International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2576
Implementation of 5’s to improve work ethic and overall performance
of the organization
Mrugendra Jagdale1, Shounak Lad2, Santosh Kamble3
1,2,3 Student, Department of Mechanical Engineering,
D.Y. Patil college of Engineering and technology, Kolhapur
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - 5s is a Japanese technique consisting of 5 words
starting with ‘S’, namely Seiri (sort), Seiton (systematic
arrangement), Seiso (shine), Seiketsu (standardize), Shitsuke
(sustain). This paper represents 5S implementation in a
company named Accura Tech located in Shiroli MIDC,
Kolhapur. 5S has direct impact on productivity as well as
quality. The need of 5S implementation was detected due to
improper utilization of space, wastage of time and presenceof
unwanted material at the workstation. The aim of
implementation of 5S was to minimize idle time, reduce effort,
increase safety to workers, and improve working conditions
and environment. All staff members took initiative; also
workers participated actively in the implementation process.
The successive implementation of 5S resulted into increase in
overall performance of the company and improved workethic
between the workers.
Key Words: 5S, Seri, Seiton, Seiso, Seiketsu, Shitsuke
1. INTRODUCTION
In today’sworld of increasing competition, it is importantto
seek better quality and productivityforsatisfyingcustomer’s
ever increasing demands. An organization needsto improve
continuously. Overall performance of organization depends
upon the workplace management. Providingproperfacilities
and working environment to the worker is importantforthe
same. 5S is an effective tool for increasing overall
performance of the organization.
Implementation of 5S ensuresproper utilizationofavailable
resources as well as modifies the system which is not fully
capable of fulfilling the required function. Small changes
make a big difference which is beneficial for the
organization. 5S not only helps to lift the standard of the
organization but also to improve the work ethic among the
workers.
1.1What is 5S?
5S is a tool used for arranging a workplace in effective
manner. 5S was introduced by Takashi Osada in early 1980s
in Japan. It is a set of 5 Japanese terms starting with S, Seiri
(sort), Seiton (systematic arrangement), Seiso (shine),
Seiketsu (standardize), Shitsuke (sustain). 5S leads to
elimination of waste, proper utilizationofplaceandprovides
clean and comfortable working conditions. It has impact on
overall performance of the organization.
1] Seiri
 Sorting the material into - need and want.
 Shifting unwanted materials to the red tag area.
 Disposing the waste and excess material by
reselling or trash.
2] Seiton
 “Place for everything and everything in its place” is
the mantra of the Seiton.
 “Go visual Go vertical”, principle is followed.
 Make proper place for each and everything needed
at workplace.
 Arrange things systematically and name them in
order to eliminate wastage of time in searching.
3] Seiso
 Keep the workplace as well as tools and equipment
clean.
 Maintain the cleanliness by following proper
schedule.
 Develop methods for proper disposal of waste.
4] Seiketsu
 Develop standard procedures for maintaining
improvements of first 3S.
 Assign responsibilities to everyone.
 Prepare checklists for various activities of 5S.
4] Shitsuke
 Carry out scheduled internal audits and surprise
audits.
 Install 5S slogans and posters.
 Give awards and recognition to the workers doing
well for maintaining 5S system.
2. LITERATURE REVIEW
Implementation of 5s is basically technique of improving
productivity as well as quality of the product in any
organisation. It totally dependsuponhowweareapplyingall
those concepts in our organisation.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2577
According to Sagar D. Ghagare (et.al 2017) - effective
implementation of 5s will manage all the tools and material
in the industry. And side by side it will help to improve the
productivity, quality and efficiency of the organisation.
Shraddha P. Deshpande (et.al 2015) - she has implemented
this technique in Samsonite South Asia Pvt. Ltd. Gonde-
Dumala, Maharashtra. According to her, because of
implementation of this concept we can save our time,wecan
improve the productivity and we can see the rapid result of
this concept.
Swapnil Patil (et.al 2016) - he has implemented the 5s
technique in Asara and Girija industries, Palus, Maharashtra.
According to him efficient implementation of 5s lead to
subsequent improvement in productivity.
Soumya R. Purohit (et.al 2015) - according to her,
implementation of 5s will tendsto reduce human effort, less
time, less inventory and increase the productivity. She has
implemented the concept of 5sin Spoorti Machine ToolsPvt.
Ltd. Bangalore, India.
Arash Ghodrati (et.al 2013) – he has implemented this
technique in V.M. Auto Pvt. Ltd. Satpur (MIDC) Nashik.
According to him it is the technique of reducing the cost,
improving the working condition of organisation and
improving the efficiency of that organisation.
3. PROBLEM STATEMENT
1) Waste of time while finding the tools or any
important equipment (no place).
2) Waste of money (for purchasing of same kind).
3) No proper disposal of waste, making environment
dirty which affects the moral of worker.
4) No systematic arrangement of toolsand equipment.
Hence, more retrieval time.
5) No specific place for job rejection, finished product
and raw material.
4. METHODOLOGY
1. Training:
Training programs were conducted to clear the idea of 5S to
the staff members and workers. Simple and effective PPT’s
were used to simplify to concept for better understanding.
Importance and benefitsof 5S were thoroughly explainedto
the workers. Some examplesofsuccessiveimplementationof
5S in other organisation and itsbenefits to that organisation
was shown with the help of photographs.
2. Zone Formation:
Photograph 1-Zone Formation
Implementing 5S in entire organisation without
systematic planning is a difficult job.Forsimplifying
the process, organisation was divided into different
zones. Each zone was given a specific name and
number.
3. Problem Identification:
Problems in the specific zone were identified by proper
observation.
- Wastage of time
- Proper place not available.
4. Training on Seiri:
- Training was conducted on 1S. The process
implementation of 1S was explained to the staff and
workers.
- After successful implementation of 1S, other 4S were
implemented in similar manner. Training session were
conducted before implementation of each ‘S’.
5. IMPLEMENTATION OF 5S
5.1Seiri Implementation
 Objective of implementation of Seiri is to removeall
the unwanted material from the workplace and
make more space available for the needed material.
 One zone is targeted at a time.
 All the material near the machine is collected
together at a place. Name of each material is noted
down and the material is categorized into
1. Need – material which are required constantly
without which production will step comes under
the category
2. Want –
a. Not ok – Damaged material, material life
expired
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2578
b. Excess – extra units of single material
c. Low/continuous frequently – material
which is rarely required comes under this
category
Seiriform is used to classify the material and keep record of
the corrective action taken for each material
Photograph 2-Seiri Form
After classification the unwanted materialismovedtothe
red tag area. After proper analysis decision about the
corrective action for each material is taken. The material is
disposed, sold, or repaired. Accordingly, action is taken.
Seiri in Zone 1
Photograph 3-Seiri in Zone 1
Seiri in Zone 6
Photograph 4-Seiri in Zone 6
Seiri Blasting
Implementation of Seiri zone wise is a time consuming
process. So a new technique is used for implementing Seiri
known as Seiriblasting. A day is selected; all the staff
membersand workersare gathered.Teamsareformed.Each
team is allotted a particular zone. Simultaneously at the
same time, each team performsthe Seiri in a particularzone.
After sorting, unwanted material is moved to red tag area,
and further decision is taken by the team after proper
analysis.
Photograph 5-Seri Blasting
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2579
5.1.1 Outcome of Seiri
1. Finding lost or forgotten material may save re-
ordering cost.
2. Easy to find tools, as only needed material are
stored at work station.
3. Easy to find documents with current information,
and avoiding outdated information.
4. Production space is free and more space is available
for needed materials.
5. Cost engaged with hidden scrap is free.
Photograph 6-Before 1S
Photograph 7-After 1S
Photograph 8-Before 1S
Photograph 9-After 1S
5.2 Seiton Implementation:
Seiton means systematic arrangement. “Place foreverything
and everything in its place” is the principle of Seiton. After
sorting, only the things which are needed are present at
workplace. Proper place is made available for each and
everything. Arrangement is made simple and effective,
followed by naming.
While designing tool boards, racks, we consideredaesthetics
as well as ergonomics. We made three to four adequate
designs and from that we chose optimum design according
to suitability.
We used different waste material which wasavailable in the
industry while implementing Seiton, to get the best output.
Waste plastic boxes were used as tool holder and bottle
holder. Scrap Steel strip was used to hold drill boxes. Scrap
wooden planks were used to prepare section for keeping
files.
Problem Statement- Job has to be turned at least 3 to 4
times while cleaning, which increases fatigue to the worker.
Also there is no proper place for storing cleaning equipment.
Insufficient light during night shifts.
Photograph 10-Cleaning table before 2S
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2580
Solution- Cleaning booth with rotary table isinstalled.Nowjob
has to be turned only once, resulting into less fatique to the
worker. Proper place is available for cleaning equipments.
Tubelight is provided in the cleaning booth,speciallyfornight
shifts.
Photograph 11-Cleaning booth after 2S
Problem Statement- No proper place for keeping bags.
Photograph 12- Before 2S
Solution-Rack for keeping bags is made.
Photograph 13-After 2S
Problem Statement- Tools are not arranged systematically,
making it difficult to find.
Photograph 14-Tool storage before 2S
Solution- Rack for storing tools is installed along with name
labels.
Photograph 15-Tool storage after 2S
Problem Statement- Jobs placed on the ground making it
difficult for worker to lift.
Photograph 16-Before 2S
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2581
Solution- Stands for keeping jobs is made, thereby
avoiding bending motion for the worker.
Photograph 17-After 2S
Problem Statement- No proper place available near machine
for storing the work documents needed near the machine.
Photograph 18-Before 2S
Solution- Bookshelf made for storing the work documents
near the machine.
Photograph 19-After 2S
Best out of Waste
Photograph 20-Scrap boxes used for storing tools
Photograph 21-Scrap steel plate used for holding drill
boxes
Photograph 22-Scrap boxes used for holding bottle
5.2.2 Outcomes of Seiton
1. Easy to find the tools, equipment and documents.
2. Any missing thing can be easily identified, so less
unscheduled downtime.
3. Increased productivity asless time is spentfortools
retrieval.
4. Less fatigue to workers, asthey do lessbendingand
lifting.
5.3 Seiso Implementation:
Seiso means shine. It aims for eliminating the dirt and
keeping workplace clean. Cleaning is everybody’s
responsibility. For maintaining cleanliness regularly,
schedule is prepared. Cleanliness is treated asinspection.All
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2582
the tools and equipment are inspected for any breakage or
defect, while cleaning. It improves safety and productivity.
Clean workplace also helps to improve morale of workers.
Scheduled housekeeping is one way to keep workplace
cleaning. But, better way is to prevent workplace from
getting dirty. For this, methods to prevent dirt are
developed.
Problem statement- Proper system not available for the
collection of waste (metal chips) generated.
Photograph 23-Before 3S
Solution- Funnel system designed forthepropercollectionof
waste.
Photograph 24-Developing stage
Photograph 25-After 3S
5.3.2 Outcomes of Seiso:
1. Improve safety in the workplace.
2. Greater visibility and reduced retrieval time.
3. Improve morale of the workers.
4. Maintenance cost is reduced
5. Higher quality products and increasedproductivity.
5.4 Seiketsu implementation
 After implementation of first 3S, it is important to
maintain the achieved improvements.Seiketsuaims
for maintaining these improvements
 Any problem related to the first 3s is deeply
investigated. Various questions are asked for that
purpose, like:
What is the problem?
Why does it happen?
When does it happen?
How can it be eliminated?
Thus a better solution is found out.
 Standard procedure for doing a particular work is
developed. Poster of these standard proceduresare
posted near the machine, so that the workersfollow
the same procedure.
 Responsibility is assigned to everyone in order to
maintain first 3S.
 Checklist is prepared to check whether everyone is
fulfilling his responsibility.
 Schedule for practising first 3S regularly is
prepared. Documentation of changes is done. The
photographsof before and after situationarepasted
in the work area. It helps to improve morale of the
workers.
5.5 Shitsuke Implementation
Shitsuke means sustain. It is important to maintain the 5s
system in order to sustain the improvement. Efforts should
be taken by the workers as well as management for the
same. Internal audits are carried out at regular intervals as
scheduled in the 4S (Shitsuke). Surprise audits are also
carried out. Proper recognition and awards are given to the
workers who do well in maintaining 5s system. 5s slogans
and posters are installed all over the industry to motivate
the workers.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2583
Photograph 26- 5S posters
6. CONCLUSION
The main aim of our project is to improve the working
environment according to type of work and comfort of the
worker. For that purpose, we implemented all the above
changes which are shown in before and after photographs.
Successful implementation of 5S has led to increase in moral
of the worker and working ability. Because of the proper
placement of all tools and gaugesthe retrieval timeisreduced.
Proper place is now available for storage of all the tools and
equipment needed near a machine as well aspersonalthings
of workers (like bags, Tiffin box, clothes etc.). After
successfully implementation of our project we conclude that,
5S implementation is beneficial for all the industries whose
working environment is not good or too old. It improves
quality as well as work ethic in the organization.
ACKNOWLEDGEMENT
We express our deep sense of gratitude to our guide Prof.
P.A. Pandav for his valuable guidance rendered in all phase
of project. We are thankful for his wholehearted assistance,
advice and expert guidance towards making our work
success. We would also like to express our thanks to Mr.
Amar Jadhav, Owner of Accura tech industries for his
assistance.
Our special thanks to honorable Principal Dr. A. N. Jadhav&
Head of Department for their keen interest, encourage and
excellent support. We would also like to express our thanks
to all of other staff members of college & friends who helped
usdirectly & indirectly during the completion of this Report.
REFERENCES
[1] Sagar D Ghagare,et.al “5S Implementation in small scale
industry: A case Study”, IJCESR, volume-4, issue-8, 2017.
[2] Shraddha P. Deshpande et.al (2015),“Implementationof
‘5s’ technique in a manufacturing organization”, IJRET
Volume: 04.
[3] Swapnil Patil, Amar Sapkal, Mahesh Sutar, “Execute 5S
Methodology in Small Scale Industry: A Case Study”,
International Journal of Research in Advent Technology,
Vol.4, No.3, March 2016.
[4] Soumya R. Purohit, V. Shantha “Implementation of 5S
Methodology in a Manufacturing Industry”, International
Journal of Scientific & Engineering Research,Volume6,Issue
8, August-2015.
[5] Arash Ghodrati, Norzima Zulkifli, “The Impact of 5S
Implementation on Industrial Organizations’ Performance”,
International Journal of Business and Management
Invention, volume 4, issue 04, April 2015.
BIOGRAPHIES
Mrugendra Prakash Jagdale, Pursuing
Final Year in Bachelor of Mechanical
Engineering degree from D.Y. Patil
college of Engineering and Technology,
Kolhapur, under the affiliation of Shivaji
University, Maharashtra, India.
Shounak Shailendra Lad, Pursuing Final
Year in Bachelor of Mechanical
Engineering degree from D.Y. Patil
college of Engineering and Technology,
Kolhapur, under the affiliation of Shivaji
University, Maharashtra, India.
Santosh Sakharam Kamble, Pursuing
Final Year in Bachelor of Mechanical
Engineering degree from D.Y. Patil
college of Engineering and Technology,
Kolhapur, under the affiliation of Shivaji
University, Maharashtra, India.

More Related Content

What's hot

Implementation of 5S Methodology in a Food & Beverage Industry: A Case Study
Implementation of 5S Methodology in a Food & Beverage Industry: A Case StudyImplementation of 5S Methodology in a Food & Beverage Industry: A Case Study
Implementation of 5S Methodology in a Food & Beverage Industry: A Case StudyIRJET Journal
 
Basic of manufacturing system
Basic of manufacturing systemBasic of manufacturing system
Basic of manufacturing systemRashidi Asari
 
5 s material (eng)
5 s material (eng)5 s material (eng)
5 s material (eng)Sumrya123
 
HRM practices in a furniture manufacturing company in Bangladesh (A Case Study)
HRM practices in a furniture manufacturing company in Bangladesh (A Case Study)HRM practices in a furniture manufacturing company in Bangladesh (A Case Study)
HRM practices in a furniture manufacturing company in Bangladesh (A Case Study)Engr. Abdun Noor
 
5S Can change the total Environments of the Manufacturing Industry
5S Can change the total Environments of the Manufacturing Industry 5S Can change the total Environments of the Manufacturing Industry
5S Can change the total Environments of the Manufacturing Industry Ashraf Hameed
 
E42e Tqm – Path Light To Success
E42e Tqm – Path Light To SuccessE42e Tqm – Path Light To Success
E42e Tqm – Path Light To Successajithsrc
 

What's hot (10)

Implementation of 5S Methodology in a Food & Beverage Industry: A Case Study
Implementation of 5S Methodology in a Food & Beverage Industry: A Case StudyImplementation of 5S Methodology in a Food & Beverage Industry: A Case Study
Implementation of 5S Methodology in a Food & Beverage Industry: A Case Study
 
5s training
5s training5s training
5s training
 
Final Kaizen
Final KaizenFinal Kaizen
Final Kaizen
 
5s methodology
5s methodology5s methodology
5s methodology
 
Basic of manufacturing system
Basic of manufacturing systemBasic of manufacturing system
Basic of manufacturing system
 
5 s material (eng)
5 s material (eng)5 s material (eng)
5 s material (eng)
 
HRM practices in a furniture manufacturing company in Bangladesh (A Case Study)
HRM practices in a furniture manufacturing company in Bangladesh (A Case Study)HRM practices in a furniture manufacturing company in Bangladesh (A Case Study)
HRM practices in a furniture manufacturing company in Bangladesh (A Case Study)
 
5S Can change the total Environments of the Manufacturing Industry
5S Can change the total Environments of the Manufacturing Industry 5S Can change the total Environments of the Manufacturing Industry
5S Can change the total Environments of the Manufacturing Industry
 
Brandon.ppt
Brandon.pptBrandon.ppt
Brandon.ppt
 
E42e Tqm – Path Light To Success
E42e Tqm – Path Light To SuccessE42e Tqm – Path Light To Success
E42e Tqm – Path Light To Success
 

Similar to IRJET- Implementation of 5’s to Improve Work Ethic and Overall Performance of the Organization

IRJET- Implementation of 5S in the Manufacturing Industry
IRJET-  	  Implementation of 5S in the Manufacturing IndustryIRJET-  	  Implementation of 5S in the Manufacturing Industry
IRJET- Implementation of 5S in the Manufacturing IndustryIRJET Journal
 
Analysis of Productivity Improvement And Safety Measures By 5-S Technique
Analysis of Productivity Improvement And Safety Measures By 5-S TechniqueAnalysis of Productivity Improvement And Safety Measures By 5-S Technique
Analysis of Productivity Improvement And Safety Measures By 5-S TechniqueIJERA Editor
 
Improvement of Plant Layout by using 5S technique-An industrial case study
Improvement of Plant Layout by using 5S technique-An industrial case studyImprovement of Plant Layout by using 5S technique-An industrial case study
Improvement of Plant Layout by using 5S technique-An industrial case studyIJMER
 
IRJET- Study and Implementation of ‘5 S’ System in Manufacturing Industry
IRJET-  	  Study and Implementation of ‘5 S’ System in Manufacturing IndustryIRJET-  	  Study and Implementation of ‘5 S’ System in Manufacturing Industry
IRJET- Study and Implementation of ‘5 S’ System in Manufacturing IndustryIRJET Journal
 
‘5S’ Implementation in a Fasteners Manufacturing Company
‘5S’ Implementation in a Fasteners Manufacturing Company‘5S’ Implementation in a Fasteners Manufacturing Company
‘5S’ Implementation in a Fasteners Manufacturing CompanyIRJET Journal
 
Application of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentApplication of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentIRJET Journal
 
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESSIMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESSIRJET Journal
 
Optimizing Workplace Efficiency and Productivity: An Introduction to the 5S S...
Optimizing Workplace Efficiency and Productivity: An Introduction to the 5S S...Optimizing Workplace Efficiency and Productivity: An Introduction to the 5S S...
Optimizing Workplace Efficiency and Productivity: An Introduction to the 5S S...IRJET Journal
 
Implementation of 5S in College(Shree Mahavir Education Society's Institute ...
Implementation of 5S in College(Shree Mahavir Education Society's  Institute ...Implementation of 5S in College(Shree Mahavir Education Society's  Institute ...
Implementation of 5S in College(Shree Mahavir Education Society's Institute ...chiragkolambe
 
Total Productive Maintenance - A Systematic Review
Total Productive Maintenance - A Systematic ReviewTotal Productive Maintenance - A Systematic Review
Total Productive Maintenance - A Systematic Reviewijsrd.com
 
IRJET- Application of Work Study in Construction Project
IRJET-  	  Application of Work Study in Construction ProjectIRJET-  	  Application of Work Study in Construction Project
IRJET- Application of Work Study in Construction ProjectIRJET Journal
 
Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...ijtsrd
 
IRJET- Applications of Process Industrial Engineering in Food Industry
IRJET- Applications of Process Industrial Engineering in Food IndustryIRJET- Applications of Process Industrial Engineering in Food Industry
IRJET- Applications of Process Industrial Engineering in Food IndustryIRJET Journal
 
IRJET- Applications of Lean Six Sigma
IRJET-  	  Applications of Lean Six SigmaIRJET-  	  Applications of Lean Six Sigma
IRJET- Applications of Lean Six SigmaIRJET Journal
 
Implementation of ‘5 s’ technique in a manufacturing organization a case s...
Implementation of ‘5 s’ technique in a manufacturing organization    a case s...Implementation of ‘5 s’ technique in a manufacturing organization    a case s...
Implementation of ‘5 s’ technique in a manufacturing organization a case s...eSAT Journals
 
5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workloadeSAT Publishing House
 

Similar to IRJET- Implementation of 5’s to Improve Work Ethic and Overall Performance of the Organization (20)

IRJET- Implementation of 5S in the Manufacturing Industry
IRJET-  	  Implementation of 5S in the Manufacturing IndustryIRJET-  	  Implementation of 5S in the Manufacturing Industry
IRJET- Implementation of 5S in the Manufacturing Industry
 
Analysis of Productivity Improvement And Safety Measures By 5-S Technique
Analysis of Productivity Improvement And Safety Measures By 5-S TechniqueAnalysis of Productivity Improvement And Safety Measures By 5-S Technique
Analysis of Productivity Improvement And Safety Measures By 5-S Technique
 
Improvement of Plant Layout by using 5S technique-An industrial case study
Improvement of Plant Layout by using 5S technique-An industrial case studyImprovement of Plant Layout by using 5S technique-An industrial case study
Improvement of Plant Layout by using 5S technique-An industrial case study
 
IRJET- Study and Implementation of ‘5 S’ System in Manufacturing Industry
IRJET-  	  Study and Implementation of ‘5 S’ System in Manufacturing IndustryIRJET-  	  Study and Implementation of ‘5 S’ System in Manufacturing Industry
IRJET- Study and Implementation of ‘5 S’ System in Manufacturing Industry
 
‘5S’ Implementation in a Fasteners Manufacturing Company
‘5S’ Implementation in a Fasteners Manufacturing Company‘5S’ Implementation in a Fasteners Manufacturing Company
‘5S’ Implementation in a Fasteners Manufacturing Company
 
Application of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentApplication of Lean Concepts in Molding Department
Application of Lean Concepts in Molding Department
 
Lean tool 5 s
Lean tool    5 sLean tool    5 s
Lean tool 5 s
 
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESSIMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
 
Eb4301774779
Eb4301774779Eb4301774779
Eb4301774779
 
TOTAL QUALITY MANAGEMENT
TOTAL QUALITY MANAGEMENT TOTAL QUALITY MANAGEMENT
TOTAL QUALITY MANAGEMENT
 
Optimizing Workplace Efficiency and Productivity: An Introduction to the 5S S...
Optimizing Workplace Efficiency and Productivity: An Introduction to the 5S S...Optimizing Workplace Efficiency and Productivity: An Introduction to the 5S S...
Optimizing Workplace Efficiency and Productivity: An Introduction to the 5S S...
 
Implementation of 5S in College(Shree Mahavir Education Society's Institute ...
Implementation of 5S in College(Shree Mahavir Education Society's  Institute ...Implementation of 5S in College(Shree Mahavir Education Society's  Institute ...
Implementation of 5S in College(Shree Mahavir Education Society's Institute ...
 
Total Productive Maintenance - A Systematic Review
Total Productive Maintenance - A Systematic ReviewTotal Productive Maintenance - A Systematic Review
Total Productive Maintenance - A Systematic Review
 
IRJET- Application of Work Study in Construction Project
IRJET-  	  Application of Work Study in Construction ProjectIRJET-  	  Application of Work Study in Construction Project
IRJET- Application of Work Study in Construction Project
 
Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...
 
IRJET- Applications of Process Industrial Engineering in Food Industry
IRJET- Applications of Process Industrial Engineering in Food IndustryIRJET- Applications of Process Industrial Engineering in Food Industry
IRJET- Applications of Process Industrial Engineering in Food Industry
 
IRJET- Applications of Lean Six Sigma
IRJET-  	  Applications of Lean Six SigmaIRJET-  	  Applications of Lean Six Sigma
IRJET- Applications of Lean Six Sigma
 
Knowledge management
Knowledge managementKnowledge management
Knowledge management
 
Implementation of ‘5 s’ technique in a manufacturing organization a case s...
Implementation of ‘5 s’ technique in a manufacturing organization    a case s...Implementation of ‘5 s’ technique in a manufacturing organization    a case s...
Implementation of ‘5 s’ technique in a manufacturing organization a case s...
 
5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 

IRJET- Implementation of 5’s to Improve Work Ethic and Overall Performance of the Organization

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2576 Implementation of 5’s to improve work ethic and overall performance of the organization Mrugendra Jagdale1, Shounak Lad2, Santosh Kamble3 1,2,3 Student, Department of Mechanical Engineering, D.Y. Patil college of Engineering and technology, Kolhapur ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - 5s is a Japanese technique consisting of 5 words starting with ‘S’, namely Seiri (sort), Seiton (systematic arrangement), Seiso (shine), Seiketsu (standardize), Shitsuke (sustain). This paper represents 5S implementation in a company named Accura Tech located in Shiroli MIDC, Kolhapur. 5S has direct impact on productivity as well as quality. The need of 5S implementation was detected due to improper utilization of space, wastage of time and presenceof unwanted material at the workstation. The aim of implementation of 5S was to minimize idle time, reduce effort, increase safety to workers, and improve working conditions and environment. All staff members took initiative; also workers participated actively in the implementation process. The successive implementation of 5S resulted into increase in overall performance of the company and improved workethic between the workers. Key Words: 5S, Seri, Seiton, Seiso, Seiketsu, Shitsuke 1. INTRODUCTION In today’sworld of increasing competition, it is importantto seek better quality and productivityforsatisfyingcustomer’s ever increasing demands. An organization needsto improve continuously. Overall performance of organization depends upon the workplace management. Providingproperfacilities and working environment to the worker is importantforthe same. 5S is an effective tool for increasing overall performance of the organization. Implementation of 5S ensuresproper utilizationofavailable resources as well as modifies the system which is not fully capable of fulfilling the required function. Small changes make a big difference which is beneficial for the organization. 5S not only helps to lift the standard of the organization but also to improve the work ethic among the workers. 1.1What is 5S? 5S is a tool used for arranging a workplace in effective manner. 5S was introduced by Takashi Osada in early 1980s in Japan. It is a set of 5 Japanese terms starting with S, Seiri (sort), Seiton (systematic arrangement), Seiso (shine), Seiketsu (standardize), Shitsuke (sustain). 5S leads to elimination of waste, proper utilizationofplaceandprovides clean and comfortable working conditions. It has impact on overall performance of the organization. 1] Seiri  Sorting the material into - need and want.  Shifting unwanted materials to the red tag area.  Disposing the waste and excess material by reselling or trash. 2] Seiton  “Place for everything and everything in its place” is the mantra of the Seiton.  “Go visual Go vertical”, principle is followed.  Make proper place for each and everything needed at workplace.  Arrange things systematically and name them in order to eliminate wastage of time in searching. 3] Seiso  Keep the workplace as well as tools and equipment clean.  Maintain the cleanliness by following proper schedule.  Develop methods for proper disposal of waste. 4] Seiketsu  Develop standard procedures for maintaining improvements of first 3S.  Assign responsibilities to everyone.  Prepare checklists for various activities of 5S. 4] Shitsuke  Carry out scheduled internal audits and surprise audits.  Install 5S slogans and posters.  Give awards and recognition to the workers doing well for maintaining 5S system. 2. LITERATURE REVIEW Implementation of 5s is basically technique of improving productivity as well as quality of the product in any organisation. It totally dependsuponhowweareapplyingall those concepts in our organisation.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2577 According to Sagar D. Ghagare (et.al 2017) - effective implementation of 5s will manage all the tools and material in the industry. And side by side it will help to improve the productivity, quality and efficiency of the organisation. Shraddha P. Deshpande (et.al 2015) - she has implemented this technique in Samsonite South Asia Pvt. Ltd. Gonde- Dumala, Maharashtra. According to her, because of implementation of this concept we can save our time,wecan improve the productivity and we can see the rapid result of this concept. Swapnil Patil (et.al 2016) - he has implemented the 5s technique in Asara and Girija industries, Palus, Maharashtra. According to him efficient implementation of 5s lead to subsequent improvement in productivity. Soumya R. Purohit (et.al 2015) - according to her, implementation of 5s will tendsto reduce human effort, less time, less inventory and increase the productivity. She has implemented the concept of 5sin Spoorti Machine ToolsPvt. Ltd. Bangalore, India. Arash Ghodrati (et.al 2013) – he has implemented this technique in V.M. Auto Pvt. Ltd. Satpur (MIDC) Nashik. According to him it is the technique of reducing the cost, improving the working condition of organisation and improving the efficiency of that organisation. 3. PROBLEM STATEMENT 1) Waste of time while finding the tools or any important equipment (no place). 2) Waste of money (for purchasing of same kind). 3) No proper disposal of waste, making environment dirty which affects the moral of worker. 4) No systematic arrangement of toolsand equipment. Hence, more retrieval time. 5) No specific place for job rejection, finished product and raw material. 4. METHODOLOGY 1. Training: Training programs were conducted to clear the idea of 5S to the staff members and workers. Simple and effective PPT’s were used to simplify to concept for better understanding. Importance and benefitsof 5S were thoroughly explainedto the workers. Some examplesofsuccessiveimplementationof 5S in other organisation and itsbenefits to that organisation was shown with the help of photographs. 2. Zone Formation: Photograph 1-Zone Formation Implementing 5S in entire organisation without systematic planning is a difficult job.Forsimplifying the process, organisation was divided into different zones. Each zone was given a specific name and number. 3. Problem Identification: Problems in the specific zone were identified by proper observation. - Wastage of time - Proper place not available. 4. Training on Seiri: - Training was conducted on 1S. The process implementation of 1S was explained to the staff and workers. - After successful implementation of 1S, other 4S were implemented in similar manner. Training session were conducted before implementation of each ‘S’. 5. IMPLEMENTATION OF 5S 5.1Seiri Implementation  Objective of implementation of Seiri is to removeall the unwanted material from the workplace and make more space available for the needed material.  One zone is targeted at a time.  All the material near the machine is collected together at a place. Name of each material is noted down and the material is categorized into 1. Need – material which are required constantly without which production will step comes under the category 2. Want – a. Not ok – Damaged material, material life expired
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2578 b. Excess – extra units of single material c. Low/continuous frequently – material which is rarely required comes under this category Seiriform is used to classify the material and keep record of the corrective action taken for each material Photograph 2-Seiri Form After classification the unwanted materialismovedtothe red tag area. After proper analysis decision about the corrective action for each material is taken. The material is disposed, sold, or repaired. Accordingly, action is taken. Seiri in Zone 1 Photograph 3-Seiri in Zone 1 Seiri in Zone 6 Photograph 4-Seiri in Zone 6 Seiri Blasting Implementation of Seiri zone wise is a time consuming process. So a new technique is used for implementing Seiri known as Seiriblasting. A day is selected; all the staff membersand workersare gathered.Teamsareformed.Each team is allotted a particular zone. Simultaneously at the same time, each team performsthe Seiri in a particularzone. After sorting, unwanted material is moved to red tag area, and further decision is taken by the team after proper analysis. Photograph 5-Seri Blasting
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2579 5.1.1 Outcome of Seiri 1. Finding lost or forgotten material may save re- ordering cost. 2. Easy to find tools, as only needed material are stored at work station. 3. Easy to find documents with current information, and avoiding outdated information. 4. Production space is free and more space is available for needed materials. 5. Cost engaged with hidden scrap is free. Photograph 6-Before 1S Photograph 7-After 1S Photograph 8-Before 1S Photograph 9-After 1S 5.2 Seiton Implementation: Seiton means systematic arrangement. “Place foreverything and everything in its place” is the principle of Seiton. After sorting, only the things which are needed are present at workplace. Proper place is made available for each and everything. Arrangement is made simple and effective, followed by naming. While designing tool boards, racks, we consideredaesthetics as well as ergonomics. We made three to four adequate designs and from that we chose optimum design according to suitability. We used different waste material which wasavailable in the industry while implementing Seiton, to get the best output. Waste plastic boxes were used as tool holder and bottle holder. Scrap Steel strip was used to hold drill boxes. Scrap wooden planks were used to prepare section for keeping files. Problem Statement- Job has to be turned at least 3 to 4 times while cleaning, which increases fatigue to the worker. Also there is no proper place for storing cleaning equipment. Insufficient light during night shifts. Photograph 10-Cleaning table before 2S
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2580 Solution- Cleaning booth with rotary table isinstalled.Nowjob has to be turned only once, resulting into less fatique to the worker. Proper place is available for cleaning equipments. Tubelight is provided in the cleaning booth,speciallyfornight shifts. Photograph 11-Cleaning booth after 2S Problem Statement- No proper place for keeping bags. Photograph 12- Before 2S Solution-Rack for keeping bags is made. Photograph 13-After 2S Problem Statement- Tools are not arranged systematically, making it difficult to find. Photograph 14-Tool storage before 2S Solution- Rack for storing tools is installed along with name labels. Photograph 15-Tool storage after 2S Problem Statement- Jobs placed on the ground making it difficult for worker to lift. Photograph 16-Before 2S
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2581 Solution- Stands for keeping jobs is made, thereby avoiding bending motion for the worker. Photograph 17-After 2S Problem Statement- No proper place available near machine for storing the work documents needed near the machine. Photograph 18-Before 2S Solution- Bookshelf made for storing the work documents near the machine. Photograph 19-After 2S Best out of Waste Photograph 20-Scrap boxes used for storing tools Photograph 21-Scrap steel plate used for holding drill boxes Photograph 22-Scrap boxes used for holding bottle 5.2.2 Outcomes of Seiton 1. Easy to find the tools, equipment and documents. 2. Any missing thing can be easily identified, so less unscheduled downtime. 3. Increased productivity asless time is spentfortools retrieval. 4. Less fatigue to workers, asthey do lessbendingand lifting. 5.3 Seiso Implementation: Seiso means shine. It aims for eliminating the dirt and keeping workplace clean. Cleaning is everybody’s responsibility. For maintaining cleanliness regularly, schedule is prepared. Cleanliness is treated asinspection.All
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2582 the tools and equipment are inspected for any breakage or defect, while cleaning. It improves safety and productivity. Clean workplace also helps to improve morale of workers. Scheduled housekeeping is one way to keep workplace cleaning. But, better way is to prevent workplace from getting dirty. For this, methods to prevent dirt are developed. Problem statement- Proper system not available for the collection of waste (metal chips) generated. Photograph 23-Before 3S Solution- Funnel system designed forthepropercollectionof waste. Photograph 24-Developing stage Photograph 25-After 3S 5.3.2 Outcomes of Seiso: 1. Improve safety in the workplace. 2. Greater visibility and reduced retrieval time. 3. Improve morale of the workers. 4. Maintenance cost is reduced 5. Higher quality products and increasedproductivity. 5.4 Seiketsu implementation  After implementation of first 3S, it is important to maintain the achieved improvements.Seiketsuaims for maintaining these improvements  Any problem related to the first 3s is deeply investigated. Various questions are asked for that purpose, like: What is the problem? Why does it happen? When does it happen? How can it be eliminated? Thus a better solution is found out.  Standard procedure for doing a particular work is developed. Poster of these standard proceduresare posted near the machine, so that the workersfollow the same procedure.  Responsibility is assigned to everyone in order to maintain first 3S.  Checklist is prepared to check whether everyone is fulfilling his responsibility.  Schedule for practising first 3S regularly is prepared. Documentation of changes is done. The photographsof before and after situationarepasted in the work area. It helps to improve morale of the workers. 5.5 Shitsuke Implementation Shitsuke means sustain. It is important to maintain the 5s system in order to sustain the improvement. Efforts should be taken by the workers as well as management for the same. Internal audits are carried out at regular intervals as scheduled in the 4S (Shitsuke). Surprise audits are also carried out. Proper recognition and awards are given to the workers who do well in maintaining 5s system. 5s slogans and posters are installed all over the industry to motivate the workers.
  • 8. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2583 Photograph 26- 5S posters 6. CONCLUSION The main aim of our project is to improve the working environment according to type of work and comfort of the worker. For that purpose, we implemented all the above changes which are shown in before and after photographs. Successful implementation of 5S has led to increase in moral of the worker and working ability. Because of the proper placement of all tools and gaugesthe retrieval timeisreduced. Proper place is now available for storage of all the tools and equipment needed near a machine as well aspersonalthings of workers (like bags, Tiffin box, clothes etc.). After successfully implementation of our project we conclude that, 5S implementation is beneficial for all the industries whose working environment is not good or too old. It improves quality as well as work ethic in the organization. ACKNOWLEDGEMENT We express our deep sense of gratitude to our guide Prof. P.A. Pandav for his valuable guidance rendered in all phase of project. We are thankful for his wholehearted assistance, advice and expert guidance towards making our work success. We would also like to express our thanks to Mr. Amar Jadhav, Owner of Accura tech industries for his assistance. Our special thanks to honorable Principal Dr. A. N. Jadhav& Head of Department for their keen interest, encourage and excellent support. We would also like to express our thanks to all of other staff members of college & friends who helped usdirectly & indirectly during the completion of this Report. REFERENCES [1] Sagar D Ghagare,et.al “5S Implementation in small scale industry: A case Study”, IJCESR, volume-4, issue-8, 2017. [2] Shraddha P. Deshpande et.al (2015),“Implementationof ‘5s’ technique in a manufacturing organization”, IJRET Volume: 04. [3] Swapnil Patil, Amar Sapkal, Mahesh Sutar, “Execute 5S Methodology in Small Scale Industry: A Case Study”, International Journal of Research in Advent Technology, Vol.4, No.3, March 2016. [4] Soumya R. Purohit, V. Shantha “Implementation of 5S Methodology in a Manufacturing Industry”, International Journal of Scientific & Engineering Research,Volume6,Issue 8, August-2015. [5] Arash Ghodrati, Norzima Zulkifli, “The Impact of 5S Implementation on Industrial Organizations’ Performance”, International Journal of Business and Management Invention, volume 4, issue 04, April 2015. BIOGRAPHIES Mrugendra Prakash Jagdale, Pursuing Final Year in Bachelor of Mechanical Engineering degree from D.Y. Patil college of Engineering and Technology, Kolhapur, under the affiliation of Shivaji University, Maharashtra, India. Shounak Shailendra Lad, Pursuing Final Year in Bachelor of Mechanical Engineering degree from D.Y. Patil college of Engineering and Technology, Kolhapur, under the affiliation of Shivaji University, Maharashtra, India. Santosh Sakharam Kamble, Pursuing Final Year in Bachelor of Mechanical Engineering degree from D.Y. Patil college of Engineering and Technology, Kolhapur, under the affiliation of Shivaji University, Maharashtra, India.