SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
BACHELOR OF QUANTITY SURVEYING (HONOURS)
Subject : CONSTRUCTION LAW (LAW 63804)
Project type : Group Assignment (maximum 6 members)
Deadline : 21st
November 2018
Marks : 30%
You are required to propose an appropriate FIDIC forms of contract and give a sound professional
advice to the Vice-Chancellor of the Construction Management University on post contract stage issues.
The Construction Management University is planning to build a RM400 million Postgraduate Student
Accommodation and Outreach Centre project in its campus at Petaling Jaya. The project will provide
state-of-the art academic block facilities for 3,000 postgraduate students, as well as an outreach centre
which will become the focal point for the University’s community-based teaching activities and
continuous professional development courses.
You should outline your assumptions.
You are required to write a report to advise the Vice-Chancellor of the Construction Management
University:
a) The general principle governing law in the construction contract.
b) To propose an appropriate FIDIC form of contract for this project to achieve this goal. Explain
how your selections will provide appropriate contract features.
c) The conditions guiding payment in the chosen FIDIC conditions of contract.
d) The contractual standing in terms of conditions governing contractual programme.
e) The conditions guiding termination for the contracting parties in the chosen FIDIC conditions of
contract.
f) Explain dispute resolution methods in chosen FIDIC contract that can be used for the project
and explain the rationale for your choice.
You are required to have a separate analysis section where you will compare the advice given based
on the chosen FIDIC condition of contract (c-f) with a chosen condition of contracts either PAM form of
contract or the JKR form of contract.
You should outline your assumptions.
Page 2 of 2
Mark Allocation for this task
 Introduction 5%
 The general principle of law governing construction contracts. 5%
 To propose an appropriate FIDIC form of contract for this project to achieve this goal. Explain
how your selections will provide appropriate contract features. 20%
 The conditions guiding payment in the chosen FIDIC conditions of contract. 10%
 The contractual standing in terms of conditions governing contractual programme.10%
 The conditions guiding termination for the contracting parties in the chosen FIDIC conditions of
contract. 10%
 Explain dispute resolution methods in chosen FIDIC contract that can be used for the project
and explain the rationale for your choice.10%
 You are required to have a separate analysis section where you will compare the advice given
based on the chosen FIDIC condition of contract (c-f) with a chosen condition of contracts either
FIDIC forms of contract or the JKR forms of contract. 15%
 Clear examples. 5%
 Presentation of report 10% (Layout, structure, visual presentation, use of language, clarity of
expression, referencing within text and bibliography)
NOTE: SUBMISSION REQUIREMENTS
The assignment is to be submitted in a report format and as such should have a formal structure
and layout. It should be presented as a neatly bound professional document single sided.
Length: should not exceed 3000 words for the task
Requirements: all submissions should have a cover sheet identifying the module, the date and the
group students’ name. All submissions shall have a bibliography of references and sources used in
the preparation of the project. APA style of referencing should be used.
Group report must include all the respective student/ peer review forms with sealed envelope
compiled by group leader.
Work must be submitted through Turnitin and a hard copy to the lecturer on or before the
due date.
Turnitin will be used to check the originality of the report.

More Related Content

What's hot

Assignment - Tender Submission Part 1
Assignment - Tender Submission Part 1Assignment - Tender Submission Part 1
Assignment - Tender Submission Part 1Kai Yun Pang
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Lee Pei Gie
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project managementJohn Constance
 
Badm 634 initiating the project research project (8 week
Badm 634 initiating the project  research project (8 week Badm 634 initiating the project  research project (8 week
Badm 634 initiating the project research project (8 week sodhi3
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 
Seminar 1 - Theory Question
Seminar 1 - Theory QuestionSeminar 1 - Theory Question
Seminar 1 - Theory QuestionKai Yun Pang
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation seenyeeyong
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment마 이환
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practiceseenyeeyong
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 AssignmentMelvin Lim
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spceirkportal
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Kipcon Inc.
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Construction industry and estimating
Construction industry and estimatingConstruction industry and estimating
Construction industry and estimatingalanchong88
 

What's hot (20)

Chapter 6- Contract Management
Chapter 6- Contract ManagementChapter 6- Contract Management
Chapter 6- Contract Management
 
Assignment - Tender Submission Part 1
Assignment - Tender Submission Part 1Assignment - Tender Submission Part 1
Assignment - Tender Submission Part 1
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Tender Presentation ( Estimating )
Tender Presentation ( Estimating )
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project management
 
Badm 634 initiating the project research project (8 week
Badm 634 initiating the project  research project (8 week Badm 634 initiating the project  research project (8 week
Badm 634 initiating the project research project (8 week
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Seminar 1 - Theory Question
Seminar 1 - Theory QuestionSeminar 1 - Theory Question
Seminar 1 - Theory Question
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Tenders
TendersTenders
Tenders
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spce
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Construction industry and estimating
Construction industry and estimatingConstruction industry and estimating
Construction industry and estimating
 

Similar to Assignment - Report

Fac 1 - Sofia, 8 february
Fac 1 - Sofia, 8 februaryFac 1 - Sofia, 8 february
Fac 1 - Sofia, 8 februaryEmil Hristov
 
Built Environment BSc Architectural Design & Technology BSc Buildi.docx
Built Environment BSc Architectural Design & Technology BSc Buildi.docxBuilt Environment BSc Architectural Design & Technology BSc Buildi.docx
Built Environment BSc Architectural Design & Technology BSc Buildi.docxchestnutkaitlyn
 
MCE Learning and Teaching Version 2.0 Page 1 of 6 Cour
MCE  Learning and Teaching Version 2.0  Page 1 of 6 CourMCE  Learning and Teaching Version 2.0  Page 1 of 6 Cour
MCE Learning and Teaching Version 2.0 Page 1 of 6 CourAbramMartino96
 
Kic InnoEnergy: Strategy, Maghrenov kickoff Barcelona - Day 2
Kic InnoEnergy: Strategy, Maghrenov kickoff Barcelona - Day 2Kic InnoEnergy: Strategy, Maghrenov kickoff Barcelona - Day 2
Kic InnoEnergy: Strategy, Maghrenov kickoff Barcelona - Day 2Maghrenov
 
Lab_Project_Work_Guidelines.pdf
Lab_Project_Work_Guidelines.pdfLab_Project_Work_Guidelines.pdf
Lab_Project_Work_Guidelines.pdfashishagrawal55977
 
Eye on Defence January 2018
Eye on Defence January 2018Eye on Defence January 2018
Eye on Defence January 2018Ankur Gupta
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startupBob Prieto
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryBob Prieto
 
Running head ACQUISITION STRATEGY PIEZOELECTRIC EMBEDDED TRA.docx
Running head  ACQUISITION STRATEGY  PIEZOELECTRIC EMBEDDED TRA.docxRunning head  ACQUISITION STRATEGY  PIEZOELECTRIC EMBEDDED TRA.docx
Running head ACQUISITION STRATEGY PIEZOELECTRIC EMBEDDED TRA.docxSUBHI7
 
Assignment AQSP for B 10.docx
Assignment AQSP for B 10.docxAssignment AQSP for B 10.docx
Assignment AQSP for B 10.docxRiRi873223
 
Pp1 presentation 2
Pp1 presentation 2Pp1 presentation 2
Pp1 presentation 2shensin1015
 
Construction management 2
Construction management 2Construction management 2
Construction management 2smumbahelp
 
introduction to public private partnership
introduction to public private partnershipintroduction to public private partnership
introduction to public private partnershipHayJirenyaa
 
1 Module KB7035 Module Title Procurement and Su
1  Module KB7035 Module Title Procurement and Su1  Module KB7035 Module Title Procurement and Su
1 Module KB7035 Module Title Procurement and SuMartineMccracken314
 

Similar to Assignment - Report (20)

Fac 1 - Sofia, 8 february
Fac 1 - Sofia, 8 februaryFac 1 - Sofia, 8 february
Fac 1 - Sofia, 8 february
 
U4 A2-2.pdf
U4 A2-2.pdfU4 A2-2.pdf
U4 A2-2.pdf
 
Built Environment BSc Architectural Design & Technology BSc Buildi.docx
Built Environment BSc Architectural Design & Technology BSc Buildi.docxBuilt Environment BSc Architectural Design & Technology BSc Buildi.docx
Built Environment BSc Architectural Design & Technology BSc Buildi.docx
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
MCE Learning and Teaching Version 2.0 Page 1 of 6 Cour
MCE  Learning and Teaching Version 2.0  Page 1 of 6 CourMCE  Learning and Teaching Version 2.0  Page 1 of 6 Cour
MCE Learning and Teaching Version 2.0 Page 1 of 6 Cour
 
Agile contracting- APM Contracts and Procurement SIG, July 2016
Agile contracting- APM Contracts and Procurement SIG, July 2016Agile contracting- APM Contracts and Procurement SIG, July 2016
Agile contracting- APM Contracts and Procurement SIG, July 2016
 
Final standard tender doc
Final standard tender docFinal standard tender doc
Final standard tender doc
 
Kic InnoEnergy: Strategy, Maghrenov kickoff Barcelona - Day 2
Kic InnoEnergy: Strategy, Maghrenov kickoff Barcelona - Day 2Kic InnoEnergy: Strategy, Maghrenov kickoff Barcelona - Day 2
Kic InnoEnergy: Strategy, Maghrenov kickoff Barcelona - Day 2
 
Lab_Project_Work_Guidelines.pdf
Lab_Project_Work_Guidelines.pdfLab_Project_Work_Guidelines.pdf
Lab_Project_Work_Guidelines.pdf
 
Eye on Defence January 2018
Eye on Defence January 2018Eye on Defence January 2018
Eye on Defence January 2018
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Running head ACQUISITION STRATEGY PIEZOELECTRIC EMBEDDED TRA.docx
Running head  ACQUISITION STRATEGY  PIEZOELECTRIC EMBEDDED TRA.docxRunning head  ACQUISITION STRATEGY  PIEZOELECTRIC EMBEDDED TRA.docx
Running head ACQUISITION STRATEGY PIEZOELECTRIC EMBEDDED TRA.docx
 
TOPIC6.pdf
TOPIC6.pdfTOPIC6.pdf
TOPIC6.pdf
 
Assignment AQSP for B 10.docx
Assignment AQSP for B 10.docxAssignment AQSP for B 10.docx
Assignment AQSP for B 10.docx
 
Pp1 presentation 2
Pp1 presentation 2Pp1 presentation 2
Pp1 presentation 2
 
4
44
4
 
Construction management 2
Construction management 2Construction management 2
Construction management 2
 
introduction to public private partnership
introduction to public private partnershipintroduction to public private partnership
introduction to public private partnership
 
1 Module KB7035 Module Title Procurement and Su
1  Module KB7035 Module Title Procurement and Su1  Module KB7035 Module Title Procurement and Su
1 Module KB7035 Module Title Procurement and Su
 

More from Kai Yun Pang

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiKai Yun Pang
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - ReportKai Yun Pang
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump StationKai Yun Pang
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectKai Yun Pang
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial AppraisalKai Yun Pang
 
Assignment - Financial Appraisal
Assignment - Financial Appraisal Assignment - Financial Appraisal
Assignment - Financial Appraisal Kai Yun Pang
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012Kai Yun Pang
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Kai Yun Pang
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S HotelKai Yun Pang
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - JournalKai Yun Pang
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service Kai Yun Pang
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final AccountKai Yun Pang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerKai Yun Pang
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - QuestionKai Yun Pang
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK LandKai Yun Pang
 
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Kai Yun Pang
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalKai Yun Pang
 
Assignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareAssignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareKai Yun Pang
 

More from Kai Yun Pang (20)

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau Langkawi
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - Report
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump Station
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft Project
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - Financial Appraisal
Assignment - Financial Appraisal Assignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S Hotel
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - Journal
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK Land
 
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
 
Assignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareAssignment 2 - Buildsoft Software
Assignment 2 - Buildsoft Software
 

Recently uploaded

Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 

Recently uploaded (20)

Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 

Assignment - Report

  • 1. Page 1 of 2 SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) Subject : CONSTRUCTION LAW (LAW 63804) Project type : Group Assignment (maximum 6 members) Deadline : 21st November 2018 Marks : 30% You are required to propose an appropriate FIDIC forms of contract and give a sound professional advice to the Vice-Chancellor of the Construction Management University on post contract stage issues. The Construction Management University is planning to build a RM400 million Postgraduate Student Accommodation and Outreach Centre project in its campus at Petaling Jaya. The project will provide state-of-the art academic block facilities for 3,000 postgraduate students, as well as an outreach centre which will become the focal point for the University’s community-based teaching activities and continuous professional development courses. You should outline your assumptions. You are required to write a report to advise the Vice-Chancellor of the Construction Management University: a) The general principle governing law in the construction contract. b) To propose an appropriate FIDIC form of contract for this project to achieve this goal. Explain how your selections will provide appropriate contract features. c) The conditions guiding payment in the chosen FIDIC conditions of contract. d) The contractual standing in terms of conditions governing contractual programme. e) The conditions guiding termination for the contracting parties in the chosen FIDIC conditions of contract. f) Explain dispute resolution methods in chosen FIDIC contract that can be used for the project and explain the rationale for your choice. You are required to have a separate analysis section where you will compare the advice given based on the chosen FIDIC condition of contract (c-f) with a chosen condition of contracts either PAM form of contract or the JKR form of contract. You should outline your assumptions.
  • 2. Page 2 of 2 Mark Allocation for this task  Introduction 5%  The general principle of law governing construction contracts. 5%  To propose an appropriate FIDIC form of contract for this project to achieve this goal. Explain how your selections will provide appropriate contract features. 20%  The conditions guiding payment in the chosen FIDIC conditions of contract. 10%  The contractual standing in terms of conditions governing contractual programme.10%  The conditions guiding termination for the contracting parties in the chosen FIDIC conditions of contract. 10%  Explain dispute resolution methods in chosen FIDIC contract that can be used for the project and explain the rationale for your choice.10%  You are required to have a separate analysis section where you will compare the advice given based on the chosen FIDIC condition of contract (c-f) with a chosen condition of contracts either FIDIC forms of contract or the JKR forms of contract. 15%  Clear examples. 5%  Presentation of report 10% (Layout, structure, visual presentation, use of language, clarity of expression, referencing within text and bibliography) NOTE: SUBMISSION REQUIREMENTS The assignment is to be submitted in a report format and as such should have a formal structure and layout. It should be presented as a neatly bound professional document single sided. Length: should not exceed 3000 words for the task Requirements: all submissions should have a cover sheet identifying the module, the date and the group students’ name. All submissions shall have a bibliography of references and sources used in the preparation of the project. APA style of referencing should be used. Group report must include all the respective student/ peer review forms with sealed envelope compiled by group leader. Work must be submitted through Turnitin and a hard copy to the lecturer on or before the due date. Turnitin will be used to check the originality of the report.