SlideShare a Scribd company logo
1 of 5
Curriculum Vitae
Page 1
Name: REGIDOR A. MANALO CV.
Proposed Position: Sub- Agent
Present Position:
Years of Experience:
Sub-Agent
22 Years
Currently Work Location: Macau Wynn Palace Project
1st of July 2014 –To Present (Sub-Agent)
Sub-Agent on Macau Wynn Palace (contract value of HK$20B) The project occupies a 21-hectares
site on the reclaimed land between the island of Taipa and Coloane. The scope of works for the
project includes ground and major foundation works together with the construction of luxury hotel with
2,000 rooms and a mixed-use podium comprising gaming, dining, retail and convention facilities, as
well as numerous specialist attraction including a 30,000 square metre performance lake that will
feature a light show.
Sub-Agent: Accountabilities and Responsibilities:
 Central plant construction: installation of all mechanical & Electrical equipment. Lifting and
skidding of 8 Nos. of 50ton water cooled chillers, huge Nos. of heavy heat pumps, boilers,
Vertical pumps, Lifting & skidding of 8Nos. of 21tons air cooler on the roof of central plant,
8Nos. of 20ton diesel generators & other equipment. Coordination with MEP Managers, civil
team, external team and podium team in regards for all mechanical, electrical and piping
installation in central plant.
 Appointed Person: Appointed by project director for all MEP site wide in terms of all electrical
and mechanical lifting and installation. e.g huge Nos. of transformer, RMU, AHU, MDB’S, &
huge LV & HV cable drums installed in main electrical room, from basement, ground floor, 1st
floor, 2nd floor, 28 & 29 floor of the Wynn palace building. Review method of statement, Risk
assessment and job hazard Analysis, coordinate with (TWC) Temporary work coordinator,
temporary works engineering manager for project compliance. Generate all TW1/ TW3 & TW4
and coordinate with Hong Kong ICE independent checking engineer for the approval of all
temporary works required for lifting and construction installation, generate specific lifting
methodology’s for all MEP manager when required
 Appointed Site Wide Crane Coordinator: Appointed by all Project director in Macau Wynn
palace project to manage all type of lifting in the whole projects, includes all types of ground
cranes, and all 13 tower cranes of the building. Generate Site Wide Crane development plan
& Strategy for both ground cranes and tower cranes, introduce Anti-Collision system, and
prevention of lifting accident, Generate Team organization composed of five construction
department which includes: External team, MEP site wide, Tower team, Podium Team, and
Fit-out team, generate team building coordination in preventing all lifting accident on the whole
project.
Project Lifting specialist: Generate all the specific lifting plan and manage the installation for
all the gondola/cable car station and deflection station surrounding the wide lake of Wynn
palace, also include the installation and construction of 2 famous 23.5carats golden dragon
and assist all the construction team to generate Specific lifting plan when necessary. Work as
adviser for all type of lifting of the project and work as project lifting specialist.
 Tower Crane: Manage the dismantling of 12 tower cranes of the project, with 143m heights
on the roof of the buildings. Coordinate to tower crane manager and supplier for producing
and reviewing all methodology’s, Communicate to all Leighton construction department project
leaders and safety for all the planning and execution of the dismantling work to prevent unsafe
occurrence.
Curriculum Vitae
Page 2
Qualifications:
 Bachelor of science and Mechanical Engineering
 Pablo Borbon memorial Institute of Technology Batangas Philippines
Experience:
2011 – 2014
08/2011 - 07/2014
Leighton Asia LTD. (Sludge treatment plant Project in Hong Kong)
Sr. Project Engineer:Accountabilities and Responsibilities:
 More than two years working in the largest sludge treatment plant in
the world. The facility is located at Tsang Tsui Tuen Mun with the
contract value of HK$4.7B
 Senior Project Engineer In-charge for the construction of two flue
gas treatment plant, two deodorization chemical plant, sludge
receiving, four weight bridge, lifting & assembly of four overhead
cranes and construction of 53m height chimney inside the
administration building. For this work we set-up dynamic mechanical
& piping team composed of: Sr. engineers, site engineers, piping
engineers & several site supervisor
 Managing all construction work with eight subcontractors for this
project are composed of mechanical, structural, Piping &
Instrumentation installation also includes heavy lifting of mechanical
& chemical equipment e.g four set of 60tons bag filters, four
numbers of huge dry reactors, four numbers of 10ton multi cyclone
and 24 numbers of chemical, ash and residue silo with minimum
10ton each weight, 16Nos. of 16ton ID fan & huge numbers of fiber
glass chemical tanks.
 In addition I am managing the construction and installation of sludge
chemical plant and deodorization, Lifting, assembly of four numbers
of permanent overhead crane with 12ton capacity, construction of
eight truck wash bay receiving and construction of weighbridge
 Guided my team of ten (10) engineers and supervisors to achieve
high standards, compliance and cohesion to the project goals.
Implemented management strategies to minimize resources
overloading from subcontractors and to ensure continuity of works
in line with the overall project program
 Providing technical support to the project completion team,
application of construction check certificate requirements and
assisting pre-com and commissioning team.
 Supporting Hook-up and commissioning team for load out/in and
start-up of mechanical equipment in flue gas treatment and
chemical plant deodorization.
Curriculum Vitae
Page 3
2008 – 2011 BEC Balance engineering company holdings limited Hong Kong (CLP)
07/2008 – 08/2011 Construction Manager: Accountabilities and Responsibilities:
 Working closely with Project Manager with regards to managing the
construction schedule/ work programmes to ensure satisfactory and
timely execution of the project.
 Coordinating, Supervising and Monitoring activities on site to ensure
compliance with agreed method of work, specification and drawings.
 Managing and controlling project engineers, QA/QC engineers,
foreman, supervisors and construction team on site and delegating
responsibilities to the site team.
 Identifying potential issues and recommend solutions
 Planning ahead to prevent problems on site before they occur e.g.
planning the delivery and storage of Equipment
 Making safety inspection on site when work is underway and
ensuring regulation relating to health, safety and the environment
(HSE) are adhered to.
 Preparing reports on work progress for the client and head office
 Logistical management and procurement of resources including
organizing and mobilizing site labour, equipment and materials.
 Liaise with client’s representative on all aspect of project
 Attending meeting with Clients regarding project issues and
progress.
 Motivate, direct, align and guide the team for the best performance,
monitor performance and provide continues appraisal & feedback.
Empower subordinates and provide apt tools and technique
including process improvement suggestion and flow up on
implementation.
 Review method of statements construction methodology risk
assessment and job hazard analysis
 Strictly enforcing safety on site
2005 – 2008 CITYWORLD LTD Hong Kong
Electrical & Mechanical (E&M): Accountabilities and Responsibilities:
 2008- Supervised the installation of LV Power distribution system at
Gammon site in Castle peak power station in Tuen Mun N.T Hong
Kong
 2006 - 2007 – Supervised the installation of LV & HV Power
distribution system for South Cargo apron extension at Hong Kong
International airport.
 Supervised the installation of all electrical containment for chiller
automatic control system in High raised building in Takoo shing
Hong Kong which include installation of cable trunking, cable
ladders, conduits, cable pulling.
 2005 – 2006 – Supervision of HVAC and MVAC maintenance work
in Hong Kong international airport
Curriculum Vitae
Page 4
2002 – 2005 Necso China State Hip-Hing Joint Venture Shatin Hong Kong
Site Supervisor : Accountabilities and Responsibilities:
 Coordinate to Site Agent of the project in regards for the lifting and
installation of KCR Rails segments using mobile and crawler cranes
and assigned for the installation of different type of gantry use for
sealing-up all the segments and water proofing.
 Supervised construction team and implement the project standard,
followed method of statement and specific lifting plan provided by
appointed person allocated by the project leaders.
 Responsible in KCR station for lifting and installation of steel
structures, lifting and installation of all mechanical and electrical
component
 Communicate to completion team and help to closeout punch-list for
the submission of construction check certificate.
 Assisting commissioning team.
 Strictly followed all safety standard of the project
1997- 1998 Ting Kau Entre CanalesJoint Venture Hong Kong
Lifting Supervisor: Accountabilities and Responsibilities:
 Front liner for the erection and installation of heavy structure in ting
Kau bridge followed by hot beams, structural road frames and
cantilever deck section with approved method of statement and
specific lifting plan provided by construction manager and appointed
person of the project.
 Assemble and disassembled 250ton American derrick crane use for
heavy lifting of the cantilever deck para-frame from approach
viaduct in Tin Kau bridge to Tsing yi link.
 Managing the allocation of all project ground cranes for lifting and
setting-up including hauling and trucking of different type of
equipment
 Lifting & Installation of huge cable ladder under the bridge, monitor,
cable pulling and assign for the installation of elevator inside the
three tower of Ting Kau bridge
 Coordinate to all safety department in regards for the preparation
and approval of risk assessment and job hazard analysis
 Conduct field control briefing to all the lifting and installation team
every day to ensure the lifting methodology, elimination of hazard
and risk assessment are understand by each team.
1995 - 1997 EEI- Engineering & Equipment Incorporated (Philippines)
Piping Supervisor: Accountabilities and Responsibilities:
 Ensure Planning & execution of the projects are within maximum
productivity in optimum quality of works
 Plan and organize, including generation of programmes. Follow-up
Curriculum Vitae
Page 5
the resources utilization, control and monitoring of department man
hour expenditure including indirect hours, overtimes and days off of
the workers.
 Coordinate and liaise with construction manager, and construction
superintendent and other relative trades to ensure smooth workflow
on projects.
 Ensure that all work is carried out to the required quality in the best
possible manner and within the guidelines of industry’s best
engineering practices
 Conduct frequent audits and document the outcomes to verify that
enough efforts have been put in the areas of productivity, safety and
quality.
 Raise occurrence report, develop corrective and preventive action
and ensure that rework is carried out to customer satisfaction.
 Ensure that the safety management programmes on department
safety objectives are strictly followed and action is taken against
defaulters to prevent recurrence
 Perform other job related duties as assigned by the project leader
 Monitoring of WCS weld control summary.
1993- 1994 Hyundai SDN BHD Bintulu Sarawak East Malaysia
Piping Supervisor: Accountabilities and Responsibilities:
 Interpret, prepare and review all piping drawing and instrumentation
diagram, blue print and isometric for piping fabrication and site
installation in liquefied national gas project in Malaysia
 Monitoring and supervising the piping activities carried out by the
module and piping fabricator
 Monitor the quality and progress of the work scope and adherence
to company and contractor procedures
 Providing weekly progress reports to EPC senior management in
regards to piping fabrication and site installation progress.
 Participating in fabrication and safety reviews for piping fabrication
and assembly works
 Providing technical support to the project on piping fabrication,
installation, commissioning and hook-up
 Provide input to project documents for piping fabrication/ assembly,
commissioning and start-up requirements.
 Supporting Hook-up and commissioning team for load out/in and
start-up of mechanical equipment.
 Coordinate closely with all interfaces design associated with
different subcontract
 Monitoring of WCS weld control summary.
Computer Skills:
Data Management software such as:
Incite, MS Office, Excel, Word, Power Point, Access Outlook, Adobe
acrobat.

More Related Content

What's hot (17)

CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
Sunil-CV-Latest
Sunil-CV-LatestSunil-CV-Latest
Sunil-CV-Latest
 
Arun Resume .
Arun Resume .Arun Resume .
Arun Resume .
 
CV 15 Sep2016
CV 15 Sep2016CV 15 Sep2016
CV 15 Sep2016
 
Jack Oldrin RS2
Jack Oldrin RS2Jack Oldrin RS2
Jack Oldrin RS2
 
stevenfrench_coordinator
stevenfrench_coordinatorstevenfrench_coordinator
stevenfrench_coordinator
 
Topside
TopsideTopside
Topside
 
resume-Sept 2016 Mazlan Alias
resume-Sept 2016 Mazlan Aliasresume-Sept 2016 Mazlan Alias
resume-Sept 2016 Mazlan Alias
 
Resume
Resume Resume
Resume
 
Tom Paterson-resume
Tom Paterson-resumeTom Paterson-resume
Tom Paterson-resume
 
Structural Engineer
Structural EngineerStructural Engineer
Structural Engineer
 
R mayers_CV 2302
R mayers_CV 2302R mayers_CV 2302
R mayers_CV 2302
 
Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017
 
Amitabha Chattopadhyay latest
Amitabha Chattopadhyay latest Amitabha Chattopadhyay latest
Amitabha Chattopadhyay latest
 
Shoaib Resume
Shoaib ResumeShoaib Resume
Shoaib Resume
 
Dnyaneshwar_Sonawane CV
Dnyaneshwar_Sonawane CVDnyaneshwar_Sonawane CV
Dnyaneshwar_Sonawane CV
 
Resume -Amarnath
Resume -AmarnathResume -Amarnath
Resume -Amarnath
 

Similar to Regidor A. Manalo Sub-Agent (Corporate C.V)

Similar to Regidor A. Manalo Sub-Agent (Corporate C.V) (20)

KWKCV16
KWKCV16KWKCV16
KWKCV16
 
Tony_Van_Grembergen
Tony_Van_GrembergenTony_Van_Grembergen
Tony_Van_Grembergen
 
Zeonn Koh 4 page CV
Zeonn Koh 4 page CVZeonn Koh 4 page CV
Zeonn Koh 4 page CV
 
Adly CV111
Adly CV111Adly CV111
Adly CV111
 
cv of suresh latest (4) (1)
cv of suresh latest (4) (1)cv of suresh latest (4) (1)
cv of suresh latest (4) (1)
 
NM SM
NM SMNM SM
NM SM
 
Yeoh KS CV Rev 1
Yeoh KS CV Rev 1Yeoh KS CV Rev 1
Yeoh KS CV Rev 1
 
Mohab Samoil_Resume
Mohab Samoil_ResumeMohab Samoil_Resume
Mohab Samoil_Resume
 
N137557385 Eben Van Dyk-CV
N137557385 Eben Van Dyk-CVN137557385 Eben Van Dyk-CV
N137557385 Eben Van Dyk-CV
 
Psm Cv Presentation 3 2012
Psm Cv Presentation 3  2012Psm Cv Presentation 3  2012
Psm Cv Presentation 3 2012
 
Stephen Vianelli CV 23 Dec 2016
Stephen Vianelli CV 23 Dec 2016Stephen Vianelli CV 23 Dec 2016
Stephen Vianelli CV 23 Dec 2016
 
Project Experience
Project ExperienceProject Experience
Project Experience
 
l CURRICULUM VITAE. [ komthorn very up date]
l CURRICULUM VITAE. [ komthorn very up date]l CURRICULUM VITAE. [ komthorn very up date]
l CURRICULUM VITAE. [ komthorn very up date]
 
LI, GUANGYA
LI,  GUANGYALI,  GUANGYA
LI, GUANGYA
 
Cv.eslam elsnosy.update
Cv.eslam elsnosy.updateCv.eslam elsnosy.update
Cv.eslam elsnosy.update
 
CV.Eslam-ELSNOSY.update
CV.Eslam-ELSNOSY.updateCV.Eslam-ELSNOSY.update
CV.Eslam-ELSNOSY.update
 
joy S resume
joy S resumejoy S resume
joy S resume
 
RESUME
RESUMERESUME
RESUME
 
Alistair Howson - Curriculum Vitae
Alistair Howson - Curriculum VitaeAlistair Howson - Curriculum Vitae
Alistair Howson - Curriculum Vitae
 
CV AMINUL 19-05-2015
CV AMINUL 19-05-2015CV AMINUL 19-05-2015
CV AMINUL 19-05-2015
 

Regidor A. Manalo Sub-Agent (Corporate C.V)

  • 1. Curriculum Vitae Page 1 Name: REGIDOR A. MANALO CV. Proposed Position: Sub- Agent Present Position: Years of Experience: Sub-Agent 22 Years Currently Work Location: Macau Wynn Palace Project 1st of July 2014 –To Present (Sub-Agent) Sub-Agent on Macau Wynn Palace (contract value of HK$20B) The project occupies a 21-hectares site on the reclaimed land between the island of Taipa and Coloane. The scope of works for the project includes ground and major foundation works together with the construction of luxury hotel with 2,000 rooms and a mixed-use podium comprising gaming, dining, retail and convention facilities, as well as numerous specialist attraction including a 30,000 square metre performance lake that will feature a light show. Sub-Agent: Accountabilities and Responsibilities:  Central plant construction: installation of all mechanical & Electrical equipment. Lifting and skidding of 8 Nos. of 50ton water cooled chillers, huge Nos. of heavy heat pumps, boilers, Vertical pumps, Lifting & skidding of 8Nos. of 21tons air cooler on the roof of central plant, 8Nos. of 20ton diesel generators & other equipment. Coordination with MEP Managers, civil team, external team and podium team in regards for all mechanical, electrical and piping installation in central plant.  Appointed Person: Appointed by project director for all MEP site wide in terms of all electrical and mechanical lifting and installation. e.g huge Nos. of transformer, RMU, AHU, MDB’S, & huge LV & HV cable drums installed in main electrical room, from basement, ground floor, 1st floor, 2nd floor, 28 & 29 floor of the Wynn palace building. Review method of statement, Risk assessment and job hazard Analysis, coordinate with (TWC) Temporary work coordinator, temporary works engineering manager for project compliance. Generate all TW1/ TW3 & TW4 and coordinate with Hong Kong ICE independent checking engineer for the approval of all temporary works required for lifting and construction installation, generate specific lifting methodology’s for all MEP manager when required  Appointed Site Wide Crane Coordinator: Appointed by all Project director in Macau Wynn palace project to manage all type of lifting in the whole projects, includes all types of ground cranes, and all 13 tower cranes of the building. Generate Site Wide Crane development plan & Strategy for both ground cranes and tower cranes, introduce Anti-Collision system, and prevention of lifting accident, Generate Team organization composed of five construction department which includes: External team, MEP site wide, Tower team, Podium Team, and Fit-out team, generate team building coordination in preventing all lifting accident on the whole project. Project Lifting specialist: Generate all the specific lifting plan and manage the installation for all the gondola/cable car station and deflection station surrounding the wide lake of Wynn palace, also include the installation and construction of 2 famous 23.5carats golden dragon and assist all the construction team to generate Specific lifting plan when necessary. Work as adviser for all type of lifting of the project and work as project lifting specialist.  Tower Crane: Manage the dismantling of 12 tower cranes of the project, with 143m heights on the roof of the buildings. Coordinate to tower crane manager and supplier for producing and reviewing all methodology’s, Communicate to all Leighton construction department project leaders and safety for all the planning and execution of the dismantling work to prevent unsafe occurrence.
  • 2. Curriculum Vitae Page 2 Qualifications:  Bachelor of science and Mechanical Engineering  Pablo Borbon memorial Institute of Technology Batangas Philippines Experience: 2011 – 2014 08/2011 - 07/2014 Leighton Asia LTD. (Sludge treatment plant Project in Hong Kong) Sr. Project Engineer:Accountabilities and Responsibilities:  More than two years working in the largest sludge treatment plant in the world. The facility is located at Tsang Tsui Tuen Mun with the contract value of HK$4.7B  Senior Project Engineer In-charge for the construction of two flue gas treatment plant, two deodorization chemical plant, sludge receiving, four weight bridge, lifting & assembly of four overhead cranes and construction of 53m height chimney inside the administration building. For this work we set-up dynamic mechanical & piping team composed of: Sr. engineers, site engineers, piping engineers & several site supervisor  Managing all construction work with eight subcontractors for this project are composed of mechanical, structural, Piping & Instrumentation installation also includes heavy lifting of mechanical & chemical equipment e.g four set of 60tons bag filters, four numbers of huge dry reactors, four numbers of 10ton multi cyclone and 24 numbers of chemical, ash and residue silo with minimum 10ton each weight, 16Nos. of 16ton ID fan & huge numbers of fiber glass chemical tanks.  In addition I am managing the construction and installation of sludge chemical plant and deodorization, Lifting, assembly of four numbers of permanent overhead crane with 12ton capacity, construction of eight truck wash bay receiving and construction of weighbridge  Guided my team of ten (10) engineers and supervisors to achieve high standards, compliance and cohesion to the project goals. Implemented management strategies to minimize resources overloading from subcontractors and to ensure continuity of works in line with the overall project program  Providing technical support to the project completion team, application of construction check certificate requirements and assisting pre-com and commissioning team.  Supporting Hook-up and commissioning team for load out/in and start-up of mechanical equipment in flue gas treatment and chemical plant deodorization.
  • 3. Curriculum Vitae Page 3 2008 – 2011 BEC Balance engineering company holdings limited Hong Kong (CLP) 07/2008 – 08/2011 Construction Manager: Accountabilities and Responsibilities:  Working closely with Project Manager with regards to managing the construction schedule/ work programmes to ensure satisfactory and timely execution of the project.  Coordinating, Supervising and Monitoring activities on site to ensure compliance with agreed method of work, specification and drawings.  Managing and controlling project engineers, QA/QC engineers, foreman, supervisors and construction team on site and delegating responsibilities to the site team.  Identifying potential issues and recommend solutions  Planning ahead to prevent problems on site before they occur e.g. planning the delivery and storage of Equipment  Making safety inspection on site when work is underway and ensuring regulation relating to health, safety and the environment (HSE) are adhered to.  Preparing reports on work progress for the client and head office  Logistical management and procurement of resources including organizing and mobilizing site labour, equipment and materials.  Liaise with client’s representative on all aspect of project  Attending meeting with Clients regarding project issues and progress.  Motivate, direct, align and guide the team for the best performance, monitor performance and provide continues appraisal & feedback. Empower subordinates and provide apt tools and technique including process improvement suggestion and flow up on implementation.  Review method of statements construction methodology risk assessment and job hazard analysis  Strictly enforcing safety on site 2005 – 2008 CITYWORLD LTD Hong Kong Electrical & Mechanical (E&M): Accountabilities and Responsibilities:  2008- Supervised the installation of LV Power distribution system at Gammon site in Castle peak power station in Tuen Mun N.T Hong Kong  2006 - 2007 – Supervised the installation of LV & HV Power distribution system for South Cargo apron extension at Hong Kong International airport.  Supervised the installation of all electrical containment for chiller automatic control system in High raised building in Takoo shing Hong Kong which include installation of cable trunking, cable ladders, conduits, cable pulling.  2005 – 2006 – Supervision of HVAC and MVAC maintenance work in Hong Kong international airport
  • 4. Curriculum Vitae Page 4 2002 – 2005 Necso China State Hip-Hing Joint Venture Shatin Hong Kong Site Supervisor : Accountabilities and Responsibilities:  Coordinate to Site Agent of the project in regards for the lifting and installation of KCR Rails segments using mobile and crawler cranes and assigned for the installation of different type of gantry use for sealing-up all the segments and water proofing.  Supervised construction team and implement the project standard, followed method of statement and specific lifting plan provided by appointed person allocated by the project leaders.  Responsible in KCR station for lifting and installation of steel structures, lifting and installation of all mechanical and electrical component  Communicate to completion team and help to closeout punch-list for the submission of construction check certificate.  Assisting commissioning team.  Strictly followed all safety standard of the project 1997- 1998 Ting Kau Entre CanalesJoint Venture Hong Kong Lifting Supervisor: Accountabilities and Responsibilities:  Front liner for the erection and installation of heavy structure in ting Kau bridge followed by hot beams, structural road frames and cantilever deck section with approved method of statement and specific lifting plan provided by construction manager and appointed person of the project.  Assemble and disassembled 250ton American derrick crane use for heavy lifting of the cantilever deck para-frame from approach viaduct in Tin Kau bridge to Tsing yi link.  Managing the allocation of all project ground cranes for lifting and setting-up including hauling and trucking of different type of equipment  Lifting & Installation of huge cable ladder under the bridge, monitor, cable pulling and assign for the installation of elevator inside the three tower of Ting Kau bridge  Coordinate to all safety department in regards for the preparation and approval of risk assessment and job hazard analysis  Conduct field control briefing to all the lifting and installation team every day to ensure the lifting methodology, elimination of hazard and risk assessment are understand by each team. 1995 - 1997 EEI- Engineering & Equipment Incorporated (Philippines) Piping Supervisor: Accountabilities and Responsibilities:  Ensure Planning & execution of the projects are within maximum productivity in optimum quality of works  Plan and organize, including generation of programmes. Follow-up
  • 5. Curriculum Vitae Page 5 the resources utilization, control and monitoring of department man hour expenditure including indirect hours, overtimes and days off of the workers.  Coordinate and liaise with construction manager, and construction superintendent and other relative trades to ensure smooth workflow on projects.  Ensure that all work is carried out to the required quality in the best possible manner and within the guidelines of industry’s best engineering practices  Conduct frequent audits and document the outcomes to verify that enough efforts have been put in the areas of productivity, safety and quality.  Raise occurrence report, develop corrective and preventive action and ensure that rework is carried out to customer satisfaction.  Ensure that the safety management programmes on department safety objectives are strictly followed and action is taken against defaulters to prevent recurrence  Perform other job related duties as assigned by the project leader  Monitoring of WCS weld control summary. 1993- 1994 Hyundai SDN BHD Bintulu Sarawak East Malaysia Piping Supervisor: Accountabilities and Responsibilities:  Interpret, prepare and review all piping drawing and instrumentation diagram, blue print and isometric for piping fabrication and site installation in liquefied national gas project in Malaysia  Monitoring and supervising the piping activities carried out by the module and piping fabricator  Monitor the quality and progress of the work scope and adherence to company and contractor procedures  Providing weekly progress reports to EPC senior management in regards to piping fabrication and site installation progress.  Participating in fabrication and safety reviews for piping fabrication and assembly works  Providing technical support to the project on piping fabrication, installation, commissioning and hook-up  Provide input to project documents for piping fabrication/ assembly, commissioning and start-up requirements.  Supporting Hook-up and commissioning team for load out/in and start-up of mechanical equipment.  Coordinate closely with all interfaces design associated with different subcontract  Monitoring of WCS weld control summary. Computer Skills: Data Management software such as: Incite, MS Office, Excel, Word, Power Point, Access Outlook, Adobe acrobat.