Submit Search
Upload
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
•
0 likes
•
47 views
IRJET Journal
Follow
https://www.irjet.net/archives/V5/i3/IRJET-V5I355.pdf
Read less
Read more
Engineering
Report
Share
Report
Share
1 of 4
Download now
Download to read offline
Recommended
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
ijmech
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
IRJET Journal
Improvement of Productivity Using Value Stream Mapping
Improvement of Productivity Using Value Stream Mapping
ijsrd.com
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET Journal
Iss 9
Iss 9
ijmvsc
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET Journal
synopsis
synopsis
Kesavan Vjs
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
IRJET Journal
Recommended
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
ijmech
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
IRJET Journal
Improvement of Productivity Using Value Stream Mapping
Improvement of Productivity Using Value Stream Mapping
ijsrd.com
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET Journal
Iss 9
Iss 9
ijmvsc
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET Journal
synopsis
synopsis
Kesavan Vjs
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
IRJET Journal
A Broad Study on Lead Time Reduction using Value Stream Mapping Techniques in...
A Broad Study on Lead Time Reduction using Value Stream Mapping Techniques in...
IRJET Journal
A Case Study on Productivity Improvement of Assembly line using VSM Methodology
A Case Study on Productivity Improvement of Assembly line using VSM Methodology
Government engineering College- Banswara,Rajasthan
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
Journal For Research
A Case Study on Reducing in Lead Time by Using Value Stream Mapping
A Case Study on Reducing in Lead Time by Using Value Stream Mapping
Government engineering College- Banswara,Rajasthan
Solving Multi-level, Multi-product and Multi-period Lot Sizing and Scheduling...
Solving Multi-level, Multi-product and Multi-period Lot Sizing and Scheduling...
Editor IJCATR
Ch5 process analysis
Ch5 process analysis
videoaakash15
An Introduction to Operations Management
An Introduction to Operations Management
Christian Reinboth
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET Journal
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET Journal
Simulative study of cause-effect interdependencies in tool logistics
Simulative study of cause-effect interdependencies in tool logistics
IDES Editor
Ppc 2 m and 16m
Ppc 2 m and 16m
Javith Saleem
Operation management problems
Operation management problems
venkataramanan Thiru
The Performance Analysis of a Fettling Shop Using Simulation
The Performance Analysis of a Fettling Shop Using Simulation
IOSR Journals
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET Journal
Process Analysis
Process Analysis
Joshua Miranda
Value stream mapping
Value stream mapping
IAEME Publication
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET Journal
Line Balancing In Garments Industry
Line Balancing In Garments Industry
Md. Mazadul Hasan Shishir
Lean assisment, LEAN OPERATIONS
Lean assisment, LEAN OPERATIONS
shujathshu
H0432045055
H0432045055
theijes
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
PERUMALSAMY M
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
IRJET Journal
More Related Content
What's hot
A Broad Study on Lead Time Reduction using Value Stream Mapping Techniques in...
A Broad Study on Lead Time Reduction using Value Stream Mapping Techniques in...
IRJET Journal
A Case Study on Productivity Improvement of Assembly line using VSM Methodology
A Case Study on Productivity Improvement of Assembly line using VSM Methodology
Government engineering College- Banswara,Rajasthan
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
Journal For Research
A Case Study on Reducing in Lead Time by Using Value Stream Mapping
A Case Study on Reducing in Lead Time by Using Value Stream Mapping
Government engineering College- Banswara,Rajasthan
Solving Multi-level, Multi-product and Multi-period Lot Sizing and Scheduling...
Solving Multi-level, Multi-product and Multi-period Lot Sizing and Scheduling...
Editor IJCATR
Ch5 process analysis
Ch5 process analysis
videoaakash15
An Introduction to Operations Management
An Introduction to Operations Management
Christian Reinboth
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET Journal
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET Journal
Simulative study of cause-effect interdependencies in tool logistics
Simulative study of cause-effect interdependencies in tool logistics
IDES Editor
Ppc 2 m and 16m
Ppc 2 m and 16m
Javith Saleem
Operation management problems
Operation management problems
venkataramanan Thiru
The Performance Analysis of a Fettling Shop Using Simulation
The Performance Analysis of a Fettling Shop Using Simulation
IOSR Journals
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET Journal
Process Analysis
Process Analysis
Joshua Miranda
Value stream mapping
Value stream mapping
IAEME Publication
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET Journal
Line Balancing In Garments Industry
Line Balancing In Garments Industry
Md. Mazadul Hasan Shishir
Lean assisment, LEAN OPERATIONS
Lean assisment, LEAN OPERATIONS
shujathshu
H0432045055
H0432045055
theijes
What's hot
(20)
A Broad Study on Lead Time Reduction using Value Stream Mapping Techniques in...
A Broad Study on Lead Time Reduction using Value Stream Mapping Techniques in...
A Case Study on Productivity Improvement of Assembly line using VSM Methodology
A Case Study on Productivity Improvement of Assembly line using VSM Methodology
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
A Case Study on Reducing in Lead Time by Using Value Stream Mapping
A Case Study on Reducing in Lead Time by Using Value Stream Mapping
Solving Multi-level, Multi-product and Multi-period Lot Sizing and Scheduling...
Solving Multi-level, Multi-product and Multi-period Lot Sizing and Scheduling...
Ch5 process analysis
Ch5 process analysis
An Introduction to Operations Management
An Introduction to Operations Management
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
Simulative study of cause-effect interdependencies in tool logistics
Simulative study of cause-effect interdependencies in tool logistics
Ppc 2 m and 16m
Ppc 2 m and 16m
Operation management problems
Operation management problems
The Performance Analysis of a Fettling Shop Using Simulation
The Performance Analysis of a Fettling Shop Using Simulation
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
Process Analysis
Process Analysis
Value stream mapping
Value stream mapping
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
Line Balancing In Garments Industry
Line Balancing In Garments Industry
Lean assisment, LEAN OPERATIONS
Lean assisment, LEAN OPERATIONS
H0432045055
H0432045055
Similar to IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
PERUMALSAMY M
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
IRJET Journal
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...
IRJET Journal
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
Karina Islam
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET Journal
Overview on Kanban Methodology and its Implementation
Overview on Kanban Methodology and its Implementation
Laukik Raut
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET Journal
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET Journal
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET Journal
O0123190100
O0123190100
IOSR Journals
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPING
FuratAj
IRJET- Production Plan and Control
IRJET- Production Plan and Control
IRJET Journal
IRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites Progress
IRJET Journal
“Development of automatic feeder system in cellular manufacturing to improve ...
“Development of automatic feeder system in cellular manufacturing to improve ...
IRJET Journal
applicationof vsm
applicationof vsm
Aro Ephrem
IRJET- Improving Quality and Productivity in Switchgear Tank Welding through ...
IRJET- Improving Quality and Productivity in Switchgear Tank Welding through ...
IRJET Journal
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
IRJET Journal
MFG 240 - Manufacturing DesignFinal ProjectScope of Project.docx
MFG 240 - Manufacturing DesignFinal ProjectScope of Project.docx
ARIV4
Process Design and Development of Engine Block
Process Design and Development of Engine Block
paperpublications3
IRJET- Single Minute Exchange of Dies (SMED) Concept
IRJET- Single Minute Exchange of Dies (SMED) Concept
IRJET Journal
Similar to IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
(20)
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
Overview on Kanban Methodology and its Implementation
Overview on Kanban Methodology and its Implementation
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
O0123190100
O0123190100
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPING
IRJET- Production Plan and Control
IRJET- Production Plan and Control
IRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites Progress
“Development of automatic feeder system in cellular manufacturing to improve ...
“Development of automatic feeder system in cellular manufacturing to improve ...
applicationof vsm
applicationof vsm
IRJET- Improving Quality and Productivity in Switchgear Tank Welding through ...
IRJET- Improving Quality and Productivity in Switchgear Tank Welding through ...
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
MFG 240 - Manufacturing DesignFinal ProjectScope of Project.docx
MFG 240 - Manufacturing DesignFinal ProjectScope of Project.docx
Process Design and Development of Engine Block
Process Design and Development of Engine Block
IRJET- Single Minute Exchange of Dies (SMED) Concept
IRJET- Single Minute Exchange of Dies (SMED) Concept
More from IRJET Journal
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
React based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
More from IRJET Journal
(20)
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
React based fullstack edtech web application
React based fullstack edtech web application
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Recently uploaded
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
SIVASHANKAR N
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
upamatechverse
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
wendy cai
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
João Esperancinha
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
upamatechverse
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
ranjana rawat
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Suman Mia
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
M Maged Hegazy, LLM, MBA, CCP, P3O
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
ranjana rawat
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
Tsuyoshi Horigome
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
soniya singh
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
NikhilNagaraju
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur High Profile
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
9953056974 Low Rate Call Girls In Saket, Delhi NCR
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur High Profile
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
srsj9000
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
null - The Open Security Community
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
Asutosh Ranjan
Recently uploaded
(20)
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
1.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 243 PRODUCTIVITY IMPROVEMENT IN A PRESSURE VESSEL USING LEAN PRINCIPLES G.Aravinddinesh 1a, Mr. A Prabukarthi 1b, M.Perumalsamy 2. 1a PG Scholar, Department of Mechanical Engineering, PSG College of Technology, Tamilnadu, India 1bAssistant Professor, Department of Mechanical Engineering, PSG College of Technology, Tamilnadu, India 2 PG Scholar, Department of Mechanical Engineering, PSG College of Technology, Tamilnadu, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - This paper deals with implementation of lean manufacturing concepts in the industry in order to improve the productivity of pressure vessel manufacturing in a small- scale industry that manufactures chemical separators pressure vessel for water treatment plants. The challengeface by the industry is not able to meet the customer demand due to production line stoppages and longer lead time of the product. The facility experiences production line stoppages due to non-availability of subcomponent. The major issuesare due to unstructured way of the inventory management, the time between the placing the order and receiving the finished product from the company is 6.5 days, which is a longer lead time significantly influence the stoppage in production. The supply chain activities were analysed with the help of the current state and future state value stream mapswiththehelp of commercial software. Kanban system is implemented in industry as cards and placed. After implementing the Kanban system, the line stoppages were eliminated and improved to 68% and lead time is reduced from 6.5 days to 4.3 days. Key Words: productivity improvement, inventory, Kanban, value stream mapping 1.INTRODUCTION The pressure vessel manufacturing company manufactures pressure vessel for water and chemical separators.Theybuy the raw material as blank sheets and they cut them into separate pieces for dished and shells. The dishes from the Pressure Vessel Division (PVD) follow a outsourcing model for forming the blanks into dish ends. PVD receives cut and blanked sheets from its raw material supplier and stores them at PVD. The sheets to be rolled into shells and edge beveled before being sent to the outsourcer for rolling process. The blanks are then sent to the outsourcer for forming. The formed dishes are then withdrawn from them and stored in PVD for fabricating them into pressure vessels for water treatment plants. The outsourcing process for forming the dish ends is inevitable, asPVD does not havethe facility for forming the blanks into dish ends. This model where PVD receives raw material from its supplier, sends them after pre-processing (if any) to a outsourcer and receives them back after forming and uses them for fabrication is referred to as the outsourced model. The inventory process flow is depicted in a flow chart in theFig1 Fig -1: Inventory flow 2.LITERATURE REVIEW Preetinder Singh Gill, (2012) [1] reported that Value Stream Mapping (VSM) as a lean/quality management tool which assists in establishing the current state of a process while aiding to uncover opportunities for improvement vis-a-vis the seven sources of waste. This research paper involves a review of existing literature pertaining to application of the VSM tool in departments. The author presents the potential benefits emanating from application of VSM along with assessing its effectiveness in scenarios where it has been implemented already. Furthermore, challenges faced in implementation of the VSM tools are collated. Various solutions to addressthese challengeshave beenpresentedin the light of tribulations faced by today’s industry. Rahani AR et. al. (2012) [2]VSMis thestartingpointofthe lean manufacturing tools, it havingthe three stagesthere are current stage, future stage and implementation. Rahani AR says current state VSM is used to identify the problem and future stage VSM (Value Stream mapping) eliminate NVA (Non-Value Added activity) and NNVA for enhance the productivity then make the SOP in production line by reducing lead time and improving method study. This tool is reducing the bottleneck for making continuous flow.
2.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 244 Venkataraman et. al. (2014) [3] Lean manufacturing initiative is being followed by various organizations in the recent years which mainly focuses on improving the efficiency of operations by eliminating and reducing wastes hasdiscussed about the applicationof ValueStreamMapping for Reduction of Cycle Time in a Machining Process. Patange Vidyut Chandra, (2013) [4] describes the procedure to do work study including the method study and work measurement. It also gives the standards to follow during the operations in manufacturing industry. It helps to improve the quality. The effective use of time study and line balancing in industry is perfectly analysed by Johan Oscar Ong, in his paper he provided a case study of a doll manufacturer focusingonproductivityincreasethroughtime study, redesign of work arrangement and line balancing According to Meyers (2002) [6] Time study is the technique of establishing an allowed time standard to perform a given task, based upon measurement of work content of the prescribed method, with due allowance for fatigue and personal and unavoidable delays. ILO defines time study as a work measurement technique for recording the times and rates of working for the elements of specified job carried out under specified conditions, and for analyzing the data so as to obtain the time necessary for carrying out the job at a defined level of performance. time standards can be defined as “the time required to produce a product at a work station with the three conditions: (1) a qualified, well- trained operator, (2) working at a normalpace, and(3)doing a specific task.” Nakayama, (2002) [7] Stopwatch time study measures how long it takes an average worker to complete a task at a normal pace. A “normal" operator is defined as a qualified, thoroughly experienced operator who is working under conditions as they customarily prevail at the work station, at a pace that is neither fast nor slow, but representative of an average. The actual time taken by the above average operation must be increased, and the time taken by the below-average must be reduced to the value representative of normal performance. Performanceratingisatechniquefor equitably determining the timerequiredtoperformataskby the normal operator after the observed values of the operation understudy have been recorded Hence, when a work is measured with the stop watch device it is known as stop watch time study method. Kanawaty, (1992)[8] Workis a technique whichcontains the method study and time study which are used in examination of human working all its contexts and which leads systematically to the investigation of all the factors which effect the efficiency of situation being reviewed in order to seek improvements. In the book Introduction to Work study by International Labour office Kanban means sign board. A Kanban can be a variety of things, most commonly it is a card, but sometimes it is a cart, while other times it is just a marked space. In all cases, its purpose is to facilitate flow, bring about pull, and limit inventory. It is one of the key tools in the battle to reduce overproduction. Kanban provides two types of communication. In both cases, itgivesthesource,destination, part number, and quantity needed. Kanban provides two major services to the Lean facility [9]. • The Kanban serves as the communication system. • The Kanban is a continuous improvement tool. Traditionalmanufacturing strategyisdrivenby'Pushsystem' which is aimed to keep large inventory of product according to customer forecast. However, this has created big problem to people on floor in dealing with high of WIP inventories, unsynchronized production processes and producing unnecessary stock. Due to that, established company like Toyota Motor Corporation has moved to next level of manufacturing approach or strategy by adopting Kanban system [6]. The adoption of Kanban system has improved their efficiency and flexibility of manufacturing according to customer needs. Kanban systemis pull system approachthat givesauthorization to produce at requiredrateandatspecific time in order to replenish part that is already consumed by customer. The number of Kanban is calculated by [10] Demand*Lead Time (1+safety stock%) Number of Kanban = container quantity (2.1) 3.CURRENT STATE VALUE STREAM MAP OF THE SUPPLY CHAIN ACTIVITIES The current state map has been drawn for the outsourced dishes. Fig 2 shows the current state map for the dish ends. Fig -2: Current state value stream map for dish ends. The current state value stream map was drawn, and the inventory process ratio was determined as • VALUE RATIO= (VALUE ADDED TIME)/ (TOTAL LEAD TIME) • The current state map has been drawn for outsourcing dish ends. The value ratio is being 0.17% • The current state value stream mapping show that this is a pull type production system
3.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 245 • The VSM shows the material department receives necessary blank sheet with a lead time of dayfrom the raw material supplier • The sheets after passed the quality checksthey wait for 2 days in the storage area before processing • Thenit ispushed to the outsourcerfacilitywhereitis formed into dishes. The processing time varies in the capacities of the outsourcer facility. • As it is dumped at the outsourcers facility it takes utmost 10 days to withdraw the formed dishes. • as the withdrawal isin arbitrary batchesthe formed dishes wait at the outsourced facility before being bought into the pressure vessel division facility. • The received dishesare stored in the storage area after the quality tests. 3.1CURRENT STATEVALUESTREAMMAPANALYSIS The map reveals that the materials wait unnecessarily without being processed before and after outsourcing. One of the main reasons for unnecessary waiting is the materials department stocks inventory and pushes the inventory to the outsourcer and further down the line, instead of the inventory being pulled. This is one of the main reasons for the very low processratio or inventory turnover. Due to withdrawal in arbitrary batch quantities, the outsourcers need to be ready with the processed inventory, which leads to over processing, which is a waste. Hence introducing Kanban system can be implemented for improving the current state. 4.FUTURE STATE VALUE STREAM MAP OF THE SUPPLY CHAIN ACTIVITIES The future state map has been drawn for the outsource dishes. Fig -3: Future state value stream map for dish ends The future state value stream map has been drawn and the inventoryprocessratiois determined as.35%fordishes, whichis 68%increased turnover ratio for dishends.TheVSM is explained as follows. 1. As indicated in the VSM, Kanban system implementation leads to pull type production, where the inventory is pulled from the end. This eliminates over processing, unnecessary waiting, and increased inventory turnover ratio as evident from table 8.2. 2. Processing and handlingofinventoryhelpinkeeping a track of the inventory at the outsourcer's end which helps in the orderly movement of inventory. 3. The supermarket icon in the future state VSM indicatesthat onlyif the levelofparticular modelof dish falls below the certain limit, the inventory is replenished 4. Kanban boardsare need to be erected at the Kanban posts which helps in tracking of the inventory and also the implementation of pull production process 5.KANBAN IMPLEMENTATION shows the Kanban cards designed to track inventory. Three colors are used for this purpose. Green color card is stuck on the Kanban board permanently. Yellow and red cards are circulated between the outsourcer and PVD. These cards are hanged on the Kanban board with the help of a hook. Fig -4: Kanban cards of outsourcer inventory.
4.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 246 Fig -5: Kanban cards of outsourcer inventory. Fig -6: Kanban cards of outsourcer inventory. 6.RESULT AND CONCLUSION The major outcome of the paper is to improve the valueratio of the supply chain process of the outsourced inventory and also the reduction of the lead time in theoutsourcedproduct. Here the current state process has only process ratio of 0.17%which have been improvedto0.35%byimplementing the lean principle of Kanban in the supply chain process. This implementation of Kanban in the industry makes the production process to change from push system to pull system. This reduce the over production andlinestoppagein the system. Fig -7: Result summary REFERENCES [1] Preetinder Singh Gill (2012) "Application of Value Stream Mapping to Eliminate WasteinanEmergencyRoom", Global Journal of Medical Research, 12, (2012), 15 - 17. [2] Fawad A.Abdulmalek , Jayant Rajgopal, "Analyzing the Benefits of Lean manufacturing and Value Stream Mapping via Simulation: A Process Sector Case Study", Int. J. Production Economics, 107, (2007), 223- 236. [3] Rahani A R, Muhammad al-Ashraf,"ProductionFlow Analysis through Value Stream Mapping: A manufacturing process case study," International Symposium on Robotics and Intelligent Sensors 2012, pp. 1727-1734. [4] Venkataramanan K, VijayaRamnathB,MuthuKumar C, Elanchezhan C, "Application of Value Stream Mapping in the Reduction of Cycle Time in a Machining Process", 3rd International Conference on Materials Processing and Characterization, (2014), pp 1187-1196. [5] Patange Vidyut Chandra, "An Effort to Apply Work and Time Study in Manufacturing Unit to Enhancing the Productivity", International Journal of Innovative Research in Science, Engineering and Technology. (2013), Vol.2, Issue 8, pp 4050-4058. [6] Meyers, "Time Study Method Implementation in Manufacturing Industry", A B.E Report, Universiti Technikal Malaysia, Melaka, 2008, PP. 6. [7] Nakayama. S, "A study on setting standard time using work achievement quotient", International Journal of Production Research, Vol. 40, No. 15, PP 3945-53, 2002. [8] Kanawaty G, "Introduction to work study," International Labour Organisation. 1992, Geneva, ISBN 92-2-107108-1. [9] Wilson, L. "How to Implement LeanManufacturing". New York: McGraw-Hill Professional Publishing; 2009. [10] Ahmad Naufal, Ahmed Jaffar, Noriah Yosef, Nurul Hayati,2012, "Development of Kanban system at Local Manufacturing Company in Malaysia — Case Study, International Symposium on Robotics and Intelligent Sensors, vol 41, pp. 17211726.
Download now