SlideShare a Scribd company logo
1 of 41
THE CHANNEL-TUNNEL
PROJECT
CLOSE OUT PHASE
PREPARED BY: SHIVAM SOOD (PP18085)
The Chunnel Tunnel Project Close Out Phase
 Reflection on overall performance
 Settlement of claims
 Financial status
 Post project evaluation
Scope Management
Time management
Cost management
Quality management
Human resource management
Communication management
Risk management
Procurement management
Integration management
OBJECTIVES
Scope Management
 Lack of defined scope
 Intervening of IGC
 Irregular and uncontrolled changes in project.
 Compatibility/Coordination issues between different teams.
 The operations began even before its completion.
Scope Creep
 Scope creep in project management the phenomenon of
uncontrolled changes or continuous growth in the project´s scope.
This phenomenon is caused when the scope is not clearly defined.
 There were irregular and sudden changes in the project.
 Without additional funding during closeout.
 Absence of historical records with similar projects.
 Lead to some requirement gaps
 Risk impact was not considered
 To improve safety, there was need of air conditioning system that was not
included in initial design.
 All this lead to budget overrun.
 Rating-2
Other Reasons
Time Management
 Gushing effects of the earlier phases.
Rapid bidding and concept development.
Insufficient time for detailed design studies
Irregular changes by IGC
Approval of drawing from both governments.
Rail and car systems were delivered late.
Alterations of door sizes. (9 months delay)
Time Management continued….
 Team work and communication broken down in several key areas.
 Time overshoot: greatest impact of ROI.
 Lead to 19 months project delay.
 Finally, took over 20% more time(6years over 5years), with an over
budget of 80%($14.9 billions over $5.5 billions) and ended in 1994.
 Rating-3.
 Cost is one of the most difficult aspect to plan for when a project has such a
huge magnitude, the project management team had serious challenges in
planning and detailing.
 Cost management is the process of planning and controlling the budget of a
business basically a form of management accounting that allows a business
to predict impending expenditures.
 In Close Out Phase, the discussion reflects on overall performance,
settlement of claims, financial status and post project evaluation
Cost Management
 The bit price was US$ 5.5 billion which included a 32 mile approximately
51.5 km double rail tunnel to accommodate both through-trains and special
car and truck carrying shuttle train.
 From Project management perspective, it was very clear that the cost
estimate were not detailed out as not enough time was provided to complete
the detailed design.
Cost Management continued….
What was the problem w.r.t. cost
management?
 The majority of effort was focussed on analysing the sources of cost
overruns and attempting to assign blame to one or more of the participating
organisation.
 The project team did a reasonable job when it came to planning the
technical equipment that would be needed and understanding the
complexity involved.
 There was much interpretation open for agencies like IGC that might have
better off detailed during the planning sessions.
 The closeout phase explores the total cost impact not only on the
construction cost overruns but also the lost revenue and carrying
cost of project delayed by 19 months.
 The project stakeholders could not expect to see a return on
investment until significantly longer than had been initially
expected because of the “bare minimum approach”.
 Rating-1
 The overall quality of the delivered project, as measured during closeout
was impressive as the quality parameters achieved were above industry
average.
 Both countries followed different specifications and it was decided that
the contribution on any detail would be done by considering higher of
the two specifications.
Quality Management
 Through the effective quality and safety programs even the work place
accident rates during the project were well below the industry average.
 In terms of Engineering design and expectations, the quality of the
project was up to the mark.
 Rating-4.
Quality Management continued….
 The Chunnel Project required the cooperation of two national governments, Bankers,
various contractors & regulatory agencies.
 46 contractors were hired to complete the design requirements and as it turned out
the time required to complete the tunnelling was finished 3 months ahead of schedule.
 Contractual errors were made in estimates leading to additional contract claims of US
2.25 Billion dollars.
 It was the misjudgement of HR department to hire 15 thousand workers on the
project.
 Below the ground thousands of construction workers , machinist and engineers were
involved in boring 3 tunnels for 32 miles from both borders across the Chunnel.
Human Resource Management
 The project Management team hindsight could have done a better
job of planning ,detailing and designing the project. As the team
gave up majority of control to IGC it enhanced the complications of
the project resulting in time and cost over run.
 Most of the employees were demotivated due to non settlement of
claims thus win-win situation was lost.
H.R. Management continued….
ITEM ENGLISH SIDE FRENCH SIDE
Recruitment 50% travelling men.
Housed in temporary camp.
Recruited by depressed
mining region.
95% men from depressed
region.
Part of employment
regeneration.
Help wit job at end of project.
Polices Poor safety record. More organized union
structure.
Problems Senior managers didn’t get
along.
Harmonious atmosphere.
H.R. Management continued….
 Rating-3
 The communication was prevalent on formal level which is evident
from the quarterly meetings that were held between the two
countries and the concerned authorities.
 The two countries didn’t had good communication among
themselves, resulting in delay and cost overrun.
 This project involved 7 lakh share holders, 220 International banks,
construction companies and suppliers causing significant logistical
and communication challenges.
 Negotiation was not proper at the closeout since bankers didn’t
settle for the claims.
Communication Management continued….
 Each side worked towards a common goal and didn’t feel the need to
communicate as they assumed that both the parties were working
towards meeting in the middle.
 Lack of communication during development and design of the project
in the early stages let to difference of opinions in the later stages.
 The financial backers of the project where keenly focused on
minimizing there losses and as such refused to accept negotiations for
settling contract disputes.
 Delay in communication regarding the specification change.
 Rating-2.
Communication Management continued….
Communication Management continued….
Procurement Management
 It was quiet complex and under vigorous time constraint. So certain
assumption errors was made regarding ability to have enough resources.
 Regular intervention from IGC and their slow decision making led to
change in scope which in turn led to repetitive procurement.
 Use of more advance and sophisticated equipments lead to procurement of
new equipment.
 Rating -2.
Risk Management
 There were two type of risks in this project:
i. Technical risk.
ii. Financial risk.
 Previous studies, technical analysis and risk involved in such projects were
studied but not implemented in the later part of the project.
 There was close to no contingency for unknown unknowns, which in turn
led to increased number of arbitrations and claims.
 Fast tracking the process of overlapping design and construction under
pressure of bankers and investors made it more risky.
 The tunnel was perfectly bored within the chalk marl layer
throughout.
 In some case risk was also overmanaged for e.g. use of much
advanced and sophisticated equipment. (eg Waterproof TBMs on
French side)
 Number of casualties was way below the industry average.
 Rating-3.
Risk Management Continued……..
Integration Management
 Both the governments refused to guarantee the project financially
which put an additional burden on privatised sector.
 Communication b/w the French and England Companies was very
limited.
 Some portions of the project were completed very early (for e.g.
tunnelling) but other areas (for e.g. key mechanical system) were
delivered late.
 Team work was focused on each party meeting it’s own priorities and
interests rather than working towards a acceptable solutions.
 Due to lack of integration they didn’t came up with a common
conclusion on the specification of rolling stocks.
 Rating-2.
Integration Management Continued..…..
Rating scale (Closure Phase)
PROJECT MANAGEMENT ASPECTS RATINGS
Scope Management 2
Time Management 3
Cost Management 1
Quality Management 4
Human Resource Management 3
Communication Management 2
Risk Management 3
Procurement Management 2
Integration Management 2
5- Excellent; 4-Very Good; 3-Good; 2-Poor; 1-Very Poor
0.0
1.0
2.0
3.0
4.0
5.0
2
3
1
4
3
2
3
2 2
RatingsScale
Ratings
Close Out Phase- Assigned Ratings
SWOT ANALYSIS OF PROJECT MANAGMENT IN CLOSE OUT PHASE
S - Strengths
• Project Quality was impressive.
Quality
Management
• Close to 15000 workers were
employed
• Overall HR management was very
good
Human Resource
Management
W - Weaknesses
• Scope was Ever-Changing.
• No Clarity
Scope
Management
• Scope was not clearly specified, led to
poor Procurements throughout the
project.
Procurement
Management
• No clarity in scope led to repetitive
approvals
• Slow approvals and late Procurements
Time
Management
O – Opportunities
• Emphasis was always on making money
rather on effective Construction
Operations.
• Too much involvement of bankers and
investors.
• Delay in Project led to loss in ROI,
Unclear Scope led to cost overruns in
settling claims.
Cost
Management
• No contingency for Unknown Unknowns
• Non effective Change ManagementRisk Management
T - Threats
• Very Poor communication b/w two
countries.
• Poor communication led to slow
approvals and thus delaying whole
project.
Communication
Management
• All parties had only their profit in mind
and not Projects’.
• Integration was poor b/w Investors – IGC
– Contractors – Sub contractors.
Integration
Management
THANK YOU!!!!

More Related Content

What's hot

Project Closure Report
Project Closure ReportProject Closure Report
Project Closure Report
Adam Edwards
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
Fakhar-un -Nisa
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure Report
Cheryl Burcham
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
Adrias TAN
 

What's hot (20)

The Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementThe Chunnel Project - Quality Management
The Chunnel Project - Quality Management
 
Channel tunnel
Channel tunnelChannel tunnel
Channel tunnel
 
Epc Vs Epcm
Epc Vs EpcmEpc Vs Epcm
Epc Vs Epcm
 
Project Finance Session 01
Project Finance Session 01Project Finance Session 01
Project Finance Session 01
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
 
Project Closure Report
Project Closure ReportProject Closure Report
Project Closure Report
 
claims management framework
 claims management framework claims management framework
claims management framework
 
Cash flow report using ms project
Cash flow report  using ms projectCash flow report  using ms project
Cash flow report using ms project
 
Flawless Project Delivery
Flawless Project DeliveryFlawless Project Delivery
Flawless Project Delivery
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure Report
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 
Architecture And Construction Services Proposal PowerPoint Presentation Slides
Architecture And Construction Services Proposal PowerPoint Presentation SlidesArchitecture And Construction Services Proposal PowerPoint Presentation Slides
Architecture And Construction Services Proposal PowerPoint Presentation Slides
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Epc contracts.
Epc contracts.Epc contracts.
Epc contracts.
 

Similar to Chunnel Project

Project XYC Project PlanEric Malone, Jennifer Napier, .docx
Project XYC  Project PlanEric Malone, Jennifer Napier, .docxProject XYC  Project PlanEric Malone, Jennifer Napier, .docx
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
wkyra78
 
Asim prasad
Asim prasadAsim prasad
Asim prasad
PMI2011
 
Asim 20prasad-131008015750-phpapp02
Asim 20prasad-131008015750-phpapp02Asim 20prasad-131008015750-phpapp02
Asim 20prasad-131008015750-phpapp02
PMI_IREP_TP
 
Investigating the Effects of Replacing the Project Manager during Project Exe...
Investigating the Effects of Replacing the Project Manager during Project Exe...Investigating the Effects of Replacing the Project Manager during Project Exe...
Investigating the Effects of Replacing the Project Manager during Project Exe...
James Dubber
 
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
MargaritoWhitt221
 

Similar to Chunnel Project (20)

Project management case study.pptx
Project management case study.pptxProject management case study.pptx
Project management case study.pptx
 
Cost and time overruns in indian construction industry
Cost and time overruns in indian construction industryCost and time overruns in indian construction industry
Cost and time overruns in indian construction industry
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
CHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdfCHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdf
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 
Infrastrcture project management
Infrastrcture project managementInfrastrcture project management
Infrastrcture project management
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better Cheaper
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
 
Risk management
Risk managementRisk management
Risk management
 
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
Project XYC  Project PlanEric Malone, Jennifer Napier, .docxProject XYC  Project PlanEric Malone, Jennifer Napier, .docx
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
 
Asim prasad
Asim prasadAsim prasad
Asim prasad
 
Asim 20prasad-131008015750-phpapp02
Asim 20prasad-131008015750-phpapp02Asim 20prasad-131008015750-phpapp02
Asim 20prasad-131008015750-phpapp02
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
Investigating the Effects of Replacing the Project Manager during Project Exe...
Investigating the Effects of Replacing the Project Manager during Project Exe...Investigating the Effects of Replacing the Project Manager during Project Exe...
Investigating the Effects of Replacing the Project Manager during Project Exe...
 
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
 

Recently uploaded

"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
pritamlangde
 

Recently uploaded (20)

Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information Systems
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdf
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 

Chunnel Project

  • 1. THE CHANNEL-TUNNEL PROJECT CLOSE OUT PHASE PREPARED BY: SHIVAM SOOD (PP18085)
  • 2. The Chunnel Tunnel Project Close Out Phase  Reflection on overall performance  Settlement of claims  Financial status  Post project evaluation Scope Management Time management Cost management Quality management Human resource management Communication management Risk management Procurement management Integration management OBJECTIVES
  • 3.
  • 4. Scope Management  Lack of defined scope  Intervening of IGC  Irregular and uncontrolled changes in project.  Compatibility/Coordination issues between different teams.  The operations began even before its completion.
  • 5. Scope Creep  Scope creep in project management the phenomenon of uncontrolled changes or continuous growth in the project´s scope. This phenomenon is caused when the scope is not clearly defined.  There were irregular and sudden changes in the project.  Without additional funding during closeout.
  • 6.  Absence of historical records with similar projects.  Lead to some requirement gaps  Risk impact was not considered  To improve safety, there was need of air conditioning system that was not included in initial design.  All this lead to budget overrun.  Rating-2 Other Reasons
  • 7.
  • 8. Time Management  Gushing effects of the earlier phases. Rapid bidding and concept development. Insufficient time for detailed design studies Irregular changes by IGC Approval of drawing from both governments. Rail and car systems were delivered late. Alterations of door sizes. (9 months delay)
  • 9. Time Management continued….  Team work and communication broken down in several key areas.  Time overshoot: greatest impact of ROI.  Lead to 19 months project delay.  Finally, took over 20% more time(6years over 5years), with an over budget of 80%($14.9 billions over $5.5 billions) and ended in 1994.  Rating-3.
  • 10.
  • 11.  Cost is one of the most difficult aspect to plan for when a project has such a huge magnitude, the project management team had serious challenges in planning and detailing.  Cost management is the process of planning and controlling the budget of a business basically a form of management accounting that allows a business to predict impending expenditures.  In Close Out Phase, the discussion reflects on overall performance, settlement of claims, financial status and post project evaluation Cost Management
  • 12.  The bit price was US$ 5.5 billion which included a 32 mile approximately 51.5 km double rail tunnel to accommodate both through-trains and special car and truck carrying shuttle train.  From Project management perspective, it was very clear that the cost estimate were not detailed out as not enough time was provided to complete the detailed design. Cost Management continued….
  • 13. What was the problem w.r.t. cost management?  The majority of effort was focussed on analysing the sources of cost overruns and attempting to assign blame to one or more of the participating organisation.  The project team did a reasonable job when it came to planning the technical equipment that would be needed and understanding the complexity involved.  There was much interpretation open for agencies like IGC that might have better off detailed during the planning sessions.
  • 14.  The closeout phase explores the total cost impact not only on the construction cost overruns but also the lost revenue and carrying cost of project delayed by 19 months.  The project stakeholders could not expect to see a return on investment until significantly longer than had been initially expected because of the “bare minimum approach”.  Rating-1
  • 15.
  • 16.  The overall quality of the delivered project, as measured during closeout was impressive as the quality parameters achieved were above industry average.  Both countries followed different specifications and it was decided that the contribution on any detail would be done by considering higher of the two specifications. Quality Management
  • 17.  Through the effective quality and safety programs even the work place accident rates during the project were well below the industry average.  In terms of Engineering design and expectations, the quality of the project was up to the mark.  Rating-4. Quality Management continued….
  • 18.
  • 19.  The Chunnel Project required the cooperation of two national governments, Bankers, various contractors & regulatory agencies.  46 contractors were hired to complete the design requirements and as it turned out the time required to complete the tunnelling was finished 3 months ahead of schedule.  Contractual errors were made in estimates leading to additional contract claims of US 2.25 Billion dollars.  It was the misjudgement of HR department to hire 15 thousand workers on the project.  Below the ground thousands of construction workers , machinist and engineers were involved in boring 3 tunnels for 32 miles from both borders across the Chunnel. Human Resource Management
  • 20.  The project Management team hindsight could have done a better job of planning ,detailing and designing the project. As the team gave up majority of control to IGC it enhanced the complications of the project resulting in time and cost over run.  Most of the employees were demotivated due to non settlement of claims thus win-win situation was lost. H.R. Management continued….
  • 21. ITEM ENGLISH SIDE FRENCH SIDE Recruitment 50% travelling men. Housed in temporary camp. Recruited by depressed mining region. 95% men from depressed region. Part of employment regeneration. Help wit job at end of project. Polices Poor safety record. More organized union structure. Problems Senior managers didn’t get along. Harmonious atmosphere. H.R. Management continued….  Rating-3
  • 22.
  • 23.  The communication was prevalent on formal level which is evident from the quarterly meetings that were held between the two countries and the concerned authorities.  The two countries didn’t had good communication among themselves, resulting in delay and cost overrun.  This project involved 7 lakh share holders, 220 International banks, construction companies and suppliers causing significant logistical and communication challenges.  Negotiation was not proper at the closeout since bankers didn’t settle for the claims. Communication Management continued….
  • 24.  Each side worked towards a common goal and didn’t feel the need to communicate as they assumed that both the parties were working towards meeting in the middle.  Lack of communication during development and design of the project in the early stages let to difference of opinions in the later stages.  The financial backers of the project where keenly focused on minimizing there losses and as such refused to accept negotiations for settling contract disputes.  Delay in communication regarding the specification change.  Rating-2. Communication Management continued….
  • 26.
  • 27. Procurement Management  It was quiet complex and under vigorous time constraint. So certain assumption errors was made regarding ability to have enough resources.  Regular intervention from IGC and their slow decision making led to change in scope which in turn led to repetitive procurement.  Use of more advance and sophisticated equipments lead to procurement of new equipment.  Rating -2.
  • 28.
  • 29. Risk Management  There were two type of risks in this project: i. Technical risk. ii. Financial risk.  Previous studies, technical analysis and risk involved in such projects were studied but not implemented in the later part of the project.  There was close to no contingency for unknown unknowns, which in turn led to increased number of arbitrations and claims.  Fast tracking the process of overlapping design and construction under pressure of bankers and investors made it more risky.
  • 30.  The tunnel was perfectly bored within the chalk marl layer throughout.  In some case risk was also overmanaged for e.g. use of much advanced and sophisticated equipment. (eg Waterproof TBMs on French side)  Number of casualties was way below the industry average.  Rating-3. Risk Management Continued……..
  • 31.
  • 32. Integration Management  Both the governments refused to guarantee the project financially which put an additional burden on privatised sector.  Communication b/w the French and England Companies was very limited.  Some portions of the project were completed very early (for e.g. tunnelling) but other areas (for e.g. key mechanical system) were delivered late.
  • 33.  Team work was focused on each party meeting it’s own priorities and interests rather than working towards a acceptable solutions.  Due to lack of integration they didn’t came up with a common conclusion on the specification of rolling stocks.  Rating-2. Integration Management Continued..…..
  • 34. Rating scale (Closure Phase) PROJECT MANAGEMENT ASPECTS RATINGS Scope Management 2 Time Management 3 Cost Management 1 Quality Management 4 Human Resource Management 3 Communication Management 2 Risk Management 3 Procurement Management 2 Integration Management 2 5- Excellent; 4-Very Good; 3-Good; 2-Poor; 1-Very Poor
  • 36. SWOT ANALYSIS OF PROJECT MANAGMENT IN CLOSE OUT PHASE
  • 37. S - Strengths • Project Quality was impressive. Quality Management • Close to 15000 workers were employed • Overall HR management was very good Human Resource Management
  • 38. W - Weaknesses • Scope was Ever-Changing. • No Clarity Scope Management • Scope was not clearly specified, led to poor Procurements throughout the project. Procurement Management • No clarity in scope led to repetitive approvals • Slow approvals and late Procurements Time Management
  • 39. O – Opportunities • Emphasis was always on making money rather on effective Construction Operations. • Too much involvement of bankers and investors. • Delay in Project led to loss in ROI, Unclear Scope led to cost overruns in settling claims. Cost Management • No contingency for Unknown Unknowns • Non effective Change ManagementRisk Management
  • 40. T - Threats • Very Poor communication b/w two countries. • Poor communication led to slow approvals and thus delaying whole project. Communication Management • All parties had only their profit in mind and not Projects’. • Integration was poor b/w Investors – IGC – Contractors – Sub contractors. Integration Management

Editor's Notes

  1. The Chunnel Project during the closeout phase showed no significant improvements with regard to management, even with the best attempt at managing the critical complications during the project did not have any impact on the overall outcome. [2] The return of the investment at the end did not materialize based on the fixed-price contracts that were used at the beginning of the Chunnel Project. The reasons were mostly the effects from the delays in the schedule. The problems with cash-flow were mainly due to impacts from the large delays in the schedule. The fixed-price model settled in the contract should give a continuous funding throughout the project, but as the payment milestones were not reached according the schedule the funding did not occur on time to cover for the costs. If the project had remained on schedule, the payment terms in the fixed-price model would have both covered for the costs when they occurred, and provided a good return on the investment, in accordance what was expected by the stakeholders. However, the overall quality of the delivered project during the closeout phase, was impressive. The completion of the final tunnel was an engineering feat that was extremely complex and there were difficulties to succeed. Even with these obstacles, the tunnel was carried out as designed. The project operated successfully through an effective quality and safety program.