SlideShare a Scribd company logo
1 of 30
TRAINING REPORT 
ON 
DESIGN & CONSTRUCTION OF CIVIL 
STRUCTURES & TRACKS WORKS 
FOR EASTERN DFCC 
AT 
TATA-ALDESA (JV) 
SUBMITTED BY:- UTSAV TIWARI 
ROLL NO.- 111000155
ABSTRACT 
This report is a summer internship report submitted in partial fulfillment of the requirements for the 
degree of Bachelor of Technology in Civil Engineering as per norms of GLA University Mathura. 
The author visited the site for construction of civil structure of DFCC, at Tundla in his training period 
and attained technical knowledge during the course, after which he was able to compile this report. 
The report consists of brief study and description of materials, equipments and procedures used at site 
for construction of an bridges. Author put his best to elaborate the actual site conditions, and problem 
faced at site and the tactics used to deal with them.The main objective of this report is to present a 
systematic text on the execution of construction of an bridges based on the Indian Standard codes. The 
report also covers the fundamental aspects of practical requirement such as safety, feasibility and 
economy at site.In this report the objective was to introduce, wherever necessary,material which 
embodies the most recent methodologies. 
1.Discusses introduction to organization profile, management structure, products, market share, 
problemdefinition (objectives, deliverables etc), and the main conclusions. 
2. Deals with materials and equipments used at site, literature review, contains description of the 
process plant/site wherepractical training was undertaken including diagrams for showing process 
scheme, major operations and process equipments, stream compositions, site conditions governing the 
process control ,discusses summary of the project with main findings. 
3.Deals with the results and laboratory tests were performed and the process and the calculations. 
4.References the method of adoption of the proposed solution by the organization. 
5.Conclusion.
ACKNOWLEDGEMENT 
IT IS INDEED A GREAT PLEASURE AND PRIVELEGE TO PRESENT THIS REPORT ON 
TRAINING AT TATA-ALDESA (JV) .I AM EXTREMELY GRATEFUL TO MY TRAINING 
AND PLACEMENT OFFICER FOR ISSUING A TRAINING LETTER,WHICHMADE MY 
TRAINING POSSIBLE AT TATA ALDESA (JV),TUNDLA. 
I WOULD LIKE TO EXPRESS MY GRATITUDE TO ER. SANJIV KUMAR (PROJECT 
MANAGER) FOR HIS INVALUABLE SUGGESTIONS,MOTIVATION,GUIDANCE AND 
SUPPORT THROUGH OUT THE TRAINING.HIS METHODOLOGY TO START FROM SIMPLE 
ANT THEN DEEPEN THROUGH MADE ME TO BRING OUT THIS REPORT WITHOUT 
ANXIETY. 
THANKS TO ALL OTHER TATA ALDESA (JV) OFFICIALS,OPERATORS AND ALL OTHER 
MEMBERS OF TATA ALDESA (JV),YET UNCOUNTED FOR THEIR HELP IN COMPLETING 
THE PROJECT AND SEE THE LIGHT OF SUCCESS. 
I AM VERY THANKFUL TO FRIENDS,COLLEAGUES AND ALL OTHER PERSONS WHO 
RENDERED THEIR ASSISTANCE DIRECTLY OR INDIRECTLY TO COMPLETE THIS 
PROJECT WORK SUCCESSFULLY. 
I EXTENDED MY DUE THANKS TO ER. MUKESH KUMAR WHO GAVE ME VALUABLE 
TIME AND SUGGESTIONS AND GUIDE ME A LOT AT VARIOUS STAGES OF MY SUMMER 
TRAINING.
TABLE OF CONTENTS 
S NO. CONTENT PAGE NO. 
ABSTRACT i 
CERTIFICATE ii 
ACKNOWLEDGEMENT iii 
1 INTRODUCTION 1 
1.1 CLIENT’S PROFILE 1 
1.1.1 GENESIS 1 
1.1.2 MISSION 1 
1.1.3 SALIENT FEATURES 2 
1.1.4 OBJECTIVE 4 
1.2 CONTRACT’S PROFILE 4 
1.3 PROJECT PROFILE 5 
1.3.1 CONTRACT STRATEGIES 6 
1.3.2 TECHNOLOGICAL INNOVATIONS 7 
1.3.3 ALIGNMENT LAYOUTS 7 
1.3.4 PROJECT MAP 8 
2 SUB STRUCTURAL WORK 
HYDRAULIC PILING RIG 
2.1 MACHINERY 9 
2.2 PROCESS FOR HYDRAULIC PILING WORK 9 
2.2.1 HYDRAULIC PILING 9 
2.2.2 REINFORCEMENT 10 
2.2.3 CONCRETING 11 
2.2.4 EXTRACTION OF TEMPORARY CASING 12 
2.3 METHODOLOGY 12 
3 LABATORY TESTS AND RESULTS 
3.1 CONCRETE TEST 
3.1.1 SLUMP TEST 14 
3.1.2 150 x 150MM CUBE MOULDS 15 
3.1.3 DIGITAL COMPRESSION TESTING MACHINE 16
3.2 AGGREGATE TEST 
3.2.1 AGGREGATE IMPACT TEST 17 
3.2.2 SIEVE ANALYSIS FOR FINE AGGREGATE 18 
3.2.3 SIEVE ANALYSIS FOR COARSE AGGREGATE 19 
3.2.4 SPECIFIC GRAVITY TEST FOR AGGREGATE 20 
3.3 CEMENT TEST 
3.3.1 STANDARD CONSISTENCY OF CEMENT 21 
4 REFERENCES 23 
5 CONCLUSION 24
INTRODUCTION 
1.1 CLIENT’S PROFILE 
Genesis of DFCCIL 
The Indian Railways' quadrilateral linking the four metropolitan cities of Delhi, Mumbai, Chennai and 
Howrah, commonly known as the Golden Quadrilateral and its two diagonals (Delhi-Chennai and 
Mumbai-Howrah), adding up to a total route length of 10,122 km carries more than 55% of revenue 
earning freight traffic of IR. The existing trunk routes of Howrah-Delhi on the Eastern Corridor and 
Mumbai-Delhi on the Western Corridor are highly saturated with line capacity utilization varying 
between 115% and 150%. 
The rapid growth of Indian economy in the last few years has created demand for additional capacity 
of rail freight transportation, and this is likely to grow further in the future. This burgeoning demand 
led to the conception of the dedicated freight corridors along the Eastern and Western Routes. Hon'ble 
Minister for Railways, made this historic announcement on the floor of the House in the Parliament 
while presenting the Railway Budget for 2005-06. 
In April 2005, the Project was discussed at the Japan-India Summit Meeting. It was included in the 
declaration of co-operation signed between the Hon'ble Prime Ministers of India and Japan for a 
feasibility study and possible funding of the dedicated rail freight corridors by Japanese Government. 
The feasibility study report was submitted to Ministry of Railways in October 2007. 
In the meanwhile, Ministry of Railways initiated action to establish a Special Purpose Vehicle for 
construction, operation and maintenance of the dedicated freight corridors. This led to the 
establishment of "Dedicated Freight Corridor Corporation of India Limited (DFCC)", to undertake 
planning & development, mobilization of financial resources and construction, maintenance and 
operation of the dedicated freight corridors. DFCC was incorporated as a company under the 
Companies Act 1956 on 30th October 2006. 
Mission 
As the dedicated agency to make the vision into reality, DFCCIL's mission is: 
 To build a corridor with appropriate technology that enables Indian railways to regain its 
market share of freight transport by creating additional capacity and guaranteeing efficient, 
reliable, safe and cheaper options for mobility to its customers. 
 To set up Multimodal logistic parks along the DFC to provide complete transport solution to 
customers.
 To support the government's initiatives toward ecological sustainability by encouraging users 
to adopt railways as the most environment friendly mode for their transport requirements. 
 Salient Features 
 Dedicated Freight Corridors are proposed to adopt world class and state-of-the-art 
technology. Significant improvement is proposed to be made in the existing carrying capacity 
by modifying basic design features. The permanent way will be constructed with significantly 
higher design features that will enable it to withstand heavier loads at higher speeds. 
Simultaneously, in order to optimize productive use of the right of way, dimensions of the 
rolling stock is proposed to be enlarged. Both these improvements will allow longer and 
heavier trains to ply on the Dedicated Freight Corridors. 
 The following tables provide comparative information of the existing standards on Indian 
Railways and the proposed standard for DFCC 
 Upgraded Dimensions Of DFC 
Feature Existing On DFC 
Moving 
Dimensio 
ns 
Height 
7.1 m for Western DFC 
5.1 m for Eastern DFC 
Width 
Container 
Stack 
Single Stack 
Double Stack 
Train 
length
Train 
Load 
 Upgraded Design Features Of DFC 
Feature Existing On DFC 
Heavier Axle Loads 
Axle Load 22.9t/25t 
32.5t/25t for Track Superstructure 
Track Loading Density 
Maximum Speed 
Single Stack 
Double Stack 
Grade Up to 1 in 100 1 in 200 
Curvature Up to 10 degree Up to 2.4 degree 
Traction Electrical(25 KV) Electrical(2x25 KV) 
Station Spacing 7-10 Km 40 Km 
Signalling 
Absolute/Automatic 
with 1 Km spacing 
Automatic with 2 Km 
spacing 
Communication 
Emergency 
Sockets/Mobile Train 
Radio 
Mobile Train Radio
OBJECTIVE 
1.2 CONTRACT’S PROFILE 
The Rs 3,300-crore eastern dedicated rail freight corridor (EDRFC) project has received a major boost 
with Tata Projects, the infrastructure arm of Tata Group, starting the construction work on the 337 km 
Bhaupur-Khurja stretch in Uttar Pradesh in a 50:50 joint venture partnership with Aldesa of Spain. 
Briefing media here, Tata Projects Managing Director Vinayak Deshpande said this is the first major 
contract awarded for the Eastern DFCC through an international competitive bidding process and 
involves construction of a 337 kilometers double track line, and 14 km of single line - between 
Bhaupur and Khurja in Uttar Pradesh. He also pointed out that the World Bank has sanctioned $975 
million for this complete project. 
Also, he added, this will be a Design-Build Lump sum contract and will be executed within four 
years. Elaborating, he said the Dedicated Freight Corridor is an ambitious programme of the Union 
Ministry of Railways for promoting a seamless movement of rail freight traffic. It has been designed 
for 32.5 ton axle load as compared to the current carriage tracks of 22.5 ton axle load which is at par 
with the standard in America, Russia, and China. 
Responding to a query, Deshpande said this project would help to take over the heavy burden of 
freight from the passenger rail tracks and roads. At present, around 60 per cent of the freight traffic 
moves on golden quadrilateral, which would definitely get declogged from the eastern to western side, 
he added. 
The company has started work and expects to complete it by 2016 for trial runs. The commissioning
would take place by end 2017. Aldesa, the Spanish JV partner, will provide the technological 
expertise in mechanically laying the tracks using the best technologies used in Europe and other 
developed countries. 
1.3 PROJECT PROFILE 
The Eastern Dedicated Freight Corridor with a route length of 1839 km consists of Dankuni in West 
Bengal & Khurja in Uttar Pradesh & an electrified single-track segment of 447 km between Ludhiana 
(Dhandarikalan) - two distinct segments: an electrified double-track segment of 1392 km between 
Khurja - Dadri in the state of Punjab and Uttar Pradesh. Due to non - availability of space along the 
existing corridor particularly near important city centers and industrial townships, the alignment of the 
corridor takes a detour to bypass densely populated towns such as Mughalsarai, Allahabad, Kanpur, 
Etawah, Ferozabad, Tundla, Barhan, Hathras, Aligarh, Hapur, Meerut, Saharanpur, Ambala, Rajpura, 
Sirhind, Doraha and Sanehwal. Since the origin and destinations of traffic do not necessarily fall on 
the DFC, a number of junction arrangements have been planned to transfer traffic from the existing 
Indian Railway Corridor to the DFC and vice versa. These include Dankuni, Andal, Gomoh, 
Sonnagar, Ganjkhwaja, Mughalsarai, Jeonathpur, Naini/Cheoki, Prempur, Bhaupur, Tundla, 
Daudkhan, Khurja, Kalanaur, Rajpura, Sirhind and Dhandarikalan. The following table depicts the 
distance traversed through each state. 
Eastern DFC 
States KMs 
Punjab 88 
Haryana 72 
Uttar Pradesh 1049 
Bihar 93 
West Bengal/Jharkhand 538 
Total 1839 
The Eastern Corridor will traverse 6 states and is projected to cater to a number of traffic streams - 
coal for the power plants in the northern region of U.P., Delhi, Harayana, Punjab and parts of 
Rajasthan from the Eastern coal fields, finished steel, food grains, cement, fertilizers, lime stone from 
Rajasthan to steel plants in the east and general goods. The total traffic in UP direction is projected to 
go up to 116 million tonnes in 2021-22. Similarly, in the Down direction, the traffic level has been 
projected to increase to 28 million tons in 2021-22. As a result, the incremental traffic since 2005- 
2006, works out to a whopping 92 million tons. A significant part of this increase would get diverted 
to the Dedicated Freight Corridor. 
The Eastern DFC will be executed in a phased manner. The World Bank funding is being planned in 
three tranches APL1 for Khurja- Kanpur, APL2 for Kanpur-Mughalsarai and APL3 for Khurja- 
Ludhiana. The Loan Agreement for APL1 between World Bank and DFCCIL has been executed for 
USD 975 million. 
As per RITES project report, the traffic that would move on the Eastern DFC, excluding the base year 
traffic (2005-06), is projected as below
Contract Strategies 
Contract Strategy for Eastern Corridor World Bank funded portion will be generally on following 
lines: 
Procurement Guidelines: For consultancy work guidelines for selection and employment of 
consultant under IBRD loans and IDA Credits and Grant by World Bank borrowers issued in January 
2011 will be applicable. For procurement of goods and works procurement guidelines under IBRD 
Loans and IDA Credits and Grant by World Bank borrowers issued in January 2011 will be 
applicable. 
Procurement of Works: Procurement of works will be two stages bidding after prequalification. 
Prequalification of bidders will be done on the basis of standard prequalification document of World 
Bank. Bid document will be generally as per standard bidding document for procurement of plant 
design, supply and installation issued by World Bank with general conditions based on FIDIC Yellow 
Book. 
Bank financing for the Eastern DFC Program would be provided under an Adoptable Program Loan 
(APL) in three phases. Each phases of the APL would be comprised of a loan for one of the three 
sections and a continuing program of technical assistance for IR and DFCCIL. The sequence of the 
loans is envisaged to be: APL 1 for Khurja - Kanpur; APL 2 for Kanpur - Mughalsarai and APL 3 for 
Ludhiana - Khurja - Dadri, with about a one year lag between these APL phases. 
TRAFFIC PROJECTIONS ON EASTERN DFC 
(in million tons/year) 
Direction/Commodity 2016-17 2021-22 
UP Direction 
Power House coal 54.46 61.96 
Public Coal 0.61 0.95 
Steel 8.24 9.74 
Others 1.61 2.96 
Logistic Park 1.20 2.40 
Sub-Total 66.12 78.01 
Down Direction 
Fertilizer 0.23 0.42 
Cement 0.78 1.52 
Limestone for the 
Steel Plants 
4.99 5.00 
Salt 0..68 1.03 
Others 1.61 2.96
Logistic Park 1.20 2.40 
Sub-Total 9.48 13.32 
Grand Total 75.60 91.33 
Rites Report: Table 14.3. of Eastern Corridor PETS Report 
It is also proposed to set up Logistics Park at Kanpur in U.P. and Ludhiana in Punjab. These parks are 
proposed to be developed on Public Private Partnership mode by creating a sub-SPV for the same. 
DFCCIL proposes to provide rail connectivity to such parks and private players would be asked to 
develop and provide state of the art infrastructure as a common user facility. 
Technological Innovations 
DFC will build its two corridors with appropriate technology that will enable Indian Railways to 
regain its market share of freight transport by creating additional capacity, efficient, reliable, safe and 
cheaper options for mobility to its customers. To achieve these objectives, DFCC will encourage use 
of latest technological innovations in the area of track, electrification, signaling and train operations. 
All DFC contracts will be Design-Build contracts to permit new technologies to be adopted on DFC 
corridors. 
Alignment Layout 
 Khurja - Bhaupur Section
Project Funding for Corridors 
The project cost for both the corridors was initially estimated by RITES, in January 2007 as Rs. 
28,000 crore. This cost was subsequently revised to about Rs. 37,000 crore by Japan International 
Cooperation Agency in its feasibility Report submitted to the Ministry of Railways in October 2007. 
When revised to 2009 costs, the two corridors are likely to cost in the region of Rs.54,000 crore, 
resulting in a project completion cost of about Rs. 80,000 crore in 2017-2018. The cost for the project 
will be funded by a combination of debt from bilateral/multilateral agencies, equity from Ministry of 
Railways and Public Private Partnership. The capital structure of DFCCIL will entail a debt equity 
ratio of 2:1. 
Eastern Corridor 
The Eastern Corridor is proposed for funding from the World Bank, internal generation and Public 
Private Partnership. Financing for the 725 km section between Ludhiana and Mughalsarai will be 
undertaken over three phases by World Bank through an IBRD loan. The section from Mugalsarai to 
Sonnagar will be funded directly by Ministry of Railways while the 5.34 km section from Sonnagar to 
Dankuni will be financed through Public Private Partnership. The first tranche of the IBRD Loan, 
aggregating to USD 975 million has already been signed by Ministry of Railways & World Bank. 
Western Corridor 
Western Corridor is funded by the Government of Japan. It was envisaged that a STEP (Special 
Terms of Economic Partnership) Loan in the region of ¥677 billion will be provided by the 
Government of Japan to finance the construction of Western DFC as well as procurement of 
Locomotives for the Ministry of Railways. The loan is extended on soft terms for a period of forty 
years with a moratorium of ten years. The remaining portion of the project construction cost will be 
borne by Ministry of Railways as equity funding to the Dedicated Freight Corridor Corporation of 
India. The first tranche of the loan for 90.2 Billion Yen for construction between Rewari and 
Vadodara has been signed. Funding for Phase II (Vadodara-JNPT) of the Corridor was also signed 
with JICA for 266 Billion Yen in March, 2013. 
PROJECT MAP
HYDRAULIC PILING RIG 
2.1 MACHINERY 
 HYDRAULIC PILING RIG 
 AUGER 
 BUCKET 
 LINER(3-5m long) 
 BENTONITE TANK 
 VERTICAL PUMP 
 DEWATERING PUMP (VERTICAL) 
 TREMIE PIPE WITH HOPER 
 BATCHING PLANT 
 TRANSIT MIXERS 
 D.G. SET 
 BAR CUTTING MACHINE 
 SOUNDING MACHINE 
2.2 PROCESS FOR HYDRAULIC PILING WORK 
i) HYDRAULIC PILING
1) Hydraulic bored piling plant shall be used. The piling plants consist of a telescopic kelly bar and 
the lower of the kelly bar is an adaptable to other drilling tools. 
2) On completion of the temporary platform, the piling rigs shall be moved in assembled and ready 
for work on the installation of the 800 mm and 1050 mm diameter bored piles. A test pile for vertical 
pile shall be carried out to verify the designed load carrying capacity of the piles, the installation of 
which shall be determined jointly with Employer’s Representative. 
3) Bored piles are cast-in-situ piles formed by excavating a hole of the specified size (diameter), to the 
required depth and casting the excavated hole with concrete of specified strength after the 
reinforcement is lowered into the hole. 
4) The hydraulic pile points setting out shall be provided by a qualified Surveyor. The boring plant 
will be moved to the pile point intended for excavation. The kelly bar mounted with an auger is placed 
just above the pile point. The vertically of the kelly bar should be checked by means of a spirit level. 
Adjustment should be made so as to enable the kelly bar to be as vertical as possible. Then the 
positions of the auger are checked against the pile point. 
5) Adjustment should be made so that the center of the auger is nearest to the pile point. The auger is 
then lowered and boring operating commenced. 
6) Reasonable care should be taken so that the pile position and vertically are constructed within the 
specified tolerance i.e. 75mm and 1 in 150 respectively. 
7) Boring commerce after the positions of the boring plant is checked. Usually, an auger of the 
required size is used to excavate hole is collapsible; a temporary casing of the same size should be 
installed to prevent collapse. Excavation of the hole continued until the required depth. 
8) At the point of encountering the rock head level where soil drilling tools are unable to penetrate the 
strata any further, boring shall cease in order that the Employer’s Representative to verify the 
occurrence and confirm the rock head reduced level. 
9) Rock drilling tools shall be used for drilling into and through rock. 
10) After reaching the required depth, a cleaning bucket will be used to clean up the bottom of the 
borehole. A joint measurement of the depth should be made before lowering of reinforcement and 
concreting. 
ii) Reinforcement
1) Reinforcement to bored piles will be fabricated in the reinforcement yard and transported to the 
borehole for placing. After fabrication by the bar benders, the helical links will be tack welded to the 
main reinforcement Laps are also to be welded sufficiently so that they are intact during 
transportation. 100 mm diameter round spacers will be welded to the reinforcement to provide the 
cover to the reinforcement against the soil during concreting. 
2) The reinforcement will be lowered to the completed bore hole, prior to concreting, by means of a 
service crane arid to be adjusted to the correct 
level. 
iii) Concreting 
Concreting conforming to the specification will be delivered to the site by Ready Mixed supplier. 
If bore hole are dry, the concrete shall be discharges through a short funnel at the top of the bored 
hole to prevent free falling concrete hitting the sides of the bore. If bored holes contain either water or 
bentonite drilling mud the concrete shall be placed by the tremie method. 
(I)Dry Hole Mix This mix shall be designed to give a works cube strength of 35 Mpa at 28days with a 
slump of 100 ± 25mm. 
(ii) Tremix Mix 
(iii) This mix shall be designed to give a minimum works cube strength of 35 Mpa at 28 days with a 
slump of 175 ± 25mm. 
(iv) The method of placing shall be such as to ensure that the concrete in its final positions shall be 
dense and homogeneous. 
(v) The piles shall be concrete in one continuous operation immediately after the excavation has been 
completed and inspected where inspection is required by the Specification. If the continuity of placing 
the concrete is interrupted, no further concrete shall be placed without the prior approval of the 
Engineer.
iv) Extraction Of Temporary Casing 
All temporary casings are to be extracted immediately after completion of 
concreting. A vibro-Hammer will be used to extract the casing. 
Reasonable care should be taken to ensure that the concrete level is above the cut-off level after 
extracting of casing point. 
2.3 METHODOLOGY 
1)PILE LOCATION: 
THE WORKING PILES SHALL BE INSTALLED AT LOCATIONS AS PER DRAWING. 
2)CASING DRAWING: 
LINER OF 1m DIA WITH 8mm/6mm THICK WILL BE PLACED IN THE POSITION AND 
PUSHED DOWN THE HAMMER ,SAME WILL BE CHECKED FOR VERTICALITY AND 
BORING WILL BE CONTINUED. 
3)BENTONITE FOR PILING: 
BENTONITE SHOULD BE USED IN THE PILING WORKS CONFORMING TO THE 
FOLLOWING SPECIFICATIONS. 
DENSITY OF MUD WILL NOT EXCEED:1.05 gm/cc-1.12 gm/cc 
MARSH CONE VISCOSITY:30-40 sec 
SWELLING INDEX:AS PER IS 6186-1986 
PH VALUE:9.5-11.50 
SAND CONTENT>.075mm: NOT MORE THAN 1% 
LIQUID LIMIT:NOT LESS THAN 400% 
THE BENTONITE REQUIRED FOR PILING WILL BE MIXED 24 HRS IN ADVANCE AND 
STORED IN THE BENTONITE TANKS.AS THE BORING PROGRESSES THE BORE WILL BE 
TOPPED WITH BENTONITE SO AS TO MAINTAIN A HEAD OF AT LEAST 1m ABOVE THE 
WATER TABLE.THE SPECIFIC GRAVITY OF BENTONITE IS LESS THAN 1.2g/cc AT THE 
BOTTOM OF THE BORE BEFORE COMMENCING CONCRETING OPERATION.
4)BORING: 
FOR BORING OF THE PILE SOIL AUGER AND BUCKET WILL BE USED.WHILE 
BORING,CARE WILL BE TAKEN TO MAINTAIN THE HEAD HEAD OF BENTONITE 
SLURRY BY CONSTANT TOPPING OF THE BORWE.THE DEPTH OF THE BORE WILL BE 
CHECKED WITH THE HELP OF SOUNDING CHAIN TAKING REFERENCE FROM THE TOP 
OF LINER.BEFORE LOWERING THE CAGE WE WILL INSURE THE BOTTOM CLEANING 
BY PUT THE BUCKET AT BOTTOM LEVEL OF BORINGS. 
5)REINFORCEMENT CAGE: 
a) FABRICATION: 
REINFORCEMENT WILL BE CUT USING CUTTING MACHINES OR MANUALLY AS 
REQUIRED.THE CAGE WILL BE FABRICATED AS PER APPROVED BBS,COVER BLOCKS 
WILL BE PROVIDD AT A SPACING OF 3m c/c ON ALL FOUR SIDES OF THE CAGE TO 
PROVIDE A CLEAR COVER OF 75mm TO THE RING.THE REBAR CAGE WILL BE OFFERED 
FOR CHECKING. 
b)LOWERING OF CAGE: 
THE APPROVED CAGE WILL BE LOWERED INTO THE BORE IN SEGMENTS.CRANE OR 
HYDRA WILL BE USED TO HANDLE THE CAGE SEGMENTS,THE FIRST SEGMENT WILL 
BE HELD IN POSITION BY A SUITABLE BAR ACROSS THE CASING AND THE SECOND 
SEGMENT WILL BE LIFTED AND POSITIONED OVER THE FIRST SEGMENT.THE 
COUPLER WILL BE USED IN PLACE OF LAPS OR THE LAP JOINT WILL BE TIED WITH 
BINDING WIRE AND SUBSEQUENTLY WELDED TO ENSURE NO SLIPPAGE OCCURS 
WHILE LOWERING OF CAGE.THIS PROCESS WILL BE REPEATED TILL ALL THE 
SEGMENTS ARE LOWERED.THE LAST SEGMENT WILL HAVE SUITABLE HOOKS TO 
ENSABLE HANGING OF CAGE FROM THE LINER. 
6)FLUSHING: 
THE PRE ASSEMBLED TREMIE PIPES SHALL BE LOWERED IN THE BORE HOLE 
KEEPING THE BOTTOM 300mm ABOVE THE TERMINATION LEVEL.FLUSHING OF THE 
BORE WILL BE DONE WITH BENTONITE PUMP ATTACHED WITH TREMIE PIPE AND 
TREMIE HEAD.FLUSHING OF FRESH BENTONITE WILL BE DONE 
CONTINOUSLY WITH FRESH BENTONITE SLURRY TILL THE CONSISTENCY 
OF INFLOWING AND OUT FLOWING SLURRY IS SIMILAR.FOR 
ENVIRONMENT ASPECT WATER WILL BE RECYCLED FOR THE DRILLING 
PROCESS.A PIT SHALL BE MADE FOR STORING BENTONITE SLURRY AND 
SHALL BE DISPOSED OFF ON THE LOCALLY AVAILABLE LAND FILL SITE 
AFTER DRY UP INTO THE PIT,SPILLAGE OF OIL AND GREASE SHALL BE 
DISPOSED AS PER HAZARDOUS WASTES RULES,2008. 
7)CONCRETING: 
THE REQUIRED GRADE OF CONCRETE WILL BE PRODUCED AS PER THE APPROVED 
DESIGN MIX AT THE CENTRALIZED BATCHING PLANT AND TRANSPORTED BY 
TRANSIT MIXERS,ENSURING A SLUMP RANGE OF 150mm TO 200mm AT SITE.THE FIRST 
CHARGE OF CONCRETE WILL BE PLACED WITH A FLOATING PLUG INSIDE,THE 
TREMIE AND,WITH SUITABLE CHARGE PLATE AT THE HOPPER MOUTH.THE 
CONCRETE WILL BE ADEQUATE IN THE TREMIE WITH BE PLACED TAKING 
NECESSARY PRECAUTINS TO ENSURE THAT ADEQUATE LENGTH OF TREMIE IS 
EMBEDDED IN CONCRETE CUBES SHALL BE TAKEN AS PER RELEVENT CODE 
PROVISION.
LABATORY TESTS AND RESULTS 
CONCRETE TEST 
SLUMP TEST 
 STATEMENT :- 
Slump test is very common test for and it is very important for consistency of concrete. It is not a 
suitable for very wet or very dry concrete. It is used convenient a control test and it gives 
uniformanity concrete. From the batch to batch. 
APPRATUS :- 
1) Slump cone 
2) Tamping rod 
Dimension of slump cone :- 
Bottom diameter – 20 cm 
Top diameter – 10 cm 
Height – 30 cm 
 PROCEDURE :- 
Take the slump cone. The cone should be cleaned and free from moisture of any old concrete before 
following test. The mould is placed on a smooth and on a smooth horizontally rigid and non-absorbent 
surface. Then the fresh concrete in placed on slump cone mould in four layer. Each layer has been 
rodded. The concrete is struck off level with trowel and tamping rod the mould is removed gradually 
from the concrete and by raising slowly and carefully in a vertically position. 
Then different in level between height of mould and that or highest part of subsides concrete is 
measured this difference in height in mm is known as slump concrete and it indicates the 
characteristic of concrete adding is slump value. If the concrete slumps it is called true slump.
150 x 150MM Cube Moulds Test 
1. Purpose 
The moulds are used for making of concrete cubes as per IS :516 – 1959 – Methods of tests for 
strength of concrete. 
2. Apparatus 
Wheel barrow, sampling scoop, trowel cube moulds of 15 x 15 x15 cm size and tamping bar 16 mm in 
diameter, 0.6 m long and bulleted point at the lower end. 
3. Procedure as per IS 516 
a. Firstly decide the number of samples to be taken during concreting. 
b. Oil the interior surface of the mould with mould releasing oil to prevent adhesion of the concrete. 
c. Collect the sample in a wheelbarrow after mixing the concrete 
properly in the transit mixer. 
d. Remix the sample thoroughly in wheelbarrow with sampling scoop. 
e. After remixing immediately fill the mould in layers approximately 5 cm deep. 
f. During filling the mould, the scoop shall be moved around the top edge of the mould as the concrete 
slides from it, in order to ensure a symmetrical distribution of the concrete within the mould. 
g. Each layer shall be compacted with the tamping rod (of 16 mm dia 60 cm long and rounded at one 
end).Minimum 35 strokes distributed in a uniform manner over thecross-section of the mould. 
h. After compacting the tip layer, top surface of the concrete shall be finished level with the top of the 
mould, using atrowel. 
i. Store the cube moulds in a place which is free from vibration and cover the surface of the concrete 
with a piece of dampsacking for initial 16 to 24 hours. 
j. After this period, mark the specimen and remove it from the mould by dismantling and submerge it 
clean water at a temperature of 27 +2oC and keep it till the time of testing for compressive strength.
DIGITAL COMPRESSION TESTING MACHINE 
1. Purpose: 
The digital compression – testing machine is used to determine the compressive strength of hardened 
concrete specimens. 
2.Procedure as per IS 516 – Methods of tests for strength of concrete 
1. Keep the specimen to be tested centrally on the clean lower platen so that small clearance is left 
between the upper platen and the top the specimen under test. 
2. Close the pressure release valve. 
3. Make the digital display to read “Zero” by adjusting the zero knobs. 
4. Put the display unit on “Peak Hold” mode to hold the maximum load reading. 
5. Start applying the load at the specified pace rate, which could be maintained by adjusting the slow 
fast knob. 
6. If the pace rate is on higher side the indicator displays red color and the pace rate is on lower side 
the indicator will display yellow color. 
7. If the pace rate is exactly equal to set rate then the indicator will display green color. 
8. As soon as sample fails, release the pressure slowly by opening valve. 
9. The digital display will be holding the maximum load reading at which sample has failed. Note 
down the pattern of failure and calculate the compressive strength in N/mm2 or kg/cm2. 
10. Pace rate for 15 cm cube is 5.15 kN/s. 
11. Before starting another test, clean the lower platen and bring the digital display to “Zero” position 
by depressing the “Reset” switch.
AGGREGATE TEST 
AGGREGATE IMPACT TEST 
 IMPACT VALUE :- 
The Impact value test generally used as alternative to its crushing strength to know quality of 
aggregate. It is also useful for to know the quality of aggregate this test is apply only 10mm metal. So 
as to decide its suitability for use in the desired concrete mix. 
PROCEDURE :- 
10mm thick metal about 1000 gms taken than this sample is passing through 12.5mm. Retained in 
10mm sieves materials shall be dried in oven free the period four hours at temperature 100 to 110oc. 
The its material cooled and this aggregate fill in the mould in three layer and stamped with 25 stakes 
with tamping rod. This sample is filled into cylindrical steel cup. The it fixed in the base of on testing 
machine. The hammer of weight about 14 kg and this hammer raised about 380 mm above upper 
surface of the aggregate in the cup and allowed to fall freely on the metal. The crushed aggregate the 
removed from the cup and whole material are sieved in 2.36 mm IS sieve. The fraction passing sieve 
is weighing to an accuracy of 0.1 gm (weight B) The fraction retained on the sieve is also weight 
(weight C) total weight (B+C) is less than the initial weight A. By more than one groom the result 
shall be discharged and fresh test is made. 
Aggregate Impact Test = C/A x 100 
Where, A =weight of aggregate passing IS sieves 12.5 mm 
B =weight of fraction retained on IS sieves 2.36 mm after sieve analysis (B) gm 
C =weight of fraction passing IS sieves analysis 
Aggregate Impact value should not be more than 45 percent by weight for aggregate used for concrete 
other than wearing surface 30 percent by weight for concrete to be used wearing surfaces such as 
runway roads and pavements.
SIEVE ANALYSIS FOR FINE AGGREGATE 
1. Purpose : 
The sieves are used for the determination of particle size distribution of fine aggregate by sieving. (As 
per IS 2386 part 1 – Methods of test for aggregates for concrete) 
2. Sizes of sieves : 
Sieves of the sizes 10mm, 4.75 mm, 2.36 mm, 1.8mm, 6000 mic., 300 mic., and 150 mic. 
3. Procedure : 
a. Take known weight of dry sample. 
b. Sieve the sample progressively starting from the largest sieve i.e. 10 mm 
c. On completion of sieving weigh the material retained on each sieve. 
d. Calculate the percentage of sand retained in each sieve and cumulative percentage retained on each 
sieve. 
e. Calculate cumulative percentage passing through each sieve. 
f. Calculate the fineness modulus of sand by summing up the cumulative percentage of sand retained 
on 10 mm, 4.75 mm, 
1.18 mm, 600 mic., 300 mic., and 150 mic., sieves and dividing the sum by 100.
SIEVE ANALYSIS FOR COARSE AGGREGATE 
1. Purpose : 
The sieves are used for the determination of particle size distribution of coarse aggregate by sieving 
(As per IS 2386 part I – Methods of test for aggregates for concrete) 
2. Procedure : 
a. Take a known weight 9 2kg) of dry aggregate. 
b. Sieve the aggregate progressively starting from the largest sieve. 
c. Note down the weight of the material retained in each sieve. 
d. Calculate the percentage of aggregate retained in eachsieve. 
e. Calculate the cumulative percentage of aggregate retainedin each sieve. 
f. Calculate the cumulative percentage of aggregate passingthrough each sieve. 
g. Check the values of percentage passing with the limitsspecified in IS 383 and record it. 
Grading requirement of coarse aggregate (IS: 383) 
25 mm 
20 mm 
12.5 mm 
10 mm 
4.75 mm
SPECIFIC GRAVITY TEST FOR AGGREGATE 
1. Purpose: 
The pycnometer is used to determine the specific gravity of aggregate asper IS 2386 part III – 
Methods of test for aggregates for concrete. 
2. Procedure 
a. Weight an empty pycnometer (W1) 
b. Fill up half of the pycnometer with dry aggregate sample andweigh. 
c. Add water to the sample, fill the pycnometer with water, roll iton a flat surface and then fill it 
completely with water and weigh (W3). 
d. Empty the contents of the pycnometer, refill it with water only and weigh. (W4). 
e. Calculate the specific gravity using this formula. 
Specific Gravity = (W2 – W1) / [(W4-W1)-(W3-W2)] 
Where W1 = weight of empty pycnometer, g. 
W2 = weight of pycnometer and dry aggregate, g. 
W3 = weight of pycnometer with aggregate and water, g 
W4 = weight of pycnometer filled with only water, g
STANDARD CONSISTENCY OF CEMENT 
 DEFINATION :- 
This test used for the finding out initial setting time, final setting time and soundness of cement. 
Cement paste it is known as Consistency of cement. 
 APPARATUS :- 
 Vical apparatus, 
 Plunger having 10mm dia, 50mm length 
 Mould 
 PROCEDURE :- 
 Step I :- 
Take about 500gms cement and prepare the paste with a weighed quality of 
water and say 24% by cement and for the first trial. Then field the cement 
into the mould and say the weighed of water 25% and preparing the paste and 
filling into the mould is about 3-5 minutes. Fill a mould with paste and shake 
it was to Expel air. 
 Step II :- 
Then bring down the plunger to touch to surface of the paste quickly release 
it. Then note down the time depth of penetration of plunger. Similarly 
conduct trials with higher W/c ratio till such time the plunger penetrates 33- 
35mm from the top. The corresponding percentage of water by weight of 
cement is known as standard consistency and it is denoted by “p” 
It finding out the test, 
1. Soundness Test 
2. Initial setting time 
3. Final setting time 
 INITIAL SETTING TIME :- 
In this test take about 400gms cement and it sieved with sieve no. 9 and add water at 
the rate of 0.85 (P) by weight of cement Ex :- (0.85 P x 400/100) = weight of water to be 
added where P is the percentage of water required for a normal consistency of cement (paste) 
and it adding instantly water. Stop watched. It also started. 
Then prepared the test block under the rod. Now, fitted with the needle and it is brought into the 
contact with the surface or paste. In the mould and take the reading with the scale and it is noted.
Then rod is release quickly without any jerk and allow it into penetrate into the test block but after 
same times paste losing it plasticity. The needly may penetrate only to a depth of 33-35 mm from the 
top the period clasping between the time when water is added to the cement and the time at which the 
needle penetrates the test block to a depth equal to 33-35 mm from the top is taken as initial setting 
time. 
 FINAL SETTING TIME :- 
The cement shall be considered finally set while applying the final setting time 
needle. Gently cover the surface on the test block the centre needle makes an impression. 
Paste has attained such hardness centre needle does not pierce through the paste more 
than 0.5mm this is known as Final Setting Time. 
Duration of setting time:- 
1. Initial Setting Time – 30 minutes 
2. Final Setting Time – 600 minutes
References 
List of IS codes Referred 
IS 456 -2000 Plain & Reinforced concrete code of practice 
IS 383-1993 Specification for Coarse and Fine Aggregate fromnatural 
sources for concrete 
IS: 383 Zone-III- specifications for Coarse & Fine Agg. From naturalsources for Concrete. 
IS 1786 -1985 Specification for High strength Deformed steel barsand wires for Concrete 
Reinforcement 
IS 2386 (Part - II) 1991 Method for Test for aggregates forconcrete Part - II Estimation of deleterious 
materials and organicimpurities 
SP-34 Hand Book on concrete reinforcement and Detailing 
SP-23 Hand Book on concrete Mix. 
IS 9103 1979 Specification for admixtures for concrete 
IS-383-1970.The grading of coarse aggregates should be as perspecifications 
IS 2751 and IS 9417 Welding of reinforcements in accordance withthe recommendations 
IS: 1786 1985 Test to be performed in Respect of Fe 415 
IS: 10262 1982 Recommended Guidelines for Concrete Mix Design. 
IS: 516 1959 Methods of tests for Strength of Concrete. 
Books 
General Theory of Bridge Construction by Hermann Haupt 
Design and construction of bridge approaches by Harvey E. Wahls 
Bridge engineering: construction and maintenance by Wai-Fah Chen 
Design Of R.C.C. Structural Elements by S.S. Bhavikatti 
Significance of tests and properties of concrete by Joseph F.Lamond, J. H. Pielert 
Materials in construction: an introduction by Geoffrey D. Taylor 
Aggregates: sand, gravel and crushed rock aggregates for By MickR.Smith, 
Aggregates in concrete by Mark G. Alexander, Sidney Mindess 
Manual of ready-mixed concrete by J. D. Dewar, R. Anderson 
Formwork for concrete by Mary Krumboltz Hurd 
E- sources
CONCLUSION 
IT WAS A WONDERFUL LEARING EXPERIENCE AT TATA ALDESA (JV), 
TUNDLA,FIROZABAD FOR FIVE WEEKS.I GAINED A LOT OF INSIGHT REGARDING 
ALMOST EVERY ASPECTS OF SITE.I WAS GIVEN EXPOSURE IN ALMOST ALL THE 
DEPARTMENTS AT THE SITE,BUT I HAD LIKED TO HIGHTLIGHT THE AREAS OF 
SAFETY,QUALITY MANAGEMENT,MATERIAL MANAGEMENT ,FORMATION AND 
EXECUTION. 
I HOPE THIS EXPERIENCE WILL SURELY HELP ME IN MY FUTURE AND ALSO IN 
SHAPING MY CAREER. 
Compaction of embankment near Aligarh 
Concreting at Minor Bridge 301 (Lot 101), Reinforcement & Shuttering fixing for Minor 
photo taken on june 2014 for Eastern Corridor Bridge 301, photo taken on july 2014 .
Training report on railway structure at tata aldesa

More Related Content

What's hot

project final year civil
project final year civilproject final year civil
project final year civilAlankar jaiswal
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTssuser5fea8f
 
Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Alok Mishra
 
Bitumin road construction
Bitumin road constructionBitumin road construction
Bitumin road constructionritwizkumar1
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION L&W BUILDING SOLUTIONS PVT. LMT.
 
Civil Engineering Project Presentation
Civil Engineering Project PresentationCivil Engineering Project Presentation
Civil Engineering Project PresentationIbrahim Ali
 
Internship Report on metro project
Internship Report on metro projectInternship Report on metro project
Internship Report on metro projectAkshathaBhandary
 
CIVIL / STRUCTURAL DESIGN ENGINEER
CIVIL / STRUCTURAL DESIGN ENGINEERCIVIL / STRUCTURAL DESIGN ENGINEER
CIVIL / STRUCTURAL DESIGN ENGINEERVinobha K
 
DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT Deepak Kumar
 
Staad.Pro Training Report or Summer Internship
Staad.Pro Training Report or Summer Internship  Staad.Pro Training Report or Summer Internship
Staad.Pro Training Report or Summer Internship Ravi Kant Sahu
 
QA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding InspectorQA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding InspectorAsad Ahsan
 
Internship Report in L&T Constructions
Internship Report in L&T ConstructionsInternship Report in L&T Constructions
Internship Report in L&T Constructionssanjay choudhary
 
INTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdf
INTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdfINTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdf
INTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdfSANJAY ACHARYA
 
Summer Training Report (GAMMON INDIA)
Summer Training Report (GAMMON INDIA)Summer Training Report (GAMMON INDIA)
Summer Training Report (GAMMON INDIA)Er Mohtisham Ali
 

What's hot (20)

project final year civil
project final year civilproject final year civil
project final year civil
 
Shakil_CV_ADB_June 28, 2021
Shakil_CV_ADB_June 28, 2021Shakil_CV_ADB_June 28, 2021
Shakil_CV_ADB_June 28, 2021
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
 
Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD
 
Bitumin road construction
Bitumin road constructionBitumin road construction
Bitumin road construction
 
Internship report
Internship report Internship report
Internship report
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 
CV of M Saidul Islam.os
CV of M Saidul Islam.osCV of M Saidul Islam.os
CV of M Saidul Islam.os
 
Civil Engineering Project Presentation
Civil Engineering Project PresentationCivil Engineering Project Presentation
Civil Engineering Project Presentation
 
Road construction report
Road construction reportRoad construction report
Road construction report
 
Cv rebbouche bilal
Cv rebbouche bilalCv rebbouche bilal
Cv rebbouche bilal
 
Internship Report on metro project
Internship Report on metro projectInternship Report on metro project
Internship Report on metro project
 
CIVIL / STRUCTURAL DESIGN ENGINEER
CIVIL / STRUCTURAL DESIGN ENGINEERCIVIL / STRUCTURAL DESIGN ENGINEER
CIVIL / STRUCTURAL DESIGN ENGINEER
 
DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT
 
Staad.Pro Training Report or Summer Internship
Staad.Pro Training Report or Summer Internship  Staad.Pro Training Report or Summer Internship
Staad.Pro Training Report or Summer Internship
 
QA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding InspectorQA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding Inspector
 
Internship Report in L&T Constructions
Internship Report in L&T ConstructionsInternship Report in L&T Constructions
Internship Report in L&T Constructions
 
SUMMER TRAINING FROM PWD
SUMMER TRAINING FROM PWDSUMMER TRAINING FROM PWD
SUMMER TRAINING FROM PWD
 
INTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdf
INTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdfINTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdf
INTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdf
 
Summer Training Report (GAMMON INDIA)
Summer Training Report (GAMMON INDIA)Summer Training Report (GAMMON INDIA)
Summer Training Report (GAMMON INDIA)
 

Viewers also liked

project report on truss bridge
project report on truss bridgeproject report on truss bridge
project report on truss bridgerajdutt1111
 
RAK & Shinepukur Ceramics Working-Capital Structure.
RAK & Shinepukur Ceramics Working-Capital Structure.RAK & Shinepukur Ceramics Working-Capital Structure.
RAK & Shinepukur Ceramics Working-Capital Structure.Farabi Ahmed
 
Ete 101 accident at workplace and prevention
Ete 101 accident at workplace and preventionEte 101 accident at workplace and prevention
Ete 101 accident at workplace and preventionChe'gu Jijan
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportReshmi R
 
Gis application in civil engineering
Gis application in civil engineeringGis application in civil engineering
Gis application in civil engineeringAmal C Varghese
 
Sample project abstract
Sample project abstractSample project abstract
Sample project abstractklezeh
 

Viewers also liked (7)

project report on truss bridge
project report on truss bridgeproject report on truss bridge
project report on truss bridge
 
RAK & Shinepukur Ceramics Working-Capital Structure.
RAK & Shinepukur Ceramics Working-Capital Structure.RAK & Shinepukur Ceramics Working-Capital Structure.
RAK & Shinepukur Ceramics Working-Capital Structure.
 
Ete 101 accident at workplace and prevention
Ete 101 accident at workplace and preventionEte 101 accident at workplace and prevention
Ete 101 accident at workplace and prevention
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Gis application in civil engineering
Gis application in civil engineeringGis application in civil engineering
Gis application in civil engineering
 
Sample project abstract
Sample project abstractSample project abstract
Sample project abstract
 
Internship report
Internship reportInternship report
Internship report
 

Similar to Training report on railway structure at tata aldesa

DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiDFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiShobhit Acharya
 
IRJET- Financial Feasibility Study of the Indian Bullet Train
IRJET-  	  Financial Feasibility Study of the Indian Bullet TrainIRJET-  	  Financial Feasibility Study of the Indian Bullet Train
IRJET- Financial Feasibility Study of the Indian Bullet TrainIRJET Journal
 
summer training report in L&T construction
summer training report in L&T construction summer training report in L&T construction
summer training report in L&T construction Manish Barwal
 
Design of Highway with Major Bridge on Stagnant Water
Design of Highway with Major Bridge on Stagnant WaterDesign of Highway with Major Bridge on Stagnant Water
Design of Highway with Major Bridge on Stagnant WaterIRJET Journal
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA WinnersLars Forslöf
 
RDSO MOTIVE POWER
RDSO MOTIVE POWERRDSO MOTIVE POWER
RDSO MOTIVE POWERFaraz Khan
 
Eia Karachi Thatta Dual Carriageway Project
Eia Karachi Thatta Dual Carriageway ProjectEia Karachi Thatta Dual Carriageway Project
Eia Karachi Thatta Dual Carriageway Projectzubeditufail
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismIRJET Journal
 
AK-BIODATA-Sep-2016
AK-BIODATA-Sep-2016AK-BIODATA-Sep-2016
AK-BIODATA-Sep-2016ANIYAN KUNJU
 
Vocational training Report for ECE department
Vocational training  Report for ECE departmentVocational training  Report for ECE department
Vocational training Report for ECE departmentManoj Verma
 
CONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGECONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGEAnkit Gautam
 
diesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedidiesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedisomesh dwivedi
 
Summer training report rdso ajju
Summer training report rdso ajjuSummer training report rdso ajju
Summer training report rdso ajjuAJEETKUMAR397
 
RDSO training report -NAVIN DIXIT
RDSO training report -NAVIN DIXITRDSO training report -NAVIN DIXIT
RDSO training report -NAVIN DIXITNavin Dixit
 
Pavement Maintenance Practices in
Pavement Maintenance Practices inPavement Maintenance Practices in
Pavement Maintenance Practices inMohhammad Sujon
 
IRJET- Feasibility Check and Analysis of a Flyover Over a Railway Cross
IRJET-  	  Feasibility Check and Analysis of a Flyover Over a Railway CrossIRJET-  	  Feasibility Check and Analysis of a Flyover Over a Railway Cross
IRJET- Feasibility Check and Analysis of a Flyover Over a Railway CrossIRJET Journal
 

Similar to Training report on railway structure at tata aldesa (20)

wdfcil
wdfcilwdfcil
wdfcil
 
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiDFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
 
IRJET- Financial Feasibility Study of the Indian Bullet Train
IRJET-  	  Financial Feasibility Study of the Indian Bullet TrainIRJET-  	  Financial Feasibility Study of the Indian Bullet Train
IRJET- Financial Feasibility Study of the Indian Bullet Train
 
Bio data dr elangovan
Bio data   dr elangovanBio data   dr elangovan
Bio data dr elangovan
 
MERAJ UL HUDA CV
MERAJ UL HUDA CVMERAJ UL HUDA CV
MERAJ UL HUDA CV
 
summer training report in L&T construction
summer training report in L&T construction summer training report in L&T construction
summer training report in L&T construction
 
Design of Highway with Major Bridge on Stagnant Water
Design of Highway with Major Bridge on Stagnant WaterDesign of Highway with Major Bridge on Stagnant Water
Design of Highway with Major Bridge on Stagnant Water
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA Winners
 
RDSO MOTIVE POWER
RDSO MOTIVE POWERRDSO MOTIVE POWER
RDSO MOTIVE POWER
 
Eia Karachi Thatta Dual Carriageway Project
Eia Karachi Thatta Dual Carriageway ProjectEia Karachi Thatta Dual Carriageway Project
Eia Karachi Thatta Dual Carriageway Project
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading Mechanism
 
AK-BIODATA-Sep-2016
AK-BIODATA-Sep-2016AK-BIODATA-Sep-2016
AK-BIODATA-Sep-2016
 
Final Project
Final ProjectFinal Project
Final Project
 
Vocational training Report for ECE department
Vocational training  Report for ECE departmentVocational training  Report for ECE department
Vocational training Report for ECE department
 
CONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGECONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGE
 
diesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedidiesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedi
 
Summer training report rdso ajju
Summer training report rdso ajjuSummer training report rdso ajju
Summer training report rdso ajju
 
RDSO training report -NAVIN DIXIT
RDSO training report -NAVIN DIXITRDSO training report -NAVIN DIXIT
RDSO training report -NAVIN DIXIT
 
Pavement Maintenance Practices in
Pavement Maintenance Practices inPavement Maintenance Practices in
Pavement Maintenance Practices in
 
IRJET- Feasibility Check and Analysis of a Flyover Over a Railway Cross
IRJET-  	  Feasibility Check and Analysis of a Flyover Over a Railway CrossIRJET-  	  Feasibility Check and Analysis of a Flyover Over a Railway Cross
IRJET- Feasibility Check and Analysis of a Flyover Over a Railway Cross
 

Recently uploaded

Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 

Recently uploaded (20)

Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 

Training report on railway structure at tata aldesa

  • 1. TRAINING REPORT ON DESIGN & CONSTRUCTION OF CIVIL STRUCTURES & TRACKS WORKS FOR EASTERN DFCC AT TATA-ALDESA (JV) SUBMITTED BY:- UTSAV TIWARI ROLL NO.- 111000155
  • 2. ABSTRACT This report is a summer internship report submitted in partial fulfillment of the requirements for the degree of Bachelor of Technology in Civil Engineering as per norms of GLA University Mathura. The author visited the site for construction of civil structure of DFCC, at Tundla in his training period and attained technical knowledge during the course, after which he was able to compile this report. The report consists of brief study and description of materials, equipments and procedures used at site for construction of an bridges. Author put his best to elaborate the actual site conditions, and problem faced at site and the tactics used to deal with them.The main objective of this report is to present a systematic text on the execution of construction of an bridges based on the Indian Standard codes. The report also covers the fundamental aspects of practical requirement such as safety, feasibility and economy at site.In this report the objective was to introduce, wherever necessary,material which embodies the most recent methodologies. 1.Discusses introduction to organization profile, management structure, products, market share, problemdefinition (objectives, deliverables etc), and the main conclusions. 2. Deals with materials and equipments used at site, literature review, contains description of the process plant/site wherepractical training was undertaken including diagrams for showing process scheme, major operations and process equipments, stream compositions, site conditions governing the process control ,discusses summary of the project with main findings. 3.Deals with the results and laboratory tests were performed and the process and the calculations. 4.References the method of adoption of the proposed solution by the organization. 5.Conclusion.
  • 3. ACKNOWLEDGEMENT IT IS INDEED A GREAT PLEASURE AND PRIVELEGE TO PRESENT THIS REPORT ON TRAINING AT TATA-ALDESA (JV) .I AM EXTREMELY GRATEFUL TO MY TRAINING AND PLACEMENT OFFICER FOR ISSUING A TRAINING LETTER,WHICHMADE MY TRAINING POSSIBLE AT TATA ALDESA (JV),TUNDLA. I WOULD LIKE TO EXPRESS MY GRATITUDE TO ER. SANJIV KUMAR (PROJECT MANAGER) FOR HIS INVALUABLE SUGGESTIONS,MOTIVATION,GUIDANCE AND SUPPORT THROUGH OUT THE TRAINING.HIS METHODOLOGY TO START FROM SIMPLE ANT THEN DEEPEN THROUGH MADE ME TO BRING OUT THIS REPORT WITHOUT ANXIETY. THANKS TO ALL OTHER TATA ALDESA (JV) OFFICIALS,OPERATORS AND ALL OTHER MEMBERS OF TATA ALDESA (JV),YET UNCOUNTED FOR THEIR HELP IN COMPLETING THE PROJECT AND SEE THE LIGHT OF SUCCESS. I AM VERY THANKFUL TO FRIENDS,COLLEAGUES AND ALL OTHER PERSONS WHO RENDERED THEIR ASSISTANCE DIRECTLY OR INDIRECTLY TO COMPLETE THIS PROJECT WORK SUCCESSFULLY. I EXTENDED MY DUE THANKS TO ER. MUKESH KUMAR WHO GAVE ME VALUABLE TIME AND SUGGESTIONS AND GUIDE ME A LOT AT VARIOUS STAGES OF MY SUMMER TRAINING.
  • 4. TABLE OF CONTENTS S NO. CONTENT PAGE NO. ABSTRACT i CERTIFICATE ii ACKNOWLEDGEMENT iii 1 INTRODUCTION 1 1.1 CLIENT’S PROFILE 1 1.1.1 GENESIS 1 1.1.2 MISSION 1 1.1.3 SALIENT FEATURES 2 1.1.4 OBJECTIVE 4 1.2 CONTRACT’S PROFILE 4 1.3 PROJECT PROFILE 5 1.3.1 CONTRACT STRATEGIES 6 1.3.2 TECHNOLOGICAL INNOVATIONS 7 1.3.3 ALIGNMENT LAYOUTS 7 1.3.4 PROJECT MAP 8 2 SUB STRUCTURAL WORK HYDRAULIC PILING RIG 2.1 MACHINERY 9 2.2 PROCESS FOR HYDRAULIC PILING WORK 9 2.2.1 HYDRAULIC PILING 9 2.2.2 REINFORCEMENT 10 2.2.3 CONCRETING 11 2.2.4 EXTRACTION OF TEMPORARY CASING 12 2.3 METHODOLOGY 12 3 LABATORY TESTS AND RESULTS 3.1 CONCRETE TEST 3.1.1 SLUMP TEST 14 3.1.2 150 x 150MM CUBE MOULDS 15 3.1.3 DIGITAL COMPRESSION TESTING MACHINE 16
  • 5. 3.2 AGGREGATE TEST 3.2.1 AGGREGATE IMPACT TEST 17 3.2.2 SIEVE ANALYSIS FOR FINE AGGREGATE 18 3.2.3 SIEVE ANALYSIS FOR COARSE AGGREGATE 19 3.2.4 SPECIFIC GRAVITY TEST FOR AGGREGATE 20 3.3 CEMENT TEST 3.3.1 STANDARD CONSISTENCY OF CEMENT 21 4 REFERENCES 23 5 CONCLUSION 24
  • 6. INTRODUCTION 1.1 CLIENT’S PROFILE Genesis of DFCCIL The Indian Railways' quadrilateral linking the four metropolitan cities of Delhi, Mumbai, Chennai and Howrah, commonly known as the Golden Quadrilateral and its two diagonals (Delhi-Chennai and Mumbai-Howrah), adding up to a total route length of 10,122 km carries more than 55% of revenue earning freight traffic of IR. The existing trunk routes of Howrah-Delhi on the Eastern Corridor and Mumbai-Delhi on the Western Corridor are highly saturated with line capacity utilization varying between 115% and 150%. The rapid growth of Indian economy in the last few years has created demand for additional capacity of rail freight transportation, and this is likely to grow further in the future. This burgeoning demand led to the conception of the dedicated freight corridors along the Eastern and Western Routes. Hon'ble Minister for Railways, made this historic announcement on the floor of the House in the Parliament while presenting the Railway Budget for 2005-06. In April 2005, the Project was discussed at the Japan-India Summit Meeting. It was included in the declaration of co-operation signed between the Hon'ble Prime Ministers of India and Japan for a feasibility study and possible funding of the dedicated rail freight corridors by Japanese Government. The feasibility study report was submitted to Ministry of Railways in October 2007. In the meanwhile, Ministry of Railways initiated action to establish a Special Purpose Vehicle for construction, operation and maintenance of the dedicated freight corridors. This led to the establishment of "Dedicated Freight Corridor Corporation of India Limited (DFCC)", to undertake planning & development, mobilization of financial resources and construction, maintenance and operation of the dedicated freight corridors. DFCC was incorporated as a company under the Companies Act 1956 on 30th October 2006. Mission As the dedicated agency to make the vision into reality, DFCCIL's mission is:  To build a corridor with appropriate technology that enables Indian railways to regain its market share of freight transport by creating additional capacity and guaranteeing efficient, reliable, safe and cheaper options for mobility to its customers.  To set up Multimodal logistic parks along the DFC to provide complete transport solution to customers.
  • 7.  To support the government's initiatives toward ecological sustainability by encouraging users to adopt railways as the most environment friendly mode for their transport requirements.  Salient Features  Dedicated Freight Corridors are proposed to adopt world class and state-of-the-art technology. Significant improvement is proposed to be made in the existing carrying capacity by modifying basic design features. The permanent way will be constructed with significantly higher design features that will enable it to withstand heavier loads at higher speeds. Simultaneously, in order to optimize productive use of the right of way, dimensions of the rolling stock is proposed to be enlarged. Both these improvements will allow longer and heavier trains to ply on the Dedicated Freight Corridors.  The following tables provide comparative information of the existing standards on Indian Railways and the proposed standard for DFCC  Upgraded Dimensions Of DFC Feature Existing On DFC Moving Dimensio ns Height 7.1 m for Western DFC 5.1 m for Eastern DFC Width Container Stack Single Stack Double Stack Train length
  • 8. Train Load  Upgraded Design Features Of DFC Feature Existing On DFC Heavier Axle Loads Axle Load 22.9t/25t 32.5t/25t for Track Superstructure Track Loading Density Maximum Speed Single Stack Double Stack Grade Up to 1 in 100 1 in 200 Curvature Up to 10 degree Up to 2.4 degree Traction Electrical(25 KV) Electrical(2x25 KV) Station Spacing 7-10 Km 40 Km Signalling Absolute/Automatic with 1 Km spacing Automatic with 2 Km spacing Communication Emergency Sockets/Mobile Train Radio Mobile Train Radio
  • 9. OBJECTIVE 1.2 CONTRACT’S PROFILE The Rs 3,300-crore eastern dedicated rail freight corridor (EDRFC) project has received a major boost with Tata Projects, the infrastructure arm of Tata Group, starting the construction work on the 337 km Bhaupur-Khurja stretch in Uttar Pradesh in a 50:50 joint venture partnership with Aldesa of Spain. Briefing media here, Tata Projects Managing Director Vinayak Deshpande said this is the first major contract awarded for the Eastern DFCC through an international competitive bidding process and involves construction of a 337 kilometers double track line, and 14 km of single line - between Bhaupur and Khurja in Uttar Pradesh. He also pointed out that the World Bank has sanctioned $975 million for this complete project. Also, he added, this will be a Design-Build Lump sum contract and will be executed within four years. Elaborating, he said the Dedicated Freight Corridor is an ambitious programme of the Union Ministry of Railways for promoting a seamless movement of rail freight traffic. It has been designed for 32.5 ton axle load as compared to the current carriage tracks of 22.5 ton axle load which is at par with the standard in America, Russia, and China. Responding to a query, Deshpande said this project would help to take over the heavy burden of freight from the passenger rail tracks and roads. At present, around 60 per cent of the freight traffic moves on golden quadrilateral, which would definitely get declogged from the eastern to western side, he added. The company has started work and expects to complete it by 2016 for trial runs. The commissioning
  • 10. would take place by end 2017. Aldesa, the Spanish JV partner, will provide the technological expertise in mechanically laying the tracks using the best technologies used in Europe and other developed countries. 1.3 PROJECT PROFILE The Eastern Dedicated Freight Corridor with a route length of 1839 km consists of Dankuni in West Bengal & Khurja in Uttar Pradesh & an electrified single-track segment of 447 km between Ludhiana (Dhandarikalan) - two distinct segments: an electrified double-track segment of 1392 km between Khurja - Dadri in the state of Punjab and Uttar Pradesh. Due to non - availability of space along the existing corridor particularly near important city centers and industrial townships, the alignment of the corridor takes a detour to bypass densely populated towns such as Mughalsarai, Allahabad, Kanpur, Etawah, Ferozabad, Tundla, Barhan, Hathras, Aligarh, Hapur, Meerut, Saharanpur, Ambala, Rajpura, Sirhind, Doraha and Sanehwal. Since the origin and destinations of traffic do not necessarily fall on the DFC, a number of junction arrangements have been planned to transfer traffic from the existing Indian Railway Corridor to the DFC and vice versa. These include Dankuni, Andal, Gomoh, Sonnagar, Ganjkhwaja, Mughalsarai, Jeonathpur, Naini/Cheoki, Prempur, Bhaupur, Tundla, Daudkhan, Khurja, Kalanaur, Rajpura, Sirhind and Dhandarikalan. The following table depicts the distance traversed through each state. Eastern DFC States KMs Punjab 88 Haryana 72 Uttar Pradesh 1049 Bihar 93 West Bengal/Jharkhand 538 Total 1839 The Eastern Corridor will traverse 6 states and is projected to cater to a number of traffic streams - coal for the power plants in the northern region of U.P., Delhi, Harayana, Punjab and parts of Rajasthan from the Eastern coal fields, finished steel, food grains, cement, fertilizers, lime stone from Rajasthan to steel plants in the east and general goods. The total traffic in UP direction is projected to go up to 116 million tonnes in 2021-22. Similarly, in the Down direction, the traffic level has been projected to increase to 28 million tons in 2021-22. As a result, the incremental traffic since 2005- 2006, works out to a whopping 92 million tons. A significant part of this increase would get diverted to the Dedicated Freight Corridor. The Eastern DFC will be executed in a phased manner. The World Bank funding is being planned in three tranches APL1 for Khurja- Kanpur, APL2 for Kanpur-Mughalsarai and APL3 for Khurja- Ludhiana. The Loan Agreement for APL1 between World Bank and DFCCIL has been executed for USD 975 million. As per RITES project report, the traffic that would move on the Eastern DFC, excluding the base year traffic (2005-06), is projected as below
  • 11. Contract Strategies Contract Strategy for Eastern Corridor World Bank funded portion will be generally on following lines: Procurement Guidelines: For consultancy work guidelines for selection and employment of consultant under IBRD loans and IDA Credits and Grant by World Bank borrowers issued in January 2011 will be applicable. For procurement of goods and works procurement guidelines under IBRD Loans and IDA Credits and Grant by World Bank borrowers issued in January 2011 will be applicable. Procurement of Works: Procurement of works will be two stages bidding after prequalification. Prequalification of bidders will be done on the basis of standard prequalification document of World Bank. Bid document will be generally as per standard bidding document for procurement of plant design, supply and installation issued by World Bank with general conditions based on FIDIC Yellow Book. Bank financing for the Eastern DFC Program would be provided under an Adoptable Program Loan (APL) in three phases. Each phases of the APL would be comprised of a loan for one of the three sections and a continuing program of technical assistance for IR and DFCCIL. The sequence of the loans is envisaged to be: APL 1 for Khurja - Kanpur; APL 2 for Kanpur - Mughalsarai and APL 3 for Ludhiana - Khurja - Dadri, with about a one year lag between these APL phases. TRAFFIC PROJECTIONS ON EASTERN DFC (in million tons/year) Direction/Commodity 2016-17 2021-22 UP Direction Power House coal 54.46 61.96 Public Coal 0.61 0.95 Steel 8.24 9.74 Others 1.61 2.96 Logistic Park 1.20 2.40 Sub-Total 66.12 78.01 Down Direction Fertilizer 0.23 0.42 Cement 0.78 1.52 Limestone for the Steel Plants 4.99 5.00 Salt 0..68 1.03 Others 1.61 2.96
  • 12. Logistic Park 1.20 2.40 Sub-Total 9.48 13.32 Grand Total 75.60 91.33 Rites Report: Table 14.3. of Eastern Corridor PETS Report It is also proposed to set up Logistics Park at Kanpur in U.P. and Ludhiana in Punjab. These parks are proposed to be developed on Public Private Partnership mode by creating a sub-SPV for the same. DFCCIL proposes to provide rail connectivity to such parks and private players would be asked to develop and provide state of the art infrastructure as a common user facility. Technological Innovations DFC will build its two corridors with appropriate technology that will enable Indian Railways to regain its market share of freight transport by creating additional capacity, efficient, reliable, safe and cheaper options for mobility to its customers. To achieve these objectives, DFCC will encourage use of latest technological innovations in the area of track, electrification, signaling and train operations. All DFC contracts will be Design-Build contracts to permit new technologies to be adopted on DFC corridors. Alignment Layout  Khurja - Bhaupur Section
  • 13. Project Funding for Corridors The project cost for both the corridors was initially estimated by RITES, in January 2007 as Rs. 28,000 crore. This cost was subsequently revised to about Rs. 37,000 crore by Japan International Cooperation Agency in its feasibility Report submitted to the Ministry of Railways in October 2007. When revised to 2009 costs, the two corridors are likely to cost in the region of Rs.54,000 crore, resulting in a project completion cost of about Rs. 80,000 crore in 2017-2018. The cost for the project will be funded by a combination of debt from bilateral/multilateral agencies, equity from Ministry of Railways and Public Private Partnership. The capital structure of DFCCIL will entail a debt equity ratio of 2:1. Eastern Corridor The Eastern Corridor is proposed for funding from the World Bank, internal generation and Public Private Partnership. Financing for the 725 km section between Ludhiana and Mughalsarai will be undertaken over three phases by World Bank through an IBRD loan. The section from Mugalsarai to Sonnagar will be funded directly by Ministry of Railways while the 5.34 km section from Sonnagar to Dankuni will be financed through Public Private Partnership. The first tranche of the IBRD Loan, aggregating to USD 975 million has already been signed by Ministry of Railways & World Bank. Western Corridor Western Corridor is funded by the Government of Japan. It was envisaged that a STEP (Special Terms of Economic Partnership) Loan in the region of ¥677 billion will be provided by the Government of Japan to finance the construction of Western DFC as well as procurement of Locomotives for the Ministry of Railways. The loan is extended on soft terms for a period of forty years with a moratorium of ten years. The remaining portion of the project construction cost will be borne by Ministry of Railways as equity funding to the Dedicated Freight Corridor Corporation of India. The first tranche of the loan for 90.2 Billion Yen for construction between Rewari and Vadodara has been signed. Funding for Phase II (Vadodara-JNPT) of the Corridor was also signed with JICA for 266 Billion Yen in March, 2013. PROJECT MAP
  • 14. HYDRAULIC PILING RIG 2.1 MACHINERY  HYDRAULIC PILING RIG  AUGER  BUCKET  LINER(3-5m long)  BENTONITE TANK  VERTICAL PUMP  DEWATERING PUMP (VERTICAL)  TREMIE PIPE WITH HOPER  BATCHING PLANT  TRANSIT MIXERS  D.G. SET  BAR CUTTING MACHINE  SOUNDING MACHINE 2.2 PROCESS FOR HYDRAULIC PILING WORK i) HYDRAULIC PILING
  • 15. 1) Hydraulic bored piling plant shall be used. The piling plants consist of a telescopic kelly bar and the lower of the kelly bar is an adaptable to other drilling tools. 2) On completion of the temporary platform, the piling rigs shall be moved in assembled and ready for work on the installation of the 800 mm and 1050 mm diameter bored piles. A test pile for vertical pile shall be carried out to verify the designed load carrying capacity of the piles, the installation of which shall be determined jointly with Employer’s Representative. 3) Bored piles are cast-in-situ piles formed by excavating a hole of the specified size (diameter), to the required depth and casting the excavated hole with concrete of specified strength after the reinforcement is lowered into the hole. 4) The hydraulic pile points setting out shall be provided by a qualified Surveyor. The boring plant will be moved to the pile point intended for excavation. The kelly bar mounted with an auger is placed just above the pile point. The vertically of the kelly bar should be checked by means of a spirit level. Adjustment should be made so as to enable the kelly bar to be as vertical as possible. Then the positions of the auger are checked against the pile point. 5) Adjustment should be made so that the center of the auger is nearest to the pile point. The auger is then lowered and boring operating commenced. 6) Reasonable care should be taken so that the pile position and vertically are constructed within the specified tolerance i.e. 75mm and 1 in 150 respectively. 7) Boring commerce after the positions of the boring plant is checked. Usually, an auger of the required size is used to excavate hole is collapsible; a temporary casing of the same size should be installed to prevent collapse. Excavation of the hole continued until the required depth. 8) At the point of encountering the rock head level where soil drilling tools are unable to penetrate the strata any further, boring shall cease in order that the Employer’s Representative to verify the occurrence and confirm the rock head reduced level. 9) Rock drilling tools shall be used for drilling into and through rock. 10) After reaching the required depth, a cleaning bucket will be used to clean up the bottom of the borehole. A joint measurement of the depth should be made before lowering of reinforcement and concreting. ii) Reinforcement
  • 16. 1) Reinforcement to bored piles will be fabricated in the reinforcement yard and transported to the borehole for placing. After fabrication by the bar benders, the helical links will be tack welded to the main reinforcement Laps are also to be welded sufficiently so that they are intact during transportation. 100 mm diameter round spacers will be welded to the reinforcement to provide the cover to the reinforcement against the soil during concreting. 2) The reinforcement will be lowered to the completed bore hole, prior to concreting, by means of a service crane arid to be adjusted to the correct level. iii) Concreting Concreting conforming to the specification will be delivered to the site by Ready Mixed supplier. If bore hole are dry, the concrete shall be discharges through a short funnel at the top of the bored hole to prevent free falling concrete hitting the sides of the bore. If bored holes contain either water or bentonite drilling mud the concrete shall be placed by the tremie method. (I)Dry Hole Mix This mix shall be designed to give a works cube strength of 35 Mpa at 28days with a slump of 100 ± 25mm. (ii) Tremix Mix (iii) This mix shall be designed to give a minimum works cube strength of 35 Mpa at 28 days with a slump of 175 ± 25mm. (iv) The method of placing shall be such as to ensure that the concrete in its final positions shall be dense and homogeneous. (v) The piles shall be concrete in one continuous operation immediately after the excavation has been completed and inspected where inspection is required by the Specification. If the continuity of placing the concrete is interrupted, no further concrete shall be placed without the prior approval of the Engineer.
  • 17. iv) Extraction Of Temporary Casing All temporary casings are to be extracted immediately after completion of concreting. A vibro-Hammer will be used to extract the casing. Reasonable care should be taken to ensure that the concrete level is above the cut-off level after extracting of casing point. 2.3 METHODOLOGY 1)PILE LOCATION: THE WORKING PILES SHALL BE INSTALLED AT LOCATIONS AS PER DRAWING. 2)CASING DRAWING: LINER OF 1m DIA WITH 8mm/6mm THICK WILL BE PLACED IN THE POSITION AND PUSHED DOWN THE HAMMER ,SAME WILL BE CHECKED FOR VERTICALITY AND BORING WILL BE CONTINUED. 3)BENTONITE FOR PILING: BENTONITE SHOULD BE USED IN THE PILING WORKS CONFORMING TO THE FOLLOWING SPECIFICATIONS. DENSITY OF MUD WILL NOT EXCEED:1.05 gm/cc-1.12 gm/cc MARSH CONE VISCOSITY:30-40 sec SWELLING INDEX:AS PER IS 6186-1986 PH VALUE:9.5-11.50 SAND CONTENT>.075mm: NOT MORE THAN 1% LIQUID LIMIT:NOT LESS THAN 400% THE BENTONITE REQUIRED FOR PILING WILL BE MIXED 24 HRS IN ADVANCE AND STORED IN THE BENTONITE TANKS.AS THE BORING PROGRESSES THE BORE WILL BE TOPPED WITH BENTONITE SO AS TO MAINTAIN A HEAD OF AT LEAST 1m ABOVE THE WATER TABLE.THE SPECIFIC GRAVITY OF BENTONITE IS LESS THAN 1.2g/cc AT THE BOTTOM OF THE BORE BEFORE COMMENCING CONCRETING OPERATION.
  • 18. 4)BORING: FOR BORING OF THE PILE SOIL AUGER AND BUCKET WILL BE USED.WHILE BORING,CARE WILL BE TAKEN TO MAINTAIN THE HEAD HEAD OF BENTONITE SLURRY BY CONSTANT TOPPING OF THE BORWE.THE DEPTH OF THE BORE WILL BE CHECKED WITH THE HELP OF SOUNDING CHAIN TAKING REFERENCE FROM THE TOP OF LINER.BEFORE LOWERING THE CAGE WE WILL INSURE THE BOTTOM CLEANING BY PUT THE BUCKET AT BOTTOM LEVEL OF BORINGS. 5)REINFORCEMENT CAGE: a) FABRICATION: REINFORCEMENT WILL BE CUT USING CUTTING MACHINES OR MANUALLY AS REQUIRED.THE CAGE WILL BE FABRICATED AS PER APPROVED BBS,COVER BLOCKS WILL BE PROVIDD AT A SPACING OF 3m c/c ON ALL FOUR SIDES OF THE CAGE TO PROVIDE A CLEAR COVER OF 75mm TO THE RING.THE REBAR CAGE WILL BE OFFERED FOR CHECKING. b)LOWERING OF CAGE: THE APPROVED CAGE WILL BE LOWERED INTO THE BORE IN SEGMENTS.CRANE OR HYDRA WILL BE USED TO HANDLE THE CAGE SEGMENTS,THE FIRST SEGMENT WILL BE HELD IN POSITION BY A SUITABLE BAR ACROSS THE CASING AND THE SECOND SEGMENT WILL BE LIFTED AND POSITIONED OVER THE FIRST SEGMENT.THE COUPLER WILL BE USED IN PLACE OF LAPS OR THE LAP JOINT WILL BE TIED WITH BINDING WIRE AND SUBSEQUENTLY WELDED TO ENSURE NO SLIPPAGE OCCURS WHILE LOWERING OF CAGE.THIS PROCESS WILL BE REPEATED TILL ALL THE SEGMENTS ARE LOWERED.THE LAST SEGMENT WILL HAVE SUITABLE HOOKS TO ENSABLE HANGING OF CAGE FROM THE LINER. 6)FLUSHING: THE PRE ASSEMBLED TREMIE PIPES SHALL BE LOWERED IN THE BORE HOLE KEEPING THE BOTTOM 300mm ABOVE THE TERMINATION LEVEL.FLUSHING OF THE BORE WILL BE DONE WITH BENTONITE PUMP ATTACHED WITH TREMIE PIPE AND TREMIE HEAD.FLUSHING OF FRESH BENTONITE WILL BE DONE CONTINOUSLY WITH FRESH BENTONITE SLURRY TILL THE CONSISTENCY OF INFLOWING AND OUT FLOWING SLURRY IS SIMILAR.FOR ENVIRONMENT ASPECT WATER WILL BE RECYCLED FOR THE DRILLING PROCESS.A PIT SHALL BE MADE FOR STORING BENTONITE SLURRY AND SHALL BE DISPOSED OFF ON THE LOCALLY AVAILABLE LAND FILL SITE AFTER DRY UP INTO THE PIT,SPILLAGE OF OIL AND GREASE SHALL BE DISPOSED AS PER HAZARDOUS WASTES RULES,2008. 7)CONCRETING: THE REQUIRED GRADE OF CONCRETE WILL BE PRODUCED AS PER THE APPROVED DESIGN MIX AT THE CENTRALIZED BATCHING PLANT AND TRANSPORTED BY TRANSIT MIXERS,ENSURING A SLUMP RANGE OF 150mm TO 200mm AT SITE.THE FIRST CHARGE OF CONCRETE WILL BE PLACED WITH A FLOATING PLUG INSIDE,THE TREMIE AND,WITH SUITABLE CHARGE PLATE AT THE HOPPER MOUTH.THE CONCRETE WILL BE ADEQUATE IN THE TREMIE WITH BE PLACED TAKING NECESSARY PRECAUTINS TO ENSURE THAT ADEQUATE LENGTH OF TREMIE IS EMBEDDED IN CONCRETE CUBES SHALL BE TAKEN AS PER RELEVENT CODE PROVISION.
  • 19. LABATORY TESTS AND RESULTS CONCRETE TEST SLUMP TEST  STATEMENT :- Slump test is very common test for and it is very important for consistency of concrete. It is not a suitable for very wet or very dry concrete. It is used convenient a control test and it gives uniformanity concrete. From the batch to batch. APPRATUS :- 1) Slump cone 2) Tamping rod Dimension of slump cone :- Bottom diameter – 20 cm Top diameter – 10 cm Height – 30 cm  PROCEDURE :- Take the slump cone. The cone should be cleaned and free from moisture of any old concrete before following test. The mould is placed on a smooth and on a smooth horizontally rigid and non-absorbent surface. Then the fresh concrete in placed on slump cone mould in four layer. Each layer has been rodded. The concrete is struck off level with trowel and tamping rod the mould is removed gradually from the concrete and by raising slowly and carefully in a vertically position. Then different in level between height of mould and that or highest part of subsides concrete is measured this difference in height in mm is known as slump concrete and it indicates the characteristic of concrete adding is slump value. If the concrete slumps it is called true slump.
  • 20. 150 x 150MM Cube Moulds Test 1. Purpose The moulds are used for making of concrete cubes as per IS :516 – 1959 – Methods of tests for strength of concrete. 2. Apparatus Wheel barrow, sampling scoop, trowel cube moulds of 15 x 15 x15 cm size and tamping bar 16 mm in diameter, 0.6 m long and bulleted point at the lower end. 3. Procedure as per IS 516 a. Firstly decide the number of samples to be taken during concreting. b. Oil the interior surface of the mould with mould releasing oil to prevent adhesion of the concrete. c. Collect the sample in a wheelbarrow after mixing the concrete properly in the transit mixer. d. Remix the sample thoroughly in wheelbarrow with sampling scoop. e. After remixing immediately fill the mould in layers approximately 5 cm deep. f. During filling the mould, the scoop shall be moved around the top edge of the mould as the concrete slides from it, in order to ensure a symmetrical distribution of the concrete within the mould. g. Each layer shall be compacted with the tamping rod (of 16 mm dia 60 cm long and rounded at one end).Minimum 35 strokes distributed in a uniform manner over thecross-section of the mould. h. After compacting the tip layer, top surface of the concrete shall be finished level with the top of the mould, using atrowel. i. Store the cube moulds in a place which is free from vibration and cover the surface of the concrete with a piece of dampsacking for initial 16 to 24 hours. j. After this period, mark the specimen and remove it from the mould by dismantling and submerge it clean water at a temperature of 27 +2oC and keep it till the time of testing for compressive strength.
  • 21. DIGITAL COMPRESSION TESTING MACHINE 1. Purpose: The digital compression – testing machine is used to determine the compressive strength of hardened concrete specimens. 2.Procedure as per IS 516 – Methods of tests for strength of concrete 1. Keep the specimen to be tested centrally on the clean lower platen so that small clearance is left between the upper platen and the top the specimen under test. 2. Close the pressure release valve. 3. Make the digital display to read “Zero” by adjusting the zero knobs. 4. Put the display unit on “Peak Hold” mode to hold the maximum load reading. 5. Start applying the load at the specified pace rate, which could be maintained by adjusting the slow fast knob. 6. If the pace rate is on higher side the indicator displays red color and the pace rate is on lower side the indicator will display yellow color. 7. If the pace rate is exactly equal to set rate then the indicator will display green color. 8. As soon as sample fails, release the pressure slowly by opening valve. 9. The digital display will be holding the maximum load reading at which sample has failed. Note down the pattern of failure and calculate the compressive strength in N/mm2 or kg/cm2. 10. Pace rate for 15 cm cube is 5.15 kN/s. 11. Before starting another test, clean the lower platen and bring the digital display to “Zero” position by depressing the “Reset” switch.
  • 22. AGGREGATE TEST AGGREGATE IMPACT TEST  IMPACT VALUE :- The Impact value test generally used as alternative to its crushing strength to know quality of aggregate. It is also useful for to know the quality of aggregate this test is apply only 10mm metal. So as to decide its suitability for use in the desired concrete mix. PROCEDURE :- 10mm thick metal about 1000 gms taken than this sample is passing through 12.5mm. Retained in 10mm sieves materials shall be dried in oven free the period four hours at temperature 100 to 110oc. The its material cooled and this aggregate fill in the mould in three layer and stamped with 25 stakes with tamping rod. This sample is filled into cylindrical steel cup. The it fixed in the base of on testing machine. The hammer of weight about 14 kg and this hammer raised about 380 mm above upper surface of the aggregate in the cup and allowed to fall freely on the metal. The crushed aggregate the removed from the cup and whole material are sieved in 2.36 mm IS sieve. The fraction passing sieve is weighing to an accuracy of 0.1 gm (weight B) The fraction retained on the sieve is also weight (weight C) total weight (B+C) is less than the initial weight A. By more than one groom the result shall be discharged and fresh test is made. Aggregate Impact Test = C/A x 100 Where, A =weight of aggregate passing IS sieves 12.5 mm B =weight of fraction retained on IS sieves 2.36 mm after sieve analysis (B) gm C =weight of fraction passing IS sieves analysis Aggregate Impact value should not be more than 45 percent by weight for aggregate used for concrete other than wearing surface 30 percent by weight for concrete to be used wearing surfaces such as runway roads and pavements.
  • 23. SIEVE ANALYSIS FOR FINE AGGREGATE 1. Purpose : The sieves are used for the determination of particle size distribution of fine aggregate by sieving. (As per IS 2386 part 1 – Methods of test for aggregates for concrete) 2. Sizes of sieves : Sieves of the sizes 10mm, 4.75 mm, 2.36 mm, 1.8mm, 6000 mic., 300 mic., and 150 mic. 3. Procedure : a. Take known weight of dry sample. b. Sieve the sample progressively starting from the largest sieve i.e. 10 mm c. On completion of sieving weigh the material retained on each sieve. d. Calculate the percentage of sand retained in each sieve and cumulative percentage retained on each sieve. e. Calculate cumulative percentage passing through each sieve. f. Calculate the fineness modulus of sand by summing up the cumulative percentage of sand retained on 10 mm, 4.75 mm, 1.18 mm, 600 mic., 300 mic., and 150 mic., sieves and dividing the sum by 100.
  • 24. SIEVE ANALYSIS FOR COARSE AGGREGATE 1. Purpose : The sieves are used for the determination of particle size distribution of coarse aggregate by sieving (As per IS 2386 part I – Methods of test for aggregates for concrete) 2. Procedure : a. Take a known weight 9 2kg) of dry aggregate. b. Sieve the aggregate progressively starting from the largest sieve. c. Note down the weight of the material retained in each sieve. d. Calculate the percentage of aggregate retained in eachsieve. e. Calculate the cumulative percentage of aggregate retainedin each sieve. f. Calculate the cumulative percentage of aggregate passingthrough each sieve. g. Check the values of percentage passing with the limitsspecified in IS 383 and record it. Grading requirement of coarse aggregate (IS: 383) 25 mm 20 mm 12.5 mm 10 mm 4.75 mm
  • 25. SPECIFIC GRAVITY TEST FOR AGGREGATE 1. Purpose: The pycnometer is used to determine the specific gravity of aggregate asper IS 2386 part III – Methods of test for aggregates for concrete. 2. Procedure a. Weight an empty pycnometer (W1) b. Fill up half of the pycnometer with dry aggregate sample andweigh. c. Add water to the sample, fill the pycnometer with water, roll iton a flat surface and then fill it completely with water and weigh (W3). d. Empty the contents of the pycnometer, refill it with water only and weigh. (W4). e. Calculate the specific gravity using this formula. Specific Gravity = (W2 – W1) / [(W4-W1)-(W3-W2)] Where W1 = weight of empty pycnometer, g. W2 = weight of pycnometer and dry aggregate, g. W3 = weight of pycnometer with aggregate and water, g W4 = weight of pycnometer filled with only water, g
  • 26. STANDARD CONSISTENCY OF CEMENT  DEFINATION :- This test used for the finding out initial setting time, final setting time and soundness of cement. Cement paste it is known as Consistency of cement.  APPARATUS :-  Vical apparatus,  Plunger having 10mm dia, 50mm length  Mould  PROCEDURE :-  Step I :- Take about 500gms cement and prepare the paste with a weighed quality of water and say 24% by cement and for the first trial. Then field the cement into the mould and say the weighed of water 25% and preparing the paste and filling into the mould is about 3-5 minutes. Fill a mould with paste and shake it was to Expel air.  Step II :- Then bring down the plunger to touch to surface of the paste quickly release it. Then note down the time depth of penetration of plunger. Similarly conduct trials with higher W/c ratio till such time the plunger penetrates 33- 35mm from the top. The corresponding percentage of water by weight of cement is known as standard consistency and it is denoted by “p” It finding out the test, 1. Soundness Test 2. Initial setting time 3. Final setting time  INITIAL SETTING TIME :- In this test take about 400gms cement and it sieved with sieve no. 9 and add water at the rate of 0.85 (P) by weight of cement Ex :- (0.85 P x 400/100) = weight of water to be added where P is the percentage of water required for a normal consistency of cement (paste) and it adding instantly water. Stop watched. It also started. Then prepared the test block under the rod. Now, fitted with the needle and it is brought into the contact with the surface or paste. In the mould and take the reading with the scale and it is noted.
  • 27. Then rod is release quickly without any jerk and allow it into penetrate into the test block but after same times paste losing it plasticity. The needly may penetrate only to a depth of 33-35 mm from the top the period clasping between the time when water is added to the cement and the time at which the needle penetrates the test block to a depth equal to 33-35 mm from the top is taken as initial setting time.  FINAL SETTING TIME :- The cement shall be considered finally set while applying the final setting time needle. Gently cover the surface on the test block the centre needle makes an impression. Paste has attained such hardness centre needle does not pierce through the paste more than 0.5mm this is known as Final Setting Time. Duration of setting time:- 1. Initial Setting Time – 30 minutes 2. Final Setting Time – 600 minutes
  • 28. References List of IS codes Referred IS 456 -2000 Plain & Reinforced concrete code of practice IS 383-1993 Specification for Coarse and Fine Aggregate fromnatural sources for concrete IS: 383 Zone-III- specifications for Coarse & Fine Agg. From naturalsources for Concrete. IS 1786 -1985 Specification for High strength Deformed steel barsand wires for Concrete Reinforcement IS 2386 (Part - II) 1991 Method for Test for aggregates forconcrete Part - II Estimation of deleterious materials and organicimpurities SP-34 Hand Book on concrete reinforcement and Detailing SP-23 Hand Book on concrete Mix. IS 9103 1979 Specification for admixtures for concrete IS-383-1970.The grading of coarse aggregates should be as perspecifications IS 2751 and IS 9417 Welding of reinforcements in accordance withthe recommendations IS: 1786 1985 Test to be performed in Respect of Fe 415 IS: 10262 1982 Recommended Guidelines for Concrete Mix Design. IS: 516 1959 Methods of tests for Strength of Concrete. Books General Theory of Bridge Construction by Hermann Haupt Design and construction of bridge approaches by Harvey E. Wahls Bridge engineering: construction and maintenance by Wai-Fah Chen Design Of R.C.C. Structural Elements by S.S. Bhavikatti Significance of tests and properties of concrete by Joseph F.Lamond, J. H. Pielert Materials in construction: an introduction by Geoffrey D. Taylor Aggregates: sand, gravel and crushed rock aggregates for By MickR.Smith, Aggregates in concrete by Mark G. Alexander, Sidney Mindess Manual of ready-mixed concrete by J. D. Dewar, R. Anderson Formwork for concrete by Mary Krumboltz Hurd E- sources
  • 29. CONCLUSION IT WAS A WONDERFUL LEARING EXPERIENCE AT TATA ALDESA (JV), TUNDLA,FIROZABAD FOR FIVE WEEKS.I GAINED A LOT OF INSIGHT REGARDING ALMOST EVERY ASPECTS OF SITE.I WAS GIVEN EXPOSURE IN ALMOST ALL THE DEPARTMENTS AT THE SITE,BUT I HAD LIKED TO HIGHTLIGHT THE AREAS OF SAFETY,QUALITY MANAGEMENT,MATERIAL MANAGEMENT ,FORMATION AND EXECUTION. I HOPE THIS EXPERIENCE WILL SURELY HELP ME IN MY FUTURE AND ALSO IN SHAPING MY CAREER. Compaction of embankment near Aligarh Concreting at Minor Bridge 301 (Lot 101), Reinforcement & Shuttering fixing for Minor photo taken on june 2014 for Eastern Corridor Bridge 301, photo taken on july 2014 .