Engr Noor updated Cv for Senior Project Manager infrastructure and Roads
Dnyaneshwar_Sonawane CV
1. :E-mail sonawaneds@gmail.com :Website https://in.linkedin.com/in/dnyaneshwar-
sonawane-12470158
:Phone +966597307124 :Address 605 Humming Bird Pranji
Garden City Phase 1
Extension Katrap
Badlapur East
Thane 421503
RAMPED July 2015 — Present
Dnyaneshwar
Sonawane
Summary
A Civil Engineer with more than 10 yrs. of vast experience in infrastructure like Metro Stations, Road and Railway tunnels,
Bridges and Metro Rail viaduct structures and High rise buildings, Long span bridges. Industrial Building, Workshop, Control
center, etc. Metro viaduct, superstructures and substructures. Experience in site supervision, construction works. Experience
in prestressing detailed. Road and rail alignment drawings and geotechnical profile. Knowledge of construction methods and
construction sequences in civil structural constructions above or below the ground. Sound knowledge of site execution. Well
familiar with IRC, Indian Standards, British Codes and Euro Codes.
Work experience
Civil Inspector
Currently working in RAMPED ( Riyadh Advanced Metro Project Execution & Delivery ) as a Civil Inspector from July
2015 to till date.
Worked in The Louis Berger Group, Inc Mumbai India in Navi Mumbai Metro Rail Project as a Civil Site Engineer from
May 2012 to July 2015.
Worked in United New Designs & Project’s Pvt Ltd Mumbai as Civil Site Engineer from Oct 2009 to April 2012.
Worked in Virida Infra Projects & Pvt Ltd as Civil Site Engineer from Oct 2008 to Oct 2009.
Worked in Tech Unique Construwel Pvt Ltd as Civil Site Engineer from May 2006 to Oct 2008.
Riyadh Metro Alliance
Project :- Riyadh Metro Alliance Package 3
Consultant :- RAMPED
Client :- Arriyadh Development Authority ( ADA )
Joint venture of Louis Berger and Hill International has secured a $265m contract from the Arriyadh Development Authority
(ADA) to offer project management and construction management services for the new $22bn automated metro system in
Riyadh, Saudi Arabia.
The joint venture, called Riyadh Advanced Metro Project Execution and Delivery (RAMPED), is 55% owned by Louis Berger,
with the remaining 45% owned by Hill.
Dnyaneshwar Sonawane 1
2. RAMPED will act as an intermediary between ADA and the design-build contractors to oversee the design and construction
deliverables during the project execution.
Line 4 of the metro will connect to the King Khalid International Airport with a mix of elevated and at-grade sections, while Line
5 will run in a bored tunnel along King Abdulaziz Street, between King Abdulaziz Historical Centre and Riyadh Airbase.
Line 6 will be operated from King Abdullah Financial District via Iman Mohamed Bin Saud University to Prince Saad Ibn
Abdulrahman Al Awal Road.
Roles & Responsibilities:-
·To prepare drawings for construction methodology with alternative methods according to different site conditions and
construction sequences for precast and cast-in-situ super structure.
·Responsible for the Checking & Inspection of All Civil Structural Activities as per Raised IRF.
·Following up all construction work for underground station, Metro rail Tunnel using cut & cover method.
·Depot.
·Construction of sewerage Water Drain
·Conduct internal meetings with the collogues to exchange information.
·Ensure that adequate safety and quality international standard as mention on site.
·Monitoring contractor progress of work, controlling directing contractor for timely completion of the works in
accordance with the contractual requirements.
·Provide all necessary information on site direction and issue site instruction quality safety notice and ensure proper
rectification.
·Quality checking of construction material.
·Monitor the quality of work to ensure compliance with specification and contract documents.
·Preparation of daily, weekly and monthly progress report, man power report and comparing the same judge the status
of the project.
·Preparing contractor surveillance report.
·Monitor the progress of underground stations construction and report back to the Resident Engineer.
·Provide reports on safety, quality, environment, instrumentation.
·Ensure the Underground stations are constructed safely & to the highest standards.
·Ensure that quality & progress are effectively monitored throughout the program period.
·Attend progress meetings with management.
·Responsible for the regular inspection of precast elements installed by contractor on Concourse, Mezzanine & roof
level.
·Responsible for the compression slab on the precast elements.
·Responsible for the finishing activities i.e. hollow block work.
·Responsible for the under track slab.
·Responsible for the regular checking of compressive strength of concrete cylinders.
·Responsible for the for the utilities i.e. Storm water drainage systems & road drainage in viaduct.
·Prepare reports on the task requirements, strategies and inspection for assigned project.
·Ensure completion, accuracy and compliance of reports to standard engineering norms.
·Inspect drainage sites and make necessary investigations.
·Assign tasks to the team and oversee the contractors performance.
·Participate in multi-discipline projects in coordination with other company staff.
Navi Mumbai Metro
Project:- Navi mumbai Metro Rail
Consultant :-The Louis Berger Group Inc
Client :- CIDCO Maharashtra
Navi Mumbai Metro is a new mass rapid transit railway project under construction in the Indian state of Maharashtra. It is
aimed at connecting the suburbs of the city of Navi Mumbai. City and Industrial Development Corporation (Cidco) of
Maharashtra is developing the metro rail to meet commercial, industrial and residential needs of the metropolis.
Corridor one is a 28.3km railway line connecting Nerul and Belapur with Uran passing through Ranjanpada and Seawood.
Corridor two is a 21.45km stretch between Belapur and Khandeshwar, with a planned extension to the proposed Navi Mumbai
International Airport. It will run through Kalamboli, Taloje and Kharghar.
Dnyaneshwar Sonawane 2
3. Roles & Responsibilities:-
·Monitoring the piling, pile foundation works pile cap as per standard.
·QA /QC work & documentation.
·Monitoring the Elevated station works. Pier arm tie beams ,cantilever beam I girder casting and erection
·Monitoring Pile load test, vertical and lateral load test, Kent ledge method Dynamic load test, Anchoring method, sonic
test, and Integrity test.
·Executing the open foundation, stepped footing.
·Inspection of SW Drain in Depot area periphery around 4 Km.
·Executing the portal pier, platform beam.
·Executing the viaduct piers, Station pier corbel and platform piers, cantilever pier, portal pier, Hammer headed piers,
bearing pedestal.
·Monitor the program vs. Progress and achievement as per the target.
·Review the work in accordance with standard determined in the contractual project drawing and specification.
·Monitor the quality control and quality assurance field measurements and assist in compiling bill of quantities reports
for payment of quantities and change in the drawing.
·Prepare daily reports in accordance with the projects requirements.
·Attending the all safety work and safety implementation, safety training and safety internal audit safety review
meetings.
·Verifying field measurements providing documentation drawing verifications.
·Monitoring all construction work inspection of all documents. Construction work procedures, project quality plan and
document quality procedures quality assurance.
United New Designs Project Pvt Ltd
UNITED NEW DESIGNS PROJECT PVT LTD
Factory Project. Buildings & Godown RWHT Tank, WWTP
Contractor: - United New Designs Projects & Pvt Ltd Mumbai.
Consultant:- Structwel Mumbai
Client: - Godfrey Philips India Ltd
Roles & Responsibilities;-
·Site Execution.
·BBS Making.
·Contractors Billing.
·Prepare Daily Progress reports.
·Monthly Progress reports.
·Construction of Rain Water Harvesting Tank.
·Manholes of RWHT.
·Manholes of SWD.
·Construction of Waste Water treatment Plant
·Construction of sewerage Water Drain
·Construction of Periphery 2.3 Km Bitumen Road
·Quality Control & its Testing’s
·Site Execution.
·Road work QA / QC & it’s all testing’s.
·Laboratory tests.
·Field Tests.
·Taking Levels
·Reporting to Resident Engineer.
Virida Infra Projects & Pvt Ltd
Project :- LAVASA City
Dnyaneshwar Sonawane 3
4. Diploma In Civil Engineering Aug 2004 — July 2006
Consultant :- HCC Construction Company
Client:- LAVASA Corporation
Studio Apartments Projects:- Its Lavasa is a private, planned city being built near Pune. It is stylistically based on the
Italian town Portofino, with a street and several buildings bearing the name of that town.
A 25,000 acres (100 km2) or 8,000 acres (32 km-Sq ) project being developed by HCC. Construction Studios in hilly
area . 5 Nos of Studio apartments.
Roles & Responsibilities:-
·Site Execution.
·BBS Making.
·Contractors Billing.
·Prepare Daily Progress reports.
·Prepare monthly progress reports.
·Reporting To Project Manager.
Tech Unique Construwel
Project :- La Cresta
Contractor :- Tech-Unique Construwell Pvt Ltd
Client :- Paranjape Scheme Construction Pvt Ltd Pune
Roles & Responsibilities:-
·Site Execution.
·BBS Making.
·Daily Progress reports
·Labor management’s
·Reporting To Project Manager.
Qualifications
Persuing B-tech Civil Engineering from Monad University Hapur Uttar Pradesh
Diploma In Civil Engineering From MSBTE Mumbai in 2006
Matriculation Passed from SSC Nashik with 1st Div in 2003
Education
Government Polytechnic Dhule Maharashtra
Computer Skills:-
MS-office from MSBTE
MS-CIT from MSBTE
MS-Excel & MS-Word.
Profile as QC Member
Profile as a Q.C. Member:
Dnyaneshwar Sonawane 4
5. Responsible for checking of all site activities going on at site.
Responsible for batching plant operation and supply of good quality concrete to site & time to time trail for mix design.
Responsible for testing and inspection of cement, bricks, specific gravity, aluminium, steel rolling margin, crushing value,
10mm Agg., 20mm Agg. And sand analysis (impact value).
Responsible for maintaining project quality lab.
Responsible for carry of soil testing at site as well as lab.
Responsible for daily testing and documentation of all reports.
Responsible for soil testing in core cutter method, CBR and proctor test and sand replacement method.
Maintaining the ISO documentation for internal and external audit.
Making Schedules of IMS Audits & Well Known about Integrated Management System.
.
Site Management
Site management
Visiting on site construction activities to ensure the operations are carried out smoothly and resource are effectively utilized
maximum output.
Visiting the site regularly, during the course of construction to check proper implementation of design.
Preparing and reviewing of method statements and work specific quality, control plans.
Interests
Playing Cricket
Songs listening
Reading Books
PERSONAL DETAILS
Name: DNYANESHWAR SHIVAJI SONAWANE
Date of Birth: 20 thOCT 1983
Sex: Male
Nationality: Indian
Marital Status: Married
Languages Known: English, Hindi, and Marathi.
Mobile No India: +918652864500
Mobile No Saudi Arabia: +966597307124
Skype: dnyaneshwarssonawane
Passport Details: Passport No : M1923883
Date of Issue : 02/09/2014
Date of Expiry : 01/09/2024
Place of Issue : THANE
Thanking You
(Dnyaneshwar Sonawane)
Dnyaneshwar Sonawane 5