SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
PROFESSIONAL PRACTICE 2 (QSB 3614)
SEMESTER 5
COURSEWORK NO. 2
BACHELOR OF QUANTITY SURVEYING (HONOURS)
NAME & STUDENT ID: NG SENG HE 0323037
HONG KAI YIN 0323361
LAU CHIN SHENG 0317899
SIONG JIA YII 0317239
LIU WEI QIAN 0322969
ABD’ALLAH SAIEF-UL-HAQQ
HOOSSAINSAEB 0324556
2
TABLE OF CONTENT
A. Coursework No. 2 Questions 3~7
B. Question 1 answer 8~14
C. Question 2 answer 15~16
D. Question 3 answer 17~22
3
SCHOOL OF ARCHITECTURE · BUILDING · DESIGN
Centre for Modern Architecture Studies in Southeast Asia
Bachelor of Quantity Surveying (Honours)
PROFESSIONAL PRACTICE [QSB 3614]
1. This assignment shall make up 15% weightage ofthe final marks.
2. This is a group assignment and shall be submitted in groups of 6 students.
3. Dateline for submission ofthis Coursework No. 2 is on or before 30th October 2017.
Coursework No. 2 – Preparation of Final Account.
You are appointed as the consulting Quantity Surveyor for a apartment project based on PAM Form of
Contract 2006 (With Quantities). The summary of the Contract Sum is as follows:
Bill No. 1 – Preliminaries RM 2,250,000.00
Bill No. 2 – Building Works RM 31,450,000.00
Bill No. 3 – Local Infrastructure Works RM 6,130,000.00
Bill No. 4 – P.C. and Provisional Sums RM 7,870,000.00
Contract Sum RM 47,700,000.00
4
Question 1.
The tender drawings shows the apartment entrance arch with guardhouse but no details were provided. The
Architect had suggested that these items be listed as Provisional Sum. However you have forgot about this
item and did not include it in your tender document. The contract was awarded without it. The director
would also like to know the significance and implications of this omission by their office.
In addition, you are required to prepare a report to your director, explaining briefly the adjustments of the
essential elements in your preparation of this project’s final account.
(25 marks)
Question 2.
In accordance with clause 30.10 of the contract, the contractor duly submitted his Final Accounts within 6
months after the issuance of the Certificate of Practical Completion. You are then required to assess this
application and prepare the Final Account for the apartment project based of the following valuations
and adjustments made to the Contract Sum:
(35 marks)
Information provided are as follows:
a. The Architect had granted the Contractor’s first application for extension of time and approved
additional insurance premium amounting to RM 10,000.00 in accordance with clause 24 of the
contract due to the delay in the completion of the works caused by the Employer’s late decision on
the toilet design.
In his second application for extension of time, the Contractor submitted an loss and expense
claim for RM200,000.00 in his Final Accounts to you. Since the delay event is not a relevant
event listed in Clause 23.8, the Architect had rejected the Contractor’s second application.
5
b. There are four variation orders carried out by the Contractor:
Addition Omission
i. Variation Order No. 1: RM 300,000.00 RM 200,000.00
Changes of toilet layout to
suit Employer’s requirements.
ii. Variation Order No. 2: RM 400,000.00 - New
lift lobby at entrance.
iii. Variation Order No. 3:
Changes from premix roads RM 1,100,000.00 RM 900,000.00 to
precast concrete paver blocks
iv. Variation Order No. 4:
Omission of glass partitions - RM 96,000.00
6
c. The following are the nominated sub-contractor’s accounts:
Original P.C. & NSC’s
Provisional Sums final account
i. Lift Services: Profit @
2% Attendance as
item
RM 1,700,000.00 RM 1,500,000.00
RM 34,000.00
RM 34,000.00
ii. Air Conditioning Services:
Profit @ 2%
Attendance as item
RM 1,200,000.00 RM 1,000,000.00
RM 24,000.00
RM 24,000.00
iii. Electrical Services:
Profit @ 2%
RM 1,600,000.00 RM 2,100,000.00
RM 32,000.00
Attendance as item RM 32,000.00
iv. Provisional Sums: Entrance Porch RM 1,270,000.00 RM 1,050,000.00
RM 6,670,000.00
7
Question 3.
Explain the basis on how the following variations may be finalised and priced during the Final
Account stage:
a. Relocation of an already installed timber door including sealing up the wall opening.
Agreed at the site meeting for Contractor to claim based on Dayworks for labour,
material and plant.
(10 marks)
b. Contractor need to provide computer equipment in the Preliminaries section but item was left
unpriced, i.e. BQ item was left blank in the rate/amount column in the contract document.
Subsequently, this item was omitted by the Architect.
(10 marks)
c. A wash trough as required and priced in the Preliminaries section was not constructed due to
site constraints imposed later by the Employer. However, the vehicles leaving the site during
construction were always kept clean including the public roads using water jet washing and full-
timed workers.
(10 marks)
d. Mistake was made in the price for excavation through rocks at RM 15 per m3. Item was not
rationalised during contract documentation. However,original quantity in BQ is 100 m3 but re-
measured quantity is 2,000 m3. The Contractor submitted a claim for revised rates of RM 150
per m3 for the total quantity of 2,000 m3.
(10 marks)
8
QUESTION 1 ANSWER
9
Final Account is the document showing the adjustments of the contract sum issued under
clause 30.10. Clause 30.10 of the PAM Contract 2006 states that final account showing the
necessary adjustment of the contract sum and the final account shall be completed by quantity
surveyor within 6 months after receipt of all necessary documents, drawings and site data from
contractor. It is a financial document indicating the final value of the works executed by Contractor
and his sub-contractors.
The purpose of Final Account is to establish the final contract value or final construction
cost of the project. It also paves the way for the Architect to issue the Final Certificate and establish
the final sum payable by the Employer or owing from the Contractor. A complete Final Account
shall include the following elements:
1. Variation Works (clause 11.6)
2. Remeasurement of Provisional Quantities (clause 11.6(f))
3. Omission of P.C. and Provisional Sum (clause 30.11(c))
4. Adding-back of NSC’s and NS’ final accounts (clause 30.11(c))
5. Adjustment of profit and attendance (clause 30.11 (c))
6. Adjustment of Provisional Sum based on actual expended and omitted if not
expended
7. Additional expenses claims (clause 11.7)
8. Loss and Expense claim (clause 24.4)
10
Variation Works
Variation works often arise in the construction stage. According to clause 11.1, it is the
alteration or modification of the design, quality and quantity of the Works. Variation works are
the only thing that can contractually change the contract sum, which must first be formally
instructed by an Architect through issuing Architect’s Instruction in writing form, and in
specifically prepared form with “Architect’s Instruction” title and serial numbering as accordance
to Clause 2.2. There are six rules to be applied in six different situations when undergoes the
valuation of variation work as stated in Clause 11.6(a)-(f). Quantity Surveyor is required to
determine the most suitable rules to be applied in the valuation of work.
Remeasurement of Provisional Quantities
Clause 11.6(f) indicates that provisional quantities in the bills may also be an important
element in the Final Account. It shall be remeasured based on the actual quantities executed and
valued based on the contract rates and prices. For example, the actual quantities of piling work or
excavation work are barely known at the early stage of construction. Thus, the final amount
payable to the Contractor shall be based on the quantities that has been remeasured upon the
completion of the particular work.
Prime Cost and Provisional Sum
Prime Cost sum and Provisional sum are also the essential elements in the Final Account.
Prime Cost sum are the sum of specialist work done by nominated sub-contractors which normally
includes a percentage of profit and attendance, whereas Provisional sum is the allowance for some
specific works which its quantities are not completely verifiable and cannot be itemized in the Bill
of Quantities yet. Provisional sum is still to be included in the Bill of Quantities even though its
quantities are not finalized.
11
Taking this case as an example:
There are no details provided for the apartment entrance arch with guardhouse. However,
provisional sums of this element are still required to be included in the Bill of Quantities as it may
provide awareness to the client’s budget and allows for cost control purpose. On the Contractor
side, Contractor need to include the provisional sum works so that he/she may plan the working
programme to be done within the stipulated date. If the provisional sum is not included in the
contract, dispute may arise and Contractor may be entitled to claim for Extension of Time.
Architect is also required to issue an Architect’s Instruction to the Contractor for the execution of
variation of work.
Adding-back of NSC’s and NS’ final accounts
The profits of Prime Cost sum and Provisional sum shall be omitted from the final account
as stated in Clause 30.11 (c). This is because these sums are the estimation of Quantity Surveyor
in the early stage and are subjected to change. The awarded nominated sub-contractors to execute
the work shall submit the Final Account along with pro-rata amount of profit. It is then being added
back based on Clause 30.11(c). The final adjustment will be made after the completion of works.
Adjustment of Profit and Attendance
Contractors are required to allow a percentage of profit and attendance for the Prime Cost
sum. The percentage varies based on the risk and workload of the specialist work. However, the
percentage of the profit will be adjusted in the final account based on pro-rata of the amount
payable to the Nominated Sub-Contractors instead of using the original percentage of profit
according to Clause 30.11(c). As for attendance, it is to ensure the Contractor to provide specific
services required by sub-contractors. It is usually in the form of lump sum or fixed amount basis.
Thus, the attendance in the final account shall be the same as in the contract.
12
Adjustment of Provisional Sum
As mentioned earlier, Provisional sum is an estimation by Quantity Surveyor in the early
stage for the specifics works or elements which have insufficient details to quantify them. In the
final account stage, the provisional sum estimated shall be adjusted based on the actual expended
as stated in Clause 30.11(d). If the provisional sum estimated is larger than the actual expended,
an omission shall be made. In contrast, if the actual expended is larger than the provisional sum,
an addition shall be made accordingly.
Additional Expenses Claim
When the contractor incurs additional expenses on the variation works, Clause 11.7 allows
the contractor to claim for the additional expenses and include the sum into the Final Account.
There are a 2 steps procedure the Contractor must follow in order to claim for the additional
expenses based on Clause 11.7(a) & (b). First, Contractor must submit a written notice to the
Architect for the intention to claim for additional expenses supported with all necessary
calculations. Such notice shall be given within 28 Days of the issuance of the Architect’s
Instruction to execute the variation of work. The next step is the Contractor shall send the complete
particulars of the claim to the Architect and Quantity Surveying within 28 Days upon the
completion of the variation of work.
Loss and Expense Claim
The Contractor is able to claim for the loss and/or expense when he/she has incurred the
loss and/or expense due to the regular progress of work has been materially affected. The matters
that may materially affected the progress of work are stated in Clause 24.3. The Contractor must
also follow a 2-step procedure to claim for the loss and/or expense according to Clause 24.1(a) &
(b). The 2-step procedure is quite similar to the claim for additional expenses. The amount of loss
and/or expenses approved by the Architect shall then be included in the contract sum and Final
Account accordingly based on Clause 24.4.
13
Significance and Implication of Omission
According to Pam contract 2006 Clause 11, the item that were forgotten to include in the
provisional sum which are the apartment entrance arch with guardhouse will then be treated as a
variation. This is because refer to Clause 11.1(a), it expresses the term ‘variation’ as the addition,
omission or substitution of any work. Hence, in this case it is applicable to treat the forgotten item
mentioned above as an addition of work to the project. Furthermore, refer to Clause 11.4 which
stated the Architect shall issue AI (Architect’s Instruction) in regard to expenditure of provisional
sum included in the Contract Bills. In Clause 11.2, the architect may issue an AI ordering a
variation or sanctioning any variation to allow the contractor to carry out the such works as
instructed by architect with due diligence and expedition.
Other than that, according to Clause 11.6(f), in respect of Provisional quantity, the quantity
stated in the Contract Documents shall be re-measured by the Quantity surveyor based on the
actual quantities executed. In this case, the apartment entrance arch and guardhouse are considered
as provisional quantities and according to Clause 11.6(a), where the item that with similar
character to the project/work, executed under similar conditions as and does not significantly
change the quantity of work as set out in the Contract Documents, the rate and price in the Contract
Document shall determine the valuation. On the other hand, refer to Clause 11.6(c) where work is
not of a similar character to work as set out in the contract documents, the valuation shall be at fair
market rates and prices determined by the Quantity surveyor, meaning to say if there is any new
item/work that is no any similar item/work that covered or included in Contract Document, the
Quantity Surveyor shall determine the valuation based on fair market rates and prices.
Presume the total cost for the entrance arch and guardhouse is RM 20,000 and in Bill No.4
PC and Provisional Sums with the consist of 10% in contingencies. The amount allocate in
contingencies is then be able to cover the cost of the entrance arch and guardhouse. However, if
there are no contingencies allowed in Bill No.4. then the addition of cost will be treated as a
variation order and the contract sum will be increased. Therefore, the final contract sum is
RM47,720,000.00
14
Besides, the act of treating the apartment arch and guardhouse as a VO will also granting
a chance to contractor to claim for Extension of Time (EOT) which we can refer from Clause 23.1,
if the contractor is of the opinion that the completion of the Works is or will be delayed beyond
the Completion Date by of the Relevant Events stated in Clause 23.8 (In this case is refer to Clause
23.8(g), which is compliance with Ai issued by the Architect under Clauses 1.4,11.2 and 21.4) he
may apply for an extension of time with the provided procedure stated in the PAM. Hence,
although the completion date is over, the employer is still didn’t entitle to impose Liquidated
damages because of the valid entitlement of EOT for contractor.
In conclusion, the consequences caused by the mistake/error made by the Quantity
Surveyor is tremendously affected to both parties which are employer and contractor in the way in
contracture dispute or delaying the completion date. Moreover, due to this incident. The reputation
of the quantity surveying consultant firm will be affected and the employer will lose their faith
toward the firm.
15
QUESTION 2 ANSWER
16
Project : Construction and Completion of Apartment
Employer : Professional Development Sdn Bhd
Contractor : Smart Builder Corporation
FINAL ACCOUNT
1.0 Original Contract Sum
2.0 Less: P.C. & Provisional Sums
RM RM
47,700,000.00
2.1 Lift Services 1,700,000.00
2.2 Air Conditioning Services 1,200,000.00
2.3 Electrical Services 1,600,000.00
2.4 Provisional Sums: Entrance Porch 1,270,000.00
2.5 Contingencies 1,920,000.00
7,690,000.00 7,690,000.00
2.6 Profit and Attendance
a. Profit @ 2% of RM 4,500,000.00 90,000.00
b. Attendance @ lump sum 90,000.00
180,000.00 180,000.00
Total Builder's works 55,570,000.00
3.0 Add: Variation Works (V.O. Nos 1 - 4)
Total Additions 1,800,000.00
Total Omissions 1,196,000.00
Nett Additions 604,000.00 604,000.00
56,174,000.00
4.0 Add back: NSCs' Final Account
4.1 Lift Services 1,500,000.00
4.2 Air Conditioning Services 1,000,000.00
4.3 Electrical Services 2,100,000.00
4.4 Provisional Sums: Entrance Porch 1,050,000.00
5,650,000.00 5,650,000.00
4.5 Profit and Attendance
a. Profit @ 2% of RM 5,650,000.00 113,000.00
b. Attendance @ lump sum 113,000.00
226,000.00 226,000.00
5.0 Contractual Claims:
Additional Expenses 10,000.00
FINAL CONTRACT VALUE 62,060,000.00
17
QUESTION 3 ANSWER
18
Question 3
Explain the basis on how the following variations may be finalised and priced during the Final
Account stage:
a. Relocation of an already installed timber door including sealing up the wall opening. Agreed
at the site meeting for Contractor to claim based on Dayworks for labour, material and plant.
Based on the situation mentioned above, the relocation of an already installed timber door
including with sealing up the wall opening is considered as work cannot be properly
measured and valued in accordance with Clause 11.6 (a), (b) or (c), the Contractor shall be
allowed to claim the daywork rates in the Contract Documents according to Clause 11.6
(d)(i) or actual cost plus 15% if there are no such daywork rates in the Contract Documents
Clause 11.6 (d)(ii).
The relocation of an already installed timber work includes the works for removal of timber
door, making a new opening for the door and sealing up the previous wall opening. Removal
of timber door and making of a new opening requires general labourers and incurred labour
cost. On the other hand, the sealing materials like bricks, cement and sand, plaster and paint
where the rates are according to the rates stated in the Bill of Quantities. As regards to the
rates, the Quantity Surveyor shall refer the breakdown rates stated in the Bill of Quantities as
the basis of new rates for the sealing up of wall opening for the material used such as bricks,
cement and sand, plaster and paint. The labourers involved would be bricklayer, plasterer
and painter. For the relocation of timber door, there will be no additional construction plant
needed to carry out the works.
In either case of Clause 11.6 (d)(i) or Clause 11.6 (d)(ii), the Contractor then shall provide
voucher specifying the time spent daily on the work, the workers’ names, materials,
scaffolding and transport used. This voucher has to be signed by the Site Agent and verified
by the Site Staff and deliver to the Architect and Quantity Surveyor at weekly intervals with
the final records delivered not later than fourteen (14) Days after the relocation of timber
door has been completed.
19
b. Contractor need to provide computer equipment in the Preliminaries section but item was left
unpriced, i.e. BQ item was left blank in the rate/amount column in the contract document.
Subsequently, this item was omitted by the Architect.
When item is left unpriced in the Preliminaries section, it is deemed to be included in the
tender price as lump sum. Under Clause 11.6 (a), where work is of a similar character to, is
executed under similar conditions as, and does not significantly change the quantity of work
as set out in the Contract Documents, the rates and prices in the Contract Documents shall
determine the valuation. The omitting of computer is of a similar character, executed under
similar conditions and does not significantly change the quantity of work, therefore, the
Quantity Surveyor shall omit the cost of computer equipment based on current fair market
price or cost from previous contract documents of similar projects.
20
c. A wash trough as required and priced in the Preliminaries section was not constructed due to
site constraints imposed later by the Employer. However, the vehicles leaving the site during
construction were always kept clean including the public roads using water jet washing and
full-timed workers.
The total value of wash trough listed in the prelim should be eliminated entirely. After that, a
variation order should be provided for this particular wash trough item where it is in
accordance with Clause 11.6 (d) as it met the pre-condition of work that could not be
properly measured and valued. This clause dictates that it should apply the said daywork
rates stated in the contract or actual cost with an additional 15%. With that said, it should be
noted that this only applies if it meets the criteria or pre-condition that the works executed
cannot be properly measured or valued.
For example, the total amount of water that has been used to wash the trucks cannot be
properly quantified because there is no dedicated water meter for this item, they share the
water meter with other amenities. This is a type of reimbursement to the Contractor with a
certain amount of profits. However, if there are daywork rates stated in the contract, then it
should be used for the valuation including a profit percentage for the Contractor. Finally, the
works that are executed shall be recorded and verified by the Site Staff and be certified by
the Consultants and Architects.
21
d. Mistake was made in the price for excavation through rocks at RM 15 per m3. Item was not
rationalised during contract documentation. However, original quantity in BQ is 100 m3 but
re-measured quantity is 2,000 m3. The Contractor submitted a claim for revised rates of RM
150 per m3 for the total quantity of 2,000 m3.
Based on the situation, rock excavation has been priced wrongly for RM15 per m3 and the
revised rate is RM 150 per m3. The quantity for rock excavation is measured wrongly as
well. 100 m3 is recorded in Bills of Quantities instead of 2000 m3. In this case, Contractor
will face a lost due to the irrationalised rates priced during contract documentation and the
quantity measured initially. Therefore, Contractor has the right to claim his loss and expense
on the outstanding work for revised rate.
Clause 11.6 (b) empowers that where work is of a similar character to work as set out in the
contract doc but is not executed under similar conditions or is executed under similar
conditions but there is a significant change in the quantity of work carried out, the rates and
prices in the contract doc shall be basis for determining valuation which shall include a fair
adjustment in the rates to take into account such difference. It means that Contractor can
claim it by using the contract rates and price but with fair adjustment to the rates for the
difference with pre-conditions: (a) the work must be of similar character but it is not
executed under similar conditions; (b) the work must be of similar character but significant
change in the quantity of work.
Hence, the revised amount that has been adjusted and to be claimed by Contractor is RM
286,500 following by the calculation below.
22
Calculation:
a) RM 15 per m3
100 m3 x RM 15 per m3 = RM 1,500
b) RM 150 per m3
1900 m3 x RM 150 per m3 = RM 285,000
Revisedrates
= RM 1,500 + RM 285,000
= RM 286,500

More Related Content

What's hot

PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: GroupFarah Sham
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017DarrenTofu
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808Arissa Loh
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
Pp2 coursework 2
Pp2 coursework  2Pp2 coursework  2
Pp2 coursework 2tfkc1212
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-dericSyafiq Zariful
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Eca presentation slides
Eca presentation slidesEca presentation slides
Eca presentation slidesahmong4
 
PP2 final report
PP2 final reportPP2 final report
PP2 final reportArissa Loh
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...Zainab Zainordin
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final accountahmong4
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7ashleyyeap
 
Certificates and payments
Certificates and paymentsCertificates and payments
Certificates and paymentsHafizul Mukhlis
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 

What's hot (20)

PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: Group
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
Pp2 coursework 2
Pp2 coursework  2Pp2 coursework  2
Pp2 coursework 2
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Eca presentation slides
Eca presentation slidesEca presentation slides
Eca presentation slides
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final account
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
 
Certificates and payments
Certificates and paymentsCertificates and payments
Certificates and payments
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 

Similar to PP2 - Assignment

Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice IIseenyeeyong
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2Shze Hwa Lee
 
Pp2 coursework 2 brief
Pp2 coursework 2  briefPp2 coursework 2  brief
Pp2 coursework 2 briefDoreen Yeo
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708Pang Khai Shuen
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group AssignmentLin Hui
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignmentfareezsham
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808ashleyyeap
 
PP1 Project 3 Cover letter
PP1 Project 3 Cover letterPP1 Project 3 Cover letter
PP1 Project 3 Cover letterTeo Kean Hui
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxMahSobeh
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011Maatla Moadi
 
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxThe importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxMy own
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Yee Len Wan
 

Similar to PP2 - Assignment (20)

Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Pp2 coursework 2 brief
Pp2 coursework 2  briefPp2 coursework 2  brief
Pp2 coursework 2 brief
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708
 
Pp2 asignment-1
Pp2 asignment-1Pp2 asignment-1
Pp2 asignment-1
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group Assignment
 
Pp2 final report
Pp2 final reportPp2 final report
Pp2 final report
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignment
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
Cl report final
Cl report finalCl report final
Cl report final
 
PP1 Project 3 Cover letter
PP1 Project 3 Cover letterPP1 Project 3 Cover letter
PP1 Project 3 Cover letter
 
Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptx
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
Practice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fiPractice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fi
 
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxThe importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 

More from lucaschinsheng

Building economics final assignment report
Building economics final assignment reportBuilding economics final assignment report
Building economics final assignment reportlucaschinsheng
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.lucaschinsheng
 
Glodon bim software presentation slide
Glodon bim software presentation slideGlodon bim software presentation slide
Glodon bim software presentation slidelucaschinsheng
 
Management science assignment report.
Management science assignment report.Management science assignment report.
Management science assignment report.lucaschinsheng
 
Energy efficient ventilation system
Energy efficient ventilation systemEnergy efficient ventilation system
Energy efficient ventilation systemlucaschinsheng
 
Enbe final project process
Enbe final project processEnbe final project process
Enbe final project processlucaschinsheng
 
Enbe final project report efkairia
Enbe final project report efkairiaEnbe final project report efkairia
Enbe final project report efkairialucaschinsheng
 
Introduction to construction industy final project
Introduction to construction industy final projectIntroduction to construction industy final project
Introduction to construction industy final projectlucaschinsheng
 
Interior Architecture Drawing
Interior Architecture DrawingInterior Architecture Drawing
Interior Architecture Drawinglucaschinsheng
 
Cl project 2 individual part
Cl project 2 individual partCl project 2 individual part
Cl project 2 individual partlucaschinsheng
 
E portfolio enbe project 1
E portfolio enbe project 1E portfolio enbe project 1
E portfolio enbe project 1lucaschinsheng
 

More from lucaschinsheng (17)

Cl presentation
Cl presentationCl presentation
Cl presentation
 
Building economics final assignment report
Building economics final assignment reportBuilding economics final assignment report
Building economics final assignment report
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.
 
Glodon bim software presentation slide
Glodon bim software presentation slideGlodon bim software presentation slide
Glodon bim software presentation slide
 
Management science assignment report.
Management science assignment report.Management science assignment report.
Management science assignment report.
 
Energy efficient ventilation system
Energy efficient ventilation systemEnergy efficient ventilation system
Energy efficient ventilation system
 
Tj 3 5senses in kl
Tj 3 5senses in klTj 3 5senses in kl
Tj 3 5senses in kl
 
Enbe final project process
Enbe final project processEnbe final project process
Enbe final project process
 
Enbe final project report efkairia
Enbe final project report efkairiaEnbe final project report efkairia
Enbe final project report efkairia
 
Introduction to construction industy final project
Introduction to construction industy final projectIntroduction to construction industy final project
Introduction to construction industy final project
 
Ici magazine
Ici magazineIci magazine
Ici magazine
 
Interior Architecture Drawing
Interior Architecture DrawingInterior Architecture Drawing
Interior Architecture Drawing
 
Cl final project
Cl final projectCl final project
Cl final project
 
Cl project 2 individual part
Cl project 2 individual partCl project 2 individual part
Cl project 2 individual part
 
Tj 2 enbe
Tj 2 enbeTj 2 enbe
Tj 2 enbe
 
Tj 1 enbe
Tj 1 enbeTj 1 enbe
Tj 1 enbe
 
E portfolio enbe project 1
E portfolio enbe project 1E portfolio enbe project 1
E portfolio enbe project 1
 

Recently uploaded

Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........LeaCamillePacle
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxsqpmdrvczh
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 

Recently uploaded (20)

Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptx
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 

PP2 - Assignment

  • 1. 1 SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN PROFESSIONAL PRACTICE 2 (QSB 3614) SEMESTER 5 COURSEWORK NO. 2 BACHELOR OF QUANTITY SURVEYING (HONOURS) NAME & STUDENT ID: NG SENG HE 0323037 HONG KAI YIN 0323361 LAU CHIN SHENG 0317899 SIONG JIA YII 0317239 LIU WEI QIAN 0322969 ABD’ALLAH SAIEF-UL-HAQQ HOOSSAINSAEB 0324556
  • 2. 2 TABLE OF CONTENT A. Coursework No. 2 Questions 3~7 B. Question 1 answer 8~14 C. Question 2 answer 15~16 D. Question 3 answer 17~22
  • 3. 3 SCHOOL OF ARCHITECTURE · BUILDING · DESIGN Centre for Modern Architecture Studies in Southeast Asia Bachelor of Quantity Surveying (Honours) PROFESSIONAL PRACTICE [QSB 3614] 1. This assignment shall make up 15% weightage ofthe final marks. 2. This is a group assignment and shall be submitted in groups of 6 students. 3. Dateline for submission ofthis Coursework No. 2 is on or before 30th October 2017. Coursework No. 2 – Preparation of Final Account. You are appointed as the consulting Quantity Surveyor for a apartment project based on PAM Form of Contract 2006 (With Quantities). The summary of the Contract Sum is as follows: Bill No. 1 – Preliminaries RM 2,250,000.00 Bill No. 2 – Building Works RM 31,450,000.00 Bill No. 3 – Local Infrastructure Works RM 6,130,000.00 Bill No. 4 – P.C. and Provisional Sums RM 7,870,000.00 Contract Sum RM 47,700,000.00
  • 4. 4 Question 1. The tender drawings shows the apartment entrance arch with guardhouse but no details were provided. The Architect had suggested that these items be listed as Provisional Sum. However you have forgot about this item and did not include it in your tender document. The contract was awarded without it. The director would also like to know the significance and implications of this omission by their office. In addition, you are required to prepare a report to your director, explaining briefly the adjustments of the essential elements in your preparation of this project’s final account. (25 marks) Question 2. In accordance with clause 30.10 of the contract, the contractor duly submitted his Final Accounts within 6 months after the issuance of the Certificate of Practical Completion. You are then required to assess this application and prepare the Final Account for the apartment project based of the following valuations and adjustments made to the Contract Sum: (35 marks) Information provided are as follows: a. The Architect had granted the Contractor’s first application for extension of time and approved additional insurance premium amounting to RM 10,000.00 in accordance with clause 24 of the contract due to the delay in the completion of the works caused by the Employer’s late decision on the toilet design. In his second application for extension of time, the Contractor submitted an loss and expense claim for RM200,000.00 in his Final Accounts to you. Since the delay event is not a relevant event listed in Clause 23.8, the Architect had rejected the Contractor’s second application.
  • 5. 5 b. There are four variation orders carried out by the Contractor: Addition Omission i. Variation Order No. 1: RM 300,000.00 RM 200,000.00 Changes of toilet layout to suit Employer’s requirements. ii. Variation Order No. 2: RM 400,000.00 - New lift lobby at entrance. iii. Variation Order No. 3: Changes from premix roads RM 1,100,000.00 RM 900,000.00 to precast concrete paver blocks iv. Variation Order No. 4: Omission of glass partitions - RM 96,000.00
  • 6. 6 c. The following are the nominated sub-contractor’s accounts: Original P.C. & NSC’s Provisional Sums final account i. Lift Services: Profit @ 2% Attendance as item RM 1,700,000.00 RM 1,500,000.00 RM 34,000.00 RM 34,000.00 ii. Air Conditioning Services: Profit @ 2% Attendance as item RM 1,200,000.00 RM 1,000,000.00 RM 24,000.00 RM 24,000.00 iii. Electrical Services: Profit @ 2% RM 1,600,000.00 RM 2,100,000.00 RM 32,000.00 Attendance as item RM 32,000.00 iv. Provisional Sums: Entrance Porch RM 1,270,000.00 RM 1,050,000.00 RM 6,670,000.00
  • 7. 7 Question 3. Explain the basis on how the following variations may be finalised and priced during the Final Account stage: a. Relocation of an already installed timber door including sealing up the wall opening. Agreed at the site meeting for Contractor to claim based on Dayworks for labour, material and plant. (10 marks) b. Contractor need to provide computer equipment in the Preliminaries section but item was left unpriced, i.e. BQ item was left blank in the rate/amount column in the contract document. Subsequently, this item was omitted by the Architect. (10 marks) c. A wash trough as required and priced in the Preliminaries section was not constructed due to site constraints imposed later by the Employer. However, the vehicles leaving the site during construction were always kept clean including the public roads using water jet washing and full- timed workers. (10 marks) d. Mistake was made in the price for excavation through rocks at RM 15 per m3. Item was not rationalised during contract documentation. However,original quantity in BQ is 100 m3 but re- measured quantity is 2,000 m3. The Contractor submitted a claim for revised rates of RM 150 per m3 for the total quantity of 2,000 m3. (10 marks)
  • 9. 9 Final Account is the document showing the adjustments of the contract sum issued under clause 30.10. Clause 30.10 of the PAM Contract 2006 states that final account showing the necessary adjustment of the contract sum and the final account shall be completed by quantity surveyor within 6 months after receipt of all necessary documents, drawings and site data from contractor. It is a financial document indicating the final value of the works executed by Contractor and his sub-contractors. The purpose of Final Account is to establish the final contract value or final construction cost of the project. It also paves the way for the Architect to issue the Final Certificate and establish the final sum payable by the Employer or owing from the Contractor. A complete Final Account shall include the following elements: 1. Variation Works (clause 11.6) 2. Remeasurement of Provisional Quantities (clause 11.6(f)) 3. Omission of P.C. and Provisional Sum (clause 30.11(c)) 4. Adding-back of NSC’s and NS’ final accounts (clause 30.11(c)) 5. Adjustment of profit and attendance (clause 30.11 (c)) 6. Adjustment of Provisional Sum based on actual expended and omitted if not expended 7. Additional expenses claims (clause 11.7) 8. Loss and Expense claim (clause 24.4)
  • 10. 10 Variation Works Variation works often arise in the construction stage. According to clause 11.1, it is the alteration or modification of the design, quality and quantity of the Works. Variation works are the only thing that can contractually change the contract sum, which must first be formally instructed by an Architect through issuing Architect’s Instruction in writing form, and in specifically prepared form with “Architect’s Instruction” title and serial numbering as accordance to Clause 2.2. There are six rules to be applied in six different situations when undergoes the valuation of variation work as stated in Clause 11.6(a)-(f). Quantity Surveyor is required to determine the most suitable rules to be applied in the valuation of work. Remeasurement of Provisional Quantities Clause 11.6(f) indicates that provisional quantities in the bills may also be an important element in the Final Account. It shall be remeasured based on the actual quantities executed and valued based on the contract rates and prices. For example, the actual quantities of piling work or excavation work are barely known at the early stage of construction. Thus, the final amount payable to the Contractor shall be based on the quantities that has been remeasured upon the completion of the particular work. Prime Cost and Provisional Sum Prime Cost sum and Provisional sum are also the essential elements in the Final Account. Prime Cost sum are the sum of specialist work done by nominated sub-contractors which normally includes a percentage of profit and attendance, whereas Provisional sum is the allowance for some specific works which its quantities are not completely verifiable and cannot be itemized in the Bill of Quantities yet. Provisional sum is still to be included in the Bill of Quantities even though its quantities are not finalized.
  • 11. 11 Taking this case as an example: There are no details provided for the apartment entrance arch with guardhouse. However, provisional sums of this element are still required to be included in the Bill of Quantities as it may provide awareness to the client’s budget and allows for cost control purpose. On the Contractor side, Contractor need to include the provisional sum works so that he/she may plan the working programme to be done within the stipulated date. If the provisional sum is not included in the contract, dispute may arise and Contractor may be entitled to claim for Extension of Time. Architect is also required to issue an Architect’s Instruction to the Contractor for the execution of variation of work. Adding-back of NSC’s and NS’ final accounts The profits of Prime Cost sum and Provisional sum shall be omitted from the final account as stated in Clause 30.11 (c). This is because these sums are the estimation of Quantity Surveyor in the early stage and are subjected to change. The awarded nominated sub-contractors to execute the work shall submit the Final Account along with pro-rata amount of profit. It is then being added back based on Clause 30.11(c). The final adjustment will be made after the completion of works. Adjustment of Profit and Attendance Contractors are required to allow a percentage of profit and attendance for the Prime Cost sum. The percentage varies based on the risk and workload of the specialist work. However, the percentage of the profit will be adjusted in the final account based on pro-rata of the amount payable to the Nominated Sub-Contractors instead of using the original percentage of profit according to Clause 30.11(c). As for attendance, it is to ensure the Contractor to provide specific services required by sub-contractors. It is usually in the form of lump sum or fixed amount basis. Thus, the attendance in the final account shall be the same as in the contract.
  • 12. 12 Adjustment of Provisional Sum As mentioned earlier, Provisional sum is an estimation by Quantity Surveyor in the early stage for the specifics works or elements which have insufficient details to quantify them. In the final account stage, the provisional sum estimated shall be adjusted based on the actual expended as stated in Clause 30.11(d). If the provisional sum estimated is larger than the actual expended, an omission shall be made. In contrast, if the actual expended is larger than the provisional sum, an addition shall be made accordingly. Additional Expenses Claim When the contractor incurs additional expenses on the variation works, Clause 11.7 allows the contractor to claim for the additional expenses and include the sum into the Final Account. There are a 2 steps procedure the Contractor must follow in order to claim for the additional expenses based on Clause 11.7(a) & (b). First, Contractor must submit a written notice to the Architect for the intention to claim for additional expenses supported with all necessary calculations. Such notice shall be given within 28 Days of the issuance of the Architect’s Instruction to execute the variation of work. The next step is the Contractor shall send the complete particulars of the claim to the Architect and Quantity Surveying within 28 Days upon the completion of the variation of work. Loss and Expense Claim The Contractor is able to claim for the loss and/or expense when he/she has incurred the loss and/or expense due to the regular progress of work has been materially affected. The matters that may materially affected the progress of work are stated in Clause 24.3. The Contractor must also follow a 2-step procedure to claim for the loss and/or expense according to Clause 24.1(a) & (b). The 2-step procedure is quite similar to the claim for additional expenses. The amount of loss and/or expenses approved by the Architect shall then be included in the contract sum and Final Account accordingly based on Clause 24.4.
  • 13. 13 Significance and Implication of Omission According to Pam contract 2006 Clause 11, the item that were forgotten to include in the provisional sum which are the apartment entrance arch with guardhouse will then be treated as a variation. This is because refer to Clause 11.1(a), it expresses the term ‘variation’ as the addition, omission or substitution of any work. Hence, in this case it is applicable to treat the forgotten item mentioned above as an addition of work to the project. Furthermore, refer to Clause 11.4 which stated the Architect shall issue AI (Architect’s Instruction) in regard to expenditure of provisional sum included in the Contract Bills. In Clause 11.2, the architect may issue an AI ordering a variation or sanctioning any variation to allow the contractor to carry out the such works as instructed by architect with due diligence and expedition. Other than that, according to Clause 11.6(f), in respect of Provisional quantity, the quantity stated in the Contract Documents shall be re-measured by the Quantity surveyor based on the actual quantities executed. In this case, the apartment entrance arch and guardhouse are considered as provisional quantities and according to Clause 11.6(a), where the item that with similar character to the project/work, executed under similar conditions as and does not significantly change the quantity of work as set out in the Contract Documents, the rate and price in the Contract Document shall determine the valuation. On the other hand, refer to Clause 11.6(c) where work is not of a similar character to work as set out in the contract documents, the valuation shall be at fair market rates and prices determined by the Quantity surveyor, meaning to say if there is any new item/work that is no any similar item/work that covered or included in Contract Document, the Quantity Surveyor shall determine the valuation based on fair market rates and prices. Presume the total cost for the entrance arch and guardhouse is RM 20,000 and in Bill No.4 PC and Provisional Sums with the consist of 10% in contingencies. The amount allocate in contingencies is then be able to cover the cost of the entrance arch and guardhouse. However, if there are no contingencies allowed in Bill No.4. then the addition of cost will be treated as a variation order and the contract sum will be increased. Therefore, the final contract sum is RM47,720,000.00
  • 14. 14 Besides, the act of treating the apartment arch and guardhouse as a VO will also granting a chance to contractor to claim for Extension of Time (EOT) which we can refer from Clause 23.1, if the contractor is of the opinion that the completion of the Works is or will be delayed beyond the Completion Date by of the Relevant Events stated in Clause 23.8 (In this case is refer to Clause 23.8(g), which is compliance with Ai issued by the Architect under Clauses 1.4,11.2 and 21.4) he may apply for an extension of time with the provided procedure stated in the PAM. Hence, although the completion date is over, the employer is still didn’t entitle to impose Liquidated damages because of the valid entitlement of EOT for contractor. In conclusion, the consequences caused by the mistake/error made by the Quantity Surveyor is tremendously affected to both parties which are employer and contractor in the way in contracture dispute or delaying the completion date. Moreover, due to this incident. The reputation of the quantity surveying consultant firm will be affected and the employer will lose their faith toward the firm.
  • 16. 16 Project : Construction and Completion of Apartment Employer : Professional Development Sdn Bhd Contractor : Smart Builder Corporation FINAL ACCOUNT 1.0 Original Contract Sum 2.0 Less: P.C. & Provisional Sums RM RM 47,700,000.00 2.1 Lift Services 1,700,000.00 2.2 Air Conditioning Services 1,200,000.00 2.3 Electrical Services 1,600,000.00 2.4 Provisional Sums: Entrance Porch 1,270,000.00 2.5 Contingencies 1,920,000.00 7,690,000.00 7,690,000.00 2.6 Profit and Attendance a. Profit @ 2% of RM 4,500,000.00 90,000.00 b. Attendance @ lump sum 90,000.00 180,000.00 180,000.00 Total Builder's works 55,570,000.00 3.0 Add: Variation Works (V.O. Nos 1 - 4) Total Additions 1,800,000.00 Total Omissions 1,196,000.00 Nett Additions 604,000.00 604,000.00 56,174,000.00 4.0 Add back: NSCs' Final Account 4.1 Lift Services 1,500,000.00 4.2 Air Conditioning Services 1,000,000.00 4.3 Electrical Services 2,100,000.00 4.4 Provisional Sums: Entrance Porch 1,050,000.00 5,650,000.00 5,650,000.00 4.5 Profit and Attendance a. Profit @ 2% of RM 5,650,000.00 113,000.00 b. Attendance @ lump sum 113,000.00 226,000.00 226,000.00 5.0 Contractual Claims: Additional Expenses 10,000.00 FINAL CONTRACT VALUE 62,060,000.00
  • 18. 18 Question 3 Explain the basis on how the following variations may be finalised and priced during the Final Account stage: a. Relocation of an already installed timber door including sealing up the wall opening. Agreed at the site meeting for Contractor to claim based on Dayworks for labour, material and plant. Based on the situation mentioned above, the relocation of an already installed timber door including with sealing up the wall opening is considered as work cannot be properly measured and valued in accordance with Clause 11.6 (a), (b) or (c), the Contractor shall be allowed to claim the daywork rates in the Contract Documents according to Clause 11.6 (d)(i) or actual cost plus 15% if there are no such daywork rates in the Contract Documents Clause 11.6 (d)(ii). The relocation of an already installed timber work includes the works for removal of timber door, making a new opening for the door and sealing up the previous wall opening. Removal of timber door and making of a new opening requires general labourers and incurred labour cost. On the other hand, the sealing materials like bricks, cement and sand, plaster and paint where the rates are according to the rates stated in the Bill of Quantities. As regards to the rates, the Quantity Surveyor shall refer the breakdown rates stated in the Bill of Quantities as the basis of new rates for the sealing up of wall opening for the material used such as bricks, cement and sand, plaster and paint. The labourers involved would be bricklayer, plasterer and painter. For the relocation of timber door, there will be no additional construction plant needed to carry out the works. In either case of Clause 11.6 (d)(i) or Clause 11.6 (d)(ii), the Contractor then shall provide voucher specifying the time spent daily on the work, the workers’ names, materials, scaffolding and transport used. This voucher has to be signed by the Site Agent and verified by the Site Staff and deliver to the Architect and Quantity Surveyor at weekly intervals with the final records delivered not later than fourteen (14) Days after the relocation of timber door has been completed.
  • 19. 19 b. Contractor need to provide computer equipment in the Preliminaries section but item was left unpriced, i.e. BQ item was left blank in the rate/amount column in the contract document. Subsequently, this item was omitted by the Architect. When item is left unpriced in the Preliminaries section, it is deemed to be included in the tender price as lump sum. Under Clause 11.6 (a), where work is of a similar character to, is executed under similar conditions as, and does not significantly change the quantity of work as set out in the Contract Documents, the rates and prices in the Contract Documents shall determine the valuation. The omitting of computer is of a similar character, executed under similar conditions and does not significantly change the quantity of work, therefore, the Quantity Surveyor shall omit the cost of computer equipment based on current fair market price or cost from previous contract documents of similar projects.
  • 20. 20 c. A wash trough as required and priced in the Preliminaries section was not constructed due to site constraints imposed later by the Employer. However, the vehicles leaving the site during construction were always kept clean including the public roads using water jet washing and full-timed workers. The total value of wash trough listed in the prelim should be eliminated entirely. After that, a variation order should be provided for this particular wash trough item where it is in accordance with Clause 11.6 (d) as it met the pre-condition of work that could not be properly measured and valued. This clause dictates that it should apply the said daywork rates stated in the contract or actual cost with an additional 15%. With that said, it should be noted that this only applies if it meets the criteria or pre-condition that the works executed cannot be properly measured or valued. For example, the total amount of water that has been used to wash the trucks cannot be properly quantified because there is no dedicated water meter for this item, they share the water meter with other amenities. This is a type of reimbursement to the Contractor with a certain amount of profits. However, if there are daywork rates stated in the contract, then it should be used for the valuation including a profit percentage for the Contractor. Finally, the works that are executed shall be recorded and verified by the Site Staff and be certified by the Consultants and Architects.
  • 21. 21 d. Mistake was made in the price for excavation through rocks at RM 15 per m3. Item was not rationalised during contract documentation. However, original quantity in BQ is 100 m3 but re-measured quantity is 2,000 m3. The Contractor submitted a claim for revised rates of RM 150 per m3 for the total quantity of 2,000 m3. Based on the situation, rock excavation has been priced wrongly for RM15 per m3 and the revised rate is RM 150 per m3. The quantity for rock excavation is measured wrongly as well. 100 m3 is recorded in Bills of Quantities instead of 2000 m3. In this case, Contractor will face a lost due to the irrationalised rates priced during contract documentation and the quantity measured initially. Therefore, Contractor has the right to claim his loss and expense on the outstanding work for revised rate. Clause 11.6 (b) empowers that where work is of a similar character to work as set out in the contract doc but is not executed under similar conditions or is executed under similar conditions but there is a significant change in the quantity of work carried out, the rates and prices in the contract doc shall be basis for determining valuation which shall include a fair adjustment in the rates to take into account such difference. It means that Contractor can claim it by using the contract rates and price but with fair adjustment to the rates for the difference with pre-conditions: (a) the work must be of similar character but it is not executed under similar conditions; (b) the work must be of similar character but significant change in the quantity of work. Hence, the revised amount that has been adjusted and to be claimed by Contractor is RM 286,500 following by the calculation below.
  • 22. 22 Calculation: a) RM 15 per m3 100 m3 x RM 15 per m3 = RM 1,500 b) RM 150 per m3 1900 m3 x RM 150 per m3 = RM 285,000 Revisedrates = RM 1,500 + RM 285,000 = RM 286,500