Factors Influence
Site Selection of
an Airport
188W1A0187 - K.JAYANAND
188W1A0188 - K.PAVANKUMAR
188W1A0193 - M.SIDDHARDHA
188W1A01A8 - S.HARSHAVARDHAN
The selection of site for a new airport has to be based on certain
criteria which will serve as a guide for the determination of its
proper location and size.
(1) Atmospheric and meteorological
conditions
(2) Availability of land for expansion
(3) Availability of utilities
(4) Development of the surrounding area
(5) Economy of construction
(6) Ground accessibility
(7) Presence of other airports.
(8) Regional plan
(9) Soil characteristics
(10) Surrounding obstructions
(11) Topography
(12) Use of airport.
Atmospheric and meteorological conditions:
● The presence of fog, haze and smoke reduces the visibility and
the poor visibility lowers the traffic capacity of an aircraft.
● Wind data should also be studied .
● Study of whether records.
Availability of land for expansion:
● As the volume of traffic increases, it will be necessary to lengthen
the runways, to provide additional support facilities and to expand
the terminal facilities. For accommodating all these new facilities,
the provision of sufficient real estate must be made.
Availability of utilities:
● An airport, especially a large one, has to be provided with the
utilities like water, electric power, telephone, sewer, etc.
Development of the surrounding area:
● The proximity of airport site to the residential areas, schools and
hospitals should be avoided whenever possible.
● Suitable zoning regulations should be imposed.
Economy of construction:
● The site which is more economical to construct should be given
preference.
● The sites having waterlogged areas or reclaimed lands and
uneven terrain should be avoided.
● The availability of local construction materials should be
considered.
Ground accessibility:
● The location of airport should be such that it results in the
shortest ground access time.
● All modes of transport should be considered for an easy ground
access to the airport.
Presence of other airports:
● The airports should be located at a
sufficient distance apart.
● The minimum distance between the
adjacent airports will depend upon
the volume and type of air traffic,
operating facilities, etc.
● If this precaution is not taken, there
will be severe air traffic congestion
due to limited air space and it will
result in the reduction of airport
capacity.
Regional plan:
● The airport site should be selected in such a way that i fits appropriately in
the regional plan.
Soil characteristics:
● The airport site with the favourable soil characteristic is desirable because it
reduces the cost of grading and drainage to a considerable extent. The area
should as far as possible be self drained.
Surrounding obstructions:
● The airport site should be clear of the obstructions likely to interfere with the
landing and taking off operations of the aircrafts.
● The zoning for height restrictions should be initiated as soon as the site has
been finally selected.
● The obstructions may either be natural like trees, sloping ground, etc., or
man-made like buildings, grid towers, etc.
Topography:
● The topographical features like ground contours, trees, streams,
etc., should be studied.
● A raised ground like a hill top is usually considered to be an ideal
site for an airport because of the following facts:
(i) It grants better visibility due to less fog.
(ii) It permits easy natural drainage.
(iii) The approach and turning zones are less obstructed.
(iv) There is natural drainage.
Use of airport:
● The airport site is decided also by the use of airport i.e.. civil or
military.
THANK YOU

More Related Content

What's hot

AIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGNAIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGNNiranjan Varma
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport EngineeringArbaz Kazi
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristicssrinivas2036
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristicsAbhishek Kumar
 
Design elements of airport taxiway
Design elements of airport taxiwayDesign elements of airport taxiway
Design elements of airport taxiwayAsok999
 
Planning OF AIRPORT REQUIREMENTS OF AIR PORT TERMINAL AREA RUNWAY LENGTH
Planning OF AIRPORT REQUIREMENTS OF AIR PORT TERMINAL AREA RUNWAY LENGTH Planning OF AIRPORT REQUIREMENTS OF AIR PORT TERMINAL AREA RUNWAY LENGTH
Planning OF AIRPORT REQUIREMENTS OF AIR PORT TERMINAL AREA RUNWAY LENGTH RAMPRASAD KUMAWAT
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Designsrinivas2036
 
Air port presentation 6th unit
Air port presentation 6th unitAir port presentation 6th unit
Air port presentation 6th unitT.Naga Anusha
 
Site distance in highway engineering
Site distance in highway engineeringSite distance in highway engineering
Site distance in highway engineeringtirath prajapati
 
Airport obstructions
Airport obstructionsAirport obstructions
Airport obstructionssrinivas2036
 
Taxiway design and geometrical design of taxiway
Taxiway design and geometrical design of taxiwayTaxiway design and geometrical design of taxiway
Taxiway design and geometrical design of taxiwayBALAJI ND
 
Wind Rose.pdf
Wind Rose.pdfWind Rose.pdf
Wind Rose.pdfWhUllahWa
 
Airport lighting airport engineering
Airport lighting  airport engineeringAirport lighting  airport engineering
Airport lighting airport engineeringKushal Patel
 

What's hot (20)

Basic runway length
Basic runway lengthBasic runway length
Basic runway length
 
AIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGNAIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGN
 
Airport lighting
Airport lightingAirport lighting
Airport lighting
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport Engineering
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristics
 
Airport engineering PART-1
Airport engineering PART-1 Airport engineering PART-1
Airport engineering PART-1
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristics
 
Airport drainage
Airport drainageAirport drainage
Airport drainage
 
Design elements of airport taxiway
Design elements of airport taxiwayDesign elements of airport taxiway
Design elements of airport taxiway
 
Planning OF AIRPORT REQUIREMENTS OF AIR PORT TERMINAL AREA RUNWAY LENGTH
Planning OF AIRPORT REQUIREMENTS OF AIR PORT TERMINAL AREA RUNWAY LENGTH Planning OF AIRPORT REQUIREMENTS OF AIR PORT TERMINAL AREA RUNWAY LENGTH
Planning OF AIRPORT REQUIREMENTS OF AIR PORT TERMINAL AREA RUNWAY LENGTH
 
Airport elements.
Airport elements.Airport elements.
Airport elements.
 
Airfield pavements
Airfield pavementsAirfield pavements
Airfield pavements
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Design
 
Air port presentation 6th unit
Air port presentation 6th unitAir port presentation 6th unit
Air port presentation 6th unit
 
Site distance in highway engineering
Site distance in highway engineeringSite distance in highway engineering
Site distance in highway engineering
 
Airport obstructions
Airport obstructionsAirport obstructions
Airport obstructions
 
airport drainage
airport drainageairport drainage
airport drainage
 
Taxiway design and geometrical design of taxiway
Taxiway design and geometrical design of taxiwayTaxiway design and geometrical design of taxiway
Taxiway design and geometrical design of taxiway
 
Wind Rose.pdf
Wind Rose.pdfWind Rose.pdf
Wind Rose.pdf
 
Airport lighting airport engineering
Airport lighting  airport engineeringAirport lighting  airport engineering
Airport lighting airport engineering
 

Similar to Factors influence site selection of an airport

Selection of Airport Site.pptx
Selection of Airport Site.pptxSelection of Airport Site.pptx
Selection of Airport Site.pptxPriyanshu Pathak
 
airports-140217060642-phpapp01 .pptx
airports-140217060642-phpapp01     .pptxairports-140217060642-phpapp01     .pptx
airports-140217060642-phpapp01 .pptxcuhp21rdtt12
 
airports-140217060642-phpapp01.pptx
airports-140217060642-phpapp01.pptxairports-140217060642-phpapp01.pptx
airports-140217060642-phpapp01.pptxNeha Kajulkar
 
Design and planning of airport
Design and planning of airportDesign and planning of airport
Design and planning of airportHarshit P Jain
 
AIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJANAIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJANNiranjan Varma
 
Airport & railways engineering ce467 pdf
Airport & railways engineering   ce467 pdfAirport & railways engineering   ce467 pdf
Airport & railways engineering ce467 pdfSaqib Imran
 
Introduction to Airport Engineering ppt.pptx
Introduction to Airport Engineering ppt.pptxIntroduction to Airport Engineering ppt.pptx
Introduction to Airport Engineering ppt.pptxPriyanka Dange
 
Airport Site Selection
Airport Site SelectionAirport Site Selection
Airport Site SelectionJulie Davis
 
Chapter 3 geometric design
Chapter 3 geometric  designChapter 3 geometric  design
Chapter 3 geometric designBashaFayissa1
 
1.introduction
1.introduction1.introduction
1.introductionMani Vel
 
Lecture 2_Route selection, Earthworks.pdf
Lecture 2_Route selection, Earthworks.pdfLecture 2_Route selection, Earthworks.pdf
Lecture 2_Route selection, Earthworks.pdfOmarAbdi39
 
Chapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaChapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaBashaFayissa1
 
Taxiway design perfect ppt
Taxiway design perfect pptTaxiway design perfect ppt
Taxiway design perfect pptVijay Reddy
 
Airport planning - Railways, airports, docks and harbour engineering (RAHE)
Airport planning - Railways, airports, docks and harbour engineering  (RAHE)Airport planning - Railways, airports, docks and harbour engineering  (RAHE)
Airport planning - Railways, airports, docks and harbour engineering (RAHE)Shanmugasundaram N
 
Airport Planning RHTA - VTU Module 4
Airport Planning RHTA - VTU Module 4Airport Planning RHTA - VTU Module 4
Airport Planning RHTA - VTU Module 4AJEETH B
 

Similar to Factors influence site selection of an airport (20)

Airport Engineering
Airport EngineeringAirport Engineering
Airport Engineering
 
Selection of Airport Site.pptx
Selection of Airport Site.pptxSelection of Airport Site.pptx
Selection of Airport Site.pptx
 
Airports
AirportsAirports
Airports
 
airports-140217060642-phpapp01 .pptx
airports-140217060642-phpapp01     .pptxairports-140217060642-phpapp01     .pptx
airports-140217060642-phpapp01 .pptx
 
airports-140217060642-phpapp01.pptx
airports-140217060642-phpapp01.pptxairports-140217060642-phpapp01.pptx
airports-140217060642-phpapp01.pptx
 
Design and planning of airport
Design and planning of airportDesign and planning of airport
Design and planning of airport
 
Airport runway construction
Airport runway constructionAirport runway construction
Airport runway construction
 
AIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJANAIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJAN
 
Airport & railways engineering ce467 pdf
Airport & railways engineering   ce467 pdfAirport & railways engineering   ce467 pdf
Airport & railways engineering ce467 pdf
 
Introduction to Airport Engineering ppt.pptx
Introduction to Airport Engineering ppt.pptxIntroduction to Airport Engineering ppt.pptx
Introduction to Airport Engineering ppt.pptx
 
Airport Site Selection
Airport Site SelectionAirport Site Selection
Airport Site Selection
 
Chapter 3 geometric design
Chapter 3 geometric  designChapter 3 geometric  design
Chapter 3 geometric design
 
1.introduction
1.introduction1.introduction
1.introduction
 
Lecture 2_Route selection, Earthworks.pdf
Lecture 2_Route selection, Earthworks.pdfLecture 2_Route selection, Earthworks.pdf
Lecture 2_Route selection, Earthworks.pdf
 
Chapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaChapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaa
 
Taxiway design perfect ppt
Taxiway design perfect pptTaxiway design perfect ppt
Taxiway design perfect ppt
 
Airport Engineering
Airport Engineering Airport Engineering
Airport Engineering
 
Airport planning - Railways, airports, docks and harbour engineering (RAHE)
Airport planning - Railways, airports, docks and harbour engineering  (RAHE)Airport planning - Railways, airports, docks and harbour engineering  (RAHE)
Airport planning - Railways, airports, docks and harbour engineering (RAHE)
 
Airport layout
Airport layoutAirport layout
Airport layout
 
Airport Planning RHTA - VTU Module 4
Airport Planning RHTA - VTU Module 4Airport Planning RHTA - VTU Module 4
Airport Planning RHTA - VTU Module 4
 

Recently uploaded

The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxThe Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxCenterEnamel
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdfKamal Acharya
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfKamal Acharya
 
Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfAyahmorsy
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234AafreenAbuthahir2
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdfAhmedHussein950959
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGKOUSTAV SARKAR
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfPipe Restoration Solutions
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdfKamal Acharya
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf884710SadaqatAli
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...Amil baba
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationRobbie Edward Sayers
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-IVigneshvaranMech
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edgePaco Orozco
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsAtif Razi
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfKamal Acharya
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerapareshmondalnita
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationDr. Radhey Shyam
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdfKamal Acharya
 

Recently uploaded (20)

The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxThe Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answer
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 

Factors influence site selection of an airport

  • 1. Factors Influence Site Selection of an Airport 188W1A0187 - K.JAYANAND 188W1A0188 - K.PAVANKUMAR 188W1A0193 - M.SIDDHARDHA 188W1A01A8 - S.HARSHAVARDHAN
  • 2. The selection of site for a new airport has to be based on certain criteria which will serve as a guide for the determination of its proper location and size. (1) Atmospheric and meteorological conditions (2) Availability of land for expansion (3) Availability of utilities (4) Development of the surrounding area (5) Economy of construction (6) Ground accessibility (7) Presence of other airports. (8) Regional plan (9) Soil characteristics (10) Surrounding obstructions (11) Topography (12) Use of airport.
  • 3. Atmospheric and meteorological conditions: ● The presence of fog, haze and smoke reduces the visibility and the poor visibility lowers the traffic capacity of an aircraft. ● Wind data should also be studied . ● Study of whether records. Availability of land for expansion: ● As the volume of traffic increases, it will be necessary to lengthen the runways, to provide additional support facilities and to expand the terminal facilities. For accommodating all these new facilities, the provision of sufficient real estate must be made.
  • 4. Availability of utilities: ● An airport, especially a large one, has to be provided with the utilities like water, electric power, telephone, sewer, etc. Development of the surrounding area: ● The proximity of airport site to the residential areas, schools and hospitals should be avoided whenever possible. ● Suitable zoning regulations should be imposed.
  • 5. Economy of construction: ● The site which is more economical to construct should be given preference. ● The sites having waterlogged areas or reclaimed lands and uneven terrain should be avoided. ● The availability of local construction materials should be considered. Ground accessibility: ● The location of airport should be such that it results in the shortest ground access time. ● All modes of transport should be considered for an easy ground access to the airport.
  • 6. Presence of other airports: ● The airports should be located at a sufficient distance apart. ● The minimum distance between the adjacent airports will depend upon the volume and type of air traffic, operating facilities, etc. ● If this precaution is not taken, there will be severe air traffic congestion due to limited air space and it will result in the reduction of airport capacity.
  • 7. Regional plan: ● The airport site should be selected in such a way that i fits appropriately in the regional plan. Soil characteristics: ● The airport site with the favourable soil characteristic is desirable because it reduces the cost of grading and drainage to a considerable extent. The area should as far as possible be self drained. Surrounding obstructions: ● The airport site should be clear of the obstructions likely to interfere with the landing and taking off operations of the aircrafts. ● The zoning for height restrictions should be initiated as soon as the site has been finally selected. ● The obstructions may either be natural like trees, sloping ground, etc., or man-made like buildings, grid towers, etc.
  • 8. Topography: ● The topographical features like ground contours, trees, streams, etc., should be studied. ● A raised ground like a hill top is usually considered to be an ideal site for an airport because of the following facts: (i) It grants better visibility due to less fog. (ii) It permits easy natural drainage. (iii) The approach and turning zones are less obstructed. (iv) There is natural drainage. Use of airport: ● The airport site is decided also by the use of airport i.e.. civil or military.