SlideShare a Scribd company logo
Project Management Framework (Fundamentals)
You are guaranteed to get at least 5 questions from this section. Following are
important topics you need to cover in this section

Definitions of Project and Project Management
Project
“A project is a temporary endeavor undertaken to create a unique product, service, or
result. The temporary nature of projects indicates a definite beginning and end.”,
PMBOK Guide, 4th edition, 2008.
-

Temporary does not necessarily mean short in duration.

-

Temporary does not generally apply to the product, service, or result created by
the project.

-

Progressive Elaboration is one of the main characteristics of the project.

Project Specifications;
-

-

A project is different from day-to-day business and it has a specific Start date and
End date.
The ongoing work effort is generally a repetitive process because it follows an
organization’s existing procedures and that’s why Project is different from
operations and maintenance...etc.
A project creates a unique product, service, or result, although repetitive
elements may be present in it.
Because of the unique nature of projects, there may be uncertainties about the
products, services, or results that the project creates.
The end is reached when:
 The stakeholders expectations are met or exceeded, or


-

The project is terminated because its objectives will not or cannot
be met, or the project is terminated because the need for it no
longer exists.

To determine if some activity is a project or not, ask the questions:
 Is it unique?
 Does the project have a limited time frame?
 Is there a way to determine when the project is completed?
 Is there a way to determine stakeholder satisfaction?

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Project Stakeholders
-

-

Stakeholders are those people or organizations with a vested interest in the
project. They have something to either gain or lose as a result of the project.
Stakeholders often have very different or conflicting objectives.
Key stakeholders should be identified and contacted early on to get their input
for the project overview, goals, and deliverables
Forgetting an important stakeholder could be a project killer.
The project sponsor, generally an executive in the organization with the
authority to assign resources and enforce decisions regarding the project. He is a
stakeholder.
The customer is a stakeholder as are contractors and suppliers.
The project manager and the managers from other departments in the
organization are stakeholders as well.

Cost, Risk and uncertainty vs. Time

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Project Management

“The application of knowledge, skills, tools, and techniques to describe,
organizes, execute, and monitor the work of project activities in order to meet or
exceed stakeholder requirements from a project.”
Managing a project typically includes:
-

-

Identifying requirements,
Addressing the various needs, concerns, and expectations of the stakeholders as
the project is planned and carried out, then, managing various constraints to
accomplish objectives.
Balancing the competing project constraints including, but not limited to:
 Scope,



Resources, and



-

Budget,



-

Schedule,



-

Quality,

Risk.

To manage Projects effectively those constraints should be divided into Phases
and smallest possible sub phases. This iterative process should go up to the level
where further division creates confusion rather than helping the project. In
database terminology we call this as "Atomic level”.
PMI defined 42 project management processes / Atomic processes to handle all
aspects of a project life.
PMBOK guide defines Knowledge Areas for the Project Managers. Managers will
use these skills (Knowledge) to work on given INPUTS using TOOLS to produce
OUTPUTS. Those are;
1. Project Integration Management
2. Project Scope Management
3. Project Time Management
4. Project Cost Management
5. Project Quality Management
6. Project Human Resource Management
7. Project Communications Management

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
8. Project Risk Management.
9. Project Procurement Management
PM processes apply to the 5 phases of a project life:
1. Initiating,
2. Planning,
3. Executing,
4. Monitoring and Controlling, and
5. Closing.
Project, Program and Portfolio
-

A program is defined as a group of related projects managed in a coordinated

-

way to obtain benefits and control which not available from managing them
individually. A project may or may not be part of a program but a program will
always have projects.
A portfolio refers to a collection of projects or programs and other work that are
grouped together to facilitate effective management of that work to meet
strategic business objectives. The projects or programs of the portfolio may not
necessarily be interdependent or directly related

Project Management Office (PMO)
-

-

A project management office (PMO) is an organizational body or entity assigned
various responsibilities related to the centralized and coordinated management
of those projects under its domain. The responsibilities of a PMO can range from
providing project management support functions to actually being responsible
for the direct management of a project.
A primary function of a PMO is to support project managers in a variety of ways
which may include, but are not limited to:
 Identifying and developing project management methodology, best
practices, and standards;


Developing and managing project policies, procedures, templates, and
other shared documentation (organizational process assets);



Coaching, monitoring, training, and oversight;



Monitoring compliance with project management standards, policies,
procedures, and templates via project audits;



Managing shared resources across all projects administered by the PMO;
and

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD


Coordinating communication across projects.

Project Manager’s Role
-

Project managers are assigned by the performing organization to achieve the
project objectives.

-

Project manager is in charge of all aspects of the project including, but not
limited to:
 Developing the project management plan and all related component
plans,



-

Keeping the project on track in terms of schedule and budget,
Identifying, monitoring, and responding to risk, and

 Providing accurate and timely reporting of project metrics.
The project manager is the lead person responsible for communicating with all
stakeholders, particularly the project sponsor, project team, and other key
stakeholders.

Good Project Manager’s Skills
-

Communication skills

-

Organizational and Planning Skills

-

Budgeting Skills

-

Problem Solving and Decision making

-

Negotiating and Influencing

-

Leadership Skills

-

Team Building and Human Resources

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Project Triple-Constraint

Project Organizational Structure
-

Organizational Structures; project organizations need to have a structure to deliver
undertaken project.
- There are 3 major types of organizations:
 Functional Organizations


Projectized Organizations



Matrix Organizations
 Weak Matrix organizations


-

Strong Matrix organizations

 Balanced Matrix organizations
Variations and combinations may exist.
The level of authority the project manager enjoys is denoted by the
organizational structure.

1. Functional Organization;
-

Organizations is centered on specialties and grouped by function.

-

Each department will do its project work independent of others.

-

Each employee reports to only one manager.

-

It is important to know and respect the chain of command.

-

Project managers have little to no formal authority.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
-

Good communication, interpersonal, and influencing skills on the part of the
project manager are required to bring about a successful project under this
structure.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
2. Projectized Organization
-

Projectized organizations are nearly the opposite of functional organizations. It
aims to develop loyalty to the project, not to a functional manager.

-

The focus of this type of organization is the project itself.

-

Most of the organization’s resources are involved in project work,

-

Team members are often co-located,

-

Project managers have a great deal of independence and authority.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
3. Matrix Organization
-

Matrix organizations are a blend of functional and projectized characteristics.

-

Weak matrix maintains many of the characteristics of a functional organization,
and the project manager role is more of a coordinator or expediter than that of a
true project manager.

-

Strong matrix has many of the characteristics of the projectized organization,
and can have full-time project managers with considerable authority and fulltime project administrative staff.

-

Balanced matrix organization recognizes the need for a project manager; it does
not provide the project manager with the full authority over the project and
project funding.

-

Employees in a matrix organization report to one functional manager and at
least one project manager.

-

It’s possible that employees could report to multiple project managers if they are
working on multiple projects at one time.

-

Functional managers pick up the administrative portion of the duties and assign
employees to projects. They also monitor the work of their employees on the
various projects.

-

Project managers are responsible for executing the project and giving out work
assignments based on project activities.

-

Project managers and functional managers share the responsibility of
performance reviews for the employee.

Strong Matrix Organization
-

The project managers have a great power.

-

They have the ability to strong-arm the functional managers into giving up their
best resources for projects.

-

When competing for resources, project managers may negotiate resources
among each other.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
-

Functional Manager handles only the administrative aspect of his employees’
life.

Weak Matrix Organization
-

The functional managers have all the power in this structure.

-

Project managers are really project coordinators or expeditors with part-time
responsibilities on projects in a weak matrix organization.

-

Project managers have little to no authority, just like in the functional
organization.

-

On the other hand, the functional managers have a lot of authority and make all
the work assignments. The project manager simply expedites the project.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Organizational Structure

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Project Management vs. Organization

Project Expediter, Coordinator, Manager
-

Depending on the type of Organization, the project manager’s role and power
can be very limited

-

Project Expediter



-

Acts primarily as a staff assistant
As communications coordinator.

 Cannot personally make or enforce decisions.
Project Coordinator
 has some power to make decisions


Has some authority



reports to a higher-level manager

Organizational Process Assets
-

Processes & Procedures;


Organizational standard processes such as standards, policies

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD


Standardized guidelines, work instruction, proposal evaluation criteria,
and performance measurement criteria




Financial control procedures



Procedures for prioritizing, approving, and issuing work authorization



-

Templates

Etc.

Corporate Knowledge Base;


Process measurement databases



Project files



Historical information & lesson learned knowledge bases



Issue and defect management databases



Configuration management knowledge bases



Financial databases



Etc.

Keynotes;

-

Be able to describe the difference between projects and operations. A project
is temporary in nature with a definite beginning and ending date. Operations are
ongoing.

-

Be able to denote some of the skills every good project manager should
possess. Communication, budgeting, organizational, problem solving,
negotiation and influencing, leading, and team building.

-

Be able to differentiate the different organizational structures. Organizations
are usually structured in some combination of the following: functional,
projectized, and matrix (including weak matrix, balanced matrix, and strong
matrix).

-

Be able to name the five project management processes. Initiation, Planning,
Executing, Controlling, and Closing.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Note:

1. A process is a set of interrelated actions and activities performed to achieve a
pre-specified product, result, or service. Each process is characterized by its
inputs, the tools and techniques that can be applied, and the resulting outputs.
2. To successfully deliver project, team needs to consider "Project related
Processes" and "Product Related Process". Always remember - Product is the
output that project produces and Project is work that needs to be done to
produce the Product. PMBOK Guide 4th Edition considers Project related
processes only.

Triple Constraints:
- Time, Cost, Scope are initially known as Triple constraints. This means that, if one
of these constraints has been changed the other two constraints will be directly
impacted. Project Management methodology is evolving Quality and Risk were also
added to those constraints.

PMBOK 4th Edition: Process ChartInitiation

Planning

Integration
1.1 Develop1.2 Develop Project
Project Charter Management Plan

Executing
1.3 Direct &
Manage Project
Execution

Monitoring and
Controlling

Closing

1.4 Monitor & Control
1.6 Close
Project Work
Project or
4.5
Phase
Perform Integrated
Change Control

Scope

2.1 Collect Requirements
2.2 Define Scope
2.3 Create Work Breakdown
Structure (WBS)

2.4 Verify Scope
2.5 Control Scope

Time

3.1 Define Activities
3.2 Sequence Activities
3.3 Estimate Activity
Resources
3.4 Estimate Activity
Durations
3.5 Develop Schedule

3.6 Control Schedule

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Cost

4.1 Estimate Costs
4.2 Determine Budget

Quality

5.1 Plan Quality

5.2 Perform Quality 5.3 Perform Quality
Assurance
Control

6.1 Develop Human
Resources Plan

6.2 Acquire Project
Team
6.3 Develop Project
Team
6.4 Manage Project
Team

7.2 Plan Communications

7.3 Distribute
Information
7.4 Manage
Stakeholder
Expectations

HR

Communications

7.1 Identify
Stakeholders

Risk

8.1 Plan Risk Management
8.2 Identify Risks
8.3 Perform Qualitative Risk
Analysis
8.4 Perform Quantitative
Risk
Analysis
8.5 Plan Risk Responses

Procurement

9.1 Plan Procurements

4.3 Control Costs

7.5 Report
Performance

8.6 Monitor and
Control Risks

9.2 Conduct
Procurements

9.3 Administer
Procurements

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD

9.4 Close
Procurements

More Related Content

What's hot

Chapter 2
Chapter 2Chapter 2
Chapter 2
uncleRhyme
 
Project management ppt
Project management pptProject management ppt
Project management ppt
Amolnarayane1
 
Introduction to Project Portfolio Management
Introduction to Project Portfolio ManagementIntroduction to Project Portfolio Management
Introduction to Project Portfolio Management
Luis Javier Serrano
 
Project management frame work part 2
Project management frame work part 2Project management frame work part 2
Project management frame work part 2
Mohamed , PMP
 
Macrosolutions Training: PMO – Project Management Office
Macrosolutions Training: PMO – Project Management OfficeMacrosolutions Training: PMO – Project Management Office
Macrosolutions Training: PMO – Project Management Office
Macrosolutions SA
 
Project management frame work part 3
Project management frame work part 3Project management frame work part 3
Project management frame work part 3
Mohamed , PMP
 
People in portfolio management
People in portfolio management People in portfolio management
People in portfolio management
Luis Javier Serrano
 
Soutenance These Gianluca Costanzi
Soutenance These Gianluca CostanziSoutenance These Gianluca Costanzi
Soutenance These Gianluca CostanziGianluca Costanzi
 
2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...
2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...
2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...
Dcolearning
 
PMO Charter Template
PMO Charter TemplatePMO Charter Template
PMO Charter Template
Demand Metric
 
Pan europa foods - Project Management
Pan europa foods - Project ManagementPan europa foods - Project Management
Pan europa foods - Project ManagementRobbi Palacios
 
Thesis MSIT 2011-12 PMO Gianluca Costanzi v2.3
Thesis MSIT 2011-12 PMO Gianluca Costanzi v2.3Thesis MSIT 2011-12 PMO Gianluca Costanzi v2.3
Thesis MSIT 2011-12 PMO Gianluca Costanzi v2.3Gianluca Costanzi
 
3 Critical Steps to Project Management Office (PMO) Development
3 Critical Steps to Project Management Office (PMO) Development3 Critical Steps to Project Management Office (PMO) Development
3 Critical Steps to Project Management Office (PMO) Development
GravesSE
 
Lecture 06: Advanced Project Management Project Organization and Integration
Lecture 06: Advanced Project Management  Project Organization and IntegrationLecture 06: Advanced Project Management  Project Organization and Integration
Lecture 06: Advanced Project Management Project Organization and Integration
Fida Karim 🇵🇰
 
CCP_SEC5_ Project Management
CCP_SEC5_ Project ManagementCCP_SEC5_ Project Management
CCP_SEC5_ Project Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
PMO FW Oct 27 2015
PMO FW Oct 27  2015PMO FW Oct 27  2015
PMO FW Oct 27 2015rhenderson08
 
E book project-management
E book project-managementE book project-management
E book project-management
GuruK32
 
The role of the project manager based on pmbok6 by mm rahman stm skill that m...
The role of the project manager based on pmbok6 by mm rahman stm skill that m...The role of the project manager based on pmbok6 by mm rahman stm skill that m...
The role of the project manager based on pmbok6 by mm rahman stm skill that m...
STM-Skill That Matters
 
Implementation of the pmo proposal
Implementation of the pmo proposalImplementation of the pmo proposal
Implementation of the pmo proposalHugh Shults
 

What's hot (20)

Chapter 2
Chapter 2Chapter 2
Chapter 2
 
Project management ppt
Project management pptProject management ppt
Project management ppt
 
Introduction to Project Portfolio Management
Introduction to Project Portfolio ManagementIntroduction to Project Portfolio Management
Introduction to Project Portfolio Management
 
Project management frame work part 2
Project management frame work part 2Project management frame work part 2
Project management frame work part 2
 
Macrosolutions Training: PMO – Project Management Office
Macrosolutions Training: PMO – Project Management OfficeMacrosolutions Training: PMO – Project Management Office
Macrosolutions Training: PMO – Project Management Office
 
Project management frame work part 3
Project management frame work part 3Project management frame work part 3
Project management frame work part 3
 
People in portfolio management
People in portfolio management People in portfolio management
People in portfolio management
 
Soutenance These Gianluca Costanzi
Soutenance These Gianluca CostanziSoutenance These Gianluca Costanzi
Soutenance These Gianluca Costanzi
 
2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...
2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...
2019 | E-Brochure | Impactful PMO - IPMO ( 2 Days) | Project Management Train...
 
PMO Charter Template
PMO Charter TemplatePMO Charter Template
PMO Charter Template
 
Oim Pmo It Governance Structure Cox
Oim Pmo It Governance Structure CoxOim Pmo It Governance Structure Cox
Oim Pmo It Governance Structure Cox
 
Pan europa foods - Project Management
Pan europa foods - Project ManagementPan europa foods - Project Management
Pan europa foods - Project Management
 
Thesis MSIT 2011-12 PMO Gianluca Costanzi v2.3
Thesis MSIT 2011-12 PMO Gianluca Costanzi v2.3Thesis MSIT 2011-12 PMO Gianluca Costanzi v2.3
Thesis MSIT 2011-12 PMO Gianluca Costanzi v2.3
 
3 Critical Steps to Project Management Office (PMO) Development
3 Critical Steps to Project Management Office (PMO) Development3 Critical Steps to Project Management Office (PMO) Development
3 Critical Steps to Project Management Office (PMO) Development
 
Lecture 06: Advanced Project Management Project Organization and Integration
Lecture 06: Advanced Project Management  Project Organization and IntegrationLecture 06: Advanced Project Management  Project Organization and Integration
Lecture 06: Advanced Project Management Project Organization and Integration
 
CCP_SEC5_ Project Management
CCP_SEC5_ Project ManagementCCP_SEC5_ Project Management
CCP_SEC5_ Project Management
 
PMO FW Oct 27 2015
PMO FW Oct 27  2015PMO FW Oct 27  2015
PMO FW Oct 27 2015
 
E book project-management
E book project-managementE book project-management
E book project-management
 
The role of the project manager based on pmbok6 by mm rahman stm skill that m...
The role of the project manager based on pmbok6 by mm rahman stm skill that m...The role of the project manager based on pmbok6 by mm rahman stm skill that m...
The role of the project manager based on pmbok6 by mm rahman stm skill that m...
 
Implementation of the pmo proposal
Implementation of the pmo proposalImplementation of the pmo proposal
Implementation of the pmo proposal
 

Viewers also liked

テキストファイルの話
テキストファイルの話テキストファイルの話
テキストファイルの話Tetsuya Yamamoto
 
Perlを勉強してみて思ったこと
Perlを勉強してみて思ったことPerlを勉強してみて思ったこと
Perlを勉強してみて思ったこと
Yuzo Iwasaki
 
Linux女子部のご紹介
Linux女子部のご紹介Linux女子部のご紹介
Linux女子部のご紹介
Manami Taira
 
101 2.5 use rpm and yum package management
101 2.5 use rpm and yum package management101 2.5 use rpm and yum package management
101 2.5 use rpm and yum package managementAcácio Oliveira
 
LPI Academy Presents Linux Essentials - A Deep Dive
LPI Academy Presents Linux Essentials - A Deep DiveLPI Academy Presents Linux Essentials - A Deep Dive
LPI Academy Presents Linux Essentials - A Deep Dive
lpiconnect
 
systemdで焦らないための Fedoraのススメ
systemdで焦らないためのFedoraのススメsystemdで焦らないためのFedoraのススメ
systemdで焦らないための Fedoraのススメ
Manami Taira
 
家庭内IoTのすすめ「IoTスーパーこまち」がバージョンアップしたよ! #soracom
家庭内IoTのすすめ「IoTスーパーこまち」がバージョンアップしたよ! #soracom家庭内IoTのすすめ「IoTスーパーこまち」がバージョンアップしたよ! #soracom
家庭内IoTのすすめ「IoTスーパーこまち」がバージョンアップしたよ! #soracom
Manami Taira
 
システム運用の視点から考える「自動化&効率化」
システム運用の視点から考える「自動化&効率化」システム運用の視点から考える「自動化&効率化」
システム運用の視点から考える「自動化&効率化」
Hinemos
 

Viewers also liked (8)

テキストファイルの話
テキストファイルの話テキストファイルの話
テキストファイルの話
 
Perlを勉強してみて思ったこと
Perlを勉強してみて思ったことPerlを勉強してみて思ったこと
Perlを勉強してみて思ったこと
 
Linux女子部のご紹介
Linux女子部のご紹介Linux女子部のご紹介
Linux女子部のご紹介
 
101 2.5 use rpm and yum package management
101 2.5 use rpm and yum package management101 2.5 use rpm and yum package management
101 2.5 use rpm and yum package management
 
LPI Academy Presents Linux Essentials - A Deep Dive
LPI Academy Presents Linux Essentials - A Deep DiveLPI Academy Presents Linux Essentials - A Deep Dive
LPI Academy Presents Linux Essentials - A Deep Dive
 
systemdで焦らないための Fedoraのススメ
systemdで焦らないためのFedoraのススメsystemdで焦らないためのFedoraのススメ
systemdで焦らないための Fedoraのススメ
 
家庭内IoTのすすめ「IoTスーパーこまち」がバージョンアップしたよ! #soracom
家庭内IoTのすすめ「IoTスーパーこまち」がバージョンアップしたよ! #soracom家庭内IoTのすすめ「IoTスーパーこまち」がバージョンアップしたよ! #soracom
家庭内IoTのすすめ「IoTスーパーこまち」がバージョンアップしたよ! #soracom
 
システム運用の視点から考える「自動化&効率化」
システム運用の視点から考える「自動化&効率化」システム運用の視点から考える「自動化&効率化」
システム運用の視点から考える「自動化&効率化」
 

Similar to 0. project management framework (fundamentals)

5 Forces Model - SWOT, PESTEL presentation.pptx
5 Forces Model - SWOT, PESTEL presentation.pptx5 Forces Model - SWOT, PESTEL presentation.pptx
5 Forces Model - SWOT, PESTEL presentation.pptx
jalal879
 
PMBOK_5th_Project Management Framework
PMBOK_5th_Project Management FrameworkPMBOK_5th_Project Management Framework
PMBOK_5th_Project Management Framework
Hossam Maghrabi
 
Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2
Amr Miqdadi
 
Project Planning and Management Notes
Project Planning and Management NotesProject Planning and Management Notes
Project Planning and Management Notes
Haris Hassan
 
Module One Project Management and the Role of the ProjectMa.docx
Module One Project Management and the Role of the ProjectMa.docxModule One Project Management and the Role of the ProjectMa.docx
Module One Project Management and the Role of the ProjectMa.docx
gilpinleeanna
 
Introduction to pmp
Introduction to pmpIntroduction to pmp
Introduction to pmpshkadry
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkejlp12
 
INTRO.pptx
INTRO.pptxINTRO.pptx
INTRO.pptx
Sankalp Sharma
 
Challenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementChallenging Aspects of Modern Project Management
Challenging Aspects of Modern Project Management
Yamanta Raj Niroula, PMP
 
ACE-FUELS- 801- PROJECT MGT for real estate
ACE-FUELS- 801- PROJECT MGT for real estateACE-FUELS- 801- PROJECT MGT for real estate
ACE-FUELS- 801- PROJECT MGT for real estate
hando2845
 
Project management
Project managementProject management
Project management
balasundaramk4
 
Introduction to PM
Introduction to PMIntroduction to PM
Introduction to PM
Jeffrey Cheah
 
PROJECT MANAGEMENT 2 (1) STADIO COURSES.pdf
PROJECT MANAGEMENT 2  (1) STADIO COURSES.pdfPROJECT MANAGEMENT 2  (1) STADIO COURSES.pdf
PROJECT MANAGEMENT 2 (1) STADIO COURSES.pdf
Alison Tutors
 
Project management for technologies MGT410
Project management for technologies   MGT410Project management for technologies   MGT410
Project management for technologies MGT410
Saqib Imran
 
Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysis
Wakas Khalid
 
Project management
Project managementProject management
Project management
satya pal
 
(Fall2016)Lecture2.pptx
(Fall2016)Lecture2.pptx(Fall2016)Lecture2.pptx
(Fall2016)Lecture2.pptx
garkapifye
 
Day 0 Introduction to PM
Day 0   Introduction to PMDay 0   Introduction to PM
Day 0 Introduction to PM
Joyce Wong
 
Day 0 Introduction to PM
Day 0   Introduction to PMDay 0   Introduction to PM
Day 0 Introduction to PM
Joyce Wong
 
Presentation of project management (907, scm. mir mohammed shorab hossein)
Presentation of project management (907, scm. mir mohammed shorab hossein)Presentation of project management (907, scm. mir mohammed shorab hossein)
Presentation of project management (907, scm. mir mohammed shorab hossein)
ferozpatowary
 

Similar to 0. project management framework (fundamentals) (20)

5 Forces Model - SWOT, PESTEL presentation.pptx
5 Forces Model - SWOT, PESTEL presentation.pptx5 Forces Model - SWOT, PESTEL presentation.pptx
5 Forces Model - SWOT, PESTEL presentation.pptx
 
PMBOK_5th_Project Management Framework
PMBOK_5th_Project Management FrameworkPMBOK_5th_Project Management Framework
PMBOK_5th_Project Management Framework
 
Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2
 
Project Planning and Management Notes
Project Planning and Management NotesProject Planning and Management Notes
Project Planning and Management Notes
 
Module One Project Management and the Role of the ProjectMa.docx
Module One Project Management and the Role of the ProjectMa.docxModule One Project Management and the Role of the ProjectMa.docx
Module One Project Management and the Role of the ProjectMa.docx
 
Introduction to pmp
Introduction to pmpIntroduction to pmp
Introduction to pmp
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
INTRO.pptx
INTRO.pptxINTRO.pptx
INTRO.pptx
 
Challenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementChallenging Aspects of Modern Project Management
Challenging Aspects of Modern Project Management
 
ACE-FUELS- 801- PROJECT MGT for real estate
ACE-FUELS- 801- PROJECT MGT for real estateACE-FUELS- 801- PROJECT MGT for real estate
ACE-FUELS- 801- PROJECT MGT for real estate
 
Project management
Project managementProject management
Project management
 
Introduction to PM
Introduction to PMIntroduction to PM
Introduction to PM
 
PROJECT MANAGEMENT 2 (1) STADIO COURSES.pdf
PROJECT MANAGEMENT 2  (1) STADIO COURSES.pdfPROJECT MANAGEMENT 2  (1) STADIO COURSES.pdf
PROJECT MANAGEMENT 2 (1) STADIO COURSES.pdf
 
Project management for technologies MGT410
Project management for technologies   MGT410Project management for technologies   MGT410
Project management for technologies MGT410
 
Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysis
 
Project management
Project managementProject management
Project management
 
(Fall2016)Lecture2.pptx
(Fall2016)Lecture2.pptx(Fall2016)Lecture2.pptx
(Fall2016)Lecture2.pptx
 
Day 0 Introduction to PM
Day 0   Introduction to PMDay 0   Introduction to PM
Day 0 Introduction to PM
 
Day 0 Introduction to PM
Day 0   Introduction to PMDay 0   Introduction to PM
Day 0 Introduction to PM
 
Presentation of project management (907, scm. mir mohammed shorab hossein)
Presentation of project management (907, scm. mir mohammed shorab hossein)Presentation of project management (907, scm. mir mohammed shorab hossein)
Presentation of project management (907, scm. mir mohammed shorab hossein)
 

More from Mohamed Salah Eldien Mohamed Ali

9. project procurement management
9. project procurement management9. project procurement management
9. project procurement management
Mohamed Salah Eldien Mohamed Ali
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
Mohamed Salah Eldien Mohamed Ali
 
7. project communications management
7. project communications management7. project communications management
7. project communications management
Mohamed Salah Eldien Mohamed Ali
 
6. project human resource management
6. project human resource management6. project human resource management
6. project human resource management
Mohamed Salah Eldien Mohamed Ali
 
5. project quality management
5. project quality management5. project quality management
5. project quality management
Mohamed Salah Eldien Mohamed Ali
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
Mohamed Salah Eldien Mohamed Ali
 
2. project scope management
2. project scope management2. project scope management
2. project scope management
Mohamed Salah Eldien Mohamed Ali
 
3. project time management
3. project time management3. project time management
3. project time management
Mohamed Salah Eldien Mohamed Ali
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
Mohamed Salah Eldien Mohamed Ali
 

More from Mohamed Salah Eldien Mohamed Ali (12)

Series_Certificate
Series_CertificateSeries_Certificate
Series_Certificate
 
Business Management Cert.
Business Management Cert.Business Management Cert.
Business Management Cert.
 
Business Management Cert.
Business Management Cert.Business Management Cert.
Business Management Cert.
 
9. project procurement management
9. project procurement management9. project procurement management
9. project procurement management
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
7. project communications management
7. project communications management7. project communications management
7. project communications management
 
6. project human resource management
6. project human resource management6. project human resource management
6. project human resource management
 
5. project quality management
5. project quality management5. project quality management
5. project quality management
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
2. project scope management
2. project scope management2. project scope management
2. project scope management
 
3. project time management
3. project time management3. project time management
3. project time management
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 

Recently uploaded

Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
AUDIJEAngelo
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
Safe PaaS
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
my Pandit
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
HajeJanKamps
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
PaulBryant58
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Jos Voskuil
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 

Recently uploaded (20)

Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 

0. project management framework (fundamentals)

  • 1. Project Management Framework (Fundamentals) You are guaranteed to get at least 5 questions from this section. Following are important topics you need to cover in this section Definitions of Project and Project Management Project “A project is a temporary endeavor undertaken to create a unique product, service, or result. The temporary nature of projects indicates a definite beginning and end.”, PMBOK Guide, 4th edition, 2008. - Temporary does not necessarily mean short in duration. - Temporary does not generally apply to the product, service, or result created by the project. - Progressive Elaboration is one of the main characteristics of the project. Project Specifications; - - A project is different from day-to-day business and it has a specific Start date and End date. The ongoing work effort is generally a repetitive process because it follows an organization’s existing procedures and that’s why Project is different from operations and maintenance...etc. A project creates a unique product, service, or result, although repetitive elements may be present in it. Because of the unique nature of projects, there may be uncertainties about the products, services, or results that the project creates. The end is reached when:  The stakeholders expectations are met or exceeded, or  - The project is terminated because its objectives will not or cannot be met, or the project is terminated because the need for it no longer exists. To determine if some activity is a project or not, ask the questions:  Is it unique?  Does the project have a limited time frame?  Is there a way to determine when the project is completed?  Is there a way to determine stakeholder satisfaction? By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 2. Project Stakeholders - - Stakeholders are those people or organizations with a vested interest in the project. They have something to either gain or lose as a result of the project. Stakeholders often have very different or conflicting objectives. Key stakeholders should be identified and contacted early on to get their input for the project overview, goals, and deliverables Forgetting an important stakeholder could be a project killer. The project sponsor, generally an executive in the organization with the authority to assign resources and enforce decisions regarding the project. He is a stakeholder. The customer is a stakeholder as are contractors and suppliers. The project manager and the managers from other departments in the organization are stakeholders as well. Cost, Risk and uncertainty vs. Time By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 3. Project Management “The application of knowledge, skills, tools, and techniques to describe, organizes, execute, and monitor the work of project activities in order to meet or exceed stakeholder requirements from a project.” Managing a project typically includes: - - Identifying requirements, Addressing the various needs, concerns, and expectations of the stakeholders as the project is planned and carried out, then, managing various constraints to accomplish objectives. Balancing the competing project constraints including, but not limited to:  Scope,   Resources, and  - Budget,  - Schedule,  - Quality, Risk. To manage Projects effectively those constraints should be divided into Phases and smallest possible sub phases. This iterative process should go up to the level where further division creates confusion rather than helping the project. In database terminology we call this as "Atomic level”. PMI defined 42 project management processes / Atomic processes to handle all aspects of a project life. PMBOK guide defines Knowledge Areas for the Project Managers. Managers will use these skills (Knowledge) to work on given INPUTS using TOOLS to produce OUTPUTS. Those are; 1. Project Integration Management 2. Project Scope Management 3. Project Time Management 4. Project Cost Management 5. Project Quality Management 6. Project Human Resource Management 7. Project Communications Management By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 4. 8. Project Risk Management. 9. Project Procurement Management PM processes apply to the 5 phases of a project life: 1. Initiating, 2. Planning, 3. Executing, 4. Monitoring and Controlling, and 5. Closing. Project, Program and Portfolio - A program is defined as a group of related projects managed in a coordinated - way to obtain benefits and control which not available from managing them individually. A project may or may not be part of a program but a program will always have projects. A portfolio refers to a collection of projects or programs and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives. The projects or programs of the portfolio may not necessarily be interdependent or directly related Project Management Office (PMO) - - A project management office (PMO) is an organizational body or entity assigned various responsibilities related to the centralized and coordinated management of those projects under its domain. The responsibilities of a PMO can range from providing project management support functions to actually being responsible for the direct management of a project. A primary function of a PMO is to support project managers in a variety of ways which may include, but are not limited to:  Identifying and developing project management methodology, best practices, and standards;  Developing and managing project policies, procedures, templates, and other shared documentation (organizational process assets);  Coaching, monitoring, training, and oversight;  Monitoring compliance with project management standards, policies, procedures, and templates via project audits;  Managing shared resources across all projects administered by the PMO; and By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 5.  Coordinating communication across projects. Project Manager’s Role - Project managers are assigned by the performing organization to achieve the project objectives. - Project manager is in charge of all aspects of the project including, but not limited to:  Developing the project management plan and all related component plans,   - Keeping the project on track in terms of schedule and budget, Identifying, monitoring, and responding to risk, and  Providing accurate and timely reporting of project metrics. The project manager is the lead person responsible for communicating with all stakeholders, particularly the project sponsor, project team, and other key stakeholders. Good Project Manager’s Skills - Communication skills - Organizational and Planning Skills - Budgeting Skills - Problem Solving and Decision making - Negotiating and Influencing - Leadership Skills - Team Building and Human Resources By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 6. Project Triple-Constraint Project Organizational Structure - Organizational Structures; project organizations need to have a structure to deliver undertaken project. - There are 3 major types of organizations:  Functional Organizations  Projectized Organizations  Matrix Organizations  Weak Matrix organizations  - Strong Matrix organizations  Balanced Matrix organizations Variations and combinations may exist. The level of authority the project manager enjoys is denoted by the organizational structure. 1. Functional Organization; - Organizations is centered on specialties and grouped by function. - Each department will do its project work independent of others. - Each employee reports to only one manager. - It is important to know and respect the chain of command. - Project managers have little to no formal authority. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 7. - Good communication, interpersonal, and influencing skills on the part of the project manager are required to bring about a successful project under this structure. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 8. 2. Projectized Organization - Projectized organizations are nearly the opposite of functional organizations. It aims to develop loyalty to the project, not to a functional manager. - The focus of this type of organization is the project itself. - Most of the organization’s resources are involved in project work, - Team members are often co-located, - Project managers have a great deal of independence and authority. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 9. 3. Matrix Organization - Matrix organizations are a blend of functional and projectized characteristics. - Weak matrix maintains many of the characteristics of a functional organization, and the project manager role is more of a coordinator or expediter than that of a true project manager. - Strong matrix has many of the characteristics of the projectized organization, and can have full-time project managers with considerable authority and fulltime project administrative staff. - Balanced matrix organization recognizes the need for a project manager; it does not provide the project manager with the full authority over the project and project funding. - Employees in a matrix organization report to one functional manager and at least one project manager. - It’s possible that employees could report to multiple project managers if they are working on multiple projects at one time. - Functional managers pick up the administrative portion of the duties and assign employees to projects. They also monitor the work of their employees on the various projects. - Project managers are responsible for executing the project and giving out work assignments based on project activities. - Project managers and functional managers share the responsibility of performance reviews for the employee. Strong Matrix Organization - The project managers have a great power. - They have the ability to strong-arm the functional managers into giving up their best resources for projects. - When competing for resources, project managers may negotiate resources among each other. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 10. - Functional Manager handles only the administrative aspect of his employees’ life. Weak Matrix Organization - The functional managers have all the power in this structure. - Project managers are really project coordinators or expeditors with part-time responsibilities on projects in a weak matrix organization. - Project managers have little to no authority, just like in the functional organization. - On the other hand, the functional managers have a lot of authority and make all the work assignments. The project manager simply expedites the project. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 11. Organizational Structure By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 12. Project Management vs. Organization Project Expediter, Coordinator, Manager - Depending on the type of Organization, the project manager’s role and power can be very limited - Project Expediter   - Acts primarily as a staff assistant As communications coordinator.  Cannot personally make or enforce decisions. Project Coordinator  has some power to make decisions  Has some authority  reports to a higher-level manager Organizational Process Assets - Processes & Procedures;  Organizational standard processes such as standards, policies By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 13.  Standardized guidelines, work instruction, proposal evaluation criteria, and performance measurement criteria   Financial control procedures  Procedures for prioritizing, approving, and issuing work authorization  - Templates Etc. Corporate Knowledge Base;  Process measurement databases  Project files  Historical information & lesson learned knowledge bases  Issue and defect management databases  Configuration management knowledge bases  Financial databases  Etc. Keynotes; - Be able to describe the difference between projects and operations. A project is temporary in nature with a definite beginning and ending date. Operations are ongoing. - Be able to denote some of the skills every good project manager should possess. Communication, budgeting, organizational, problem solving, negotiation and influencing, leading, and team building. - Be able to differentiate the different organizational structures. Organizations are usually structured in some combination of the following: functional, projectized, and matrix (including weak matrix, balanced matrix, and strong matrix). - Be able to name the five project management processes. Initiation, Planning, Executing, Controlling, and Closing. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 14. Note: 1. A process is a set of interrelated actions and activities performed to achieve a pre-specified product, result, or service. Each process is characterized by its inputs, the tools and techniques that can be applied, and the resulting outputs. 2. To successfully deliver project, team needs to consider "Project related Processes" and "Product Related Process". Always remember - Product is the output that project produces and Project is work that needs to be done to produce the Product. PMBOK Guide 4th Edition considers Project related processes only. Triple Constraints: - Time, Cost, Scope are initially known as Triple constraints. This means that, if one of these constraints has been changed the other two constraints will be directly impacted. Project Management methodology is evolving Quality and Risk were also added to those constraints. PMBOK 4th Edition: Process ChartInitiation Planning Integration 1.1 Develop1.2 Develop Project Project Charter Management Plan Executing 1.3 Direct & Manage Project Execution Monitoring and Controlling Closing 1.4 Monitor & Control 1.6 Close Project Work Project or 4.5 Phase Perform Integrated Change Control Scope 2.1 Collect Requirements 2.2 Define Scope 2.3 Create Work Breakdown Structure (WBS) 2.4 Verify Scope 2.5 Control Scope Time 3.1 Define Activities 3.2 Sequence Activities 3.3 Estimate Activity Resources 3.4 Estimate Activity Durations 3.5 Develop Schedule 3.6 Control Schedule By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 15. Cost 4.1 Estimate Costs 4.2 Determine Budget Quality 5.1 Plan Quality 5.2 Perform Quality 5.3 Perform Quality Assurance Control 6.1 Develop Human Resources Plan 6.2 Acquire Project Team 6.3 Develop Project Team 6.4 Manage Project Team 7.2 Plan Communications 7.3 Distribute Information 7.4 Manage Stakeholder Expectations HR Communications 7.1 Identify Stakeholders Risk 8.1 Plan Risk Management 8.2 Identify Risks 8.3 Perform Qualitative Risk Analysis 8.4 Perform Quantitative Risk Analysis 8.5 Plan Risk Responses Procurement 9.1 Plan Procurements 4.3 Control Costs 7.5 Report Performance 8.6 Monitor and Control Risks 9.2 Conduct Procurements 9.3 Administer Procurements By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD 9.4 Close Procurements