alphabet with drawing, hindi alphabet pdf, hindi varnamala for childrens, hindi language, hindi varnamala practice for kids, https://www.drmullaadamali.com
Macroeconomics- Movie Location
This will be used as part of your Personal Professional Portfolio once graded.
Objective:
Prepare a presentation or a paper using research, basic comparative analysis, data organization and application of economic information. You will make an informed assessment of an economic climate outside of the United States to accomplish an entertainment industry objective.
How to Manage Your Lost Opportunities in Odoo 17 CRMCeline George
Odoo 17 CRM allows us to track why we lose sales opportunities with "Lost Reasons." This helps analyze our sales process and identify areas for improvement. Here's how to configure lost reasons in Odoo 17 CRM
How to Add Chatter in the odoo 17 ERP ModuleCeline George
In Odoo, the chatter is like a chat tool that helps you work together on records. You can leave notes and track things, making it easier to talk with your team and partners. Inside chatter, all communication history, activity, and changes will be displayed.
Executive Directors Chat Leveraging AI for Diversity, Equity, and InclusionTechSoup
Let’s explore the intersection of technology and equity in the final session of our DEI series. Discover how AI tools, like ChatGPT, can be used to support and enhance your nonprofit's DEI initiatives. Participants will gain insights into practical AI applications and get tips for leveraging technology to advance their DEI goals.
This presentation was provided by Steph Pollock of The American Psychological Association’s Journals Program, and Damita Snow, of The American Society of Civil Engineers (ASCE), for the initial session of NISO's 2024 Training Series "DEIA in the Scholarly Landscape." Session One: 'Setting Expectations: a DEIA Primer,' was held June 6, 2024.
1. By
Rajesh Prasad, IRSE
Chief Project Manager (M) & Group General Manager
RVNL, Kolkata
07.102016 at IRICEN Pune
Bridge Structural Health Monitoring System
(BSHM) for live Monitoring of the Cable Forces
at Barddhaman ROB
2. SCOPE
• Why Bridge Structural Health Monitoring
(BSHM) required?
• How Bridge Structural Health Monitoring
(BSHM) function in this case?
• Methodology and Monitoring
• Output and Report generation
3. WHY BSHM?
• New concept and New Technology
• Health Assessment for change of load
pattern
• Condition Assessment with the passage of
time
• Life Extension Beyond Design life
• Experimental Verification of Design
Procedure/Criteria
4. BSHM Consists of :-
• Design, Installation, Commissioning of
BSHMS
• Operation, Maintenance, Data Recording,
Analysing and Reporting
• Sensors to measure environmental and
structural response factors (F&T).
• Signal acquisition solution, signal verification
and temperature adjustment, conversion of
signal to digital format etc.
8. RVNL Kolkata PIU is Implementing Agency
M/s GPT-RANHILL(JV) are main Contractor
M/s Freyssinet are specialized subcontractor
M/s Consulting Engineering Services(India) Pvt. Ltd
(JACOB) are the DDC and PMC
IIT Roorkee is the proof consultant
Wind Tunnel Test Being Executed By CRRI
STUP Consultant for Geometry Control
Experts like Dr. Prem Krishna and Shri R.R.Jaruhar
Railways and CRS for blocks and approval
AGENCIES INVOLVED
9. Clear Span(ABT to ABT): 184.429m
Main span length : 124.163 m
Back span length : 64.265 m
No of cable planes : 3
Type of cable in main span : harp pattern
No. of cables in main span : 9 per plane
No. of cable per side span : 9 per plane
Spacing between cables in main span : 12 m
Spacing between the cables in side span : 6.881 m
Height of centre pylon : 53.798 m
Clearance above rail track: 6500mm
Maximum height of road surface from rail track level:
7500MM
(Road surface to bottommost part of superstructure =
1000mm)
BARDDHAMAN CABLE STAYED BRIDGE DETAILS
10. • Engineering Challenge confronted…
• Superstructure carries 7.5m carriageway and 1.5 m wide
footpath on each side.
• DECK Geometry:
Total Length of the Bridge : 188.431 m
CP1 to P1 (Steel composite deck) : 124.163 m
P1 to CP2 (RCC Deck) : 64.265 m
Number of Lanes in each Direction : 2
Cross Slope : 2 %
GEOMETRY OF THE CABLE STAY BRIDGE
Barddhaman yard is one of the busiest yard of Eastern Railway and
Rajdhani route over Barddhaman station spanning across 8 platforms and
10 tracks.
12. Online Video link :
https://www.youtube.com/watch?v=aApXrEmwq5U
Cable Stayed Bridge Construction at Barddhaman
Handbook cum Coffee Table Book titled Staying
with Cables - A modern construction in new era
is at:
http://www.slideshare.net/slideshow/embed_code/key/
13. • LARSA 4D model for design
• Wind tunnel test
• Use of precast RCC slabs to avoid scaffolding on deck
• Composite structures for easier construction
• Monolithic Back Span
• Durable painting by epoxy based paint of Akzonobel
• Erection scheme
• LUSAS model for Construction Stage Analysis
• Geometry Control during execution.
• ROBO Control (Monitoring System) by M/s Mageba
FEATURES
14. • For monitoring of the structural health of the bridge during its service
life, 6 nos. of sensors have been installed on the stay cables
subjected to maximum loads.
• The structural monitoring system issues alarm notification based on
measurements by the on-structure instrumentation when pre-
defined threshold values of structural loads are passed. Alarm criteria
can be configured based on the structural design of the bridge
MONITORING SYSTEM (ROBO-CONTROL)
15. • Long term monitoring system.
• Measurement of forces on stay cables.
• Compact Monitoring System.
• System sustenance to extreme conditions.
• Graphical data output in web interface
with redundant data storage.
MAJOR COMPONENTS OF THE MONITORING SYSTEM
16. DESIGN
The sensors are placed to measure the various physical
performance parameters with the following general requirements
Solution was designed for bridge monitoring application and all
components is of such design as to sustain severe environmental
conditions and stand for several years of operation.
Hardware and sensors are available on open markets.
Alternatively any proprietary components is replaceable with
components available on open markets with reasonable
modifications to the overall configuration.
Software operating system is based on Windows.
Software application packages is an open source or code
available based programs in case vendor unavailability to support
the solution at any time in the future
17. DESIGN
User interface is very easy to operate and very much user
friendly.
User interface is Standard Web Browser based to ensure
compatibility to any future operating environment.
Bridge Structural Health Monitoring System (BSHMS) is
designed to sustain partial damage and the undamaged parts
remain operational and not lose real time and stored data.
Manual has been made in electronic format (PDF) and paper
copy.
Mageba has on-line auto diagnostic, trouble shooting and
support services for hardware and software.
Archived data has on-line controlled access.
18. SENSOR SCHEME
6(six) Nos. of sensors have been provided on the central pylon and
extreme cables to monitor the forces on these critical cables which are
subjected to maximum load. (10% of the total Cables need to be
instrumented)
20. FUNCTIONAL PRINCIPAL
Electromagnetic measures magnetolastic characteristics (magnetic flux) of
the ferromagnetic materials which are in relation with the mechanical
stress. Accuracy: + 0.5%
(Comparator)
23. Monitoring Cockpit -Monitoring Cockpit -
All measured dataAll measured data
presented in real timepresented in real time
Min / Max Values
System overview
Actual values of each sensor
Alarm values
DATA PRESENTATION IN WEB FORMAT
28. • Placed inside
protected box
• Round the clock
running
• Data redundancy
• Internet connection
required
• Uninterrupted power
supply required
SYSTEM INSIDE THE PYLON
29. Sensor tied up on the required strand Sensor on strand inside the AV tube
INSTALLATION
Onsite calibration Cabling left inside for future connections
30. Installation of strands & Stressing
Freyssinet’s Parallel Strand System (PSS) stay cables - which
has a design life of 100 years and is the most advanced
and durable stay cable system in the world today. There
are 3 planes of stay cables with 18 cables each. Vibration
control dampers have been installed in long stay cables (>
80m) as per CIP recommendations. Sensors for permanent
monitoring of forces during service condition, have also been
installed in 6 stays subjected to heavy loads. An inspection
and maintenance manual for the stay cables has been
prepared. 15.7mm 7 wire strand. Erected and tensioned
individually, easier to inspect, repair, replace.
Isotension® Method
36. Main benefits of Structural
Health Monitoring:
• Design Confirmation.
• Safety of the structure.
• Understanding behaviour
of structures at certain
environmental
conditions.
• Load Validation
CONCLUSION
41. It was done at the location where maximum stresses in bridge girder
assumed
Loading on footpath for live load @300 kg/sqm
Test load of 160 MT was given for Vehicular Live Load on both the carriage
way
Vehicular live load is increased and decreased in four stages i.e. at 50%, 75%,
90% & 100% of test load
Initial survey to measure deflection was carried out at pre-determined
location as marked on deck/girder before loading.
After loading on foot path (live load) survey was carried out and deflection
are measured
Incremental loading of vehicular live load was carried out as per stages as
mentioned above.
FEATURES OF LOAD TEST
LOAD TEST WAS CARRIED OUT IN MAIN SPAN AT CH. 12.163 TO
25.563M AS PER IRC:SP:51.
Loading on Bridge Deck conducted in following sequences :
42. FEATURES OF LOAD TEST
Deflection are measured after stabilization of the load applied,
normally after one hour period
The final load maintained for 24 hours and hourly reading of
deflection was recorded with full load
Unloading was carried out at two stages: (1) vehicular live load and
(2) footpath live load.
The removal of vehicular live load has been done at the same
sequences as adopted during loading
Reading of Deflection was taken at the end of every sequential stages
Net deflection was recorded after removal of full load and the same
was compared with original profile (before loading) of the deck
It is found that after unloading of entire loads, the recovery of
structure deflection is above 90% (as per guideline mentioned in
IRC:SP:51, Cl. 6.8.2 for steel composite structure minimum recovery
shall be 75%)
43. VEHICULAR LIVE LOAD IN CARRIAGEWAY
Axle No.
Dimension of supporting block
Block Load on
Each (Tonne)
B (mm) W (mm)
1 265 860
27.2
2 265 860
3 265 860
27.2
4 265 860
5 265 860
19.2
6 265 860
7 265 860 6.4
46. Instrument Used : Automatic Level
Description Date
Time
(Hrs)
Ambient
Temp (o
C)
Reading at Survey Point (Reduced Level)
A B C D E F G H I J K L
Location (Chainage in m): 12.163 (A) 12.163 (C) 12.163 (H) 16.163 (A) 16.163 (C) 16.163 (H) 58.163 (A) 58.163 (C) 58.163 (H) 94.163 (A) 94.163 (C) 94.163 (H)
Reading initial 20.08.16 16.00 30.0 39.555 40.112 39.530 39.588 40.149 39.573 39.935 40.378 39.895 39.804 40.315 39.780
After loading on Foot
Path (both Side)
25.08.16 11.00 32.0 39.540 40.093 39.512 39.567 40.127 39.550 39.909 40.354 39.868 39.796 40.308 39.773
Reading during Loading : Reading taken after 1 hour of loading (After Stabilization)
After 50% loading 29.08.16 12.10 38.5 39.513 40.065 39.487 39.536 40.092 39.518 39.890 40.337 39.849 39.791 40.306 39.766
After 75% loading 30.08.16 8.00 32.0 39.515 40.060 39.488 39.538 40.085 39.519 39.907 40.347 39.864 39.800 40.309 39.774
After 90% loading 30.08.16 13.20 38.0 39.500 40.049 39.474 39.519 40.071 39.503 39.883 40.329 39.841 39.791 40.304 39.767
After 100% loading 30.08.16 18.20 30.0 39.501 40.048 39.478 39.52 40.072 39.508 39.897 40.338 39.857 39.797 40.308 39.772
47. Description Date
Time
(Hrs)
Ambient
Temp (o
C)
Reading at Survey Point (Reduced Level)
A B C D E F G H I J K L
Location (Chainage in m): 12.163 (A) 12.163 (C) 12.163 (H) 16.163 (A) 16.163 (C) 16.163 (H) 58.163 (A) 58.163 (C) 58.163 (H) 94.163 (A) 94.163 (C) 94.163 (H)
Reading during Unloading : Reading during Loading : Reading taken after 1 hour of Unloading (After Stabilization)
After 90% loading31.08.16 19.00 28.0 39.507 40.052 39.481 39.528 40.078 39.512 39.902 40.345 39.864 39.799 40.309 39.773
After 75% loading31.08.16 22.20 27.0 39.516 40.061 39.491 39.537 40.088 39.525 39.913 40.353 39.873 39.801 40.312 39.777
After 50% loading01.09.16 11.30 34.0 39.516 40.066 39.490 39.541 40.095 39.524 39.899 40.342 39.857 39.795 40.306 39.769
After 0% loading03.09.16 13.00 34.0 39.534 40.089 39.510 39.559 40.120 39.545 39.903 40.348 39.863 39.793 40.304 39.768
After unloading from
Foot Path (both side)
05.09.16 15.55 33.0 39.554 40.108 39.528 39.587 40.145 39.570 39.934 40.377 39.894 39.803 40.313 39.779
Difference between initial and after
100% Loading (Deflection measured)
(mm) (-) 54 (-) 64 (-) 52 (-) 68 (-) 77 (-) 65 (-) 38 (-) 40 (-) 38 (-) 7 (-) 7 (-) 8
Expected Deflection (By Designer) (mm) (-) 87 (-) 92 (-) 87 (-) 106 (-) 111 (-) 106 (-) 67 (-) 66 (-) 67 (-) 19 (-) 18 (-) 19
48. Sl. No. CHAINAGE
REF.
POINT
INITIAL
READING
OBSERVATION AFTER 50% LOADING OBSERVATION AFTER 75% LOADING OBSERVATION AFTER 90% LOADING
OBSERVATION AFTER 100%
LOADING
READING
DEFLECTION (IN MM)
READING
DEFLECTION (IN MM)
READING
DEFLECTION (IN MM)
READING
DEFLECTION (IN MM)
ACTUAL THEOR ACTUAL THEOR ACTUAL THEOR ACTUAL THEOR
1 12.163 A 39.555 39.513 42.0 33.0 39.515 40.0 49.0 39.500 55 59 39.554 1 0
2 12.163 B 40.112 40.065 47.0 36.0 40.060 52.0 54.0 40.049 63 64 40.108 4 0
3 12.163 C 39.530 39.487 43.0 33.0 39.488 42.0 49.0 39.474 56 59 39.528 2 0
4 16.163 D 39.588 39.536 52.0 39.0 39.538 50.0 59.0 39.519 69 71 39.587 1 0
5 16.163 E 40.149 40.092 57.0 43.0 40.085 64.0 65.0 40.071 78 78 40.145 4 0
6 16.163 F 39.573 39.518 55.0 39.0 39.519 54.0 59.0 39.503 70 71 39.570 3 0
7 58.163 G 39.935 39.890 45.0 16.0 39.907 28.0 23.0 39.883 52 28 39.934 1 0
8 58.163 H 40.378 40.337 41.0 16.0 40.347 31.0 24.0 40.329 49 29 40.377 1 0
9 58.163 I 39.895 39.849 46.0 16.0 39.864 31.0 23.0 39.841 54 28 39.894 1 0
10 94.163 J 39.804 39.791 13.0 3.0 39.800 4.0 4.0 39.791 13 5 39.803 1 0
11 94.163 K 40.315 40.306 9.0 3.0 40.309 6.0 4.0 40.304 11 5 40.313 2 0
12 94.163 L 39.780 39.766 14.0 3.0 39.774 6.0 4.0 39.767 13 5 39.779 1 0
49. • In order to reduce the effect of fatigue on the stay cables due to
oscillations induced by wind or other external phenomena, stay cables
of more than 80m length have been provided with Internal Radial
Dampers (IRD). 15 such dampers have been installed on the stays
• IRD is composed of three hydraulic pistons placed at 120° angle
around the cable. The inner end of the pistons is fixed with a pin joint
on a collar compacting the strand bundle. Their outer end is fixed with
pin joints to a metallic tube called the guide tube. The damper is fixed
rigidly to the guide tube.
• The available stroke for the transverse displacements is +/- 40mm.
INTERNAL RADIAL DAMPERS
51. In Larsa 4D these construction stages are simulated so as
to get more realistic analysis. As cable elements have been
used which are nonlinear in nature, nonlinear analysis is
carried out at each stage. The initial structure has been
kept with a pre-camber such that after complete
construction, the deflection brings the structure to desired
finish level.
Fundamental period of vibration of the structure is
calculated by creating a 3D model of the structure and
carrying out its modal analysis in STAAD Pro V8i/ Midas
Civil/ Larsa4D.
DESIGN SIMULATION BY LARSA 4D
Transverse section showing components of Back Span (124.163m)
65mm WEARING COAT
52. Stage 16
•Max moment in Pylon. Utilization ratio
<1
Bending Moment diagram
Stage 16
•Max moment in Pylon. Utilization ratio
<1 Max. deflection is 208 mm (with lane
reduction it will become 166mm)
(Dead Load + SIDL) (Two Tracks of 70R wheeled)
53. Construction Stage Analysis using LUSAS model
• Analysis has been done using finite element analysis software LUSAS.
• Deck is modeled as grillage of longitudinal and transverse members.
• Deck is integral at P1 and CP2. At CP1 pin support with longitudinal
free movement is used representing the Guided PTFE bearings.
• At P1 and CP2, elastic spring supports representing the pile stiffness
are used.
• Load Cases : 67