SlideShare a Scribd company logo
1 of 39
Download to read offline
PROFESSIONAL PRACTICE 2
PANG KAI YUN 0319802
SIM CHIA TING 0320932
WAH YUN CHEN 0319115
SECTIONAL COMPLETION AND PARTIAL
POSSESSION BY EMPLOYER
Partial Possession By Employer (with consent)
What is Partial Possession?
● Premature or early occupation of parts or sections of the works before
practical completion.
● Clause 16.0 provides for this type of situation where the Employer wishes to
take possession of certain sections of the works before the whole Works is
completed.
● The part taken over is called the “Occupied Part.”
Partial Possession By Employer (with consent)
Why Partial Possession?
a) Business pressure
- current demand and price is good so they need to start business or
production. (eg: factory, shopping mall)
b) Commercial reasons
- commencement date of Works has been delayed so the need to
complete early, thus take partial possession for some sections
Partial Possession By Employer (with consent)
How to take Partial Possession?
a) Under Clause 16.0, the employer must comply with the following:-
i) To give written notice of intention to take partial possession to contractor
ii) The partial possession occurs before practical completion.
iii) The employer to identify part to be taken over.
iv) That the contractor has given his consent.
Partial Possession By Employer (with consent)
Contractor’s Consent for Partial Possession
Clause 16.1 prohibits the Contractor from unreasonably withholding or delaying
consent. However, the Contractor is not bound to give consent for partial
possession.
The Contractor may withhold consent by reasons of:
a) When partial possession may give rise to safety and health issues, or
b) When partial possession may materially disrupt the regular progress of the
remaining works
c) Where there is non-payment issue for work done.
Partial Possession By Employer (with consent)
Certificate of Partial Completion
Clause 16.1(a) requires the Architect to issue the Certificate of Partial Completion
within 14 days of taking partial possession of the Occupied Parts.
The Certificate of Partial Completion shall state the following:-
a) Date of partial possession
b) Must have layout plan to identify or demarcate the occupied part
c) Estimated value of the occupied part
Partial Possession By Employer (with consent)
Contractual Effects of Partial Possession
a) Practical Completion
- Under clause 16.1(b), practical completion of the Occupied Part shall be
deemed to have occurred on the date of taking over the Occupied Part.
b) Defects Liability Period (DLP)
- The DLP is deemed to have commenced on the date of practical
completion of the Occupied Part by the Employer.
Partial Possession By Employer (with consent)
Contractual Effects of Partial Possession
c) Liquidated Damages
- Under Clause 16.1 (c), Liquidated damages shall be reduced by the ratio
of the estimated value of occupied part to the contract sum.
d) Retention Sum
- Under Clause 16.1(d), the Architect is required to:
1. issue a payment certificate to release half the amount of Retention
Fund in the ratio of the estimated value of the Occupied Part
2. issue payment certificate within 14 days after the issuance of the
Certificate of Partial Completion
Partial Possession By Employer (with consent)
Contractual Effects of Partial Possession
e) Certificate of Making Good Defects (CMGD)
- Under Clause 16.1(e), where all defects in the Occupied Parts have been
made good, the Architect shall issue a CMGD.
f) Release of Second Moiety of Retention
- Under Clause 16.1(f), the Architect shall issue a certificate for the release
of the remaining amount of the Retention Fund for the Occupied Part
within 14 days after the issue of CMGD of the same Occupied Part.
Partial Possession By Employer (with consent)
Item Not Affected by Partial Possession
a) Works Insurance
i) Clause 20.A.1 states that ‘the Contractor shall keep such works so
insured notwithstanding any arrangement for ……. partial possession’.
ii) Clause 20.B.1 and 20.C.1 contain similar provision as for Clause 20.A.1.
iii) The total sum insured of the above provisions is that the parties’
insurance obligations remain unaffected.
iv) The respective parties remain obliged to insure and keep the works
insured to the ‘full value’, there being no reduction for the value of the
Occupied Part.
Partial Possession By Employer (with consent)
Item Not Affected by Partial Possession
b) Performance Bond and Final Certificate
i) Clause 37 for Performance Bond does not indicate any deduction or
reduction of the bond value after partial possession.
ii) Clause 30.0 for Final Certificate are not affected by the partial possession
since there is only one Final Certificate issued.
iii) Hence, it can be inferred that both the Performance Bond and the Final
Certificate are to remain unaffected by the issuance of Certificate of
Partial Completion.
● If the Employer takes partial possession of the Occupied Part without the
Contractor’s consent, the Employer is in culpable breach of
contract.
● Clause 16.2 is a provision which caters for the common practice
where the Employer does, or is forced to take over parts of the works before
practical completion without the Contractor’s consent.
Partial Possession by Employer (without consent)
Restrictions on employer’s Rights to take partial possession without
consent
1) Employer has no absolute rights.
- The contract placed certain restrictions on the Employer’s rights to do so.
Pursuant to Clause 16.2(a) may take partial possession provided three
pre-conditions are met:-
a) The completion of Works have been delayed by the contractor
b) A Certificate of Non-Completion has been issued by Architect
under clause 22.1
c) Such entry and partial possession of the Occupied Part do not
unreasonably disturb the regular progress of the Contractor’s
remaining works or adversely affect the safety and health
issues.
Partial Possession by Employer (without consent)
Restrictions on employer’s Rights to take partial possession without
consent
1) Employer has no absolute rights
- For Clause 16.2 (a) to be applicable, it may be implied that the Certificate
of Non- Completion (CNC) is still operative and the Contractor is liable for
liquidated damages.
Partial Possession by Employer (without consent)
Restrictions on employer’s Rights to take partial possession without
consent
2) Employer’s Rights limited by the Contract
a) Clause 16.2 uses the phrase ‘without prejudice to any other rights and
remedies which he may possess under the contract’. This limits the
Employer’s right to those under the contract only and in the process
excludes his common law rights.
b) Clause 16.2 makes it clear that the procedural and contractual effect of
clause 16.2 are equally applicable as those under clauses 16.1(a) to (f).
Clause 16.1 and 16.2 deal essentially with the same circumstance, separated only
by issue of the Contractor’s consent.
Partial Possession by Employer (without consent)
The provision of Clause 16.3 govern the Contractor’s duties following partial
possession by the Employer, whether with or without contractor’s consent.
1) Contractor to remove his site facilities, equipments, plants, materials, etc
from Occupied Part upon receipt of A.I
2) It is implied that the Architect must prescribe a definite time for removal from
the Occupied Part and this should be a reasonable time frame.
3) However the contract is silent on consequences of non-compliance by
contractor with Architect’s written instruction to remove such items.
4) It is also silent on remedies available to employer for such non-compliance by
the Contractor.
Procedures following Partial Possession (with or without consent)
Different Commencement Dates
● The Date of Commencement under Clause 21.1 assume that the whole of the
Site be handed over to the Contractor on such date.
● If this is not possible, the Employer may want to plan for different sections of
the Site or phases to be handed over on different dates. In this case, this
information must be properly documented and made known to the Contractor
in the Contract so that he can price accordingly.
● The details of the different commencement dates must be recorded in the
Appendix to PAM contract as Sectional Commencement Date under Clause
21.2, together with the demarcation layout showing the different sections.
Sectional Commencement Dates and Sectional Completion Dates
Different Commencement Dates
Sectional Commencement Dates and Sectional Completion Dates
Different Commencement Dates
● This clause is useful where the site is big or where piling works are carried out
under a separate contract. Completed piling areas can be handed over to the
building contractor to start work.
● Sectional Commencement has the following advantages:
1) Save time - overlapping of construction activities being carried out by
different contractors on the same site
2) Improve cash-flow - Build according to sales and demand.
Sectional Commencement Dates and Sectional Completion Dates
Different Completion Dates
● The Sectional Completion Dates under Clause 21.3 can arise regardless of
whether the Site was handed over to the Contractor as a whole or in sections.
Employer may planned for completion of certain sections for business or
commercial reasons, such as phase completion of apartments to improve
cash-flow.
● The details of the different completion dates must be recorded in the
Appendix to PAM contract, together with the demarcation layout showing the
different sections.
Sectional Commencement Dates and Sectional Completion Dates
Contractual effect of Sectional Completion
● Same as in Partial Completion:
1) Practical Completion and Defects Liability Period (clause 15.0)
2) Extension of time (clause 23.0)
3) Liquidated Damages (clause 22.2)
4) Release of Retention Sum (clause 30.6)
● Apply to each section of the work as though it is a separate and distinct
contract.
Sectional Commencement Dates and Sectional Completion Dates
QUESTION
QUESTION 1:
Explain the differences between Sectional Completion and
Partial Possession in PAM 2006.
ANSWER:
Sectional Completion Partial Possession
Agreed before signing of the contract Not agreed before signing of the
contract (happened during the
construction)
Under clause 21.0 in PAM 2006 Under clause 16.0 in PAM 2006
QUESTION 2:
Under what circumstance can the Employer take partial
possession of the site? Please explain for both partial
possession with and without consent from the Contractor.
ANSWER:
Under Clause 16.0, the employer must comply with the following:-
1. To give written notice of intention to take partial possession to contractor
2. The partial possession occurs before practical completion.
3. The employer to identify part to be taken over.
4. That the contractor has given his consent.
ANSWER:
Partial possession with consent from the Contractor:
● Under clause 16.1, the contractor cannot unreasonably delay or withhold such consent.
Partial possession without consent from the Contractor:
● Under clause 16.2, the Employer may take partial possession provided three
pre-conditions are met:-
a) The completion of Works have been delayed
b) A Certificate of Non-Completion has been issued by Architect under clause 22.1
c) Such entry and partial possession of the Occupied Part do not unreasonably
disturb the regular progress of the Contractor’s remaining works or adversely
affect the safety and health issues.
QUESTION 3:
Explain the contractual implications of partial possession
and the items not affected by it.
ANSWER:
Contractual implications of partial possession:
1. Practical Completion - clause 16.1(b)
2. Defects Liability Period (DLP) - clause 16.1(b)
3. Liquidated Damages - clause 16.1(c)
4. Retention Sum - clause 16.1(d)
5. Certificate of Making Good Defects (CMGD) - clause 16.1(e)
6. Release of Second Moiety of Retention - clause 16.1(f)
Item Not Affected by Partial Possession:
a) Works Insurance
i) Clause 20.A.1 states that ‘the Contractor shall keep such works so
insured notwithstanding any arrangement for ……. partial possession’.
ii) Clause 20.B.1 and 20.C.1 contain similar provision as for Clause 20.A.1.
iii) The total sum insured of the above provisions is that the parties’
insurance obligations remain unaffected.
iv) The respective parties remain obliged to insure and keep the works
insured to the ‘full value’, there being no reduction for the value of the
Occupied Part.
ANSWER:
Item Not Affected by Partial Possession:
b) Performance Bond and Final Certificate.
i) Clause 37 for Performance Bond does not indicate any deduction or
reduction of the bond value after partial possession.
ii) Clause 30.0 for Final Certificate are not affected by the partial possession
since there is only one Final Certificate issued.
iii) Hence, it can be inferred that both the Performance Bond and the Final
Certificate are to remain unaffected by the issuance of Certificate of
Partial Completion.
ANSWER:
ADDITIONAL QUESTION
QUESTION 1:
After the employer has taken possession of the Occupied
Parts, the Architect shall issue the Certificate of Partial
Completion within how many days? What should be stated in
the Certificate of Partial Completion?
Under clause 16.1(a), the Architect shall issue the Certificate of Partial Completion
within 14 days of taking partial possession of the Occupied Parts.
The Certificate of Partial Completion shall state the following:-
a) Date of partial possession
b) Must have layout plan to identify or demarcate the occupied part
c) Estimated value of the occupied part
ANSWER:
QUESTION 2:
Under clause 16.1, the contractor cannot unreasonably delay
or withhold such consent. Under what circumstances will the
contractor withhold such consent?
The Contractor may withhold consent by reasons of:
1) When partial possession may give rise to safety and health issues, or
2) When partial possession may materially disrupt the regular progress of the
remaining works, or
3) Where there is non-payment issue for work done.
ANSWER:
QUESTION 3:
Whats should the contractor do if the employer takes
possession of the Occupied Part, whether with or without
contractor’s consent?
Under clause 16.3 govern the Contractor’s duties following partial possession by
the Employer, whether with or without contractor’s consent.
1) Contractor to remove his site facilities, equipments, plants, materials,
etc from Occupied Part upon receipt of Architect’s written instruction.
2) It is implied that the Architect must prescribe a definite time for
removal from the Occupied Part and this should be a reasonable time
frame.
ANSWER:
THANK YOU!

More Related Content

What's hot

Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017DarrenTofu
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 reportNgo Jia Haur
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management ContractingKai Yun Pang
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityPang Khai Shuen
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selectionanojan kanagarathnam
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in MalaysiaDayat Mohamad
 
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Kai Yun Pang
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Yee Len Wan
 

What's hot (20)

Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selection
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Site Possession
Site PossessionSite Possession
Site Possession
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 

Similar to Here are the key differences between Sectional Completion and Partial Possession:Sectional Completion:- Refers to completing different sections/phases of the overall works separately based on pre-agreed sectional completion dates. - The contractor completes each section as a whole and hands it over to the employer.- Each section is treated as a separate completion with its own DLP period, retention sum, etc.Partial Possession: - Refers to the employer taking possession of part of the completed works before the whole works is completed. - Only a part/portion of the overall works is handed over, not a whole section.- Requires contractor's consent unless delayed by contractor

Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxNathannielGonzales1
 
TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019Cerasela Angelescu
 
HM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTHM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTEuan Pirie
 
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptxCONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptxssuserb7dd601
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentationYong Sy
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & AssociatesCerasela Angelescu
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...tdartnell
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10 Farah Sham
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspensionbreyerhanna
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice IIseenyeeyong
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentationashleyyeap
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxMahSobeh
 

Similar to Here are the key differences between Sectional Completion and Partial Possession:Sectional Completion:- Refers to completing different sections/phases of the overall works separately based on pre-agreed sectional completion dates. - The contractor completes each section as a whole and hands it over to the employer.- Each section is treated as a separate completion with its own DLP period, retention sum, etc.Partial Possession: - Refers to the employer taking possession of part of the completed works before the whole works is completed. - Only a part/portion of the overall works is handed over, not a whole section.- Requires contractor's consent unless delayed by contractor (20)

Pp2 p7
Pp2   p7Pp2   p7
Pp2 p7
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptx
 
TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019
 
HM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTHM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPT
 
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptxCONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
 
Cl report final
Cl report finalCl report final
Cl report final
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentation
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Progress and delay_
Progress and delay_Progress and delay_
Progress and delay_
 
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
 
Seminar p8x
Seminar p8xSeminar p8x
Seminar p8x
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspension
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentation
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptx
 

More from Kai Yun Pang

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiKai Yun Pang
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - ReportKai Yun Pang
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump StationKai Yun Pang
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectKai Yun Pang
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial AppraisalKai Yun Pang
 
Assignment - Financial Appraisal
Assignment - Financial Appraisal Assignment - Financial Appraisal
Assignment - Financial Appraisal Kai Yun Pang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012Kai Yun Pang
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Kai Yun Pang
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S HotelKai Yun Pang
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study ReportKai Yun Pang
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - JournalKai Yun Pang
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service Kai Yun Pang
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final AccountKai Yun Pang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - QuestionKai Yun Pang
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK LandKai Yun Pang
 
Assignment - Financial Analysis
Assignment - Financial AnalysisAssignment - Financial Analysis
Assignment - Financial AnalysisKai Yun Pang
 
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Kai Yun Pang
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalKai Yun Pang
 

More from Kai Yun Pang (20)

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau Langkawi
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - Report
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump Station
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft Project
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - Financial Appraisal
Assignment - Financial Appraisal Assignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S Hotel
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study Report
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - Journal
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK Land
 
Assignment - Financial Analysis
Assignment - Financial AnalysisAssignment - Financial Analysis
Assignment - Financial Analysis
 
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
 

Recently uploaded

Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 

Recently uploaded (20)

Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 

Here are the key differences between Sectional Completion and Partial Possession:Sectional Completion:- Refers to completing different sections/phases of the overall works separately based on pre-agreed sectional completion dates. - The contractor completes each section as a whole and hands it over to the employer.- Each section is treated as a separate completion with its own DLP period, retention sum, etc.Partial Possession: - Refers to the employer taking possession of part of the completed works before the whole works is completed. - Only a part/portion of the overall works is handed over, not a whole section.- Requires contractor's consent unless delayed by contractor

  • 1. PROFESSIONAL PRACTICE 2 PANG KAI YUN 0319802 SIM CHIA TING 0320932 WAH YUN CHEN 0319115 SECTIONAL COMPLETION AND PARTIAL POSSESSION BY EMPLOYER
  • 2. Partial Possession By Employer (with consent) What is Partial Possession? ● Premature or early occupation of parts or sections of the works before practical completion. ● Clause 16.0 provides for this type of situation where the Employer wishes to take possession of certain sections of the works before the whole Works is completed. ● The part taken over is called the “Occupied Part.”
  • 3. Partial Possession By Employer (with consent) Why Partial Possession? a) Business pressure - current demand and price is good so they need to start business or production. (eg: factory, shopping mall) b) Commercial reasons - commencement date of Works has been delayed so the need to complete early, thus take partial possession for some sections
  • 4. Partial Possession By Employer (with consent) How to take Partial Possession? a) Under Clause 16.0, the employer must comply with the following:- i) To give written notice of intention to take partial possession to contractor ii) The partial possession occurs before practical completion. iii) The employer to identify part to be taken over. iv) That the contractor has given his consent.
  • 5. Partial Possession By Employer (with consent) Contractor’s Consent for Partial Possession Clause 16.1 prohibits the Contractor from unreasonably withholding or delaying consent. However, the Contractor is not bound to give consent for partial possession. The Contractor may withhold consent by reasons of: a) When partial possession may give rise to safety and health issues, or b) When partial possession may materially disrupt the regular progress of the remaining works c) Where there is non-payment issue for work done.
  • 6. Partial Possession By Employer (with consent) Certificate of Partial Completion Clause 16.1(a) requires the Architect to issue the Certificate of Partial Completion within 14 days of taking partial possession of the Occupied Parts. The Certificate of Partial Completion shall state the following:- a) Date of partial possession b) Must have layout plan to identify or demarcate the occupied part c) Estimated value of the occupied part
  • 7. Partial Possession By Employer (with consent) Contractual Effects of Partial Possession a) Practical Completion - Under clause 16.1(b), practical completion of the Occupied Part shall be deemed to have occurred on the date of taking over the Occupied Part. b) Defects Liability Period (DLP) - The DLP is deemed to have commenced on the date of practical completion of the Occupied Part by the Employer.
  • 8. Partial Possession By Employer (with consent) Contractual Effects of Partial Possession c) Liquidated Damages - Under Clause 16.1 (c), Liquidated damages shall be reduced by the ratio of the estimated value of occupied part to the contract sum. d) Retention Sum - Under Clause 16.1(d), the Architect is required to: 1. issue a payment certificate to release half the amount of Retention Fund in the ratio of the estimated value of the Occupied Part 2. issue payment certificate within 14 days after the issuance of the Certificate of Partial Completion
  • 9. Partial Possession By Employer (with consent) Contractual Effects of Partial Possession e) Certificate of Making Good Defects (CMGD) - Under Clause 16.1(e), where all defects in the Occupied Parts have been made good, the Architect shall issue a CMGD. f) Release of Second Moiety of Retention - Under Clause 16.1(f), the Architect shall issue a certificate for the release of the remaining amount of the Retention Fund for the Occupied Part within 14 days after the issue of CMGD of the same Occupied Part.
  • 10. Partial Possession By Employer (with consent) Item Not Affected by Partial Possession a) Works Insurance i) Clause 20.A.1 states that ‘the Contractor shall keep such works so insured notwithstanding any arrangement for ……. partial possession’. ii) Clause 20.B.1 and 20.C.1 contain similar provision as for Clause 20.A.1. iii) The total sum insured of the above provisions is that the parties’ insurance obligations remain unaffected. iv) The respective parties remain obliged to insure and keep the works insured to the ‘full value’, there being no reduction for the value of the Occupied Part.
  • 11. Partial Possession By Employer (with consent) Item Not Affected by Partial Possession b) Performance Bond and Final Certificate i) Clause 37 for Performance Bond does not indicate any deduction or reduction of the bond value after partial possession. ii) Clause 30.0 for Final Certificate are not affected by the partial possession since there is only one Final Certificate issued. iii) Hence, it can be inferred that both the Performance Bond and the Final Certificate are to remain unaffected by the issuance of Certificate of Partial Completion.
  • 12. ● If the Employer takes partial possession of the Occupied Part without the Contractor’s consent, the Employer is in culpable breach of contract. ● Clause 16.2 is a provision which caters for the common practice where the Employer does, or is forced to take over parts of the works before practical completion without the Contractor’s consent. Partial Possession by Employer (without consent)
  • 13. Restrictions on employer’s Rights to take partial possession without consent 1) Employer has no absolute rights. - The contract placed certain restrictions on the Employer’s rights to do so. Pursuant to Clause 16.2(a) may take partial possession provided three pre-conditions are met:- a) The completion of Works have been delayed by the contractor b) A Certificate of Non-Completion has been issued by Architect under clause 22.1 c) Such entry and partial possession of the Occupied Part do not unreasonably disturb the regular progress of the Contractor’s remaining works or adversely affect the safety and health issues. Partial Possession by Employer (without consent)
  • 14. Restrictions on employer’s Rights to take partial possession without consent 1) Employer has no absolute rights - For Clause 16.2 (a) to be applicable, it may be implied that the Certificate of Non- Completion (CNC) is still operative and the Contractor is liable for liquidated damages. Partial Possession by Employer (without consent)
  • 15. Restrictions on employer’s Rights to take partial possession without consent 2) Employer’s Rights limited by the Contract a) Clause 16.2 uses the phrase ‘without prejudice to any other rights and remedies which he may possess under the contract’. This limits the Employer’s right to those under the contract only and in the process excludes his common law rights. b) Clause 16.2 makes it clear that the procedural and contractual effect of clause 16.2 are equally applicable as those under clauses 16.1(a) to (f). Clause 16.1 and 16.2 deal essentially with the same circumstance, separated only by issue of the Contractor’s consent. Partial Possession by Employer (without consent)
  • 16. The provision of Clause 16.3 govern the Contractor’s duties following partial possession by the Employer, whether with or without contractor’s consent. 1) Contractor to remove his site facilities, equipments, plants, materials, etc from Occupied Part upon receipt of A.I 2) It is implied that the Architect must prescribe a definite time for removal from the Occupied Part and this should be a reasonable time frame. 3) However the contract is silent on consequences of non-compliance by contractor with Architect’s written instruction to remove such items. 4) It is also silent on remedies available to employer for such non-compliance by the Contractor. Procedures following Partial Possession (with or without consent)
  • 17. Different Commencement Dates ● The Date of Commencement under Clause 21.1 assume that the whole of the Site be handed over to the Contractor on such date. ● If this is not possible, the Employer may want to plan for different sections of the Site or phases to be handed over on different dates. In this case, this information must be properly documented and made known to the Contractor in the Contract so that he can price accordingly. ● The details of the different commencement dates must be recorded in the Appendix to PAM contract as Sectional Commencement Date under Clause 21.2, together with the demarcation layout showing the different sections. Sectional Commencement Dates and Sectional Completion Dates
  • 18. Different Commencement Dates Sectional Commencement Dates and Sectional Completion Dates
  • 19. Different Commencement Dates ● This clause is useful where the site is big or where piling works are carried out under a separate contract. Completed piling areas can be handed over to the building contractor to start work. ● Sectional Commencement has the following advantages: 1) Save time - overlapping of construction activities being carried out by different contractors on the same site 2) Improve cash-flow - Build according to sales and demand. Sectional Commencement Dates and Sectional Completion Dates
  • 20. Different Completion Dates ● The Sectional Completion Dates under Clause 21.3 can arise regardless of whether the Site was handed over to the Contractor as a whole or in sections. Employer may planned for completion of certain sections for business or commercial reasons, such as phase completion of apartments to improve cash-flow. ● The details of the different completion dates must be recorded in the Appendix to PAM contract, together with the demarcation layout showing the different sections. Sectional Commencement Dates and Sectional Completion Dates
  • 21. Contractual effect of Sectional Completion ● Same as in Partial Completion: 1) Practical Completion and Defects Liability Period (clause 15.0) 2) Extension of time (clause 23.0) 3) Liquidated Damages (clause 22.2) 4) Release of Retention Sum (clause 30.6) ● Apply to each section of the work as though it is a separate and distinct contract. Sectional Commencement Dates and Sectional Completion Dates
  • 23. QUESTION 1: Explain the differences between Sectional Completion and Partial Possession in PAM 2006.
  • 24. ANSWER: Sectional Completion Partial Possession Agreed before signing of the contract Not agreed before signing of the contract (happened during the construction) Under clause 21.0 in PAM 2006 Under clause 16.0 in PAM 2006
  • 25. QUESTION 2: Under what circumstance can the Employer take partial possession of the site? Please explain for both partial possession with and without consent from the Contractor.
  • 26. ANSWER: Under Clause 16.0, the employer must comply with the following:- 1. To give written notice of intention to take partial possession to contractor 2. The partial possession occurs before practical completion. 3. The employer to identify part to be taken over. 4. That the contractor has given his consent.
  • 27. ANSWER: Partial possession with consent from the Contractor: ● Under clause 16.1, the contractor cannot unreasonably delay or withhold such consent. Partial possession without consent from the Contractor: ● Under clause 16.2, the Employer may take partial possession provided three pre-conditions are met:- a) The completion of Works have been delayed b) A Certificate of Non-Completion has been issued by Architect under clause 22.1 c) Such entry and partial possession of the Occupied Part do not unreasonably disturb the regular progress of the Contractor’s remaining works or adversely affect the safety and health issues.
  • 28. QUESTION 3: Explain the contractual implications of partial possession and the items not affected by it.
  • 29. ANSWER: Contractual implications of partial possession: 1. Practical Completion - clause 16.1(b) 2. Defects Liability Period (DLP) - clause 16.1(b) 3. Liquidated Damages - clause 16.1(c) 4. Retention Sum - clause 16.1(d) 5. Certificate of Making Good Defects (CMGD) - clause 16.1(e) 6. Release of Second Moiety of Retention - clause 16.1(f)
  • 30. Item Not Affected by Partial Possession: a) Works Insurance i) Clause 20.A.1 states that ‘the Contractor shall keep such works so insured notwithstanding any arrangement for ……. partial possession’. ii) Clause 20.B.1 and 20.C.1 contain similar provision as for Clause 20.A.1. iii) The total sum insured of the above provisions is that the parties’ insurance obligations remain unaffected. iv) The respective parties remain obliged to insure and keep the works insured to the ‘full value’, there being no reduction for the value of the Occupied Part. ANSWER:
  • 31. Item Not Affected by Partial Possession: b) Performance Bond and Final Certificate. i) Clause 37 for Performance Bond does not indicate any deduction or reduction of the bond value after partial possession. ii) Clause 30.0 for Final Certificate are not affected by the partial possession since there is only one Final Certificate issued. iii) Hence, it can be inferred that both the Performance Bond and the Final Certificate are to remain unaffected by the issuance of Certificate of Partial Completion. ANSWER:
  • 33. QUESTION 1: After the employer has taken possession of the Occupied Parts, the Architect shall issue the Certificate of Partial Completion within how many days? What should be stated in the Certificate of Partial Completion?
  • 34. Under clause 16.1(a), the Architect shall issue the Certificate of Partial Completion within 14 days of taking partial possession of the Occupied Parts. The Certificate of Partial Completion shall state the following:- a) Date of partial possession b) Must have layout plan to identify or demarcate the occupied part c) Estimated value of the occupied part ANSWER:
  • 35. QUESTION 2: Under clause 16.1, the contractor cannot unreasonably delay or withhold such consent. Under what circumstances will the contractor withhold such consent?
  • 36. The Contractor may withhold consent by reasons of: 1) When partial possession may give rise to safety and health issues, or 2) When partial possession may materially disrupt the regular progress of the remaining works, or 3) Where there is non-payment issue for work done. ANSWER:
  • 37. QUESTION 3: Whats should the contractor do if the employer takes possession of the Occupied Part, whether with or without contractor’s consent?
  • 38. Under clause 16.3 govern the Contractor’s duties following partial possession by the Employer, whether with or without contractor’s consent. 1) Contractor to remove his site facilities, equipments, plants, materials, etc from Occupied Part upon receipt of Architect’s written instruction. 2) It is implied that the Architect must prescribe a definite time for removal from the Occupied Part and this should be a reasonable time frame. ANSWER: