Time Study and Method Study Application in Machining Plant for
Improvement in Production
Manish Chandrakant Pawar
Mechanical Engineering Department, Jawaharlal Nehru Engineering College (JNEC), Aurangabad, Maharashtra,
India
------------------------------------------------------------------------***-------------------------------------------------------------------------
Abstract- Improvement in production is the main aim of any organization with less employee’s effort, with justified quality
and wanted quantity to be produced. To increase the quality of product ‘Productivity’ is the main tool. For continuous
improvement in Machining industry, Productivity improvement is the very important factor to survive and for achieving the
Breakthroughs in the work carried out. Taking look at the production department which include assembly line, machining
shop, material handling, quality department there is some unwanted work process is done which is taking more effort, more
time as well as increasing the product expense and worker experience some unwanted fatigue, so the production cycle time
increases as well as productivity of the industry decreases. Quality control, Quality assurance, statistical quality control, Total
quality management, etc are the Tools and Techniques which are most favourable factor for improving the quality of a
product and also improvement of the productivity as well overall efficiency of the product. In the following paper introduction
of quality checking technique like Autocollimator, Digital measuring instruments like Vernier, micrometre, digital roughness
tester etc has been used. Compared results of process carried out before and after application of method and time study has
been illustrated.
Key words- firm, breakthrough, fatigue, Productivity, method study.
1. INTRODUCTION
1.1 Time study
It is a work measurement technique for recording the times and rates of working for the elements of a job carried out with
some specific conditions and analysing the data so as to obtain the time necessary for carrying out the specified job at a
level which is defined for performance.
Time study procedure-
Select- selection of the job to be timed
Define- The element, Break the job into elements convenient for timing
Obtain and Record - Details regarding operator, job, method and working conditions
Extend- Observed time into normal time (basic time)
Measure- assess the rating and time duration for each element
Compute- defined job with standard time for the operation
Determine- relaxation and personal allowances
There are unnecessary processes which are conducted often the same work can be done using some simple and less
complicated tools in a production department of an industry
1.2 Method study
It is the systematic recording and critical examination of existing and proposed ways of doing work, as a means of
developing and applying easier and more effective methods and reducing costs[1]
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 02 | Feb 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 208
Method study involves following sequence of steps-
Select (the work to be studied)
Record (all relevant information about that work)
Examine (the recorded information)
Develop (an improved way of doing things)
Install (the new method as standard practice)
Maintain (the new standard proactive)
The work and processes studied and carried out here is done in Machining industry which is manufacturing component
like frame of compound DC motor, helical shafts, hollow shafts. In order to implement method study and time study
techniques are performed to increase the Productivity and meet the customer demand.
To improve Productivity in small scale industry by using work study and method study. motive behind following research
behind is to improve production capabilities for small scale industries. Work study technique is used to improve work
process in company, objectives of the research also identify problems in production work process and improve work
process terms of the production cycle time, efficient work process to company by carrying out number of process and
production rate. This study uses systematic observation, stopwatch time study and flow process methodology. Conclusion
focused on improvement of work process by eliminating and combining of work process point by using multiple
applications to decrease the inspection time as possible.
1.3 Wire cut EDM (electric discharge machining) – wire electrical discharge machining is a process of metal
machining in which a tool discharges thousands of sparks to a metal workpiece. Wire cut EDM equipment is run by
computer numerically controlled (CNC) instruments, which can control the wire on three- dimensional axis to provide
greater flexibility. Simple cuts can be achieved by varying the x-y coordinates of the cutter and going for more complex
cuts, adding axes of motion to the wire guides will give result
2. LITERATURE REVIEW
F. W. Taylor was the founder of Modern method and Time study. Taylor began his Time Study work in 1881. He
established that each job should follow standard time, determined by time studies. In the timing process Taylor divided
the work into small divisions of effort known as Elements. Time was obtained for these elements individually and their
collective values were used to determine the allowed time for the task.[2]
Similarly, individuals such as Gilbreth (1909), Marshall and Cadbury heavily criticized Taylor and pervaded his work with
subjectivity. ‘Modern Motion Study Technique’ is founded by Gilbreth. Which defined that the study of body motions used
in performing an operation for the purpose of improving the operation by eliminating unnecessary motions, simplifying
necessary motions and then establishing the most favourable motion sequence for maximum efficiency [2]
Allowing for the analysis of the labour process in a scientific context, Gilbreth proposed a technical language. In contrast
to, and motivated by, Taylor's time study methods. Based upon the analysis of ‘work motions’ Gilbreths made the use of
scientific insights to develop a study method. Consisting in part of filming the details of a body posture and worker's
activities while recording the time. Emphasizing areas for improvement and how work had been done with visual record.
Secondly, the films also helped training workers to give their best performance in working hours, these were two films
served. This method allowed the Gilbreths to build on the best elements of these workflows and was able to create a
standardized best practice.[2]
3. WORK OBSERVATION AND MODIFICATION
Machining process from converting raw material to well finished hollow shaft of 600mm in length, with ID QA (internal
diameter QA)
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 02 | Feb 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 209
Fig-1: wire cut EDM for ID QA in Hollow shaft.
3.1 Method study and time study observation -
Table-1: Standard time required for machining
Processes involved Timing calculated in ‘Min’
Loading the workpiece in cutter machine by human efforts 20
Dimension and material checking 25
Outer Rough turning with conventional lathe machine 90
Inner turning with conventional lathe machine 120
Lathe finish/smooth turning 30
Removing of 0.2 or 0.3 mm of excess material (internal and external)
with cylindrical grinding machine
120
Inspection with dial gauge 35
Giving ID QA with wire cutting machine 120
Drilling specified holes in job 90
Overall inspection by quality head 100
Job removal 25
Packaging of job (manually) 30
Cleaning the machines and Scrap disposal 60
Total 865
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 02 | Feb 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 210
Fig-2 Ready hollow shaft
Table-2: Modified timing in Machining after implementation of Method and Time study
Processes involved Timing calculated in ‘Min’
Loading the workpiece in cutter machine by portable Gantry 10
Dimension and material checking 25
Outer Rough turning with CNC lathe 30
Inner turning with CNC lathe 50
Lathe finish/smooth turning 30
Removing of 0.2 or 0.3 mm of excess material (internal and external)
with cylindrical grinding machine
120
Inspection with sine bar (flatness) 20
Giving ID QA with wire cutting machine 120
CNC Drilling specified holes in job 35
Overall inspection by the quality head with the help of modern
measuring instruments (digital roughness tester, digital vernier
calliper and digital vernier height gauge)
50
Job removal 25
Packaging of the job with automatic packaging machine 15
Cleaning the machines and Scrap disposal 60
Total 590
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 02 | Feb 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 211
4. RESULT
Productivity: Productivity is the efficiency of production of any type of goods or services expressed by some measure.
It is the ratio of input parameter to the output parameter Reduction in production cycle time [3]
= Overall time before Modification - Overall time after modification
= 865min -590min
=275 min
Increase in productivity= 275/865 = 0.31791 %
% Increase in productivity = 31.79 %
4.1 Suggestions to be noted
 5s techniques must be maintained during the inspection period.
 Use of digital measuring instrument.
 Conventional machining instead of non-conventional machining.
5. CONCLUSION
The above result concludes that proper use of method study and time study can increase the rate of productivity and
desired production can be achieved by proper utilization of machines and material according to the required job. Worker’s
fatigue can be minimized by applying the following techniques in particular industry. As time is saved, a different task can
be assigned according to the potential of the individual resulting in productivity. Also, time consumed in unwanted
operations can be saved.
The above method helped in increasing productivity up to 31.79% and the reduction in time is 275 minutes.
6. REFERENCES
[1] International Labour Office., Introduction to work study. International Labour Office, 1979.
[2] “No Title.” https://en.wikipedia.org/wiki/Time_and_motion_study.
[3] P. Takmoge et al., “Paper on Time and Method Study Productivity Improvement in Machining Industry by using
Time Study and Method Study Techniques Modification of Single Ball Transmission Drive View project
Modification of Single Ball Transmission Drive View project Paper on,” Int. Res. J. Eng. Technol., vol. 9001, no. 07, pp.
4763–4766, 2008, [Online]. Available: www.irjet.net.

More Related Content

Similar to Time Study and Method Study Application in Machining Plant for Improvement in Production

IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVANIMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVANIRJET Journal
 
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...IRJET Journal
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET Journal
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET Journal
 
Improvement of supply chain process using Maynard Operation Sequence Techniqu...
Improvement of supply chain process using Maynard Operation Sequence Techniqu...Improvement of supply chain process using Maynard Operation Sequence Techniqu...
Improvement of supply chain process using Maynard Operation Sequence Techniqu...IRJET Journal
 
Manufacturing of Toggle Jack
Manufacturing of Toggle JackManufacturing of Toggle Jack
Manufacturing of Toggle JackIRJET Journal
 
IRJET- Improving Quality and Productivity in Switchgear Tank Welding through ...
IRJET- Improving Quality and Productivity in Switchgear Tank Welding through ...IRJET- Improving Quality and Productivity in Switchgear Tank Welding through ...
IRJET- Improving Quality and Productivity in Switchgear Tank Welding through ...IRJET Journal
 
IRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 HousingIRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 HousingIRJET Journal
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingeSAT Publishing House
 
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET Journal
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET Journal
 
IRJET- Development of Ejection System to Improve Productivity
IRJET-  	  Development of Ejection System to Improve ProductivityIRJET-  	  Development of Ejection System to Improve Productivity
IRJET- Development of Ejection System to Improve ProductivityIRJET Journal
 
IRJET- Development of Ejection System to Improve Productivity
IRJET- Development of Ejection System to Improve ProductivityIRJET- Development of Ejection System to Improve Productivity
IRJET- Development of Ejection System to Improve ProductivityIRJET Journal
 
Impact of Mechanical System in Machining Of AISI 1018 Using Taguchi Design o...
Impact of Mechanical System in Machining Of AISI 1018 Using  Taguchi Design o...Impact of Mechanical System in Machining Of AISI 1018 Using  Taguchi Design o...
Impact of Mechanical System in Machining Of AISI 1018 Using Taguchi Design o...IJMER
 
Productivity Enhancement Using Method Study
Productivity Enhancement Using Method StudyProductivity Enhancement Using Method Study
Productivity Enhancement Using Method StudyIRJET Journal
 
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case StudyValue Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case StudyIRJET Journal
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudybejayrocks
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining TimeIRJET Journal
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET Journal
 

Similar to Time Study and Method Study Application in Machining Plant for Improvement in Production (20)

IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVANIMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
 
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
 
Improvement of supply chain process using Maynard Operation Sequence Techniqu...
Improvement of supply chain process using Maynard Operation Sequence Techniqu...Improvement of supply chain process using Maynard Operation Sequence Techniqu...
Improvement of supply chain process using Maynard Operation Sequence Techniqu...
 
Manufacturing of Toggle Jack
Manufacturing of Toggle JackManufacturing of Toggle Jack
Manufacturing of Toggle Jack
 
IRJET- Improving Quality and Productivity in Switchgear Tank Welding through ...
IRJET- Improving Quality and Productivity in Switchgear Tank Welding through ...IRJET- Improving Quality and Productivity in Switchgear Tank Welding through ...
IRJET- Improving Quality and Productivity in Switchgear Tank Welding through ...
 
IRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 HousingIRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 Housing
 
Work Study Part- I
Work Study Part- IWork Study Part- I
Work Study Part- I
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casing
 
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
 
IRJET- Development of Ejection System to Improve Productivity
IRJET-  	  Development of Ejection System to Improve ProductivityIRJET-  	  Development of Ejection System to Improve Productivity
IRJET- Development of Ejection System to Improve Productivity
 
IRJET- Development of Ejection System to Improve Productivity
IRJET- Development of Ejection System to Improve ProductivityIRJET- Development of Ejection System to Improve Productivity
IRJET- Development of Ejection System to Improve Productivity
 
Impact of Mechanical System in Machining Of AISI 1018 Using Taguchi Design o...
Impact of Mechanical System in Machining Of AISI 1018 Using  Taguchi Design o...Impact of Mechanical System in Machining Of AISI 1018 Using  Taguchi Design o...
Impact of Mechanical System in Machining Of AISI 1018 Using Taguchi Design o...
 
Productivity Enhancement Using Method Study
Productivity Enhancement Using Method StudyProductivity Enhancement Using Method Study
Productivity Enhancement Using Method Study
 
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case StudyValue Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudy
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall Productivity
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

Time Study and Method Study Application in Machining Plant for Improvement in Production

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 02 | Feb 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 207 Time Study and Method Study Application in Machining Plant for Improvement in Production Manish Chandrakant Pawar Mechanical Engineering Department, Jawaharlal Nehru Engineering College (JNEC), Aurangabad, Maharashtra, India ------------------------------------------------------------------------***------------------------------------------------------------------------- Abstract- Improvement in production is the main aim of any organization with less employee’s effort, with justified quality and wanted quantity to be produced. To increase the quality of product ‘Productivity’ is the main tool. For continuous improvement in Machining industry, Productivity improvement is the very important factor to survive and for achieving the Breakthroughs in the work carried out. Taking look at the production department which include assembly line, machining shop, material handling, quality department there is some unwanted work process is done which is taking more effort, more time as well as increasing the product expense and worker experience some unwanted fatigue, so the production cycle time increases as well as productivity of the industry decreases. Quality control, Quality assurance, statistical quality control, Total quality management, etc are the Tools and Techniques which are most favourable factor for improving the quality of a product and also improvement of the productivity as well overall efficiency of the product. In the following paper introduction of quality checking technique like Autocollimator, Digital measuring instruments like Vernier, micrometre, digital roughness tester etc has been used. Compared results of process carried out before and after application of method and time study has been illustrated. Key words- firm, breakthrough, fatigue, Productivity, method study. 1. INTRODUCTION 1.1 Time study It is a work measurement technique for recording the times and rates of working for the elements of a job carried out with some specific conditions and analysing the data so as to obtain the time necessary for carrying out the specified job at a level which is defined for performance. Time study procedure- Select- selection of the job to be timed Define- The element, Break the job into elements convenient for timing Obtain and Record - Details regarding operator, job, method and working conditions Extend- Observed time into normal time (basic time) Measure- assess the rating and time duration for each element Compute- defined job with standard time for the operation Determine- relaxation and personal allowances There are unnecessary processes which are conducted often the same work can be done using some simple and less complicated tools in a production department of an industry 1.2 Method study It is the systematic recording and critical examination of existing and proposed ways of doing work, as a means of developing and applying easier and more effective methods and reducing costs[1]
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 02 | Feb 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 208 Method study involves following sequence of steps- Select (the work to be studied) Record (all relevant information about that work) Examine (the recorded information) Develop (an improved way of doing things) Install (the new method as standard practice) Maintain (the new standard proactive) The work and processes studied and carried out here is done in Machining industry which is manufacturing component like frame of compound DC motor, helical shafts, hollow shafts. In order to implement method study and time study techniques are performed to increase the Productivity and meet the customer demand. To improve Productivity in small scale industry by using work study and method study. motive behind following research behind is to improve production capabilities for small scale industries. Work study technique is used to improve work process in company, objectives of the research also identify problems in production work process and improve work process terms of the production cycle time, efficient work process to company by carrying out number of process and production rate. This study uses systematic observation, stopwatch time study and flow process methodology. Conclusion focused on improvement of work process by eliminating and combining of work process point by using multiple applications to decrease the inspection time as possible. 1.3 Wire cut EDM (electric discharge machining) – wire electrical discharge machining is a process of metal machining in which a tool discharges thousands of sparks to a metal workpiece. Wire cut EDM equipment is run by computer numerically controlled (CNC) instruments, which can control the wire on three- dimensional axis to provide greater flexibility. Simple cuts can be achieved by varying the x-y coordinates of the cutter and going for more complex cuts, adding axes of motion to the wire guides will give result 2. LITERATURE REVIEW F. W. Taylor was the founder of Modern method and Time study. Taylor began his Time Study work in 1881. He established that each job should follow standard time, determined by time studies. In the timing process Taylor divided the work into small divisions of effort known as Elements. Time was obtained for these elements individually and their collective values were used to determine the allowed time for the task.[2] Similarly, individuals such as Gilbreth (1909), Marshall and Cadbury heavily criticized Taylor and pervaded his work with subjectivity. ‘Modern Motion Study Technique’ is founded by Gilbreth. Which defined that the study of body motions used in performing an operation for the purpose of improving the operation by eliminating unnecessary motions, simplifying necessary motions and then establishing the most favourable motion sequence for maximum efficiency [2] Allowing for the analysis of the labour process in a scientific context, Gilbreth proposed a technical language. In contrast to, and motivated by, Taylor's time study methods. Based upon the analysis of ‘work motions’ Gilbreths made the use of scientific insights to develop a study method. Consisting in part of filming the details of a body posture and worker's activities while recording the time. Emphasizing areas for improvement and how work had been done with visual record. Secondly, the films also helped training workers to give their best performance in working hours, these were two films served. This method allowed the Gilbreths to build on the best elements of these workflows and was able to create a standardized best practice.[2] 3. WORK OBSERVATION AND MODIFICATION Machining process from converting raw material to well finished hollow shaft of 600mm in length, with ID QA (internal diameter QA)
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 02 | Feb 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 209 Fig-1: wire cut EDM for ID QA in Hollow shaft. 3.1 Method study and time study observation - Table-1: Standard time required for machining Processes involved Timing calculated in ‘Min’ Loading the workpiece in cutter machine by human efforts 20 Dimension and material checking 25 Outer Rough turning with conventional lathe machine 90 Inner turning with conventional lathe machine 120 Lathe finish/smooth turning 30 Removing of 0.2 or 0.3 mm of excess material (internal and external) with cylindrical grinding machine 120 Inspection with dial gauge 35 Giving ID QA with wire cutting machine 120 Drilling specified holes in job 90 Overall inspection by quality head 100 Job removal 25 Packaging of job (manually) 30 Cleaning the machines and Scrap disposal 60 Total 865
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 02 | Feb 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 210 Fig-2 Ready hollow shaft Table-2: Modified timing in Machining after implementation of Method and Time study Processes involved Timing calculated in ‘Min’ Loading the workpiece in cutter machine by portable Gantry 10 Dimension and material checking 25 Outer Rough turning with CNC lathe 30 Inner turning with CNC lathe 50 Lathe finish/smooth turning 30 Removing of 0.2 or 0.3 mm of excess material (internal and external) with cylindrical grinding machine 120 Inspection with sine bar (flatness) 20 Giving ID QA with wire cutting machine 120 CNC Drilling specified holes in job 35 Overall inspection by the quality head with the help of modern measuring instruments (digital roughness tester, digital vernier calliper and digital vernier height gauge) 50 Job removal 25 Packaging of the job with automatic packaging machine 15 Cleaning the machines and Scrap disposal 60 Total 590
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 02 | Feb 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 211 4. RESULT Productivity: Productivity is the efficiency of production of any type of goods or services expressed by some measure. It is the ratio of input parameter to the output parameter Reduction in production cycle time [3] = Overall time before Modification - Overall time after modification = 865min -590min =275 min Increase in productivity= 275/865 = 0.31791 % % Increase in productivity = 31.79 % 4.1 Suggestions to be noted  5s techniques must be maintained during the inspection period.  Use of digital measuring instrument.  Conventional machining instead of non-conventional machining. 5. CONCLUSION The above result concludes that proper use of method study and time study can increase the rate of productivity and desired production can be achieved by proper utilization of machines and material according to the required job. Worker’s fatigue can be minimized by applying the following techniques in particular industry. As time is saved, a different task can be assigned according to the potential of the individual resulting in productivity. Also, time consumed in unwanted operations can be saved. The above method helped in increasing productivity up to 31.79% and the reduction in time is 275 minutes. 6. REFERENCES [1] International Labour Office., Introduction to work study. International Labour Office, 1979. [2] “No Title.” https://en.wikipedia.org/wiki/Time_and_motion_study. [3] P. Takmoge et al., “Paper on Time and Method Study Productivity Improvement in Machining Industry by using Time Study and Method Study Techniques Modification of Single Ball Transmission Drive View project Modification of Single Ball Transmission Drive View project Paper on,” Int. Res. J. Eng. Technol., vol. 9001, no. 07, pp. 4763–4766, 2008, [Online]. Available: www.irjet.net.