SlideShare a Scribd company logo
1 of 28
SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
Bachelor of Quantity Surveying (Honours)
LITERATURE REVIEW
BUILDING COST COMPARISON BETWEEN
CONVENTIONAL METHOD AND INDUSTRIALIZED
BUILDING SYSTEM (IBS) IN MALAYSIA
STUDENT NAME: THAN LEK MEI
STUDENT ID NO: 0315538
SUPERVISOR: MR. MOHAMMED RIZAL
DATE OF SUBMISSION: 30 NOVEMBER2017
BUILDING COST COMPARISON BETWEEN
CONVENTIONAL METHOD AND INDUSTRIALIZED
BUILDING SYSTEM (IBS) IN MALAYSIA
THAN LEK MEI
(0315538)
TABLES OF CONTENTS
CHAPTER TITLE PAGE
2 2.1 Introduction 1
2.2 Definitions and Principles 2
2.2.1 Conventional Construction System 2
2.2.2 Industrialized Building System (IBS) 3
2.3 Comparison between Conventional Construction
System and IBS
5
2.4 IBS Involvement Worldwide 6
2.5 Types of IBS 7
2.6 Cost Comparison between Conventional
Construction System and IBS in Malaysia
12
2.7 Factors Affecting the Cost of IBS 14
2.8 Summary 18
2.8.1 Findings in relation to the first objective 18
2.8.2 Findings in relation to the second objective 19
2.8.3 Findings in relation to the third objective 19
REFERENCES
LIST OF TABLES
PAGE
Table 2.0 Categorization of IBS terminologies 4
Table 2.1 Comparison between Conventional and IBS Construction 5
Table 2.2 Daily IBS installer wage rates in Selangor in 2017 14
LIST OF FIGURES
PAGE
Figure 2.0 IBS Involvement Worldwide 6
Figure 2.1 Precast Concrete Framing 8
Figure 2.2 Steel Formwork System 9
Figure 2.3 Steel Framing System 10
Figure 2.4 Timber Framing System 11
Figure 2.5 Blockwork System 11
Figure 2.6 The Number of IBS Manufacturer and IBS Products 16
CHAPTER 2
LITERATURE REVIEW
2.1 Introduction
The Malaysian construction firms are always encouraged to do more with less. More
speed, more efficiency with less manpower, costs and delays. In another words, productivity
needs to be increased. CIDB has championed IBS through a variation of initiatives, which
include crediting IBS courses, hosting seminars to promote IBS and providing support for
trainings (CIDB, 2016). Notwithstanding, there still sees reluctance of local construction
industry to take up IBS as most of the contractors are get used to the conventional method as
well as the abundance of cheap foreign labour available in Malaysia. While the cost of IBS
implementation is not clearly outlined by any official institutions, this research paper aims to
identify the factors affecting cost of IBS and the cost differences between IBS and
conventional method in residential building.
2.2 Definitions and Principles
2.2.1 Conventional Construction System
Over the decades, conventional building system has been broadly practiced
worldwide and locally in Malaysian construction industry as the contractors are familiar with
its procedures and limitations. This method has also displayed a reasonable level of
performance which encourages the contractors to stay with the system. The ground of
conventional construction is not from engineering analysis; instead it is from the historic
methods of construction with wood members. Conventional system in Malaysia consists of
reinforced concrete frames with brick in-fill walls, timber or cold formed metal trussed roof
with either clay or concrete tiles, or sheet metal roofs. The building frame components are
pre-fabricated on site by means of 4-steps course (Ramli et. al., 2016):
i. Erection of timber or plywood formwork and scaffolding
ii. Installation of steel reinforcement
iii. Pouring of fresh concrete
iv. Dissemble of formwork and scaffolding
There sees how crucial it is to realize that the original structures from which these
methods of construction were derived are relatively small, with small horizontal spans and
moderate wall heights. The floor plans for these building were typically rectilinear.
According to Resat (2007), conventional, also recognized as traditional construction
method possesses its characteristics which are the basic construction methods in construction
industry in the world. The characteristics of conventional method include:
i. Use cast in-situ system. All building components are being built and cast on site with
high usage of construction materials and load of site works.
ii. Labour-intensive practices.
iii. 3-D syndrome which are Dirty, Difficult and Dangerous. Conventional system is
known with the 3-D syndrome. All sites work that being done which involved many
types of construction materials and machineries and high number of workers will
make the construction sites messy and crowded. This will lead to dirty and dangerous
environment.
2.2.2 Industrialized Building System (IBS)
Kamar et. al. (2011) provide a clear understanding on IBS’s etymology and
classification for practitioners and policy makers. In the perspective of construction.
Council for Research and Innovation in Building and Construction (CIB) defined
industrialized construction as a generic process of standardization and rationalization of
the work processes in the industry to reach cost efficiency, higher productivity and quality.
Further, Abdullah and Egbu defined IBS as a construction method developed due to
human investment in innovation and on rethinking the best ways of construction work
deliveries based on the level of industrialization. The level of industrialization in IBS can be
classified as pre-building system, modern construction, advance automation and
volumetric construction. On the other hand, Hassim defined IBS as an organizational process-
continuity of production implying a steady flow of demand, standardization, integration of
the whole production process, a high degree of organization of work mechanization to replace
human labour. IBS also defined by Rahman and Omar as a construction system using pre-
fabricated components. The manufacturing of the components is systematically organized
using machine, formworks and other forms of mechanical equipment. The components are
manufactured in the factory and once completed will be delivered to construction sites for
assembly and erection. However Pan (2006) outlined other terminologies used globally as
presented in Table 2.0, where all these terms are all representing IBS in this paper.
Table 2.0: Categorization of IBS terminologies. (Pan, 2006)
Terminology Category Term
OS
Offsite Production (OSP)
Offsite Manufacturing (OSM)
Offsite Fabrication (OSF)
Offsite Construction
PRE
Pre-assembly
Prefabrication
Prefab
MM
Modern Methods of Construction
Modern Methods of House Construction
Modern Methods of House Building
Building
System Building
Non-traditional Building
Industrialized Building
In Malaysia, CIDB defines IBS as a system of construction whereby building
components are produced at factories or off site, transported and consequently bring together
into a structure with slightest work. According to CIDB, systems to be accepted as part of
IBS need to portrait all six essential characteristics as listed below to warrant the realization
of the claimed benefits. (MIDFR, 2014):
1. Industrial production of components though pre-fabrication;
2. Highly mechanised in-situ processes i.e. slip-forms, post-tensioning, tunnel
shutters;
3. Reduced labour during prefabrication of components and site works;
4. Modern design and manufacturing methods i.e. involvement of Computer Aided
Design (CAD) and Computer Aided Manufacturing (CAM);
5. Systematic Quality Control i.e. ISO 9000 principles;
6. Open Building Concept i.e. permitting hybrid applications, adaptable to
standardisation and Modular Coordination (MC).
The Construction Industry Master Plan 2006–2015 in Malaysia has given significant
importance to the off-site manufacturing. The term used is Industrialised Building System
(IBS) and is defined as a construction technique in which components are manufactured in a
controlled environment (on- or off-site), transported, positioned, and assembled into an on-
site structure with minimal additional site works.
2.3 Comparison between Conventional Construction System and IBS
Different approach of construction provides different outcomes. In fact, there are some
differences between conventional construction method and IBS, which can be measured from
the perspective of productivity, value chain, construction time, reduction on dependency on
foreign labour, cost of construction and construction wastages as shown in Table 2.1
( Natasha et. al., 2016) :
Table 2.1: Comparison between Conventional and IBS Construction
Component Approach
Conventional Construction IBS Construction
Cost Require higher cost in terms of:



 Overhead costs
Reduce construction wastage and
increases the cost savings as follows:



 Overhead costs
Speed 
 Delay completion of the
project due to the on-site
 Components are disaggregated
and difficult to assemble and
erected.
 Shorter construction period.
 Permit a faster completion of
the project because of its rapid
and all-weather
construc
 The components are easy
assembled and erected.
Wastage Wastage of steel, followed by brick,
cement, concrete and timber are
closed to 10% of the total material
used in the construction project.
Wastage of timber, followed by
cement, brick, soil and concrete is less
than 5% of the total material used.
Quality  Low quality and poor finishes
due to workmanship.
 Require higher maintenance
expenses due to low quality.
 Provide higher quality and
better finishes with production
in sheltered environment or
factory.
 Better quality reduces the
maintenance expenses because
prefabricated components
required less repair and
preventive maintenance.
2.4 IBS Involvement Worldwide
IBS is widely used in developed countries. Although statistics are not readily
available, in 2002, most IBS systems in Malaysia were found to have originated from the U.S,
Germany and Australia with market share of approximately 25%, 17% and 17% respectively.
Malaysia-owned IBS accounted for only 12%. This indicates that there is a considerable
room for improvement in the area of research and development of IBS in Malaysia. Diagram
2.0 indicates the IBS involvement worldwide.
Figure 2.0: IBS Involvement Worldwide (Source: MIDFR, 2014)
25%
8%
17%4%
17%
12%
17%
U.S. Austria Germany U.K. Australia Malaysia Other countries
According to Khalfan and Maqsood’s (2014) off-site manufacturing (OSM) is a
construction technique in which prefabricated and standardised components/modules are
manufactured in a controlled factory environment (either on- or off-site), transported, erected,
and assembled into the on-site structure. OSM requires rethinking about the entire project
development process, in order to take full advantage of both on- and off-site activities.
Construction industry players in many countries started to think about innovative ways of
construction by integrating the off-site production with the on-site activities. In the UK, off-
site manufacturing has seen huge momentum since the Egan report; the size of off-site
construction industry in the UK grew from £2.2 billion in 2004 to £6 billion in 2006.
Likewise, the Australian construction industry has identified off-site manufacturing as
a key vision for improving the industry in the coming decade. In China, in order to increase
the uptake of sustainable practices, off-site manufacturing has been repeatedly promoted as a
potentially viable alternative.
2.5 Types of IBS
Based on Construction Industry Development Board (CIDB), there are 6 types of IBS
most commonly used in Malaysia, which are precast concrete system, reusable formwork
system, steel framing system, prefabricated timber framing elements such as wall, slab,
column, beam and roof truss, blockwork system and innovative system (MIDFR, 2014).
i. Precast Concrete System
This IBS consists of precast concrete columns, beams, slabs, walls, “3- D”
components (e.g. balconies, staircases, toilets, lift chambers, refuse chambers),
lightweight precast concrete and permanent concrete formworks.
Figure 2.1: Precast Concrete Framing (Source: The Constructor)
ii. Steel Formwork System
This IBS is made up of tunnel forms, beams and columns moulding forms, and
permanent steel formworks. This system is the least pre-fabricated among the IBS, as
it normally involves site casting. Therefore, it is subject to structural quality control,
high-quality finishes and fast construction with less site labour and material
requirement.
Figure 2.2: Steel Formwork System (Source: DirectIndustry)
iii. Steel Framing System
This IBS is commonly used with precast concrete slabs, steel columns/beams and
steel framing systems, and is used extensively in the fast-track construction of
skyscrapers. Apart from that, it is extensively used for light steel trusses consisting of
cost-effective profiled cold-formed channels and steel portal frame systems as
alternatives to the heavier traditional hot-rolled sections.
Figure 2.3: Steel Framing System (Source: ECOCMI)
iv. Timber framing system
It consists of timber building frames and timber roof trusses. Although the latter is
more common, timber building frame systems also offer interesting designs from
simple dwelling units to buildings such as chalets for resorts.
Figure 2.4: Timber Framing System (Source: Setia-Wood)
v. Blockwork System
It includes of interlocking concrete masonry units (CMU) and lightweight concrete
blocks. The block system is mainly used for non-structural wall as an alternative to
conventional brick and plaster.
Figure 2.5: Blockwork System (Source: CIDB)
vi. Innovative System
This is the latest IBS type which incorporates various “green” elements, which are
considered innovative in the industry. An example of the innovation is the mixture of
two elements such as polystyrene and concrete, to produce IBS components for use in
the construction of a wall which has better heat insulation properties. Indeed, with the
advancement in technology and innovation, new materials are being introduced at the
fabrication stage. Some of the new materials introduced in IBS include gypsum, wood
wool, polymer, fiberglass and aluminium-based IBS components.
2.6 Cost Comparison between Conventional Construction System and IBS in
Malaysia
There is always questions on whether IBS can reduce cost, yet there is no any
organized body that is able to provide a clear ready benchmark on this issue. In other
countries the construction labour rates are relatively higher which makes the implementation
of IBS appears to be contributing to cost saving when most of the works are done off-site.
Unlike other countries, one of the main reasons that inhibit the growth in IBS implementation
within Malaysia is due to the availability of cheap labours (Kamar et. al., 2009).
During the past decade a large number of such studies has been carried out and
published. In the existing studies three principal approaches for comparing costs of building
projects among countries can be distinguished (Haron et. al., 2005):
 Comparison of standardized identical buildings
 Comparison of standard buildings with local modifications
 Comparison of functional similar buildings
Comparison of Standardized Identical Buildings: With the first method exactly the same
building work is priced on the basis of the same drawings and specifications. This is possible
only in theory, largely as a result of national (or even regional) differences which exist in
architecture, standards, availability of products, etc. The building and the costs will be
comparable, but they are not necessarily representative.
Comparison of Standard Buildings with Local Modifications: Better representative can be
achieved when modifications for local circumstances, like building codes, standards,
specification levels, are taken into account.
Comparison of Functionally Similar Buildings: With the third approach, typical,
functionally similar buildings are compared: this means building types, which are
representative. Not only locally divergent circumstances and quality-levels are taken into
account, but also various performances and aesthetic criteria, which reflect typical client
requirements or tenant expectations for a building in that sector. The buildings and the costs
are representative, but not necessarily comparable. Arguably ‘apples’ are being compared
with ‘oranges’.
A meaningful cost comparison must take into account all relevant (time-dependent and
quantity-dependant) cost components, classified as follows:
 Labour
 Materials
 Investment
 General expenses (site and plant)
 Transportation (for system construction only)
 Overhead
2.7 Factors Affecting the Cost of IBS
Cost is the most important concern in any business endeavour, not least in the
construction industry. In order to promote the usage of IBS, it is important to exercise
foresight of the various determinants for IBS cost. The realization and understanding of cost-
determinants of IBS will enrich the cost estimator’s competence, hence, advising their clients
on the usage of IBS (Bari et.al., 2011). The factors that affect the cost of IBS are explained as
followed:
i. Labour
Malaysian construction industry is heavily dependent on unskilled worker foreigners
from countries like Bangladesh, Myanmar, Nepal, Indonesia and Vietnam as they are
cheaply available. The availability of cheap foreign labour which offsets the cost
benefit of using IBS is a root cause of the slow adoption in the past. As long as it is
easy for the industry to find foreign workers, labour rates will remain low and
builders will find it unattractive to change into simplified solutions such as IBS (Din,
2013). Table 2.2 shows the Daily IBS installer wage rates in Selangor.
Table 2.2: Daily IBS installer wage rates in Selangor in 2017. (Source: CIDB, 2017)
List of Labour Max. Min. Common
Precast Concrete Installer
Skilled, Local 150.00 80.00 102.50
Semi-skilled, Local 130.00 65.00 83.00
Lightweight Panel Installer
Skilled, Local 150.00 80.00 107.00
Semi-skilled, Local 130.00 70.00 88.00
Lightweight Blockwall Installer
Skilled, Local 150.00 90.00 109.50
Semi-skilled, Local 130.00 70.00 89.00
System Formwork Installer
Skilled, Local 150.00 90.00 111.80
Semi-skilled, Local 130.00 75.00 91.50
Roof Truss Installer (Timber)
Skilled, Local 180.00 60.00 85.50
Semi-skilled, Local 160.00 45.00 74.50
Roof Truss Installer (Light Gauge Steel)
Skilled, Local 180.00 60.00 106.30
Semi-skilled, Local 160.00 45.00 88.20
ii. Material
As compared to conventional construction method, IBS components cost higher.
However, in-situ construction contains hidden cots that usually lead to higher
expenditure, due to rectifications, wastages, etc. Furthermore, the IBS components
costs higher in Malaysia because there is still low demand and low standardization of
components. (RISM, 2015). The tailor-made components which do not fit into another
project will increase initial costs due to the cost of the mould and design. Lack of
standardisation was due to a lack of a certification and accreditation scheme on IBS
and the lukewarm response to Modular Coordination (MC) promotion under MS 1064.
There is also general consensus among practitioners that IBS needs mass production
to achieve economic viability, but currently in Malaysia, there is no assurance of
continuity of production (Din et.al., 2013).
iii. Investment
Implementation of IBS costs is about 12-13% higher compared with to conventional
methods. This is due to the high prices of IBS components that can be broken down to
purchase of new machinery, mould manufacturing, tax and machinery imported from
abroad as well as cost of training workers for the installation of the components and
operation of various high tech machines (MIDFR, 2014). To use a higher level of IBS,
the adopters require a huge volume of works to break even on the investment.
Although it creates more value to construction, it is literally a more expensive option
due to the paid up capitals and maintenance of machineries. Inconsistency of volume
over time and lack of business continuity resulted in the investment in latest
innovation not being commercially sustainable (Din et. al., 2013). In most cases,
builders have different requests in term of components’ specifications, which further
require the manufacturers to invest for new moulds. This scenario is deemed not
sustainable as the manufacturing companies usually have their own economic
strategic planning. It is because of the trend of mass production which requires the
customization of products and services that eventually leading to cost reduction
(Ariffin et. al., 2016). Hence, the high initial capital can be overcome by sufficient
volume and ability to reduce mould cost with repetition use of the design.
iv. General expenses (Site and Plant)
Enormous capital cost also includes setting up the plant. Most of the IBS
manufacturer was concerned on the value obtained from the project before the setting
up the IBS precast manufacturing plant and rule of the thumb for the profit margin
IBS project is around 10%. Usually the large IBS manufacturer player will target a
minimum production value of RM100 million annually and for the new player will
target a minimum project value of at least RM10 million annually. The new IBS
manufacturer player will preferable choose the mobile manufacturing plant which
require a lower initial capital and the average initial cost for the setting up of the plant
is about RM1 million. Although, the big IBS player have the capacity for setting up a
permanent manufacturing plant, but the initial capital will cost about RM15 million to
RM25 million and it is 15 to 25 times the cost for setting up a mobile IBS
manufacturing plant (Azman et.al., 2013). The high cost of IBS can also be due to a
mismatch in supply and demand for IBS components as there are limited numbers of
IBS suppliers in the industry against the backdrop of a rising demand for IBS
components. Figure 2.6 shows the number of IBS products according to the
classification groups (Azman et. al., 2010).
Figure 2.6: The Number of IBS Manufacturer and IBS Products
According to Pan et al., (2004) site specifics or constraints also cause additional costs
in the IBS construction process since IBS components required additional space for
storage, mobilization and circulation of machines and equipment (Jabar et.al., 2013).
v. Transportation
Transportation cost high affect cost of IBS implementation due to difficulties to
access to site and difficulties to transport big components from factory to construction
site. The expenditures of transportation process can amount to 3%-5% of the total cost
for distances not exceeding 50km – 100km (Qays et.al., 2010). According to CIDB,
the majority of IBS manufacturers are located in industrial zones in urban areas. If a
construction site is located too far away from the IBS manufacturers or suppliers,
this will indirectly increase the logistics and shipping costs in a construction project
budget (Wong & Lau, 2015). On the other hand, the transport used to carry IBS
components need to be redesign to be able to carry larger panels. Lorries that are
redesigned must meet the suitability and at the same time to follow the road
regulations. Currently, the transporters can carry limited weight, length and depth of
IBS components stated in the road regulations therefore the optimum carrying
capacity is not met, causing the transportation and delivery cost to be expensive.
vi. Overhead
According to CIDB, with less labour involved in the IBS construction, overall
construction time is shorter. This will enable the constructor to save on the overhead
cost involved in the construction. Kadir (2006) also agreed that shorter construction
time of IBS implies lower site staff overhead and cost saving on equipment rental.
2.8 Summary
The literature review has outlined insights into the current thinking on IBS. Moreover,
related works of researchers in the past have been studies with a view to visualize the gaps in
the literature where the current study may contribute to fill in.
In regards to the research objectives, the reviews have provided part answers as
proffered by the researchers in the past. They are then discussed as below.
2.8.1 Findings in relation to the first objective
The first objective of the study is to determine the most common type of IBS used in
Malaysia. Outcome from the literature review has identified the six categories of IBS adopted
by Malaysian construction industry. However, there is still lack of information on evaluating
and rank a range of six IBS types frequently used in Malaysia. Therefore this study is
important to identify the most regularly implemented IBS type hence focus on its value to be
promoted to local construction industry player.
2.8.2 Findings in relation to the second objective
The second objective is to identify the factors affecting the cost of IBS construction
method in Malaysia. A clearer understanding of the cost determinants is vital to achieve the
desired level of accuracy of anticipated labour costs, material costs, investment cost, general
expenses, transportation cost and overhead cost in total cost estimation, hence add value to
Malaysian construction industry while deciding whether to adopt IBS in their respective
projects.
2.8.3 Findings in relation to the third objective
The third objective is to compare the cost differences between IBS and conventional
construction method in residential building. In order to carry out meaningful comparison,
various considerations must take into account, which include time-dependent and quantity-
dependent cost components. There are three types of comparison as suggested in the literature
review, which are comparison of standardized identical buildings, comparison of standard
buildings with local modifications and comparison of functional similar building. In this
research, the first and third approaches are adopted simultaneously.
REFERENCES
A.R.Z. Abidin (2007). Simulation of IBS Formation for Housing Construction. Retrieved on
28th Nov 2017, from
http://eprints.utm.my/11242/1/AhmadRazinZainalMFKA2007.pdf
CIDB (2017). Labour Wage Rate. Retrieved on 28th Nov2017, from
http://myn3c.cidb.gov.my/cidb_n3c/output/a_web_lwr_details.php?4#
D. Natasha, M.N.A.Azman, Khuan, W.B., N.F. Habidin and A.R. Ayub (2016). Issues of
Payment Procurement Process for IBS Project. Retrieved on 28th Nov 2017, from
https://www.researchgate.net/publication/303681753_ISSUES_OF_PAYMENT_PR
OCUREMENT_PROCESS_FOR_INDUSTRIALISED_BUILDING_SYSTEM_IBS_
PROJECT
K.A.M. Kamar , Z.A. Hamid, M.N.A. Azman , M.S.S. Ahamad (2011). Industrialized
Building System (IBS): Revisiting Issues of Definition and Classification. Retrieved
on 28th Nov 2017, from
http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.301.2957&rep=rep1&type=
pdf
M. A. Khalfan and Tayyab Maqsood. (2014). Current State of Off-Site Manufacturing in
Australian and Chinese Residential Construction. Retrieved on 28th Nov 2017, from
https://www.hindawi.com/journals/jcen/2014/164863/
MIDFR (2014). Construction IBS: Practical Solution to Rising Costs. Retrieved on 28th Nov 2017,
from
http://www.midf.com.my/images/Downloads/Research/EqStrategy/SpecialReports/Co
nstruction-IBS_MIDF_140214.pdf
M.N.A. Azman, M.S.S. Ahamad, T.A.Majid, and M.H. Hanafi(2010). Status of Industrialized
Building System Manufacturing Plant in Malaysia. Retrieved on 28th Nov 2017, from
https://www.academia.edu/6389771/Status_of_Industrialized_Building_System_Man
ufacturing_Plant_in_Malaysia
M.N.A. Azman, M.S.S. Ahamad, T.A. Majid and M.H. Hanafi(2013). Permanent and Mobile
Industrialised Building System Manufacturing Plant Based on Malaysian Case Study.
Retrieved on 28th Nov 2017, from
https://www.academia.edu/21345738/Permanent_and_Mobile_Industrialised_Buildin
g_System_Manufacturing_Plant_Based_on_Malaysian_Case_Study
M.R. A. Kadir, Lee,W.P.,M.S. Jaafar,S.M. Sapuan and A.A.A. Ali (2006). Construction
Performance Comparison between Conventional and Industrialized Building System in
Malaysia. Retrieved on 28th Nov 2017, from
http://leewp33.tripod.com/sitebuildercontent/sitebuilderfiles/structuralsurvey2006.pdf
M.Qays,K.N.Mustapha,Al-Mattarneh and N.S. Mohamed (2010). The Constraints of Industrialized
Building System from Stakeholders’ Point of View. Retrieved on 28th Nov 2017, from
https://www.researchgate.net/publication/303330111_The_Constraints_of_Industriali
zed_Building_System_from_Stakeholders%27_Point_of_View
M.Z. Ramli, M.H. Hanipah, M.H. Zawawi,M.Z.Z. Abidin, NurAtiqah Zainal, N.S.A. Halim (2016).
Cost comparison on industrialized building system (IBS) and conventional method for school
construction project. Retrieved on 28th Nov 2017, from http://jsrad.org/wp-
content/2016/Issue%204,%202016/16jj.pdf
N.A.A. Bari,R.Y.N. Ismail, A. Jaapar and R. Ahmad (2011). Factors Influencing the Construction
Cost of Industrialised Building System (IBS) Projects. Retrieved on 28th Nov 2017, from
https://ac.els-cdn.com/S1877042812004508/1-s2.0-S1877042812004508-
main.pdf?_tid=b0075874-d279-11e7-a471-
00000aab0f6b&acdnat=1511680754_7c70445cf8d146069e7145fff0e8e9a9
N.A. Haron, Ir. S.H. Mohd. R.A. Kadir and M.S. Jaafar (2005). Building Cost Comparison
Between Conventional and Formwork System: A Case Study of Four-storey School Buildings
in Malaysia. Retrieved on 28th Nov 2017, from
http://thescipub.com/PDF/ajassp.2005.819.823.pdf
RISM (2015). Translating Innovative Construction Method into Cost Saving. Retrieved on 28th Nov
2017, from http://www.rism.org.my/wp-content/uploads/2015/11/03-3-Translating-
Innovative-Construction-Method-Into-Cost-Saving-Ar-Haji-Abdul-HalimSuhor.pdf
Wong, S.S., Lau, L.K. (2015). Advantages and Setbacks of IBS Implementation: A Case Study in
Sarawak. Retrieved on 28th Nov 2017, from
https://www.researchgate.net/publication/281071898_Advantages_and_Setbacks_of_I
ndustrialized_Building_System_IBS_Implementation_A_Case_Study_in_Sarawak
Chap 2-literature-review (3)

More Related Content

What's hot

B.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsB.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsCarmen Chan
 
prefabrication structure report
prefabrication structure report prefabrication structure report
prefabrication structure report AbhishekM45
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)I'mMiss Lily
 
230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).pptMohd Zulhairi Mohd Noor
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technologyGedalaJairam
 
Building Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSBuilding Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSJing Fan Koh
 
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...Haziq1511
 
Pre fabricated structures
Pre fabricated structuresPre fabricated structures
Pre fabricated structuresjamali husain
 
Blockwork system
Blockwork systemBlockwork system
Blockwork systemWen Crystal
 
PREFABRICATION BUILDING
PREFABRICATION BUILDINGPREFABRICATION BUILDING
PREFABRICATION BUILDINGsathish sak
 
Modular building seminar REPORT 1
Modular building seminar REPORT 1Modular building seminar REPORT 1
Modular building seminar REPORT 1Sabik Np
 
Building technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSBuilding technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSDigital Space Consultancy Ltd
 
Modular Construction Solution For Rapid Cost-effective Development Of Housing
Modular Construction Solution For Rapid Cost-effective Development Of HousingModular Construction Solution For Rapid Cost-effective Development Of Housing
Modular Construction Solution For Rapid Cost-effective Development Of HousingLoay Ghazaleh MBA, BSc Civil Eng.
 
Method statement honycomb repairing
Method statement  honycomb repairingMethod statement  honycomb repairing
Method statement honycomb repairingBharatha Rathnayke
 
Building Technology PJT 1 Report
Building Technology PJT 1 Report Building Technology PJT 1 Report
Building Technology PJT 1 Report ForestedTiger
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionJenilPatel22
 

What's hot (20)

B.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsB.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building Systems
 
prefabrication structure report
prefabrication structure report prefabrication structure report
prefabrication structure report
 
Bracing connections
Bracing connectionsBracing connections
Bracing connections
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
 
230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technology
 
Building Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSBuilding Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBS
 
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
 
Pre fabricated structures
Pre fabricated structuresPre fabricated structures
Pre fabricated structures
 
Blockwork system
Blockwork systemBlockwork system
Blockwork system
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
 
PREFABRICATION BUILDING
PREFABRICATION BUILDINGPREFABRICATION BUILDING
PREFABRICATION BUILDING
 
Modular building seminar REPORT 1
Modular building seminar REPORT 1Modular building seminar REPORT 1
Modular building seminar REPORT 1
 
Building technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSBuilding technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBS
 
Modular Construction Solution For Rapid Cost-effective Development Of Housing
Modular Construction Solution For Rapid Cost-effective Development Of HousingModular Construction Solution For Rapid Cost-effective Development Of Housing
Modular Construction Solution For Rapid Cost-effective Development Of Housing
 
Method statement honycomb repairing
Method statement  honycomb repairingMethod statement  honycomb repairing
Method statement honycomb repairing
 
Building Technology PJT 1 Report
Building Technology PJT 1 Report Building Technology PJT 1 Report
Building Technology PJT 1 Report
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 

Similar to Chap 2-literature-review (3)

Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3 Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3 Yee Len Wan
 
MS Ibs in malaysia
MS Ibs in malaysiaMS Ibs in malaysia
MS Ibs in malaysiaEst
 
CSCM Ibs in malaysia
CSCM Ibs in malaysiaCSCM Ibs in malaysia
CSCM Ibs in malaysiaEst
 
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...IRJET Journal
 
Coordination of Building Services: A Review
Coordination of Building Services: A ReviewCoordination of Building Services: A Review
Coordination of Building Services: A ReviewIRJET Journal
 
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET Journal
 
IRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET Journal
 
Chapter 1-research proposal
Chapter 1-research proposalChapter 1-research proposal
Chapter 1-research proposalJessyca Than
 
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET Journal
 
Productivity in Building Construction
Productivity in Building ConstructionProductivity in Building Construction
Productivity in Building ConstructionIOSR Journals
 
Modular Coordination in buildings and construction.pptx
Modular Coordination in buildings and construction.pptxModular Coordination in buildings and construction.pptx
Modular Coordination in buildings and construction.pptxAtulBhagwat6
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsIRJET Journal
 
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET Journal
 
IRJET- Comparative Study between RCC Structures and Prefabricated Structures
IRJET- Comparative Study between RCC Structures and Prefabricated StructuresIRJET- Comparative Study between RCC Structures and Prefabricated Structures
IRJET- Comparative Study between RCC Structures and Prefabricated StructuresIRJET Journal
 
IRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate Developers
IRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate DevelopersIRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate Developers
IRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate DevelopersIRJET Journal
 
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET Journal
 
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...IRJET Journal
 
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...IRJET Journal
 
Building Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyBuilding Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyQuinn Liew
 

Similar to Chap 2-literature-review (3) (20)

Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3 Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3
 
MS Ibs in malaysia
MS Ibs in malaysiaMS Ibs in malaysia
MS Ibs in malaysia
 
CSCM Ibs in malaysia
CSCM Ibs in malaysiaCSCM Ibs in malaysia
CSCM Ibs in malaysia
 
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
 
Coordination of Building Services: A Review
Coordination of Building Services: A ReviewCoordination of Building Services: A Review
Coordination of Building Services: A Review
 
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
 
IRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case Study
 
Chapter 1-research proposal
Chapter 1-research proposalChapter 1-research proposal
Chapter 1-research proposal
 
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
 
Productivity in Building Construction
Productivity in Building ConstructionProductivity in Building Construction
Productivity in Building Construction
 
Modular Coordination in buildings and construction.pptx
Modular Coordination in buildings and construction.pptxModular Coordination in buildings and construction.pptx
Modular Coordination in buildings and construction.pptx
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast Buildings
 
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
 
IRJET- Comparative Study between RCC Structures and Prefabricated Structures
IRJET- Comparative Study between RCC Structures and Prefabricated StructuresIRJET- Comparative Study between RCC Structures and Prefabricated Structures
IRJET- Comparative Study between RCC Structures and Prefabricated Structures
 
IRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate Developers
IRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate DevelopersIRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate Developers
IRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate Developers
 
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
 
A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES
 
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...
 
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
 
Building Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyBuilding Technology : Industrialize Building Technology
Building Technology : Industrialize Building Technology
 

More from Jessyca Than

Construction law lecture 10
Construction law lecture 10Construction law lecture 10
Construction law lecture 10Jessyca Than
 
Be assignment-presentation 0
Be assignment-presentation 0Be assignment-presentation 0
Be assignment-presentation 0Jessyca Than
 
Be final report (1)
Be final report (1)Be final report (1)
Be final report (1)Jessyca Than
 
Indoor environmental-quality-in-healthcare-3-2
Indoor environmental-quality-in-healthcare-3-2Indoor environmental-quality-in-healthcare-3-2
Indoor environmental-quality-in-healthcare-3-2Jessyca Than
 
Measurement 1 site report
Measurement 1 site reportMeasurement 1 site report
Measurement 1 site reportJessyca Than
 
Mural presentation
Mural presentationMural presentation
Mural presentationJessyca Than
 
Spiderman vs batman
Spiderman vs batman Spiderman vs batman
Spiderman vs batman Jessyca Than
 
Threesome love with storyline
Threesome love with storylineThreesome love with storyline
Threesome love with storylineJessyca Than
 
Psychology comic strip slides
Psychology comic strip slidesPsychology comic strip slides
Psychology comic strip slidesJessyca Than
 
Psychology journal
Psychology journal Psychology journal
Psychology journal Jessyca Than
 

More from Jessyca Than (18)

Vm report
Vm reportVm report
Vm report
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Construction law lecture 10
Construction law lecture 10Construction law lecture 10
Construction law lecture 10
 
Be assignment-presentation 0
Be assignment-presentation 0Be assignment-presentation 0
Be assignment-presentation 0
 
Be final report (1)
Be final report (1)Be final report (1)
Be final report (1)
 
Fm compilation
Fm compilationFm compilation
Fm compilation
 
Seminar p8x
Seminar p8xSeminar p8x
Seminar p8x
 
Pp2 asignment-1
Pp2 asignment-1Pp2 asignment-1
Pp2 asignment-1
 
Indoor environmental-quality-in-healthcare-3-2
Indoor environmental-quality-in-healthcare-3-2Indoor environmental-quality-in-healthcare-3-2
Indoor environmental-quality-in-healthcare-3-2
 
Measurement 1 site report
Measurement 1 site reportMeasurement 1 site report
Measurement 1 site report
 
Presentation1 1
Presentation1 1Presentation1 1
Presentation1 1
 
Compilation
CompilationCompilation
Compilation
 
Mural presentation
Mural presentationMural presentation
Mural presentation
 
Spiderman vs batman
Spiderman vs batman Spiderman vs batman
Spiderman vs batman
 
Psycho report
Psycho reportPsycho report
Psycho report
 
Threesome love with storyline
Threesome love with storylineThreesome love with storyline
Threesome love with storyline
 
Psychology comic strip slides
Psychology comic strip slidesPsychology comic strip slides
Psychology comic strip slides
 
Psychology journal
Psychology journal Psychology journal
Psychology journal
 

Recently uploaded

Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........LeaCamillePacle
 
ROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationAadityaSharma884161
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxLigayaBacuel1
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 

Recently uploaded (20)

Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........
 
ROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint Presentation
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptx
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 

Chap 2-literature-review (3)

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN Bachelor of Quantity Surveying (Honours) LITERATURE REVIEW BUILDING COST COMPARISON BETWEEN CONVENTIONAL METHOD AND INDUSTRIALIZED BUILDING SYSTEM (IBS) IN MALAYSIA STUDENT NAME: THAN LEK MEI STUDENT ID NO: 0315538 SUPERVISOR: MR. MOHAMMED RIZAL DATE OF SUBMISSION: 30 NOVEMBER2017
  • 2. BUILDING COST COMPARISON BETWEEN CONVENTIONAL METHOD AND INDUSTRIALIZED BUILDING SYSTEM (IBS) IN MALAYSIA THAN LEK MEI (0315538)
  • 3. TABLES OF CONTENTS CHAPTER TITLE PAGE 2 2.1 Introduction 1 2.2 Definitions and Principles 2 2.2.1 Conventional Construction System 2 2.2.2 Industrialized Building System (IBS) 3 2.3 Comparison between Conventional Construction System and IBS 5 2.4 IBS Involvement Worldwide 6 2.5 Types of IBS 7 2.6 Cost Comparison between Conventional Construction System and IBS in Malaysia 12 2.7 Factors Affecting the Cost of IBS 14 2.8 Summary 18 2.8.1 Findings in relation to the first objective 18 2.8.2 Findings in relation to the second objective 19 2.8.3 Findings in relation to the third objective 19 REFERENCES
  • 4. LIST OF TABLES PAGE Table 2.0 Categorization of IBS terminologies 4 Table 2.1 Comparison between Conventional and IBS Construction 5 Table 2.2 Daily IBS installer wage rates in Selangor in 2017 14
  • 5. LIST OF FIGURES PAGE Figure 2.0 IBS Involvement Worldwide 6 Figure 2.1 Precast Concrete Framing 8 Figure 2.2 Steel Formwork System 9 Figure 2.3 Steel Framing System 10 Figure 2.4 Timber Framing System 11 Figure 2.5 Blockwork System 11 Figure 2.6 The Number of IBS Manufacturer and IBS Products 16
  • 6. CHAPTER 2 LITERATURE REVIEW 2.1 Introduction The Malaysian construction firms are always encouraged to do more with less. More speed, more efficiency with less manpower, costs and delays. In another words, productivity needs to be increased. CIDB has championed IBS through a variation of initiatives, which include crediting IBS courses, hosting seminars to promote IBS and providing support for trainings (CIDB, 2016). Notwithstanding, there still sees reluctance of local construction industry to take up IBS as most of the contractors are get used to the conventional method as well as the abundance of cheap foreign labour available in Malaysia. While the cost of IBS implementation is not clearly outlined by any official institutions, this research paper aims to identify the factors affecting cost of IBS and the cost differences between IBS and conventional method in residential building.
  • 7. 2.2 Definitions and Principles 2.2.1 Conventional Construction System Over the decades, conventional building system has been broadly practiced worldwide and locally in Malaysian construction industry as the contractors are familiar with its procedures and limitations. This method has also displayed a reasonable level of performance which encourages the contractors to stay with the system. The ground of conventional construction is not from engineering analysis; instead it is from the historic methods of construction with wood members. Conventional system in Malaysia consists of reinforced concrete frames with brick in-fill walls, timber or cold formed metal trussed roof with either clay or concrete tiles, or sheet metal roofs. The building frame components are pre-fabricated on site by means of 4-steps course (Ramli et. al., 2016): i. Erection of timber or plywood formwork and scaffolding ii. Installation of steel reinforcement iii. Pouring of fresh concrete iv. Dissemble of formwork and scaffolding There sees how crucial it is to realize that the original structures from which these methods of construction were derived are relatively small, with small horizontal spans and moderate wall heights. The floor plans for these building were typically rectilinear. According to Resat (2007), conventional, also recognized as traditional construction method possesses its characteristics which are the basic construction methods in construction industry in the world. The characteristics of conventional method include:
  • 8. i. Use cast in-situ system. All building components are being built and cast on site with high usage of construction materials and load of site works. ii. Labour-intensive practices. iii. 3-D syndrome which are Dirty, Difficult and Dangerous. Conventional system is known with the 3-D syndrome. All sites work that being done which involved many types of construction materials and machineries and high number of workers will make the construction sites messy and crowded. This will lead to dirty and dangerous environment. 2.2.2 Industrialized Building System (IBS) Kamar et. al. (2011) provide a clear understanding on IBS’s etymology and classification for practitioners and policy makers. In the perspective of construction. Council for Research and Innovation in Building and Construction (CIB) defined industrialized construction as a generic process of standardization and rationalization of the work processes in the industry to reach cost efficiency, higher productivity and quality. Further, Abdullah and Egbu defined IBS as a construction method developed due to human investment in innovation and on rethinking the best ways of construction work deliveries based on the level of industrialization. The level of industrialization in IBS can be classified as pre-building system, modern construction, advance automation and volumetric construction. On the other hand, Hassim defined IBS as an organizational process- continuity of production implying a steady flow of demand, standardization, integration of the whole production process, a high degree of organization of work mechanization to replace human labour. IBS also defined by Rahman and Omar as a construction system using pre- fabricated components. The manufacturing of the components is systematically organized using machine, formworks and other forms of mechanical equipment. The components are manufactured in the factory and once completed will be delivered to construction sites for
  • 9. assembly and erection. However Pan (2006) outlined other terminologies used globally as presented in Table 2.0, where all these terms are all representing IBS in this paper. Table 2.0: Categorization of IBS terminologies. (Pan, 2006) Terminology Category Term OS Offsite Production (OSP) Offsite Manufacturing (OSM) Offsite Fabrication (OSF) Offsite Construction PRE Pre-assembly Prefabrication Prefab MM Modern Methods of Construction Modern Methods of House Construction Modern Methods of House Building Building System Building Non-traditional Building Industrialized Building In Malaysia, CIDB defines IBS as a system of construction whereby building components are produced at factories or off site, transported and consequently bring together into a structure with slightest work. According to CIDB, systems to be accepted as part of IBS need to portrait all six essential characteristics as listed below to warrant the realization of the claimed benefits. (MIDFR, 2014): 1. Industrial production of components though pre-fabrication; 2. Highly mechanised in-situ processes i.e. slip-forms, post-tensioning, tunnel shutters; 3. Reduced labour during prefabrication of components and site works; 4. Modern design and manufacturing methods i.e. involvement of Computer Aided Design (CAD) and Computer Aided Manufacturing (CAM); 5. Systematic Quality Control i.e. ISO 9000 principles; 6. Open Building Concept i.e. permitting hybrid applications, adaptable to standardisation and Modular Coordination (MC).
  • 10. The Construction Industry Master Plan 2006–2015 in Malaysia has given significant importance to the off-site manufacturing. The term used is Industrialised Building System (IBS) and is defined as a construction technique in which components are manufactured in a controlled environment (on- or off-site), transported, positioned, and assembled into an on- site structure with minimal additional site works. 2.3 Comparison between Conventional Construction System and IBS Different approach of construction provides different outcomes. In fact, there are some differences between conventional construction method and IBS, which can be measured from the perspective of productivity, value chain, construction time, reduction on dependency on foreign labour, cost of construction and construction wastages as shown in Table 2.1 ( Natasha et. al., 2016) : Table 2.1: Comparison between Conventional and IBS Construction Component Approach Conventional Construction IBS Construction Cost Require higher cost in terms of:     Overhead costs Reduce construction wastage and increases the cost savings as follows:     Overhead costs Speed   Delay completion of the project due to the on-site  Components are disaggregated and difficult to assemble and erected.  Shorter construction period.  Permit a faster completion of the project because of its rapid and all-weather construc  The components are easy assembled and erected.
  • 11. Wastage Wastage of steel, followed by brick, cement, concrete and timber are closed to 10% of the total material used in the construction project. Wastage of timber, followed by cement, brick, soil and concrete is less than 5% of the total material used. Quality  Low quality and poor finishes due to workmanship.  Require higher maintenance expenses due to low quality.  Provide higher quality and better finishes with production in sheltered environment or factory.  Better quality reduces the maintenance expenses because prefabricated components required less repair and preventive maintenance. 2.4 IBS Involvement Worldwide IBS is widely used in developed countries. Although statistics are not readily available, in 2002, most IBS systems in Malaysia were found to have originated from the U.S, Germany and Australia with market share of approximately 25%, 17% and 17% respectively. Malaysia-owned IBS accounted for only 12%. This indicates that there is a considerable room for improvement in the area of research and development of IBS in Malaysia. Diagram 2.0 indicates the IBS involvement worldwide. Figure 2.0: IBS Involvement Worldwide (Source: MIDFR, 2014) 25% 8% 17%4% 17% 12% 17% U.S. Austria Germany U.K. Australia Malaysia Other countries
  • 12. According to Khalfan and Maqsood’s (2014) off-site manufacturing (OSM) is a construction technique in which prefabricated and standardised components/modules are manufactured in a controlled factory environment (either on- or off-site), transported, erected, and assembled into the on-site structure. OSM requires rethinking about the entire project development process, in order to take full advantage of both on- and off-site activities. Construction industry players in many countries started to think about innovative ways of construction by integrating the off-site production with the on-site activities. In the UK, off- site manufacturing has seen huge momentum since the Egan report; the size of off-site construction industry in the UK grew from £2.2 billion in 2004 to £6 billion in 2006. Likewise, the Australian construction industry has identified off-site manufacturing as a key vision for improving the industry in the coming decade. In China, in order to increase the uptake of sustainable practices, off-site manufacturing has been repeatedly promoted as a potentially viable alternative. 2.5 Types of IBS Based on Construction Industry Development Board (CIDB), there are 6 types of IBS most commonly used in Malaysia, which are precast concrete system, reusable formwork system, steel framing system, prefabricated timber framing elements such as wall, slab, column, beam and roof truss, blockwork system and innovative system (MIDFR, 2014).
  • 13. i. Precast Concrete System This IBS consists of precast concrete columns, beams, slabs, walls, “3- D” components (e.g. balconies, staircases, toilets, lift chambers, refuse chambers), lightweight precast concrete and permanent concrete formworks. Figure 2.1: Precast Concrete Framing (Source: The Constructor)
  • 14. ii. Steel Formwork System This IBS is made up of tunnel forms, beams and columns moulding forms, and permanent steel formworks. This system is the least pre-fabricated among the IBS, as it normally involves site casting. Therefore, it is subject to structural quality control, high-quality finishes and fast construction with less site labour and material requirement. Figure 2.2: Steel Formwork System (Source: DirectIndustry)
  • 15. iii. Steel Framing System This IBS is commonly used with precast concrete slabs, steel columns/beams and steel framing systems, and is used extensively in the fast-track construction of skyscrapers. Apart from that, it is extensively used for light steel trusses consisting of cost-effective profiled cold-formed channels and steel portal frame systems as alternatives to the heavier traditional hot-rolled sections. Figure 2.3: Steel Framing System (Source: ECOCMI)
  • 16. iv. Timber framing system It consists of timber building frames and timber roof trusses. Although the latter is more common, timber building frame systems also offer interesting designs from simple dwelling units to buildings such as chalets for resorts. Figure 2.4: Timber Framing System (Source: Setia-Wood) v. Blockwork System It includes of interlocking concrete masonry units (CMU) and lightweight concrete blocks. The block system is mainly used for non-structural wall as an alternative to conventional brick and plaster. Figure 2.5: Blockwork System (Source: CIDB)
  • 17. vi. Innovative System This is the latest IBS type which incorporates various “green” elements, which are considered innovative in the industry. An example of the innovation is the mixture of two elements such as polystyrene and concrete, to produce IBS components for use in the construction of a wall which has better heat insulation properties. Indeed, with the advancement in technology and innovation, new materials are being introduced at the fabrication stage. Some of the new materials introduced in IBS include gypsum, wood wool, polymer, fiberglass and aluminium-based IBS components. 2.6 Cost Comparison between Conventional Construction System and IBS in Malaysia There is always questions on whether IBS can reduce cost, yet there is no any organized body that is able to provide a clear ready benchmark on this issue. In other countries the construction labour rates are relatively higher which makes the implementation of IBS appears to be contributing to cost saving when most of the works are done off-site. Unlike other countries, one of the main reasons that inhibit the growth in IBS implementation within Malaysia is due to the availability of cheap labours (Kamar et. al., 2009). During the past decade a large number of such studies has been carried out and published. In the existing studies three principal approaches for comparing costs of building projects among countries can be distinguished (Haron et. al., 2005):  Comparison of standardized identical buildings  Comparison of standard buildings with local modifications  Comparison of functional similar buildings
  • 18. Comparison of Standardized Identical Buildings: With the first method exactly the same building work is priced on the basis of the same drawings and specifications. This is possible only in theory, largely as a result of national (or even regional) differences which exist in architecture, standards, availability of products, etc. The building and the costs will be comparable, but they are not necessarily representative. Comparison of Standard Buildings with Local Modifications: Better representative can be achieved when modifications for local circumstances, like building codes, standards, specification levels, are taken into account. Comparison of Functionally Similar Buildings: With the third approach, typical, functionally similar buildings are compared: this means building types, which are representative. Not only locally divergent circumstances and quality-levels are taken into account, but also various performances and aesthetic criteria, which reflect typical client requirements or tenant expectations for a building in that sector. The buildings and the costs are representative, but not necessarily comparable. Arguably ‘apples’ are being compared with ‘oranges’. A meaningful cost comparison must take into account all relevant (time-dependent and quantity-dependant) cost components, classified as follows:  Labour  Materials  Investment  General expenses (site and plant)  Transportation (for system construction only)  Overhead
  • 19. 2.7 Factors Affecting the Cost of IBS Cost is the most important concern in any business endeavour, not least in the construction industry. In order to promote the usage of IBS, it is important to exercise foresight of the various determinants for IBS cost. The realization and understanding of cost- determinants of IBS will enrich the cost estimator’s competence, hence, advising their clients on the usage of IBS (Bari et.al., 2011). The factors that affect the cost of IBS are explained as followed: i. Labour Malaysian construction industry is heavily dependent on unskilled worker foreigners from countries like Bangladesh, Myanmar, Nepal, Indonesia and Vietnam as they are cheaply available. The availability of cheap foreign labour which offsets the cost benefit of using IBS is a root cause of the slow adoption in the past. As long as it is easy for the industry to find foreign workers, labour rates will remain low and builders will find it unattractive to change into simplified solutions such as IBS (Din, 2013). Table 2.2 shows the Daily IBS installer wage rates in Selangor. Table 2.2: Daily IBS installer wage rates in Selangor in 2017. (Source: CIDB, 2017) List of Labour Max. Min. Common Precast Concrete Installer Skilled, Local 150.00 80.00 102.50 Semi-skilled, Local 130.00 65.00 83.00 Lightweight Panel Installer Skilled, Local 150.00 80.00 107.00 Semi-skilled, Local 130.00 70.00 88.00 Lightweight Blockwall Installer Skilled, Local 150.00 90.00 109.50 Semi-skilled, Local 130.00 70.00 89.00 System Formwork Installer Skilled, Local 150.00 90.00 111.80 Semi-skilled, Local 130.00 75.00 91.50 Roof Truss Installer (Timber) Skilled, Local 180.00 60.00 85.50 Semi-skilled, Local 160.00 45.00 74.50 Roof Truss Installer (Light Gauge Steel) Skilled, Local 180.00 60.00 106.30 Semi-skilled, Local 160.00 45.00 88.20
  • 20. ii. Material As compared to conventional construction method, IBS components cost higher. However, in-situ construction contains hidden cots that usually lead to higher expenditure, due to rectifications, wastages, etc. Furthermore, the IBS components costs higher in Malaysia because there is still low demand and low standardization of components. (RISM, 2015). The tailor-made components which do not fit into another project will increase initial costs due to the cost of the mould and design. Lack of standardisation was due to a lack of a certification and accreditation scheme on IBS and the lukewarm response to Modular Coordination (MC) promotion under MS 1064. There is also general consensus among practitioners that IBS needs mass production to achieve economic viability, but currently in Malaysia, there is no assurance of continuity of production (Din et.al., 2013). iii. Investment Implementation of IBS costs is about 12-13% higher compared with to conventional methods. This is due to the high prices of IBS components that can be broken down to purchase of new machinery, mould manufacturing, tax and machinery imported from abroad as well as cost of training workers for the installation of the components and operation of various high tech machines (MIDFR, 2014). To use a higher level of IBS, the adopters require a huge volume of works to break even on the investment. Although it creates more value to construction, it is literally a more expensive option due to the paid up capitals and maintenance of machineries. Inconsistency of volume over time and lack of business continuity resulted in the investment in latest innovation not being commercially sustainable (Din et. al., 2013). In most cases, builders have different requests in term of components’ specifications, which further require the manufacturers to invest for new moulds. This scenario is deemed not sustainable as the manufacturing companies usually have their own economic strategic planning. It is because of the trend of mass production which requires the customization of products and services that eventually leading to cost reduction (Ariffin et. al., 2016). Hence, the high initial capital can be overcome by sufficient volume and ability to reduce mould cost with repetition use of the design.
  • 21. iv. General expenses (Site and Plant) Enormous capital cost also includes setting up the plant. Most of the IBS manufacturer was concerned on the value obtained from the project before the setting up the IBS precast manufacturing plant and rule of the thumb for the profit margin IBS project is around 10%. Usually the large IBS manufacturer player will target a minimum production value of RM100 million annually and for the new player will target a minimum project value of at least RM10 million annually. The new IBS manufacturer player will preferable choose the mobile manufacturing plant which require a lower initial capital and the average initial cost for the setting up of the plant is about RM1 million. Although, the big IBS player have the capacity for setting up a permanent manufacturing plant, but the initial capital will cost about RM15 million to RM25 million and it is 15 to 25 times the cost for setting up a mobile IBS manufacturing plant (Azman et.al., 2013). The high cost of IBS can also be due to a mismatch in supply and demand for IBS components as there are limited numbers of IBS suppliers in the industry against the backdrop of a rising demand for IBS components. Figure 2.6 shows the number of IBS products according to the classification groups (Azman et. al., 2010). Figure 2.6: The Number of IBS Manufacturer and IBS Products According to Pan et al., (2004) site specifics or constraints also cause additional costs in the IBS construction process since IBS components required additional space for storage, mobilization and circulation of machines and equipment (Jabar et.al., 2013).
  • 22. v. Transportation Transportation cost high affect cost of IBS implementation due to difficulties to access to site and difficulties to transport big components from factory to construction site. The expenditures of transportation process can amount to 3%-5% of the total cost for distances not exceeding 50km – 100km (Qays et.al., 2010). According to CIDB, the majority of IBS manufacturers are located in industrial zones in urban areas. If a construction site is located too far away from the IBS manufacturers or suppliers, this will indirectly increase the logistics and shipping costs in a construction project budget (Wong & Lau, 2015). On the other hand, the transport used to carry IBS components need to be redesign to be able to carry larger panels. Lorries that are redesigned must meet the suitability and at the same time to follow the road regulations. Currently, the transporters can carry limited weight, length and depth of IBS components stated in the road regulations therefore the optimum carrying capacity is not met, causing the transportation and delivery cost to be expensive. vi. Overhead According to CIDB, with less labour involved in the IBS construction, overall construction time is shorter. This will enable the constructor to save on the overhead cost involved in the construction. Kadir (2006) also agreed that shorter construction time of IBS implies lower site staff overhead and cost saving on equipment rental.
  • 23. 2.8 Summary The literature review has outlined insights into the current thinking on IBS. Moreover, related works of researchers in the past have been studies with a view to visualize the gaps in the literature where the current study may contribute to fill in. In regards to the research objectives, the reviews have provided part answers as proffered by the researchers in the past. They are then discussed as below. 2.8.1 Findings in relation to the first objective The first objective of the study is to determine the most common type of IBS used in Malaysia. Outcome from the literature review has identified the six categories of IBS adopted by Malaysian construction industry. However, there is still lack of information on evaluating and rank a range of six IBS types frequently used in Malaysia. Therefore this study is important to identify the most regularly implemented IBS type hence focus on its value to be promoted to local construction industry player.
  • 24. 2.8.2 Findings in relation to the second objective The second objective is to identify the factors affecting the cost of IBS construction method in Malaysia. A clearer understanding of the cost determinants is vital to achieve the desired level of accuracy of anticipated labour costs, material costs, investment cost, general expenses, transportation cost and overhead cost in total cost estimation, hence add value to Malaysian construction industry while deciding whether to adopt IBS in their respective projects. 2.8.3 Findings in relation to the third objective The third objective is to compare the cost differences between IBS and conventional construction method in residential building. In order to carry out meaningful comparison, various considerations must take into account, which include time-dependent and quantity- dependent cost components. There are three types of comparison as suggested in the literature review, which are comparison of standardized identical buildings, comparison of standard buildings with local modifications and comparison of functional similar building. In this research, the first and third approaches are adopted simultaneously.
  • 25. REFERENCES A.R.Z. Abidin (2007). Simulation of IBS Formation for Housing Construction. Retrieved on 28th Nov 2017, from http://eprints.utm.my/11242/1/AhmadRazinZainalMFKA2007.pdf CIDB (2017). Labour Wage Rate. Retrieved on 28th Nov2017, from http://myn3c.cidb.gov.my/cidb_n3c/output/a_web_lwr_details.php?4# D. Natasha, M.N.A.Azman, Khuan, W.B., N.F. Habidin and A.R. Ayub (2016). Issues of Payment Procurement Process for IBS Project. Retrieved on 28th Nov 2017, from https://www.researchgate.net/publication/303681753_ISSUES_OF_PAYMENT_PR OCUREMENT_PROCESS_FOR_INDUSTRIALISED_BUILDING_SYSTEM_IBS_ PROJECT K.A.M. Kamar , Z.A. Hamid, M.N.A. Azman , M.S.S. Ahamad (2011). Industrialized Building System (IBS): Revisiting Issues of Definition and Classification. Retrieved on 28th Nov 2017, from http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.301.2957&rep=rep1&type= pdf M. A. Khalfan and Tayyab Maqsood. (2014). Current State of Off-Site Manufacturing in Australian and Chinese Residential Construction. Retrieved on 28th Nov 2017, from https://www.hindawi.com/journals/jcen/2014/164863/
  • 26. MIDFR (2014). Construction IBS: Practical Solution to Rising Costs. Retrieved on 28th Nov 2017, from http://www.midf.com.my/images/Downloads/Research/EqStrategy/SpecialReports/Co nstruction-IBS_MIDF_140214.pdf M.N.A. Azman, M.S.S. Ahamad, T.A.Majid, and M.H. Hanafi(2010). Status of Industrialized Building System Manufacturing Plant in Malaysia. Retrieved on 28th Nov 2017, from https://www.academia.edu/6389771/Status_of_Industrialized_Building_System_Man ufacturing_Plant_in_Malaysia M.N.A. Azman, M.S.S. Ahamad, T.A. Majid and M.H. Hanafi(2013). Permanent and Mobile Industrialised Building System Manufacturing Plant Based on Malaysian Case Study. Retrieved on 28th Nov 2017, from https://www.academia.edu/21345738/Permanent_and_Mobile_Industrialised_Buildin g_System_Manufacturing_Plant_Based_on_Malaysian_Case_Study M.R. A. Kadir, Lee,W.P.,M.S. Jaafar,S.M. Sapuan and A.A.A. Ali (2006). Construction Performance Comparison between Conventional and Industrialized Building System in Malaysia. Retrieved on 28th Nov 2017, from http://leewp33.tripod.com/sitebuildercontent/sitebuilderfiles/structuralsurvey2006.pdf M.Qays,K.N.Mustapha,Al-Mattarneh and N.S. Mohamed (2010). The Constraints of Industrialized Building System from Stakeholders’ Point of View. Retrieved on 28th Nov 2017, from https://www.researchgate.net/publication/303330111_The_Constraints_of_Industriali zed_Building_System_from_Stakeholders%27_Point_of_View M.Z. Ramli, M.H. Hanipah, M.H. Zawawi,M.Z.Z. Abidin, NurAtiqah Zainal, N.S.A. Halim (2016).
  • 27. Cost comparison on industrialized building system (IBS) and conventional method for school construction project. Retrieved on 28th Nov 2017, from http://jsrad.org/wp- content/2016/Issue%204,%202016/16jj.pdf N.A.A. Bari,R.Y.N. Ismail, A. Jaapar and R. Ahmad (2011). Factors Influencing the Construction Cost of Industrialised Building System (IBS) Projects. Retrieved on 28th Nov 2017, from https://ac.els-cdn.com/S1877042812004508/1-s2.0-S1877042812004508- main.pdf?_tid=b0075874-d279-11e7-a471- 00000aab0f6b&acdnat=1511680754_7c70445cf8d146069e7145fff0e8e9a9 N.A. Haron, Ir. S.H. Mohd. R.A. Kadir and M.S. Jaafar (2005). Building Cost Comparison Between Conventional and Formwork System: A Case Study of Four-storey School Buildings in Malaysia. Retrieved on 28th Nov 2017, from http://thescipub.com/PDF/ajassp.2005.819.823.pdf RISM (2015). Translating Innovative Construction Method into Cost Saving. Retrieved on 28th Nov 2017, from http://www.rism.org.my/wp-content/uploads/2015/11/03-3-Translating- Innovative-Construction-Method-Into-Cost-Saving-Ar-Haji-Abdul-HalimSuhor.pdf Wong, S.S., Lau, L.K. (2015). Advantages and Setbacks of IBS Implementation: A Case Study in Sarawak. Retrieved on 28th Nov 2017, from https://www.researchgate.net/publication/281071898_Advantages_and_Setbacks_of_I ndustrialized_Building_System_IBS_Implementation_A_Case_Study_in_Sarawak