Implementation of the PMO Proposal

               Hugh Shults

          St. Edwards University

MGMT 6320 Project and Change Management

               June 7, 2011
Hugh Shults
3600 West Parmer Lane
Austin, TX 78727
June 6, 2011


Michael Leahy
System Delivery
Federal Signal Technologies
2 Technology Circle
Irvine, CA 92630


Dear Mr. Leahy:

As you probably know by now, I have been actively pursuing the implementation of the Project
Management Office at Federal Signal Technologies (FS Tech). I have done extensive outreach to many
other FS Tech stakeholders and have found that the general consensus is that a PMO shall provide for
the answers to some unresolved kinks in the evolvement of the new company. Now that the organization
is larger and more distributed, it is an ideal time to seriously consider the implementation of a PMO.

I am confident that I can complete this project within the designated time period and close to (or under)
budget. I also believe that my recommended approach will have credibility with the Stakeholders. I am
prepared to deliver a presentation of this project to the Stakeholders and answer any questions you and
they may have about it; I anticipate that there will be many.

If you have questions before the presentation, please give me a call. I can be reached on my cell phone
anytime.




Sincerely,




Hugh Shults
Project Management Professional

Enclosure:

Implementation of the PMO plan




Implementation of the PMO                                                                      Page 2 of 13
PROJECT SUMMARY

                                       Implementation of the PMO

This proposal is for preparing the organization for the adoption of a Project Management Office (PMO)
and the strategy for implementing the PMO.

The PMO is established to improve Federal Signal Technologies’ (FS Techs’) project management
capability and the organization’s competitive advantage. To enable the PMO to provide independent
services, the PMO shall operate as a separate business unit. This plan outlines the PMO’s goals and
objectives, responsibility, organization, strategy, preliminary budget, preliminary schedule, authority, key
stakeholders, project team, and critical success factors.

Project Management Institute (PMI) defines the PMO as an organizational body or entity assigned various
responsibilities related to centralized and coordinated management of those projects under its domain.
The centralized management of programs such that corporate benefit is realized by sharing of resources,
methodologies, tools, and techniques, and related high-level project management focus. This entity is
also known by names such as Center of Excellence, Project Support Office, Program Management
Office, and Strategic Project Office.

The benefits of the PMO is it’s capacity to provide leadership in support of FS Tech business teams on
internal and external projects, and to position FS Tech to be the benchmark in the industry. The PMO
has become an important unit in today’s businesses, and by adopting and successfully implementing it,
FS Tech shall have a superior reputation for client management and project delivery. The PMO is to the
organization as the Project Manager is to the project. The PMO shall be a consolidation of all Project
Management staff into one cohesive unit using a standard tool set and standard methodologies. Project
Managers’ skills shall be fully developed to efficiently manage projects in any product line or market. .




Implementation of the PMO                                                                         Page 3 of 13
PROJECT DESCRIPTION

                                       Implementation of the PMO

Introduction
The implementation of the PMO shall occur in phases to ensure that proper organizational restructure
takes place and business activity proceeds with minimal impact. The intent is to introduce the new
structure, methodologies, and standards using best practices and adjust to the business as much as
possible while addressing the stakeholders concerns regarding project management practices, standards
and performance

Background Situation
Upon the companies’ consolidation to form FS Tech, each company runs its project management
activities and businesses to the best of its knowledge, experience, and resource constraints. This causes
many issues for the consolidated company. Some of those issues are:
    •   The inability to get a good portfolio of company goal alignment and performance.
    •   Up to seven different project/business reporting mechanisms.
    •   Up to seven different methodologies for delivery projects and measuring performance.
    •   Difficult resource allocation and reporting.
    •   Up to seven different ways of handling stakeholder concerns.
    •   Unfit collaboration tools and expectations.

PMO goals and objectives
The goal is to establish a PMO that provides portfolio, program, and project leadership.
The objectives to accomplish this goal are as follows:
    •   Align business and project activities.
    •   Develop and implement good project management standards and practices in FS Tech.
    •   Develop project resource skills.
    •   Develop project resource management processes.
    •   Facilitate multi-project coordination in FS Tech.
    •   Develop/Implement a project management information system (PMIS).
    •   Integrate a shared project management system in FS Tech.
    •   Improve PMO and project stakeholder communication.
    •   Develop a set of metrics to measure performance to the organization.
    •   Establish continuous improvement procedures for the PMO and project delivery.

PMO Responsibilities
The PMO provides the following services:
    •   Governance of project, program, and portfolio management of the subsidiaries, so that they
        operate as the FS Tech organization, as opposed to individual companies.
    •   Monitoring and controlling of multiple projects
    •   Maintain a consolidated resource pool across the business unit to more efficiently manage
        resource allocation and availability
    •   Develop and implement a code of ethics for the PMO and its membership
    •   Standardize FS Tech’s project management methodology, processes and procedures, and tools



Implementation of the PMO                                                                      Page 4 of 13
•      Manage the flow and repository of information and knowledge, to ensure that relevant staff has
           the correct level of access.
    •      Assist with vendor and customer management.
    •      Monitor, control, support, and continuously improve the project management capability.
    •      Facilitate effective communication in projects.

Organization
By operating independently, it is expected that the PMO is able to provide an unbiased service to other
departments within the organization. The PMO will operate in a strong matrix organizational structure.
Project managers and functional managers will cooperate, although primary control of everything related
to the project is the Project Manager’s domain, and control of everything else is the Functional Manager’s
realm. In this organization, all Project Managers report to the PMO. Figure 1 is the proposed matrix
organization for FS Tech.




Figure 1



PMO Strategies
  To ensure that the PMO understands its mission and vision, the support from key stakeholders and end
  users is very important. The following is an outline of the PMO’s strategies to achieve those supports:
    •      Circulate the draft PMO Charter to obtain inputs from key stakeholders, and ensure that all
           relevant parties are consulted.
    •      Refine the PMO Charter based on those inputs.
    •      Have the approval of the relevant executive on the final PMO Charter.
    •      Execute the implementation of the PMO in phases.

Implementing the PMO
Schedule             Description



Implementation of the PMO                                                                        Page 5 of 13
Months 1 to 3               1. Implementation of PM standards for Irvine and Austin offices.
                            2. An assessment is conducted and a plan developed with the project and
                               functional Managers to meet Project Management Institute’s (PMI’s)
                               minimum project standards where applicable.
                                   a. The PMO performs Strengths, Weaknesses, Opportunities, and
                                         Threats (SWOT) analysis to set the baseline for the plans.
                                   b. The PMO determines Specific, Measurable, Achievable,
                                         Realistic, and Timely (SMART) objectives to complete the
                                         plans.
                            3. Determine existing project, program and portfolio domain maturity
                               across the business unit.
                            4. Communicate the expectations in regards to the project management
                               standards.
                            5. Establish technical tools to standardize the project management
                               activities, performance, and deliverables.
Months 3 to 6               6. Implementation of PM standards for other five FS Tech locations.
                            7. Develop and implement a plan to manage the domains
                            8. Monitor and control PMIS activity for standard conformity; adjust as
                               necessary.
Months 6 to 9               9. Monitoring and controlling for all domains in respect to project
                                management is conducted to measure the success of the ‘restructure’.
                            10. Design and conduct internal and external stakeholders’ surveys.
                            11. Plan with Customer Service, Sales, and Finance about project
                                integration that shall benefit the organization.
Months 9 to 12              12. Monitor and control program and portfolio alignment with business
                                goals.
                            13. Implement PM cross-training and internal knowledge sessions.

The Project Team
   • Mike Leahy shall provide his expertise on systems delivery and business strategy to this project.
   • Hugh Shults shall provide his expertise on business development and project management to this
       project.
   • Harry Hansen shall provide his expertise on business strategy, start-up assessment, business
       plan competitions, and technology evaluation to the project.
   • Tony Wong shall bring his years of customer relations and communication experience to manage
       the outreach, communications and networking components of the project.
   • Ben Bedrossian shall bring his expertise and experience in financial reconciliation and contract
       management to the project.
   • Jon Ramirez shall bring his expertise and experience in sales and new market penetration to the
       project.
   • Tenrox Team shall bring their expertise at project management and information systems to this
       project.

PMO Steering Committee
The following are the key governing team members within the PMO
    •   Operations
    •   Systems Delivery
    •   Technology


Implementation of the PMO                                                                   Page 6 of 13
•   PMO
    •   Staff position (TBD)

PMO Escalation Model
When project issues cannot be resolved within the project itself, even with the assistance of the PMO, the
PMO facilitates the escalation of the issue to the higher authorities. The escalation process ensures that
the relevant authorities are informed within a specific time frame to ensure a timely solution. The
escalation path follows the model in Figure 2:




                                                Figure 2


PMO Authority
    •   The PMO is positioned in the organization to be effective with all the business units, and its
        authority is inherent of the position in the organization.
    •   The PMO has review and acceptance authority on internal and external contracts that are
        initiated as a function of a project.
    •   The PMO has the authority to work with the Finance Division for the vendor or contractor
        invoicing and payment management, including oversight of acceptable performance and approval
        of deliverables.
    •   The PMO has the authority to work with the Finance Division for customer invoicing and payment
        management including revenue recognition evidences.
    •   The PMO has the responsibility for commitment and allocation of project funds as well as the
        reporting of revenue and cash flow resulting from project work, and the preparation and
        management of the business unit budget
    •   The PMO operates in a strong matrix organization and has the authority to direct the work efforts
        of resources allocated to projects.
    •   The PMO has the authority and responsibility to contribute to the resource’s performance review.
    •   The PMO has the authority to redirect individuals to additional projects, project–related training,
        and follow-on work.
    •   The PMO has the authority to meet with customers and nurture customer relationships. The
        PMO has the responsibility to resolve customer issues as they relate to all aspects of the project.
    •   The PMO has the authority to work with the Customer Service Division for management of
        customer risks and issues.

Implementation of the PMO                                                                      Page 7 of 13
•   The PMO has the authority for the development, implementation, and management of project
        management practices within the FS Tech organization.

PMO Key Stakeholders
The PMO regards the following as primary stakeholders:
Organizational Position           Role                 Activities
President                         PMO Sponsor          • Ensures that the PMO has the necessary
                                                           resources and funding for optimum
                                                           operation.
                                                       • Approves PMO initiatives
PMO Steering Committee            PMO Executives       • Provides PMO direction
                                                       • Approves PMO funding
                                                       • Reviews project’s alignment with business
                                                           goals
                                                       • Resolves project issues as necessary
PMO Manager                       PMO Lead             • Resolves project issues
                                                       • Provides project directions
                                                       • Approves project deliverables
                                                       • Approves project funding
                                                       • Approves project time frame
                                                       • Devises continuous process improvements
                                                       • Plans knowledge improvement of business
                                                           and project units.
Project Managers                  Project SMEs         • Ensures project compliance with PMO’s
                                                           project management standards
                                                       • Ensures timely delivery of project goals
                                                       • Escalates project issues when they cannot
                                                           be resolved within the project
                                                       • Ensures flow of communications with the
                                                           PMO and clients.
Functional Managers               Team Members         • Ensures that project resources are allowed
                                                           to complete project activities on time.
                                                       • Cooperate with the PMO to resolve project
                                                           issues in a timely manner
Business Staff                    End Users            • Provides feedback on PMO services
                                                       • Is actively involved when required by the
                                                           PMO

Communication Plan
Type                        Schedule              Mechanism                  Stakeholder
PMO Performance             Monthly               Scorecard(s) prepared      • PMO Sponsor
Metrics                                           by the PMO and             • PMO Executives
                                                  delivered electronically
Project Status              Monthly               Seven Keys (or similar)    •   PMO Manager
                                                  prepared by the Project    •   Client
                                                  Manager and delivered
                                                  electronically
Project Status              Weekly                In-person or               •   Client
                                                  teleconference             •   End-User
                                                  delivered by the Project
                                                  Manager



Implementation of the PMO                                                               Page 8 of 13
Critical Success Factor
    •   The End-Users provide valuable feedback to improve current processes and propose changes that
        are beneficial to the PMO.
    •   Full Support of the PMO is provided by Executive Management.
    •   Stakeholders are identified accurately and timely.
    •   Projects and programs are successfully initiated, planned, executed, monitored/controlled, and
        closed using the proposed PMO strategies implemented.
    •   Portfolios are organized and reported-on to Executive Management’s specifications and
        satisfaction.

Return on Investment
These are ideas on how we can capture and realize the return on investment of the PMO. However,
each group tracks project metrics in different ways. The standardization of the way projects are created,
tracked, and evaluated will improve the ability to measure ROI. This will likely be a work in progress as of
PMO initiation. The following can be measured in percentages or dollars.
    •   Improved cost savings
    •   Improved budget performance
    •   Improved resource planning and forecasting
    •   Improved schedule performance
    •   Decrease failed projects
    •   Improved customer relations

PMO Metrics of Performance
    •   Program/Portfolio Cost and Resources
            o   The PMO tracks Planned Value, Earned Value, and Actual Cost to derive the following:
                          Cost Variance
                          Project Profitability Projection
                          Cost and Revenue Forecast
    •   Program/Portfolio Schedule and Resources
            o   The PMO tracks Planned Value and Earned Value to derive the following:
                          Schedule Variance
                          Schedule Performance
    •   Internal Metrics
            o   The PMO (or third-party) performs project audits to validate whether the project teams
                are utilizing the appropriate project management processes.
            o   Stakeholders Satisfaction
                          The PMO tracks the following thru survey to derive Stakeholder Satisfaction:
                               •   Access

                               •   Communication

                               •   Competence

                               •   Courtesy

Implementation of the PMO                                                                       Page 9 of 13
•   Credibility

                            •   Reliability

                            •   Responsiveness

                            •   Security

                            •   Tangibles

                            •   Understanding/Knowing the Customer

    •   Other areas of performance that may be considered for performance are Risk and Quality,
        depending on the needs of the Stakeholders.




Implementation of the PMO                                                         Page 10 of 13
BUDGET JUSTIFICATION

PMO Funding and Cost Estimates
    •    Funding
              o    Project Managers
                   The funding of the Project Manager position is derived on a level-of-effort plus expenses
                   basis, and is provided by the project. An estimate of effort would be performed, and the
                   hourly rate would be charged to the project or subsidiary overhead. Any travel required,
                   etc. is the same. These costs must be included in estimation of all bid and quotation
                   projects, or AFE’s for internal projects.
              o    Project Management Tool
                   Upon demonstration and review of the candidates1, Tenrox Project Workforce
                   Management was the team’s first choice based on its intuitive nature for time-reporting,
                   its ability to initiate and customize workflows, and its compatibility with MS Project and
                   other tools. This product connects to Salesforce.com using a ‘connector’, instead of
                   residing on the platform. This is a SaaS solution; therefore it is easily expanded to other
                   FS Tech locations and is available to Project Management staff at remote locations.

Initial Costs
6 Month Phased Implementation to all locations
    •    Project Management and Information System                                                               $66,717.00
    •    Training                                                                                                $21,200.00

    •    Salaries of Implementation Team (1 full-time PM, 2 quarter-time                                         $48,500.00
         PMs)                                                                                                    $60,000,00
    •    Travel Expenses of the Implementation Team                                                               $5,000.00
              o    all FS Tech locations for initial assessment
              o    all FS Tech locations for monitoring, controlling, and
                   continuous improvement
Total:                                                                                                         $201,417.00

Budget Items:
PM’s who are not actively working on a project shall be bench support. They review and document best
practices, support PMO projects, update procedures, attend training and meetings, assist assigned PM’s,
perform internal audits, etc. which would be funded by the PMO department.
    •    Yearly PMO staff’s salaries (1 quarter-time staff)                                                      $30,000.00
    •    Yearly PMO training (10 PMs * 2 wks)                                                                    $40,000.00

    •    Project management software license                                                                     $41,978.00
Total:                                                                                                           111,978.00




1
 Candidates were chosen from the perspective of integrating the Sales, Customer Service, and Financial departments. The
consensus was that there is value to be had from the ability to collaborate using the software.


Implementation of the PMO                                                                                      Page 11 of 13
FACILITIES, EQUIPMENT & OTHER RESOURCES
FACILITIES: No additional facilities shall be required for this implementation.

System Development:
Tenrox Project Workforce Management shall provide the ‘sandbox’ for PMIS development at no additional
charge. The team has access to this environment upon Notice to Proceed.

Clinical:
  N/A



Animal:
 N/A



Technical:
This is a SaaS solution; therefore it is easily expanded to other FS Tech locations and is available to
Project Management staff at remote locations. The only requirement is access to an Internet connection.

Office:
 A separate office shall not be required for the PMO.



Other:




Implementation of the PMO                                                                 Page 12 of 13
REFERENCES CITED

[1] “Establishing a Successful PMO”. Retrieved from http://www.pmsolutions.com/uploads/file/White
    %20Paper_Establishing%20a%20Successful%20PMO.pdf.

[2] Project Management Institute (2011). Project Management Book of Knowledge (PMBoK). Retrieved
    from http://www.pmi.org/

[3] NM State University (2008). “Project Management Office (PMO) Charter. Retrieve from
    http://ict.nmsu.edu/ict/reports/ICT_PMO_Charter_PMOCHTR_4.0_01-10-2008.pdf




Implementation of the PMO                                                                 Page 13 of 13

Implementation of the pmo proposal

  • 1.
    Implementation of thePMO Proposal Hugh Shults St. Edwards University MGMT 6320 Project and Change Management June 7, 2011
  • 2.
    Hugh Shults 3600 WestParmer Lane Austin, TX 78727 June 6, 2011 Michael Leahy System Delivery Federal Signal Technologies 2 Technology Circle Irvine, CA 92630 Dear Mr. Leahy: As you probably know by now, I have been actively pursuing the implementation of the Project Management Office at Federal Signal Technologies (FS Tech). I have done extensive outreach to many other FS Tech stakeholders and have found that the general consensus is that a PMO shall provide for the answers to some unresolved kinks in the evolvement of the new company. Now that the organization is larger and more distributed, it is an ideal time to seriously consider the implementation of a PMO. I am confident that I can complete this project within the designated time period and close to (or under) budget. I also believe that my recommended approach will have credibility with the Stakeholders. I am prepared to deliver a presentation of this project to the Stakeholders and answer any questions you and they may have about it; I anticipate that there will be many. If you have questions before the presentation, please give me a call. I can be reached on my cell phone anytime. Sincerely, Hugh Shults Project Management Professional Enclosure: Implementation of the PMO plan Implementation of the PMO Page 2 of 13
  • 3.
    PROJECT SUMMARY Implementation of the PMO This proposal is for preparing the organization for the adoption of a Project Management Office (PMO) and the strategy for implementing the PMO. The PMO is established to improve Federal Signal Technologies’ (FS Techs’) project management capability and the organization’s competitive advantage. To enable the PMO to provide independent services, the PMO shall operate as a separate business unit. This plan outlines the PMO’s goals and objectives, responsibility, organization, strategy, preliminary budget, preliminary schedule, authority, key stakeholders, project team, and critical success factors. Project Management Institute (PMI) defines the PMO as an organizational body or entity assigned various responsibilities related to centralized and coordinated management of those projects under its domain. The centralized management of programs such that corporate benefit is realized by sharing of resources, methodologies, tools, and techniques, and related high-level project management focus. This entity is also known by names such as Center of Excellence, Project Support Office, Program Management Office, and Strategic Project Office. The benefits of the PMO is it’s capacity to provide leadership in support of FS Tech business teams on internal and external projects, and to position FS Tech to be the benchmark in the industry. The PMO has become an important unit in today’s businesses, and by adopting and successfully implementing it, FS Tech shall have a superior reputation for client management and project delivery. The PMO is to the organization as the Project Manager is to the project. The PMO shall be a consolidation of all Project Management staff into one cohesive unit using a standard tool set and standard methodologies. Project Managers’ skills shall be fully developed to efficiently manage projects in any product line or market. . Implementation of the PMO Page 3 of 13
  • 4.
    PROJECT DESCRIPTION Implementation of the PMO Introduction The implementation of the PMO shall occur in phases to ensure that proper organizational restructure takes place and business activity proceeds with minimal impact. The intent is to introduce the new structure, methodologies, and standards using best practices and adjust to the business as much as possible while addressing the stakeholders concerns regarding project management practices, standards and performance Background Situation Upon the companies’ consolidation to form FS Tech, each company runs its project management activities and businesses to the best of its knowledge, experience, and resource constraints. This causes many issues for the consolidated company. Some of those issues are: • The inability to get a good portfolio of company goal alignment and performance. • Up to seven different project/business reporting mechanisms. • Up to seven different methodologies for delivery projects and measuring performance. • Difficult resource allocation and reporting. • Up to seven different ways of handling stakeholder concerns. • Unfit collaboration tools and expectations. PMO goals and objectives The goal is to establish a PMO that provides portfolio, program, and project leadership. The objectives to accomplish this goal are as follows: • Align business and project activities. • Develop and implement good project management standards and practices in FS Tech. • Develop project resource skills. • Develop project resource management processes. • Facilitate multi-project coordination in FS Tech. • Develop/Implement a project management information system (PMIS). • Integrate a shared project management system in FS Tech. • Improve PMO and project stakeholder communication. • Develop a set of metrics to measure performance to the organization. • Establish continuous improvement procedures for the PMO and project delivery. PMO Responsibilities The PMO provides the following services: • Governance of project, program, and portfolio management of the subsidiaries, so that they operate as the FS Tech organization, as opposed to individual companies. • Monitoring and controlling of multiple projects • Maintain a consolidated resource pool across the business unit to more efficiently manage resource allocation and availability • Develop and implement a code of ethics for the PMO and its membership • Standardize FS Tech’s project management methodology, processes and procedures, and tools Implementation of the PMO Page 4 of 13
  • 5.
    Manage the flow and repository of information and knowledge, to ensure that relevant staff has the correct level of access. • Assist with vendor and customer management. • Monitor, control, support, and continuously improve the project management capability. • Facilitate effective communication in projects. Organization By operating independently, it is expected that the PMO is able to provide an unbiased service to other departments within the organization. The PMO will operate in a strong matrix organizational structure. Project managers and functional managers will cooperate, although primary control of everything related to the project is the Project Manager’s domain, and control of everything else is the Functional Manager’s realm. In this organization, all Project Managers report to the PMO. Figure 1 is the proposed matrix organization for FS Tech. Figure 1 PMO Strategies To ensure that the PMO understands its mission and vision, the support from key stakeholders and end users is very important. The following is an outline of the PMO’s strategies to achieve those supports: • Circulate the draft PMO Charter to obtain inputs from key stakeholders, and ensure that all relevant parties are consulted. • Refine the PMO Charter based on those inputs. • Have the approval of the relevant executive on the final PMO Charter. • Execute the implementation of the PMO in phases. Implementing the PMO Schedule Description Implementation of the PMO Page 5 of 13
  • 6.
    Months 1 to3 1. Implementation of PM standards for Irvine and Austin offices. 2. An assessment is conducted and a plan developed with the project and functional Managers to meet Project Management Institute’s (PMI’s) minimum project standards where applicable. a. The PMO performs Strengths, Weaknesses, Opportunities, and Threats (SWOT) analysis to set the baseline for the plans. b. The PMO determines Specific, Measurable, Achievable, Realistic, and Timely (SMART) objectives to complete the plans. 3. Determine existing project, program and portfolio domain maturity across the business unit. 4. Communicate the expectations in regards to the project management standards. 5. Establish technical tools to standardize the project management activities, performance, and deliverables. Months 3 to 6 6. Implementation of PM standards for other five FS Tech locations. 7. Develop and implement a plan to manage the domains 8. Monitor and control PMIS activity for standard conformity; adjust as necessary. Months 6 to 9 9. Monitoring and controlling for all domains in respect to project management is conducted to measure the success of the ‘restructure’. 10. Design and conduct internal and external stakeholders’ surveys. 11. Plan with Customer Service, Sales, and Finance about project integration that shall benefit the organization. Months 9 to 12 12. Monitor and control program and portfolio alignment with business goals. 13. Implement PM cross-training and internal knowledge sessions. The Project Team • Mike Leahy shall provide his expertise on systems delivery and business strategy to this project. • Hugh Shults shall provide his expertise on business development and project management to this project. • Harry Hansen shall provide his expertise on business strategy, start-up assessment, business plan competitions, and technology evaluation to the project. • Tony Wong shall bring his years of customer relations and communication experience to manage the outreach, communications and networking components of the project. • Ben Bedrossian shall bring his expertise and experience in financial reconciliation and contract management to the project. • Jon Ramirez shall bring his expertise and experience in sales and new market penetration to the project. • Tenrox Team shall bring their expertise at project management and information systems to this project. PMO Steering Committee The following are the key governing team members within the PMO • Operations • Systems Delivery • Technology Implementation of the PMO Page 6 of 13
  • 7.
    PMO • Staff position (TBD) PMO Escalation Model When project issues cannot be resolved within the project itself, even with the assistance of the PMO, the PMO facilitates the escalation of the issue to the higher authorities. The escalation process ensures that the relevant authorities are informed within a specific time frame to ensure a timely solution. The escalation path follows the model in Figure 2: Figure 2 PMO Authority • The PMO is positioned in the organization to be effective with all the business units, and its authority is inherent of the position in the organization. • The PMO has review and acceptance authority on internal and external contracts that are initiated as a function of a project. • The PMO has the authority to work with the Finance Division for the vendor or contractor invoicing and payment management, including oversight of acceptable performance and approval of deliverables. • The PMO has the authority to work with the Finance Division for customer invoicing and payment management including revenue recognition evidences. • The PMO has the responsibility for commitment and allocation of project funds as well as the reporting of revenue and cash flow resulting from project work, and the preparation and management of the business unit budget • The PMO operates in a strong matrix organization and has the authority to direct the work efforts of resources allocated to projects. • The PMO has the authority and responsibility to contribute to the resource’s performance review. • The PMO has the authority to redirect individuals to additional projects, project–related training, and follow-on work. • The PMO has the authority to meet with customers and nurture customer relationships. The PMO has the responsibility to resolve customer issues as they relate to all aspects of the project. • The PMO has the authority to work with the Customer Service Division for management of customer risks and issues. Implementation of the PMO Page 7 of 13
  • 8.
    The PMO has the authority for the development, implementation, and management of project management practices within the FS Tech organization. PMO Key Stakeholders The PMO regards the following as primary stakeholders: Organizational Position Role Activities President PMO Sponsor • Ensures that the PMO has the necessary resources and funding for optimum operation. • Approves PMO initiatives PMO Steering Committee PMO Executives • Provides PMO direction • Approves PMO funding • Reviews project’s alignment with business goals • Resolves project issues as necessary PMO Manager PMO Lead • Resolves project issues • Provides project directions • Approves project deliverables • Approves project funding • Approves project time frame • Devises continuous process improvements • Plans knowledge improvement of business and project units. Project Managers Project SMEs • Ensures project compliance with PMO’s project management standards • Ensures timely delivery of project goals • Escalates project issues when they cannot be resolved within the project • Ensures flow of communications with the PMO and clients. Functional Managers Team Members • Ensures that project resources are allowed to complete project activities on time. • Cooperate with the PMO to resolve project issues in a timely manner Business Staff End Users • Provides feedback on PMO services • Is actively involved when required by the PMO Communication Plan Type Schedule Mechanism Stakeholder PMO Performance Monthly Scorecard(s) prepared • PMO Sponsor Metrics by the PMO and • PMO Executives delivered electronically Project Status Monthly Seven Keys (or similar) • PMO Manager prepared by the Project • Client Manager and delivered electronically Project Status Weekly In-person or • Client teleconference • End-User delivered by the Project Manager Implementation of the PMO Page 8 of 13
  • 9.
    Critical Success Factor • The End-Users provide valuable feedback to improve current processes and propose changes that are beneficial to the PMO. • Full Support of the PMO is provided by Executive Management. • Stakeholders are identified accurately and timely. • Projects and programs are successfully initiated, planned, executed, monitored/controlled, and closed using the proposed PMO strategies implemented. • Portfolios are organized and reported-on to Executive Management’s specifications and satisfaction. Return on Investment These are ideas on how we can capture and realize the return on investment of the PMO. However, each group tracks project metrics in different ways. The standardization of the way projects are created, tracked, and evaluated will improve the ability to measure ROI. This will likely be a work in progress as of PMO initiation. The following can be measured in percentages or dollars. • Improved cost savings • Improved budget performance • Improved resource planning and forecasting • Improved schedule performance • Decrease failed projects • Improved customer relations PMO Metrics of Performance • Program/Portfolio Cost and Resources o The PMO tracks Planned Value, Earned Value, and Actual Cost to derive the following:  Cost Variance  Project Profitability Projection  Cost and Revenue Forecast • Program/Portfolio Schedule and Resources o The PMO tracks Planned Value and Earned Value to derive the following:  Schedule Variance  Schedule Performance • Internal Metrics o The PMO (or third-party) performs project audits to validate whether the project teams are utilizing the appropriate project management processes. o Stakeholders Satisfaction  The PMO tracks the following thru survey to derive Stakeholder Satisfaction: • Access • Communication • Competence • Courtesy Implementation of the PMO Page 9 of 13
  • 10.
    Credibility • Reliability • Responsiveness • Security • Tangibles • Understanding/Knowing the Customer • Other areas of performance that may be considered for performance are Risk and Quality, depending on the needs of the Stakeholders. Implementation of the PMO Page 10 of 13
  • 11.
    BUDGET JUSTIFICATION PMO Fundingand Cost Estimates • Funding o Project Managers The funding of the Project Manager position is derived on a level-of-effort plus expenses basis, and is provided by the project. An estimate of effort would be performed, and the hourly rate would be charged to the project or subsidiary overhead. Any travel required, etc. is the same. These costs must be included in estimation of all bid and quotation projects, or AFE’s for internal projects. o Project Management Tool Upon demonstration and review of the candidates1, Tenrox Project Workforce Management was the team’s first choice based on its intuitive nature for time-reporting, its ability to initiate and customize workflows, and its compatibility with MS Project and other tools. This product connects to Salesforce.com using a ‘connector’, instead of residing on the platform. This is a SaaS solution; therefore it is easily expanded to other FS Tech locations and is available to Project Management staff at remote locations. Initial Costs 6 Month Phased Implementation to all locations • Project Management and Information System $66,717.00 • Training $21,200.00 • Salaries of Implementation Team (1 full-time PM, 2 quarter-time $48,500.00 PMs) $60,000,00 • Travel Expenses of the Implementation Team $5,000.00 o all FS Tech locations for initial assessment o all FS Tech locations for monitoring, controlling, and continuous improvement Total: $201,417.00 Budget Items: PM’s who are not actively working on a project shall be bench support. They review and document best practices, support PMO projects, update procedures, attend training and meetings, assist assigned PM’s, perform internal audits, etc. which would be funded by the PMO department. • Yearly PMO staff’s salaries (1 quarter-time staff) $30,000.00 • Yearly PMO training (10 PMs * 2 wks) $40,000.00 • Project management software license $41,978.00 Total: 111,978.00 1 Candidates were chosen from the perspective of integrating the Sales, Customer Service, and Financial departments. The consensus was that there is value to be had from the ability to collaborate using the software. Implementation of the PMO Page 11 of 13
  • 12.
    FACILITIES, EQUIPMENT &OTHER RESOURCES FACILITIES: No additional facilities shall be required for this implementation. System Development: Tenrox Project Workforce Management shall provide the ‘sandbox’ for PMIS development at no additional charge. The team has access to this environment upon Notice to Proceed. Clinical: N/A Animal: N/A Technical: This is a SaaS solution; therefore it is easily expanded to other FS Tech locations and is available to Project Management staff at remote locations. The only requirement is access to an Internet connection. Office: A separate office shall not be required for the PMO. Other: Implementation of the PMO Page 12 of 13
  • 13.
    REFERENCES CITED [1] “Establishinga Successful PMO”. Retrieved from http://www.pmsolutions.com/uploads/file/White %20Paper_Establishing%20a%20Successful%20PMO.pdf. [2] Project Management Institute (2011). Project Management Book of Knowledge (PMBoK). Retrieved from http://www.pmi.org/ [3] NM State University (2008). “Project Management Office (PMO) Charter. Retrieve from http://ict.nmsu.edu/ict/reports/ICT_PMO_Charter_PMOCHTR_4.0_01-10-2008.pdf Implementation of the PMO Page 13 of 13