A Claim submitted by the
contractor during project of:
Development of internal
Roads in GAZA
MAHMOUD SOBEH
contents
Background
Contract duration
Issue 1
Issue 2
Issue 3
Documents
Project background
Development of internal roads in GAZA
Infra-structure
$500K
Refugee camp
3 roads 6+8+9
manual labor and bulldozers together
Project background
Parties
Employer contractor
Municipalit
y
Eng.
Association
N&I F
locals
Contract performance time
2020 2021 2022
10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3
1/11/20 1/4/21 9/6/21 31/10/21 28/2/22
Planned (contract) duration
Bid closure date
stopping
period actual duration
3/11/20 3/04/21 24/6
12/7
29/6
29/10/2021
Critical path
lighting
poles
Tiles
base-
course
Curb-
stone
sewage
excava
tion
mobili
zation
water
supply
Rain-
water
Variations and change orders
The project involved a set of change orders that had
been agreed upon, and given an additional 33 days of
time. Execution prices have been agreed upon, and
there is no dispute over them.
List of Major Issues and Problems
1. Delay due to the Employer's failure to handover the site.
1.2. Suspension of work by direct order from the employer
3. Material Prices Increase
1. Delay due to the Employer's
failure to handover the site.
a. From the 1st day encroachments problem was existed, and had been noticed
and informed by contractor. (The correspondence below shows that)
b. The contractor started mobilization works, stocking the raw materials, hiring
the work team, and starting to prepare the shop drawings.
Encroachments report (examples)
street 6 Street 8 Street 9
On June 9, 2021, the problem was resolved in Streets 8 + 9, and the contractor was able
to start work on these two streets, and an understanding was reached between the agency
and the contractor in an official meeting, provided that the agency considers positively
the claim for compensation presented by the contractor, and that it removes any
obstruction to work for the same reason that comes in the future, and that the contractor
has the right to compensation in the event of damage as a result of that, as the paragraph
of the minutes of the meeting stipulates that
Contract performance time
2020 2021 2022
10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3
1/11/20 1/4/21 9/6/21 31/10/21 28/2/22
Planned (contract) duration
Bid closure date
stopping
period actual duration
3/11/20 3/04/21 24/6
12/7
29/6
29/10/2021
work interruption period
month
day 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13
st 8+9
st 6
total state
Jun-21 Jul-21
15 days 13 days
5 days
the planned final delivery date for the project was on
October 29, 2021,
after updating the schedule and entering the stopping
work days according to the work reports the delivery
date became January 23, 2022, which means an
increase of 86 days.
Relevant Contract Provisions
The employer's failure to hand over the site led to a breach of the
contractor's right to access the work site, and this right is stipulated in
the following contractual articles:
a) In the contract documents, it was stated in the document called (infra-structure specification),
section1: work site, paragraph 1.1 called (Right of way and work area), as follows:
(The AGENCY will provide all the necessary right of way and will designate
the access Roads to the Site which the Contractor will be permitted to use The
Work area, i.e., the area or areas where the Contractor may set up his offices,
stores, workshops, yards for mechanical plant, etc. and transport depots, will
be shown on the Drawings or designated by the Director of Works).
Relevant Contract Provisions
b) In the contract documents, General Conditions, Article 3b stated
that (IF the Agency fail to hand over the Site to the Contractor within
the period specified or within the period agree in writing, the
Contractor may serve notice on the Agency, as provided for in Article
19, terminating the Contract).
Relevant Contract Provisions
c) When referring to the unified FIDIC contract, we found that the
first duties of the employer are to enable the contractor to access the
work site and possess all its parts at the time specified for the
implementation of the contract, as Paragraph 2.1 entitled Right of
Access to the site states:
(The Employer shall give the Contractor right of access to, and
possession of, all parts of the Site within the time (or times) stated
in the Appendix to Tender.
Relevant Contract Provisions
d) The same paragraph also stipulated the contractor’s entitlement to claim
compensation in the event that the employer was unable to hand over the
site and was exposed to damage because of that, as it was stated in it (If the
Contractor suffers delay and/or incurs Cost as a result of a failure by the
Employer to give any such right or Possession within such time, the
Contractor shall give notice to the Engineer and shall be entitled subject to
Sub-Clause 20.1 [Contractor's Claims] to: (a) an extension of time for any
such delay, if completion is or will be delayed, under Sub-Clause 8.4
[Extension of Time for Completion], and (b) payment of any such Cost plus
reasonable profit, which shall be included in the Contract Price.
Required compensation, issue no 1
Ex. Of Time
•77 days
•28*50%= 14 days
•Total = 81 days
Payment
• Damages for one day=
$225
• Total damages= $18,225
List of Major Issues and Problems
1. Delay due to the Employer's failure to handover the site.
1.2. Suspension of work by direct order from the employer
3. Material Prices Increase
2. Suspension of work by direct order
from the employer
On June 24, 2021, the contractor submitted permission to start
the works as planned in the schedule on Street 8, 9 and in
accordance with the usual daily work procedures, and the agency
engineer agreed to that, and after starting the work, the agency
engineer requested to stop work by his order, after work on the
project was prohibited by the local residents. The problem lasted
for five days, when it was solved by the intervention of the
national and Islamic forces, the municipality, the Engineers
Association, the employer (the agency), and the neighborhood
committees
Relevant Contract Provisions
According to FIDIC, the contractor has the right to claim compensation from the
employer as a result of suspending the works in compliance with the employer's
order, as stated Clause 8.9 Consequences of Suspension:
If the Contractor suffers delay and/or incurs Cost from complying with the
engineer's instructions under Sub-Clause 8.8 [Suspension of Work] and/or from
resuming the work, the Contractor shall give notice to the Engineer and shall be
entitled subject to Sub- Clause 20.1 [Contractor's Claims] to:
A. an extension of time for any such delay, if completion is or will be delayed,
under Sub-Clause 8.4 [Extension of Time for Completion],
B. and payment of any such Cost, which shall be included in the Contract Price
Required compensation, issue no 2
Ex. Of Time
•5 days
Payment
• Damages for one day=
$1475
• Total damages= $7375
equipments
List of Major Issues and Problems
1. Delay due to the Employer's failure to handover the site.
1.2. Suspension of work by direct order from the employer
3. Material Prices Increase
3. Material Prices Increase
a. Rising raw material prices
There are huge price differences for raw materials
between the period of preparing and submitting bid
documents, which was in November 2020, and the
implementation period, which lasted until February
2022.
a. Rising raw material prices
This delay is due to a number of reasons:
1. The length of the period between the closing date of tenders and the
signing of the contract: it reached 150 days.
2. The delay caused by issue 1 + 2 delayed the supply of raw materials
by 86 days
3. Due to the delays, the contractor was forced to purchase raw
materials during the expensive period, after entering the war period
from May 11 to May 23, 2021, and the subsequent closure of the
crossings led to an increase in prices.
b. The decline
of the dollar
price.
The decline in the
price of the dollar
during the project by
11%, as it reached its
lowest level, at the
end of 2021
The problem is that the tender prices are in
dollars and the payments and costs paid by the
contractor are in shekels
Relevant Contract Provisions
According to sub-clause 13.8 of in FIDIC, it is prescribed
that the amounts payable to the contractor shall be adjusted
for rises or falls in the cost of labor, goods and other inputs to
the works, by the addition or deduction of the amounts
determined by the formula. The adjustment to be applied to
the amount otherwise payable to the contractor, as valued in
accordance with the appropriate schedule and certified in
payment certificates, shall be determined from formulas for
each of the currencies in which the contract price is payable.
Calculation of compensation (sample)
‫م‬
‫الصنف‬
‫الوحدة‬
‫الكمية‬
"
A
"
‫السعر‬
‫اثناء‬
‫التسعير‬
‫بالشيكل‬
"
B
"
‫السعر‬
‫عند‬
‫التنفيذ‬
‫بالشيكل‬
"
C
"
‫قيمة‬
‫الفرق‬
‫بالشيكل‬
D=C-B
‫اجمالي‬
‫الفرق‬
A*D
‫أوال‬
/
‫مواسير‬ ‫أسعار‬ ‫فروق‬
UPVC
1
‫امطار‬ ‫مياه‬ ‫تصريف‬ ‫مواسير‬
UPVC
‫قطر‬
400
‫ملم‬
‫ط‬ ‫م‬
40
160
240
80
3,200
2
‫امطار‬ ‫مياه‬ ‫تصريف‬ ‫مواسير‬
UPVC
‫قطر‬
315
‫ملم‬
‫ط‬ ‫م‬
40
103
150
47
1,880
3
‫صحي‬ ‫صرف‬ ‫مواسير‬
UPVC
‫قطر‬
250
‫ملم‬
‫ط‬ ‫م‬
115
68
85
17
1,955
Required compensation, issue no 3
‫البند‬
‫المبلغ‬
‫بالشيكل‬
‫أوال‬
/
‫مواسير‬ ‫أسعار‬ ‫فروق‬
UPVC
34,075
‫ثانيا‬
/
‫و‬ ‫والمناهل‬ ‫المسلح‬ ‫الباطون‬ ‫في‬ ‫المستخدم‬ ‫الحديد‬ ‫أسعار‬ ‫فروق‬
‫االسمنت‬
31,250
‫ثالثا‬
/
‫أسعار‬ ‫فرق‬ ‫نتيجة‬ ‫المستوردة‬ ‫الكهربائية‬ ‫المواد‬ ‫أسعار‬ ‫فروق‬
‫النقل‬
57,500
‫بالشيكل‬ ‫اإلجمالي‬
122,825
‫بالدوالر‬ ‫اإلجمالي‬
$ 37,792
List of Major Issues and Problems
1. Delay due to the Employer's failure to handover the site.
1.2. Suspension of work by direct order from the employer
3. Material Prices Increase
Summary of Required Compensation
Issue
Required Compensation
Compensation ($) Time (days)
Delay due to the Employer's failure to
handover the site
18,225 81
Suspension of work by direct order
from the employer (agency) 7,375 5
Material Prices Increase 37,792 -
Total 63,492 86
Documents
Documents
1.1. Correspondence
2. Contract documents
3. Meeting minutes
1.4. Daily report
1.5. Schedule (planned and revised)
CODING
1.D 1.1 – D 1.21
D 2.1 – D 2.5
D 3
D 4
D 5
Development of Internal Roads Claim

More Related Content

Similar to Development of Internal Roads Claim

Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignmentfareezsham
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final accountahmong4
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017DarrenTofu
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - AssignmentQuo Ming
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
ZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxFairFASST
 
11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen Antov11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen AntovAssen Antov
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2Shze Hwa Lee
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011Maatla Moadi
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAAvinash Kumar Gupta
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKegler Brown Hill + Ritter
 

Similar to Development of Internal Roads Claim (20)

Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignment
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final account
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - Assignment
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
ZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docx
 
11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen Antov11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen Antov
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
Tender
TenderTender
Tender
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Chapter 4- Contract Management
Chapter 4- Contract ManagementChapter 4- Contract Management
Chapter 4- Contract Management
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
 
NEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinarNEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinar
 

Recently uploaded

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 

Recently uploaded (20)

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 

Development of Internal Roads Claim

  • 1. A Claim submitted by the contractor during project of: Development of internal Roads in GAZA MAHMOUD SOBEH
  • 3. Project background Development of internal roads in GAZA Infra-structure $500K Refugee camp 3 roads 6+8+9 manual labor and bulldozers together
  • 5. Contract performance time 2020 2021 2022 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 1/11/20 1/4/21 9/6/21 31/10/21 28/2/22 Planned (contract) duration Bid closure date stopping period actual duration 3/11/20 3/04/21 24/6 12/7 29/6 29/10/2021
  • 7. Variations and change orders The project involved a set of change orders that had been agreed upon, and given an additional 33 days of time. Execution prices have been agreed upon, and there is no dispute over them.
  • 8. List of Major Issues and Problems 1. Delay due to the Employer's failure to handover the site. 1.2. Suspension of work by direct order from the employer 3. Material Prices Increase
  • 9. 1. Delay due to the Employer's failure to handover the site. a. From the 1st day encroachments problem was existed, and had been noticed and informed by contractor. (The correspondence below shows that) b. The contractor started mobilization works, stocking the raw materials, hiring the work team, and starting to prepare the shop drawings.
  • 11.
  • 12. On June 9, 2021, the problem was resolved in Streets 8 + 9, and the contractor was able to start work on these two streets, and an understanding was reached between the agency and the contractor in an official meeting, provided that the agency considers positively the claim for compensation presented by the contractor, and that it removes any obstruction to work for the same reason that comes in the future, and that the contractor has the right to compensation in the event of damage as a result of that, as the paragraph of the minutes of the meeting stipulates that
  • 13. Contract performance time 2020 2021 2022 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 1/11/20 1/4/21 9/6/21 31/10/21 28/2/22 Planned (contract) duration Bid closure date stopping period actual duration 3/11/20 3/04/21 24/6 12/7 29/6 29/10/2021
  • 14. work interruption period month day 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 st 8+9 st 6 total state Jun-21 Jul-21 15 days 13 days 5 days
  • 15. the planned final delivery date for the project was on October 29, 2021, after updating the schedule and entering the stopping work days according to the work reports the delivery date became January 23, 2022, which means an increase of 86 days.
  • 16.
  • 17. Relevant Contract Provisions The employer's failure to hand over the site led to a breach of the contractor's right to access the work site, and this right is stipulated in the following contractual articles: a) In the contract documents, it was stated in the document called (infra-structure specification), section1: work site, paragraph 1.1 called (Right of way and work area), as follows: (The AGENCY will provide all the necessary right of way and will designate the access Roads to the Site which the Contractor will be permitted to use The Work area, i.e., the area or areas where the Contractor may set up his offices, stores, workshops, yards for mechanical plant, etc. and transport depots, will be shown on the Drawings or designated by the Director of Works).
  • 18. Relevant Contract Provisions b) In the contract documents, General Conditions, Article 3b stated that (IF the Agency fail to hand over the Site to the Contractor within the period specified or within the period agree in writing, the Contractor may serve notice on the Agency, as provided for in Article 19, terminating the Contract).
  • 19. Relevant Contract Provisions c) When referring to the unified FIDIC contract, we found that the first duties of the employer are to enable the contractor to access the work site and possess all its parts at the time specified for the implementation of the contract, as Paragraph 2.1 entitled Right of Access to the site states: (The Employer shall give the Contractor right of access to, and possession of, all parts of the Site within the time (or times) stated in the Appendix to Tender.
  • 20. Relevant Contract Provisions d) The same paragraph also stipulated the contractor’s entitlement to claim compensation in the event that the employer was unable to hand over the site and was exposed to damage because of that, as it was stated in it (If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or Possession within such time, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to: (a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price.
  • 21. Required compensation, issue no 1 Ex. Of Time •77 days •28*50%= 14 days •Total = 81 days Payment • Damages for one day= $225 • Total damages= $18,225
  • 22. List of Major Issues and Problems 1. Delay due to the Employer's failure to handover the site. 1.2. Suspension of work by direct order from the employer 3. Material Prices Increase
  • 23. 2. Suspension of work by direct order from the employer On June 24, 2021, the contractor submitted permission to start the works as planned in the schedule on Street 8, 9 and in accordance with the usual daily work procedures, and the agency engineer agreed to that, and after starting the work, the agency engineer requested to stop work by his order, after work on the project was prohibited by the local residents. The problem lasted for five days, when it was solved by the intervention of the national and Islamic forces, the municipality, the Engineers Association, the employer (the agency), and the neighborhood committees
  • 24. Relevant Contract Provisions According to FIDIC, the contractor has the right to claim compensation from the employer as a result of suspending the works in compliance with the employer's order, as stated Clause 8.9 Consequences of Suspension: If the Contractor suffers delay and/or incurs Cost from complying with the engineer's instructions under Sub-Clause 8.8 [Suspension of Work] and/or from resuming the work, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub- Clause 20.1 [Contractor's Claims] to: A. an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], B. and payment of any such Cost, which shall be included in the Contract Price
  • 25. Required compensation, issue no 2 Ex. Of Time •5 days Payment • Damages for one day= $1475 • Total damages= $7375 equipments
  • 26. List of Major Issues and Problems 1. Delay due to the Employer's failure to handover the site. 1.2. Suspension of work by direct order from the employer 3. Material Prices Increase
  • 27. 3. Material Prices Increase a. Rising raw material prices There are huge price differences for raw materials between the period of preparing and submitting bid documents, which was in November 2020, and the implementation period, which lasted until February 2022.
  • 28. a. Rising raw material prices This delay is due to a number of reasons: 1. The length of the period between the closing date of tenders and the signing of the contract: it reached 150 days. 2. The delay caused by issue 1 + 2 delayed the supply of raw materials by 86 days 3. Due to the delays, the contractor was forced to purchase raw materials during the expensive period, after entering the war period from May 11 to May 23, 2021, and the subsequent closure of the crossings led to an increase in prices.
  • 29. b. The decline of the dollar price. The decline in the price of the dollar during the project by 11%, as it reached its lowest level, at the end of 2021
  • 30. The problem is that the tender prices are in dollars and the payments and costs paid by the contractor are in shekels
  • 31. Relevant Contract Provisions According to sub-clause 13.8 of in FIDIC, it is prescribed that the amounts payable to the contractor shall be adjusted for rises or falls in the cost of labor, goods and other inputs to the works, by the addition or deduction of the amounts determined by the formula. The adjustment to be applied to the amount otherwise payable to the contractor, as valued in accordance with the appropriate schedule and certified in payment certificates, shall be determined from formulas for each of the currencies in which the contract price is payable.
  • 32. Calculation of compensation (sample) ‫م‬ ‫الصنف‬ ‫الوحدة‬ ‫الكمية‬ " A " ‫السعر‬ ‫اثناء‬ ‫التسعير‬ ‫بالشيكل‬ " B " ‫السعر‬ ‫عند‬ ‫التنفيذ‬ ‫بالشيكل‬ " C " ‫قيمة‬ ‫الفرق‬ ‫بالشيكل‬ D=C-B ‫اجمالي‬ ‫الفرق‬ A*D ‫أوال‬ / ‫مواسير‬ ‫أسعار‬ ‫فروق‬ UPVC 1 ‫امطار‬ ‫مياه‬ ‫تصريف‬ ‫مواسير‬ UPVC ‫قطر‬ 400 ‫ملم‬ ‫ط‬ ‫م‬ 40 160 240 80 3,200 2 ‫امطار‬ ‫مياه‬ ‫تصريف‬ ‫مواسير‬ UPVC ‫قطر‬ 315 ‫ملم‬ ‫ط‬ ‫م‬ 40 103 150 47 1,880 3 ‫صحي‬ ‫صرف‬ ‫مواسير‬ UPVC ‫قطر‬ 250 ‫ملم‬ ‫ط‬ ‫م‬ 115 68 85 17 1,955
  • 33. Required compensation, issue no 3 ‫البند‬ ‫المبلغ‬ ‫بالشيكل‬ ‫أوال‬ / ‫مواسير‬ ‫أسعار‬ ‫فروق‬ UPVC 34,075 ‫ثانيا‬ / ‫و‬ ‫والمناهل‬ ‫المسلح‬ ‫الباطون‬ ‫في‬ ‫المستخدم‬ ‫الحديد‬ ‫أسعار‬ ‫فروق‬ ‫االسمنت‬ 31,250 ‫ثالثا‬ / ‫أسعار‬ ‫فرق‬ ‫نتيجة‬ ‫المستوردة‬ ‫الكهربائية‬ ‫المواد‬ ‫أسعار‬ ‫فروق‬ ‫النقل‬ 57,500 ‫بالشيكل‬ ‫اإلجمالي‬ 122,825 ‫بالدوالر‬ ‫اإلجمالي‬ $ 37,792
  • 34. List of Major Issues and Problems 1. Delay due to the Employer's failure to handover the site. 1.2. Suspension of work by direct order from the employer 3. Material Prices Increase
  • 35. Summary of Required Compensation Issue Required Compensation Compensation ($) Time (days) Delay due to the Employer's failure to handover the site 18,225 81 Suspension of work by direct order from the employer (agency) 7,375 5 Material Prices Increase 37,792 - Total 63,492 86
  • 36. Documents Documents 1.1. Correspondence 2. Contract documents 3. Meeting minutes 1.4. Daily report 1.5. Schedule (planned and revised) CODING 1.D 1.1 – D 1.21 D 2.1 – D 2.5 D 3 D 4 D 5