SlideShare a Scribd company logo
RUNWAY DESIGN
Change in direction of runway
It may not be always possible to orient the runway exactly
along the direction as determined from the wind rose. Slight
adjustment in the directions may be imperative because of the
following reasons.
1. Obstructions
2. Excessive grading
3. Noise nuisance
Basic runway length
It is the length of the runway under the following assumed
conditions at the airport
1) Airport altitude is at sea level
2) Temperature at the Airport is standard (15’C)
3) Runway is levelled in the longitudinal direction
4) No wind is blowing on runway
5) Aircraft is loaded to its full loading capacity
6) There is no wind blowing enroute to the destination
7) Enroute temperature is standard
Basic runway length
The basic runway length is determined from the performance
characteristics of the aircrafts using the airport. The following
cases are usually considered
 Normal landing case
 Normal take-off case
 Engine failure case
 For jet engine aircrafts all 3 cases are considered
 For the piston engine aircraft only 1st and 3rd cases are considered
 The case which works out the longest runway length is finally
adopted.
1) Normal landing case
The landing case requires that aircraft should come to stop within
60% of the landing distance. The runway of full strength
pavement is provided for the entire landing distance.
2) Normal take-off case
 The normal take-off case requires a clearway which is an area beyond the
runway and is in alignment with the centre of runway.
 The width of clearway should not be less than 150 m and is also kept free from
obstructions.
stopway clearway
3) Engine failure case
 The engine failure case may require either a clearway or a stopway, or both.
 Stopway is described as an area beyond the runway and centrally located in
alignment with the centre of runway.
 It is used for decelerating during an aborted (terminated) take-off.
 The strength of stopway pavement should be just sufficient to carry the
weight of aircraft without causing any structural damage to the designated
engine failure speed, the pilot decelerate the aircraft and makes use of the
stopway.
Correction for Elevation, Temperature & Gradient
1) Correction for elevation:-
As the elevation increases, the air density reduces. This in turn reduces the
lift on the wings of the aircraft and the aircraft requires greater ground speed
before it can rise into the air.
To achieve greater speed, longer length of runway is required.
ICAO recommends that the basic runway length should be increased at the
rate of 7% per 300 m rise in elevation above the mean sea level.
2) Correction for temperature:-
Airport reference temperature
Where Ta- Average daily temperature
Tm- Maximum daily temperature
ICAO recommends that the basic runway length after having been corrected
for elevation, should be further increased at the rate 1% for every 1oc rise of
airport reference temperature above the standard atmospheric temperature at
the elevation.
3) Check for the total correction for the elevation plus temperature
 ICAO further recommends that's, if total corrections exceeds 35% of the basic
runway length, these corrections should be further checked up by conducting
specific studies at the site by model tests.
 Steeper gradient results in greater consumption of energy & as such longer
length of runway is required to attain the desired ground speed.
 ICAO does not recommends any specification for the correction of gradients.
 FAA recommends that the runway length after having been corrected for
elevation & temperature should be further increased at the rate of 20% for
every 1% of effective gradients.
4) Corrections for gradients:-
Runway Geometric Design
ICAO gives various geometric standards for the airport design.
1) Runway length
2) Runway width
3) Width & length of safety area
4) Transverse gradients
5) Longitudinal & effective gradient
6) Sight distance
Runway Geometric Design
1) Runway length
The basic runway length as recommended by ICAO for different types of
airport are there. To obtain the actual length of runway, corrections for
elevation, temperature & gradient are applied to the basic runway length.
2) Runway width
 ICAO recommends the pavement width varying from 45 m - 18 m for
different types of aircraft.
 The aircraft traffic is more concentrated in the central 24m width of the
runway pavement.
3) Width & Length Of Safety Area
 safety area consists of the runway, which is paved area plus the shoulder on
either side of runway plus the area is cleared, graded & drained as shown in
fig.
 The shoulder are usually unpaved as they are used during emergency.
 ICAO recommends.
Types of airport Width of safety area
Non-instrumental runway A,B&C
D&E
150 m
78 m
Instrumental runway A,B,C,D&E Mini. 300 m
Typical C/S of runway for ILS approach is shown below
(Instrumental Landing Systems)
(Instrumental Landing Systems)
4) Transverse gradient
 Transverse gradient is essential for quick drainage of surface water. If
surface water is allowed to pond on the runway, the aircraft can meet severe
hazards.
 ICAO recommends that the transverse gradient of runway pavement should
not exceed 1.5% for A,B, C & D 2 % for D & E types.
 ICAO does not recommends that the minimum transverse gradient of
runway pavement but it should not greater then 0.5 %.
5) Longitudinal & Effective Gradients.
 The longitudinal gradient of runway increases the required runway length.
 ICAO recommendation as follows
Types of
airport
Longitudinal
gradient
Effective
gradient
A,B & C 1.5 % 1 %
D & E 2 % 2 %
6) Sight distance (is the length of roadway visible to a driver)
 Two runways or a runway & taxiway intersect each other, there are chances of
collision of aircraft, if sufficient sight distance are not available.
 ICAO recommends that for A,B & C types of airports, any two points 3 m above the
surface of runway should be mutually visible from a distance equal to ½ the runway
length.
 For D & E types of runway there should be unobstructed line of sight from any point
3 m above runway and to all other point 2.1 m above runway within a distance of at
least ½ the length of runway.
TAXIWAY
TAXIWAY
The main function of the taxiway is the inter connection between runway and
loading apron or service hanger
Following consideration decide the layout of taxiway.
 Not interfere with the landing and take-off aircrafts
 At busy airports, taxiway should be located at various points along the runway
so that the landing aircraft leaves the runway as early as possible and keeps it
clear for use by other aircrafts. Such taxiway are called exit taxiways
 The route for taxiway should be so selected that it provides the shortest
distance from the apron to the runway end.
 As for as possible the intersection of taxiway and runway should be avoided.
 Exit taxiways should be designed for high turn-off speed.
Taxiway Geometric Design
ICAO gives various geometric standards for the airport design.
1) Taxiway length
2) Taxiway width
3) Width & length of safety area
4) Transverse gradients
5) Longitudinal & effective gradient
6) Sight distance
7) Turning radius
 Taxiway Geometric Design…
 Length of taxiway:
 As short as possible.
Increased number of taxiways have to be provided along the
runway.
Width of taxiway:
 It is observed that the width of a taxiway is much lower than
the runway width, as aircraft is not airborne and speeds are
small.
Varies between 22.5 m & 7.5 m
 Taxiway Geometric Design…
Width of taxiway:
 Width of taxiway (ICAO)
Longitudinal gradient:
 Level taxiway are operationally more desirable.
If gradient is steep, it affects fuel consumption.
 As per ICAO, maximum longitudinal gradient is 1.5% for
A&B type of airports & 3.0% for C,D&E type of airports.
Airport Code Taxiway width
A 22.5 m
B 22.5 m
C 15.0 m
D 9.9 m
E 7.5m
 Taxiway Geometric Design…
 Rate of change of longitudinal gradient:
 Available sight distance on the pavements is affected by the
rate of change of longitudinal gradient.
As per ICAO, the maximum change in pavement longitudinal
gradient is 4% for A&B category of airport & 3.33% for C,D&E
category of airports.
 Sight distance:
 As speed of aircraft on taxiway is lower than the speed on
runway, the smaller value of sight distance will be sufficient on
the taxiway.
Sight distance:
ICAO recommended that the surface of taxiway must be
visible at least up to a distance of X- from any point at a height
of Y above the taxiway surface.
 Transverse gradient:
 Adopted same as recommended for runway.
Transverse gradient is essential for quick drainage of surface
water.
Airport Code Y X
A 1.5 m 150 m
B 2.0 m 200 m
C,D&E 3.0 m 300 m
 Transverse gradient:
 ICAO recommended that the transverse gradient of runway
pavement should not exceed 1.5% for A,B&C & 2% for D&E
types. Shoulder are usually provided with steeper gradients.
Width of safety area:
 Safety area is made up to partially paved shoulders on either
side plus the area which is graded & drained.
 Turning radius:
 Change in aircraft path is done by providing a horizontal
curve.
The design should be such that the aircraft can negotiate the
curve without significantly reducing the speed.
Circular curve of large radius is provided.
Recommended radii corresponding of taxing speeds of small,
subsonic & supersonic airplanes is 60 m, 135 m & 240 m
respectively.
R2= V2/125f,
Where, R=radius in meter, V=speed in KMPhr
F=Friction btw tire and pavement
Exit Taxiways
Location of exit taxiway
This depends upon several factors
 Number of exit taxiways
 Exit speed
 Types of aircrafts
 Weather conditions
 Topographical features
 Pilot variability
Exit Taxiways
Location of exit taxiway
This depends upon several factors
 Number of exit taxiways: the number of taxiways to be provided decides
their location. If there are only two exit taxiways they should be provided
at the runway ends. If there are more than it should be ditributed along the
runway length.
 Exit speed: the maximum speed with which an aircraft can take a turn and
enter the exit taxiway is limited for each aircraft. The aircraft requires
certain length of runway to reduce its speed from the landing speed to the
turnoff speed. Thus this affects the location of taxiway.
 Types of aircrafts: different types of aircraft lands at different speed.
Therefore the distance required by different aircrafts, to reduce their speed
to the exit speed value, varies with the type of the aircraft, Thus in turn
affects the location of taxiway.
 Weather conditions
 Topographical features
 Pilot variability
DESIGN OF EXIT TAXIWAY CONNECTING RUNWAY & PARALLEL
TAXIWAY
1) The most significant factor is the exit speed of aircraft.
2) Slightly widened entrance of 30 m will be provide.
3) Total angle of turn is 3 300c-
4) The turning radius should be calculated by the following formula
5) A high turn-off speeds of 65-95 kmph a compound curve is necessary to
minimize the tire wear on the nose gear.
6) The length of longer radius curve can be roughly obtained by
valve of C=0.39
7) Stopping distance (SD)
Where d- deceleration distance
300-450
R=
VISUAL AIDS: A device which improves vision
NECESSITY OF VISUAL AIDS :-
 The pilots needs visual aids while landing or taking-off during all weather and
at every time.
 The pilots usually takes helps of the perspective view of the runway & other
ground reference marks during the landing operation.
 Runway thresholds, runway edges and the runway centre line are the most
essential items which should be clearly visible to the pilot. (lighting)
 In order to enhance the day time visibility runways, taxiways and allied
structures are marked with lines & numbers. (marking)
Airport Marking
Airport area is marked in a simple manner so that the pilots can easily
spot & recognize to the various airport elements.
The airport markings are divided into the following
 Runway marking
 Taxiway marking
 Runway & taxiway shoulder marking
 Apron marking
 Wind direction indicator
 Landing direction indicator
Airport Markings
Airport Lighting
In the day time during poor weather conditions, or at night, the visibility
reduces considerably. It is essential to provide adequate lighting. the colour &
general pattern of lights used in airport lighting are standardized for all civil
airports.
The airport lightings are divided into the following elements
 Runway lighting
 Taxiway lighting
 Apron & hanger lighting
 Lighting of Wind direction indicator
 Lighting of Landing direction indicator
Wind direction indicator

More Related Content

What's hot

Design elements of airport taxiway
Design elements of airport taxiwayDesign elements of airport taxiway
Design elements of airport taxiway
Asok999
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristicsAbhishek Kumar
 
Airport apron and holding bays
Airport apron and holding baysAirport apron and holding bays
Airport apron and holding bays
srinivas2036
 
Airport lighting
Airport lightingAirport lighting
Airport lighting
srinivas2036
 
1.introduction
1.introduction1.introduction
1.introduction
Mani Vel
 
Runway orientation
Runway orientationRunway orientation
Runway orientation
jagadish108
 
Layout of Airport Planning
Layout of Airport PlanningLayout of Airport Planning
Layout of Airport Planning
ManoharanM12
 
Airpot design
Airpot designAirpot design
Airpot design
pradip dangar
 
Airport elements.
Airport elements.Airport elements.
Airport elements.
Tulsi Makwana
 
Terminal area
Terminal areaTerminal area
Terminal area
RAMPRASAD KUMAWAT
 
Taxiway design perfect ppt
Taxiway design perfect pptTaxiway design perfect ppt
Taxiway design perfect ppt
Vijay Reddy
 
Factors in Airport site selection PART-2
Factors in Airport site selection PART-2Factors in Airport site selection PART-2
Factors in Airport site selection PART-2
RAMPRASAD KUMAWAT
 
Airport engineering
Airport engineering Airport engineering
Airport engineering
Jaspreet singh
 
Airport capacity and airport marking
Airport capacity and airport markingAirport capacity and airport marking
Airport capacity and airport marking
IsmailQubaisMotiya
 
Airport lighting
Airport lightingAirport lighting
Airport lighting
ArunaKunwor
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Design
srinivas2036
 
Airport presentation 5th unit
Airport presentation 5th unitAirport presentation 5th unit
Airport presentation 5th unit
T.Naga Anusha
 
Airfield Imaginary Surfaces
Airfield Imaginary SurfacesAirfield Imaginary Surfaces
Airfield Imaginary SurfacesAhsan Zahid
 
Taxiway design and geometrical design of taxiway
Taxiway design and geometrical design of taxiwayTaxiway design and geometrical design of taxiway
Taxiway design and geometrical design of taxiway
BALAJI ND
 

What's hot (20)

Design elements of airport taxiway
Design elements of airport taxiwayDesign elements of airport taxiway
Design elements of airport taxiway
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristics
 
Airport apron and holding bays
Airport apron and holding baysAirport apron and holding bays
Airport apron and holding bays
 
Airport lighting
Airport lightingAirport lighting
Airport lighting
 
1.introduction
1.introduction1.introduction
1.introduction
 
Runway orientation
Runway orientationRunway orientation
Runway orientation
 
Layout of Airport Planning
Layout of Airport PlanningLayout of Airport Planning
Layout of Airport Planning
 
Airpot design
Airpot designAirpot design
Airpot design
 
Airport elements.
Airport elements.Airport elements.
Airport elements.
 
Terminal area
Terminal areaTerminal area
Terminal area
 
Taxiway design perfect ppt
Taxiway design perfect pptTaxiway design perfect ppt
Taxiway design perfect ppt
 
Factors in Airport site selection PART-2
Factors in Airport site selection PART-2Factors in Airport site selection PART-2
Factors in Airport site selection PART-2
 
Airport lighting
Airport lightingAirport lighting
Airport lighting
 
Airport engineering
Airport engineering Airport engineering
Airport engineering
 
Airport capacity and airport marking
Airport capacity and airport markingAirport capacity and airport marking
Airport capacity and airport marking
 
Airport lighting
Airport lightingAirport lighting
Airport lighting
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Design
 
Airport presentation 5th unit
Airport presentation 5th unitAirport presentation 5th unit
Airport presentation 5th unit
 
Airfield Imaginary Surfaces
Airfield Imaginary SurfacesAirfield Imaginary Surfaces
Airfield Imaginary Surfaces
 
Taxiway design and geometrical design of taxiway
Taxiway design and geometrical design of taxiwayTaxiway design and geometrical design of taxiway
Taxiway design and geometrical design of taxiway
 

Viewers also liked

Pavement Products PPT (October 2014)
Pavement Products PPT (October 2014)Pavement Products PPT (October 2014)
Pavement Products PPT (October 2014)
The D.S. Brown Company
 
Pkqa iso 17025 requirements
Pkqa iso 17025 requirementsPkqa iso 17025 requirements
Pkqa iso 17025 requirements
Pat Kilbane
 
Airport runway By Nikhil Pakwanne
Airport runway By Nikhil PakwanneAirport runway By Nikhil Pakwanne
Airport runway By Nikhil PakwanneNIKHIL PAKWANNE
 
Iso 17025 nabl implementation steps lakshy rev00-240914
Iso 17025 nabl  implementation steps lakshy rev00-240914Iso 17025 nabl  implementation steps lakshy rev00-240914
Iso 17025 nabl implementation steps lakshy rev00-240914
Lakshy Management Consultant Pvt Ltd
 
Distresses in flexible pavements by water
Distresses in flexible pavements by waterDistresses in flexible pavements by water
Distresses in flexible pavements by water
ammar rasheed
 
Airports presentation
Airports presentationAirports presentation
Airports presentation
Poornananda Kumar
 
Pdce
PdcePdce
Crack repair techniques
Crack repair techniquesCrack repair techniques
Crack repair techniques
Nayana 54321
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Malay Talaviya
 
TOP DOWN CRACKING IN FLEXIBLE PAVEMENTS
TOP DOWN CRACKING  IN FLEXIBLE PAVEMENTSTOP DOWN CRACKING  IN FLEXIBLE PAVEMENTS
TOP DOWN CRACKING IN FLEXIBLE PAVEMENTS
EVERSENDAI ENGINEERING (L.L.C.)
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavement
Randhir Kumar
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavement
Rafi Khan
 
Annex 14 ppt cheng
Annex 14 ppt chengAnnex 14 ppt cheng
Annex 14 ppt cheng
guestb793fe2
 
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURESCASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
Prabhu Saran
 
Flexible pavement failure
Flexible pavement failureFlexible pavement failure
Flexible pavement failure
Nabaraj Poudel
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
Pawan Kumar
 
Airport Layout
Airport LayoutAirport Layout
Airport Layout
Naveed Hussain
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
Amol Pawar
 

Viewers also liked (18)

Pavement Products PPT (October 2014)
Pavement Products PPT (October 2014)Pavement Products PPT (October 2014)
Pavement Products PPT (October 2014)
 
Pkqa iso 17025 requirements
Pkqa iso 17025 requirementsPkqa iso 17025 requirements
Pkqa iso 17025 requirements
 
Airport runway By Nikhil Pakwanne
Airport runway By Nikhil PakwanneAirport runway By Nikhil Pakwanne
Airport runway By Nikhil Pakwanne
 
Iso 17025 nabl implementation steps lakshy rev00-240914
Iso 17025 nabl  implementation steps lakshy rev00-240914Iso 17025 nabl  implementation steps lakshy rev00-240914
Iso 17025 nabl implementation steps lakshy rev00-240914
 
Distresses in flexible pavements by water
Distresses in flexible pavements by waterDistresses in flexible pavements by water
Distresses in flexible pavements by water
 
Airports presentation
Airports presentationAirports presentation
Airports presentation
 
Pdce
PdcePdce
Pdce
 
Crack repair techniques
Crack repair techniquesCrack repair techniques
Crack repair techniques
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
 
TOP DOWN CRACKING IN FLEXIBLE PAVEMENTS
TOP DOWN CRACKING  IN FLEXIBLE PAVEMENTSTOP DOWN CRACKING  IN FLEXIBLE PAVEMENTS
TOP DOWN CRACKING IN FLEXIBLE PAVEMENTS
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavement
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavement
 
Annex 14 ppt cheng
Annex 14 ppt chengAnnex 14 ppt cheng
Annex 14 ppt cheng
 
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURESCASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
 
Flexible pavement failure
Flexible pavement failureFlexible pavement failure
Flexible pavement failure
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
 
Airport Layout
Airport LayoutAirport Layout
Airport Layout
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 

Similar to Air port presentation 6th unit

runway orientation.pdf
runway orientation.pdfrunway orientation.pdf
runway orientation.pdf
MargaretAbrahamCE
 
Airport layout
Airport layoutAirport layout
Airport layout
ArmanAnsari37
 
Lecture 7 (1).pptx
Lecture 7 (1).pptxLecture 7 (1).pptx
Lecture 7 (1).pptx
WhUllahWa
 
Airport Design RHTA - VTU Module 5
Airport Design RHTA - VTU Module 5Airport Design RHTA - VTU Module 5
Airport Design RHTA - VTU Module 5
AJEETH B
 
IRJET- Design of Runway for Navi-Mumbai International Airport
IRJET-  	  Design of Runway for Navi-Mumbai International AirportIRJET-  	  Design of Runway for Navi-Mumbai International Airport
IRJET- Design of Runway for Navi-Mumbai International Airport
IRJET Journal
 
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
Hossam Shafiq I
 
Circular Runway
Circular RunwayCircular Runway
Circular Runway
IRJET Journal
 
Airport Engineering
Airport Engineering Airport Engineering
Airport Engineering
Abhishek Pandey
 
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
irjes
 
Lecture 9.pdf
Lecture 9.pdfLecture 9.pdf
Lecture 9.pdf
ShashankSR6
 
AIRPORT PAVEMENT - CONSTRUCTION & REPAIR.pptx
AIRPORT PAVEMENT -  CONSTRUCTION & REPAIR.pptxAIRPORT PAVEMENT -  CONSTRUCTION & REPAIR.pptx
AIRPORT PAVEMENT - CONSTRUCTION & REPAIR.pptx
Anujyadav514462
 
Air traffic management
Air traffic managementAir traffic management
Air traffic management
Amidee Azizan Stringfellow
 
Airport
AirportAirport
Airport
Sajid Mehboob
 
Taneja Aerospace and Aviation limied
Taneja Aerospace and Aviation limiedTaneja Aerospace and Aviation limied
Taneja Aerospace and Aviation limied
darshakb
 
Proposed RWY21 RESA at YIA
Proposed RWY21 RESA at YIAProposed RWY21 RESA at YIA
Proposed RWY21 RESA at YIA
Kozarni Koko
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport Engineering
Becky Gilbert
 
AIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJANAIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJAN
Niranjan Varma
 
AIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGNAIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGN
Niranjan Varma
 

Similar to Air port presentation 6th unit (20)

runway orientation.pdf
runway orientation.pdfrunway orientation.pdf
runway orientation.pdf
 
Airport layout
Airport layoutAirport layout
Airport layout
 
Lecture 7 (1).pptx
Lecture 7 (1).pptxLecture 7 (1).pptx
Lecture 7 (1).pptx
 
Airport Design RHTA - VTU Module 5
Airport Design RHTA - VTU Module 5Airport Design RHTA - VTU Module 5
Airport Design RHTA - VTU Module 5
 
IRJET- Design of Runway for Navi-Mumbai International Airport
IRJET-  	  Design of Runway for Navi-Mumbai International AirportIRJET-  	  Design of Runway for Navi-Mumbai International Airport
IRJET- Design of Runway for Navi-Mumbai International Airport
 
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
 
Circular Runway
Circular RunwayCircular Runway
Circular Runway
 
Airport Engineering
Airport Engineering Airport Engineering
Airport Engineering
 
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
 
Lecture 9.pdf
Lecture 9.pdfLecture 9.pdf
Lecture 9.pdf
 
AIRPORT PAVEMENT - CONSTRUCTION & REPAIR.pptx
AIRPORT PAVEMENT -  CONSTRUCTION & REPAIR.pptxAIRPORT PAVEMENT -  CONSTRUCTION & REPAIR.pptx
AIRPORT PAVEMENT - CONSTRUCTION & REPAIR.pptx
 
Air traffic management
Air traffic managementAir traffic management
Air traffic management
 
Airport
AirportAirport
Airport
 
Taneja Aerospace and Aviation limied
Taneja Aerospace and Aviation limiedTaneja Aerospace and Aviation limied
Taneja Aerospace and Aviation limied
 
Proposed RWY21 RESA at YIA
Proposed RWY21 RESA at YIAProposed RWY21 RESA at YIA
Proposed RWY21 RESA at YIA
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport Engineering
 
Airports
AirportsAirports
Airports
 
ThunderCats_Revised_2
ThunderCats_Revised_2ThunderCats_Revised_2
ThunderCats_Revised_2
 
AIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJANAIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJAN
 
AIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGNAIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGN
 

Recently uploaded

AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 

Recently uploaded (20)

AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 

Air port presentation 6th unit

  • 2. Change in direction of runway It may not be always possible to orient the runway exactly along the direction as determined from the wind rose. Slight adjustment in the directions may be imperative because of the following reasons. 1. Obstructions 2. Excessive grading 3. Noise nuisance
  • 3. Basic runway length It is the length of the runway under the following assumed conditions at the airport 1) Airport altitude is at sea level 2) Temperature at the Airport is standard (15’C) 3) Runway is levelled in the longitudinal direction 4) No wind is blowing on runway 5) Aircraft is loaded to its full loading capacity 6) There is no wind blowing enroute to the destination 7) Enroute temperature is standard
  • 4. Basic runway length The basic runway length is determined from the performance characteristics of the aircrafts using the airport. The following cases are usually considered  Normal landing case  Normal take-off case  Engine failure case  For jet engine aircrafts all 3 cases are considered  For the piston engine aircraft only 1st and 3rd cases are considered  The case which works out the longest runway length is finally adopted.
  • 5. 1) Normal landing case The landing case requires that aircraft should come to stop within 60% of the landing distance. The runway of full strength pavement is provided for the entire landing distance.
  • 6. 2) Normal take-off case  The normal take-off case requires a clearway which is an area beyond the runway and is in alignment with the centre of runway.  The width of clearway should not be less than 150 m and is also kept free from obstructions.
  • 8. 3) Engine failure case  The engine failure case may require either a clearway or a stopway, or both.  Stopway is described as an area beyond the runway and centrally located in alignment with the centre of runway.  It is used for decelerating during an aborted (terminated) take-off.  The strength of stopway pavement should be just sufficient to carry the weight of aircraft without causing any structural damage to the designated engine failure speed, the pilot decelerate the aircraft and makes use of the stopway.
  • 9. Correction for Elevation, Temperature & Gradient 1) Correction for elevation:- As the elevation increases, the air density reduces. This in turn reduces the lift on the wings of the aircraft and the aircraft requires greater ground speed before it can rise into the air. To achieve greater speed, longer length of runway is required. ICAO recommends that the basic runway length should be increased at the rate of 7% per 300 m rise in elevation above the mean sea level. 2) Correction for temperature:- Airport reference temperature Where Ta- Average daily temperature Tm- Maximum daily temperature ICAO recommends that the basic runway length after having been corrected for elevation, should be further increased at the rate 1% for every 1oc rise of airport reference temperature above the standard atmospheric temperature at the elevation.
  • 10.
  • 11. 3) Check for the total correction for the elevation plus temperature  ICAO further recommends that's, if total corrections exceeds 35% of the basic runway length, these corrections should be further checked up by conducting specific studies at the site by model tests.  Steeper gradient results in greater consumption of energy & as such longer length of runway is required to attain the desired ground speed.  ICAO does not recommends any specification for the correction of gradients.  FAA recommends that the runway length after having been corrected for elevation & temperature should be further increased at the rate of 20% for every 1% of effective gradients. 4) Corrections for gradients:-
  • 12. Runway Geometric Design ICAO gives various geometric standards for the airport design. 1) Runway length 2) Runway width 3) Width & length of safety area 4) Transverse gradients 5) Longitudinal & effective gradient 6) Sight distance
  • 13. Runway Geometric Design 1) Runway length The basic runway length as recommended by ICAO for different types of airport are there. To obtain the actual length of runway, corrections for elevation, temperature & gradient are applied to the basic runway length. 2) Runway width  ICAO recommends the pavement width varying from 45 m - 18 m for different types of aircraft.  The aircraft traffic is more concentrated in the central 24m width of the runway pavement.
  • 14. 3) Width & Length Of Safety Area  safety area consists of the runway, which is paved area plus the shoulder on either side of runway plus the area is cleared, graded & drained as shown in fig.  The shoulder are usually unpaved as they are used during emergency.  ICAO recommends. Types of airport Width of safety area Non-instrumental runway A,B&C D&E 150 m 78 m Instrumental runway A,B,C,D&E Mini. 300 m
  • 15.
  • 16. Typical C/S of runway for ILS approach is shown below (Instrumental Landing Systems)
  • 18. 4) Transverse gradient  Transverse gradient is essential for quick drainage of surface water. If surface water is allowed to pond on the runway, the aircraft can meet severe hazards.  ICAO recommends that the transverse gradient of runway pavement should not exceed 1.5% for A,B, C & D 2 % for D & E types.  ICAO does not recommends that the minimum transverse gradient of runway pavement but it should not greater then 0.5 %.
  • 19. 5) Longitudinal & Effective Gradients.  The longitudinal gradient of runway increases the required runway length.  ICAO recommendation as follows Types of airport Longitudinal gradient Effective gradient A,B & C 1.5 % 1 % D & E 2 % 2 %
  • 20. 6) Sight distance (is the length of roadway visible to a driver)  Two runways or a runway & taxiway intersect each other, there are chances of collision of aircraft, if sufficient sight distance are not available.  ICAO recommends that for A,B & C types of airports, any two points 3 m above the surface of runway should be mutually visible from a distance equal to ½ the runway length.  For D & E types of runway there should be unobstructed line of sight from any point 3 m above runway and to all other point 2.1 m above runway within a distance of at least ½ the length of runway.
  • 22. TAXIWAY The main function of the taxiway is the inter connection between runway and loading apron or service hanger Following consideration decide the layout of taxiway.  Not interfere with the landing and take-off aircrafts  At busy airports, taxiway should be located at various points along the runway so that the landing aircraft leaves the runway as early as possible and keeps it clear for use by other aircrafts. Such taxiway are called exit taxiways  The route for taxiway should be so selected that it provides the shortest distance from the apron to the runway end.  As for as possible the intersection of taxiway and runway should be avoided.  Exit taxiways should be designed for high turn-off speed.
  • 23. Taxiway Geometric Design ICAO gives various geometric standards for the airport design. 1) Taxiway length 2) Taxiway width 3) Width & length of safety area 4) Transverse gradients 5) Longitudinal & effective gradient 6) Sight distance 7) Turning radius
  • 24.  Taxiway Geometric Design…  Length of taxiway:  As short as possible. Increased number of taxiways have to be provided along the runway. Width of taxiway:  It is observed that the width of a taxiway is much lower than the runway width, as aircraft is not airborne and speeds are small. Varies between 22.5 m & 7.5 m
  • 25.  Taxiway Geometric Design… Width of taxiway:  Width of taxiway (ICAO) Longitudinal gradient:  Level taxiway are operationally more desirable. If gradient is steep, it affects fuel consumption.  As per ICAO, maximum longitudinal gradient is 1.5% for A&B type of airports & 3.0% for C,D&E type of airports. Airport Code Taxiway width A 22.5 m B 22.5 m C 15.0 m D 9.9 m E 7.5m
  • 26.  Taxiway Geometric Design…  Rate of change of longitudinal gradient:  Available sight distance on the pavements is affected by the rate of change of longitudinal gradient. As per ICAO, the maximum change in pavement longitudinal gradient is 4% for A&B category of airport & 3.33% for C,D&E category of airports.  Sight distance:  As speed of aircraft on taxiway is lower than the speed on runway, the smaller value of sight distance will be sufficient on the taxiway.
  • 27. Sight distance: ICAO recommended that the surface of taxiway must be visible at least up to a distance of X- from any point at a height of Y above the taxiway surface.  Transverse gradient:  Adopted same as recommended for runway. Transverse gradient is essential for quick drainage of surface water. Airport Code Y X A 1.5 m 150 m B 2.0 m 200 m C,D&E 3.0 m 300 m
  • 28.  Transverse gradient:  ICAO recommended that the transverse gradient of runway pavement should not exceed 1.5% for A,B&C & 2% for D&E types. Shoulder are usually provided with steeper gradients. Width of safety area:  Safety area is made up to partially paved shoulders on either side plus the area which is graded & drained.
  • 29.  Turning radius:  Change in aircraft path is done by providing a horizontal curve. The design should be such that the aircraft can negotiate the curve without significantly reducing the speed. Circular curve of large radius is provided. Recommended radii corresponding of taxing speeds of small, subsonic & supersonic airplanes is 60 m, 135 m & 240 m respectively. R2= V2/125f, Where, R=radius in meter, V=speed in KMPhr F=Friction btw tire and pavement
  • 30.
  • 31. Exit Taxiways Location of exit taxiway This depends upon several factors  Number of exit taxiways  Exit speed  Types of aircrafts  Weather conditions  Topographical features  Pilot variability
  • 32. Exit Taxiways Location of exit taxiway This depends upon several factors  Number of exit taxiways: the number of taxiways to be provided decides their location. If there are only two exit taxiways they should be provided at the runway ends. If there are more than it should be ditributed along the runway length.  Exit speed: the maximum speed with which an aircraft can take a turn and enter the exit taxiway is limited for each aircraft. The aircraft requires certain length of runway to reduce its speed from the landing speed to the turnoff speed. Thus this affects the location of taxiway.  Types of aircrafts: different types of aircraft lands at different speed. Therefore the distance required by different aircrafts, to reduce their speed to the exit speed value, varies with the type of the aircraft, Thus in turn affects the location of taxiway.  Weather conditions  Topographical features  Pilot variability
  • 33. DESIGN OF EXIT TAXIWAY CONNECTING RUNWAY & PARALLEL TAXIWAY 1) The most significant factor is the exit speed of aircraft. 2) Slightly widened entrance of 30 m will be provide. 3) Total angle of turn is 3 300c- 4) The turning radius should be calculated by the following formula 5) A high turn-off speeds of 65-95 kmph a compound curve is necessary to minimize the tire wear on the nose gear. 6) The length of longer radius curve can be roughly obtained by valve of C=0.39 7) Stopping distance (SD) Where d- deceleration distance 300-450 R=
  • 34.
  • 35.
  • 36.
  • 37. VISUAL AIDS: A device which improves vision NECESSITY OF VISUAL AIDS :-  The pilots needs visual aids while landing or taking-off during all weather and at every time.  The pilots usually takes helps of the perspective view of the runway & other ground reference marks during the landing operation.  Runway thresholds, runway edges and the runway centre line are the most essential items which should be clearly visible to the pilot. (lighting)  In order to enhance the day time visibility runways, taxiways and allied structures are marked with lines & numbers. (marking)
  • 38. Airport Marking Airport area is marked in a simple manner so that the pilots can easily spot & recognize to the various airport elements. The airport markings are divided into the following  Runway marking  Taxiway marking  Runway & taxiway shoulder marking  Apron marking  Wind direction indicator  Landing direction indicator
  • 40. Airport Lighting In the day time during poor weather conditions, or at night, the visibility reduces considerably. It is essential to provide adequate lighting. the colour & general pattern of lights used in airport lighting are standardized for all civil airports. The airport lightings are divided into the following elements  Runway lighting  Taxiway lighting  Apron & hanger lighting  Lighting of Wind direction indicator  Lighting of Landing direction indicator