CAREER PROFILE
My career profile includes nineteen (19) years of professional experience and in-depth knowledge
in Project Management, Construction Management, planning, monitoring and control, cost
estimation, Tenders preparation, development of procedures, Methods of Statements.
Specialized mainly in various projects in Oil and Gas Sector. Projects accomplished belongs to the
following categories: Greenfield, Brownfield, revamping’s, Shut Downs, Maintenance works,
Modules Design Fabrication and Off-shore works.
EMPLOYMENT OVERVIEW
ARCOMET RMC FZC UAE Technical Manager Nov 2014 – Present
BIOTEK S.A CYPRUS Project Manager Aug 2012 – Oct 2014
BIOTEK S.A GREECE Project Manager April 2004 – July 2012
BIOTEK S.A GREECE Construction Manager Sep 2002 – Mar 2004
BIOTEK S.A GREECE Construction engineer Apr 1997 - Aug 2002
SUMMARY OF EXPERTISE
 Developing detailed Project Schedules
 Establishing a cost and time control
system as per Project’s details (CPI, SPI,
Earned Value)
 Establishing of productivity control system
per activity
 Preparation of Project Budget and ensure
compliance
 Establishing and monitoring of Project’s
Quality System
 Contract Administration
 Establishing and monitoring of Project’s
Safety System
 Tenders Preparation, evaluation of sub-
contractors
 Cost Estimation and Budget Preparation
for Tenders
 Managing relationships with clients
 Close out reports of Projects with detailed
analysis of variations between Project’s
Budget and Project’s Final cost.
 Feed Back to Tendering Department of
the achieved Productivities and lessons
to learn for future Projects
DETAILED PROFESSIONAL EXPERIENCE
TECHNICAL MANAGER Nov. 2014 – Present
ARCOMET RMC FZC Ras Al Khaimah, UAE
ARCOMET, which was established on November 2014, is a sister company of ARCHIRODON ,one of the top
marine contractors internationally, who undertakes the construction of ports and harbors, jetties, terminals,
offshore structures, offshore pipelines, intakes and outfalls, dredging and reclamation and generally all types
of marine Infrastructure, oil and gas facilities, power plants, bridges, road and railroads and EKME S.A., one
of the top European companies in oil and gas construction sector of Pressure Vessels, Reactors, Heat
Exchangers , Process Units.
Joining to ARCOMET RMC FZC, my tasks were:
-Design, Construction of ARCOMET’s Fabrication – Modules Yard.
-Tenders preparation, Technical /Commercial negotiations and Selection of Subcontractors and equipment
suppliers of ARCOMET’s installations.
-Selection Recruitment of key Indirect Personnel (QA/QC and HSE Manager).
-Company certification according to DIN EN ISO 9001:2008, DIN EN ISO 14001:2009, BS OHSAS
18001:2007
-Company certification from ASME as a stamp holder of U, U2, PP, and S
-Company certification from N.B. as a stamp holder of R
-Tenders Preparation, with detailed Budget, execution plans and time schedules preparation.
-Execution of Projects
From November of 2014 up to the end of May 2016, all the above tasks have been successfully accomplished.
ARCOMET has under operation a modern Fabrication and Module Yard in an area of 67,000 sq. meters
equipped with PWHT Furnace, Grit Blasting and Painting Rooms, Bunker and two Fabrication Shops.
In parallel ARCOMET, from December 2015 is sub-contractor of ARCHIRODON for Al Dabb’iya Project
(3844- ADCO Al Dabb’iya Surface Facilities – Phase III), for the fabrication of Pipes, Pipes Supports including
Painting, Insulation Works, and Modularization Works (34 Pipe Rack Modules).
Client: Abu Dhabi Company for Onshore Petroleum Operations Ltd (ADCO), Tecnimont (EPC Contractor)
Role: Fabrication Manager
Key Responsibilities:
 Preparation detailed project schedule
 Preparation of detailed Budget
 Selection of tier subcontractors (technical and commercial negotiations – evaluations.
 Establishment and monitoring procedures of project progress (CPI, SPI, Earned Value).
 Establishment and monitoring procedures of productivity factors
 Establishment of reporting system to BoD and to client
 Establishment of QA/QC Plan
 Establishment of HSE Plan
 Establishment of Detailed Execution Plan
 Preparation of Method of Statements, Procedures, TRA’s.
 Recruitment of Direct Personnel from India and Philippines.
 Recruitment of Key Indirect Personnel as per Project’s Organization Chart
PROJECT MANAGER April 2004 – October 2014
From the 17 years I was in BIOTEK S.A. the last ten years I was the Technical Manager of the
company and the Project/Site Manager of the most important projects.
Key Responsibilities:
 Preparation detailed projects schedule
 Preparation of detailed Budget
 Selection of tier subcontractors (technical and commercial negotiations – evaluations.
 Establishment and monitoring procedures of productivity factors
 Establishment of reporting system to BoD and to client
 Establishment of QA/QC Plans
 Establishment of HSE Plans
 Establishment of Detailed Execution Plan
 Preparation of Method of Statements, Procedures, TRA’s.
 Management of Projects executed in parallel
 Tenders Preparation
Key Projects:
Project: VTT Vasiliko Oil Terminal and Jetty at Vasiliko Cyprus
Client: VTTV
EPC Contractor: J&P and J&P (O) Vasiliko Oil Tank JV
Sub-Contractor: BIOTEK S.A.
Scope: All Mechanical Top Side Works
Duration: August 2012 – October 2014
Project’s Details:
Project Scope was the construction and installation of a 1.5 km Jetty’s Superstructure and relevant
Topside Facilities (Piping, Mechanical, Fire Fighting System facilities, Equipment installation on the
Jetty, painting and insulation works).
The Jetty Superstructure was consisting of a 1485 long steel trestle and two lateral 200 m and 226
m branch trestles, totally made of 42Nos pre-fabricated and pre-assembled Trestle-modules, all to
be erected finally in situ on concrete pile caps. For piping expansion also other 9 trestles-modules
pre-assembled and erected.
Modules were erected with all piping, supports, cable trays and driving lanes. Except the trestles in
project’s scope was also the erection of all top side facilities on three concrete platforms. T-platform,
platform 1-2 and platform 3-4. Except piping and steel structure works, on platforms we erected-
installed Access Gangways, Catwalks, Loading Arms, Pumps.
The weights of Jetty were 3,700 tons of Steel Structure, 2,800 tons of piping (77.000 dia inches),
300 tons of pipe supports.
Trestles sizes were maximum 45 meters length, 5 meters width and 5 meters height. Weight of
trestles were from 90 to 150 tons.
Fabrication and Erection works duration was 18 months (from May 2013 up to October 2014).
Total Man-hours: 430,000
Peak: 230 persons (direct)
Project: Unit 32 Flexi-Coker, Elefsina Refinery, Athens, Greece
Client: HELLENIC PETROLEUM
EPCM: TECNICAS REUNIDAS
Contractor: JV Terna S.A. 0 Sices Construction S.p.A.
Tier Sub-Contractor: BIOTEK S.A.
Scope: Piping Works
Duration: July 2010 – August 2012
Project’s Details:
Project Scope was the prefabrication – erection of all piping networks in a new Flexi-coking Unit
except steam tracing, erection of prefabricated Pipe Supports.
The total weight of Piping was 2,670 tons. Out of the 2670 tons of piping, 2,390 tons were CS, 80
tons SS 316 and 200 tons alloy P5.
In terms of dia inches, the total number of welded dia inches were 355,000.
Total Man-hours: 850,000
Peak: 480 persons (direct)
Project: 2279_ NEW CDU COMPLEX
Client: MOTOR OIL HELLAS S.A.
EPCM: TECHNIP ITALY
Contractor: BIOTEK S.A.
Scope: Erection of Desulphurization Units.
Duration: March 2009 – July 2010
Project’s Details:
Units: 6700/ 6800/ 8300/ 7750/ 9800
Project Scope was the execution of the installation of Mechanical Equipment (850 tons), Steel
Structure (510 tons), Piping Prefabrication and Erection (1,150 tons), Pre-commissioning and Start
Up assistance. In terms of dia inches, the total number of welded dia inches were 135,000.
Total Man-hours: 446,884
Peak: 325 persons (direct)
Due to successful completion of the Project, we have been awarded by the Client with the Contract
of the second Train.
Project Scope was the execution of the installation of Mechanical Equipment (239 tons), Steel
Structure (100 tons), Piping Prefabrication and Erection (170 tons), Pre-commissioning and Start
Up assistance. In terms of dia inches, the total number of welded dia inches were 35,000.
Total Man-hours: 446,884
Peak: 325 persons (direct)
Project: ULSADO UNIT REVAMPING ERECTION ACTIVITIES
Client: HELLENIC PETROLEUM
ECM: ASPROFOS S.A.
Contractor: BIOTEK S.A.
Scope: Revamping of Ulsado Unit
Duration: 2008 – 2009
Project’s Details:
Units: 9200
Project Scope was the revamping of existing Unit. Activities performed with the Unit under operation
and they concluded during a Shut Down. In detail scope was the execution of the installation of
Mechanical Equipment (235 tons), Piping Prefabrication and Erection (213 tons), Electrical,
Instrumentation, Painting, Insulation Works, Pre-commissioning and Start Up assistance.
Total Man-hours: 59,128
Peak: 130 persons (direct)
Project: ERECTION WORKS TO THE FCC NAPHTHA DESULPHURIZATION UNIT 9200
Client: HELLENIC PETROLEUM
ECM: ASPROFOS S.A.
Contractor: BIOTEK S.A.
Scope: Erection of Desulphurization Unit 9200
Duration: 2006 – 2008
Project’s Details:
Units: 9200
Project Scope was the execution of the installation of Mechanical Equipment (750 tons), Piping
Prefabrication and Erection (650 tons), Electrical, Instrumentation, Painting, Insulation Works, Pre-
commissioning and Start Up assistance. In terms of dia inches, the total number of welded dia
inches were 117,000.
Total Man-hours: 180,000
Peak: 75 persons (direct)
(Attached detailed list of Projects per Category)
QUALIFICATION
Bachelor of Chemical Engineering Licensed Chemical Engineer
Polytechnic School
Aristotelio University
Greece
ORGANIZATIONS AND AFFILIATIONS
Member of Technical Chamber of Greece
PERSONAL DATA
Age: 48 years old Gender: Male
Date of Birth: March 13, 1968 Religion: Christian Orthodox
Nationality: Greek

More Related Content

What's hot (19)

MIDEL C resume013[1] (1)
MIDEL C resume013[1] (1)MIDEL C resume013[1] (1)
MIDEL C resume013[1] (1)
 
Arun Resume .
Arun Resume .Arun Resume .
Arun Resume .
 
S nikkhah CV Oil Gas CSG LNG
S nikkhah CV Oil Gas CSG LNGS nikkhah CV Oil Gas CSG LNG
S nikkhah CV Oil Gas CSG LNG
 
Amjad survey inspector
Amjad survey inspectorAmjad survey inspector
Amjad survey inspector
 
CV Abd. Hadi Ahmad
CV Abd. Hadi AhmadCV Abd. Hadi Ahmad
CV Abd. Hadi Ahmad
 
Hisham Resume ( CV )
Hisham Resume ( CV )Hisham Resume ( CV )
Hisham Resume ( CV )
 
curr. vitae
curr. vitaecurr. vitae
curr. vitae
 
Structural Engineer
Structural EngineerStructural Engineer
Structural Engineer
 
Ghufran Resume 2015 a
Ghufran Resume 2015 aGhufran Resume 2015 a
Ghufran Resume 2015 a
 
Cv Presentation
Cv PresentationCv Presentation
Cv Presentation
 
Resume Jamilatul Adawiah Rev.6
Resume Jamilatul Adawiah Rev.6Resume Jamilatul Adawiah Rev.6
Resume Jamilatul Adawiah Rev.6
 
Hisham.cv
Hisham.cvHisham.cv
Hisham.cv
 
Dnyaneshwar_Sonawane CV
Dnyaneshwar_Sonawane CVDnyaneshwar_Sonawane CV
Dnyaneshwar_Sonawane CV
 
Cv kanysh komyshev_21_12_2018
Cv kanysh komyshev_21_12_2018Cv kanysh komyshev_21_12_2018
Cv kanysh komyshev_21_12_2018
 
CV.Eng Ashraf Abdulsalam(2016)
CV.Eng Ashraf Abdulsalam(2016)CV.Eng Ashraf Abdulsalam(2016)
CV.Eng Ashraf Abdulsalam(2016)
 
Kleynhans Claudius - Senior Project Manager R
Kleynhans Claudius - Senior Project Manager RKleynhans Claudius - Senior Project Manager R
Kleynhans Claudius - Senior Project Manager R
 
Sunil-CV-Latest
Sunil-CV-LatestSunil-CV-Latest
Sunil-CV-Latest
 
NM SM
NM SMNM SM
NM SM
 
NEW UPDATE CV QC ROTATING & STATIC
NEW UPDATE CV QC ROTATING & STATICNEW UPDATE CV QC ROTATING & STATIC
NEW UPDATE CV QC ROTATING & STATIC
 

Similar to Salakidis Savvas

Similar to Salakidis Savvas (20)

Yahia Eisa- pipeline technical specialist
Yahia Eisa- pipeline technical specialistYahia Eisa- pipeline technical specialist
Yahia Eisa- pipeline technical specialist
 
KWKCV16
KWKCV16KWKCV16
KWKCV16
 
Resume
ResumeResume
Resume
 
Yeoh KS CV Rev 1
Yeoh KS CV Rev 1Yeoh KS CV Rev 1
Yeoh KS CV Rev 1
 
PLB Format CV Updated 16-03-2015
PLB Format CV Updated 16-03-2015PLB Format CV Updated 16-03-2015
PLB Format CV Updated 16-03-2015
 
Khaled CV
Khaled CVKhaled CV
Khaled CV
 
CV Updated 8-10-16
CV Updated 8-10-16CV Updated 8-10-16
CV Updated 8-10-16
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017
 
Ahmed El- Kholy CV
Ahmed El- Kholy CVAhmed El- Kholy CV
Ahmed El- Kholy CV
 
Ramy Emad C.V Project Engineer
Ramy Emad C.V Project EngineerRamy Emad C.V Project Engineer
Ramy Emad C.V Project Engineer
 
CV Updated
CV UpdatedCV Updated
CV Updated
 
Khaled HSE
Khaled HSEKhaled HSE
Khaled HSE
 
MS CV May 2016
MS CV May 2016MS CV May 2016
MS CV May 2016
 
Trevor Kemp CV - January 2015
Trevor Kemp CV - January 2015Trevor Kemp CV - January 2015
Trevor Kemp CV - January 2015
 
my_cv_WP
my_cv_WPmy_cv_WP
my_cv_WP
 
updated CVlarrybisa
updated CVlarrybisaupdated CVlarrybisa
updated CVlarrybisa
 
Adly CV111
Adly CV111Adly CV111
Adly CV111
 
CV of broosto -7-2016
CV of broosto -7-2016CV of broosto -7-2016
CV of broosto -7-2016
 
Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017
 

Salakidis Savvas

  • 1. Savvas Salakidis. Job Classification : Project Manager Primary Discipline : Oil and Gas Present Address : Marjan Islands, Fairuz Block 505 Ras Al Khaimah, United Arab Emirates Mobile No. : (+971) 0564550381 Email Address : s.salakidis14@gmail.com CAREER PROFILE My career profile includes nineteen (19) years of professional experience and in-depth knowledge in Project Management, Construction Management, planning, monitoring and control, cost estimation, Tenders preparation, development of procedures, Methods of Statements. Specialized mainly in various projects in Oil and Gas Sector. Projects accomplished belongs to the following categories: Greenfield, Brownfield, revamping’s, Shut Downs, Maintenance works, Modules Design Fabrication and Off-shore works. EMPLOYMENT OVERVIEW ARCOMET RMC FZC UAE Technical Manager Nov 2014 – Present BIOTEK S.A CYPRUS Project Manager Aug 2012 – Oct 2014 BIOTEK S.A GREECE Project Manager April 2004 – July 2012 BIOTEK S.A GREECE Construction Manager Sep 2002 – Mar 2004 BIOTEK S.A GREECE Construction engineer Apr 1997 - Aug 2002 SUMMARY OF EXPERTISE  Developing detailed Project Schedules  Establishing a cost and time control system as per Project’s details (CPI, SPI, Earned Value)  Establishing of productivity control system per activity  Preparation of Project Budget and ensure compliance  Establishing and monitoring of Project’s Quality System  Contract Administration  Establishing and monitoring of Project’s Safety System  Tenders Preparation, evaluation of sub- contractors  Cost Estimation and Budget Preparation for Tenders  Managing relationships with clients  Close out reports of Projects with detailed analysis of variations between Project’s Budget and Project’s Final cost.  Feed Back to Tendering Department of the achieved Productivities and lessons to learn for future Projects
  • 2. DETAILED PROFESSIONAL EXPERIENCE TECHNICAL MANAGER Nov. 2014 – Present ARCOMET RMC FZC Ras Al Khaimah, UAE ARCOMET, which was established on November 2014, is a sister company of ARCHIRODON ,one of the top marine contractors internationally, who undertakes the construction of ports and harbors, jetties, terminals, offshore structures, offshore pipelines, intakes and outfalls, dredging and reclamation and generally all types of marine Infrastructure, oil and gas facilities, power plants, bridges, road and railroads and EKME S.A., one of the top European companies in oil and gas construction sector of Pressure Vessels, Reactors, Heat Exchangers , Process Units. Joining to ARCOMET RMC FZC, my tasks were: -Design, Construction of ARCOMET’s Fabrication – Modules Yard. -Tenders preparation, Technical /Commercial negotiations and Selection of Subcontractors and equipment suppliers of ARCOMET’s installations. -Selection Recruitment of key Indirect Personnel (QA/QC and HSE Manager). -Company certification according to DIN EN ISO 9001:2008, DIN EN ISO 14001:2009, BS OHSAS 18001:2007 -Company certification from ASME as a stamp holder of U, U2, PP, and S -Company certification from N.B. as a stamp holder of R -Tenders Preparation, with detailed Budget, execution plans and time schedules preparation. -Execution of Projects From November of 2014 up to the end of May 2016, all the above tasks have been successfully accomplished. ARCOMET has under operation a modern Fabrication and Module Yard in an area of 67,000 sq. meters equipped with PWHT Furnace, Grit Blasting and Painting Rooms, Bunker and two Fabrication Shops. In parallel ARCOMET, from December 2015 is sub-contractor of ARCHIRODON for Al Dabb’iya Project (3844- ADCO Al Dabb’iya Surface Facilities – Phase III), for the fabrication of Pipes, Pipes Supports including Painting, Insulation Works, and Modularization Works (34 Pipe Rack Modules). Client: Abu Dhabi Company for Onshore Petroleum Operations Ltd (ADCO), Tecnimont (EPC Contractor) Role: Fabrication Manager Key Responsibilities:  Preparation detailed project schedule  Preparation of detailed Budget  Selection of tier subcontractors (technical and commercial negotiations – evaluations.  Establishment and monitoring procedures of project progress (CPI, SPI, Earned Value).  Establishment and monitoring procedures of productivity factors  Establishment of reporting system to BoD and to client  Establishment of QA/QC Plan  Establishment of HSE Plan  Establishment of Detailed Execution Plan  Preparation of Method of Statements, Procedures, TRA’s.  Recruitment of Direct Personnel from India and Philippines.  Recruitment of Key Indirect Personnel as per Project’s Organization Chart
  • 3. PROJECT MANAGER April 2004 – October 2014 From the 17 years I was in BIOTEK S.A. the last ten years I was the Technical Manager of the company and the Project/Site Manager of the most important projects. Key Responsibilities:  Preparation detailed projects schedule  Preparation of detailed Budget  Selection of tier subcontractors (technical and commercial negotiations – evaluations.  Establishment and monitoring procedures of productivity factors  Establishment of reporting system to BoD and to client  Establishment of QA/QC Plans  Establishment of HSE Plans  Establishment of Detailed Execution Plan  Preparation of Method of Statements, Procedures, TRA’s.  Management of Projects executed in parallel  Tenders Preparation Key Projects: Project: VTT Vasiliko Oil Terminal and Jetty at Vasiliko Cyprus Client: VTTV EPC Contractor: J&P and J&P (O) Vasiliko Oil Tank JV Sub-Contractor: BIOTEK S.A. Scope: All Mechanical Top Side Works Duration: August 2012 – October 2014 Project’s Details: Project Scope was the construction and installation of a 1.5 km Jetty’s Superstructure and relevant Topside Facilities (Piping, Mechanical, Fire Fighting System facilities, Equipment installation on the Jetty, painting and insulation works). The Jetty Superstructure was consisting of a 1485 long steel trestle and two lateral 200 m and 226 m branch trestles, totally made of 42Nos pre-fabricated and pre-assembled Trestle-modules, all to be erected finally in situ on concrete pile caps. For piping expansion also other 9 trestles-modules pre-assembled and erected. Modules were erected with all piping, supports, cable trays and driving lanes. Except the trestles in project’s scope was also the erection of all top side facilities on three concrete platforms. T-platform, platform 1-2 and platform 3-4. Except piping and steel structure works, on platforms we erected- installed Access Gangways, Catwalks, Loading Arms, Pumps. The weights of Jetty were 3,700 tons of Steel Structure, 2,800 tons of piping (77.000 dia inches), 300 tons of pipe supports. Trestles sizes were maximum 45 meters length, 5 meters width and 5 meters height. Weight of trestles were from 90 to 150 tons. Fabrication and Erection works duration was 18 months (from May 2013 up to October 2014).
  • 4. Total Man-hours: 430,000 Peak: 230 persons (direct) Project: Unit 32 Flexi-Coker, Elefsina Refinery, Athens, Greece Client: HELLENIC PETROLEUM EPCM: TECNICAS REUNIDAS Contractor: JV Terna S.A. 0 Sices Construction S.p.A. Tier Sub-Contractor: BIOTEK S.A. Scope: Piping Works Duration: July 2010 – August 2012 Project’s Details: Project Scope was the prefabrication – erection of all piping networks in a new Flexi-coking Unit except steam tracing, erection of prefabricated Pipe Supports. The total weight of Piping was 2,670 tons. Out of the 2670 tons of piping, 2,390 tons were CS, 80 tons SS 316 and 200 tons alloy P5. In terms of dia inches, the total number of welded dia inches were 355,000. Total Man-hours: 850,000 Peak: 480 persons (direct) Project: 2279_ NEW CDU COMPLEX Client: MOTOR OIL HELLAS S.A. EPCM: TECHNIP ITALY Contractor: BIOTEK S.A. Scope: Erection of Desulphurization Units. Duration: March 2009 – July 2010 Project’s Details: Units: 6700/ 6800/ 8300/ 7750/ 9800 Project Scope was the execution of the installation of Mechanical Equipment (850 tons), Steel Structure (510 tons), Piping Prefabrication and Erection (1,150 tons), Pre-commissioning and Start Up assistance. In terms of dia inches, the total number of welded dia inches were 135,000. Total Man-hours: 446,884 Peak: 325 persons (direct) Due to successful completion of the Project, we have been awarded by the Client with the Contract of the second Train. Project Scope was the execution of the installation of Mechanical Equipment (239 tons), Steel Structure (100 tons), Piping Prefabrication and Erection (170 tons), Pre-commissioning and Start Up assistance. In terms of dia inches, the total number of welded dia inches were 35,000. Total Man-hours: 446,884 Peak: 325 persons (direct)
  • 5. Project: ULSADO UNIT REVAMPING ERECTION ACTIVITIES Client: HELLENIC PETROLEUM ECM: ASPROFOS S.A. Contractor: BIOTEK S.A. Scope: Revamping of Ulsado Unit Duration: 2008 – 2009 Project’s Details: Units: 9200 Project Scope was the revamping of existing Unit. Activities performed with the Unit under operation and they concluded during a Shut Down. In detail scope was the execution of the installation of Mechanical Equipment (235 tons), Piping Prefabrication and Erection (213 tons), Electrical, Instrumentation, Painting, Insulation Works, Pre-commissioning and Start Up assistance. Total Man-hours: 59,128 Peak: 130 persons (direct) Project: ERECTION WORKS TO THE FCC NAPHTHA DESULPHURIZATION UNIT 9200 Client: HELLENIC PETROLEUM ECM: ASPROFOS S.A. Contractor: BIOTEK S.A. Scope: Erection of Desulphurization Unit 9200 Duration: 2006 – 2008 Project’s Details: Units: 9200 Project Scope was the execution of the installation of Mechanical Equipment (750 tons), Piping Prefabrication and Erection (650 tons), Electrical, Instrumentation, Painting, Insulation Works, Pre- commissioning and Start Up assistance. In terms of dia inches, the total number of welded dia inches were 117,000. Total Man-hours: 180,000 Peak: 75 persons (direct) (Attached detailed list of Projects per Category)
  • 6. QUALIFICATION Bachelor of Chemical Engineering Licensed Chemical Engineer Polytechnic School Aristotelio University Greece ORGANIZATIONS AND AFFILIATIONS Member of Technical Chamber of Greece PERSONAL DATA Age: 48 years old Gender: Male Date of Birth: March 13, 1968 Religion: Christian Orthodox Nationality: Greek