SlideShare a Scribd company logo
1 of 5
Download to read offline
Investigating the Effects of Replacing the Project Manager during Project
Execution
RJ Dubber1
, JHC Pretorius2
1
Faculty of Engineering and the Built Environment, Postgraduate Student, University of Johannesburg, Johannesburg,
South Africa, rjdubber@gmail.com
2
Faculty of Engineering and the Built Environment, Head of School: Postgraduate School of Engineering Management,
University of Johannesburg, Johannesburg, South Africa
jhcpretorius@uj.ac.za
Abstract - It is a setback that many projects face and
senior management fear, that a well-run project heading for
success can take a turn for the worst when the project
manager is replaced as a result of resignation or transfer. The
replacement of the leader and foundation of the project can
result in poor management of the triple constraint (scope,
time and budget), loss of historical project information, as
well as cause a ripple effect of conflict, confusion,
misunderstanding and poor team spirit within the project
team. The term “replacing the project manager” or “RPM”
should be easily recognized by organizations, yet, there is very
little documentation available discussing this common issue.
The frequency of replacement, the circumstances in which the
project manager is replaced, and the effect it has on a project
during execution is investigated.
Keywords - project manager, replacing the project
manager (RPM), project execution, engineering, procurement
and construction (EPC), engineering, procurement and
construction management (EPCM)
I. INTRODUCTION
Project management is a growing profession in all
industries and there is much literature on the subject. The
correct implementation of the principles of project
management is, however, more difficult in practice. This,
together with different individual personalities, interests
and capabilities almost guarantees the assertion that
replacing the project manager (RPM) is not a simple
procedure. RPM can cause major disruption to the project
from both an employer and employee perspective.
Investigating the effects of RPM during project
execution identifies the frequency of RPM, the
circumstances in which the project manager is replaced,
and the effect on a project in terms of project management
principles. Guidelines to facilitate the handover to limit the
impact on a project as a result of RPM are proposed and
investigated.
A. Introducing and Defining RPM
Many believe that employee turnover can be beneficial
for an organization in terms of development and career
opportunities [1]. However, changes in management
personnel have been found by many to have a significant
negative effect on project performance. A survey carried
out by [1] revealed the following:
• 97% strongly agreed that project managers are critical
to project success;
• 85% disagreed that project management turnover has
no effect on project performance, and
• Project management turnover occurs primarily in the
execution phase of the project life cycle, increasing
risk, cost and the probability of project failure.
Project managers are critical to project management
success and limited research has been undertaken to
ascertain the percentage of project managers who maintain
the position from project initiation to close-out.
B. Rationale of the Research
A report published by [2] concluded that 90% of global
senior executives ranked project management methods as
either critical or somewhat important to their ability to
deliver successful projects and remain competitive.
Furthermore, a survey carried out by [3] yielded 60% of
senior executives stating that building a strong project
management discipline is a top-three priority for their
companies.
There is a rapid growth in project-orientated firms
(projectized organizational structures) [4]. An international
study conducted by [5] confirms that project matrix (strong
matrix) and projectized structures are perceived as the most
effective across all types of projects. As indicated in Figure
1, project managers in these structures have high authority,
manage the project budget and are dedicated full-time to a
project.
Figure 1: Influence of organizational structures on projects [6]
The project manager is therefore the nucleus of a
project, which highlights the need for organizations to
identify RPM and recognize the effects, consequences and
the requirement for mitigation and cautious management.
C. Problem Statement and Research Objectives
Guidelines to carry out project management, tailored
to suit the industry in which it is practiced, are well
documented. The literature focuses particularly on project
management and managers, their roles and responsibilities,
and how critical they are during the project process.
Information that is not often documented or portrayed as
an integral part of a project life cycle is the effect of RPM
during project execution.
RPM has a net effect on a project – either positive or
negative (and in very few instances neutral). The influence
of RPM is not well understood, neither documented nor
assessed in great detail. This information is critical to the
project management process and ensuring project success
in cases where RPM is experienced.
The research objectives were to identify the frequency
of replacing the project manager, the circumstances in
which the project manager is replaced, and the effect on a
project in terms of project management principles.
Guidelines to facilitate the handover to limit the impact on
a project were also proposed and investigated.
II. METHODOLOGY
Qualitative and quantitative research methodologies
were implemented in order to fulfil the research objectives.
The methodologies were individually investigated to
determine the most effective research approach to satisfy
the research objectives.
A. Case Study – Qualitative Research Approach
A descriptive case study type was selected for the
qualitative research method. The case study was presented
through the eyes of the author who, as a project engineer in
an engineering, procurement and construction (EPC)
organization, experienced the effects of RPM during the
execution phase of a project. The findings of the
descriptive case study should be considered as preliminary
rather than conclusive as no data analysis techniques were
implemented.
A world-renowned gold mining company required a
new cyanide make-up facility and piping distribution
network at one of its existing gold-processing plants in
Ghana, West Africa. The upgrade was necessary as the
existing cyanide system did not meet with the International
Cyanide Management Code (ICMI). Strict deadlines were
put in place as the plant audit and compliance review was
under pressure from external governmental factors. The
remeasurable contract was based on the supply,
manufacturing and installation of structural, mechanical,
plate work and piping (SMPP) as well as electrical and
instrumentation (E&I) governed by the FIDIC Conditions
of Contracts for Construction – The Red Book.
In the initial stages of construction, the project
manager resigned and a new project manager was
appointed. The newly appointed project manager had
previously been in the operations side of the organization
with no contractual experience. The organizational
structure was projectized and the involvement of the initial
project manager was full-time. However, the new project
manager was site-based and only partially involved in the
day-to-day construction operations, with the scope,
schedule and budget managed remotely by the appointed
project engineer. Furthermore, no official handover was
initiated by either project manager – resigned project
manager out, new project manager in.
The project was negatively affected, with deteriorated
project schedule and performance, an increase in cost and
project risk, loss of information, and weakened
communication and project team morale. The project is
summarized in Table 1 with the initial and final results as
indicated.
Table 1: Case study project summary
B. Survey – Quantitative Research Approach
A quantitative research approach was selected to
determine the effects of RPM during project execution as
literature has shown that RPM is a known phenomenon
with few studies discussing this issue [7]. The case study
provides a preliminary investigation based on the author’s
experience and a quantitative research approach permits
further investigation.
A questionnaire was designed for the distribution and
collection of data for analysis. The questionnaire was
designed to limit the number of questions and reduce the
overall time required to complete the survey. The decision
to limit the questionnaire and maintain simplicity was
taken with the intention of motivating potential
respondents to complete the survey.
III. RESULTS
A. Demographics of the Survey
The survey population was selected by means of
LinkedIn, a professional social network. South African
project houses providing engineering, procurement and
construction (EPC), as well as engineering, procurement
and construction management (EPCM) services to the
mining industry were targeted.
The total number of respondents (100%, n=45), with
an overall achieved response rate of 56% was made up of
senior management totaling 22% (n=10), project managers
totaling 36% (n=16) and project team members making up
42% (n=19). The respondents’ professional capacities are
indicated in Figure 2.
Respondents’ Professional Capacities
Figure 2: Percentage distribution of respondents’ professional
capacities
The industries in which the respondents are currently
active are predominantly the mining industry (53%, n=24),
followed by “other”, comprising 22% of the total
respondents, who are involved in EPC or EPCM business
models. The targeted industries are indicated in Figure 3.
Targeted Industries
Figure 3: Percentage distribution of respondents’ industries
The majority of the respondents (31%, n=14) had five
to 10 years’ experience in the industry in which they are
currently active. The respondents’ industry experience is
indicated in Figure 4.
Respondents’ Industry Experience
Figure 4: Percentage distribution of respondents’ industry
experience
B. Overview of the RPM Survey
The results of the web-based survey yielded 93%
(n=42) of respondents experiencing RPM in the work place
– an extremely high frequency of project management
turnover in the execution phase of a project.
The survey confirmed that career motives (48%, n=20)
followed by “other” (24%, n=10) are the major motives for
the project manager relieving his/her duties on a project.
“Other” is attributed to a client’s request for removing the
project manager from a project as a result of poor
performance or a bitter relationship. The company culture
and/or structure has quite a big effect on a project manager
departing a project with 19% (n=8) share and a high stress
environment playing a very small role (7%, n=3). Figure 5
graphically presents the percentage distribution for the
motives of a project manager to depart a project during
project execution.
Motives for Project Manager Departure
Figure 5: Percentage distribution of respondents’ motives for a
project manager departing a project
The net effect on a project as a result of RPM was
identified and two classes disclosed:
1. The project manager had to be replaced in order to
rescue a troubled project and resulted in a net positive
effect.
2. The project manager resigned and was replaced
reluctantly by the organization and resulted in a net
negative effect.
The results yielded 31% of respondents identifying
RPM with a net positive effect compared to 62% of
respondents identifying RPM with a net negative effect – a
major stake in the results. A net positive effect corresponds
to the motive “other” in Figure 5 identified to be a client’s
request for RPM which is only experienced under irregular
circumstances that could be identified and possibly
corrected in the early stages of a project. A net negative
effect as a result of the project manager departing a project
of their own accord for prospective career motives
identified in Figure 5 is the real concern.
Figure 6 graphically presents the cumulative
percentage distribution for the positive and negative
impacted areas of project management on a project as a
result of RPM. An assumption was made that the project
deliverables in terms of quality are not compromised
through RPM i.e. the final product is always within the set
quality parameters upon project handover.
Impact of RPM on a Project
Figure 6: Cumulative percentage distribution of responses to
impacted areas as a result of RPM
The project management areas impacted, in sequence
from the highest ranked positively impacted area to the
lowest, are client’s trust (92%), project schedule and
performance (69%), communication (62%), team
motivation (62%), documentation and information sharing
(46%), project risk (31%) and cost and cash flow (8%).
The project management areas impacted, in sequence
from the highest ranked negatively impacted area to the
lowest, are communication (85%), project schedule and
performance (73%), documentation and information
sharing (69%), client’s trust (65%), project risk (54%),
team motivation (54%) and cost and cash flow (27%).
The controls to minimize the impact of RPM and
facilitate the handover between the replaced project
manager and the replacement project manager are indicated
in Figure 7.
Controls to Facilitate Handover
Figure 7: Cumulative percentage distribution of responses to
facilitate RPM to reduce impact on a project
The most effective controls were identified as
including a senior project leader in all communications
(71%), document control (67%), project management
office (PMO) (38%) and “other” (18%) identified as
implementing a sufficient handover period.
IV. DISCUSSION
The conducted survey identifies that RPM during
project execution is a common phenomenon. Furthermore,
the survey results indicate a tendency of RPM to have a net
negative effect on a project when a successful project
manager leaves for personal growth. RPM and the negative
effect it could potentially have on a project as a result of
the project manager departing a project of their own
accord, is the real concern.
With the movement into projectized organizations and
the associated responsibilities of the project manager,
organizations should want to mitigate and manage RPM
before it transpires and impacts on interdependent project
management areas and project outcomes.
The controls to facilitate the handover were found to
be the most effective measures to reduce the impact of
RPM, should it transpire. However, project management
maturity and the ineffective implementation of the PMO as
a tool to move forward from individual dependency into
project management processes by means of organizational
policies and procedures should be considered a vital step
towards reducing the negative effects of RPM.
V. CONCLUSION
A. Summary of Findings
RPM, a form of managerial turnover, will almost
always have an effect on a project outcome. The topic
“Investigating the Effects of Replacing the Project
Manager during Project Execution” was identified to be a
critical subject with little information addressing the issue.
Literature identifies the fact that the maximum effort is
required during the execution phase of a project, verifying
the vulnerability of a project during this stage should RPM
take place. Journals and documented surveys carried out by
[1], [7], [8], [9] and [10] confirm that RPM is a high risk
issue, primarily occurring in the execution phase of the
project life cycle, increasing risk, cost and the probability
of project failure.
The case study identified that the net effect on a project
during RPM is negative, with emphasis on the identified
key areas of project management. The case study provided
a preliminary investigation based on the author’s
experience and a quantitative research approach followed
in the form of a web-based survey to permit further
investigation. The following summary is deducted from the
responses to the survey:
• 93% confirmed having experienced RPM in their work
environment;
• 48% confirmed that career motives are the main drive
for the project manager departing a project;
• 31% confirmed that RPM has a net positive effect on
a project;
• 62% confirmed that RPM has a net negative effect on
a project;
• 71% confirmed that including a senior project leader
in all communications is the best control to facilitate a
project handover, and
• 100% agreed that a project manager’s role in project
success is important or very important (four and five
on a Likert scale).
The survey reflects an extremely high frequency of
project management turnover in the execution phase of a
project. Based on the survey, it was recognized that a net
negative impact on a project is the true concern when a
project manager departs a project. RPM primarily occurs
as a result of the project manager departing a project of
their own accord, predominantly motivated by career
opportunities. The departure of the project manager results
in a net negative effect, negatively impacting vital key
areas of project management that facilitate project success.
The project management areas impacted, in sequence
from the highest ranked negatively impacted area to the
lowest, are communication (85%), project schedule and
performance (73%), documentation and information
sharing (69%), client’s trust (65%), project risk (54%),
team motivation (54%) and cost and cash flow (27%).
The requirement for selecting the appropriate project
manager in the early stages of a project is critical.
However, the selected project manager requires motivation
to see the project through from conception to conclusion.
Organizations should consider ways to motivate the project
manager, including personal skills development and/or
monetary incentives to mitigate RPM and the effects it
could potentially have on project success. A study
conducted by [11] suggests that cash rewards are the
highest ranked forms of recognition.
B. Recommendations
The qualitative research approach focused on a single
case study in which the project under examination had
experienced a net negative effect. It is recommended that
similar case studies be investigated and compared to the
outcomes of this case study. Further analysis of the cause-
and-effect of RPM, the interdependent areas of project
management affected downstream and the project risk
associated with RPM, particularly adapted to a customized
Ishikawa or “fishbone” diagram, would be an interesting
topic for future investigation.
The survey presented interesting results on a high level
of RPM. It would be of interest to further determine the
impact of RPM and categorize the outcomes as a function
of the organizational structure type implemented in EPC
and EPCM industries. Quantitative research can be carried
out to further investigate all circumstances of RPM to an
elaborate level of analysis.
ACKNOWLEDGMENT
I would like to thank Professor JHC Pretorius for his
assistance and guidance in the completion of this
document. I would further like to express my gratitude
towards all participants who took the time and effort to
complete the questionnaire for the quantitative research
analysis.
REFERENCES
[1] S. Parker and R. Skitmore, “Project Management Turnover:
Cause and Effects on Project Performance,” International
Journal of Project Management, vol. 23, no. 3, pp. 205-
214, 2005.
[2] Economist Intelligence Unit, “Closing the Gap: The Link
between Project Management Excellence and Long-Term
Success,” New York, 2009.
[3] KcKinsey and Company, “Building Organisational
Capabilities: KcKinsey Global Survey Results,” March
2010. [Online]. Available:
http://www.mckinsey.com/insights/organization/building_
organizational_capabilities_mckinsey_global_survey_resu
lts. [Accessed 9 May 2015].
[4] J. Meredith and S. Mantel Jr, Project Management, A
Managerial Approach, 7th Ed, New York: John Wiley &
Sons, Inc, 2009.
[5] C. Gray, S. Dworatschek, D. Gobeli, H. Knoepfel and E.
Larson, “International Comparison of Project
Organizational Structures: Use and Effectiveness,”
International Journal of Project Management, vol. 8, no.
1, pp. 26-32, 1990.
[6] PMI, Project Management Body of Knowledge, 5th Ed,
Pennsylvania: Project Management Institute, Inc, 2013.
[7] T. Vartiainen, H. Aramo-Immonen and K. Liikamaa,
“Replacing Project Managers: Reasons of Replacement
Interpreted Through the Activity Theory,” pp. 1828-1835.
[8] T. Abdel-Hamid, “Investigating the Impacts of Managerial
Turnover/Succession on Software Project Performance,”
Journal of Management Information Systems, vol. 9, no. 2,
pp. 127-144.
[9] R. Chapman, “The Role of System Dynamics in
Understanding the Impact of Changes to Key Personnel on
Design Production within Construction Projects,”
International Journal of Project Management, vol. 16, no.
4, pp. 235-247, 1998.
[10] F. Höffler and D. Sliwka, “Do New Brooms Sweep Clean?
When and Why Dismissing a Manager Increases the
Subordinates' Performance,” European Economic Review,
vol. 47, no. 5, pp. 877-890, 2003.
[11] D. J. Hancock, “What Value Does Money Play in the
Motivation of 'Knowledge Workers' such as Project
Managers,” IEEE International, 2006.

More Related Content

What's hot

Duncan.william
Duncan.williamDuncan.william
Duncan.william
NASAPMC
 
Risk.panel handout
Risk.panel handoutRisk.panel handout
Risk.panel handout
NASAPMC
 
Essentials of Project Management
Essentials of Project ManagementEssentials of Project Management
Essentials of Project Management
Living Online
 
Romeo.mitchell
Romeo.mitchellRomeo.mitchell
Romeo.mitchell
NASAPMC
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jim
NASAPMC
 
Pressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsPressman ch-21-project-management-concepts
Pressman ch-21-project-management-concepts
seethaveera
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.k
NASAPMC
 
Presentatio Pmi
Presentatio PmiPresentatio Pmi
Presentatio Pmi
bhuphender
 
Managing scope creep in IT projects
Managing scope creep in IT projectsManaging scope creep in IT projects
Managing scope creep in IT projects
Himanshu Prabhakar
 

What's hot (20)

Duncan.william
Duncan.williamDuncan.william
Duncan.william
 
Risk.panel handout
Risk.panel handoutRisk.panel handout
Risk.panel handout
 
Essentials of Project Management
Essentials of Project ManagementEssentials of Project Management
Essentials of Project Management
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 
Romeo.mitchell
Romeo.mitchellRomeo.mitchell
Romeo.mitchell
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jim
 
Pressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsPressman ch-21-project-management-concepts
Pressman ch-21-project-management-concepts
 
Project management fundamentals
Project management fundamentalsProject management fundamentals
Project management fundamentals
 
Project Management
Project ManagementProject Management
Project Management
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.k
 
Hr Management
Hr ManagementHr Management
Hr Management
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideas
 
Self test engine PSP-PMI-SP
Self test engine PSP-PMI-SPSelf test engine PSP-PMI-SP
Self test engine PSP-PMI-SP
 
Presentatio Pmi
Presentatio PmiPresentatio Pmi
Presentatio Pmi
 
Managing scope creep in IT projects
Managing scope creep in IT projectsManaging scope creep in IT projects
Managing scope creep in IT projects
 
Chap008
Chap008Chap008
Chap008
 

Similar to Investigating the Effects of Replacing the Project Manager during Project Execution 2016

Agile methodologies in_project_management
Agile methodologies in_project_managementAgile methodologies in_project_management
Agile methodologies in_project_management
Pravin Asar
 
Pm600 1103 a-02-schwappach-loren-p1-t3
Pm600 1103 a-02-schwappach-loren-p1-t3Pm600 1103 a-02-schwappach-loren-p1-t3
Pm600 1103 a-02-schwappach-loren-p1-t3
Loren Schwappach
 
C19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docx
C19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docxC19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docx
C19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docx
chestnutkaitlyn
 
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...
International Journal of Technical Research & Application
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docx
write22
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docx
write31
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)
Rintu Das
 
3The Project Management ProcessGroups A Case StudyAft.docx
3The Project Management ProcessGroups A Case StudyAft.docx3The Project Management ProcessGroups A Case StudyAft.docx
3The Project Management ProcessGroups A Case StudyAft.docx
gilbertkpeters11344
 

Similar to Investigating the Effects of Replacing the Project Manager during Project Execution 2016 (20)

The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
UNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project managementUNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project management
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project Success
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
Agile methodologies in_project_management
Agile methodologies in_project_managementAgile methodologies in_project_management
Agile methodologies in_project_management
 
Bluedog White Paper - Fix Broken Projects.pdf
Bluedog White Paper - Fix Broken Projects.pdfBluedog White Paper - Fix Broken Projects.pdf
Bluedog White Paper - Fix Broken Projects.pdf
 
Pm600 1103 a-02-schwappach-loren-p1-t3
Pm600 1103 a-02-schwappach-loren-p1-t3Pm600 1103 a-02-schwappach-loren-p1-t3
Pm600 1103 a-02-schwappach-loren-p1-t3
 
C19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docx
C19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docxC19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docx
C19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docx
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
PMC4
PMC4PMC4
PMC4
 
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docx
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docx
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)
 
3The Project Management ProcessGroups A Case StudyAft.docx
3The Project Management ProcessGroups A Case StudyAft.docx3The Project Management ProcessGroups A Case StudyAft.docx
3The Project Management ProcessGroups A Case StudyAft.docx
 
Project Management
Project ManagementProject Management
Project Management
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
Mega project not mega problems session 1
Mega project not mega problems session 1Mega project not mega problems session 1
Mega project not mega problems session 1
 
12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management Fundamentals12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management Fundamentals
 

Recently uploaded

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 

Recently uploaded (20)

Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 

Investigating the Effects of Replacing the Project Manager during Project Execution 2016

  • 1. Investigating the Effects of Replacing the Project Manager during Project Execution RJ Dubber1 , JHC Pretorius2 1 Faculty of Engineering and the Built Environment, Postgraduate Student, University of Johannesburg, Johannesburg, South Africa, rjdubber@gmail.com 2 Faculty of Engineering and the Built Environment, Head of School: Postgraduate School of Engineering Management, University of Johannesburg, Johannesburg, South Africa jhcpretorius@uj.ac.za Abstract - It is a setback that many projects face and senior management fear, that a well-run project heading for success can take a turn for the worst when the project manager is replaced as a result of resignation or transfer. The replacement of the leader and foundation of the project can result in poor management of the triple constraint (scope, time and budget), loss of historical project information, as well as cause a ripple effect of conflict, confusion, misunderstanding and poor team spirit within the project team. The term “replacing the project manager” or “RPM” should be easily recognized by organizations, yet, there is very little documentation available discussing this common issue. The frequency of replacement, the circumstances in which the project manager is replaced, and the effect it has on a project during execution is investigated. Keywords - project manager, replacing the project manager (RPM), project execution, engineering, procurement and construction (EPC), engineering, procurement and construction management (EPCM) I. INTRODUCTION Project management is a growing profession in all industries and there is much literature on the subject. The correct implementation of the principles of project management is, however, more difficult in practice. This, together with different individual personalities, interests and capabilities almost guarantees the assertion that replacing the project manager (RPM) is not a simple procedure. RPM can cause major disruption to the project from both an employer and employee perspective. Investigating the effects of RPM during project execution identifies the frequency of RPM, the circumstances in which the project manager is replaced, and the effect on a project in terms of project management principles. Guidelines to facilitate the handover to limit the impact on a project as a result of RPM are proposed and investigated. A. Introducing and Defining RPM Many believe that employee turnover can be beneficial for an organization in terms of development and career opportunities [1]. However, changes in management personnel have been found by many to have a significant negative effect on project performance. A survey carried out by [1] revealed the following: • 97% strongly agreed that project managers are critical to project success; • 85% disagreed that project management turnover has no effect on project performance, and • Project management turnover occurs primarily in the execution phase of the project life cycle, increasing risk, cost and the probability of project failure. Project managers are critical to project management success and limited research has been undertaken to ascertain the percentage of project managers who maintain the position from project initiation to close-out. B. Rationale of the Research A report published by [2] concluded that 90% of global senior executives ranked project management methods as either critical or somewhat important to their ability to deliver successful projects and remain competitive. Furthermore, a survey carried out by [3] yielded 60% of senior executives stating that building a strong project management discipline is a top-three priority for their companies. There is a rapid growth in project-orientated firms (projectized organizational structures) [4]. An international study conducted by [5] confirms that project matrix (strong matrix) and projectized structures are perceived as the most effective across all types of projects. As indicated in Figure 1, project managers in these structures have high authority, manage the project budget and are dedicated full-time to a project. Figure 1: Influence of organizational structures on projects [6]
  • 2. The project manager is therefore the nucleus of a project, which highlights the need for organizations to identify RPM and recognize the effects, consequences and the requirement for mitigation and cautious management. C. Problem Statement and Research Objectives Guidelines to carry out project management, tailored to suit the industry in which it is practiced, are well documented. The literature focuses particularly on project management and managers, their roles and responsibilities, and how critical they are during the project process. Information that is not often documented or portrayed as an integral part of a project life cycle is the effect of RPM during project execution. RPM has a net effect on a project – either positive or negative (and in very few instances neutral). The influence of RPM is not well understood, neither documented nor assessed in great detail. This information is critical to the project management process and ensuring project success in cases where RPM is experienced. The research objectives were to identify the frequency of replacing the project manager, the circumstances in which the project manager is replaced, and the effect on a project in terms of project management principles. Guidelines to facilitate the handover to limit the impact on a project were also proposed and investigated. II. METHODOLOGY Qualitative and quantitative research methodologies were implemented in order to fulfil the research objectives. The methodologies were individually investigated to determine the most effective research approach to satisfy the research objectives. A. Case Study – Qualitative Research Approach A descriptive case study type was selected for the qualitative research method. The case study was presented through the eyes of the author who, as a project engineer in an engineering, procurement and construction (EPC) organization, experienced the effects of RPM during the execution phase of a project. The findings of the descriptive case study should be considered as preliminary rather than conclusive as no data analysis techniques were implemented. A world-renowned gold mining company required a new cyanide make-up facility and piping distribution network at one of its existing gold-processing plants in Ghana, West Africa. The upgrade was necessary as the existing cyanide system did not meet with the International Cyanide Management Code (ICMI). Strict deadlines were put in place as the plant audit and compliance review was under pressure from external governmental factors. The remeasurable contract was based on the supply, manufacturing and installation of structural, mechanical, plate work and piping (SMPP) as well as electrical and instrumentation (E&I) governed by the FIDIC Conditions of Contracts for Construction – The Red Book. In the initial stages of construction, the project manager resigned and a new project manager was appointed. The newly appointed project manager had previously been in the operations side of the organization with no contractual experience. The organizational structure was projectized and the involvement of the initial project manager was full-time. However, the new project manager was site-based and only partially involved in the day-to-day construction operations, with the scope, schedule and budget managed remotely by the appointed project engineer. Furthermore, no official handover was initiated by either project manager – resigned project manager out, new project manager in. The project was negatively affected, with deteriorated project schedule and performance, an increase in cost and project risk, loss of information, and weakened communication and project team morale. The project is summarized in Table 1 with the initial and final results as indicated. Table 1: Case study project summary B. Survey – Quantitative Research Approach A quantitative research approach was selected to determine the effects of RPM during project execution as literature has shown that RPM is a known phenomenon with few studies discussing this issue [7]. The case study provides a preliminary investigation based on the author’s experience and a quantitative research approach permits further investigation. A questionnaire was designed for the distribution and collection of data for analysis. The questionnaire was designed to limit the number of questions and reduce the overall time required to complete the survey. The decision to limit the questionnaire and maintain simplicity was taken with the intention of motivating potential respondents to complete the survey. III. RESULTS A. Demographics of the Survey The survey population was selected by means of LinkedIn, a professional social network. South African project houses providing engineering, procurement and construction (EPC), as well as engineering, procurement and construction management (EPCM) services to the mining industry were targeted.
  • 3. The total number of respondents (100%, n=45), with an overall achieved response rate of 56% was made up of senior management totaling 22% (n=10), project managers totaling 36% (n=16) and project team members making up 42% (n=19). The respondents’ professional capacities are indicated in Figure 2. Respondents’ Professional Capacities Figure 2: Percentage distribution of respondents’ professional capacities The industries in which the respondents are currently active are predominantly the mining industry (53%, n=24), followed by “other”, comprising 22% of the total respondents, who are involved in EPC or EPCM business models. The targeted industries are indicated in Figure 3. Targeted Industries Figure 3: Percentage distribution of respondents’ industries The majority of the respondents (31%, n=14) had five to 10 years’ experience in the industry in which they are currently active. The respondents’ industry experience is indicated in Figure 4. Respondents’ Industry Experience Figure 4: Percentage distribution of respondents’ industry experience B. Overview of the RPM Survey The results of the web-based survey yielded 93% (n=42) of respondents experiencing RPM in the work place – an extremely high frequency of project management turnover in the execution phase of a project. The survey confirmed that career motives (48%, n=20) followed by “other” (24%, n=10) are the major motives for the project manager relieving his/her duties on a project. “Other” is attributed to a client’s request for removing the project manager from a project as a result of poor performance or a bitter relationship. The company culture and/or structure has quite a big effect on a project manager departing a project with 19% (n=8) share and a high stress environment playing a very small role (7%, n=3). Figure 5 graphically presents the percentage distribution for the motives of a project manager to depart a project during project execution. Motives for Project Manager Departure Figure 5: Percentage distribution of respondents’ motives for a project manager departing a project The net effect on a project as a result of RPM was identified and two classes disclosed: 1. The project manager had to be replaced in order to rescue a troubled project and resulted in a net positive effect. 2. The project manager resigned and was replaced reluctantly by the organization and resulted in a net negative effect. The results yielded 31% of respondents identifying RPM with a net positive effect compared to 62% of respondents identifying RPM with a net negative effect – a major stake in the results. A net positive effect corresponds to the motive “other” in Figure 5 identified to be a client’s request for RPM which is only experienced under irregular circumstances that could be identified and possibly corrected in the early stages of a project. A net negative effect as a result of the project manager departing a project of their own accord for prospective career motives identified in Figure 5 is the real concern. Figure 6 graphically presents the cumulative percentage distribution for the positive and negative impacted areas of project management on a project as a result of RPM. An assumption was made that the project deliverables in terms of quality are not compromised through RPM i.e. the final product is always within the set quality parameters upon project handover.
  • 4. Impact of RPM on a Project Figure 6: Cumulative percentage distribution of responses to impacted areas as a result of RPM The project management areas impacted, in sequence from the highest ranked positively impacted area to the lowest, are client’s trust (92%), project schedule and performance (69%), communication (62%), team motivation (62%), documentation and information sharing (46%), project risk (31%) and cost and cash flow (8%). The project management areas impacted, in sequence from the highest ranked negatively impacted area to the lowest, are communication (85%), project schedule and performance (73%), documentation and information sharing (69%), client’s trust (65%), project risk (54%), team motivation (54%) and cost and cash flow (27%). The controls to minimize the impact of RPM and facilitate the handover between the replaced project manager and the replacement project manager are indicated in Figure 7. Controls to Facilitate Handover Figure 7: Cumulative percentage distribution of responses to facilitate RPM to reduce impact on a project The most effective controls were identified as including a senior project leader in all communications (71%), document control (67%), project management office (PMO) (38%) and “other” (18%) identified as implementing a sufficient handover period. IV. DISCUSSION The conducted survey identifies that RPM during project execution is a common phenomenon. Furthermore, the survey results indicate a tendency of RPM to have a net negative effect on a project when a successful project manager leaves for personal growth. RPM and the negative effect it could potentially have on a project as a result of the project manager departing a project of their own accord, is the real concern. With the movement into projectized organizations and the associated responsibilities of the project manager, organizations should want to mitigate and manage RPM before it transpires and impacts on interdependent project management areas and project outcomes. The controls to facilitate the handover were found to be the most effective measures to reduce the impact of RPM, should it transpire. However, project management maturity and the ineffective implementation of the PMO as a tool to move forward from individual dependency into project management processes by means of organizational policies and procedures should be considered a vital step towards reducing the negative effects of RPM. V. CONCLUSION A. Summary of Findings RPM, a form of managerial turnover, will almost always have an effect on a project outcome. The topic “Investigating the Effects of Replacing the Project Manager during Project Execution” was identified to be a critical subject with little information addressing the issue. Literature identifies the fact that the maximum effort is required during the execution phase of a project, verifying the vulnerability of a project during this stage should RPM take place. Journals and documented surveys carried out by [1], [7], [8], [9] and [10] confirm that RPM is a high risk issue, primarily occurring in the execution phase of the project life cycle, increasing risk, cost and the probability of project failure. The case study identified that the net effect on a project during RPM is negative, with emphasis on the identified key areas of project management. The case study provided a preliminary investigation based on the author’s experience and a quantitative research approach followed in the form of a web-based survey to permit further investigation. The following summary is deducted from the responses to the survey: • 93% confirmed having experienced RPM in their work environment; • 48% confirmed that career motives are the main drive for the project manager departing a project; • 31% confirmed that RPM has a net positive effect on a project;
  • 5. • 62% confirmed that RPM has a net negative effect on a project; • 71% confirmed that including a senior project leader in all communications is the best control to facilitate a project handover, and • 100% agreed that a project manager’s role in project success is important or very important (four and five on a Likert scale). The survey reflects an extremely high frequency of project management turnover in the execution phase of a project. Based on the survey, it was recognized that a net negative impact on a project is the true concern when a project manager departs a project. RPM primarily occurs as a result of the project manager departing a project of their own accord, predominantly motivated by career opportunities. The departure of the project manager results in a net negative effect, negatively impacting vital key areas of project management that facilitate project success. The project management areas impacted, in sequence from the highest ranked negatively impacted area to the lowest, are communication (85%), project schedule and performance (73%), documentation and information sharing (69%), client’s trust (65%), project risk (54%), team motivation (54%) and cost and cash flow (27%). The requirement for selecting the appropriate project manager in the early stages of a project is critical. However, the selected project manager requires motivation to see the project through from conception to conclusion. Organizations should consider ways to motivate the project manager, including personal skills development and/or monetary incentives to mitigate RPM and the effects it could potentially have on project success. A study conducted by [11] suggests that cash rewards are the highest ranked forms of recognition. B. Recommendations The qualitative research approach focused on a single case study in which the project under examination had experienced a net negative effect. It is recommended that similar case studies be investigated and compared to the outcomes of this case study. Further analysis of the cause- and-effect of RPM, the interdependent areas of project management affected downstream and the project risk associated with RPM, particularly adapted to a customized Ishikawa or “fishbone” diagram, would be an interesting topic for future investigation. The survey presented interesting results on a high level of RPM. It would be of interest to further determine the impact of RPM and categorize the outcomes as a function of the organizational structure type implemented in EPC and EPCM industries. Quantitative research can be carried out to further investigate all circumstances of RPM to an elaborate level of analysis. ACKNOWLEDGMENT I would like to thank Professor JHC Pretorius for his assistance and guidance in the completion of this document. I would further like to express my gratitude towards all participants who took the time and effort to complete the questionnaire for the quantitative research analysis. REFERENCES [1] S. Parker and R. Skitmore, “Project Management Turnover: Cause and Effects on Project Performance,” International Journal of Project Management, vol. 23, no. 3, pp. 205- 214, 2005. [2] Economist Intelligence Unit, “Closing the Gap: The Link between Project Management Excellence and Long-Term Success,” New York, 2009. [3] KcKinsey and Company, “Building Organisational Capabilities: KcKinsey Global Survey Results,” March 2010. [Online]. Available: http://www.mckinsey.com/insights/organization/building_ organizational_capabilities_mckinsey_global_survey_resu lts. [Accessed 9 May 2015]. [4] J. Meredith and S. Mantel Jr, Project Management, A Managerial Approach, 7th Ed, New York: John Wiley & Sons, Inc, 2009. [5] C. Gray, S. Dworatschek, D. Gobeli, H. Knoepfel and E. Larson, “International Comparison of Project Organizational Structures: Use and Effectiveness,” International Journal of Project Management, vol. 8, no. 1, pp. 26-32, 1990. [6] PMI, Project Management Body of Knowledge, 5th Ed, Pennsylvania: Project Management Institute, Inc, 2013. [7] T. Vartiainen, H. Aramo-Immonen and K. Liikamaa, “Replacing Project Managers: Reasons of Replacement Interpreted Through the Activity Theory,” pp. 1828-1835. [8] T. Abdel-Hamid, “Investigating the Impacts of Managerial Turnover/Succession on Software Project Performance,” Journal of Management Information Systems, vol. 9, no. 2, pp. 127-144. [9] R. Chapman, “The Role of System Dynamics in Understanding the Impact of Changes to Key Personnel on Design Production within Construction Projects,” International Journal of Project Management, vol. 16, no. 4, pp. 235-247, 1998. [10] F. Höffler and D. Sliwka, “Do New Brooms Sweep Clean? When and Why Dismissing a Manager Increases the Subordinates' Performance,” European Economic Review, vol. 47, no. 5, pp. 877-890, 2003. [11] D. J. Hancock, “What Value Does Money Play in the Motivation of 'Knowledge Workers' such as Project Managers,” IEEE International, 2006.