Contract and Project Management




David Sowden, The University of Hull
8
57086
Contract and Project Management

Introduction to Processes -
Closing a Project




David Sowden, The University of Hull
Overview

• Closing a Project
  –   Fundamental principles
  –   Contexts
  –   Process description
  –   Decommissioning a Project
  –   Identifying Follow-on Actions
  –   Evaluating a Project




                                      3
Closing a Project                           THE B
                                                  AS              ICS
    Check that all products have
   been delivered and approved by
            the customers

                                    Document and later actions that
                                        should be taken by the
                                      management and support
                                               groups

    Plan when and how to assess
    achievement of the expected
              benefits


                                        Report on the project’s
                                            performance



                                                                      4
Relationships
of Processes
                                     Initiating a
                                       Project

                                                    Managing
                                                     a Stage
                                                    Boundary



                      Directing a
                        Project     End
          Starting
          a Project




                                    Controlling
         Closing a                    a Stage
          Project




                        Managing
                        ‘Product’
                        Delivery

                                                               5
Icons

        Guidelines - Rules, Policies,
        instructions that should be
        followed



        Resources - tools, systems
        or materials required to
        complete a task



                                        6
Closing a Project (1a)


Directing a
  Project     Premature close           Prepare premature close



                                Create additional work estimates
                                Update Issue Register
                                Update Project Plan
                                PID
                                Project Plan




                                                                   7
Closing a Project (1b)


Controlling    Project end
              approaching
                                     Prepare planned closure
 a Stage



                             Update Project Plan
                             ‘Product Status Account
                             PID
                             Project Plan




                                                               8
Closing a Project (2)



    Closure prepared                 Hand over ‘products’



                        Obtain acceptance record
                        Update Benefits Review Plan
                        Update Configuration Item Records
                        Create follow-on action recommendations
                        PID
                        Issues register
                        Configuration Management Strategy
                        Risk Register


                                                              9
Closing a Project (3)



  ‘Products’ handed over                 Evaluate the project



                           Create Lessons Report
                           End Project Report
                           Follow-on actions recommendations
                           Issues register
                           Lessons Log
                           Quality Register




                                                                10
Closing a Project (4)



    Project evaluated           Recommend project closure



                        Close Daily Log
                        Prepare draft project closure notification
                        Close Issue Register
                        Close Lessons Log
                        Close Quality Register
                        PID
                        Communication Management Strategy




                                                                    11
Closing a Project (5)



  Closure recommended   Directing a Project


                                        section 4




                                               12
TASK


Review your project closure
        procedures
Closing a Project                                                                                        CHEC
  Have all products been completed and approved?                                                                              K
  Has a Product Status Account been created to verify the status of all the products?

  Have all outstanding issues been documented as follow-on recommendations ready for distribution subject to Project Board
  approval?
  For premature closure, has the means for recovering products that have been completed or are in progress been approved by
  the Project Board? If requested, was an Exception Plan created and approved?
  Is there an acceptance record for the handover of the project product?

  Does the acceptance record include operational and maintenance acceptance (if applicable)

  Has the lessons Log been reviewed and a Lessons Report created ready for distribution subject to Project Board approval?

  Has the Project Plan been updated with actuals?

  Has the Business Case been updated with actuals?

  Has the Benefits Review Plan been updated with actuals

  Has the End Project Report been produced showing actuals against planned performance and summarising lessons and follow-
  on action recommendations?
  Has the End Project Report been issued to the Project Board in accordance with project controls?

  Has a draft project closure notification been created for the Project Board approval and onward distribution?

  Has all registers and logs been closed?

  Has all project documentation been archived?

More Related Content

What's hot

Sas Presentation
Sas PresentationSas Presentation
Sas Presentationpats384888
 
Project Management in nutshell
Project Management in nutshellProject Management in nutshell
Project Management in nutshellStamford Global
 
Project integration-slidesppt3386
Project integration-slidesppt3386Project integration-slidesppt3386
Project integration-slidesppt3386Mabroor Ahmed
 
Bechtel project planning example
Bechtel project planning exampleBechtel project planning example
Bechtel project planning exampleasfandiyar
 
PRINCE2 Process Model
PRINCE2 Process ModelPRINCE2 Process Model
PRINCE2 Process ModelprojectingIT
 
Paul Capello CHC 2010 Final
Paul Capello CHC 2010 FinalPaul Capello CHC 2010 Final
Paul Capello CHC 2010 Finaltigcap
 
Vonnie simonsen
Vonnie simonsenVonnie simonsen
Vonnie simonsenNASAPMC
 
Project scope management
Project scope managementProject scope management
Project scope managementAnit Roy
 
Scrum under PRINCE 2
Scrum under PRINCE 2Scrum under PRINCE 2
Scrum under PRINCE 2Vishal Sharma
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthewNASAPMC
 
Agile Project Manager
Agile Project ManagerAgile Project Manager
Agile Project ManagerYogesh Hubli
 
Project Tracking and Scope Management
Project Tracking and Scope ManagementProject Tracking and Scope Management
Project Tracking and Scope ManagementTalha Siddiqui
 
SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01Steven Leahy
 
Deciding the software development life cycle procedure (according to iso12207)
Deciding the software development life cycle procedure (according to iso12207)Deciding the software development life cycle procedure (according to iso12207)
Deciding the software development life cycle procedure (according to iso12207)Fatih Algün
 
Sage Project Management
Sage Project Management Sage Project Management
Sage Project Management RKLeSolutions
 
Unit2 scheduling wbs_network Management
Unit2 scheduling wbs_network Management Unit2 scheduling wbs_network Management
Unit2 scheduling wbs_network Management Reetesh Gupta
 

What's hot (20)

Sas Presentation
Sas PresentationSas Presentation
Sas Presentation
 
Project Management in nutshell
Project Management in nutshellProject Management in nutshell
Project Management in nutshell
 
Itto
IttoItto
Itto
 
Project integration-slidesppt3386
Project integration-slidesppt3386Project integration-slidesppt3386
Project integration-slidesppt3386
 
Bechtel project planning example
Bechtel project planning exampleBechtel project planning example
Bechtel project planning example
 
PRINCE2 Process Model
PRINCE2 Process ModelPRINCE2 Process Model
PRINCE2 Process Model
 
Paul Capello CHC 2010 Final
Paul Capello CHC 2010 FinalPaul Capello CHC 2010 Final
Paul Capello CHC 2010 Final
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Vonnie simonsen
Vonnie simonsenVonnie simonsen
Vonnie simonsen
 
Project scope management
Project scope managementProject scope management
Project scope management
 
Scrum under PRINCE 2
Scrum under PRINCE 2Scrum under PRINCE 2
Scrum under PRINCE 2
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 
Agile Project Manager
Agile Project ManagerAgile Project Manager
Agile Project Manager
 
Project Tracking and Scope Management
Project Tracking and Scope ManagementProject Tracking and Scope Management
Project Tracking and Scope Management
 
SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01
 
Stepwise planning
Stepwise planningStepwise planning
Stepwise planning
 
Deciding the software development life cycle procedure (according to iso12207)
Deciding the software development life cycle procedure (according to iso12207)Deciding the software development life cycle procedure (according to iso12207)
Deciding the software development life cycle procedure (according to iso12207)
 
A guide for project managers prince2
A guide for project managers prince2A guide for project managers prince2
A guide for project managers prince2
 
Sage Project Management
Sage Project Management Sage Project Management
Sage Project Management
 
Unit2 scheduling wbs_network Management
Unit2 scheduling wbs_network Management Unit2 scheduling wbs_network Management
Unit2 scheduling wbs_network Management
 

Viewers also liked

Security Surveillance 2010_Final
Security Surveillance 2010_FinalSecurity Surveillance 2010_Final
Security Surveillance 2010_FinalRKDickey
 
Board presentation
Board presentationBoard presentation
Board presentationProjRisk302
 
Why You Should Learn The Command Line
Why You Should Learn The Command LineWhy You Should Learn The Command Line
Why You Should Learn The Command LineLaurence Bradford
 
Power over ethernet
Power over ethernetPower over ethernet
Power over ethernetMoises Rojas
 
Ingilizce SBS Kursu Unit 2 road to success , adjectives and adverbs
Ingilizce SBS Kursu Unit 2 road to success , adjectives and adverbsIngilizce SBS Kursu Unit 2 road to success , adjectives and adverbs
Ingilizce SBS Kursu Unit 2 road to success , adjectives and adverbsbuket77
 
Assessment kurikulum 2013
Assessment kurikulum 2013Assessment kurikulum 2013
Assessment kurikulum 2013Jati Jakmania
 

Viewers also liked (7)

Security Surveillance 2010_Final
Security Surveillance 2010_FinalSecurity Surveillance 2010_Final
Security Surveillance 2010_Final
 
Board presentation
Board presentationBoard presentation
Board presentation
 
Why You Should Learn The Command Line
Why You Should Learn The Command LineWhy You Should Learn The Command Line
Why You Should Learn The Command Line
 
Power over ethernet
Power over ethernetPower over ethernet
Power over ethernet
 
Ingilizce SBS Kursu Unit 2 road to success , adjectives and adverbs
Ingilizce SBS Kursu Unit 2 road to success , adjectives and adverbsIngilizce SBS Kursu Unit 2 road to success , adjectives and adverbs
Ingilizce SBS Kursu Unit 2 road to success , adjectives and adverbs
 
Seo game
Seo gameSeo game
Seo game
 
Assessment kurikulum 2013
Assessment kurikulum 2013Assessment kurikulum 2013
Assessment kurikulum 2013
 

Similar to 57086 08 closing_a_project

Project management
Project managementProject management
Project managementSameer Kumar
 
Introduction project management
Introduction  project managementIntroduction  project management
Introduction project managementHager Aamer
 
William.tippin.update
William.tippin.updateWilliam.tippin.update
William.tippin.updateNASAPMC
 
1844final 100811113357 Phpapp01
1844final 100811113357 Phpapp011844final 100811113357 Phpapp01
1844final 100811113357 Phpapp01pmfigliola
 
1844final 100811113357 Phpapp01
1844final 100811113357 Phpapp011844final 100811113357 Phpapp01
1844final 100811113357 Phpapp01pmfigliola
 
Pmbok 4th edition chapter 3 - Project Management Processes for a Project
Pmbok 4th edition   chapter 3 - Project Management Processes for a Project Pmbok 4th edition   chapter 3 - Project Management Processes for a Project
Pmbok 4th edition chapter 3 - Project Management Processes for a Project Ahmad Maharma, PMP,RMP
 
Project management fundamentals
Project management fundamentals Project management fundamentals
Project management fundamentals Rajasekar M
 
Pmbok 4th edition chapter 4 - Project Integration Management
Pmbok 4th edition   chapter 4 - Project Integration Management Pmbok 4th edition   chapter 4 - Project Integration Management
Pmbok 4th edition chapter 4 - Project Integration Management Ahmad Maharma, PMP,RMP
 
Agile governance The New Disinfectant
Agile governance The New DisinfectantAgile governance The New Disinfectant
Agile governance The New DisinfectantRenee Troughton
 
Pmbok 4th edition chapter 6 - Project Time Management
Pmbok 4th edition   chapter 6 - Project Time Management Pmbok 4th edition   chapter 6 - Project Time Management
Pmbok 4th edition chapter 6 - Project Time Management Ahmad Maharma, PMP,RMP
 
Project mgmt life cycle origination
Project mgmt life cycle originationProject mgmt life cycle origination
Project mgmt life cycle originationMujtaba Masood
 
Pmbok 4th edition chapter 5 - Project Scope Management
Pmbok 4th edition   chapter 5 - Project Scope Management Pmbok 4th edition   chapter 5 - Project Scope Management
Pmbok 4th edition chapter 5 - Project Scope Management Ahmad Maharma, PMP,RMP
 
ERP Implementation Methodology
ERP Implementation MethodologyERP Implementation Methodology
ERP Implementation MethodologyThanh Nguyen
 

Similar to 57086 08 closing_a_project (20)

57086 03 initiating_a_project
57086 03 initiating_a_project57086 03 initiating_a_project
57086 03 initiating_a_project
 
57086 05 managing_productdelivery
57086 05 managing_productdelivery57086 05 managing_productdelivery
57086 05 managing_productdelivery
 
57086 07 managing_a_stageboundary
57086 07 managing_a_stageboundary57086 07 managing_a_stageboundary
57086 07 managing_a_stageboundary
 
58086 04 directing_a_project
58086 04 directing_a_project58086 04 directing_a_project
58086 04 directing_a_project
 
Project management
Project managementProject management
Project management
 
Introduction project management
Introduction  project managementIntroduction  project management
Introduction project management
 
William.tippin.update
William.tippin.updateWilliam.tippin.update
William.tippin.update
 
1844final 100811113357 Phpapp01
1844final 100811113357 Phpapp011844final 100811113357 Phpapp01
1844final 100811113357 Phpapp01
 
1844final 100811113357 Phpapp01
1844final 100811113357 Phpapp011844final 100811113357 Phpapp01
1844final 100811113357 Phpapp01
 
Pmbok 4th edition chapter 3 - Project Management Processes for a Project
Pmbok 4th edition   chapter 3 - Project Management Processes for a Project Pmbok 4th edition   chapter 3 - Project Management Processes for a Project
Pmbok 4th edition chapter 3 - Project Management Processes for a Project
 
Project management fundamentals
Project management fundamentals Project management fundamentals
Project management fundamentals
 
Pmbok 4th edition chapter 4 - Project Integration Management
Pmbok 4th edition   chapter 4 - Project Integration Management Pmbok 4th edition   chapter 4 - Project Integration Management
Pmbok 4th edition chapter 4 - Project Integration Management
 
Agile Project Management
Agile Project ManagementAgile Project Management
Agile Project Management
 
57086 13 controls
57086 13 controls57086 13 controls
57086 13 controls
 
Agile governance The New Disinfectant
Agile governance The New DisinfectantAgile governance The New Disinfectant
Agile governance The New Disinfectant
 
Pmbok 4th edition chapter 6 - Project Time Management
Pmbok 4th edition   chapter 6 - Project Time Management Pmbok 4th edition   chapter 6 - Project Time Management
Pmbok 4th edition chapter 6 - Project Time Management
 
57086 02 starting_upa_project
57086 02 starting_upa_project57086 02 starting_upa_project
57086 02 starting_upa_project
 
Project mgmt life cycle origination
Project mgmt life cycle originationProject mgmt life cycle origination
Project mgmt life cycle origination
 
Pmbok 4th edition chapter 5 - Project Scope Management
Pmbok 4th edition   chapter 5 - Project Scope Management Pmbok 4th edition   chapter 5 - Project Scope Management
Pmbok 4th edition chapter 5 - Project Scope Management
 
ERP Implementation Methodology
ERP Implementation MethodologyERP Implementation Methodology
ERP Implementation Methodology
 

More from Engineering Department (15)

Glossary
GlossaryGlossary
Glossary
 
57086 23 goldratt
57086 23 goldratt57086 23 goldratt
57086 23 goldratt
 
57086 22 comic_relief
57086 22 comic_relief57086 22 comic_relief
57086 22 comic_relief
 
57086 20 quality_review
57086 20 quality_review57086 20 quality_review
57086 20 quality_review
 
57086 19 change_controltechniques
57086 19 change_controltechniques57086 19 change_controltechniques
57086 19 change_controltechniques
 
57086 18 product-based_planning
57086 18 product-based_planning57086 18 product-based_planning
57086 18 product-based_planning
 
57086 17 change_control_01
57086 17 change_control_0157086 17 change_control_01
57086 17 change_control_01
 
57086 16 configuration_management
57086 16 configuration_management57086 16 configuration_management
57086 16 configuration_management
 
57086 15 quality
57086 15 quality57086 15 quality
57086 15 quality
 
57086 14 management_ofrisk
57086 14 management_ofrisk57086 14 management_ofrisk
57086 14 management_ofrisk
 
57086 12 plans
57086 12 plans57086 12 plans
57086 12 plans
 
57086 09 planning
57086 09 planning57086 09 planning
57086 09 planning
 
57086 11 organisation
57086 11 organisation57086 11 organisation
57086 11 organisation
 
57086 10 business_case
57086 10 business_case57086 10 business_case
57086 10 business_case
 
57086 01 introduction
57086 01 introduction57086 01 introduction
57086 01 introduction
 

Recently uploaded

Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 

Recently uploaded (20)

Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 

57086 08 closing_a_project

  • 1. 8 57086 Contract and Project Management David Sowden, The University of Hull
  • 2. 8 57086 Contract and Project Management Introduction to Processes - Closing a Project David Sowden, The University of Hull
  • 3. Overview • Closing a Project – Fundamental principles – Contexts – Process description – Decommissioning a Project – Identifying Follow-on Actions – Evaluating a Project 3
  • 4. Closing a Project THE B AS ICS Check that all products have been delivered and approved by the customers Document and later actions that should be taken by the management and support groups Plan when and how to assess achievement of the expected benefits Report on the project’s performance 4
  • 5. Relationships of Processes Initiating a Project Managing a Stage Boundary Directing a Project End Starting a Project Controlling Closing a a Stage Project Managing ‘Product’ Delivery 5
  • 6. Icons Guidelines - Rules, Policies, instructions that should be followed Resources - tools, systems or materials required to complete a task 6
  • 7. Closing a Project (1a) Directing a Project Premature close Prepare premature close Create additional work estimates Update Issue Register Update Project Plan PID Project Plan 7
  • 8. Closing a Project (1b) Controlling Project end approaching Prepare planned closure a Stage Update Project Plan ‘Product Status Account PID Project Plan 8
  • 9. Closing a Project (2) Closure prepared Hand over ‘products’ Obtain acceptance record Update Benefits Review Plan Update Configuration Item Records Create follow-on action recommendations PID Issues register Configuration Management Strategy Risk Register 9
  • 10. Closing a Project (3) ‘Products’ handed over Evaluate the project Create Lessons Report End Project Report Follow-on actions recommendations Issues register Lessons Log Quality Register 10
  • 11. Closing a Project (4) Project evaluated Recommend project closure Close Daily Log Prepare draft project closure notification Close Issue Register Close Lessons Log Close Quality Register PID Communication Management Strategy 11
  • 12. Closing a Project (5) Closure recommended Directing a Project section 4 12
  • 13. TASK Review your project closure procedures
  • 14. Closing a Project CHEC Have all products been completed and approved? K Has a Product Status Account been created to verify the status of all the products? Have all outstanding issues been documented as follow-on recommendations ready for distribution subject to Project Board approval? For premature closure, has the means for recovering products that have been completed or are in progress been approved by the Project Board? If requested, was an Exception Plan created and approved? Is there an acceptance record for the handover of the project product? Does the acceptance record include operational and maintenance acceptance (if applicable) Has the lessons Log been reviewed and a Lessons Report created ready for distribution subject to Project Board approval? Has the Project Plan been updated with actuals? Has the Business Case been updated with actuals? Has the Benefits Review Plan been updated with actuals Has the End Project Report been produced showing actuals against planned performance and summarising lessons and follow- on action recommendations? Has the End Project Report been issued to the Project Board in accordance with project controls? Has a draft project closure notification been created for the Project Board approval and onward distribution? Has all registers and logs been closed? Has all project documentation been archived?