SlideShare a Scribd company logo
1 of 57
Download to read offline
SUMMER TRAININGREPORT
(9/6/2014 ‐‐‐ 5/7/2014)
Submitted by:­
Mohtisham Ali
Third year undergraduate student,
Department of Civil Engineering,
INTEGRAL UNIVERSITY, LUCKNOW
ii
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
Aknowledgement
I am very thankful to GAMMON INDIA LIMITED & NATIONAL
HIGHWAYS AUTHORITY OF INDIA for given me the opportunity to
undertake my summer training at their prestigious GANGA BRIDGE AND
FLYOVER PROJECT. It was a very good learning experience for me to
have worked at this site as this project involved many unique construction
practices and challenges. I would like to convey my heartiest thanks to
Mr. MANOJ BISWAS (Project Manager), who heartily welcomed me for the
internship. I would also like to give my heart-felt thanks to Mr. U.N. SINGH
(Execution Head), Mr. RAMESH PAL (QA/QC Head), who guided and
encouraged me all through the summer training and imparted in-depth
knowledge of the project. Also I would like to thank Mr. T.K. CHATTERJEE
(Planning Head), who assisted and guided me whenever I needed help.
We also thankful and pay our sincere gratitude to Mr. Somnath Bajpai
(Executive –HR), We sincere thanks to all the department heads of Gammon
India Limited for giving their precious time and valuable guidance during
my internship programme.
Last but not the least; I would like to thank all the staff at Gammon India
Limited, for being so helpful during this summer training.
Name: Mohtisham Ali
Date: 5th July 2014
iii
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
ABSTRACT
GAMMON INDIA LIMITED have developed so many project which
are so large and whose costing alot. The project “Rehabilitation and
Upgradation from 75 Km to 80.60 Km of NH-25. (GANGA BRIDGE &
FLYOVER PROJECT)” is important to relief from a big jams in the town of
Kanpur.
The total length of the project is 5.06 KM and the estimating cost of
the project is Rs. 159.06 Cr. In this project I was Trainee. I work on Pre-
stressed Beam. Following are important department where I work :
 PLANNING
 QUALITY CONTROL
 PLANT
 EXECUTION
iv
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
INDEX
S.No. CONTENTS Page No.
1. Project Details 1
2. Objective 2
3. Brief Introduction of G.I.L 3
4. Organizational Chart 9
5. Product/Specification/Activities 11
6. Planning Department 12
7. System/Plan Layout 14
8. QA / QC Department 15
9. Plant Information 35
10. Project Execution 40
11. Chronological Training Dairy 47
12. Safety Requirement 49
13. Suggestions 51
14. Conclusion 52
15. References 53
1
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
DETAIL OF THE PROJECT
A. PROJECT NAME Rehabilitation and
Upgradation from 75 Km
to 80.60 Km of NH-25.
(GANGA BRIDGE & FLYOVER
PROJECT)
B. CLIENT NATIONAL HIGHWAYS
AUTHORITY OF INDIA
(N.H.A.I)
C. CONTRACTOR GAMMON INDIA LTD.
D. CONSULTANT Feedback Infra Pvt. Ltd.
(F.I.P.L)
E. CONTRACT SECTION EW-II (UP-06)
F. CONTRACT LENGTH Km 75.00 to Km 80.60
G. AGREEMENT DATE 29.09.2005
H. TENDER AMOUNT INR 159.06 Cr.
I. TYPE OF CONTRACT BILLING OF QUANTITY
J. STARTING DATE 02.12.2005
K. CONTRACTUAL DATE OF
COMPLETION
01.09.2008
L. EXTENDED DATE OF COMPLETION 18.09.2014
2
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
OBJECTIVE
 CONSTRUCTION OF PRE-STRESSED BEAM.
3
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
INTRODUCTION
ABOUT THE ORGANIZATION:
 HISTORY:
The beginning of such a formidable company is to be found in the
vision of an equally formidable man. Mr J. C. Gammon was the
driving force behind the introduction of prestressed concrete to India.
He designed the reinforced concrete piles of the Gateway of India.
The foundations of the arch reach deep into the bedrock. With time,
he came to be known as the ‘Sculptor of Concrete’.
His foresight was fundamental to the company reaching its present
stature. His pioneering spirit led to a number of innovations that were
the first of their kind.
His enduring values continue to build the Gammon legacy.
J. C. Gammon – The Legacy
 Bridges like the Bonum Bridge and the Patalganga Bridge.
 The Colloidal Grouting Process at Mundali Weir.
 The RCC Pile Foundations for the Gateway of India.
 Thin Shell Prestressed Structures of Meerut Garages.
 The Hyperbolic Cooling Towers at Sabarmati
4
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
 GAMMON GROUP :
AN OVERVIEW
Gammon India is built on a legacy that has stood the test of time.
Technological and design excellence, and a discerning eye for quality and
safety are some of the characteristics that distinguish Gammon’s tradition
for perfection in its areas of operation.
Gammon India is amongst the largest physical infrastructure
construction companies in India. Its track record spans significant landmark
projects built over several decades, with a prominent presence across all
sectors of civil engineering, design and construction. It has a track record of
building landmark structures, some of which have become iconic. This
includes ‘The Gateway of India’, the piling and civil foundation work for
which was successfully executed by Gammon as its maiden project way
back in 1919.
Besides its large scale of operations
in the Construction and Infrastructure
domain, Gammon has a dominant
presence in energy business in which it
operates in the hydro, nuclear and
thermal power sectors. In fact,
Gammon’s association with the
construction of nuclear power projects dates back to 1959 when it
completed the Pre-Stresses Concrete (PSC) Ball Tank of India’s first
Atomic Reactor Plant in Trombay.
Gammon’s projects cover businesses
and projects involving highways, public
utilities, environmental engineering and
marine structures. Gammon’s expertise
also covers the design, financing,
construction and operation of modern
bridges, viaducts, and metro rail, both on a Built­Operate–Transfer (BOT)
basis as well as contract execution. An example is the upcoming ‘Signature
Bridge’ project in Wazirabad in North­West Delhi. This project would
5
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
significantly help in the efficient flow and management of traffic in the
region.
Gammon is also active in the Social Infrastructure sector through its
operations in the realty project segment. Examples include residential
complexes such as Pebble Bay and Godrej WoodsMan Estate in
Bangalore,Godrej Kalyan in Mumbai, RNA Exotica, Mumbai; Hotel
complexes such as Hotel Leela Palace, Chennai and G Staad, Bangalore
besides commercial complexes such as Galleria Mall(INXS) in Bangalore.
Gammon is also currently undertaking a major project for ISKON at Sri
Mayapur in West Bengal involving the construction of a temple complex
and a modern cultural centre.
Gammon international include a
majority holding in Franco Tosi
Meccanica, SAE Power lines, and
Sofinter group, Italy spanning the
sectors of power and industrial boilers as
well as waste and environment
management systems. Gammon has
received accolades and recognitions
from a variety of reputed institutions. Examples include the Indian Concrete
Institute Award for most outstanding concrete structure presented for the
segmental arch bridge across the River Beas (Himachal Pradesh) and the
first prize for ‘Excellent Aesthetics’ for the Vidyasagar Sethu Project across
the River Hoogly in Kolkata.
Currently Gammon India has a
strong talent base of over 3350
employees on its own rolls apart from
5500 officers and staff working under its
aegis at various project sites. It further
engages more than 200,000 labour/staff on daily wage basis. Its stand­alone
turnover in financial year 2011­12 was close to US $ 1.1 billion with the
Group’s turnover in excess of US $ 1.6 billion.
6
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
 QUALITY POLICY
Gammon India is the first Construction in India to have ISO9001
certification in design as well as execution for all Civil Engineering
structures.
Gammon is committed to form seamless partnership with its
customers, so that their requirements become our challenge. Gammon’s
quest for excellence is achieved by its innovative engineering and quality
execution of the projects, on time, within budget, by its high performance
team which is adaptable to each project..
7
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
 HEALTH SAFTEY AND ENVIRONMENTAL POLICY
At Gammon, extensive health and safety guidelines defined standards
for every project. Regular safety training programmes are undertaken at the
sites. Further, regular health and fitness checkup for every member of
our staff is mandatory.
We maintain a high standard of safety through meticulous risk
assessment. Gammon has a stellar record of twelve million hours of
accident­free work at Kalpakkam. This is a consistent track record, which is
no mean achievement, since most of our initiatives take place under
hazardous geographical conditions. These are challenges that our staff can
face because of their training. They also have the assurance of a health &
safety code that is considerate and transparent. To set standards, we must
first set an example.
Gammon is an ISO 9001, ISO 14001 and OHSAS18001 certified
company. We have a number of National Safety Awards to our credit. The
concern inherent in our corporate culture inspires a sense of loyalty toward
Gammon.
 WORK CULTURE
Work Culture emphasises:
• Freedom to experiment
• Continuous learning and training
• Transparency
• Quality in all aspects of work
• Rewards based on performance and potential
8
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
 TRAINING
Human Resources Department believes that Quality is the hallmark
of any successful venture. Quality Training and Development ofHuman
Resourcesisrealized through: Identifying training needs within the
Organization and designing and implementing those need based training
programs to bring about continuous up­gradation of knowledge, skills and
employee attitudes.
VISION&MISSION
VISION
“To Consistently build the reputation of Gammon amongst all
stakeholders as a respected and influential leader in the Construction
and Infrastructure Domain with Global Presence and Local Expertise
backed with a sustained focus on attributes of Sustainability and
Profitability and Employee engagement and Pride”
“To be leaders in innovation engineering, with uncompromising integrity,
timely delivery, pride and ownership and highest standards of quality to
reinforce the positioning of the organisation as “Builders to the Nation”.
MISSION
"To design, build and service physical infrastructure for
improved living, enhanced work environment
and swift transportation."
9
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
ORGANIZATIONAL CHART
CHIEF PROJECT MANAGER (C.P.M.)
PROJECT MANAGER (P.M.)
DEPUTY MANAGER (Dy. M.)
ASSISTANT MANAGER (A.M.)
ENGINEER (E.)
JUNIOR ENGINEER (J.E.)
10
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
PROPOSED–PROJECT
“Rehabilitation and Upgradation from 75 Km to
80.60 Km of NH-25.”
(GANGA BRIDGE & FLYOVER PROJECT)
KANPUR, INDIA
11
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
PRODUCT (S) & SPECIFICATIONS / ACTIVITIES /
CODING
Product:- “Rehabilitation and Upgradation from 75 Km to 80.60 Km of
NH­25.”
(GANGA BRIDGE & FLYOVER PROJECT).
Specifications:- All the works shall be carried out as per standard practice
of Engineering, IS­codes, I.R.C specifications and M.O.R.T.H
specifications.
Activities:- All the work consists :­
1. Planning ,
2. Quality Control ,
3. Plant Information ,
4. Execution ,
12
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
PLANNING DEPARTMENT
Construction planning is a fundamental and challenging activity in the management
and execution of construction projects. It involves the choice of technology, the
definition of work tasks, the estimation of the required resources and durations for
individual tasks, and the identification of any interactions among the different work
tasks. A good construction plan is the basis for developing the budget and the
schedule for work. Developing the construction plan is a critical task in the
management of construction, even if the plan is not written or otherwise formally
recorded. In addition to these technical aspects of construction planning, it may also
be necessary to make organizational decisions about the relationships between project
participants and even which organizations to include in a project.
Essential aspects of construction planning include the generation of required
activities, analysis of the implications of these activities, and choice among the
various alternative means of performing activities.
In developing a construction plan, it is common to adopt a primary emphasis on either
cost control or on schedule control. Some projects are primarily divided into expense
categories with associated costs. In these cases, construction planning is cost or
expense oriented. Within the categories of expenditure, a distinction is made between
costs incurred directly in the performance of an activity and indirectly for the
accomplishment of the project. For example, borrowing expenses for project
financing and overhead items are commonly treated as indirect costs. For other
projects, scheduling of work activities over time is critical and is emphasized in the
planning process. In this case, the planner insures that the proper precedence’s among
activities are maintained and that efficient scheduling of the available resources
prevails. Traditional scheduling procedures emphasize the maintenance of task
precedence’s (resulting in critical path scheduling procedures) or efficient use of
resources over time (resulting in jobshop scheduling procedures). Finally, most
complex projects require consideration of cost and scheduling over time, so that
planning, monitoring and record keeping must consider both dimensions. In these
cases, the integration of schedule and budget information is a major concern.
13
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
A parallel step in the planning process is to define the various work tasks that must be
accomplished. These work tasks represent the necessary frame work to permit
scheduling of construction activities, along with estimating the resources required by
the individual work tasks, and any necessary precedence’s or required sequence
among the tasks. The terms work "tasks" or "activities" are often used interchangeably
in construction plans to refer to specific, defined items of work.
Planning department in Gammon India Limited uses Primavera as a powering tool for
reducing risk. Primavera gives efficiency to plan a project, identify the
resources required and identify the tasks required in a sequence, increasing probability
of delivery of the project to the time, cost and quality objectives. Primavera gives you
a powerful, visually enhanced way to effectively manage a wide range of projects and
programs. From meeting crucial deadlines, to selecting the right resources, Primavera
empowering your teams.
The initial schedule of major construction activities S0 is prepared according to the
Clients preference. S0 is the basis for all types of scheduling. Preliminary schedules
representing the monthly work estimates are prepared based on experience
considering local climate conditions, environment, learning curve, pace of work,
mobilization, etc in Primavera. Productivities of different activities are estimated and
validated during the course of execution. Man power requirement is calculated based
on these productivities. Drawings released by the Client. Revisions and change orders
are issued as and when there is a change and distributed to all the units. The planning
system is updated in the first week of every month. Two progress schedules are
maintained– original schedule prepared in the starting of the project, planned schedule
which is modified according to the requirements and conditions. Actual progress is
compared with the planned schedule and in case any delay in progress is then a
Catch up schedule is prepared and executed accordingly to overcome the delay.
14
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
System / Plan Layout
15
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
QUALITY ASSURANCE & QUALITY CONTROL
DEPARTMENT
Quality is the key component which propels performance and defines leadership
traits. At GIL, Quality Standards have been internalised and documented in
Quality Assurance manuals. GIL recognizes the crucial significance of the human
element in ensuring quality. Structured training programmes ensure that every
GIL employee is conscious of his/her role and responsibility in extending
Company’s tradition of leadership through quality. A commitment to safety springs
from a concern for the individual worker – every one of the thousands braving the
rigours of construction at numerous project sites. Gammon India Limited has a well­
established and documented Quality Management System (QMS) and is taking
appropriate steps to improve its effectiveness in accordance with the requirements of
ISO 9001:2008. Relevant procedures established clearly specify the criteria and
methods for effective operation, control and necessary resources and information to
support the operation and monitoring of these processes.
QUALITY IMPLEMENTATION AT SITE
GIL has established procedure for monitoring, measuring and analyzing of these
processes and to take necessary actions to achieve planned results and continual
improvement of these processes. It has also maintained relevant procedures to identify
and exercise required control over outsourced processes, if any Systems and
procedures have been established for implementing the requisites at all
stagesofconstructionandtheyareaccreditedtotheInternationalstandardsofISO
9001:2008, ISO 14001:2004 and OHSAS 18001:2007. GIL continues to maintain the
trail blazing tradition of meeting the stringent quality standards and adherence to time
schedules in all the projects.
16
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
TESTS ON CEMENT
CONSISTENCY
AIM
To determine the quantity of water required to produce a cement paste of standard
consistency as per IS: 4031 (Part 4) ­ 1988.
PRINCIPLE
The standard consistency of a cement paste is defined as that consistency which will
permit the Vicat plunger to penetrate to a point 5 to 7mm from the bottom of the Vicat
mould.
APPARATUS
17
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
VICAT APPARATUS
Vicat apparatus conforming to IS: 5513 ­ 1976 Balance, whose permissible variation
at a load of 1000g should be +1.0g Gauging trowel conforming to IS: 10086 ­ 1982
PROCEDURE
i) Weigh approximately 400g of cement and mix it with a weighed quantity of water.
The time of gauging should be between 3 to 5 minutes.
ii) Fill the Vicat mould with paste and level it with a trowel.
iii) Lower the plunger gently till it touches the cement surface.
iv) Release the plunger allowing it to sink into the paste.
v) Note the reading on the gauge.
vi) Repeat the above procedure taking fresh samples of cement and different
quantities of water until the reading on the gauge is 5 to 7mm.
REPORTING OF RESULTS
Express the amount of water as a percentage of the weight of dry cement to the first
place of decimal.
INITIAL AND FINAL SETTING TIME
AIM
To determine the initial and the final setting time of cement as per IS: 4031 (Part 5) ­
1988.
APPARATUS
Vicat apparatus conforming to IS: 5513 ­ 1976 Balance, whose permissible variation
at a load of 1000g should be +1.0g Gauging trowel conforming to IS: 10086 ­ 1982
PROCEDURE
i) Prepare a cement paste by gauging the cement with 0.85 times the water required to
give a paste of standard consistency.
18
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
ii) Start a stop­watch, the moment water is added to the cement.
iii) Fill the Vicat mould completely with the cement paste gauged as above, the mould
resting on a non­porous plate and smooth off the surface of the paste making it level
with the top of the mould. The cement block thus prepared in the mould is the test
block.
INITIAL SETTING TIME
Place the test block under the rod bearing the needle. Lower the needle gently in order
to make contact with the surface of the cement paste and release quickly, allowing it
to penetrate the test block. Repeat the procedure till the needle fails to pierce the test
block to a point 5.0 ± 0.5mm measured from the bottom of the mould . The time
period elapsing between the time, water is added to the cement and the time, the
needle fails to pierce the test block by 5.0 ± 0.5mm measured from the bottom of the
mould, is the initial setting time.
FINAL SETTING TIME
Replace the above needle by the one with an annular attachment.
The cement should be considered as finally set when, upon applying the needle gently
to the surface of the test block, the needle makes an impression therein, while the
attachment fails to do so. The period elapsing between the time, water is added to the
cement and the time, the needle makes an impression on the surface of the test block,
while the attachment fails to do so, is the final setting time.
REPORTING OF RESULTS
The results of the initial and the final setting time should be reported to the nearest
five minutes.
19
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
TESTS ON AGGREGATES
SIEVE ANALYSIS
AIM
To determine the Grain size analysis of coarseaggregates for Concrete Material by
sieving as per IS: 2386 (Part I) & Grain size analysis of Sand (As per Table 1000­2
MOST Specification).
PRINCIPLE
By passing the sample downward through a series of standard sieves, each of
decreasing size openings, the aggregates are separated into several groups, each of
which contains aggregates in a particular size range.
APPARATUS
A SET OF IS SIEVES
i) A set of IS Sieves –
a). Coarse Aggregate : 20mm (Nominal Singal Size) Sizes : 40mm, 20mm, 10mm,
4.75mm.
b). Coarse Aggregate : 10mm (Nominal Singal Size) Sizes : 12.5mm, 10mm,
4.75mm, 2.36mm.
20
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
c). Coarse Aggregate : 20mm : 10mm and Sand (36:24:40) Sizes : 40mm, 20mm,
4.75mm, 0.600mm, 0.150mm.
ii)Balance or scale with an accuracy to measure 0.1 percent of the weight of the test
sample.
iii) A set of IS Sieve for Sand : 10mm, 4.75mm, 2.36mm, 1.18mm, 0.600mm,
0.300mm, 0.150mm.
PROCEDURE
i) The test sample is dried to a constant weight at a temperature of 110 + 5 oC
and weighed.
ii) The sample is sieved by using a set of IS Sieves.
iii) On completion of sieving, the material on each sieve is weighed.
iv) Cumulative weight passing through each sieve is calculated as a percentage of the
total sample weight.
v) Fineness modulus is obtained by adding cumulative percentage of aggregates
retained on each sieve and dividing the sum by 100.
REPORTING OF RESULTS
The results should be calculated and reported as:
i) the cumulative percentage by weight of the total sample
ii) the percentage by weight of the total sample passing through one sieve and
retained on the next smaller sieve, to the nearest 0.1 percent.
21
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
22
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
23
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
AGGREGATE IMPACT
VALUE TEST
AIM
To determine the Aggregate Impact value of coarse aggregates as per
IS: 2386 (Part IV).
APPARATUS
24
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
PROCEDURE
i) The sample should be pass through 12.5mm and retained on 10mm IS sieve
weight as W1.
ii) The sample is filled in three layers and each layer is tampered with 25 blows of
tampering rod.
iii) Then the hammer of 14 kg is allowed to fall a height of 380mm.
iv) After 15 blows, sample is taken off and sieve on 2.36mm IS sieve and weight
passing as W2.
REPORTING OF RESULTS
Impact value = [W2 / W1] x 100%
25
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
26
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
TESTS ON FRESH CONCRETE
SLUMP
AIM
To determine the workability of fresh concrete by slump test as per IS: 1199 ­ 1959.
APPARATUS
i) Slump cone
ii) Tamping rod
27
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
PROCEDURE
i) The internal surface of the mould is thoroughly cleaned and applied with a light
coat of oil.
ii) The mould is placed on a smooth, horizontal, rigid and non­ absorbent surface.
iii) The mould is then filled in four layers with freshly mixed concrete, each
approximately to one­fourth of the height of the mould.
iv) Each layer is tamped 25 times by the rounded end of the tamping rod (strokes are
distributed evenly over the cross­ section).
v) After the top layer is rodded, the concrete is struck off the level with a trowel.
vi) The mould is removed from the concrete immediately by raising it slowly in the
vertical direction.
vii)The difference in level between the height of the mould and that of the highest
point of the subsided concrete is measured.
viii) This difference in height in mm is the slump of the concrete.
REPORTING OF RESULTS
The slump measured should be recorded in mm of subsidence of the specimen
during the test. Any slump specimen, which collapses or shears off laterally gives
incorrect result and if this occurs, the test should be repeated with another
sample. If, in the repeat test also, the specimen shears, the slump should be
measured and the fact that the specimen sheared, should be recorded.
28
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
CUBE STRENGTH TEST
AIM
To determine the compressive strength of concrete cube by Compression Testing
Machine (CTM).
APPARATUS
i) CTM
29
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
PROCEDURE
i) The internal surface of the mould is thoroughly cleaned and applied with a light
coat of oil.
ii) The mould is placed on a smooth, horizontal, rigid and non­ absorbent surface.
iii) The mould is then filled in four layers with freshly mixed concrete, each
approximately to one­fourth of the height of the mould.
iv) Each layer is tamped 25 times by the rounded end of the tamping rod (strokes are
distributed evenly over the cross­ section).
v) After the top layer is rodded, the concrete is struck off the level with a trowel.
vi) The mould is removed from the concrete immediately by raising it slowly in the
vertical direction.
vii)The difference in level between the height of the mould and that of the highest
point of the subsided concrete is measured.
viii) This difference in height in mm is the slump of the concrete.
REPORTING OF RESULTS
The slump measured should be recorded in mm of subsidence of the specimen during
the test. Any slump specimen, which collapses or shears off laterally gives incorrect
result and if this occurs, the test should be repeated with another sample. If, in the
repeat test also, the specimen shears, the slump should be measured and the fact that
the specimen sheared, should be recorded.
30
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
31
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
OMC & MDD TEST
This test is done to determine the maximum dry density and the optimum moisture
content of soil using heavy compaction as per IS: 2720 (Part 8 ) – 1983.The apparatus
used is:­
i) Cylindrical metal mould – it should be either of 100mm dia. and 1000cc volume or
150mm dia. and 2250cc volume and should conform to IS: 10074 – 1982.
ii) Balances – one of 10kg capacity, sensitive to 1g and the other of 200g capacity,
sensitive to 0.01g
iii) Oven – thermostatically controlled with an interior of noncorroding material to
maintain temperature between 105 and 110o
C
iv) Steel straightedge – 30cm long
v) IS Sieves of sizes – 4.75mm, 19mm and 37.5mm.
PREPARATION OF SAMPLE
A representative portion of air­dried soil material, large enough to provide about 6kg
of material passing through a 19mm IS Sieve (for soils not susceptible to crushing
during compaction) or about 15kg of material passing through a 19mm IS Sieve (for
soils susceptible to crushing during compaction), should be taken. This portion should
be sieved through a 19mm IS Sieve and the coarse fraction rejected after its
proportion of the total sample has been recorded. Aggregations of particles should be
broken down so that if the sample was sieved through a 4.75mm IS Sieve, only
separated individual particles would be retained.
Procedure To Determine The Maximum Dry Density And The Optimum
Moisture Content Of Soil
A) Soil not susceptible to crushing during compaction –
i) A 5kg sample of air­dried soil passing through the 19mm IS Sieve should be taken.
The sample should be mixed thoroughly with a suitable amount of water depending
on the soil type (for sandy and gravelly soil – 3 to 5% and for cohesive soil – 12 to
32
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
16% below the plastic limit). The soil sample should be stored in a sealed container
for a minimum period of 16hrs.
ii) The mould of 1000cc capacity with base plate attached, should be weighed to the
nearest 1g (W1). The mould should be placed on a solid base, such as a concrete floor
or plinth and the moist soil should be compacted into the mould, with the extension
attached, in five layers of approximately equal mass, each layer being given 25 blows
from the 4.9kg rammer dropped from a height of 450mm above the soil. The blows
should be distributed uniformly over the surface of each layer. The amount of soil
used should be sufficient to fill the mould, leaving not more than about 6mm to be
struck off when the extension is removed. The extension should be removed and the
compacted soil should be levelled off carefully to the top of the mould by means of
the straight edge. The mould and soil should then be weighed to the nearest gram
(W2).
iii) The compacted soil specimen should be removed from the mould and placed onto
the mixing tray. The water content (w) of a representative sample of the specimen
should be determined.
iv) The remaining soil specimen should be broken up, rubbed through 19mm IS
Sieve and then mixed with the remaining original sample. Suitable increments of
water should be added successively and mixed into the sample, and the above
operations i.e. ii) to iv) should be repeated for each increment of water added. The
total number of determinations made should be at least five and the moisture
contents should be such that the optimum moisture content at which the maximum
dry density occurs,lies within that range.
B) Soil susceptible to crushing during compaction –
Five or more 2.5kg samples of air­dried soil passing through the 19mm IS Sieve,
should be taken. The samples should each be mixed thoroughly with different
amounts of water and stored in a sealed container as mentioned in Part A)
C) Compaction in large size mould –
For compacting soil containing coarse material upto 37.5mm size, the 2250cc
mould should be used. A sample weighing about 30kg and passing through the
37.5mm IS Sieve is used for the test. Soil is compacted in five layers, each layer
33
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
being given 55 blows of the 4.9kg rammer. The rest of the procedure is same as
above.
REPORTING OF RESULTS
Bulk density Y(gamma) in g/cc of each compacted specimen should be calculated
from the equation,
Y(gamma) = (W2-W1)/ V
where, V = volume in cc of the mould. The dry density Yd in g/cc
Yd = 100Y/(100+w)
The dry densities, Yd obtained in a series of determinations should be plotted
against the corresponding moisture contents,w. A smooth curve should be drawn
through the resulting points and the position of the maximum on the curve should
be determined.
The dry density in g/cc corresponding to the maximum point on the moisture
content/dry density curve should be reported as the maximum dry density to the
nearest 0.01. The percentage moisture content corresponding to the maximum dry
density on the moisture content/dry density curve should be reported as the
optimummoisture content and quoted to the nearest 0.2 for values below 5
percent, to the nearest 0.5 for values from 5 to 10 percent and to the nearest whole
number for values exceeding 10 percent.
34
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
35
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
PLANT INFORMATION
BATCHINGPLANT
36
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
EQUIPMENT USED IN CONSTRUCTION OF PRE-STRESSED
BEAM
 Shutter handling Gantry – 1 nos.
37
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
 Pre­stressing jack with Power pack – 2 nos.
38
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
 Grouting Pump (fressy j­600, 300kg/cm2
, 2hp) – 1 nos.
 Grout mixer & Agitator – 1 nos.
 Compressor 300 CFM – 1 nos.
 Concrete pump –1 nos.
 Poker Vibrators with needle – 4 nos.
 Shutter vibrators – 4 nos.
 Concrete production plant – 1 nos.
39
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
For Transportation of Concrete, steel bars, Aggregates, sand etc.
 Transit Mixer (7m3
)
 Truck
40
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
PROJECTEXECUTION
METHOD STATEMENT FOR PRE STRESSED BEAM
I. SCOPE: This method of statement is applicable for casting of P­40 to P­41
(G1) super structure Beam of the project “Rehabilitation and upgradation from
75.00 Km to 80.06 Km of NH­25 in the town of Kanpur (including bridge across
river Ganga) to 4 lane divided carriageway configuration (contract package EW­
II UP­06).
II. REFERENCE:
1. Drawing nos. DCPL/KANPUR/SUP/3X26/004
DCPL/KANPUR/SUP/3X26/008
2. MoRT&H Specifications
3. Contract Document – Technical specifications
III. MATERIAL AND RESOURCES :
For One Beam
1. Construction Material :
Cement (OPC 53 Grade) 140 Bags
Aggregate 20 mm 9 cum.
Aggregate 10 mm 6 cum.
Coarse Sand 9 cum.
Reinforcement Steel as per list
H T Steel (12.7mm) 1.20 ton
Sheathing Pipe 130 Rm
Anchorage 10 set
(Guide cone, Bearing Plate, Anchor Grips)
2. Plant and Equipment’s :
(Discussed in Plant Information)
3. Man Power :
Skilled worker for concrete breaking ­ 4 nos.
Skilled / S.skilled workers for concreting & grouting ­ 8 nos.
Reinforcement steel cutting and bending ­ 6 nos.
Reinforcement steel and shuttering fixing ­ 8 to 10 nos.
Pre­Stressing ­ 6 nos.
41
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
IV. PROCEDURE :
Form Work :
 Formwork for the beam will be fabricated at the site as per approved drawing of
Beam.
 It is fabricated in panels for one beam of 2 sides. For the alignment of formwork,
adjustable struts & through bolts shall be used.
 Rigid working platform shall be made at beam top level eith structural steel.
STEP 1:
 After completing of casting bed and pedestals, fabricated beam bottom shall be
erected and fixed as per our drawings. Uniform level of beam bottom shall be
made.
STEP 2:
 One side shuttering panel shall be erected and placed over beam bottom as per
drawing and true plumb of side shuttering to be made to start making of cable
profile. Flexi foams with adhesive shall be used at joints of each panel in order to
check the leakage of cement slurry during concreting.
STEP 3: Cable Profile
 Cable profile shall be marked by paint over beam bottom and side shuttering as
per drawing.
STEP 4: Reinforcement
 Steel shall be fabricated in advance as per approved bar bending scheduled at
centralized bending yard. Fabricated reinforcement shall be shifted to casting
yard.
 Reinforcement cage shall be fabricated in advance outside the casting bed. The
pre­fabricated cage shall be shifted and placed at casting bed with the help of
spreader beam and lifting Gantry as soon as bed is ready to receive
reinforcement cage for next beam.
STEP 5: Laying of Sheathing Pipe
 Sheathing pipe of 75mm (or shown in approved drawing) dia. of single length
shall be laid over marked profile (ref: STEP 3). Then the pipes shall be
accurately located and tied as per drawings in both direction of vertical and
horizontal.
42
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
 Ladders, spacers @ 2m C/C shall be provided to keep sheathing duct in position.
78mm dia. (or as suitable for sheathing pipe as per approved drawing) 150mm
long coupler shall be provided for joining sheathing ducts and at both junctions
of end Guide cone. Joints in between couplers and pipe shall be sealed with
adhesive celling tape to prevent ingress of cement slurry in to ducts during
concreting. In addition, couplers of adjacent ducts shall be staggered whenever
possible.
STEP 6: Closing of Shuttering
 After checking of reinforcement and Profiling of sheathing, other side of beam
shuttering shall be shifted and erected by means of shutter handling gantry.
Shuttering shall be closed by side bolting as well as by fixing of tie angle and by
adjustable props.
STEP 7: Concreting of PSC Beam
 Concrete of M50 grade shall be produced at batching plant and will be
transported by transit mixers to the casting yard.
 Placing of concrete shall be done by concrete pump or concrete conveyor.
43
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
 Concreting shall be done up to a depth of 400 mm andthe same layer will be
continued until completion of the beam.
 Compaction of concreting at bottom flange, web shall be done by using shutter
vibrator and with immersion vibrator simultaneously.
 Proper care shall be taken to ensure all the cables are free from concrete.
 During concreting and up to 3 to 4hrs after completion of concreting, the cable
duct shall be checked by movement of the dummy pipe through it for any ingress
of concrete slurry.
STEP 8: Threading of Cables
 Cutting of HT Strands shall be done with angle grinder after uncoiling of HT
Strands. Proper care shall be taken to avoid damages, kinks or bents and stacking
shall be done properly preventing ground contact.
 After 3 days of concrete, threading of cable shall be started from one end to the
other end. Bundle of 12nos. HT Strands be made and same to be inserted
manually inside the Sheathing duct. Proper care shall be taken to avoid damage
to sheathing duct while threading.
STEP 9: Curing & De­Shuttering
 Normal curing shall be commenced after final setting of concrete i.e. 6hrs
(approx.) depending on cement. Curing shall be continued until the concrete
reaches strength 35N/mm2
 After attaining strength of 10Mpa, the vertical side shuttering of PSC girder shall
be removed and taken out of the bed with the help of gantry, to use in the second
bed.
STEP 10: Pre­Stressing
Method of stressing: FPCC System (Proposed) or any other system
approved by Engineer
Important Points:
 Stressing will be done after 10 days of concrete and achieves strength as
specified in Drawing. Number of cables to be stressed, will be as mentioned in
drawing.
44
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
 Future cable shall be stressed after completion of stressing and if required and as
advised by the Engineer.
 It is to be seen whether the extensions specified in the table account for effect of
slip at each end or not. Accordingly, no extra allowance of slip should be made.
 Extension at each end during stressing operation should be equal as far as
possible, max. Difference should not exceed 5% of the prescribe extensions at
each end. In case the required extensions are not obtained at the specified
pressure, stressing should be continued till the required extensions are obtained
subjected to jack pressures not exceeding the prescribe limits.
 Difference between calculated and observed tension and elongations during the
pre­stressing operations shall be regulated as per MORTH sec. 1807 under post
tensioning head as point a, b, c, d.
Method of Stressing
 During curing of PSC Beam, arrangements for pre­stressing shall be started
Erect a tripod or scaffolding tower on both end of PSC Beam.
 HT Strands to be physically checked to ensure the strands are free from any
friction.
 Keep all strands ends at particular point approx. 750mm from the anchorage
cone.
 Clean all projected HT strands by petrol and afterward give a coating of wax for
smooth operation.
 Place the bearing plate on the buter face of each of the anchorage cone of PSC
Beam.
 Fix the anchorage grips in each hole of bearing plates by means of pipe.
 Erect the pre stressing jack at both the end and place in first cable as per the
stressing sequence and then fix the barrel and master grips in pre­stressing jacks.
 Initial force shall be applied for tightening of jacks till slackness of the strands is
removed. A mark shall be made at each strand at a suitable distance to measure
the extensions of cables at both ends.
 Incremental load shall be applied to keep control over the extensions. A see­saw
action on loading may be applied to get equal extension at both the ends.
Stressing to continue till it reaches its final extensions as per table i.
45
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
 Afterward, all other cables shall be stressed as per sequence in above manner.
 Slip of each cable shall be measured and recorded.
STEP 11: Grouting of cables in Pre­stressed girders
Grouting of cables shall be conducted at stacking bed as soon as it stacked there.
Materials:
 Water: clean, potable water free form impurities will be used.
 Cement: OPC as mentioned above
 Sand: sand conforming to IS: 383 will be used.
 Admixture: admixture if required conforming to IS: 9102 will be used.
Equipment:
(Discussed in Plant Information)
Mixing of Grout:
 Proportions of the required materials will be measured by weight before starting
of mixing operation.
 Water shall be added to the mixer followed by cement, sand & admixture /
Readymade grout mixture.
 Mixing shall be done for approximately 2 to 3 min until uniform and thoroughly
blended grout is achieved.
 Adequate care shall be taken to prevent any addition of water to mixed grout to
increase fluidity.
 Cubes of 100mm shall be taken for verification of compressive strength.
Grouting Operations:
 Grouting shall be carried out within 2 weeks of stressing of cables.
 Ducts shall be flushed with water for cleaning as well as for wetting the surfaces
of the ducts walls. Water used for flushing should of same quality as used for
grouting.
 After cleaning, all the water shall be drained thoroughly by vent pipe or by
blowing compressed air through duct.
 Sequence of grouting shall commence from bottom to top.
46
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
 During and after 3 to 4 hours of grouting other non­stressed cables shall be
checked manually for free movement.
 All outlet points including vent openings should be kept open before to
commencement of grouting.
Injection of Grout:
 After mixing grout should be kept in continuous movement and injection of
grout must be continuous without any interruptions.
 Grouting shall be commenced initially with a low pressure of injection of up to
0.3Mpa increasing it until the grout come out through the other end with same
consistency as that of the grout @ injection end.
 Full injection pressure (approx. 0.5Mpa) shall be maintained for a minimum of 1
min before closing the injection pipe.
TIME CYCLE:
Following is the time cycle of construction of 1 no. PSC Beam:
S.No Activity No of Days
1. Bottom plate cleaning, leveling 0.5 day
2. Erection of outer shutter 0.5 day
3. Lowering of Pre-fabricated cage 0.5 day
4. Sheathing laying and profiling 0.5 day
5. Shutter closing and checking 0.5 day
6. Concreting 1 day
7. Waiting and de-shuttering of side shutter 1 day
8. Cable threading and Pre-stressing after 10
days
11 days
9. Lifting of Beam and vacating bed 0.5 day
TOTAL 15 days
47
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
CHRONOLOGICAL TRAINING DIARY
Date Description
06­06­2014 Joining letter taken from G.I.L office.
07­06­2014 Visit of office & site and meeting with
Engineers.
08­06­2014 Sunday holiday.
09­06­2014 Visit the office & study the plan of project.
(Planning Department)
10­06­2014 Discussion with the Planning Engineers.
11­06­2014 Study different drawing, work and contract
documents.
12­06­2014 Meeting with Plant Engineer and Discussion
about machines.
13­06­2014 Meeting with QC Engineer and Discussion
about Quality Policy.
14­06­2014 Performing Sieve analysis & Aggregate
impact value Test.
15­06­2014 Sunday holiday.
16­06­2014 Visit the site & Meeting with Execution
Engineer and Execution Team.
17­06­2014 Visit full site and Discussion about Project
Execution with Engineers.
18­06­2014 Construction of Pre­stressed Beam (G1)
start (Bottom Plate clearing and leveling).
19­06­2014 Erection of outer shutter & Lowering of
Pre­fabricated cage.
20­06­2014 Sheathing Laying and Profiling &
Shuttering Closing and Checking.
48
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
21­06­2014 Visit plant and see making of Concrete and
Concreting of Beam in casting yard.
22­06­2014 Sunday holiday.
23­06­2014 De­shuttering of side shutter & Curing of
Beam.
24­06­2014 Curing of Beam &
Construction of Pier cap no. 43.
25­06­2014 Curing of Beam &
Construction of Pier cap no. 43.
26­06­2014 Curing of Beam &
Construction of Pile cap no. 45.
27­06­2014 Curing of Beam &
Construction of Pile cap no. 45.
28­06­2014 Curing of Beam & Laying of Reinforcement
on deck b/w P36 to P39.
29­06­2014 Sunday holiday.
30­06­2014 Curing of Beam & Laying of Reinforcement
on deck b/w P36 to P39.
01­07­2014 Visit office (QC Department) and perform
Cube Test of Beam P39­P40.
02­07­2014 Cable Threading and Pre­Stressing of Beam
after 10 days in Casting yard.
03­07­2014 Lifting of Beam to Pier P40­P41 with the
help of Gantry.
04­07­2014 Collecting all Drawings & Preparation of
Project report.
05­07­2014 Discussion with Project Manager about
Project Report.
06­07­2014 Sunday holiday.
07­07­2014 Submission of Project Report to Project
Manager at G.I.L office.
49
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
SAFETY REQUIREMENT
SAFETY APPLIANCES
The requirement of sufficient number of safety appliances are planned well in advance
and made available at stores.
HEAD PROTECTION
Every individual entering the site must wear safety helmet, confirming to IS: 2925­1984
with the chinstrap fixed to the chin.
FOOT AND LEG PROTECTION
Safety footwear with steel toe is essential on site to prevent crush injuries to our toes
and injury due to striking against the object.
HEARING PROTECTION
Excessive noise causes damage to the inner ear and permanent loss of hearing. To
protect ears use ear plugs / ear muff as suitable.
EYE PROTECTION
Person carrying out grinding works, operating pavement breakers, and those involved
in welding and cutting works should wear safety goggles & face shield suitably
Goggles, Safety Spectacles, face shield confirm to IS: 5983­1980.
EAR PROTECTION
Ear Muff / Earplug should be provided to those working at places with high sound levels
(confirm to IS: 9167­1979).
HAND AND ARM PROTECTION
While handling cement and concrete & while carrying out hot works like gas cutting,
grinding & welding usage of hand gloves is a must to protect the hand,
1) COTTON Gloves (for materials handling)­­‐IS: 6994­­‐1973
2) RUBEER Gloves­18” (380/450mm long) electrical grade, tested to 15000
Volts conforming to IS: 4770­­‐1991
3) LEATHER Gloves – hot work / handling of sharp edges .
50
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
RESPIRATORY PROTECTION
Required respiratory protection according to the exposure of hazards to be
provided.
SAFETY NET
Though it is mandatory to wear safety harness while working at height on the working
platforms, safety nets of suitable mesh size shall
be provided to arrest the falling of person and materials on need basis.
FALL PROTECTION
To prevent fall of person while working at height, personnel engaged more than 2m
wear standard Full Body harness should be conforming to IS: 3521­1999 (Third
Revision).
1) Lanyard should be of 12mm Polypropylene rope and of length not more than 2m.
2) Double lanyard, based on the requirement.
SAFETY DURING STRESSING
Use hydraulic equipment’s supplied with a relief valve.
Place safely valve in between jacks and connection high­pressure hose.
Use hosepipes in good conditions and avoid using worn out hosepipes.
Check the concrete around bearing plate and anchorage to see whether there are any
voids / honeycombing.
Do not allow anybody behind stressing devices, in line with tendon, or near hydraulic
hoses.
When the stressing works are in progress no other work should continue in the vicinity.
Health of safety systems incorporated in the stressing equipment shall be ascertained
once a week.
Display a clearly visible sign “DANGER…PRESTRESSING WORKS IN
PROGRESS”
51
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
SUGGESTION
Gammon India Limited (G.I.L) is playing a vital and very
important role by giving the good and comfortable facilities of Bridges for
the Roads users and also giving the better Structures which are giving
beauty to our Country.
In this process of construction there is big jams occurs on Service
Roads. So I requested to G.I.L. to provide good moving facilities for
service lane users.
I have seen that several numbers of labour were working day &night
as to complete the project in given estimated time. The Engineers Staff was
also working very hard. Overall the Work of this Project is Satisfying its
drawing& Specifications.
52
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
CONCLUSION
It was a wonderful learning experience at Gammon India Limited site
“Rehabilitation and Upgradation from 75 Km to 80.60 Km of NH­25
(GANGA BRIDGE & FLYOVER PROJECT)” for one months in
KANPUR. I gained a lot of insight regarding almost every aspect of site. I
was given exposure in almost all the departments at the site. The friendly
welcome from all the employees is appreciating, sharing their experience
and giving their peace of wisdom which they have gained in long journey
of work. I am very much thankful for the wonderful accommodation
facility from G.I.L. I hope this experience will surely help me in my future
and also in shaping my career.
53
SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW)
MOHTISHAM ALI (1100111112)
REFERENCES
In Preparing this Project Report the following references has been taken in
accounts are :­
 SpecificationsofG.I.L.
 SpecificationsofN.H.A.I.
 Specificationsof MoRT&H.
 Drawing nos. :­
1. DCPL/KANPUR/SUP/3X26/004
2. DCPL/KANPUR/SUP/3X26/008
 Contract Document – Technical Specifications.

More Related Content

What's hot

PPT on industrial summer training in civil engineer
PPT  on industrial summer training in civil engineer PPT  on industrial summer training in civil engineer
PPT on industrial summer training in civil engineer ramit raj
 
Super-Structural Construction Work of a Six Storied Residential Building
Super-Structural Construction Work of a Six Storied Residential BuildingSuper-Structural Construction Work of a Six Storied Residential Building
Super-Structural Construction Work of a Six Storied Residential BuildingShariful Haque Robin
 
training report
training reporttraining report
training reportLilonheart
 
Construction of residential building
Construction of residential buildingConstruction of residential building
Construction of residential buildingSumit Singh
 
Civil Engineering Summer Training Report at RITES Ltd.
Civil Engineering Summer Training Report at RITES Ltd.Civil Engineering Summer Training Report at RITES Ltd.
Civil Engineering Summer Training Report at RITES Ltd.Sahab Assas Ajaz
 
Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building Self-employed
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION L&W BUILDING SOLUTIONS PVT. LMT.
 
Internship presentation 180 27 presentation-mistry kevin
Internship presentation 180 27 presentation-mistry kevinInternship presentation 180 27 presentation-mistry kevin
Internship presentation 180 27 presentation-mistry kevinKEVINMISTRY8
 
Internship Report on Building Construction
Internship Report on Building ConstructionInternship Report on Building Construction
Internship Report on Building ConstructionEsmael Aragaw
 
Industrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil EngineeringIndustrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil EngineeringRAVI KUMAR
 
Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Ram1239
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGJAPJEETSINGH13
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineeringalok0025
 
training report civil engg. 7th sem
training report civil engg. 7th semtraining report civil engg. 7th sem
training report civil engg. 7th semRajat kashv
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteRAVI KUMAR
 
INTERNSHIP REPORT FOR CONCSTRUCTION MANAGEMENT AND ORGANISING WORKS OF A BUIL...
INTERNSHIP REPORT FOR CONCSTRUCTION MANAGEMENT AND ORGANISING WORKS OF A BUIL...INTERNSHIP REPORT FOR CONCSTRUCTION MANAGEMENT AND ORGANISING WORKS OF A BUIL...
INTERNSHIP REPORT FOR CONCSTRUCTION MANAGEMENT AND ORGANISING WORKS OF A BUIL...SufiyanAhmedJeddy
 
Construction site report
Construction site reportConstruction site report
Construction site reportRavi Kant Sahu
 
Industrial Training Report
Industrial Training ReportIndustrial Training Report
Industrial Training ReportVj NiroSh
 
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONROHITASH ROJ
 

What's hot (20)

PPT on industrial summer training in civil engineer
PPT  on industrial summer training in civil engineer PPT  on industrial summer training in civil engineer
PPT on industrial summer training in civil engineer
 
Super-Structural Construction Work of a Six Storied Residential Building
Super-Structural Construction Work of a Six Storied Residential BuildingSuper-Structural Construction Work of a Six Storied Residential Building
Super-Structural Construction Work of a Six Storied Residential Building
 
training report
training reporttraining report
training report
 
Construction of residential building
Construction of residential buildingConstruction of residential building
Construction of residential building
 
Civil Engineering Summer Training Report at RITES Ltd.
Civil Engineering Summer Training Report at RITES Ltd.Civil Engineering Summer Training Report at RITES Ltd.
Civil Engineering Summer Training Report at RITES Ltd.
 
Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 
Internship presentation 180 27 presentation-mistry kevin
Internship presentation 180 27 presentation-mistry kevinInternship presentation 180 27 presentation-mistry kevin
Internship presentation 180 27 presentation-mistry kevin
 
Internship Report on Building Construction
Internship Report on Building ConstructionInternship Report on Building Construction
Internship Report on Building Construction
 
Industrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil EngineeringIndustrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil Engineering
 
Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERING
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineering
 
training report civil engg. 7th sem
training report civil engg. 7th semtraining report civil engg. 7th sem
training report civil engg. 7th sem
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction Site
 
INTERNSHIP REPORT FOR CONCSTRUCTION MANAGEMENT AND ORGANISING WORKS OF A BUIL...
INTERNSHIP REPORT FOR CONCSTRUCTION MANAGEMENT AND ORGANISING WORKS OF A BUIL...INTERNSHIP REPORT FOR CONCSTRUCTION MANAGEMENT AND ORGANISING WORKS OF A BUIL...
INTERNSHIP REPORT FOR CONCSTRUCTION MANAGEMENT AND ORGANISING WORKS OF A BUIL...
 
Construction site report
Construction site reportConstruction site report
Construction site report
 
Industrial Training Report
Industrial Training ReportIndustrial Training Report
Industrial Training Report
 
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
 
Internship review (Civil Engineering)
Internship review (Civil Engineering)Internship review (Civil Engineering)
Internship review (Civil Engineering)
 

Viewers also liked

Summer internship report L&T
Summer internship report L&TSummer internship report L&T
Summer internship report L&TUmed Paliwal
 
Summer Training Report
Summer Training ReportSummer Training Report
Summer Training ReportPrateek Dubey
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONGLA University
 
Training under Gammon India Ltd. in Guwahati
Training under Gammon India Ltd. in GuwahatiTraining under Gammon India Ltd. in Guwahati
Training under Gammon India Ltd. in GuwahatiRahul Tamsoy
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMIshant Gautam.
 
Training report on railway structure at tata aldesa
Training report on railway structure at tata aldesaTraining report on railway structure at tata aldesa
Training report on railway structure at tata aldesaUtsav Tripathy
 
BRIEF THEORY OF SIGNATURE BRIDGE
BRIEF THEORY OF SIGNATURE BRIDGEBRIEF THEORY OF SIGNATURE BRIDGE
BRIEF THEORY OF SIGNATURE BRIDGEPravin Gaurav
 
A presentation on Gammon India Ltd.
A presentation on Gammon India Ltd.A presentation on Gammon India Ltd.
A presentation on Gammon India Ltd.kunal2091
 
Summer traning report
Summer traning reportSummer traning report
Summer traning reportAmit Raj
 
CONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGECONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGEAnkit Gautam
 
Summer Internship Report
Summer Internship ReportSummer Internship Report
Summer Internship ReportHari Krishnan
 
Strategic Sales for Colleges
Strategic Sales for CollegesStrategic Sales for Colleges
Strategic Sales for CollegesTrenton Hightower
 
Summer training @ L&T
Summer training @ L&TSummer training @ L&T
Summer training @ L&Tams_5686
 
Ne railway gorakhpur summer training report
Ne railway gorakhpur summer training reportNe railway gorakhpur summer training report
Ne railway gorakhpur summer training reportKrishna Yadav
 
RSMML training report
RSMML  training report RSMML  training report
RSMML training report ujjawalnagda
 
SOLAR STREET LIGHTING SYSTEM
SOLAR STREET LIGHTING SYSTEMSOLAR STREET LIGHTING SYSTEM
SOLAR STREET LIGHTING SYSTEMsubhankar Dash
 
Summer Training Report of Role & Implications of Micro-Finance
Summer Training Report  of Role & Implications of Micro-FinanceSummer Training Report  of Role & Implications of Micro-Finance
Summer Training Report of Role & Implications of Micro-FinanceFellowBuddy.com
 
Summer training guidelines ppt
Summer training guidelines pptSummer training guidelines ppt
Summer training guidelines pptGurjar Patel
 
inplant training report
inplant training reportinplant training report
inplant training reportanandasagar
 

Viewers also liked (20)

Summer internship report L&T
Summer internship report L&TSummer internship report L&T
Summer internship report L&T
 
Summer Training Report
Summer Training ReportSummer Training Report
Summer Training Report
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
 
Training under Gammon India Ltd. in Guwahati
Training under Gammon India Ltd. in GuwahatiTraining under Gammon India Ltd. in Guwahati
Training under Gammon India Ltd. in Guwahati
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
Training report on railway structure at tata aldesa
Training report on railway structure at tata aldesaTraining report on railway structure at tata aldesa
Training report on railway structure at tata aldesa
 
Appointment final
Appointment finalAppointment final
Appointment final
 
BRIEF THEORY OF SIGNATURE BRIDGE
BRIEF THEORY OF SIGNATURE BRIDGEBRIEF THEORY OF SIGNATURE BRIDGE
BRIEF THEORY OF SIGNATURE BRIDGE
 
A presentation on Gammon India Ltd.
A presentation on Gammon India Ltd.A presentation on Gammon India Ltd.
A presentation on Gammon India Ltd.
 
Summer traning report
Summer traning reportSummer traning report
Summer traning report
 
CONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGECONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGE
 
Summer Internship Report
Summer Internship ReportSummer Internship Report
Summer Internship Report
 
Strategic Sales for Colleges
Strategic Sales for CollegesStrategic Sales for Colleges
Strategic Sales for Colleges
 
Summer training @ L&T
Summer training @ L&TSummer training @ L&T
Summer training @ L&T
 
Ne railway gorakhpur summer training report
Ne railway gorakhpur summer training reportNe railway gorakhpur summer training report
Ne railway gorakhpur summer training report
 
RSMML training report
RSMML  training report RSMML  training report
RSMML training report
 
SOLAR STREET LIGHTING SYSTEM
SOLAR STREET LIGHTING SYSTEMSOLAR STREET LIGHTING SYSTEM
SOLAR STREET LIGHTING SYSTEM
 
Summer Training Report of Role & Implications of Micro-Finance
Summer Training Report  of Role & Implications of Micro-FinanceSummer Training Report  of Role & Implications of Micro-Finance
Summer Training Report of Role & Implications of Micro-Finance
 
Summer training guidelines ppt
Summer training guidelines pptSummer training guidelines ppt
Summer training guidelines ppt
 
inplant training report
inplant training reportinplant training report
inplant training report
 

Similar to Summer Training Report (GAMMON INDIA)

INTRODUCTION 89.pdf
INTRODUCTION 89.pdfINTRODUCTION 89.pdf
INTRODUCTION 89.pdfsukoon6
 
Shameera - Work Report - Maga Engineering
Shameera - Work Report - Maga EngineeringShameera - Work Report - Maga Engineering
Shameera - Work Report - Maga EngineeringShameera Wijesooriya
 
Internship Report on metro project
Internship Report on metro projectInternship Report on metro project
Internship Report on metro projectAkshathaBhandary
 
CV of Lead HSE Supervisor-Ghulam Shabbeer
CV of Lead HSE Supervisor-Ghulam ShabbeerCV of Lead HSE Supervisor-Ghulam Shabbeer
CV of Lead HSE Supervisor-Ghulam ShabbeerGhulam Shabbeer
 
Resume HSE Officer (Jitendra dubey)
Resume HSE Officer (Jitendra dubey)Resume HSE Officer (Jitendra dubey)
Resume HSE Officer (Jitendra dubey)Jitendra Dubey
 
EDPM Report # 1_ Pankaj Shukla
EDPM Report # 1_ Pankaj ShuklaEDPM Report # 1_ Pankaj Shukla
EDPM Report # 1_ Pankaj ShuklaPankaj Shukla
 
HSE ENGINEER JIBRAN A.
HSE ENGINEER JIBRAN A.HSE ENGINEER JIBRAN A.
HSE ENGINEER JIBRAN A.jibran ansari
 
CV-Engr. JAKIR_05-October-2015
CV-Engr. JAKIR_05-October-2015CV-Engr. JAKIR_05-October-2015
CV-Engr. JAKIR_05-October-2015S.M. Jakir Hossain
 
AMIT KUMAR (3)
AMIT KUMAR (3)AMIT KUMAR (3)
AMIT KUMAR (3)Amit Singh
 
AMIT KUMAR (3)
AMIT KUMAR (3)AMIT KUMAR (3)
AMIT KUMAR (3)Amit Singh
 

Similar to Summer Training Report (GAMMON INDIA) (20)

INTRODUCTION 89.pdf
INTRODUCTION 89.pdfINTRODUCTION 89.pdf
INTRODUCTION 89.pdf
 
Final Project
Final ProjectFinal Project
Final Project
 
Sanjeev Barwal
Sanjeev BarwalSanjeev Barwal
Sanjeev Barwal
 
Shameera - Work Report - Maga Engineering
Shameera - Work Report - Maga EngineeringShameera - Work Report - Maga Engineering
Shameera - Work Report - Maga Engineering
 
13.ICON Brochure
13.ICON Brochure13.ICON Brochure
13.ICON Brochure
 
TATIRA TATIRA CV Current 1
TATIRA TATIRA CV Current 1TATIRA TATIRA CV Current 1
TATIRA TATIRA CV Current 1
 
Satish Gangadhar - Resume
Satish Gangadhar - ResumeSatish Gangadhar - Resume
Satish Gangadhar - Resume
 
Sanjay CV
Sanjay CVSanjay CV
Sanjay CV
 
Internship Report on metro project
Internship Report on metro projectInternship Report on metro project
Internship Report on metro project
 
DavidBourneResume
DavidBourneResumeDavidBourneResume
DavidBourneResume
 
Eng.Hazem's CV
Eng.Hazem's CVEng.Hazem's CV
Eng.Hazem's CV
 
CV of Lead HSE Supervisor-Ghulam Shabbeer
CV of Lead HSE Supervisor-Ghulam ShabbeerCV of Lead HSE Supervisor-Ghulam Shabbeer
CV of Lead HSE Supervisor-Ghulam Shabbeer
 
Resume HSE Officer (Jitendra dubey)
Resume HSE Officer (Jitendra dubey)Resume HSE Officer (Jitendra dubey)
Resume HSE Officer (Jitendra dubey)
 
EDPM Report # 1_ Pankaj Shukla
EDPM Report # 1_ Pankaj ShuklaEDPM Report # 1_ Pankaj Shukla
EDPM Report # 1_ Pankaj Shukla
 
Syed Sufyan Ahmed CV
Syed Sufyan Ahmed  CVSyed Sufyan Ahmed  CV
Syed Sufyan Ahmed CV
 
HSE ENGINEER JIBRAN A.
HSE ENGINEER JIBRAN A.HSE ENGINEER JIBRAN A.
HSE ENGINEER JIBRAN A.
 
Pankaj report
Pankaj reportPankaj report
Pankaj report
 
CV-Engr. JAKIR_05-October-2015
CV-Engr. JAKIR_05-October-2015CV-Engr. JAKIR_05-October-2015
CV-Engr. JAKIR_05-October-2015
 
AMIT KUMAR (3)
AMIT KUMAR (3)AMIT KUMAR (3)
AMIT KUMAR (3)
 
AMIT KUMAR (3)
AMIT KUMAR (3)AMIT KUMAR (3)
AMIT KUMAR (3)
 

Recently uploaded

Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 

Recently uploaded (20)

Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 

Summer Training Report (GAMMON INDIA)

  • 1. SUMMER TRAININGREPORT (9/6/2014 ‐‐‐ 5/7/2014) Submitted by:­ Mohtisham Ali Third year undergraduate student, Department of Civil Engineering, INTEGRAL UNIVERSITY, LUCKNOW
  • 2. ii SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) Aknowledgement I am very thankful to GAMMON INDIA LIMITED & NATIONAL HIGHWAYS AUTHORITY OF INDIA for given me the opportunity to undertake my summer training at their prestigious GANGA BRIDGE AND FLYOVER PROJECT. It was a very good learning experience for me to have worked at this site as this project involved many unique construction practices and challenges. I would like to convey my heartiest thanks to Mr. MANOJ BISWAS (Project Manager), who heartily welcomed me for the internship. I would also like to give my heart-felt thanks to Mr. U.N. SINGH (Execution Head), Mr. RAMESH PAL (QA/QC Head), who guided and encouraged me all through the summer training and imparted in-depth knowledge of the project. Also I would like to thank Mr. T.K. CHATTERJEE (Planning Head), who assisted and guided me whenever I needed help. We also thankful and pay our sincere gratitude to Mr. Somnath Bajpai (Executive –HR), We sincere thanks to all the department heads of Gammon India Limited for giving their precious time and valuable guidance during my internship programme. Last but not the least; I would like to thank all the staff at Gammon India Limited, for being so helpful during this summer training. Name: Mohtisham Ali Date: 5th July 2014
  • 3. iii SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) ABSTRACT GAMMON INDIA LIMITED have developed so many project which are so large and whose costing alot. The project “Rehabilitation and Upgradation from 75 Km to 80.60 Km of NH-25. (GANGA BRIDGE & FLYOVER PROJECT)” is important to relief from a big jams in the town of Kanpur. The total length of the project is 5.06 KM and the estimating cost of the project is Rs. 159.06 Cr. In this project I was Trainee. I work on Pre- stressed Beam. Following are important department where I work :  PLANNING  QUALITY CONTROL  PLANT  EXECUTION
  • 4. iv SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) INDEX S.No. CONTENTS Page No. 1. Project Details 1 2. Objective 2 3. Brief Introduction of G.I.L 3 4. Organizational Chart 9 5. Product/Specification/Activities 11 6. Planning Department 12 7. System/Plan Layout 14 8. QA / QC Department 15 9. Plant Information 35 10. Project Execution 40 11. Chronological Training Dairy 47 12. Safety Requirement 49 13. Suggestions 51 14. Conclusion 52 15. References 53
  • 5. 1 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) DETAIL OF THE PROJECT A. PROJECT NAME Rehabilitation and Upgradation from 75 Km to 80.60 Km of NH-25. (GANGA BRIDGE & FLYOVER PROJECT) B. CLIENT NATIONAL HIGHWAYS AUTHORITY OF INDIA (N.H.A.I) C. CONTRACTOR GAMMON INDIA LTD. D. CONSULTANT Feedback Infra Pvt. Ltd. (F.I.P.L) E. CONTRACT SECTION EW-II (UP-06) F. CONTRACT LENGTH Km 75.00 to Km 80.60 G. AGREEMENT DATE 29.09.2005 H. TENDER AMOUNT INR 159.06 Cr. I. TYPE OF CONTRACT BILLING OF QUANTITY J. STARTING DATE 02.12.2005 K. CONTRACTUAL DATE OF COMPLETION 01.09.2008 L. EXTENDED DATE OF COMPLETION 18.09.2014
  • 6. 2 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) OBJECTIVE  CONSTRUCTION OF PRE-STRESSED BEAM.
  • 7. 3 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) INTRODUCTION ABOUT THE ORGANIZATION:  HISTORY: The beginning of such a formidable company is to be found in the vision of an equally formidable man. Mr J. C. Gammon was the driving force behind the introduction of prestressed concrete to India. He designed the reinforced concrete piles of the Gateway of India. The foundations of the arch reach deep into the bedrock. With time, he came to be known as the ‘Sculptor of Concrete’. His foresight was fundamental to the company reaching its present stature. His pioneering spirit led to a number of innovations that were the first of their kind. His enduring values continue to build the Gammon legacy. J. C. Gammon – The Legacy  Bridges like the Bonum Bridge and the Patalganga Bridge.  The Colloidal Grouting Process at Mundali Weir.  The RCC Pile Foundations for the Gateway of India.  Thin Shell Prestressed Structures of Meerut Garages.  The Hyperbolic Cooling Towers at Sabarmati
  • 8. 4 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)  GAMMON GROUP : AN OVERVIEW Gammon India is built on a legacy that has stood the test of time. Technological and design excellence, and a discerning eye for quality and safety are some of the characteristics that distinguish Gammon’s tradition for perfection in its areas of operation. Gammon India is amongst the largest physical infrastructure construction companies in India. Its track record spans significant landmark projects built over several decades, with a prominent presence across all sectors of civil engineering, design and construction. It has a track record of building landmark structures, some of which have become iconic. This includes ‘The Gateway of India’, the piling and civil foundation work for which was successfully executed by Gammon as its maiden project way back in 1919. Besides its large scale of operations in the Construction and Infrastructure domain, Gammon has a dominant presence in energy business in which it operates in the hydro, nuclear and thermal power sectors. In fact, Gammon’s association with the construction of nuclear power projects dates back to 1959 when it completed the Pre-Stresses Concrete (PSC) Ball Tank of India’s first Atomic Reactor Plant in Trombay. Gammon’s projects cover businesses and projects involving highways, public utilities, environmental engineering and marine structures. Gammon’s expertise also covers the design, financing, construction and operation of modern bridges, viaducts, and metro rail, both on a Built­Operate–Transfer (BOT) basis as well as contract execution. An example is the upcoming ‘Signature Bridge’ project in Wazirabad in North­West Delhi. This project would
  • 9. 5 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) significantly help in the efficient flow and management of traffic in the region. Gammon is also active in the Social Infrastructure sector through its operations in the realty project segment. Examples include residential complexes such as Pebble Bay and Godrej WoodsMan Estate in Bangalore,Godrej Kalyan in Mumbai, RNA Exotica, Mumbai; Hotel complexes such as Hotel Leela Palace, Chennai and G Staad, Bangalore besides commercial complexes such as Galleria Mall(INXS) in Bangalore. Gammon is also currently undertaking a major project for ISKON at Sri Mayapur in West Bengal involving the construction of a temple complex and a modern cultural centre. Gammon international include a majority holding in Franco Tosi Meccanica, SAE Power lines, and Sofinter group, Italy spanning the sectors of power and industrial boilers as well as waste and environment management systems. Gammon has received accolades and recognitions from a variety of reputed institutions. Examples include the Indian Concrete Institute Award for most outstanding concrete structure presented for the segmental arch bridge across the River Beas (Himachal Pradesh) and the first prize for ‘Excellent Aesthetics’ for the Vidyasagar Sethu Project across the River Hoogly in Kolkata. Currently Gammon India has a strong talent base of over 3350 employees on its own rolls apart from 5500 officers and staff working under its aegis at various project sites. It further engages more than 200,000 labour/staff on daily wage basis. Its stand­alone turnover in financial year 2011­12 was close to US $ 1.1 billion with the Group’s turnover in excess of US $ 1.6 billion.
  • 10. 6 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)  QUALITY POLICY Gammon India is the first Construction in India to have ISO9001 certification in design as well as execution for all Civil Engineering structures. Gammon is committed to form seamless partnership with its customers, so that their requirements become our challenge. Gammon’s quest for excellence is achieved by its innovative engineering and quality execution of the projects, on time, within budget, by its high performance team which is adaptable to each project..
  • 11. 7 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)  HEALTH SAFTEY AND ENVIRONMENTAL POLICY At Gammon, extensive health and safety guidelines defined standards for every project. Regular safety training programmes are undertaken at the sites. Further, regular health and fitness checkup for every member of our staff is mandatory. We maintain a high standard of safety through meticulous risk assessment. Gammon has a stellar record of twelve million hours of accident­free work at Kalpakkam. This is a consistent track record, which is no mean achievement, since most of our initiatives take place under hazardous geographical conditions. These are challenges that our staff can face because of their training. They also have the assurance of a health & safety code that is considerate and transparent. To set standards, we must first set an example. Gammon is an ISO 9001, ISO 14001 and OHSAS18001 certified company. We have a number of National Safety Awards to our credit. The concern inherent in our corporate culture inspires a sense of loyalty toward Gammon.  WORK CULTURE Work Culture emphasises: • Freedom to experiment • Continuous learning and training • Transparency • Quality in all aspects of work • Rewards based on performance and potential
  • 12. 8 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)  TRAINING Human Resources Department believes that Quality is the hallmark of any successful venture. Quality Training and Development ofHuman Resourcesisrealized through: Identifying training needs within the Organization and designing and implementing those need based training programs to bring about continuous up­gradation of knowledge, skills and employee attitudes. VISION&MISSION VISION “To Consistently build the reputation of Gammon amongst all stakeholders as a respected and influential leader in the Construction and Infrastructure Domain with Global Presence and Local Expertise backed with a sustained focus on attributes of Sustainability and Profitability and Employee engagement and Pride” “To be leaders in innovation engineering, with uncompromising integrity, timely delivery, pride and ownership and highest standards of quality to reinforce the positioning of the organisation as “Builders to the Nation”. MISSION "To design, build and service physical infrastructure for improved living, enhanced work environment and swift transportation."
  • 13. 9 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) ORGANIZATIONAL CHART CHIEF PROJECT MANAGER (C.P.M.) PROJECT MANAGER (P.M.) DEPUTY MANAGER (Dy. M.) ASSISTANT MANAGER (A.M.) ENGINEER (E.) JUNIOR ENGINEER (J.E.)
  • 14. 10 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) PROPOSED–PROJECT “Rehabilitation and Upgradation from 75 Km to 80.60 Km of NH-25.” (GANGA BRIDGE & FLYOVER PROJECT) KANPUR, INDIA
  • 15. 11 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) PRODUCT (S) & SPECIFICATIONS / ACTIVITIES / CODING Product:- “Rehabilitation and Upgradation from 75 Km to 80.60 Km of NH­25.” (GANGA BRIDGE & FLYOVER PROJECT). Specifications:- All the works shall be carried out as per standard practice of Engineering, IS­codes, I.R.C specifications and M.O.R.T.H specifications. Activities:- All the work consists :­ 1. Planning , 2. Quality Control , 3. Plant Information , 4. Execution ,
  • 16. 12 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) PLANNING DEPARTMENT Construction planning is a fundamental and challenging activity in the management and execution of construction projects. It involves the choice of technology, the definition of work tasks, the estimation of the required resources and durations for individual tasks, and the identification of any interactions among the different work tasks. A good construction plan is the basis for developing the budget and the schedule for work. Developing the construction plan is a critical task in the management of construction, even if the plan is not written or otherwise formally recorded. In addition to these technical aspects of construction planning, it may also be necessary to make organizational decisions about the relationships between project participants and even which organizations to include in a project. Essential aspects of construction planning include the generation of required activities, analysis of the implications of these activities, and choice among the various alternative means of performing activities. In developing a construction plan, it is common to adopt a primary emphasis on either cost control or on schedule control. Some projects are primarily divided into expense categories with associated costs. In these cases, construction planning is cost or expense oriented. Within the categories of expenditure, a distinction is made between costs incurred directly in the performance of an activity and indirectly for the accomplishment of the project. For example, borrowing expenses for project financing and overhead items are commonly treated as indirect costs. For other projects, scheduling of work activities over time is critical and is emphasized in the planning process. In this case, the planner insures that the proper precedence’s among activities are maintained and that efficient scheduling of the available resources prevails. Traditional scheduling procedures emphasize the maintenance of task precedence’s (resulting in critical path scheduling procedures) or efficient use of resources over time (resulting in jobshop scheduling procedures). Finally, most complex projects require consideration of cost and scheduling over time, so that planning, monitoring and record keeping must consider both dimensions. In these cases, the integration of schedule and budget information is a major concern.
  • 17. 13 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) A parallel step in the planning process is to define the various work tasks that must be accomplished. These work tasks represent the necessary frame work to permit scheduling of construction activities, along with estimating the resources required by the individual work tasks, and any necessary precedence’s or required sequence among the tasks. The terms work "tasks" or "activities" are often used interchangeably in construction plans to refer to specific, defined items of work. Planning department in Gammon India Limited uses Primavera as a powering tool for reducing risk. Primavera gives efficiency to plan a project, identify the resources required and identify the tasks required in a sequence, increasing probability of delivery of the project to the time, cost and quality objectives. Primavera gives you a powerful, visually enhanced way to effectively manage a wide range of projects and programs. From meeting crucial deadlines, to selecting the right resources, Primavera empowering your teams. The initial schedule of major construction activities S0 is prepared according to the Clients preference. S0 is the basis for all types of scheduling. Preliminary schedules representing the monthly work estimates are prepared based on experience considering local climate conditions, environment, learning curve, pace of work, mobilization, etc in Primavera. Productivities of different activities are estimated and validated during the course of execution. Man power requirement is calculated based on these productivities. Drawings released by the Client. Revisions and change orders are issued as and when there is a change and distributed to all the units. The planning system is updated in the first week of every month. Two progress schedules are maintained– original schedule prepared in the starting of the project, planned schedule which is modified according to the requirements and conditions. Actual progress is compared with the planned schedule and in case any delay in progress is then a Catch up schedule is prepared and executed accordingly to overcome the delay.
  • 18. 14 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) System / Plan Layout
  • 19. 15 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) QUALITY ASSURANCE & QUALITY CONTROL DEPARTMENT Quality is the key component which propels performance and defines leadership traits. At GIL, Quality Standards have been internalised and documented in Quality Assurance manuals. GIL recognizes the crucial significance of the human element in ensuring quality. Structured training programmes ensure that every GIL employee is conscious of his/her role and responsibility in extending Company’s tradition of leadership through quality. A commitment to safety springs from a concern for the individual worker – every one of the thousands braving the rigours of construction at numerous project sites. Gammon India Limited has a well­ established and documented Quality Management System (QMS) and is taking appropriate steps to improve its effectiveness in accordance with the requirements of ISO 9001:2008. Relevant procedures established clearly specify the criteria and methods for effective operation, control and necessary resources and information to support the operation and monitoring of these processes. QUALITY IMPLEMENTATION AT SITE GIL has established procedure for monitoring, measuring and analyzing of these processes and to take necessary actions to achieve planned results and continual improvement of these processes. It has also maintained relevant procedures to identify and exercise required control over outsourced processes, if any Systems and procedures have been established for implementing the requisites at all stagesofconstructionandtheyareaccreditedtotheInternationalstandardsofISO 9001:2008, ISO 14001:2004 and OHSAS 18001:2007. GIL continues to maintain the trail blazing tradition of meeting the stringent quality standards and adherence to time schedules in all the projects.
  • 20. 16 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) TESTS ON CEMENT CONSISTENCY AIM To determine the quantity of water required to produce a cement paste of standard consistency as per IS: 4031 (Part 4) ­ 1988. PRINCIPLE The standard consistency of a cement paste is defined as that consistency which will permit the Vicat plunger to penetrate to a point 5 to 7mm from the bottom of the Vicat mould. APPARATUS
  • 21. 17 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) VICAT APPARATUS Vicat apparatus conforming to IS: 5513 ­ 1976 Balance, whose permissible variation at a load of 1000g should be +1.0g Gauging trowel conforming to IS: 10086 ­ 1982 PROCEDURE i) Weigh approximately 400g of cement and mix it with a weighed quantity of water. The time of gauging should be between 3 to 5 minutes. ii) Fill the Vicat mould with paste and level it with a trowel. iii) Lower the plunger gently till it touches the cement surface. iv) Release the plunger allowing it to sink into the paste. v) Note the reading on the gauge. vi) Repeat the above procedure taking fresh samples of cement and different quantities of water until the reading on the gauge is 5 to 7mm. REPORTING OF RESULTS Express the amount of water as a percentage of the weight of dry cement to the first place of decimal. INITIAL AND FINAL SETTING TIME AIM To determine the initial and the final setting time of cement as per IS: 4031 (Part 5) ­ 1988. APPARATUS Vicat apparatus conforming to IS: 5513 ­ 1976 Balance, whose permissible variation at a load of 1000g should be +1.0g Gauging trowel conforming to IS: 10086 ­ 1982 PROCEDURE i) Prepare a cement paste by gauging the cement with 0.85 times the water required to give a paste of standard consistency.
  • 22. 18 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) ii) Start a stop­watch, the moment water is added to the cement. iii) Fill the Vicat mould completely with the cement paste gauged as above, the mould resting on a non­porous plate and smooth off the surface of the paste making it level with the top of the mould. The cement block thus prepared in the mould is the test block. INITIAL SETTING TIME Place the test block under the rod bearing the needle. Lower the needle gently in order to make contact with the surface of the cement paste and release quickly, allowing it to penetrate the test block. Repeat the procedure till the needle fails to pierce the test block to a point 5.0 ± 0.5mm measured from the bottom of the mould . The time period elapsing between the time, water is added to the cement and the time, the needle fails to pierce the test block by 5.0 ± 0.5mm measured from the bottom of the mould, is the initial setting time. FINAL SETTING TIME Replace the above needle by the one with an annular attachment. The cement should be considered as finally set when, upon applying the needle gently to the surface of the test block, the needle makes an impression therein, while the attachment fails to do so. The period elapsing between the time, water is added to the cement and the time, the needle makes an impression on the surface of the test block, while the attachment fails to do so, is the final setting time. REPORTING OF RESULTS The results of the initial and the final setting time should be reported to the nearest five minutes.
  • 23. 19 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) TESTS ON AGGREGATES SIEVE ANALYSIS AIM To determine the Grain size analysis of coarseaggregates for Concrete Material by sieving as per IS: 2386 (Part I) & Grain size analysis of Sand (As per Table 1000­2 MOST Specification). PRINCIPLE By passing the sample downward through a series of standard sieves, each of decreasing size openings, the aggregates are separated into several groups, each of which contains aggregates in a particular size range. APPARATUS A SET OF IS SIEVES i) A set of IS Sieves – a). Coarse Aggregate : 20mm (Nominal Singal Size) Sizes : 40mm, 20mm, 10mm, 4.75mm. b). Coarse Aggregate : 10mm (Nominal Singal Size) Sizes : 12.5mm, 10mm, 4.75mm, 2.36mm.
  • 24. 20 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) c). Coarse Aggregate : 20mm : 10mm and Sand (36:24:40) Sizes : 40mm, 20mm, 4.75mm, 0.600mm, 0.150mm. ii)Balance or scale with an accuracy to measure 0.1 percent of the weight of the test sample. iii) A set of IS Sieve for Sand : 10mm, 4.75mm, 2.36mm, 1.18mm, 0.600mm, 0.300mm, 0.150mm. PROCEDURE i) The test sample is dried to a constant weight at a temperature of 110 + 5 oC and weighed. ii) The sample is sieved by using a set of IS Sieves. iii) On completion of sieving, the material on each sieve is weighed. iv) Cumulative weight passing through each sieve is calculated as a percentage of the total sample weight. v) Fineness modulus is obtained by adding cumulative percentage of aggregates retained on each sieve and dividing the sum by 100. REPORTING OF RESULTS The results should be calculated and reported as: i) the cumulative percentage by weight of the total sample ii) the percentage by weight of the total sample passing through one sieve and retained on the next smaller sieve, to the nearest 0.1 percent.
  • 25. 21 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)
  • 26. 22 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)
  • 27. 23 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) AGGREGATE IMPACT VALUE TEST AIM To determine the Aggregate Impact value of coarse aggregates as per IS: 2386 (Part IV). APPARATUS
  • 28. 24 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) PROCEDURE i) The sample should be pass through 12.5mm and retained on 10mm IS sieve weight as W1. ii) The sample is filled in three layers and each layer is tampered with 25 blows of tampering rod. iii) Then the hammer of 14 kg is allowed to fall a height of 380mm. iv) After 15 blows, sample is taken off and sieve on 2.36mm IS sieve and weight passing as W2. REPORTING OF RESULTS Impact value = [W2 / W1] x 100%
  • 29. 25 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)
  • 30. 26 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) TESTS ON FRESH CONCRETE SLUMP AIM To determine the workability of fresh concrete by slump test as per IS: 1199 ­ 1959. APPARATUS i) Slump cone ii) Tamping rod
  • 31. 27 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) PROCEDURE i) The internal surface of the mould is thoroughly cleaned and applied with a light coat of oil. ii) The mould is placed on a smooth, horizontal, rigid and non­ absorbent surface. iii) The mould is then filled in four layers with freshly mixed concrete, each approximately to one­fourth of the height of the mould. iv) Each layer is tamped 25 times by the rounded end of the tamping rod (strokes are distributed evenly over the cross­ section). v) After the top layer is rodded, the concrete is struck off the level with a trowel. vi) The mould is removed from the concrete immediately by raising it slowly in the vertical direction. vii)The difference in level between the height of the mould and that of the highest point of the subsided concrete is measured. viii) This difference in height in mm is the slump of the concrete. REPORTING OF RESULTS The slump measured should be recorded in mm of subsidence of the specimen during the test. Any slump specimen, which collapses or shears off laterally gives incorrect result and if this occurs, the test should be repeated with another sample. If, in the repeat test also, the specimen shears, the slump should be measured and the fact that the specimen sheared, should be recorded.
  • 32. 28 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) CUBE STRENGTH TEST AIM To determine the compressive strength of concrete cube by Compression Testing Machine (CTM). APPARATUS i) CTM
  • 33. 29 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) PROCEDURE i) The internal surface of the mould is thoroughly cleaned and applied with a light coat of oil. ii) The mould is placed on a smooth, horizontal, rigid and non­ absorbent surface. iii) The mould is then filled in four layers with freshly mixed concrete, each approximately to one­fourth of the height of the mould. iv) Each layer is tamped 25 times by the rounded end of the tamping rod (strokes are distributed evenly over the cross­ section). v) After the top layer is rodded, the concrete is struck off the level with a trowel. vi) The mould is removed from the concrete immediately by raising it slowly in the vertical direction. vii)The difference in level between the height of the mould and that of the highest point of the subsided concrete is measured. viii) This difference in height in mm is the slump of the concrete. REPORTING OF RESULTS The slump measured should be recorded in mm of subsidence of the specimen during the test. Any slump specimen, which collapses or shears off laterally gives incorrect result and if this occurs, the test should be repeated with another sample. If, in the repeat test also, the specimen shears, the slump should be measured and the fact that the specimen sheared, should be recorded.
  • 34. 30 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)
  • 35. 31 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) OMC & MDD TEST This test is done to determine the maximum dry density and the optimum moisture content of soil using heavy compaction as per IS: 2720 (Part 8 ) – 1983.The apparatus used is:­ i) Cylindrical metal mould – it should be either of 100mm dia. and 1000cc volume or 150mm dia. and 2250cc volume and should conform to IS: 10074 – 1982. ii) Balances – one of 10kg capacity, sensitive to 1g and the other of 200g capacity, sensitive to 0.01g iii) Oven – thermostatically controlled with an interior of noncorroding material to maintain temperature between 105 and 110o C iv) Steel straightedge – 30cm long v) IS Sieves of sizes – 4.75mm, 19mm and 37.5mm. PREPARATION OF SAMPLE A representative portion of air­dried soil material, large enough to provide about 6kg of material passing through a 19mm IS Sieve (for soils not susceptible to crushing during compaction) or about 15kg of material passing through a 19mm IS Sieve (for soils susceptible to crushing during compaction), should be taken. This portion should be sieved through a 19mm IS Sieve and the coarse fraction rejected after its proportion of the total sample has been recorded. Aggregations of particles should be broken down so that if the sample was sieved through a 4.75mm IS Sieve, only separated individual particles would be retained. Procedure To Determine The Maximum Dry Density And The Optimum Moisture Content Of Soil A) Soil not susceptible to crushing during compaction – i) A 5kg sample of air­dried soil passing through the 19mm IS Sieve should be taken. The sample should be mixed thoroughly with a suitable amount of water depending on the soil type (for sandy and gravelly soil – 3 to 5% and for cohesive soil – 12 to
  • 36. 32 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) 16% below the plastic limit). The soil sample should be stored in a sealed container for a minimum period of 16hrs. ii) The mould of 1000cc capacity with base plate attached, should be weighed to the nearest 1g (W1). The mould should be placed on a solid base, such as a concrete floor or plinth and the moist soil should be compacted into the mould, with the extension attached, in five layers of approximately equal mass, each layer being given 25 blows from the 4.9kg rammer dropped from a height of 450mm above the soil. The blows should be distributed uniformly over the surface of each layer. The amount of soil used should be sufficient to fill the mould, leaving not more than about 6mm to be struck off when the extension is removed. The extension should be removed and the compacted soil should be levelled off carefully to the top of the mould by means of the straight edge. The mould and soil should then be weighed to the nearest gram (W2). iii) The compacted soil specimen should be removed from the mould and placed onto the mixing tray. The water content (w) of a representative sample of the specimen should be determined. iv) The remaining soil specimen should be broken up, rubbed through 19mm IS Sieve and then mixed with the remaining original sample. Suitable increments of water should be added successively and mixed into the sample, and the above operations i.e. ii) to iv) should be repeated for each increment of water added. The total number of determinations made should be at least five and the moisture contents should be such that the optimum moisture content at which the maximum dry density occurs,lies within that range. B) Soil susceptible to crushing during compaction – Five or more 2.5kg samples of air­dried soil passing through the 19mm IS Sieve, should be taken. The samples should each be mixed thoroughly with different amounts of water and stored in a sealed container as mentioned in Part A) C) Compaction in large size mould – For compacting soil containing coarse material upto 37.5mm size, the 2250cc mould should be used. A sample weighing about 30kg and passing through the 37.5mm IS Sieve is used for the test. Soil is compacted in five layers, each layer
  • 37. 33 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) being given 55 blows of the 4.9kg rammer. The rest of the procedure is same as above. REPORTING OF RESULTS Bulk density Y(gamma) in g/cc of each compacted specimen should be calculated from the equation, Y(gamma) = (W2-W1)/ V where, V = volume in cc of the mould. The dry density Yd in g/cc Yd = 100Y/(100+w) The dry densities, Yd obtained in a series of determinations should be plotted against the corresponding moisture contents,w. A smooth curve should be drawn through the resulting points and the position of the maximum on the curve should be determined. The dry density in g/cc corresponding to the maximum point on the moisture content/dry density curve should be reported as the maximum dry density to the nearest 0.01. The percentage moisture content corresponding to the maximum dry density on the moisture content/dry density curve should be reported as the optimummoisture content and quoted to the nearest 0.2 for values below 5 percent, to the nearest 0.5 for values from 5 to 10 percent and to the nearest whole number for values exceeding 10 percent.
  • 38. 34 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)
  • 39. 35 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) PLANT INFORMATION BATCHINGPLANT
  • 40. 36 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) EQUIPMENT USED IN CONSTRUCTION OF PRE-STRESSED BEAM  Shutter handling Gantry – 1 nos.
  • 41. 37 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)  Pre­stressing jack with Power pack – 2 nos.
  • 42. 38 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)  Grouting Pump (fressy j­600, 300kg/cm2 , 2hp) – 1 nos.  Grout mixer & Agitator – 1 nos.  Compressor 300 CFM – 1 nos.  Concrete pump –1 nos.  Poker Vibrators with needle – 4 nos.  Shutter vibrators – 4 nos.  Concrete production plant – 1 nos.
  • 43. 39 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) For Transportation of Concrete, steel bars, Aggregates, sand etc.  Transit Mixer (7m3 )  Truck
  • 44. 40 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) PROJECTEXECUTION METHOD STATEMENT FOR PRE STRESSED BEAM I. SCOPE: This method of statement is applicable for casting of P­40 to P­41 (G1) super structure Beam of the project “Rehabilitation and upgradation from 75.00 Km to 80.06 Km of NH­25 in the town of Kanpur (including bridge across river Ganga) to 4 lane divided carriageway configuration (contract package EW­ II UP­06). II. REFERENCE: 1. Drawing nos. DCPL/KANPUR/SUP/3X26/004 DCPL/KANPUR/SUP/3X26/008 2. MoRT&H Specifications 3. Contract Document – Technical specifications III. MATERIAL AND RESOURCES : For One Beam 1. Construction Material : Cement (OPC 53 Grade) 140 Bags Aggregate 20 mm 9 cum. Aggregate 10 mm 6 cum. Coarse Sand 9 cum. Reinforcement Steel as per list H T Steel (12.7mm) 1.20 ton Sheathing Pipe 130 Rm Anchorage 10 set (Guide cone, Bearing Plate, Anchor Grips) 2. Plant and Equipment’s : (Discussed in Plant Information) 3. Man Power : Skilled worker for concrete breaking ­ 4 nos. Skilled / S.skilled workers for concreting & grouting ­ 8 nos. Reinforcement steel cutting and bending ­ 6 nos. Reinforcement steel and shuttering fixing ­ 8 to 10 nos. Pre­Stressing ­ 6 nos.
  • 45. 41 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) IV. PROCEDURE : Form Work :  Formwork for the beam will be fabricated at the site as per approved drawing of Beam.  It is fabricated in panels for one beam of 2 sides. For the alignment of formwork, adjustable struts & through bolts shall be used.  Rigid working platform shall be made at beam top level eith structural steel. STEP 1:  After completing of casting bed and pedestals, fabricated beam bottom shall be erected and fixed as per our drawings. Uniform level of beam bottom shall be made. STEP 2:  One side shuttering panel shall be erected and placed over beam bottom as per drawing and true plumb of side shuttering to be made to start making of cable profile. Flexi foams with adhesive shall be used at joints of each panel in order to check the leakage of cement slurry during concreting. STEP 3: Cable Profile  Cable profile shall be marked by paint over beam bottom and side shuttering as per drawing. STEP 4: Reinforcement  Steel shall be fabricated in advance as per approved bar bending scheduled at centralized bending yard. Fabricated reinforcement shall be shifted to casting yard.  Reinforcement cage shall be fabricated in advance outside the casting bed. The pre­fabricated cage shall be shifted and placed at casting bed with the help of spreader beam and lifting Gantry as soon as bed is ready to receive reinforcement cage for next beam. STEP 5: Laying of Sheathing Pipe  Sheathing pipe of 75mm (or shown in approved drawing) dia. of single length shall be laid over marked profile (ref: STEP 3). Then the pipes shall be accurately located and tied as per drawings in both direction of vertical and horizontal.
  • 46. 42 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)  Ladders, spacers @ 2m C/C shall be provided to keep sheathing duct in position. 78mm dia. (or as suitable for sheathing pipe as per approved drawing) 150mm long coupler shall be provided for joining sheathing ducts and at both junctions of end Guide cone. Joints in between couplers and pipe shall be sealed with adhesive celling tape to prevent ingress of cement slurry in to ducts during concreting. In addition, couplers of adjacent ducts shall be staggered whenever possible. STEP 6: Closing of Shuttering  After checking of reinforcement and Profiling of sheathing, other side of beam shuttering shall be shifted and erected by means of shutter handling gantry. Shuttering shall be closed by side bolting as well as by fixing of tie angle and by adjustable props. STEP 7: Concreting of PSC Beam  Concrete of M50 grade shall be produced at batching plant and will be transported by transit mixers to the casting yard.  Placing of concrete shall be done by concrete pump or concrete conveyor.
  • 47. 43 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)  Concreting shall be done up to a depth of 400 mm andthe same layer will be continued until completion of the beam.  Compaction of concreting at bottom flange, web shall be done by using shutter vibrator and with immersion vibrator simultaneously.  Proper care shall be taken to ensure all the cables are free from concrete.  During concreting and up to 3 to 4hrs after completion of concreting, the cable duct shall be checked by movement of the dummy pipe through it for any ingress of concrete slurry. STEP 8: Threading of Cables  Cutting of HT Strands shall be done with angle grinder after uncoiling of HT Strands. Proper care shall be taken to avoid damages, kinks or bents and stacking shall be done properly preventing ground contact.  After 3 days of concrete, threading of cable shall be started from one end to the other end. Bundle of 12nos. HT Strands be made and same to be inserted manually inside the Sheathing duct. Proper care shall be taken to avoid damage to sheathing duct while threading. STEP 9: Curing & De­Shuttering  Normal curing shall be commenced after final setting of concrete i.e. 6hrs (approx.) depending on cement. Curing shall be continued until the concrete reaches strength 35N/mm2  After attaining strength of 10Mpa, the vertical side shuttering of PSC girder shall be removed and taken out of the bed with the help of gantry, to use in the second bed. STEP 10: Pre­Stressing Method of stressing: FPCC System (Proposed) or any other system approved by Engineer Important Points:  Stressing will be done after 10 days of concrete and achieves strength as specified in Drawing. Number of cables to be stressed, will be as mentioned in drawing.
  • 48. 44 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)  Future cable shall be stressed after completion of stressing and if required and as advised by the Engineer.  It is to be seen whether the extensions specified in the table account for effect of slip at each end or not. Accordingly, no extra allowance of slip should be made.  Extension at each end during stressing operation should be equal as far as possible, max. Difference should not exceed 5% of the prescribe extensions at each end. In case the required extensions are not obtained at the specified pressure, stressing should be continued till the required extensions are obtained subjected to jack pressures not exceeding the prescribe limits.  Difference between calculated and observed tension and elongations during the pre­stressing operations shall be regulated as per MORTH sec. 1807 under post tensioning head as point a, b, c, d. Method of Stressing  During curing of PSC Beam, arrangements for pre­stressing shall be started Erect a tripod or scaffolding tower on both end of PSC Beam.  HT Strands to be physically checked to ensure the strands are free from any friction.  Keep all strands ends at particular point approx. 750mm from the anchorage cone.  Clean all projected HT strands by petrol and afterward give a coating of wax for smooth operation.  Place the bearing plate on the buter face of each of the anchorage cone of PSC Beam.  Fix the anchorage grips in each hole of bearing plates by means of pipe.  Erect the pre stressing jack at both the end and place in first cable as per the stressing sequence and then fix the barrel and master grips in pre­stressing jacks.  Initial force shall be applied for tightening of jacks till slackness of the strands is removed. A mark shall be made at each strand at a suitable distance to measure the extensions of cables at both ends.  Incremental load shall be applied to keep control over the extensions. A see­saw action on loading may be applied to get equal extension at both the ends. Stressing to continue till it reaches its final extensions as per table i.
  • 49. 45 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)  Afterward, all other cables shall be stressed as per sequence in above manner.  Slip of each cable shall be measured and recorded. STEP 11: Grouting of cables in Pre­stressed girders Grouting of cables shall be conducted at stacking bed as soon as it stacked there. Materials:  Water: clean, potable water free form impurities will be used.  Cement: OPC as mentioned above  Sand: sand conforming to IS: 383 will be used.  Admixture: admixture if required conforming to IS: 9102 will be used. Equipment: (Discussed in Plant Information) Mixing of Grout:  Proportions of the required materials will be measured by weight before starting of mixing operation.  Water shall be added to the mixer followed by cement, sand & admixture / Readymade grout mixture.  Mixing shall be done for approximately 2 to 3 min until uniform and thoroughly blended grout is achieved.  Adequate care shall be taken to prevent any addition of water to mixed grout to increase fluidity.  Cubes of 100mm shall be taken for verification of compressive strength. Grouting Operations:  Grouting shall be carried out within 2 weeks of stressing of cables.  Ducts shall be flushed with water for cleaning as well as for wetting the surfaces of the ducts walls. Water used for flushing should of same quality as used for grouting.  After cleaning, all the water shall be drained thoroughly by vent pipe or by blowing compressed air through duct.  Sequence of grouting shall commence from bottom to top.
  • 50. 46 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112)  During and after 3 to 4 hours of grouting other non­stressed cables shall be checked manually for free movement.  All outlet points including vent openings should be kept open before to commencement of grouting. Injection of Grout:  After mixing grout should be kept in continuous movement and injection of grout must be continuous without any interruptions.  Grouting shall be commenced initially with a low pressure of injection of up to 0.3Mpa increasing it until the grout come out through the other end with same consistency as that of the grout @ injection end.  Full injection pressure (approx. 0.5Mpa) shall be maintained for a minimum of 1 min before closing the injection pipe. TIME CYCLE: Following is the time cycle of construction of 1 no. PSC Beam: S.No Activity No of Days 1. Bottom plate cleaning, leveling 0.5 day 2. Erection of outer shutter 0.5 day 3. Lowering of Pre-fabricated cage 0.5 day 4. Sheathing laying and profiling 0.5 day 5. Shutter closing and checking 0.5 day 6. Concreting 1 day 7. Waiting and de-shuttering of side shutter 1 day 8. Cable threading and Pre-stressing after 10 days 11 days 9. Lifting of Beam and vacating bed 0.5 day TOTAL 15 days
  • 51. 47 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) CHRONOLOGICAL TRAINING DIARY Date Description 06­06­2014 Joining letter taken from G.I.L office. 07­06­2014 Visit of office & site and meeting with Engineers. 08­06­2014 Sunday holiday. 09­06­2014 Visit the office & study the plan of project. (Planning Department) 10­06­2014 Discussion with the Planning Engineers. 11­06­2014 Study different drawing, work and contract documents. 12­06­2014 Meeting with Plant Engineer and Discussion about machines. 13­06­2014 Meeting with QC Engineer and Discussion about Quality Policy. 14­06­2014 Performing Sieve analysis & Aggregate impact value Test. 15­06­2014 Sunday holiday. 16­06­2014 Visit the site & Meeting with Execution Engineer and Execution Team. 17­06­2014 Visit full site and Discussion about Project Execution with Engineers. 18­06­2014 Construction of Pre­stressed Beam (G1) start (Bottom Plate clearing and leveling). 19­06­2014 Erection of outer shutter & Lowering of Pre­fabricated cage. 20­06­2014 Sheathing Laying and Profiling & Shuttering Closing and Checking.
  • 52. 48 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) 21­06­2014 Visit plant and see making of Concrete and Concreting of Beam in casting yard. 22­06­2014 Sunday holiday. 23­06­2014 De­shuttering of side shutter & Curing of Beam. 24­06­2014 Curing of Beam & Construction of Pier cap no. 43. 25­06­2014 Curing of Beam & Construction of Pier cap no. 43. 26­06­2014 Curing of Beam & Construction of Pile cap no. 45. 27­06­2014 Curing of Beam & Construction of Pile cap no. 45. 28­06­2014 Curing of Beam & Laying of Reinforcement on deck b/w P36 to P39. 29­06­2014 Sunday holiday. 30­06­2014 Curing of Beam & Laying of Reinforcement on deck b/w P36 to P39. 01­07­2014 Visit office (QC Department) and perform Cube Test of Beam P39­P40. 02­07­2014 Cable Threading and Pre­Stressing of Beam after 10 days in Casting yard. 03­07­2014 Lifting of Beam to Pier P40­P41 with the help of Gantry. 04­07­2014 Collecting all Drawings & Preparation of Project report. 05­07­2014 Discussion with Project Manager about Project Report. 06­07­2014 Sunday holiday. 07­07­2014 Submission of Project Report to Project Manager at G.I.L office.
  • 53. 49 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) SAFETY REQUIREMENT SAFETY APPLIANCES The requirement of sufficient number of safety appliances are planned well in advance and made available at stores. HEAD PROTECTION Every individual entering the site must wear safety helmet, confirming to IS: 2925­1984 with the chinstrap fixed to the chin. FOOT AND LEG PROTECTION Safety footwear with steel toe is essential on site to prevent crush injuries to our toes and injury due to striking against the object. HEARING PROTECTION Excessive noise causes damage to the inner ear and permanent loss of hearing. To protect ears use ear plugs / ear muff as suitable. EYE PROTECTION Person carrying out grinding works, operating pavement breakers, and those involved in welding and cutting works should wear safety goggles & face shield suitably Goggles, Safety Spectacles, face shield confirm to IS: 5983­1980. EAR PROTECTION Ear Muff / Earplug should be provided to those working at places with high sound levels (confirm to IS: 9167­1979). HAND AND ARM PROTECTION While handling cement and concrete & while carrying out hot works like gas cutting, grinding & welding usage of hand gloves is a must to protect the hand, 1) COTTON Gloves (for materials handling)­­‐IS: 6994­­‐1973 2) RUBEER Gloves­18” (380/450mm long) electrical grade, tested to 15000 Volts conforming to IS: 4770­­‐1991 3) LEATHER Gloves – hot work / handling of sharp edges .
  • 54. 50 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) RESPIRATORY PROTECTION Required respiratory protection according to the exposure of hazards to be provided. SAFETY NET Though it is mandatory to wear safety harness while working at height on the working platforms, safety nets of suitable mesh size shall be provided to arrest the falling of person and materials on need basis. FALL PROTECTION To prevent fall of person while working at height, personnel engaged more than 2m wear standard Full Body harness should be conforming to IS: 3521­1999 (Third Revision). 1) Lanyard should be of 12mm Polypropylene rope and of length not more than 2m. 2) Double lanyard, based on the requirement. SAFETY DURING STRESSING Use hydraulic equipment’s supplied with a relief valve. Place safely valve in between jacks and connection high­pressure hose. Use hosepipes in good conditions and avoid using worn out hosepipes. Check the concrete around bearing plate and anchorage to see whether there are any voids / honeycombing. Do not allow anybody behind stressing devices, in line with tendon, or near hydraulic hoses. When the stressing works are in progress no other work should continue in the vicinity. Health of safety systems incorporated in the stressing equipment shall be ascertained once a week. Display a clearly visible sign “DANGER…PRESTRESSING WORKS IN PROGRESS”
  • 55. 51 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) SUGGESTION Gammon India Limited (G.I.L) is playing a vital and very important role by giving the good and comfortable facilities of Bridges for the Roads users and also giving the better Structures which are giving beauty to our Country. In this process of construction there is big jams occurs on Service Roads. So I requested to G.I.L. to provide good moving facilities for service lane users. I have seen that several numbers of labour were working day &night as to complete the project in given estimated time. The Engineers Staff was also working very hard. Overall the Work of this Project is Satisfying its drawing& Specifications.
  • 56. 52 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) CONCLUSION It was a wonderful learning experience at Gammon India Limited site “Rehabilitation and Upgradation from 75 Km to 80.60 Km of NH­25 (GANGA BRIDGE & FLYOVER PROJECT)” for one months in KANPUR. I gained a lot of insight regarding almost every aspect of site. I was given exposure in almost all the departments at the site. The friendly welcome from all the employees is appreciating, sharing their experience and giving their peace of wisdom which they have gained in long journey of work. I am very much thankful for the wonderful accommodation facility from G.I.L. I hope this experience will surely help me in my future and also in shaping my career.
  • 57. 53 SUMMER TRAINING REPORT 2014 (INTEGRAL UNIVERSITY, LUCKNOW) MOHTISHAM ALI (1100111112) REFERENCES In Preparing this Project Report the following references has been taken in accounts are :­  SpecificationsofG.I.L.  SpecificationsofN.H.A.I.  Specificationsof MoRT&H.  Drawing nos. :­ 1. DCPL/KANPUR/SUP/3X26/004 2. DCPL/KANPUR/SUP/3X26/008  Contract Document – Technical Specifications.