Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Rbi masterclass fleming summit_ss
1. Saudi Aramco: Company General Use
Risk Based Inspection or RBI
1
Ganesh Smart
Ganesh.smart@outlook.com
Australia
2. Saudi Aramco: Company General Use
2
AGENDA
Introduction of RBI
Workflow
Data Analysis
Assessments
Reporting
RISK BASED INSPECTION
3. Saudi Aramco: Company General Use
3
WHY DO WE NEED RBI?
Many codes/standards based on LOF, not COF
Reduce risk of high consequence failures
Cost effective inspection and maintenance resources
Shifts resources from lower to higher risk equipment
Measure and understand the risks
Measure risk reduction as a result of inspection practices
4. Saudi Aramco: Company General Use
4
OBJECTIVES
Determine the purpose of RBI
Appreciate the benefits of RBI
Understand the workflow and process
Manage and execute an RBI program
Analyze, interpret and report results
Create inspection/equipment plans
Influence maintenance and turnarounds
5. Saudi Aramco: Company General Use
5
TEAM OBJECTIVES
•Tailor to plant operations
•RBI (Risk Based Inspection) of Pressure
Equipment to Avoid
Failure of Plant
Endangering personnel
Environmental damage
Business interruption losses
Property damage
6. Saudi Aramco: Company General Use
6
WHAT IS RBI?
•Risk Based Inspection (API RP 580)
• A risk assessment and management process that is focused on loss of
containment of pressurized equipment in processing facilities, due to material
deterioration. These risks are managed primarily through equipment
inspection.
•Other Definitions:
Strategic process for lowering risk and costs
Manages equipment integrity
Establishes risk levels for equipment
Addresses life cycle value of equipment
Time based to condition based inspection
Optimizes inspection/maintenance
7. Saudi Aramco: Company General Use
7
RISK BASED INSPECTIONS
IDENTIFY AND QUANTIFY THE RISK:
Risks considered are:
* Safety
* Environmental
* Business
The inspection is planned to reduce the risk based on
the factors creating the risk.
LIKELIHOOD
OF EVENT
X CONSEQUENCE = RISK
8. Saudi Aramco: Company General Use
How RBI Works
• The LOF assessment indicates the damage mechanism, typical
locations and rate of development. The damage mechanism indicates
what inspection techniques should be used.
8
9. Saudi Aramco: Company General Use
RBI Deliverable
9
Being risk based, the method requires consideration of both the probability of failure as well
as the consequences associated with failure. The methodology can be applied to process
equipment, structures and pipelines.
The main deliverable of an RBI study is an “ Inspection Programme” describing:
11. Saudi Aramco: Company General Use
11
INDUSTRY TRENDS TROUBLING
Capacity creep in most process facilities
Operating older plants without major replacements.
Major losses are now dominated by mechanical (also
includes corrosion) failures.
Move towards legislation based on risk criteria.
12. Saudi Aramco: Company General Use
12
RBI Motivator
A large percent of the total
unit risk is concentrated in a
small percent of the
equipment items.
13. Saudi Aramco: Company General Use
13
STEPS
Screen operating units to identify critical areas
Estimate risk value for each equipment
Prioritize equipment based on risk
Create useful equipment inspection plans.
Design an optimum inspection program
Manage risk of equipment failures
Reduce likelihood of failures
Review consequences of failures
Demonstrate cost benefit to the plants
RBI Ever greening
14. Saudi Aramco: Company General Use
14
WHAT IS RISK?
Dictionaries define risk as the chance of a loss. This portrays risk as a
probability.
Chronic risk is ongoing, long term, low level doses of a potentially
hazardous substance.
Acute risk is short term, high intensity events that can cause severe
consequences.
RBI focuses on acute risk.
•API 580 defines:
Risk: Combination of the probability of an event and its consequence. In
some situations, risk is a deviation from the expected. When
probability and consequence are expressed numerically, risk is the
product.
15. Saudi Aramco: Company General Use
15
WHERE RBI / INSPECTION HELPS
Mechanical
Failure
41%
Process Upset
8%
Sabotage/Arson
3%
Unknown
18%Operational
Error
20%
Design Error
4%
Natural Hazard
6%
About half of the
containment
losses in a
typical
petrrochemical
process plant
can be
influenced by
inspection
activities
17. Saudi Aramco: Company General Use
17
RISK ACCEPTABILITY
ACCEPTABLE – No requirement for additional activities based on current
inspection strategy.
ACCEPTABLE WITH CONTROLS – Although risk is acceptable, additional/more
effective controls may be required.
UNDESIRABLE – Additional controls must be implemented and their effect on
reducing risk evaluated.
UNACCEPTABLE – Additional and more effective controls must be
implemented at the earliest opportunity.
18. Saudi Aramco: Company General Use
18
RISK MEASURE Eg. of Quantitative
L
i
k
e
l
i
h
o
o
d
Consequence
10-5
10-3
10-1
10-7
103 104 105
10 102
Risk = 10
Risk = 1
19. Saudi Aramco: Company General Use
19
RISK MATRIX
High Risk
Medium Risk
5
4
3
2
1
LIKELIHOOD
CATEGORY
A B C D E
CONSEQUENCE CATEGORY
Low Risk
Medium Risk
Medium High Risk
High RiskMedium high Risk
23. Saudi Aramco: Company General Use
23
RISK MANAGEMENT
RISKLEVEL
AMOUNT OF INSPECTION
Uninspectable risk
Risk with typical inspection program
Risk using RBI
24. Saudi Aramco: Company General Use
24
RISK CONTROLS
Losses($)Exp.
Quantify annual expenditure spent to avoid losses
Inspection
Maintenance
Training
Procedure
Insurance
25. Saudi Aramco: Company General Use
25
REDUCE RISKS
Losses($)
Exp.
Optimise expenses to reduce loss
26. Saudi Aramco: Company General Use
26
RISK AND INSPECTION
Inspection modifies risk by control
Inspection optimization requires cost/risk analysis
Risk evaluates value of information
New technologies allow practical application of risk analysis
Probabilistic modeling
Computer simulation
Computerized databases
27. Saudi Aramco: Company General Use
27
INSPECTION COSTS & RISKS
Equipment risk is a major factor contributing to operational risk, and the maintenance strategy adopted.
Increase in inspection or maintenance intervals generally imply lower maintenance costs, but increased
“failure cost” because of higher associated probability of failure.
Optimum inspection interval defined as the having the lowest sum of maintenance and failure costs.
28. Saudi Aramco: Company General Use
28
UNINSPECTABLE RISKS
Human error
Natural disasters
External events like collisions
Secondary effects from nearby units
Deliberate acts like sabotage
Hazardous materials handling
Inspection method detectability
29. Saudi Aramco: Company General Use
29
API 580 RBI COVERS
Reactors
Pressure Vessels
Piping
Furnaces
Pumps
Compressors
Heat Exchangers
Storage Tanks
30. Saudi Aramco: Company General Use
30
API 580 RBI DOES NOT COVER
Individual Components
Instrument systems
Control systems
Electrical gear
Machinery components
Non-pressurized equipment
31. Saudi Aramco: Company General Use
31
RBI Methodologies
DNV-API 580, 581
Shell RBI
TWI – RISKWISE software
AEA Technology – Operational Critical Assessment (OCA) software
Aptech Engineering –Risk Directed Mechanical Integrity Program
(RDMIP) software
WGIM – Nexus Integrity Centre
GL Noble Denton Galiom software
Meridium APM (Asset Performance Management) Software
API RBI
BV RBeye
32. Saudi Aramco: Company General Use
32
RBI ISSUES
Resistance to Change
Inadequate Records
Lack of Resources
Risk Acceptance
KPI data
Internal versus Contractor
RBI Validation
33. Saudi Aramco: Company General Use
How do we measure Risk?
Acceptable Risk
Area
Very Low Risk
Area
High Risk
Medium-
High Risk
Medium
Risk
Low Risk
Probability
Consequence
34. Saudi Aramco: Company General Use
Sq. ft / year
PoF is expressed in frequency of occurrence
or
PoF = Number of Possible event / total number of events
or
Gff of 3.06x10-5 = 1 in 306,000 per year
Definition:
Extent to which an event is likely to occur within the time
frame under consideration.
35. Saudi Aramco: Company General Use
LOF or POF
Introduction to Probability analysis
Units of measure in POF analysis
• Definition:
Extent to which an event is likely to occur within the time frame
under consideration.
The chance that a given event will occur.
Probability = Number of Possible event / total number of events
The probability of failure used in API RBI is computed as:
Pf (t)=gff. Df(t) .Fms
35
36. Saudi Aramco: Company General Use
LOF or POF
• Generic Failure Frequency: A probability of failure developed
for specific component types based on a large population
of component data that does not include the effects of
specific damage mechanisms.
• Damage Factor: is the equipment specific adjustment factor
• Management Systems Factor: Adjusts the generic failure
frequencies for differences in process safety management
systems. The factor is derived from the results of an
evaluation of a facility or operating unit’s management
systems that affect plant risk.
36
38. Saudi Aramco: Company General Use
Damage Factor
38
• Definition:
• An adjustment factor applied to the generic
failure frequency to account for damage
mechanisms that are active in a component.
• The damage factor is determined based on the
applicable damage mechanisms.
40. Saudi Aramco: Company General Use
Management System Factor
40
• The API RBI procedure includes an evaluation
tool to assess the portions of the facility’s
management system that most directly impact the
probability of failure of a component.
• This evaluation consists of a series of interviews
with plant management, operations, inspection,
maintenance, engineering, training, and safety
personnel.
• A listing of the subjects covered in the
management systems evaluation and the weight
given to each subject is presented in next slide.
41. Saudi Aramco: Company General Use
Probability Analysis
41
The Key Concepts of RBI
RISK = Probability of Failure X
Consequence of
Failure
GFF Item DFX
Age
Damage
type/rate
Insp.
effective.
Damage area
Item repair
Other repairs
Injury
Business int.
Env. clean up
The probability of failure used in API RBI is computed as:
Pf (t)=gff. Df(t) .Fms
42. Saudi Aramco: Company General Use
Inspection and POF
42
The probability of failure can be managed....
By recognizing the types of damage that
different environments cause.
AND
By using the right inspection method at the right
location and right frequency.
AND
Addressing the mechanism before failure.
43. Saudi Aramco: Company General Use
Probability Analysis
43
It should be noted that damage mechanisms are not the
only causes of loss of containment. Other causes of loss
of containment include but are not limited to:
seismic activity,
weather extremes,
overpressure due to pressure-relief device failure,
operator error,
inadvertent substitution of materials of
construction,
design error,
Sabotage.
44. Saudi Aramco: Company General Use
Units of measure in POF analysis
• POF is typically expressed in terms of frequency.
• The time frame is typically expressed as a fixed interval.
• The frequency is expressed as events per interval.
• For a quantitative analysis, the POF may be categorized as one
through five.
45. Saudi Aramco: Company General Use
Continuous Improvement in Asset
Operations
8
Developing Maintenance,
Inspection/ Monitoring
Program