PERIL DISSECTION CHIC FOR ROAD
CONSTRUCTION PROJECT:
A Case Study Construction of the UpGradation of Road From Kerehuba
to Runguzu Nasa Under NLCPR. Phase –I
Mr. Molay Reja1
, Prof Ashish P. Waghmare(PG Guide)2
,
1
M.E (construction and management) 2
Assistant Professor, M.E (construction and management)
Dr D Y Patil School of Engineering & Technology, Savitribai Phule Pune University.
Abstract- In Indian scenario of infrastructure industry,
there is a colossal vocation of peril analysis knacks and
tools available for the management of affliction. In
dogma, each peril analysis knack has its strengths and
weaknesses. Knacks such as Probability Theory,
Certainty Factors and Dempster-Shaffer theory of
evidence are discussed with regard to their application
to peril analysis in road projects. Suggestions on the
most appropriate tools associated with the knacks are
also presented. The mighty and emaciation of each
knack are highlighted and discussed. This paper
inferred the peril to be determined in project.
Index Terms- Peril analysis, construction, road projects,
knacks, uncertainty.
I. INTRODUCTION
Peril management and peril planning are used
interchangeably to describe a sequence of analysis
and management activities focused on creating a
project specific response to the inherent perils of
developing a new capital facility. It can be scrutinize
in different ways. Peril management is the discipline
of identifying, monitoring and limiting perils. Peril
management in infrastructure project is an organized
method for identifying and measuring peril and for
selecting, developing, and implementing options for
the handling of peril. It is a process, not a series of
events. Peril management depends on peril
management planning, early identification and
analysis of perils, continuous peril tracking and
reassessment, early implementation of corrective
actions, communication, documentation, and
coordination .Though there are many ways to
structure peril management, this book will structure it
as having four parts: Planning, Assessment,
Handling, and Monitoring. As depicted in Figure1 all
of the parts are interlocked to demonstrate that after
initial planning the parts begin to be dependent on
each other.
Fig: 1 Elements of Peril Management
All these steps are interconnected and are part of a
system, which means each should be properly
addressed so as to enable an effective operation of the
whole. Peril analysis aims to estimate or assess the
likely outcomes or impacts of perils under
consideration, in case they materialize.
II. PERILS IN CONSTRUCTION PROJECTS IN
NORTH EAST INDIA
India’s north eastern region, where the road ministry
has made ambitious plans to improve road
infrastructure, including an accelerated road
development program is witnessing a lack luster
demand from private road developers, largely due to
security concerns and threats from local terrorist
groups. Road developers have been staying away
from road projects in the region as officials have been
kidnapped and ransoms demanded for, in addition to
machinery and equipment being burnt down by local
HandelMonitor
Assess
Planning
p
Reports
© 2014 IJIRT | Volume 1 Issue 4 | ISSN : 2349-6002
IJIRT 100070 INTERNATONAL JOURNAL OF INNOVATIVE RESEARCH IN TECHNOLOGY 62
terrorist groups. The private sector is not interested in
road projects here and they have to arrange for
protection money. They are not interested in taking
the perils and we do not think the problem can be
resolved soon. India's road sector has been suffering
since the past few years largely due to inactive
participation from the private sector developers due
to funding constraints. In addition, land acquisition
has also become a major concern in Asia's third
largest economy. There is a higher execution peril in
the region but we think developers factor in these
perils. There are other concerns such as labor and
geographical constraints which has made the
implementation of projects difficult. Others
challenges things are Geographical dispersion,
significant number of players, technical variability,
technical complexity and large number of inputs are
some of the variables that make construction projects
defy. As a result of these interconnections the
enumeration and peculiarity of perils tend to be
toilsome. Peril classification is not a consensual
exercise even among the construction community but
the most important issue is the recognition of perils
and the need to tackle them so as to increase the
chance of project success. From this reasoning, it
follows that it is fundamental to identify the most
effective knacks to perform the operation.
III. NATURE OF ROAD PROJECTS PERILS IN
NAGALAND
(Construction of the UpGradation of Road From
Kerehuba to Runguzu Nasa Under NLCPR. Phase –
I):
Kerehuba to Runguzu Nasa Road project in Nagaland
perils were classified in accordance with source as
technical, legal, natural, logistic, social, economic,
financial, and commercial and political. The road
project starts from Kerehuba near the District
Headquarter Phek and traverses through the villages
of Shorhuba, Thevopisu, Runguzu Naghu and finally
ends at Runguzu Nasa on the Kohima Zunheboto
State Highway. Up Gradation of this road has been a
long standing demand of the people of Phek District
as this road will serve as the shortest possible route to
connect the District Headquarter Phek to Chozuba
and Chetheba ranges as well as commuter travelling
to the state capital Kohima from Phek and beyond.
Fig: 2 Location of road
In order to facilitate the analysis and reduce the
number of classes, these perils can be grouped at a
higher level in the breakdown structure using the
concept of environment layers. Before that is done it
is important to present some important concepts.
Following the project perils are assumed to be
associated with the internal, operational and general
environments. Projects perils are, therefore, classified
according to their primary source or cause and the
environmental layers as:
 Industries Peril Factors
1. Material Delay
2. Labor Problem
3. Equipment Break down
RUNGUZU NASA KEREHUBA
© 2014 IJIRT | Volume 1 Issue 4 | ISSN : 2349-6002
IJIRT 100070 INTERNATONAL JOURNAL OF INNOVATIVE RESEARCH IN TECHNOLOGY 63
4. Estimator Error
5. Management faux pas
6. Flaw Construction
7. Finance
 Catholic Peril Factors
1. Environmental Issue
2. Economic
3. Political Issue
4. Competition
5. Project/Design
6. Construction
7. Estimation
8. Scheduling
 Acts Of God
1. Heavy Floods;
2. Massive Landslides;
3. Earthquakes, And
4. Others.
IV. CONVENANT KNACKS FOR PERIL
PERSONATING AND DISSECTION
The kinds of perils that permeate construction of road
projects have been presented and briefly described.
Project managers have been confronted with the
choice of right peril analysis knack. It is important
for a manager for choosing appropriate knacks for
different kind of peril as Acts of Gods peril modeling
is not smellier to the model of industries specific
peril. Though the outcome is linear but the sources
are different. To substantiate the above parameter of
peril, the dissection used is apropos commencing.
The analysis is expected to shed some light on the
diversity of modeling and analysis perspectives as
well as their effectiveness.
V. PROBABILISTIC ANALYSIS KNACK
Probability analysis tools one of the most
sophisticated methods of identifying the construction
peril. As such, probabilistic modeling and analysis
has been the prominent way to handle perils
regardless their nature. Probability is a mathematics
deals with random variables. As such, it deals with
stochastic processes and events through frequents,
outcomes of repeated experiments, and subjective
views. Probability theory has been widely used to
model precisely described, repetitive experiments
with observable but uncertain outcomes. Normal
distribution is one of the tools to finding out the
uncertainty of landslides occurrence etc. Fig.3 shows
the landslide occurrence or not occurrence.
Fig. 3 Normal distribution curve
VI. INDUSTRIES PERILS
A more disciplined process involves using checklists
of potential perils and evaluating the likelihood that
those events might happen on the project. Some
companies and industries develop peril checklists
based on experience from past projects. These
checklists can be helpful to the project manager and
project team in identifying both specific perils on the
checklist and expanding the thinking of the team. The
past experience of the project team, project
experience within the company, and experts in the
industry can be valuable resources for identifying
potential peril on a project.
Identifying the sources of peril by category is another
method for exploring potential peril on a project.
Some examples of categories for potential perils
include the following:
1. Technical
2. Cost
3. Schedule
4. Client
5. Contractual
6. Weather
7. Financial
8. Political
9. Environmental
10. People
The people category can be subdivided into perils
associated with the people. Examples of people perils
include the peril of not finding the skills needed to
execute the project or the sudden unavailability of
key people on the project. David Hillson [1] uses the
same framework as the work breakdown structure
(WBS) for developing a peril breakdown structure
(RBS). A peril breakdown structure organizes the
perils that have been identified into categories using a
table with increasing levels of detail to the right.
Industries perils are related to the internal
environment of industries and these are supposed to
manage them. Industries level of knowledge about
the operations is significantly higher than other type
of peril. Indeed, issues such as planning, finance,
human resources, equipment and materials logistics
are dealt with on a daily basis. Industries can conduct
operations studies in order to build robust databases
0
0.05
0.1
0.15
0.2
0.25
0 5 10 15 20
© 2014 IJIRT | Volume 1 Issue 4 | ISSN : 2349-6002
IJIRT 100070 INTERNATONAL JOURNAL OF INNOVATIVE RESEARCH IN TECHNOLOGY 64
and learn systematically. Very often databases are
used as a means for routine programmed decision
king. The large quantity of information obtained in
this way can be retrieved in order to make
probabilistic estimates. For example, important
aspects such as labor productivity and cost can be
estimated in probabilistic terms in the planning
process through probability distributions. From this
point of view, it appears that probabilistic modeling
and analysis is suitable for this kind of perils. As a
great deal of knowledge is available, predictions
about the likelihood and impacts of perils can be
made with some degree of certainty. The prominent
uncertainty associated with industries related perils is
assumed to be eminently random. In term of tools,
simulation and analytical models can be utilized for
peril modeling analysis. One of the most effective
tools for this purpose would be Decision Support
Systems – DSS, which are computer information
systems that provide information in a given domain
of application by means of analytical decision models
and databases, in order to support a decision making
in complex and ill structured problems.
VII. GLOBAL PERIL FACTORS
Global peril factors are beyond industries’ control.
They relate to a more complex, erratic and dynamic
environment. As such, the possibility for collecting
data and information in order to draw useful lessons
becomes limited. Even taking into account the cyclic
nature of some factors such as economy ups and
downs, it is very difficult to make reasonable
estimates about them. Although there have some
attempts to estimate the degree of peril associated
with global perils the amount of available data make
the exercise difficult. An example of probabilistic
modeling applied to global peril factors is the
production of political peril indices covering a large
number of countries around the world as explained
by Bremmer9. The exercise has been conducted and
the results marketed systematically over the years.
The indices measure the stability perception over
specific countries and aim to help investors and other
interested parties in their business decision making.
Political variables are complex and dynamic and, as
consequence, very difficult to grasp. In general,
political phenomena are rarely repetitive, which
creates serious challenges for effective modeling. The
same applies to the economic and social variables.
Furthermore, political, economic and social events
are rarely mutually exclusive, exhaustive and
conditionally independent. First, there have been
strong interrelationships among these variables.
Economy, for example, is strongly associated with
social and political events. In the light of these
characteristics it can be concluded that probabilistic
modeling of global peril factors poses serious
challenges in terms of robustness and validity. The
uncertainty inherent in this group of peril factors is
much more epistemic rather than random.
VIII. ACTS OF GOD
Acts of God are generally classified as ‘’force
majeure’’ under the contractual terms, because no
party is supposed to be able to manage them and,
consequently, bear the associated costs. They
represent extreme events stemming from nature and,
as such, tremendously difficult to predict. It would be
important for a contractor, for example, to know the
likelihood of an earthquake striking and disrupting
construction works. Unfortunately, such estimates are
not available. That is the reason why the best
response strategy to this type of peril has been
transfer to a third party. Attempts have been made to
predict the probability of occurrence of these events,
but very little progress has been achieved so far.
Concerns over the problem have led analysts to
develop some probabilistic models but, it should
recognized, these can hardly be robust due to
prevailing nature of uncertainty. Therefore, such
estimates may be precise but not accurate. In
addition, since most nature related peril factors are
poorly defined and fuzzy in nature they cannot be
evaluated with such high precision inherent in
numerical expressions. These models have used
subjective probabilities instead of objective ones, as
the latter are difficult to obtain due to lack of data.
The fact that subjective probabilities cannot be
distinguished from objective ones once in the model,
is likely to hinder the quality of the analysis. There is
guarantee that subjective probabilities capture
uncertainty effectively. As a result, probabilistic
modeling and analysis of nature related perils is
debatable.
IX. CERTAINTY THEORY ANALYSIS KNACK
GLOBAL PERIL FACTORS AND ACTS OF
GOD
As previously shown, while industries related peril
factors can be well modeled through probabilistic
means, global perils and Acts of God are far more
difficult to handle in the same way due to the
inherent kind of uncertainty and scarcity of data and
information. MYCIN (an expert system for the
diagnosis and therapy of blood infections and
meningitis) introduced certainty factors theory, based
on belief MB(H, E) and disbelief MD(H, E). These
functions indicate the degree to which a
belief/disbelief in hypothesis H would be increased
by observing E. MB(H, E) = ( 1 if p(H) = 1
max[p(H|E),p(H)]−p(H) max[1,0]−p(H) otherwise
(11) MD(H, E) = ( 1 if p(H) = 0
© 2014 IJIRT | Volume 1 Issue 4 | ISSN : 2349-6002
IJIRT 100070 INTERNATONAL JOURNAL OF INNOVATIVE RESEARCH IN TECHNOLOGY 65
min[p(H|E),p(H)]−p(H) min[1,0]−p(H) otherwise
(12) To determine the total strength of belief or
disbelief, we use the following equation: cf = MB(H,
E) − MD(H, E) 1 − min[MB(H, E), MD(H, E)]. (13)
Certainty theory is mainly a theory for handling
uncertainty in knowledge based systems KBSs. It
was developed in attempt to overcome some of the
weaknesses of the so called idiot Bayes approaches
for inexact reasoning, according to Duda.10 Certainty
theory relies on defining judgmental measures of
belief rather than adhering to strict probability
estimates. Therefore, certainty factors (CF) are not
probabilities but informal measures of confidence for
a piece of evidence. They represent the degree to
which peoplebelieve that the given evidence is true.
In other words, they express how accurate, reliable,
truthful people judge statements or evidences.
Certainty theory fundamentals are the concepts of
certainty measures which are associated with factual
statements .The certainty measures or factors CFs
consist of numbers ranging from –1 to +1 and factual
statements, (rules). A negative value of the certainty
factor indicates that one believes that a fact is not true
and a positive value indicates the one believes that a
fact is true with complete knowledge. CF = 1, there is
complete certainty that a proposition is true CF = 1,
there is complete certainty that a proposition is false
CF = 0, there is no information at all about or no
change in belief 1 < CF < 1, measure of the degree of
belief about the proposition with decreasing and
increasing beliefs respectively. Global peril factors
and Acts of God in engineering projects can be
modeled using CFs within knowledge based systems,
where the following format is common: If A Then B
with certainty factor CF = CF (rule), where A is the
antecedent and B, the consequent. The antecedent
comprises facts (evidence) that support the derivation
of the consequent (hypothesis). The CF is the net
degree of belief in hypothesis, given that the evidence
is observed (given). For example: If the rate of
inflation increases then the prices will be high CF =
1, where the rate of inflation increases is the evidence
and the prices will be high is the consequence. The
degree of belief associated with the rule is 1, which
means the analyst is 100% sure.
X. DEMPSTER SHAFER THEORY OF EVIDENCE
ANALYSIS KNACK
The Dempster Shafer theory is based on two ideas:
the idea of obtaining degrees of belief for one
question from subjective probabilities for a related
question, and Dumpster’s rule for combining such
degrees of belief when they are based on independent
items of evidence. To illustrate the idea of obtaining
degrees of belief for one question from subjective
probabilities for another, suppose I have subjective
probabilities for the reliability of my friend Betty. My
probability that she is reliable is 0.9, and my
probability that she is unreliable is 0.1. Suppose she
tells me a limb fell on my car. This statement, which
must true if she is reliable, is not necessarily false if
she is unreliable. So her testimony alone justifies a
0.9 degree of belief that a limb fell on my car, but
only a zero degree of belief (not a 0.1 degree of
belief) that no limb fell on my car. This zero does not
mean that I am sure that no limb fell on my car, as a
zero probability would; it merely means that Betty's
testimony gives me no reason to believe that no limb
fell on my car. The 0.9 and the zero together
constitute a belief function.
XI. SUMMARY OF THE KNACKS
The strengths and weaknesses of the knacks that have
been discussed are summarized in Table 1. For each
of therefore peril analysis knacks, the evaluation of
type of peril, prominent uncertainty and tools to be
employed are shown.
Sr.No. Technique Modeling and Analysis Suitability
Peril Groups Probability of
UncertaintyIndustry (A) Global (B) Acts of
God(C)
1 Probablity Very Good Very poor Very poor Random A
2 Certainty Factor Very poor Good Good Epistemic B & C
3 Dempster_Shaffer Poor Good Good Epistemic B & C
Table 1 : Summary of peril analysis techniques and tools.
The indications provided in the table constitute a
guide on what a specific knack can help to manage.
For example, probabilistic modeling can be
effectively to model industries specific and global
perils factors where the underlying uncertainty is
mainly random. For that purpose Decision Support
Systems DSS seem to be the most appropriate tools.
On the other hand, probabilistic modeling is very
poor in tackling natural events or Acts of God as data
for these is scarce and frequently unavailable. The
© 2014 IJIRT | Volume 1 Issue 4 | ISSN : 2349-6002
IJIRT 100070 INTERNATONAL JOURNAL OF INNOVATIVE RESEARCH IN TECHNOLOGY 66
same procedure is followed with regard to other peril
analysis knacks.
XII. CONCLUSIONS
The importance of managing construction of road
project engineering peril factors has been discussed.
An extensive analysis of construction projects
implementation with emphasis on cost performance
has triggered work on peril modeling and analysis. It
has been concluded that the nature of perils under
consideration is determinant in the selection of
modeling and analysis knacks. As it has been shown,
not all uncertainty is random in nature. A great deal
of engineering management and technical issues do
not comply with randomness properties. They are
mainly cognitive and thus do not lend themselves to
precise measurement. Three groups of peril factors
inherent in construction engineering projects have
been presented and explained. It is understood that
the nature of the peril factors is diverse and thus their
handling requires appropriate knacks and tools.
Indeed, the type uncertainty associated with each of
the groups differs. While industries specific peril
factors can be effectively modeled through
probabilistic analysis, uncertainty underlying global
and acts of god peril factors appears to be much more
difficult to capture using the same approach. The
uncertainty type associated with the latter peril
factors derives mainly from reduced knowledge
rather than natural variability. As such, epistemic
uncertainty handling knacks are likely to be more
effective than probabilistic approaches. Several
uncertainty modeling knacks namely uncertainty
theory and Dempster Shaffer Theory of Evidence
have been discussed with emphasis on
appropriateness and robustness. Although there is no
consensus on the applicability of these knacks to
bridge the gap between the ideal and feasible
solutions provided by the probabilistic analysis, it
appears that they can be employed for such purpose.
In particular, Dempster Shafer Theory is capable of
modeling epistemic uncertainty through belief and
membership functions. Nevertheless, research is
required to ascertain the extent to which these and
additional knacks can be applied to improve
construction engineering perils modeling and
analysis.
REFERENCES
1. David Hillson, “Using a Peril Breakdown
Structure in Project Management,” Journal
of Facilities Management 2, no. 1 (2003):
85–97.
2. Thompson, P. and Perry, J., Engineering
Construction Perils. A Guide to Project Peril
Analysis and Peril Management. (London:
Thomas Telford. 1992).
3. Dempster, A.P. (1968). A generalization of
Bayesian inference. Journal of the Royal
Statistical Society, Series B 30 205247.
4. Shafer, Glenn (1976). A Mathematical
Theory of Evidence. Princeton University
Press.
5. DempsterShafer Theory By Glenn Shafer
Ronald G. Harper Distinguished Professor
of Business, School of Business,
Summerfield Hall, University of Kansas,
Lawrence, Kansas 66045.
6. Flanagan, R and Norman, G., Peril
Management and Construction. (London:
Blackwell. 1993)
7. Helton,, J Uncertainty and sensitivity
analysis in the presence of stochastic and
subjective uncertainty. “Journal of Statistical
Computation and Simulation” 57: 376
(1997).
8. Klir, G. Where Do We Stand on Measures
of Uncertainty, Ambiguity, Fuzziness and
the Like?. Fuzzy Sets and Systems, 1987,
24, pp.141160.
9. Van Gelder, P.H.A.J.M., "Statistical
Methods for the Peril Based Design of Civil
Structures", 2000, Communications on
Hydraulic and Geotechnical Engineering,
ISSN:0169654800 1, 248pages.
10. Zadeh, L. A., Fuzzy Sets. Information and
Control, 1965, 8, pp.338353.
11. Uher, T., Probabilistic Estimating. Cost
Engineering, 1996, 38(4), pp. 3340.
12. Ian Bremmer, “How to Calculate Political
Peril,” Inc. Magazine, April 2007, p. 101
13. Duda, R. O. et al Development of
PROSPECTOR System for Mineral
Exploration. Final Report, SRI Projects
5821 and 6415, (Menlo Park, CA, 1979).
14. Wang, G.Q, Jia, X. L (2005).Peril
Management on the BOT Investment and
Financing Mode, India Water &
Wastewater,21(9):8588.
15. Project Management Institute. Construction
extension to the PMBOKR Guide.3rd ed.
Newtown Square: Project Management
Institute;2007.
16. Institution of Civil Engineers and the
Actuarial Profession. Peril analysis and
management for projects (RAMP). 2nd ed.
Institute of Civil Engineers and the Actuarial
Profession. London: Thomas Telford Ltd;
2005.

More Related Content

What's hot

IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET Journal
 
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...IAEME Publication
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- 	  Analysis of Risk Management in Construction Sector using Fault Tree...IRJET- 	  Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...IRJET Journal
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET Journal
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSvivatechijri
 
A Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsA Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsIJMER
 
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...IJCMESJOURNAL
 
Establishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraqEstablishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraqIAEME Publication
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction worksvivatechijri
 
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET Journal
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSvivatechijri
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET Journal
 
Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.Rizwan Khurram
 
Critical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction ProjectsCritical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction Projectstheijes
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...IRJET Journal
 
Effectiveness of Risk Management and Chosen Methods in Construction Sector
Effectiveness of Risk Management and Chosen Methods in Construction SectorEffectiveness of Risk Management and Chosen Methods in Construction Sector
Effectiveness of Risk Management and Chosen Methods in Construction SectorIRJET Journal
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET Journal
 

What's hot (19)

IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
 
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- 	  Analysis of Risk Management in Construction Sector using Fault Tree...IRJET- 	  Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
 
A Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsA Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction Projects
 
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
 
Establishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraqEstablishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraq
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
 
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
 
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature Review
 
Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.
 
Critical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction ProjectsCritical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction Projects
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
 
Effectiveness of Risk Management and Chosen Methods in Construction Sector
Effectiveness of Risk Management and Chosen Methods in Construction SectorEffectiveness of Risk Management and Chosen Methods in Construction Sector
Effectiveness of Risk Management and Chosen Methods in Construction Sector
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction Projects
 

Similar to Ijirt100070 paper

RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIOIAEME Publication
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingAlexander Decker
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...IRJET Journal
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential SectorIRJET Journal
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...Dr. Amarjeet Singh
 
risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdfRidaShahid36
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET Journal
 
Risk Severity Framework for a BOT Highway Project
Risk Severity Framework for a BOT Highway ProjectRisk Severity Framework for a BOT Highway Project
Risk Severity Framework for a BOT Highway ProjectIOSRJMCE
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsIRJET Journal
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET Journal
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Sibo Kanyambari Aimable
 
Risk Management in Construction Project
Risk Management in Construction ProjectRisk Management in Construction Project
Risk Management in Construction ProjectDr. Amarjeet Singh
 
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...Sibo Kanyambari Aimable
 
Risk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectRisk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectIRJET Journal
 
IRJET- Risk Assessment of Public Private Partnership Projects In Kerala
IRJET- Risk Assessment of Public Private Partnership Projects In KeralaIRJET- Risk Assessment of Public Private Partnership Projects In Kerala
IRJET- Risk Assessment of Public Private Partnership Projects In KeralaIRJET Journal
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...IRJET Journal
 
IRJET-Risk Management Analysis on Cochin Metro Rail Project
IRJET-Risk Management Analysis on Cochin Metro Rail ProjectIRJET-Risk Management Analysis on Cochin Metro Rail Project
IRJET-Risk Management Analysis on Cochin Metro Rail ProjectIRJET Journal
 

Similar to Ijirt100070 paper (20)

RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk ranking
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential Sector
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...
 
risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdf
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
 
Risk Severity Framework for a BOT Highway Project
Risk Severity Framework for a BOT Highway ProjectRisk Severity Framework for a BOT Highway Project
Risk Severity Framework for a BOT Highway Project
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction Projects
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera Software
 
IJET-V2I6P23
IJET-V2I6P23IJET-V2I6P23
IJET-V2I6P23
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...
 
Risk Management in Construction Project
Risk Management in Construction ProjectRisk Management in Construction Project
Risk Management in Construction Project
 
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
 
Risk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectRisk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure project
 
IRJET- Risk Assessment of Public Private Partnership Projects In Kerala
IRJET- Risk Assessment of Public Private Partnership Projects In KeralaIRJET- Risk Assessment of Public Private Partnership Projects In Kerala
IRJET- Risk Assessment of Public Private Partnership Projects In Kerala
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 
IRJET-Risk Management Analysis on Cochin Metro Rail Project
IRJET-Risk Management Analysis on Cochin Metro Rail ProjectIRJET-Risk Management Analysis on Cochin Metro Rail Project
IRJET-Risk Management Analysis on Cochin Metro Rail Project
 

Recently uploaded

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Ijirt100070 paper

  • 1. © 2014 IJIRT | Volume 1 Issue 4 | ISSN : 2349-6002 IJIRT 100070 INTERNATONAL JOURNAL OF INNOVATIVE RESEARCH IN TECHNOLOGY 61 PERIL DISSECTION CHIC FOR ROAD CONSTRUCTION PROJECT: A Case Study Construction of the UpGradation of Road From Kerehuba to Runguzu Nasa Under NLCPR. Phase –I Mr. Molay Reja1 , Prof Ashish P. Waghmare(PG Guide)2 , 1 M.E (construction and management) 2 Assistant Professor, M.E (construction and management) Dr D Y Patil School of Engineering & Technology, Savitribai Phule Pune University. Abstract- In Indian scenario of infrastructure industry, there is a colossal vocation of peril analysis knacks and tools available for the management of affliction. In dogma, each peril analysis knack has its strengths and weaknesses. Knacks such as Probability Theory, Certainty Factors and Dempster-Shaffer theory of evidence are discussed with regard to their application to peril analysis in road projects. Suggestions on the most appropriate tools associated with the knacks are also presented. The mighty and emaciation of each knack are highlighted and discussed. This paper inferred the peril to be determined in project. Index Terms- Peril analysis, construction, road projects, knacks, uncertainty. I. INTRODUCTION Peril management and peril planning are used interchangeably to describe a sequence of analysis and management activities focused on creating a project specific response to the inherent perils of developing a new capital facility. It can be scrutinize in different ways. Peril management is the discipline of identifying, monitoring and limiting perils. Peril management in infrastructure project is an organized method for identifying and measuring peril and for selecting, developing, and implementing options for the handling of peril. It is a process, not a series of events. Peril management depends on peril management planning, early identification and analysis of perils, continuous peril tracking and reassessment, early implementation of corrective actions, communication, documentation, and coordination .Though there are many ways to structure peril management, this book will structure it as having four parts: Planning, Assessment, Handling, and Monitoring. As depicted in Figure1 all of the parts are interlocked to demonstrate that after initial planning the parts begin to be dependent on each other. Fig: 1 Elements of Peril Management All these steps are interconnected and are part of a system, which means each should be properly addressed so as to enable an effective operation of the whole. Peril analysis aims to estimate or assess the likely outcomes or impacts of perils under consideration, in case they materialize. II. PERILS IN CONSTRUCTION PROJECTS IN NORTH EAST INDIA India’s north eastern region, where the road ministry has made ambitious plans to improve road infrastructure, including an accelerated road development program is witnessing a lack luster demand from private road developers, largely due to security concerns and threats from local terrorist groups. Road developers have been staying away from road projects in the region as officials have been kidnapped and ransoms demanded for, in addition to machinery and equipment being burnt down by local HandelMonitor Assess Planning p Reports
  • 2. © 2014 IJIRT | Volume 1 Issue 4 | ISSN : 2349-6002 IJIRT 100070 INTERNATONAL JOURNAL OF INNOVATIVE RESEARCH IN TECHNOLOGY 62 terrorist groups. The private sector is not interested in road projects here and they have to arrange for protection money. They are not interested in taking the perils and we do not think the problem can be resolved soon. India's road sector has been suffering since the past few years largely due to inactive participation from the private sector developers due to funding constraints. In addition, land acquisition has also become a major concern in Asia's third largest economy. There is a higher execution peril in the region but we think developers factor in these perils. There are other concerns such as labor and geographical constraints which has made the implementation of projects difficult. Others challenges things are Geographical dispersion, significant number of players, technical variability, technical complexity and large number of inputs are some of the variables that make construction projects defy. As a result of these interconnections the enumeration and peculiarity of perils tend to be toilsome. Peril classification is not a consensual exercise even among the construction community but the most important issue is the recognition of perils and the need to tackle them so as to increase the chance of project success. From this reasoning, it follows that it is fundamental to identify the most effective knacks to perform the operation. III. NATURE OF ROAD PROJECTS PERILS IN NAGALAND (Construction of the UpGradation of Road From Kerehuba to Runguzu Nasa Under NLCPR. Phase – I): Kerehuba to Runguzu Nasa Road project in Nagaland perils were classified in accordance with source as technical, legal, natural, logistic, social, economic, financial, and commercial and political. The road project starts from Kerehuba near the District Headquarter Phek and traverses through the villages of Shorhuba, Thevopisu, Runguzu Naghu and finally ends at Runguzu Nasa on the Kohima Zunheboto State Highway. Up Gradation of this road has been a long standing demand of the people of Phek District as this road will serve as the shortest possible route to connect the District Headquarter Phek to Chozuba and Chetheba ranges as well as commuter travelling to the state capital Kohima from Phek and beyond. Fig: 2 Location of road In order to facilitate the analysis and reduce the number of classes, these perils can be grouped at a higher level in the breakdown structure using the concept of environment layers. Before that is done it is important to present some important concepts. Following the project perils are assumed to be associated with the internal, operational and general environments. Projects perils are, therefore, classified according to their primary source or cause and the environmental layers as:  Industries Peril Factors 1. Material Delay 2. Labor Problem 3. Equipment Break down RUNGUZU NASA KEREHUBA
  • 3. © 2014 IJIRT | Volume 1 Issue 4 | ISSN : 2349-6002 IJIRT 100070 INTERNATONAL JOURNAL OF INNOVATIVE RESEARCH IN TECHNOLOGY 63 4. Estimator Error 5. Management faux pas 6. Flaw Construction 7. Finance  Catholic Peril Factors 1. Environmental Issue 2. Economic 3. Political Issue 4. Competition 5. Project/Design 6. Construction 7. Estimation 8. Scheduling  Acts Of God 1. Heavy Floods; 2. Massive Landslides; 3. Earthquakes, And 4. Others. IV. CONVENANT KNACKS FOR PERIL PERSONATING AND DISSECTION The kinds of perils that permeate construction of road projects have been presented and briefly described. Project managers have been confronted with the choice of right peril analysis knack. It is important for a manager for choosing appropriate knacks for different kind of peril as Acts of Gods peril modeling is not smellier to the model of industries specific peril. Though the outcome is linear but the sources are different. To substantiate the above parameter of peril, the dissection used is apropos commencing. The analysis is expected to shed some light on the diversity of modeling and analysis perspectives as well as their effectiveness. V. PROBABILISTIC ANALYSIS KNACK Probability analysis tools one of the most sophisticated methods of identifying the construction peril. As such, probabilistic modeling and analysis has been the prominent way to handle perils regardless their nature. Probability is a mathematics deals with random variables. As such, it deals with stochastic processes and events through frequents, outcomes of repeated experiments, and subjective views. Probability theory has been widely used to model precisely described, repetitive experiments with observable but uncertain outcomes. Normal distribution is one of the tools to finding out the uncertainty of landslides occurrence etc. Fig.3 shows the landslide occurrence or not occurrence. Fig. 3 Normal distribution curve VI. INDUSTRIES PERILS A more disciplined process involves using checklists of potential perils and evaluating the likelihood that those events might happen on the project. Some companies and industries develop peril checklists based on experience from past projects. These checklists can be helpful to the project manager and project team in identifying both specific perils on the checklist and expanding the thinking of the team. The past experience of the project team, project experience within the company, and experts in the industry can be valuable resources for identifying potential peril on a project. Identifying the sources of peril by category is another method for exploring potential peril on a project. Some examples of categories for potential perils include the following: 1. Technical 2. Cost 3. Schedule 4. Client 5. Contractual 6. Weather 7. Financial 8. Political 9. Environmental 10. People The people category can be subdivided into perils associated with the people. Examples of people perils include the peril of not finding the skills needed to execute the project or the sudden unavailability of key people on the project. David Hillson [1] uses the same framework as the work breakdown structure (WBS) for developing a peril breakdown structure (RBS). A peril breakdown structure organizes the perils that have been identified into categories using a table with increasing levels of detail to the right. Industries perils are related to the internal environment of industries and these are supposed to manage them. Industries level of knowledge about the operations is significantly higher than other type of peril. Indeed, issues such as planning, finance, human resources, equipment and materials logistics are dealt with on a daily basis. Industries can conduct operations studies in order to build robust databases 0 0.05 0.1 0.15 0.2 0.25 0 5 10 15 20
  • 4. © 2014 IJIRT | Volume 1 Issue 4 | ISSN : 2349-6002 IJIRT 100070 INTERNATONAL JOURNAL OF INNOVATIVE RESEARCH IN TECHNOLOGY 64 and learn systematically. Very often databases are used as a means for routine programmed decision king. The large quantity of information obtained in this way can be retrieved in order to make probabilistic estimates. For example, important aspects such as labor productivity and cost can be estimated in probabilistic terms in the planning process through probability distributions. From this point of view, it appears that probabilistic modeling and analysis is suitable for this kind of perils. As a great deal of knowledge is available, predictions about the likelihood and impacts of perils can be made with some degree of certainty. The prominent uncertainty associated with industries related perils is assumed to be eminently random. In term of tools, simulation and analytical models can be utilized for peril modeling analysis. One of the most effective tools for this purpose would be Decision Support Systems – DSS, which are computer information systems that provide information in a given domain of application by means of analytical decision models and databases, in order to support a decision making in complex and ill structured problems. VII. GLOBAL PERIL FACTORS Global peril factors are beyond industries’ control. They relate to a more complex, erratic and dynamic environment. As such, the possibility for collecting data and information in order to draw useful lessons becomes limited. Even taking into account the cyclic nature of some factors such as economy ups and downs, it is very difficult to make reasonable estimates about them. Although there have some attempts to estimate the degree of peril associated with global perils the amount of available data make the exercise difficult. An example of probabilistic modeling applied to global peril factors is the production of political peril indices covering a large number of countries around the world as explained by Bremmer9. The exercise has been conducted and the results marketed systematically over the years. The indices measure the stability perception over specific countries and aim to help investors and other interested parties in their business decision making. Political variables are complex and dynamic and, as consequence, very difficult to grasp. In general, political phenomena are rarely repetitive, which creates serious challenges for effective modeling. The same applies to the economic and social variables. Furthermore, political, economic and social events are rarely mutually exclusive, exhaustive and conditionally independent. First, there have been strong interrelationships among these variables. Economy, for example, is strongly associated with social and political events. In the light of these characteristics it can be concluded that probabilistic modeling of global peril factors poses serious challenges in terms of robustness and validity. The uncertainty inherent in this group of peril factors is much more epistemic rather than random. VIII. ACTS OF GOD Acts of God are generally classified as ‘’force majeure’’ under the contractual terms, because no party is supposed to be able to manage them and, consequently, bear the associated costs. They represent extreme events stemming from nature and, as such, tremendously difficult to predict. It would be important for a contractor, for example, to know the likelihood of an earthquake striking and disrupting construction works. Unfortunately, such estimates are not available. That is the reason why the best response strategy to this type of peril has been transfer to a third party. Attempts have been made to predict the probability of occurrence of these events, but very little progress has been achieved so far. Concerns over the problem have led analysts to develop some probabilistic models but, it should recognized, these can hardly be robust due to prevailing nature of uncertainty. Therefore, such estimates may be precise but not accurate. In addition, since most nature related peril factors are poorly defined and fuzzy in nature they cannot be evaluated with such high precision inherent in numerical expressions. These models have used subjective probabilities instead of objective ones, as the latter are difficult to obtain due to lack of data. The fact that subjective probabilities cannot be distinguished from objective ones once in the model, is likely to hinder the quality of the analysis. There is guarantee that subjective probabilities capture uncertainty effectively. As a result, probabilistic modeling and analysis of nature related perils is debatable. IX. CERTAINTY THEORY ANALYSIS KNACK GLOBAL PERIL FACTORS AND ACTS OF GOD As previously shown, while industries related peril factors can be well modeled through probabilistic means, global perils and Acts of God are far more difficult to handle in the same way due to the inherent kind of uncertainty and scarcity of data and information. MYCIN (an expert system for the diagnosis and therapy of blood infections and meningitis) introduced certainty factors theory, based on belief MB(H, E) and disbelief MD(H, E). These functions indicate the degree to which a belief/disbelief in hypothesis H would be increased by observing E. MB(H, E) = ( 1 if p(H) = 1 max[p(H|E),p(H)]−p(H) max[1,0]−p(H) otherwise (11) MD(H, E) = ( 1 if p(H) = 0
  • 5. © 2014 IJIRT | Volume 1 Issue 4 | ISSN : 2349-6002 IJIRT 100070 INTERNATONAL JOURNAL OF INNOVATIVE RESEARCH IN TECHNOLOGY 65 min[p(H|E),p(H)]−p(H) min[1,0]−p(H) otherwise (12) To determine the total strength of belief or disbelief, we use the following equation: cf = MB(H, E) − MD(H, E) 1 − min[MB(H, E), MD(H, E)]. (13) Certainty theory is mainly a theory for handling uncertainty in knowledge based systems KBSs. It was developed in attempt to overcome some of the weaknesses of the so called idiot Bayes approaches for inexact reasoning, according to Duda.10 Certainty theory relies on defining judgmental measures of belief rather than adhering to strict probability estimates. Therefore, certainty factors (CF) are not probabilities but informal measures of confidence for a piece of evidence. They represent the degree to which peoplebelieve that the given evidence is true. In other words, they express how accurate, reliable, truthful people judge statements or evidences. Certainty theory fundamentals are the concepts of certainty measures which are associated with factual statements .The certainty measures or factors CFs consist of numbers ranging from –1 to +1 and factual statements, (rules). A negative value of the certainty factor indicates that one believes that a fact is not true and a positive value indicates the one believes that a fact is true with complete knowledge. CF = 1, there is complete certainty that a proposition is true CF = 1, there is complete certainty that a proposition is false CF = 0, there is no information at all about or no change in belief 1 < CF < 1, measure of the degree of belief about the proposition with decreasing and increasing beliefs respectively. Global peril factors and Acts of God in engineering projects can be modeled using CFs within knowledge based systems, where the following format is common: If A Then B with certainty factor CF = CF (rule), where A is the antecedent and B, the consequent. The antecedent comprises facts (evidence) that support the derivation of the consequent (hypothesis). The CF is the net degree of belief in hypothesis, given that the evidence is observed (given). For example: If the rate of inflation increases then the prices will be high CF = 1, where the rate of inflation increases is the evidence and the prices will be high is the consequence. The degree of belief associated with the rule is 1, which means the analyst is 100% sure. X. DEMPSTER SHAFER THEORY OF EVIDENCE ANALYSIS KNACK The Dempster Shafer theory is based on two ideas: the idea of obtaining degrees of belief for one question from subjective probabilities for a related question, and Dumpster’s rule for combining such degrees of belief when they are based on independent items of evidence. To illustrate the idea of obtaining degrees of belief for one question from subjective probabilities for another, suppose I have subjective probabilities for the reliability of my friend Betty. My probability that she is reliable is 0.9, and my probability that she is unreliable is 0.1. Suppose she tells me a limb fell on my car. This statement, which must true if she is reliable, is not necessarily false if she is unreliable. So her testimony alone justifies a 0.9 degree of belief that a limb fell on my car, but only a zero degree of belief (not a 0.1 degree of belief) that no limb fell on my car. This zero does not mean that I am sure that no limb fell on my car, as a zero probability would; it merely means that Betty's testimony gives me no reason to believe that no limb fell on my car. The 0.9 and the zero together constitute a belief function. XI. SUMMARY OF THE KNACKS The strengths and weaknesses of the knacks that have been discussed are summarized in Table 1. For each of therefore peril analysis knacks, the evaluation of type of peril, prominent uncertainty and tools to be employed are shown. Sr.No. Technique Modeling and Analysis Suitability Peril Groups Probability of UncertaintyIndustry (A) Global (B) Acts of God(C) 1 Probablity Very Good Very poor Very poor Random A 2 Certainty Factor Very poor Good Good Epistemic B & C 3 Dempster_Shaffer Poor Good Good Epistemic B & C Table 1 : Summary of peril analysis techniques and tools. The indications provided in the table constitute a guide on what a specific knack can help to manage. For example, probabilistic modeling can be effectively to model industries specific and global perils factors where the underlying uncertainty is mainly random. For that purpose Decision Support Systems DSS seem to be the most appropriate tools. On the other hand, probabilistic modeling is very poor in tackling natural events or Acts of God as data for these is scarce and frequently unavailable. The
  • 6. © 2014 IJIRT | Volume 1 Issue 4 | ISSN : 2349-6002 IJIRT 100070 INTERNATONAL JOURNAL OF INNOVATIVE RESEARCH IN TECHNOLOGY 66 same procedure is followed with regard to other peril analysis knacks. XII. CONCLUSIONS The importance of managing construction of road project engineering peril factors has been discussed. An extensive analysis of construction projects implementation with emphasis on cost performance has triggered work on peril modeling and analysis. It has been concluded that the nature of perils under consideration is determinant in the selection of modeling and analysis knacks. As it has been shown, not all uncertainty is random in nature. A great deal of engineering management and technical issues do not comply with randomness properties. They are mainly cognitive and thus do not lend themselves to precise measurement. Three groups of peril factors inherent in construction engineering projects have been presented and explained. It is understood that the nature of the peril factors is diverse and thus their handling requires appropriate knacks and tools. Indeed, the type uncertainty associated with each of the groups differs. While industries specific peril factors can be effectively modeled through probabilistic analysis, uncertainty underlying global and acts of god peril factors appears to be much more difficult to capture using the same approach. The uncertainty type associated with the latter peril factors derives mainly from reduced knowledge rather than natural variability. As such, epistemic uncertainty handling knacks are likely to be more effective than probabilistic approaches. Several uncertainty modeling knacks namely uncertainty theory and Dempster Shaffer Theory of Evidence have been discussed with emphasis on appropriateness and robustness. Although there is no consensus on the applicability of these knacks to bridge the gap between the ideal and feasible solutions provided by the probabilistic analysis, it appears that they can be employed for such purpose. In particular, Dempster Shafer Theory is capable of modeling epistemic uncertainty through belief and membership functions. Nevertheless, research is required to ascertain the extent to which these and additional knacks can be applied to improve construction engineering perils modeling and analysis. REFERENCES 1. David Hillson, “Using a Peril Breakdown Structure in Project Management,” Journal of Facilities Management 2, no. 1 (2003): 85–97. 2. Thompson, P. and Perry, J., Engineering Construction Perils. A Guide to Project Peril Analysis and Peril Management. (London: Thomas Telford. 1992). 3. Dempster, A.P. (1968). A generalization of Bayesian inference. Journal of the Royal Statistical Society, Series B 30 205247. 4. Shafer, Glenn (1976). A Mathematical Theory of Evidence. Princeton University Press. 5. DempsterShafer Theory By Glenn Shafer Ronald G. Harper Distinguished Professor of Business, School of Business, Summerfield Hall, University of Kansas, Lawrence, Kansas 66045. 6. Flanagan, R and Norman, G., Peril Management and Construction. (London: Blackwell. 1993) 7. Helton,, J Uncertainty and sensitivity analysis in the presence of stochastic and subjective uncertainty. “Journal of Statistical Computation and Simulation” 57: 376 (1997). 8. Klir, G. Where Do We Stand on Measures of Uncertainty, Ambiguity, Fuzziness and the Like?. Fuzzy Sets and Systems, 1987, 24, pp.141160. 9. Van Gelder, P.H.A.J.M., "Statistical Methods for the Peril Based Design of Civil Structures", 2000, Communications on Hydraulic and Geotechnical Engineering, ISSN:0169654800 1, 248pages. 10. Zadeh, L. A., Fuzzy Sets. Information and Control, 1965, 8, pp.338353. 11. Uher, T., Probabilistic Estimating. Cost Engineering, 1996, 38(4), pp. 3340. 12. Ian Bremmer, “How to Calculate Political Peril,” Inc. Magazine, April 2007, p. 101 13. Duda, R. O. et al Development of PROSPECTOR System for Mineral Exploration. Final Report, SRI Projects 5821 and 6415, (Menlo Park, CA, 1979). 14. Wang, G.Q, Jia, X. L (2005).Peril Management on the BOT Investment and Financing Mode, India Water & Wastewater,21(9):8588. 15. Project Management Institute. Construction extension to the PMBOKR Guide.3rd ed. Newtown Square: Project Management Institute;2007. 16. Institution of Civil Engineers and the Actuarial Profession. Peril analysis and management for projects (RAMP). 2nd ed. Institute of Civil Engineers and the Actuarial Profession. London: Thomas Telford Ltd; 2005.