・As JAXA design/manufacturing facility, JAXA requires the manufacturing contractors to make the reliability program standards and to execute the reliability activities defined by those standards.
・
・
・
・
・
【Point】
・The basis of this "Manage" and "Control" is Safety and Mission Assurance.
・5 Management.
【Explanation and Other Information】
Project Management Process is the process for management and control to support development process, and to manage and control the development process of the project based on various management/ control plans as specified in aforementioned “Project Management”
The basis of this "Manage" and "Control" is Safety and Mission Assurance. That is, safety assurance is the major premise for Mission Success.
In Controlling Process, the followings shall be performed under the above circumstances.
① Reliability Program ② Quality Management
③ Configuration Management ④ Safety Management
⑤ Risk Management
【Point】
Reliability Program
【Explanation and Other Information】
・What is Reliability?
The probability that a system of hardware, software, and human elements will function as intended over a specified period of time under specified environmental conditions. (See NASA-STD-0809.22)
・What is Reliability Program?
Reliability Program is the activities related to following three items in order to ensure the Reliability (See JMR-004B)
① Reliability Program Management
② Reliability Engineering
③ Tests and Reliability Evaluation
【Point】
Reliability Program Management
【Explanation and Other Information】
・Reliability Program Management is the following activities related to Reliability Program operation.
(1) Organization
In order to ensure the independency of the Reliability Program function, Reliability Program organization in project organization is functionally independent from the operating section such as designing, producing and testing. The top of the organization should have proper authority and resources (money, talent) necessary to carry out his responsibility.
(2) Reliability Program Plan
In order to meet the requirements of the Reliability program specified in the contract, the reliability program shall be created and maintained, and the actual program shall be carried out.
(3) Promotion and Surveillance
Promote and audit the reliability activities defined in reliability program plan.
(4)Education and Training
In order to meet the requirements of the Reliability program, the staff who are involved in the reliability program activities shall be educated and trained.
【Point】
Reliability Engineering
【Explanation and Other Information】
Reliability Engineering is technical activities which ensure the reliability itself.
These activities apply the entire life-cycle from the initial phase of the project to production/testing, launching and operation.
Basic concept of reliability design: Contractor shall pursue to decrease the failure risk to the allowable level according to the importance and severity of a failure’s influence on the system.
Standardization of design practice: Contractor should use existing standards or specifications when the use of those standards or specifications is considered more economical and effective, after necessary modifications are made to comply with the reliability, quality, and other requirements specified in the contract.
【Point】
Reliability Engineering
【Explanation and Other Information】
The main and typical activities are as follows.
①Preparation and maintenance of Design specification
②Reliability Prediction
③FMEA(Fault Mode Effect Analysis)
④Identification of Reliability Control Items
⑤Stress Analysis for parts
⑥Worst-case Analysis
⑦FTA(Fault Tree Analysis)
⑧Design Review
【Point】
①Preparation and maintenance of Design specification
【Explanation and Other Information】
The design specification is a document which contents are broken down for specific designing based on the development specification, and includes the followings.
Requirements related to performances, operations and environments.
Requirements for the test under the specified stress level.
Design margin/Derating factor
Reliability requirements in quality and in quantity under the specified environments.
This specification should be prepared in the initial phase of the development and kept up-to-date in each phase.
【Point】
・Why you need Reliability Program?
・Reliability Function: R(t)
【Explanation and Other Information】
・You can not repair or maintain the satellite on orbit.
・The satellite should work for the expected period of time.
・You must decide the end of life's survival probability of the satellite.
・Bath-tub Curve
・Failure rate : λ(t)
・60% after 5years (If you launched 100 satellites, you lost 40 satellites after 5years )
【Point】
Reliability Prediction
【Explanation and Other Information】
・Typical reliability prediction models
・ Serial model, parallel model, complex model
・ Calculation method
【Point】
FMEA、FMECA
【Explanation and Other Information】
・FMEA(Fault Mode Effect Analysis)、FMECA(Fault Mode Effect and Criticality Analysis)
The possible failure mode of elements in the early phase of designing and the influence rate which the failure may affect the target mission shall be analyzed (Bottom up failure detection).
The purpose of the analyze is for the designer or the designing section to eliminate the critical design failure mode based on the analyzed results.
Single point failure, critical items and critical characteristics shall be identified, and recovery plans shall be established.
【Point】
Example of FMEA worksheet
【Explanation and Other Information】
This worksheet is shown in ECSS-Q-ST-30-02C, Failure modes, effects (and criticality) analysis.
Key word: failure mode, failure cause, failure effect, Severity classification
【Point】
Identification of Reliability Control Items
【Explanation and Other Information】
・Identification of CIL: To ensure the reliability, important characteristics to be controlled shall be identified at each phase of production, inspection, test, maintenance and operation, and listed and managed as Critical Item List (CIL) and/or Reliability Critical Item (RCI).
・RCI:parts defined fixed time of usage, parts defined fixed time of stock, Critical attachment,
parts defined operation duration, and so on.
【Point】
Stress Analysis for Parts, Worst-case Analysis
【Explanation and Other Information】
Stress Analysis for Parts :
For use of EEE Parts (Electrical Electronic and Electromechanical parts) used for electrical circuits, the applied stress in the required environmental conditions and operational conditions shall be analyzed to determine whether the parts could withhold the stress.
Worst-case Analysis :
For the design characteristic values with possible performance deterioration during the mission, the worst-case environmental conditions such as aging variation, temperature and radiation during the mission shall be analyzed to determine whether there are appropriate design margins.
【Point】
FTA(Fault Tree Analysis)
【Explanation and Other Information】
・Prior analysis:
A potential important failure mode shall be selected as a top (the treetop) event and deployed into developmental pathways to identify the ultimate root event and examine the probability of occurrence, etc. The objective of this analysis is to reflect the results in design optimization, manufacturing/testing plan and operation.
・Post analysis:
Post analysis is performed to determine the nonconformance occurrence route, and reflect the results through remedial actions and countermeasures.
【Point】
Example of FTA
【Explanation and Other Information】
【Point】
Design Review
【Explanation and Other Information】
Objectives:
To ensure that the development model complies with all the development specifications and design specifications.
Review documents:
Design and analysis reports, drawings, compliance matrix to requirements and etc.
Review meeting:PDR, CDR, PQR and etc.
The Reliability Program organization and related departments shall ensure the accuracy and completeness of the design review reports. The Reliability Program organization shall also follow up on action items to confirm their satisfactory completion.
【Point】
Testing and reliability assessment
【Explanation and Other Information】
To ensure the compliance of the items which are manufactured on the base of the design specifications to requirements in design specifications and to evaluate their reliabilities. This is imperative verification activity to confirm the availability as the flight items.
(1)Preparation of reliability assessment plan:
Means of verification(test, inspection, analysis, etc.) of compliance to requirements in design specification, Reliability analysis, CIL/RCI.
(2)Test plan:
Verification of function, performance, durability of the item under the variety of the environment loads, and etc.
【Point】
Quality Management Program
【Explanation and Other Information】
・What is Quality Management?
Quality Management is various process and tasks to improve the quality where the production process is managed to see if it is properly operated. (See JAXA Quality Program Standard JAXA-JMR-005A)
(1) Planning of Quality Assurance Program
(2) Technical Management
(3) Identification and Search
(4) Purchase Management
(5) Production Management
(6) Inspection and Test
(7) Non-conformance Management
(8) Record of Items
(9) Measurement Management
(10) Marking of Item Conditions
(11) Stamp Management
(12) Establishment of Procedure, Documentation and Implementation
・QMS(Quality Management System) in space industry is carried on according to the
standard AS/EN/JIS Q 9100 established by IAQG society, which consists on the general contractor in aeronautics and astronautics field.
【Point】
Planning of Quality Assurance Program
【Explanation and Other Information】
(1)Planning of Quality Assurance Program
Plans for organization, quality record, quality information report, quality review, education and training shall be clarified in Quality Assurance Program.
Especially, organization shall be functionally independent from the operational sections such as design, production and testing in order to ensure the independency of the quality management function.
【Point】
Technical Management
【Explanation and Other Information】
(2) Technical Management
The technical documents (preparation, maintenance and review) and changes to the technical contents of designing, production, testing and inspections shall be properly managed.
The suitably assigned role for quality assurance section in each review board shall be required.
( Technical documents)
Technical instruction documents such as specifications, design documents, plans, and drawings.
Fabrication instruction documents such as process charts, work standards and written procedures.
【Point】
Identification and Search
【Explanation and Other Information】
(3) Identification and Search
Implementation of identification methods such as part number, dating code, lot number and serial number, etc. for products and management of IDs and ensuring of traceability shall be performed.
Establishment and maintenance of the management system which could look up the specific component by identification within the identification list are required as well as the preparation of identification list based on the identification method.
(Traceability)
Quality assurance records on the articles and materials shall identify the part or type number to ensure their traceability to show parts or materials used in fabrication, as well as to show locations of the same article models and materials used in the same fabrication process or in the same assembly.
【Point】
Purchase Management
【Explanation and Other Information】
(4) Purchase Management
Purchase Management is activities related to selection of contractor, review of purchased documents, quality assurance activities for contractors and acceptance inspection.
Confirmation using records that include previous qualitative and quantitative information that will ensure the quality of articles and materials being procured or of a similar article-type being procured.
Implementation of a pre-order survey of the supplier’s facility and quality assurance system, as well as the status of the quality assurance to determine if the supplier is capable of satisfying quality requirements regarding articles and materials based on the contract and the quality assurance program requirements, or, confirmation using survey records conducted by the official certification organization.
【Point】
Production Management
【Explanation and Other Information】
(5) Production Management
Production Management is activities to record production process, evaluate the quality at each process (detecting abnormality by data monitoring), manage the items and goods to be included in the production instruction document and establish and maintain the production process.
Record the fabrication tasks:1)monitor the important quality characteristics and important processing parameters of the critical items per the Reliability Program and maintain these records. 2)compared to previous similar items.
Fabrication instructions:Nomenclature and identification number of the article/fabrication equipment/Characteristics and tolerance/procedures for controlling processes/etc
【Point】
Inspection and Test
【Explanation and Other Information】
(6) Inspection and Test
Inspection and Test are the activities to plan the tests and to prepare test specification, inspection procedure and records as quality assurance section.
Quality assurance activity at test
Task briefing meeting before testing, Joint confirmation in testing and task review meeting after testing.
【Point】
Non- conformance Management
【Explanation and Other Information】
(7)Non- conformance Management
For identification, separation, and corrective actions in the case of non-conformance products, establishment and maintenance of proper corrective system shall be required.
Investigation of the cause, analysis, being handled by Material Review Board (MRB) and corrective actions shall be specified.
・PR-1:The designated board member of the quality assurance shall review the noncompliance and select the disposition.
Preliminary Review 1-rework, Scrap, Return to suppliers, Submission to PR-2
・PR-2:The designated QA member and the engineer responsible for designing shall review and select the disposition.
Preliminary Review 2rework, repair, Scrap, use as is, Return to suppliers
・MRB:Representatives of QA and engineering section, and JAXA inspector shall review and select the disposition.
MRB rework, repair, Scrap, use as is, Return to suppliers, Propose to customer
【Point】
Record of Items & Measurement Management
【Explanation and Other Information】
(8)Record of Items
For the history or traceability of items, recording of the data of a series of operations from production, testing, inspection to corrective actions shall be required.
(9)Measurement Management
To assure the objectivity of the results of the test and inspection, acceptance, evaluation, modification and recording of the measuring devices or equipment shall be specified.
・Document Package
Document Package shall be attached to the shipping product, which consists of the equipment log, the list of components with limitted life, the noncompliance historical log, the records of inspection and testing and so on.