SlideShare a Scribd company logo
1 of 26
Download to read offline
CIPAA 2012
THE STATUTORY
ADJUDICATION
WHAT IS CIPAA?
2
Construction Industry Payment and Adjudication Act
22 June 2012
CIPAA enacted in
Parliament
15 April 2014
CIPAA came into
operation
COVERAGE OF CIPAA 2012
Responsibility
of KLRCA
Competency Standard
& criteria of adjudicators
Standard Fees &
Expense
of KLRCA
Factors
to be considered in
awarding costs
Governing Fee &
Expense
of Adjudicators
3
IMPORTANT CHARACTERISTICS OF CIPAA
Temporary decision
It does not constitute
finality but immediately
binding pending final
resolution by arbitration.
No contract out allowed
Entering into a
supplementary contract
among contracting
parties is prohibited.
Statutory adjudication
Impose on payment
related disputes in
construction industry.
4
MAIN OBJECTIVES OF CIPAA 2012
▣ A cheaper and speedy dispute resolution through adjudication
▣ Ensure and encourage regular and timely payment
▣ Eliminate ‘pay when paid’ arrangement (Sec 35)
▣ Reduce cash flow related problems
▣ Provide remedies for payment recovery
▣ A mandatory statutory process
5
Applications & Restrictions of CIPAA
6
SEC 2
CIPAA applies to:
- Written construction
contract
- Related to construction
work
- Wholly / partly in M’sia
SEC 3
Not applicable to a
construction contracts
by a natural person
SEC 4
Restricted to claims for
payment of work done
or services rendered
ADJUDICATION PROCESS OF CIPAA 2012
7
● 8
ADJUDICATION DECISION
Section 13 of CIPAA 2012
Adjudication decision is binding unless
Fraud / Bribery
Denial of Natural
Justice
Not independently /
impartially
Excess of his jurisdiction
Written agreement between parties
The dispute is finally decided by
arbitration / court
9
ADJUDICATION DECISION
Suspend performance
&
Reduce the rate of progress of
performance/consultancy
services
Winner may enforce adjudication decision by:
Apply to high court
Seek direct payment from
employer
10
ADJUDICATION AUTHORITY
K L R C A
Kuala Lumpur Regional Centre for Arbitration
(Part V of CIPAA)
11
K L R C A
Kuala Lumpur Regional Centre for Arbitration
(Part V of CIPAA)
KLRCA CIPAA CIRCULAR 01
On Section 41 of CIPAA 2012
NOTHING IN THE ACT
shall affect any proceedings relating to any PAYMENT DISPUTE
under a construction contract which had been commenced an any court
or arbitration before the coming into operation of the act.
12
K L R C A
Kuala Lumpur Regional Centre for Arbitration
(Part V of CIPAA)
KLRCA CIPAA CIRCULAR 03
“Construction Contract Made in Writing”
1. If the contract is made in writing
2. If contract is made by exchange of communications in writing;
or
3. If contract is evidenced in writing
13
POSSIBLE IMPACT OF CIPAA 2012
-
Long time Frame for
adjudication process
Respondents
disadvantaged
Professionals may,
similarly to arbitration
& litigation
Insufficient trained
adjudicators
Unaware &
ill-prepared on the
effect of the Act
Concurrent causes of
action increase
litigation
Q1.
If Con. & Em. enter into a written contract without a certain
payment term, how Con. receives his payment with the help of
CIPAA?
14
“Sec 36(4)
The due date for payment under subsection (3) is thirty calendar
days from the receipt of the invoice.
- Provided contractor must prove invoice and progress claim
15
Q2.
How a winning party enforce the adjudication decision?
16
“
1. Register the decision as a Court Judgment or Order and
enforce the decision as if it is a judgment or order of the High
Court.
2. Suspend the work
3. Seek direct payment from the principal of losing party
17
Q3.
If the non-paying party fail to respond to the payment claim within
10 working days, can the unpaid party proceed to adjudication
process?
18
“
- Yes
- If the non-paying party fails to respond, it is deemed to have
disputed the entire payment claims under Section 6 (4)
- Under Section 7, the unpaid party has the right to refer a
dispute to adjudication after the expiry of the period to serve
a payment response
19
Q4.
If the adjudicator rejects his appointment or fails to indicate his
acceptance of the appointment, what can the parties do?
20
“
Section 22 (3)
If the adjudicator rejects his appointment or fails to indicate his
acceptance of the appointment within the period specified in
subsection (2), the parties may proceed to appoint another
adjudicator in the manner provided under section 21.
21
Q5.
What is the responsibility of KLRCA in Malaysia?
22
“
To determine the standard and criteria required of an
adjudicator in Malaysia
To determine the term and fee of the appointment
23
Q6.
Give two possible impact of CIPAA 2012
24
“Comparatively long time frame for adjudication process
compromise the very aim of the act to expedite cash flow.
Respondents generally disadvantaged if ‘ambushed’ by
claimants.
25
Thank you !

More Related Content

What's hot

Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document xingxin_GOh
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 
LAND LAW 1 TOL 2014
LAND LAW 1 TOL 2014LAND LAW 1 TOL 2014
LAND LAW 1 TOL 2014xareejx
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-paymentArthur Wilson
 
Dealings and registration
Dealings and registrationDealings and registration
Dealings and registrationFAROUQ
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final ReportArissa Loh
 
2) int walls element query sheet
2) int walls element   query sheet2) int walls element   query sheet
2) int walls element query sheetJeanne Hoo
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityPang Khai Shuen
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in MalaysiaDayat Mohamad
 
definition of land / Law of fixture
definition of land / Law of fixturedefinition of land / Law of fixture
definition of land / Law of fixtureIntan Muhammad
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...Zainab Zainordin
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONFarah Sham
 

What's hot (20)

Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Construction law cl3 (completed)
Construction law cl3 (completed)Construction law cl3 (completed)
Construction law cl3 (completed)
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
LAND LAW 1 TOL 2014
LAND LAW 1 TOL 2014LAND LAW 1 TOL 2014
LAND LAW 1 TOL 2014
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-payment
 
Dealings and registration
Dealings and registrationDealings and registration
Dealings and registration
 
Site possession
Site possessionSite possession
Site possession
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
 
2) int walls element query sheet
2) int walls element   query sheet2) int walls element   query sheet
2) int walls element query sheet
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
definition of land / Law of fixture
definition of land / Law of fixturedefinition of land / Law of fixture
definition of land / Law of fixture
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATION
 
Strata titles
Strata titlesStrata titles
Strata titles
 

Similar to Seminar - CIPAA 2012

Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspensionbreyerhanna
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxPujanNeupane6
 
Construction for Accountants - Part Two
Construction for Accountants - Part TwoConstruction for Accountants - Part Two
Construction for Accountants - Part TwoRedchip
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7ashleyyeap
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsEversheds Sutherland
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsRobert MacDonald
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesAMILA GAYAN
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Public sector breakfast club, January 2017 - Exeter
Public sector breakfast club, January 2017 - ExeterPublic sector breakfast club, January 2017 - Exeter
Public sector breakfast club, January 2017 - ExeterBrowne Jacobson LLP
 
KEY NOTE- IBC DESIGN (BEFORE& DURING & AFTER COVID-19)- PPT.pptx
KEY NOTE- IBC DESIGN (BEFORE& DURING & AFTER COVID-19)- PPT.pptxKEY NOTE- IBC DESIGN (BEFORE& DURING & AFTER COVID-19)- PPT.pptx
KEY NOTE- IBC DESIGN (BEFORE& DURING & AFTER COVID-19)- PPT.pptxRRR Chambers
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aColin Tomlinson
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Colin Tomlinson
 

Similar to Seminar - CIPAA 2012 (20)

Colin Harris and Mark Kenney
Colin Harris and Mark KenneyColin Harris and Mark Kenney
Colin Harris and Mark Kenney
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspension
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptx
 
Turkey Presentation, Erkan Ozdemir, PPA, Review and remedies procedures in pr...
Turkey Presentation, Erkan Ozdemir, PPA, Review and remedies procedures in pr...Turkey Presentation, Erkan Ozdemir, PPA, Review and remedies procedures in pr...
Turkey Presentation, Erkan Ozdemir, PPA, Review and remedies procedures in pr...
 
Construction for Accountants - Part Two
Construction for Accountants - Part TwoConstruction for Accountants - Part Two
Construction for Accountants - Part Two
 
Cl report final
Cl report finalCl report final
Cl report final
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
 
CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claims
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and Penalties
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
CIAC-ADR_PPT.pptx
CIAC-ADR_PPT.pptxCIAC-ADR_PPT.pptx
CIAC-ADR_PPT.pptx
 
Public sector breakfast club, January 2017 - Exeter
Public sector breakfast club, January 2017 - ExeterPublic sector breakfast club, January 2017 - Exeter
Public sector breakfast club, January 2017 - Exeter
 
KEY NOTE- IBC DESIGN (BEFORE& DURING & AFTER COVID-19)- PPT.pptx
KEY NOTE- IBC DESIGN (BEFORE& DURING & AFTER COVID-19)- PPT.pptxKEY NOTE- IBC DESIGN (BEFORE& DURING & AFTER COVID-19)- PPT.pptx
KEY NOTE- IBC DESIGN (BEFORE& DURING & AFTER COVID-19)- PPT.pptx
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 a
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2
 

More from Kai Yun Pang

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiKai Yun Pang
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - ReportKai Yun Pang
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump StationKai Yun Pang
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectKai Yun Pang
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial AppraisalKai Yun Pang
 
Assignment - Financial Appraisal
Assignment - Financial Appraisal Assignment - Financial Appraisal
Assignment - Financial Appraisal Kai Yun Pang
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Kai Yun Pang
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S HotelKai Yun Pang
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study ReportKai Yun Pang
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - JournalKai Yun Pang
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service Kai Yun Pang
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final AccountKai Yun Pang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerKai Yun Pang
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - QuestionKai Yun Pang
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK LandKai Yun Pang
 
Assignment - Financial Analysis
Assignment - Financial AnalysisAssignment - Financial Analysis
Assignment - Financial AnalysisKai Yun Pang
 
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Kai Yun Pang
 

More from Kai Yun Pang (20)

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau Langkawi
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - Report
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump Station
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft Project
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - Financial Appraisal
Assignment - Financial Appraisal Assignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S Hotel
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study Report
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - Journal
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK Land
 
Assignment - Financial Analysis
Assignment - Financial AnalysisAssignment - Financial Analysis
Assignment - Financial Analysis
 
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)
 

Recently uploaded

Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxJiesonDelaCerna
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 

Recently uploaded (20)

Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 

Seminar - CIPAA 2012

  • 2. WHAT IS CIPAA? 2 Construction Industry Payment and Adjudication Act 22 June 2012 CIPAA enacted in Parliament 15 April 2014 CIPAA came into operation
  • 3. COVERAGE OF CIPAA 2012 Responsibility of KLRCA Competency Standard & criteria of adjudicators Standard Fees & Expense of KLRCA Factors to be considered in awarding costs Governing Fee & Expense of Adjudicators 3
  • 4. IMPORTANT CHARACTERISTICS OF CIPAA Temporary decision It does not constitute finality but immediately binding pending final resolution by arbitration. No contract out allowed Entering into a supplementary contract among contracting parties is prohibited. Statutory adjudication Impose on payment related disputes in construction industry. 4
  • 5. MAIN OBJECTIVES OF CIPAA 2012 ▣ A cheaper and speedy dispute resolution through adjudication ▣ Ensure and encourage regular and timely payment ▣ Eliminate ‘pay when paid’ arrangement (Sec 35) ▣ Reduce cash flow related problems ▣ Provide remedies for payment recovery ▣ A mandatory statutory process 5
  • 6. Applications & Restrictions of CIPAA 6 SEC 2 CIPAA applies to: - Written construction contract - Related to construction work - Wholly / partly in M’sia SEC 3 Not applicable to a construction contracts by a natural person SEC 4 Restricted to claims for payment of work done or services rendered
  • 7. ADJUDICATION PROCESS OF CIPAA 2012 7
  • 8. ● 8 ADJUDICATION DECISION Section 13 of CIPAA 2012 Adjudication decision is binding unless Fraud / Bribery Denial of Natural Justice Not independently / impartially Excess of his jurisdiction Written agreement between parties The dispute is finally decided by arbitration / court
  • 9. 9 ADJUDICATION DECISION Suspend performance & Reduce the rate of progress of performance/consultancy services Winner may enforce adjudication decision by: Apply to high court Seek direct payment from employer
  • 10. 10 ADJUDICATION AUTHORITY K L R C A Kuala Lumpur Regional Centre for Arbitration (Part V of CIPAA)
  • 11. 11 K L R C A Kuala Lumpur Regional Centre for Arbitration (Part V of CIPAA) KLRCA CIPAA CIRCULAR 01 On Section 41 of CIPAA 2012 NOTHING IN THE ACT shall affect any proceedings relating to any PAYMENT DISPUTE under a construction contract which had been commenced an any court or arbitration before the coming into operation of the act.
  • 12. 12 K L R C A Kuala Lumpur Regional Centre for Arbitration (Part V of CIPAA) KLRCA CIPAA CIRCULAR 03 “Construction Contract Made in Writing” 1. If the contract is made in writing 2. If contract is made by exchange of communications in writing; or 3. If contract is evidenced in writing
  • 13. 13 POSSIBLE IMPACT OF CIPAA 2012 - Long time Frame for adjudication process Respondents disadvantaged Professionals may, similarly to arbitration & litigation Insufficient trained adjudicators Unaware & ill-prepared on the effect of the Act Concurrent causes of action increase litigation
  • 14. Q1. If Con. & Em. enter into a written contract without a certain payment term, how Con. receives his payment with the help of CIPAA? 14
  • 15. “Sec 36(4) The due date for payment under subsection (3) is thirty calendar days from the receipt of the invoice. - Provided contractor must prove invoice and progress claim 15
  • 16. Q2. How a winning party enforce the adjudication decision? 16
  • 17. “ 1. Register the decision as a Court Judgment or Order and enforce the decision as if it is a judgment or order of the High Court. 2. Suspend the work 3. Seek direct payment from the principal of losing party 17
  • 18. Q3. If the non-paying party fail to respond to the payment claim within 10 working days, can the unpaid party proceed to adjudication process? 18
  • 19. “ - Yes - If the non-paying party fails to respond, it is deemed to have disputed the entire payment claims under Section 6 (4) - Under Section 7, the unpaid party has the right to refer a dispute to adjudication after the expiry of the period to serve a payment response 19
  • 20. Q4. If the adjudicator rejects his appointment or fails to indicate his acceptance of the appointment, what can the parties do? 20
  • 21. “ Section 22 (3) If the adjudicator rejects his appointment or fails to indicate his acceptance of the appointment within the period specified in subsection (2), the parties may proceed to appoint another adjudicator in the manner provided under section 21. 21
  • 22. Q5. What is the responsibility of KLRCA in Malaysia? 22
  • 23. “ To determine the standard and criteria required of an adjudicator in Malaysia To determine the term and fee of the appointment 23
  • 24. Q6. Give two possible impact of CIPAA 2012 24
  • 25. “Comparatively long time frame for adjudication process compromise the very aim of the act to expedite cash flow. Respondents generally disadvantaged if ‘ambushed’ by claimants. 25