SlideShare a Scribd company logo
Working with Tasks
Projects have some tasks that needs to be completed within specified time period. First, you list your task
and analyze possible relationships between the tasks. Then you are ready to create tasks. Tasks can be
automatically or manually scheduled, depending on the needs of the project and the information currently
available. At any point during a project, you can change a task from manual scheduling to automatic
scheduling, or vice versa.
Creating a Manually ScheduledTask
By default, all new tasks in Project 2016 are set for manual scheduling. With manual scheduling, you can
fully control the task’s duration, start date, and finish date. The duration can be entered in minutes (m),
hours (h), days (d), weeks (w), or months (mo.). Manually scheduled tasks are marked with the pushpin
icon in the Task Mode field.
To create a manually scheduled (Default setting) task:
1. In the first row of the task table, type in name of project, for this “Example Project” in the Task
Name field (see Figure 1).
2. Enter Duration of the project in the Duration field, for this I’ll type 3mo. This sets the duration of
the task to three months.
3. Enter the day you want to begin the project (for this Monday) in the Start field. Project 2016
automatically calculates the date for Monday from today in this month and the finish date using the
given information and fills in the Start date and Finish field respectively. Also, a task bar appears
in the timescale (on the same row as the task) showing the task’s time frame.
You can also select start date from the drop down (See Figure)
(Note: - You can also try typing in “Today” or “Tomorrow” in Start field.)
(Note: - Good practice is to first set the project Start date or Project End date. Otherwise, as you can see
the project starts field takes today’s date which is not the project start date. Project schedule is always
created before the project begins hence project start date is always set in future.)
Creating an Automatically Scheduled Task
A complete project has a lot of tasks that can further have subtasks. Let’s create an automatically scheduled
task.
(Note:- Automatically scheduled tasks are marked with the Gantt bar icon in the Task Mode field.)
To create an automatically scheduled task:
1. In the second row of the task table, enter “Task 1” in the Task Name field (see Figure).
2. Click in the Task Mode field, click the down arrow that appears, and then click Auto Scheduled.
By default, Project 2016 assigns the task an estimated duration of one day and automatically fills in
the Duration, Start, and Finish fields. Also, a task bar appears in the timescale showing the task’s
time frame.
3. Now let’s put a duration to “Task1” for this, enter 25d in the Duration field. Project 2016
recalculates the finish date and updates the Finish field.
4. Here the Task in 1st row has same level of hierarchy with the 2nd row, so need to indent task. To
indent task, with the task selected, click on the icon in the task tab.
(Note: - In this example: Task in 1st row “Example Project” is the Main Task i.e. the project itself
and there are 3 summary tasks namely Task1, Task2 & Task3. Each has different subtasks namely
Subtask1, Subtask2 & Subtask3.)
(Tip: To make the full Timescale visible drag the bar in Timeline.)
5. After creating Task1 under Example Project. Similarly, create Subtasks under it. Then create Task2
& Task3 and out-dent it by using icon in Task tab. Alternatively, you can create summary tasks
of same hierarchy using icon in Task tab and then create subtasks. You can insert tasks using
icon in Task tab within Insert panel.
(Tip: You can anytime change default settings of new tasks creating from Manual Scheduling to Automatic
Scheduling by clicking on the left corner of screen.)
(Tip: If you have list of tasks in Excel the you can import directly into project. How to do that effectively is
covered in Miscellaneous: How to? chapter of this document.)
Drag this bar.
Linking Tasks
In a project each task may have certain relation with another. When you link tasks, you create a relationship
between them called a task dependency. Project 2016 supports four types of task dependencies (*FS, SS,
FF & SF). By default, Project 2016 creates finish-to-start (FS) links, which means the first task needs to
finish before the second task can start. Depending upon the relation (between tasks and constraints) the
tasks are linked under Predecessors column (here appears the Task ID and type of dependency) of Task
Table.
To link tasks:
1. In the Task Name column, click to select the tasks of same hierarchy, for this select Task1, and then
hold down the Ctrl key and click to select the remaining two tasks (Task2 & Task3). After selecting
click on the icon ( Shortcut: Ctrl+F2) on the Task tab. Similarly, link each Subtasks under each
Task. You must select the order in which they will execute, the selection order is significant. Now
you’ll see arrow line linking three tasks. (Notice that Task2 and Task3 is Auto Scheduled while Task1
is Manually Scheduled. You may try altering them. ). Similarly link other subtasks to each other.
1. Select Sub-task 3 under Task1 and double click in Predecessors column. You’ll see a pop like below.
In the ID row enter 3 (Task ID of Sub-task1). This is a way to link task to one another. Here we have
Sub-Task3 with FS with 0d lag dependency with Sub-Task1 & Sub-Task2. You can choose different
task dependencies based on the task execution schedule.
2. Now, let’s assign durations to Subtasks as in screenshot below.
The faint line highlighted in image above shows the current date i.e. also indicates the tasks and what
should be their progress in order to finish as scheduled. Above we can see Sub-Task1 of Task1 must
have already finished and in the same Sub-Task2 must have been finished around 25% so we need to
update task progress. To show the progress, select Sub-Task1 and choose 100% from
icon located in Task tab. Alternatively, you can input manually in Task
Information.
Notice the dark line in
task bar.

More Related Content

Similar to Tasks manual automatic_linking_summary_progress_microsoft_project_2016

MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docxMS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
rosemarybdodson23141
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)douggillis
 
Ms project 2000 tutorial
Ms project 2000 tutorialMs project 2000 tutorial
Ms project 2000 tutorialpaolocollector
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
Ronald Oroya
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
Kushal Patel
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
MuhammadZahidQazi
 
How to Create Tasks in MS Outlook?
How to Create Tasks in MS Outlook?How to Create Tasks in MS Outlook?
How to Create Tasks in MS Outlook?
peterb8
 
Microsoft® Project Painting Exercise CPMGT303 Version 111
Microsoft® Project Painting Exercise CPMGT303 Version 111Microsoft® Project Painting Exercise CPMGT303 Version 111
Microsoft® Project Painting Exercise CPMGT303 Version 111
DioneWang844
 
Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering...
Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering...Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering...
Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering...
DeltaBahn
 
Autocad excel vba
Autocad excel vbaAutocad excel vba
Autocad excel vbarjg_vijay
 
Using Microsoft Project 2003
Using Microsoft Project 2003Using Microsoft Project 2003
Using Microsoft Project 2003
pparakh
 
Microsoft® Project Painting ExerciseMicrosoft® Project .docx
Microsoft® Project Painting ExerciseMicrosoft® Project .docxMicrosoft® Project Painting ExerciseMicrosoft® Project .docx
Microsoft® Project Painting ExerciseMicrosoft® Project .docx
ARIV4
 
Chapter A Guide to Using Microsoft Project 2013 Exploring Pro.docx
Chapter A Guide to Using Microsoft Project 2013 Exploring Pro.docxChapter A Guide to Using Microsoft Project 2013 Exploring Pro.docx
Chapter A Guide to Using Microsoft Project 2013 Exploring Pro.docx
mccormicknadine86
 
Tutorials on Macro
Tutorials on MacroTutorials on Macro
Tutorials on Macro
Anurag Deb
 
Work Breakdown Structure (WBS) ActivityYour organisati.docx
Work Breakdown Structure (WBS) ActivityYour organisati.docxWork Breakdown Structure (WBS) ActivityYour organisati.docx
Work Breakdown Structure (WBS) ActivityYour organisati.docx
ambersalomon88660
 
Planner blender app deck.psv1104b complete
Planner blender app deck.psv1104b   completePlanner blender app deck.psv1104b   complete
Planner blender app deck.psv1104b complete
paulchristopher44
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
Ong-Art Sanpinit
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
Ong-Art Sanpinit
 
Creating a task list
Creating a task listCreating a task list
Creating a task list
ahmed hamza
 

Similar to Tasks manual automatic_linking_summary_progress_microsoft_project_2016 (20)

MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docxMS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)
 
Ms project 2000 tutorial
Ms project 2000 tutorialMs project 2000 tutorial
Ms project 2000 tutorial
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
 
How to Create Tasks in MS Outlook?
How to Create Tasks in MS Outlook?How to Create Tasks in MS Outlook?
How to Create Tasks in MS Outlook?
 
Microsoft® Project Painting Exercise CPMGT303 Version 111
Microsoft® Project Painting Exercise CPMGT303 Version 111Microsoft® Project Painting Exercise CPMGT303 Version 111
Microsoft® Project Painting Exercise CPMGT303 Version 111
 
Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering...
Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering...Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering...
Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering...
 
Autocad excel vba
Autocad excel vbaAutocad excel vba
Autocad excel vba
 
Using Microsoft Project 2003
Using Microsoft Project 2003Using Microsoft Project 2003
Using Microsoft Project 2003
 
Microsoft® Project Painting ExerciseMicrosoft® Project .docx
Microsoft® Project Painting ExerciseMicrosoft® Project .docxMicrosoft® Project Painting ExerciseMicrosoft® Project .docx
Microsoft® Project Painting ExerciseMicrosoft® Project .docx
 
Chapter A Guide to Using Microsoft Project 2013 Exploring Pro.docx
Chapter A Guide to Using Microsoft Project 2013 Exploring Pro.docxChapter A Guide to Using Microsoft Project 2013 Exploring Pro.docx
Chapter A Guide to Using Microsoft Project 2013 Exploring Pro.docx
 
Omni plan 2-manual
Omni plan 2-manualOmni plan 2-manual
Omni plan 2-manual
 
Tutorials on Macro
Tutorials on MacroTutorials on Macro
Tutorials on Macro
 
Work Breakdown Structure (WBS) ActivityYour organisati.docx
Work Breakdown Structure (WBS) ActivityYour organisati.docxWork Breakdown Structure (WBS) ActivityYour organisati.docx
Work Breakdown Structure (WBS) ActivityYour organisati.docx
 
Planner blender app deck.psv1104b complete
Planner blender app deck.psv1104b   completePlanner blender app deck.psv1104b   complete
Planner blender app deck.psv1104b complete
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
 
Creating a task list
Creating a task listCreating a task list
Creating a task list
 

Recently uploaded

Orion Context Broker introduction 20240604
Orion Context Broker introduction 20240604Orion Context Broker introduction 20240604
Orion Context Broker introduction 20240604
Fermin Galan
 
In 2015, I used to write extensions for Joomla, WordPress, phpBB3, etc and I ...
In 2015, I used to write extensions for Joomla, WordPress, phpBB3, etc and I ...In 2015, I used to write extensions for Joomla, WordPress, phpBB3, etc and I ...
In 2015, I used to write extensions for Joomla, WordPress, phpBB3, etc and I ...
Juraj Vysvader
 
How Recreation Management Software Can Streamline Your Operations.pptx
How Recreation Management Software Can Streamline Your Operations.pptxHow Recreation Management Software Can Streamline Your Operations.pptx
How Recreation Management Software Can Streamline Your Operations.pptx
wottaspaceseo
 
Paketo Buildpacks : la meilleure façon de construire des images OCI? DevopsDa...
Paketo Buildpacks : la meilleure façon de construire des images OCI? DevopsDa...Paketo Buildpacks : la meilleure façon de construire des images OCI? DevopsDa...
Paketo Buildpacks : la meilleure façon de construire des images OCI? DevopsDa...
Anthony Dahanne
 
Navigating the Metaverse: A Journey into Virtual Evolution"
Navigating the Metaverse: A Journey into Virtual Evolution"Navigating the Metaverse: A Journey into Virtual Evolution"
Navigating the Metaverse: A Journey into Virtual Evolution"
Donna Lenk
 
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERROR
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERRORTROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERROR
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERROR
Tier1 app
 
2024 RoOUG Security model for the cloud.pptx
2024 RoOUG Security model for the cloud.pptx2024 RoOUG Security model for the cloud.pptx
2024 RoOUG Security model for the cloud.pptx
Georgi Kodinov
 
Accelerate Enterprise Software Engineering with Platformless
Accelerate Enterprise Software Engineering with PlatformlessAccelerate Enterprise Software Engineering with Platformless
Accelerate Enterprise Software Engineering with Platformless
WSO2
 
Globus Connect Server Deep Dive - GlobusWorld 2024
Globus Connect Server Deep Dive - GlobusWorld 2024Globus Connect Server Deep Dive - GlobusWorld 2024
Globus Connect Server Deep Dive - GlobusWorld 2024
Globus
 
RISE with SAP and Journey to the Intelligent Enterprise
RISE with SAP and Journey to the Intelligent EnterpriseRISE with SAP and Journey to the Intelligent Enterprise
RISE with SAP and Journey to the Intelligent Enterprise
Srikant77
 
Vitthal Shirke Microservices Resume Montevideo
Vitthal Shirke Microservices Resume MontevideoVitthal Shirke Microservices Resume Montevideo
Vitthal Shirke Microservices Resume Montevideo
Vitthal Shirke
 
OpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoam
OpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoamOpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoam
OpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoam
takuyayamamoto1800
 
Into the Box 2024 - Keynote Day 2 Slides.pdf
Into the Box 2024 - Keynote Day 2 Slides.pdfInto the Box 2024 - Keynote Day 2 Slides.pdf
Into the Box 2024 - Keynote Day 2 Slides.pdf
Ortus Solutions, Corp
 
Corporate Management | Session 3 of 3 | Tendenci AMS
Corporate Management | Session 3 of 3 | Tendenci AMSCorporate Management | Session 3 of 3 | Tendenci AMS
Corporate Management | Session 3 of 3 | Tendenci AMS
Tendenci - The Open Source AMS (Association Management Software)
 
Cracking the code review at SpringIO 2024
Cracking the code review at SpringIO 2024Cracking the code review at SpringIO 2024
Cracking the code review at SpringIO 2024
Paco van Beckhoven
 
Enterprise Resource Planning System in Telangana
Enterprise Resource Planning System in TelanganaEnterprise Resource Planning System in Telangana
Enterprise Resource Planning System in Telangana
NYGGS Automation Suite
 
Developing Distributed High-performance Computing Capabilities of an Open Sci...
Developing Distributed High-performance Computing Capabilities of an Open Sci...Developing Distributed High-performance Computing Capabilities of an Open Sci...
Developing Distributed High-performance Computing Capabilities of an Open Sci...
Globus
 
Graphic Design Crash Course for beginners
Graphic Design Crash Course for beginnersGraphic Design Crash Course for beginners
Graphic Design Crash Course for beginners
e20449
 
A Comprehensive Look at Generative AI in Retail App Testing.pdf
A Comprehensive Look at Generative AI in Retail App Testing.pdfA Comprehensive Look at Generative AI in Retail App Testing.pdf
A Comprehensive Look at Generative AI in Retail App Testing.pdf
kalichargn70th171
 
Exploring Innovations in Data Repository Solutions - Insights from the U.S. G...
Exploring Innovations in Data Repository Solutions - Insights from the U.S. G...Exploring Innovations in Data Repository Solutions - Insights from the U.S. G...
Exploring Innovations in Data Repository Solutions - Insights from the U.S. G...
Globus
 

Recently uploaded (20)

Orion Context Broker introduction 20240604
Orion Context Broker introduction 20240604Orion Context Broker introduction 20240604
Orion Context Broker introduction 20240604
 
In 2015, I used to write extensions for Joomla, WordPress, phpBB3, etc and I ...
In 2015, I used to write extensions for Joomla, WordPress, phpBB3, etc and I ...In 2015, I used to write extensions for Joomla, WordPress, phpBB3, etc and I ...
In 2015, I used to write extensions for Joomla, WordPress, phpBB3, etc and I ...
 
How Recreation Management Software Can Streamline Your Operations.pptx
How Recreation Management Software Can Streamline Your Operations.pptxHow Recreation Management Software Can Streamline Your Operations.pptx
How Recreation Management Software Can Streamline Your Operations.pptx
 
Paketo Buildpacks : la meilleure façon de construire des images OCI? DevopsDa...
Paketo Buildpacks : la meilleure façon de construire des images OCI? DevopsDa...Paketo Buildpacks : la meilleure façon de construire des images OCI? DevopsDa...
Paketo Buildpacks : la meilleure façon de construire des images OCI? DevopsDa...
 
Navigating the Metaverse: A Journey into Virtual Evolution"
Navigating the Metaverse: A Journey into Virtual Evolution"Navigating the Metaverse: A Journey into Virtual Evolution"
Navigating the Metaverse: A Journey into Virtual Evolution"
 
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERROR
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERRORTROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERROR
TROUBLESHOOTING 9 TYPES OF OUTOFMEMORYERROR
 
2024 RoOUG Security model for the cloud.pptx
2024 RoOUG Security model for the cloud.pptx2024 RoOUG Security model for the cloud.pptx
2024 RoOUG Security model for the cloud.pptx
 
Accelerate Enterprise Software Engineering with Platformless
Accelerate Enterprise Software Engineering with PlatformlessAccelerate Enterprise Software Engineering with Platformless
Accelerate Enterprise Software Engineering with Platformless
 
Globus Connect Server Deep Dive - GlobusWorld 2024
Globus Connect Server Deep Dive - GlobusWorld 2024Globus Connect Server Deep Dive - GlobusWorld 2024
Globus Connect Server Deep Dive - GlobusWorld 2024
 
RISE with SAP and Journey to the Intelligent Enterprise
RISE with SAP and Journey to the Intelligent EnterpriseRISE with SAP and Journey to the Intelligent Enterprise
RISE with SAP and Journey to the Intelligent Enterprise
 
Vitthal Shirke Microservices Resume Montevideo
Vitthal Shirke Microservices Resume MontevideoVitthal Shirke Microservices Resume Montevideo
Vitthal Shirke Microservices Resume Montevideo
 
OpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoam
OpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoamOpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoam
OpenFOAM solver for Helmholtz equation, helmholtzFoam / helmholtzBubbleFoam
 
Into the Box 2024 - Keynote Day 2 Slides.pdf
Into the Box 2024 - Keynote Day 2 Slides.pdfInto the Box 2024 - Keynote Day 2 Slides.pdf
Into the Box 2024 - Keynote Day 2 Slides.pdf
 
Corporate Management | Session 3 of 3 | Tendenci AMS
Corporate Management | Session 3 of 3 | Tendenci AMSCorporate Management | Session 3 of 3 | Tendenci AMS
Corporate Management | Session 3 of 3 | Tendenci AMS
 
Cracking the code review at SpringIO 2024
Cracking the code review at SpringIO 2024Cracking the code review at SpringIO 2024
Cracking the code review at SpringIO 2024
 
Enterprise Resource Planning System in Telangana
Enterprise Resource Planning System in TelanganaEnterprise Resource Planning System in Telangana
Enterprise Resource Planning System in Telangana
 
Developing Distributed High-performance Computing Capabilities of an Open Sci...
Developing Distributed High-performance Computing Capabilities of an Open Sci...Developing Distributed High-performance Computing Capabilities of an Open Sci...
Developing Distributed High-performance Computing Capabilities of an Open Sci...
 
Graphic Design Crash Course for beginners
Graphic Design Crash Course for beginnersGraphic Design Crash Course for beginners
Graphic Design Crash Course for beginners
 
A Comprehensive Look at Generative AI in Retail App Testing.pdf
A Comprehensive Look at Generative AI in Retail App Testing.pdfA Comprehensive Look at Generative AI in Retail App Testing.pdf
A Comprehensive Look at Generative AI in Retail App Testing.pdf
 
Exploring Innovations in Data Repository Solutions - Insights from the U.S. G...
Exploring Innovations in Data Repository Solutions - Insights from the U.S. G...Exploring Innovations in Data Repository Solutions - Insights from the U.S. G...
Exploring Innovations in Data Repository Solutions - Insights from the U.S. G...
 

Tasks manual automatic_linking_summary_progress_microsoft_project_2016

  • 1. Working with Tasks Projects have some tasks that needs to be completed within specified time period. First, you list your task and analyze possible relationships between the tasks. Then you are ready to create tasks. Tasks can be automatically or manually scheduled, depending on the needs of the project and the information currently available. At any point during a project, you can change a task from manual scheduling to automatic scheduling, or vice versa. Creating a Manually ScheduledTask By default, all new tasks in Project 2016 are set for manual scheduling. With manual scheduling, you can fully control the task’s duration, start date, and finish date. The duration can be entered in minutes (m), hours (h), days (d), weeks (w), or months (mo.). Manually scheduled tasks are marked with the pushpin icon in the Task Mode field. To create a manually scheduled (Default setting) task: 1. In the first row of the task table, type in name of project, for this “Example Project” in the Task Name field (see Figure 1). 2. Enter Duration of the project in the Duration field, for this I’ll type 3mo. This sets the duration of the task to three months. 3. Enter the day you want to begin the project (for this Monday) in the Start field. Project 2016 automatically calculates the date for Monday from today in this month and the finish date using the given information and fills in the Start date and Finish field respectively. Also, a task bar appears in the timescale (on the same row as the task) showing the task’s time frame. You can also select start date from the drop down (See Figure) (Note: - You can also try typing in “Today” or “Tomorrow” in Start field.) (Note: - Good practice is to first set the project Start date or Project End date. Otherwise, as you can see the project starts field takes today’s date which is not the project start date. Project schedule is always created before the project begins hence project start date is always set in future.)
  • 2. Creating an Automatically Scheduled Task A complete project has a lot of tasks that can further have subtasks. Let’s create an automatically scheduled task. (Note:- Automatically scheduled tasks are marked with the Gantt bar icon in the Task Mode field.) To create an automatically scheduled task: 1. In the second row of the task table, enter “Task 1” in the Task Name field (see Figure). 2. Click in the Task Mode field, click the down arrow that appears, and then click Auto Scheduled. By default, Project 2016 assigns the task an estimated duration of one day and automatically fills in the Duration, Start, and Finish fields. Also, a task bar appears in the timescale showing the task’s time frame. 3. Now let’s put a duration to “Task1” for this, enter 25d in the Duration field. Project 2016 recalculates the finish date and updates the Finish field. 4. Here the Task in 1st row has same level of hierarchy with the 2nd row, so need to indent task. To indent task, with the task selected, click on the icon in the task tab.
  • 3. (Note: - In this example: Task in 1st row “Example Project” is the Main Task i.e. the project itself and there are 3 summary tasks namely Task1, Task2 & Task3. Each has different subtasks namely Subtask1, Subtask2 & Subtask3.) (Tip: To make the full Timescale visible drag the bar in Timeline.) 5. After creating Task1 under Example Project. Similarly, create Subtasks under it. Then create Task2 & Task3 and out-dent it by using icon in Task tab. Alternatively, you can create summary tasks of same hierarchy using icon in Task tab and then create subtasks. You can insert tasks using icon in Task tab within Insert panel. (Tip: You can anytime change default settings of new tasks creating from Manual Scheduling to Automatic Scheduling by clicking on the left corner of screen.) (Tip: If you have list of tasks in Excel the you can import directly into project. How to do that effectively is covered in Miscellaneous: How to? chapter of this document.) Drag this bar.
  • 4. Linking Tasks In a project each task may have certain relation with another. When you link tasks, you create a relationship between them called a task dependency. Project 2016 supports four types of task dependencies (*FS, SS, FF & SF). By default, Project 2016 creates finish-to-start (FS) links, which means the first task needs to finish before the second task can start. Depending upon the relation (between tasks and constraints) the tasks are linked under Predecessors column (here appears the Task ID and type of dependency) of Task Table. To link tasks: 1. In the Task Name column, click to select the tasks of same hierarchy, for this select Task1, and then hold down the Ctrl key and click to select the remaining two tasks (Task2 & Task3). After selecting click on the icon ( Shortcut: Ctrl+F2) on the Task tab. Similarly, link each Subtasks under each Task. You must select the order in which they will execute, the selection order is significant. Now you’ll see arrow line linking three tasks. (Notice that Task2 and Task3 is Auto Scheduled while Task1 is Manually Scheduled. You may try altering them. ). Similarly link other subtasks to each other.
  • 5. 1. Select Sub-task 3 under Task1 and double click in Predecessors column. You’ll see a pop like below. In the ID row enter 3 (Task ID of Sub-task1). This is a way to link task to one another. Here we have Sub-Task3 with FS with 0d lag dependency with Sub-Task1 & Sub-Task2. You can choose different task dependencies based on the task execution schedule. 2. Now, let’s assign durations to Subtasks as in screenshot below. The faint line highlighted in image above shows the current date i.e. also indicates the tasks and what should be their progress in order to finish as scheduled. Above we can see Sub-Task1 of Task1 must have already finished and in the same Sub-Task2 must have been finished around 25% so we need to update task progress. To show the progress, select Sub-Task1 and choose 100% from icon located in Task tab. Alternatively, you can input manually in Task Information. Notice the dark line in task bar.