Microsoft® Project Painting Exercise
CPMGT/303 Version 11
1
University of Phoenix Material
Microsoft® Project Painting Exercise
Microsoft® Project
Microsoft® Project (also called “MS-Project”) is one of the
most popular tools for project planning projects today. It is
relatively easy to use and makes it easier to manage projects.
Microsoft® Project Exercise: The Painting Project
This is a simple exercise in Microsoft® Project. These
instructions are brief and only cover the basics. The objective of
this exercise is to prepare you for Week 3 Learning Team
assignment. This exercise only covers how to log into
Microsoft® Project, set up a simple schedule, and log out. The
exercise is not concerned with monitoring or controlling the
execution of a plan.
Start Microsoft® Project
To start Microsoft® Project; click through “Start > Programs >
Microsoft Office 2013 > Microsoft Project” Microsoft® Project
should start up, with a blank “Gantt chart” view of a new
project.
Saving Microsoft® Project
It is recommended that you save your project immediately. So
please Save your project now using the following format ‘Last
Name_Paint_Project’. If you last name is Allen, your
Microsoft® Project file name will be ‘Allen_Paint_Project’.
If you are prompted to save the project with a baseline, click
Yes. You may continue to work on the baseline until you have
completed the exercise and turned it in as the final baseline.
Microsoft® Project Settings
Before getting into the details of the Painting Project, it is
beneficial to enter a few Microsoft® Project settings. These
settings are:
· Duration Unit of Measure. The normal default for duration is
the day (day) which consist of 8 hours. There are other unit of
measures that you may decide to use. The most popular are
minute (min), hour (hr), and week (wk). For this exercise we
will use the default setting.
The working calendar. There is a default Standard Calendar
which consists of a 5-day work week (Monday through Friday)
with Saturday and Sunday set as non-working days. A day is
made up of 8 hours. It is recommended for this exercise that you
leave Microsoft® Project set to the Standard Calendar. If you
want to explore other calendars or how to set up your own
calendar, click as follows “Project > Project Information”. The
following pop up menu will appear with Calendar showing as
‘Standard’.
Available resources. It is beneficial to set up your known
resources pool at the start of the project. Note. You may change
the resources in the pool at any time, as resources are added to
and subtracted from the project. To set up the resource pool
click as follows “Resource> Resource Sheet”. You’ll get a table
in which you can define the names of resources that you wish to
be available.
Simply type a name in the “Name” field, and use a new line for
each different resource. For the Painting Project, the following
are the resources.
Jackie Smith – Standard Rate $25.00; Overtime Rate $37.00
Tom Busch – Standard Rate $20.00; Overtime Rate $30.00
Alan Jacobs – Standard Rate $15.00; Overtime Rate $22.00
Suzie Smith – Standard Rate $15.00; Overtime Rate $22.00
Paint – One time cost of $700
Paint Supplies (paint brushes and tape, drop cloth, etc.) – One
time cost of $450
Enter these in your resource sheet.
Project start or end date. When you first start developing a
schedule for a project it is useful to set up the project start or
end date. To enter this date, click as follows “Project > Project
Information”. At work you may have a project that will start in
a few weeks so you would use a project start date. If this is the
case you will select ‘Project Start Date’ in the ‘Schedule from:’
field and enter the projected project start date in the ‘Start date’
field as follows:
If you are doing a project for a wedding or an event, the project
would have an end date; the date the event will occur. If this is
the case you will select ‘Project End Date’ in the ‘Schedule
from:’ field and enter the desired project end date in the ‘Finish
date’ field as follows:
For the Paint Project, select Project Start Date and enter June
21, 2014.
Creating Tasks (aka activities). When you start Microsoft®
Project, by default you’ll see a blank Gantt chart. The first three
columns (on the left) are headed “”, “Task Mode”, “Task Name”
and “Task Duration”. To enter the tasks, work down the third
column, entering Task Name and pressing the Down Arrow key
(↓) at the end of each entry.
Note. Microsoft® Project assigns each task a Task ID or line #
and inserted a default duration of 1 day for each task. Do not
worry about this duration at this point in time.
Creating work packages and subtasks. Just like outlining a
report in Microsoft® Word, or a presentation in Microsoft®
PowerPoint®, you can outline a project’s tasks. There are
several ways of doing this, but here’s just one.
· First (outside of the software), write down your tasks, grouped
under headings that describe their intended effect. These
headings are called “Work packages”. For example, the Paint
Project consist of several work packages:
Painting bedroom and bathroom
Purchase paint and materials
Prep rooms for painting
Paint rooms
Clean up paint items
· These work packages are then expressed in detail as sets of
subtasks, as follows:
Painting bedroom and bathroom
Purchase paint and materials
Drive to paint store
Select paint and materials
Purchase paint and materials
Drive back and put paint and materials at house
Purchase of paint materials complete
Prep rooms for painting
Remove any furniture that is in the way
Tape off any fixtures that will not be removed; covering so
paint does not get on them
Place drop cloths in appropriate areas
Inspect to make sure all surfaces not requiring paint are covered
adequately
Prep rooms for painting complete
Paint rooms
Paint bedroom
Paint bathroom
Let paint dry
Paint room complete
Clean up paint items
Pick up drop cloths and dispose of them
Remove tape form any fixtures and dispose of tape
Place furniture back where required
Clean up items complete
· To achieve this effect in Microsoft® Project, enter all the
tasks, grouping them together under their work package. Then
use the “Indent” function (the icon) to make the subtasks part of
the work package by moving them to the right. Note how the
task immediately above the indented one changes to work
package, or summary tasks, with a bold font. When you indent a
task, it becomes a subtask of the next “un-indented” task (work
package) above it. You may also “outdent” using the icon.
This indenting to form work packages is extremely useful to
control how projects are displayed. By expanding and
collapsing a Work package, you can show or hide subtasks to
show just the level of detail you want.
You can select multiple tasks (shift-click) before indenting.
· Enter the Paint Project Work Packages and Subtasks. Once
you have entered these items it is recommend that you set
Microsoft Project to Auto-Schedule which allows Microsoft
Project to calculate the task start and end dates for you. To set
each work package and subtask to auto schedule highlight each
and then click on Auto Schedule.
When done your Gantt Chart should look as follows:
Linking Tasks
You should understand the concept of linkage or precedence —
in other words, which activities need to finish before others can
start (like putting on socks before putting on shoes before tying
laces). It is easy to create the commonest type of linkage — FS,
or Finish-to-Start — between them. Simply:
With the left mouse button, select the earlier activity.
Hold down the ‘Control’ (or ‘Ctrl’) key
Select the later activity and release the left mouse button and
control key
Click the ‘Link tasks’ icon (it looks like a chain).
You should see the later activity’s duration bar get pushed to
the right, and its left end will align with the right end of the
earlier one. An arrow will appear showing the link.
General rule
Never link work packages themselves — always expand both
work packages first and specify linkages between specific
activities.
Link the tasks as they could occur, regardless of resources, in
the Paint Project. When complete, your file should look as
follows:
Note: Removing any furniture that is in the way does not have
to wait for delivery of paint and paint supplies, but Taping off
any fixtures or placing drop cloths does have to wait, so those
tasks are linked to a purchase of paint and material task.
Assigning Resources to Tasks
Now it is time to use the resources that you set up. To assign a
resource to a task, go to the Gantt chart and, on the task line
item. Click on the resource name column. A pop up menu
should appear with the list of the resources in your resource
pool.
Simply select the correct resource and move to the next sub
task. Work packages are not assigned resources. For the Paint
Project, the following resource are to be assigned to each
subtask.
Task Name
Task Resource(s) to be assigned
Drive to paint store
Alan Jacobs
Select paint and materials
Alan Jacobs
Purchase paint and material
Alan Jacobs; Paint; Paint supplies
Drive back and put paint and materials at house
Alan Jacobs
Remove any furniture that is in the way
Tom Busch
Tape off any fixtures that will not be removed
Suzie Smith
Place drop cloths in appropriate areas
Suzie Smith
Inspect to make sure all surfaces are covered adequately
Suzie Smith
Paint bedroom
Jackie Smith
Paint bathroom
Jackie Smith
Pick up drop cloths and dispose of them
Suzie Smith
Remove tape from any fixtures and dispose of tape
Suzie Smith
Place furniture back where required
Tom Busch
Assigning Task Duration
Now you can work with our resources to determine the duration
of each of their assigned tasks. Once durations have been agreed
to you will input that into Microsoft Project. To input the
durations, click in the “Duration” box for each task and specify
its duration and time unit (min, hr, day or wk). The agreed to
durations for the Paint Project are as follows:
Task Name
Task Agreed to Duration
Drive to paint store
1 hr
Select paint and materials
6 hr
Purchase paint and material
45 min
Drive back and put paint and materials at house
1 hr
Purchase paint and materials complete
0 day
Remove any furniture that is in the way
2 hr
Tape off any fixtures that will not be removed
6 hr
Place drop cloths in appropriate areas
1 hr
Inspect to make sure all surfaces are covered adequately
1 hr
Prep rooms for painting complete
0 day
Paint bedroom
1 day
Paint bathroom
4 hr
Let paint dry
1 day
Paint rooms complete
0 day
Pick up drop cloths and dispose of them
1 hr
Remove tape from any fixtures and dispose of tape
4 hr
Place furniture back where required
1 hr
Clean up paint items complete
0 day
Upon entering these durations, you should see Jackie Smith as
an over-allocated resource.
If Jackie is the only painter available then the resource must be
leveled so that Jackie is not working a 12 hour day and getting
paid overtime. To level resources in Microsoft® Project go to
‘Resource’ tab and click on Level Resource. Then select Jackie
Smith and click on level now.
Scheduling a project – determining duration and the critical
path
By default, the Gantt chart shows what is happening in the
project. With the Gantt chart open, click the Format tab and
notice the Critical Tasks checkbox.
If you check the box, Microsoft® Project will show you the
Critical Path highlighted in red as follows.
At this point you have completed the Paint Project Exercise.
Save the file and submit in the Assessments Tab.
Copyright © 2018, 2016, 2014 by University of Phoenix. All
rights reserved.
Project Estimating and Control Techniques Grading Guide
CPMGT/303 Version 11
3
Microsoft® Project Painting Exercise and Executive Summary
Grading Guide
CPMGT/303 Version 11
Project Estimating and Control Techniques
Copyright
Copyright © 2018, 2016 by University of Phoenix. All rights
reserved.
University of Phoenix® is a registered trademark of Apollo
Group, Inc. in the United States and/or other countries.
Microsoft®, Windows®, and Windows NT® are registered
trademarks of Microsoft Corporation in the United States and/or
other countries. All other company and product names are
trademarks or registered trademarks of their respective
companies. Use of these marks is not intended to imply
endorsement, sponsorship, or affiliation.
Edited in accordance with University of Phoenix® editorial
standards and practices.
Individual Assignment: Project Estimating and Control
Techniques
Purpose of Assignment
Students use the University of Phoenix Library to research
Critical Path and then follow the Exercise instructions to
complete the Paint exercise in MS Project. An executive
summary is then prepared to discuss how the Critical Path was
determined and what lessons they learned in completing this
assignment.
Resources Required
Microsoft® Project Student Desktop
Microsoft® Project Painting Exercise WorksheetGrading Guide
Content
Met
Partially Met
Not Met
Comments:
The student searches the UOP Library for the Critical Path
Method.
The student uses Microsoft® Project to complete the
Microsoft® Project Painting Exercise.
The student includes the primary deliverables and the activities
associated with them in the Microsoft Project Schedule.
The student writes an Executive Summary describing the
process used for finding the critical path in Microsoft® Project,
and lessons learned while completing the Painting Exercise.
Total Available
Total Earned
7
#/7
Writing Guidelines
Met
Partially Met
Not Met
Comments:
The paper—including tables and graphs, headings, title page,
and reference page—is consistent with APA formatting
guidelines and meets course-level requirements.
Intellectual property is recognized with in-text citations and a
reference page.
Paragraph and sentence transitions are present, logical, and
maintain the flow throughout the paper.
Sentences are complete, clear, and concise.
Rules of grammar and usage are followed including spelling and
punctuation.
Total Available
Total Earned
3
#/3
Assignment Total
#
10
#/10
Additional comments:
Copyright © 2018, 2016 by University of Phoenix. All rights
reserved.
Microsoft
®
Project Painting
Exercise and
Executive Summary
Grading
Guide
CPMGT/303 Version 11
Project Estimating and Control Techniques
Copyright
Copyright ©
2018,
2016
by University of Phoenix. All rights reserved.
University of Phoenix® is a registered trademark of Apollo
Group, Inc. in the United States and/or other countries.
Microsoft®, Windows®, and Windows NT® are registered
trademarks of Microsoft Corporation in the United States and/ or
other co
untries. All
other company and product names are trademarks or registered
trademarks of their respective companies. Use of these ma
rks is not intended
to imply endorsement, sponsorship, or affiliation.
Edited in accordance with University of Phoenix® editorial
standards and practices.
Microsoft
®
Project Painting Exercise and
Executive Summary Grading Guide
CPMGT/303 Version 11
Project Estimating and Control Techniques
Copyright
Copyright © 2018, 2016 by University of Phoenix. All rights
reserved.
University of Phoenix® is a registered trademark of Apollo
Group, Inc. in the United States and/or other countries.
Microsoft®, Windows®, and Windows NT® are registered
trademarks of Microsoft Corporation in the United States and/or
other countries. All
other company and product names are trademarks or registered
trademarks of their respective companies. Use of these marks is
not intended
to imply endorsement, sponsorship, or affiliation.
Edited in accordance with University of Phoenix® editorial
standards and practices.

More Related Content

What's hot

Ms project management
Ms  project managementMs  project management
Ms project management
chinunki4
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)
douggillis
 

What's hot (11)

05 Formatting and Sharing Your Plan
05 Formatting and Sharing Your Plan 05 Formatting and Sharing Your Plan
05 Formatting and Sharing Your Plan
 
Ms project management
Ms  project managementMs  project management
Ms project management
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)
 
How to Create Tasks in MS Outlook?
How to Create Tasks in MS Outlook?How to Create Tasks in MS Outlook?
How to Create Tasks in MS Outlook?
 
Project Management Application | Task Closet
 Project Management Application | Task Closet  Project Management Application | Task Closet
Project Management Application | Task Closet
 
Ms project lectures
Ms project lecturesMs project lectures
Ms project lectures
 
Devry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project newDevry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project new
 
Group works in collaboration
Group works in collaborationGroup works in collaboration
Group works in collaboration
 
Flash card interactive quiz - final
Flash card   interactive quiz - finalFlash card   interactive quiz - final
Flash card interactive quiz - final
 
06 Tracking Progress on Tasks
06 Tracking Progress on Tasks06 Tracking Progress on Tasks
06 Tracking Progress on Tasks
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECT
 

Similar to Microsoft® project painting exercise cpmgt303 version 111

Microsoft® Project Painting ExerciseMicrosoft® Project .docx
Microsoft® Project Painting ExerciseMicrosoft® Project .docxMicrosoft® Project Painting ExerciseMicrosoft® Project .docx
Microsoft® Project Painting ExerciseMicrosoft® Project .docx
ARIV4
 
Work Breakdown Structure (WBS) ActivityYour organisati.docx
Work Breakdown Structure (WBS) ActivityYour organisati.docxWork Breakdown Structure (WBS) ActivityYour organisati.docx
Work Breakdown Structure (WBS) ActivityYour organisati.docx
ambersalomon88660
 
MS Project - Lesson #1B - Basics of Project Scheduling - Part 2Obj.docx
MS Project - Lesson #1B - Basics of Project Scheduling - Part 2Obj.docxMS Project - Lesson #1B - Basics of Project Scheduling - Part 2Obj.docx
MS Project - Lesson #1B - Basics of Project Scheduling - Part 2Obj.docx
rosemarybdodson23141
 
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docxMS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
rosemarybdodson23141
 
Primavera manual tutorial book
Primavera manual tutorial bookPrimavera manual tutorial book
Primavera manual tutorial book
Thomas Britto
 
Primavera manual tutorial book
Primavera manual tutorial bookPrimavera manual tutorial book
Primavera manual tutorial book
Thomas Britto
 
Ms project 2000 tutorial
Ms project 2000 tutorialMs project 2000 tutorial
Ms project 2000 tutorial
paolocollector
 
2009 ms project 2010 (2)
2009 ms project 2010 (2)2009 ms project 2010 (2)
2009 ms project 2010 (2)
constancemccrea
 
Yom Institute Presentations lecture notes of project management
Yom Institute Presentations lecture notes of project managementYom Institute Presentations lecture notes of project management
Yom Institute Presentations lecture notes of project management
Abebaw31
 

Similar to Microsoft® project painting exercise cpmgt303 version 111 (20)

Microsoft® Project Painting ExerciseMicrosoft® Project .docx
Microsoft® Project Painting ExerciseMicrosoft® Project .docxMicrosoft® Project Painting ExerciseMicrosoft® Project .docx
Microsoft® Project Painting ExerciseMicrosoft® Project .docx
 
Work Breakdown Structure (WBS) ActivityYour organisati.docx
Work Breakdown Structure (WBS) ActivityYour organisati.docxWork Breakdown Structure (WBS) ActivityYour organisati.docx
Work Breakdown Structure (WBS) ActivityYour organisati.docx
 
MS Project - Lesson #1B - Basics of Project Scheduling - Part 2Obj.docx
MS Project - Lesson #1B - Basics of Project Scheduling - Part 2Obj.docxMS Project - Lesson #1B - Basics of Project Scheduling - Part 2Obj.docx
MS Project - Lesson #1B - Basics of Project Scheduling - Part 2Obj.docx
 
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docxMS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
 
Primavera manual tutorial book
Primavera manual tutorial bookPrimavera manual tutorial book
Primavera manual tutorial book
 
Primavera manual tutorial book
Primavera manual tutorial bookPrimavera manual tutorial book
Primavera manual tutorial book
 
A Primavera Tutorial
A Primavera TutorialA Primavera Tutorial
A Primavera Tutorial
 
Ms project 2000 tutorial
Ms project 2000 tutorialMs project 2000 tutorial
Ms project 2000 tutorial
 
2009 ms project 2010 (2)
2009 ms project 2010 (2)2009 ms project 2010 (2)
2009 ms project 2010 (2)
 
Managing Projects With HomeSpot
Managing Projects With HomeSpotManaging Projects With HomeSpot
Managing Projects With HomeSpot
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
 
Sketchup-Handbook.pdf
Sketchup-Handbook.pdfSketchup-Handbook.pdf
Sketchup-Handbook.pdf
 
Yom Institute Presentations lecture notes of project management
Yom Institute Presentations lecture notes of project managementYom Institute Presentations lecture notes of project management
Yom Institute Presentations lecture notes of project management
 
Project Management Quick Reference Guide
Project Management Quick Reference GuideProject Management Quick Reference Guide
Project Management Quick Reference Guide
 
Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
 
Project management software
Project management softwareProject management software
Project management software
 
Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007
 

More from amit657720

Organizational BehaviorThe field of organizational behavior ca.docx
Organizational BehaviorThe field of organizational behavior ca.docxOrganizational BehaviorThe field of organizational behavior ca.docx
Organizational BehaviorThe field of organizational behavior ca.docx
amit657720
 
Organizational Culture Edgar H. Schein I I I I II I II .docx
Organizational Culture Edgar H. Schein I I I I II I II .docxOrganizational Culture Edgar H. Schein I I I I II I II .docx
Organizational Culture Edgar H. Schein I I I I II I II .docx
amit657720
 
Organizational culture is so ubiquitous that it affects all area.docx
Organizational culture is so ubiquitous that it affects all area.docxOrganizational culture is so ubiquitous that it affects all area.docx
Organizational culture is so ubiquitous that it affects all area.docx
amit657720
 
OracleFIT5195-2-Star Schema.pdfWeek 2 – Star SchemaSe.docx
OracleFIT5195-2-Star Schema.pdfWeek 2 – Star SchemaSe.docxOracleFIT5195-2-Star Schema.pdfWeek 2 – Star SchemaSe.docx
OracleFIT5195-2-Star Schema.pdfWeek 2 – Star SchemaSe.docx
amit657720
 
Option A.  You are a student at a New York City college in Septe.docx
Option A.  You are a student at a New York City college in Septe.docxOption A.  You are a student at a New York City college in Septe.docx
Option A.  You are a student at a New York City college in Septe.docx
amit657720
 
Organizational change initiatives are a team effort. It is the j.docx
Organizational change initiatives are a team effort. It is the j.docxOrganizational change initiatives are a team effort. It is the j.docx
Organizational change initiatives are a team effort. It is the j.docx
amit657720
 
Organizational Behavior OpenStax Rice Univer.docx
Organizational Behavior OpenStax Rice Univer.docxOrganizational Behavior OpenStax Rice Univer.docx
Organizational Behavior OpenStax Rice Univer.docx
amit657720
 
Organisms Causing Systemic MycosesObjectives -.docx
Organisms Causing Systemic MycosesObjectives   -.docxOrganisms Causing Systemic MycosesObjectives   -.docx
Organisms Causing Systemic MycosesObjectives -.docx
amit657720
 
Option 1 Media and Mental IllnessFind a source of informa.docx
Option 1 Media and Mental IllnessFind a source of informa.docxOption 1 Media and Mental IllnessFind a source of informa.docx
Option 1 Media and Mental IllnessFind a source of informa.docx
amit657720
 
Option One—The Odyssey  For the first option, focused solely on.docx
Option One—The Odyssey  For the first option, focused solely on.docxOption One—The Odyssey  For the first option, focused solely on.docx
Option One—The Odyssey  For the first option, focused solely on.docx
amit657720
 
Option 2 Art Select any 2 of works of art about the Hol.docx
Option 2 Art Select any 2 of works of art about the Hol.docxOption 2 Art Select any 2 of works of art about the Hol.docx
Option 2 Art Select any 2 of works of art about the Hol.docx
amit657720
 

More from amit657720 (20)

Organizational Analysis  Write a 5-7-page paper on a conflict th.docx
Organizational Analysis  Write a 5-7-page paper on a conflict th.docxOrganizational Analysis  Write a 5-7-page paper on a conflict th.docx
Organizational Analysis  Write a 5-7-page paper on a conflict th.docx
 
Organizational BehaviorThe field of organizational behavior ca.docx
Organizational BehaviorThe field of organizational behavior ca.docxOrganizational BehaviorThe field of organizational behavior ca.docx
Organizational BehaviorThe field of organizational behavior ca.docx
 
Organizational behavior is the combination of four areas of study—ps.docx
Organizational behavior is the combination of four areas of study—ps.docxOrganizational behavior is the combination of four areas of study—ps.docx
Organizational behavior is the combination of four areas of study—ps.docx
 
Organizational CommunicationPeople in this organization don’t.docx
Organizational CommunicationPeople in this organization don’t.docxOrganizational CommunicationPeople in this organization don’t.docx
Organizational CommunicationPeople in this organization don’t.docx
 
Organizational Culture Edgar H. Schein I I I I II I II .docx
Organizational Culture Edgar H. Schein I I I I II I II .docxOrganizational Culture Edgar H. Schein I I I I II I II .docx
Organizational Culture Edgar H. Schein I I I I II I II .docx
 
Organizational culture is so ubiquitous that it affects all area.docx
Organizational culture is so ubiquitous that it affects all area.docxOrganizational culture is so ubiquitous that it affects all area.docx
Organizational culture is so ubiquitous that it affects all area.docx
 
OracleFIT5195-2-Star Schema.pdfWeek 2 – Star SchemaSe.docx
OracleFIT5195-2-Star Schema.pdfWeek 2 – Star SchemaSe.docxOracleFIT5195-2-Star Schema.pdfWeek 2 – Star SchemaSe.docx
OracleFIT5195-2-Star Schema.pdfWeek 2 – Star SchemaSe.docx
 
Oral PresentationPlease pick (1) one of the following topics.docx
Oral PresentationPlease pick (1) one of the following topics.docxOral PresentationPlease pick (1) one of the following topics.docx
Oral PresentationPlease pick (1) one of the following topics.docx
 
Option A.  You are a student at a New York City college in Septe.docx
Option A.  You are a student at a New York City college in Septe.docxOption A.  You are a student at a New York City college in Septe.docx
Option A.  You are a student at a New York City college in Septe.docx
 
Order #12087Type of serviceWriting from ScratchWork type.docx
Order #12087Type of serviceWriting from ScratchWork type.docxOrder #12087Type of serviceWriting from ScratchWork type.docx
Order #12087Type of serviceWriting from ScratchWork type.docx
 
ORAL PRESENTATION( POWER POINT ) 12 SLICES . use the Manual of Menta.docx
ORAL PRESENTATION( POWER POINT ) 12 SLICES . use the Manual of Menta.docxORAL PRESENTATION( POWER POINT ) 12 SLICES . use the Manual of Menta.docx
ORAL PRESENTATION( POWER POINT ) 12 SLICES . use the Manual of Menta.docx
 
Organizational change initiatives are a team effort. It is the j.docx
Organizational change initiatives are a team effort. It is the j.docxOrganizational change initiatives are a team effort. It is the j.docx
Organizational change initiatives are a team effort. It is the j.docx
 
Organizational Behavior OpenStax Rice Univer.docx
Organizational Behavior OpenStax Rice Univer.docxOrganizational Behavior OpenStax Rice Univer.docx
Organizational Behavior OpenStax Rice Univer.docx
 
Organisms Causing Systemic MycosesObjectives -.docx
Organisms Causing Systemic MycosesObjectives   -.docxOrganisms Causing Systemic MycosesObjectives   -.docx
Organisms Causing Systemic MycosesObjectives -.docx
 
Option 2Several artists created multiple self-portraits. Select.docx
Option 2Several artists created multiple self-portraits. Select.docxOption 2Several artists created multiple self-portraits. Select.docx
Option 2Several artists created multiple self-portraits. Select.docx
 
Option 1 Media and Mental IllnessFind a source of informa.docx
Option 1 Media and Mental IllnessFind a source of informa.docxOption 1 Media and Mental IllnessFind a source of informa.docx
Option 1 Media and Mental IllnessFind a source of informa.docx
 
Option 1 Thought about a child who is dying. Is a death of a chil.docx
Option 1 Thought about a child who is dying. Is a death of a chil.docxOption 1 Thought about a child who is dying. Is a death of a chil.docx
Option 1 Thought about a child who is dying. Is a death of a chil.docx
 
Option One—The Odyssey  For the first option, focused solely on.docx
Option One—The Odyssey  For the first option, focused solely on.docxOption One—The Odyssey  For the first option, focused solely on.docx
Option One—The Odyssey  For the first option, focused solely on.docx
 
Option 1Right to Counsel PresentationAnalyze two case.docx
Option 1Right to Counsel PresentationAnalyze two case.docxOption 1Right to Counsel PresentationAnalyze two case.docx
Option 1Right to Counsel PresentationAnalyze two case.docx
 
Option 2 Art Select any 2 of works of art about the Hol.docx
Option 2 Art Select any 2 of works of art about the Hol.docxOption 2 Art Select any 2 of works of art about the Hol.docx
Option 2 Art Select any 2 of works of art about the Hol.docx
 

Recently uploaded

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
httgc7rh9c
 

Recently uploaded (20)

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
VAMOS CUIDAR DO NOSSO PLANETA! .
VAMOS CUIDAR DO NOSSO PLANETA!                    .VAMOS CUIDAR DO NOSSO PLANETA!                    .
VAMOS CUIDAR DO NOSSO PLANETA! .
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111
 
Model Attribute _rec_name in the Odoo 17
Model Attribute _rec_name in the Odoo 17Model Attribute _rec_name in the Odoo 17
Model Attribute _rec_name in the Odoo 17
 
Play hard learn harder: The Serious Business of Play
Play hard learn harder:  The Serious Business of PlayPlay hard learn harder:  The Serious Business of Play
Play hard learn harder: The Serious Business of Play
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
Our Environment Class 10 Science Notes pdf
Our Environment Class 10 Science Notes pdfOur Environment Class 10 Science Notes pdf
Our Environment Class 10 Science Notes pdf
 
21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17
 
How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 

Microsoft® project painting exercise cpmgt303 version 111

  • 1. Microsoft® Project Painting Exercise CPMGT/303 Version 11 1 University of Phoenix Material Microsoft® Project Painting Exercise Microsoft® Project Microsoft® Project (also called “MS-Project”) is one of the most popular tools for project planning projects today. It is relatively easy to use and makes it easier to manage projects. Microsoft® Project Exercise: The Painting Project This is a simple exercise in Microsoft® Project. These instructions are brief and only cover the basics. The objective of this exercise is to prepare you for Week 3 Learning Team assignment. This exercise only covers how to log into Microsoft® Project, set up a simple schedule, and log out. The exercise is not concerned with monitoring or controlling the execution of a plan. Start Microsoft® Project To start Microsoft® Project; click through “Start > Programs > Microsoft Office 2013 > Microsoft Project” Microsoft® Project should start up, with a blank “Gantt chart” view of a new project. Saving Microsoft® Project It is recommended that you save your project immediately. So
  • 2. please Save your project now using the following format ‘Last Name_Paint_Project’. If you last name is Allen, your Microsoft® Project file name will be ‘Allen_Paint_Project’. If you are prompted to save the project with a baseline, click Yes. You may continue to work on the baseline until you have completed the exercise and turned it in as the final baseline. Microsoft® Project Settings Before getting into the details of the Painting Project, it is beneficial to enter a few Microsoft® Project settings. These settings are: · Duration Unit of Measure. The normal default for duration is the day (day) which consist of 8 hours. There are other unit of measures that you may decide to use. The most popular are minute (min), hour (hr), and week (wk). For this exercise we will use the default setting. The working calendar. There is a default Standard Calendar which consists of a 5-day work week (Monday through Friday) with Saturday and Sunday set as non-working days. A day is made up of 8 hours. It is recommended for this exercise that you leave Microsoft® Project set to the Standard Calendar. If you want to explore other calendars or how to set up your own calendar, click as follows “Project > Project Information”. The following pop up menu will appear with Calendar showing as ‘Standard’. Available resources. It is beneficial to set up your known resources pool at the start of the project. Note. You may change the resources in the pool at any time, as resources are added to
  • 3. and subtracted from the project. To set up the resource pool click as follows “Resource> Resource Sheet”. You’ll get a table in which you can define the names of resources that you wish to be available. Simply type a name in the “Name” field, and use a new line for each different resource. For the Painting Project, the following are the resources. Jackie Smith – Standard Rate $25.00; Overtime Rate $37.00 Tom Busch – Standard Rate $20.00; Overtime Rate $30.00 Alan Jacobs – Standard Rate $15.00; Overtime Rate $22.00 Suzie Smith – Standard Rate $15.00; Overtime Rate $22.00 Paint – One time cost of $700 Paint Supplies (paint brushes and tape, drop cloth, etc.) – One time cost of $450 Enter these in your resource sheet. Project start or end date. When you first start developing a schedule for a project it is useful to set up the project start or end date. To enter this date, click as follows “Project > Project Information”. At work you may have a project that will start in a few weeks so you would use a project start date. If this is the case you will select ‘Project Start Date’ in the ‘Schedule from:’ field and enter the projected project start date in the ‘Start date’ field as follows:
  • 4. If you are doing a project for a wedding or an event, the project would have an end date; the date the event will occur. If this is the case you will select ‘Project End Date’ in the ‘Schedule from:’ field and enter the desired project end date in the ‘Finish date’ field as follows: For the Paint Project, select Project Start Date and enter June 21, 2014. Creating Tasks (aka activities). When you start Microsoft® Project, by default you’ll see a blank Gantt chart. The first three columns (on the left) are headed “”, “Task Mode”, “Task Name” and “Task Duration”. To enter the tasks, work down the third column, entering Task Name and pressing the Down Arrow key (↓) at the end of each entry. Note. Microsoft® Project assigns each task a Task ID or line # and inserted a default duration of 1 day for each task. Do not worry about this duration at this point in time. Creating work packages and subtasks. Just like outlining a report in Microsoft® Word, or a presentation in Microsoft® PowerPoint®, you can outline a project’s tasks. There are several ways of doing this, but here’s just one. · First (outside of the software), write down your tasks, grouped under headings that describe their intended effect. These headings are called “Work packages”. For example, the Paint Project consist of several work packages: Painting bedroom and bathroom Purchase paint and materials Prep rooms for painting
  • 5. Paint rooms Clean up paint items · These work packages are then expressed in detail as sets of subtasks, as follows: Painting bedroom and bathroom Purchase paint and materials Drive to paint store Select paint and materials Purchase paint and materials Drive back and put paint and materials at house Purchase of paint materials complete Prep rooms for painting Remove any furniture that is in the way Tape off any fixtures that will not be removed; covering so paint does not get on them Place drop cloths in appropriate areas Inspect to make sure all surfaces not requiring paint are covered adequately Prep rooms for painting complete Paint rooms Paint bedroom Paint bathroom Let paint dry Paint room complete Clean up paint items Pick up drop cloths and dispose of them Remove tape form any fixtures and dispose of tape Place furniture back where required Clean up items complete · To achieve this effect in Microsoft® Project, enter all the tasks, grouping them together under their work package. Then use the “Indent” function (the icon) to make the subtasks part of
  • 6. the work package by moving them to the right. Note how the task immediately above the indented one changes to work package, or summary tasks, with a bold font. When you indent a task, it becomes a subtask of the next “un-indented” task (work package) above it. You may also “outdent” using the icon. This indenting to form work packages is extremely useful to control how projects are displayed. By expanding and collapsing a Work package, you can show or hide subtasks to show just the level of detail you want. You can select multiple tasks (shift-click) before indenting. · Enter the Paint Project Work Packages and Subtasks. Once you have entered these items it is recommend that you set Microsoft Project to Auto-Schedule which allows Microsoft Project to calculate the task start and end dates for you. To set each work package and subtask to auto schedule highlight each and then click on Auto Schedule. When done your Gantt Chart should look as follows: Linking Tasks You should understand the concept of linkage or precedence — in other words, which activities need to finish before others can start (like putting on socks before putting on shoes before tying laces). It is easy to create the commonest type of linkage — FS, or Finish-to-Start — between them. Simply: With the left mouse button, select the earlier activity.
  • 7. Hold down the ‘Control’ (or ‘Ctrl’) key Select the later activity and release the left mouse button and control key Click the ‘Link tasks’ icon (it looks like a chain). You should see the later activity’s duration bar get pushed to the right, and its left end will align with the right end of the earlier one. An arrow will appear showing the link. General rule Never link work packages themselves — always expand both work packages first and specify linkages between specific activities. Link the tasks as they could occur, regardless of resources, in the Paint Project. When complete, your file should look as follows: Note: Removing any furniture that is in the way does not have to wait for delivery of paint and paint supplies, but Taping off any fixtures or placing drop cloths does have to wait, so those tasks are linked to a purchase of paint and material task. Assigning Resources to Tasks Now it is time to use the resources that you set up. To assign a resource to a task, go to the Gantt chart and, on the task line item. Click on the resource name column. A pop up menu should appear with the list of the resources in your resource pool. Simply select the correct resource and move to the next sub
  • 8. task. Work packages are not assigned resources. For the Paint Project, the following resource are to be assigned to each subtask. Task Name Task Resource(s) to be assigned Drive to paint store Alan Jacobs Select paint and materials Alan Jacobs Purchase paint and material Alan Jacobs; Paint; Paint supplies Drive back and put paint and materials at house Alan Jacobs Remove any furniture that is in the way Tom Busch Tape off any fixtures that will not be removed Suzie Smith Place drop cloths in appropriate areas Suzie Smith Inspect to make sure all surfaces are covered adequately Suzie Smith Paint bedroom Jackie Smith Paint bathroom Jackie Smith Pick up drop cloths and dispose of them Suzie Smith Remove tape from any fixtures and dispose of tape Suzie Smith Place furniture back where required Tom Busch Assigning Task Duration Now you can work with our resources to determine the duration
  • 9. of each of their assigned tasks. Once durations have been agreed to you will input that into Microsoft Project. To input the durations, click in the “Duration” box for each task and specify its duration and time unit (min, hr, day or wk). The agreed to durations for the Paint Project are as follows: Task Name Task Agreed to Duration Drive to paint store 1 hr Select paint and materials 6 hr Purchase paint and material 45 min Drive back and put paint and materials at house 1 hr Purchase paint and materials complete 0 day Remove any furniture that is in the way 2 hr Tape off any fixtures that will not be removed 6 hr Place drop cloths in appropriate areas 1 hr Inspect to make sure all surfaces are covered adequately 1 hr Prep rooms for painting complete 0 day Paint bedroom 1 day Paint bathroom 4 hr Let paint dry 1 day Paint rooms complete 0 day
  • 10. Pick up drop cloths and dispose of them 1 hr Remove tape from any fixtures and dispose of tape 4 hr Place furniture back where required 1 hr Clean up paint items complete 0 day Upon entering these durations, you should see Jackie Smith as an over-allocated resource. If Jackie is the only painter available then the resource must be leveled so that Jackie is not working a 12 hour day and getting paid overtime. To level resources in Microsoft® Project go to ‘Resource’ tab and click on Level Resource. Then select Jackie Smith and click on level now. Scheduling a project – determining duration and the critical path By default, the Gantt chart shows what is happening in the project. With the Gantt chart open, click the Format tab and notice the Critical Tasks checkbox. If you check the box, Microsoft® Project will show you the Critical Path highlighted in red as follows. At this point you have completed the Paint Project Exercise.
  • 11. Save the file and submit in the Assessments Tab. Copyright © 2018, 2016, 2014 by University of Phoenix. All rights reserved. Project Estimating and Control Techniques Grading Guide CPMGT/303 Version 11 3 Microsoft® Project Painting Exercise and Executive Summary Grading Guide CPMGT/303 Version 11 Project Estimating and Control Techniques
  • 12. Copyright Copyright © 2018, 2016 by University of Phoenix. All rights reserved. University of Phoenix® is a registered trademark of Apollo Group, Inc. in the United States and/or other countries. Microsoft®, Windows®, and Windows NT® are registered trademarks of Microsoft Corporation in the United States and/or other countries. All other company and product names are trademarks or registered trademarks of their respective companies. Use of these marks is not intended to imply endorsement, sponsorship, or affiliation. Edited in accordance with University of Phoenix® editorial standards and practices. Individual Assignment: Project Estimating and Control Techniques Purpose of Assignment Students use the University of Phoenix Library to research Critical Path and then follow the Exercise instructions to complete the Paint exercise in MS Project. An executive summary is then prepared to discuss how the Critical Path was determined and what lessons they learned in completing this
  • 13. assignment. Resources Required Microsoft® Project Student Desktop Microsoft® Project Painting Exercise WorksheetGrading Guide Content Met Partially Met Not Met Comments: The student searches the UOP Library for the Critical Path Method. The student uses Microsoft® Project to complete the Microsoft® Project Painting Exercise. The student includes the primary deliverables and the activities associated with them in the Microsoft Project Schedule. The student writes an Executive Summary describing the process used for finding the critical path in Microsoft® Project, and lessons learned while completing the Painting Exercise.
  • 14. Total Available Total Earned 7 #/7 Writing Guidelines Met Partially Met Not Met Comments: The paper—including tables and graphs, headings, title page, and reference page—is consistent with APA formatting guidelines and meets course-level requirements. Intellectual property is recognized with in-text citations and a reference page. Paragraph and sentence transitions are present, logical, and maintain the flow throughout the paper.
  • 15. Sentences are complete, clear, and concise. Rules of grammar and usage are followed including spelling and punctuation. Total Available Total Earned 3 #/3 Assignment Total # 10 #/10 Additional comments:
  • 16. Copyright © 2018, 2016 by University of Phoenix. All rights reserved. Microsoft ® Project Painting Exercise and Executive Summary Grading Guide CPMGT/303 Version 11 Project Estimating and Control Techniques
  • 17. Copyright Copyright © 2018, 2016 by University of Phoenix. All rights reserved. University of Phoenix® is a registered trademark of Apollo Group, Inc. in the United States and/or other countries. Microsoft®, Windows®, and Windows NT® are registered trademarks of Microsoft Corporation in the United States and/ or
  • 18. other co untries. All other company and product names are trademarks or registered trademarks of their respective companies. Use of these ma rks is not intended to imply endorsement, sponsorship, or affiliation. Edited in accordance with University of Phoenix® editorial standards and practices. Microsoft ® Project Painting Exercise and Executive Summary Grading Guide CPMGT/303 Version 11 Project Estimating and Control Techniques
  • 19. Copyright Copyright © 2018, 2016 by University of Phoenix. All rights reserved. University of Phoenix® is a registered trademark of Apollo Group, Inc. in the United States and/or other countries. Microsoft®, Windows®, and Windows NT® are registered trademarks of Microsoft Corporation in the United States and/or other countries. All other company and product names are trademarks or registered trademarks of their respective companies. Use of these marks is not intended to imply endorsement, sponsorship, or affiliation. Edited in accordance with University of Phoenix® editorial standards and practices.