This document provides guidance on accurately estimating quantities for civil works projects. It lists important points to consider when estimating excavation, backfilling, structure dimensions, reinforcement lengths and weights, and conversion factors. The document also outlines steps for quantity take-off, including estimating excavation, concrete, waterproofing, blockwork, plastering, finishes and more. Careful measurement and consideration of project details is emphasized.
CADmantra Technologies Pvt. Ltd. is one of the best Cad training company in northern zone in India . which are provided many types of courses in cad field i.e AUTOCAD,SOLIDWORK,CATIA,CRE-O,Uniraphics-NX, CNC, REVIT, STAAD.Pro. And many courses
Contact: www.cadmantra.com
www.cadmantra.blogspot.com
www.cadmantra.wix.com
CADmantra Technologies Pvt. Ltd. is one of the best Cad training company in northern zone in India . which are provided many types of courses in cad field i.e AUTOCAD,SOLIDWORK,CATIA,CRE-O,Uniraphics-NX, CNC, REVIT, STAAD.Pro. And many courses
Contact: www.cadmantra.com
www.cadmantra.blogspot.com
www.cadmantra.wix.com
Forklift Classes Overview by Intella PartsIntella Parts
Discover the different forklift classes and their specific applications. Learn how to choose the right forklift for your needs to ensure safety, efficiency, and compliance in your operations.
For more technical information, visit our website https://intellaparts.com
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSveerababupersonal22
It consists of cw radar and fmcw radar ,range measurement,if amplifier and fmcw altimeterThe CW radar operates using continuous wave transmission, while the FMCW radar employs frequency-modulated continuous wave technology. Range measurement is a crucial aspect of radar systems, providing information about the distance to a target. The IF amplifier plays a key role in signal processing, amplifying intermediate frequency signals for further analysis. The FMCW altimeter utilizes frequency-modulated continuous wave technology to accurately measure altitude above a reference point.
1. Important Points to Remember for Quantity Estimation.
Civil Works:
To carefully note the various levels while calculating excavation & backfilling.
To make note of the various levels of the structure & compare the measured
heights/length of various items with the levels.
To check all the sections & elevations carefully prior to any estimation.
To look into the NOTES given at the right side of the drawing in the info column.
To look out for trenches, drops, slab elevations, projections & many others.
To check for different slab depths over the plan.
To carefully look into the openings, their types & numbers.
To measure the height of the pedestal & columns up to the top level of above Ground
(plinth) & Roof beams respectively.
To measure the length of the beam from column face to face.
To carefully note the various given dimensions of the different structures.
To carefully carry out the estimation of staircase, trenches etc. separately.
To carefully note the beam positions & their depths while calculating Block/Brickwork.
To consider the height of the wall for internal plastering works up to the slab bottom &
thereby considering deductions for openings.
To carefully note the beams bottom surface (where there is no block work) for roof
bottom plastering.
Steel Reinforcement:
To carefully name & number every individual rods before any calculations & workout
the no. of rods, length & span accordingly & individually.
To learn the extra length formulae for the 45 & 30 deg cranks.
To learn the calculations of the length & no. of rods for the top reinforcement in slab.
To carefully note the data while calculating the length of rods, their numbers, their
span of distribution etc.
To carefully keep note of the covers for various items of the structure.
To carefully note the bends, elevations, cranks, while calculating length of rods.
To carefully calculate the stirrups, their shapes, bends & the no. of stirrups for columns
& beams – Please learn about no. of branches of stirrups.
To learn the measurement of lengths of 45, 90 deg bends, small cranks, hooks etc.
2. Unit Weight of steel (Kg/m)
Unit Weight of steel (Kg/m) = Area (mm2) X Density (Kg/m3)
= (Pi * d2) / 4 X 7850.
= 3.141*d2 / 4 X 7850.
Since d is in mm, convert it into meters by diving it by (1000)
= 3.141*d2*7850/ (4*(1000)2)
= (3.141*7850*d2) / (4000000)
= 0.00616 * (d2)
= d2 / 162.
1 cum = 30.31 cft.
1 sqm = 10.76 sft.
1 m = 3.28 ft.
1 feet = 0.305 m.
1 inch = 25.4 mm.
1 cum of cement = 1440 kgs.
1 bag of cement (50kg) = 0.034 cum.
1 sqm of block work = 13 blocks (for 6” & 8”),
15 blocks (for 4” block)
1 cum of brick work = 473 bricks
1 sqm of brick work = 44 bricks
M5 = 1:5:4
M7.5 = 1:4:8
M10 = 1:3:6
M15 = 1:2:4
M20 = 1:1.5:3
M25 = 1:1:2
3. Steps in Quantity Estimation
1. Excavation - Individual footings / Entire Area with extra working space.
2. Backfilling - By Parts / Total excavation minus concrete qty below GL.
3. Column Necks/Pedestals - up to Grade Beam top level.
4. Plinth/Grade Beam - PCC & Concrete (Column face to face).
5. Columns - Grade Beam top to Roof Beam bottom.
6. Grade Slab - PCC, moisture insulation polyethylene & concrete.
7. Water Insulation/Bitumen for the substructure
Footing bottom, side & top
Column neck sides
Concrete Walls
Grade beams below GL
Grade Slab Bottom
8. Roof Beam concrete
9. Roof Slab Concrete
10. Parappet Wall - RCC / Block work
11. Lintel Concrete
12. Block work
13. Plastering - Ceiling, Wall - ext & int, jambs.
14. Painting
15. Flooring - cement, tiles, marble etc.
16. Schedule of openings
17. Floor Finishes
Roof Concrete slopes
Heat insulation layers
Screed concrete
Mortar floor