CHECK LIST FOR OHE BONDING AND EARTHING FOR INDIAN RAILWAY
1 | P a g e
In case of any doubt or corrections please mail to : v.gopal21@gmail.com
1) Check Structure bond on all type of masts and up rights of OHE
2) Check Longitudinal bond on fish plate joints of rails on all non-track circuited area
3) Check Cross bond-between rails (open route 3 per KM in non-track circuited area)
4) Check Cross bond between track on double line and yards ( negative rails in track
circuited area)
5) Check Z bonding at insulated rail joint for staggering of polarity for DC track circuited
area
6) Check “U’’ Bond (check / guard rails in bridges)
7) Check bonding for girders of ROB
8) Check bonding for FOB
9) Check bonding for Passengers Shelters in platforms provide proper embedding of
bond on platforms and ensure cleat on coping of platform
10) Check bonding metal fencing
11) Check in major bridge for every 100 m hand rails to be connected to track by bond
12) Check at tunnel for earth wire to run through out
13) Check bond for metal pipeline along track if any
14) Check at Level crossings All the traction rails shall be provided with cross-bonds at only
one location which shall be within five metres from either of the transverse edges
(non-track circuited)
15) Check the Level crossing A frame, Lifting barrier base , lever mechanism provided with
bond.
16) Check PTFE neutral section connected with structure and earthed
17) Check earthing for girders of ROB, FOB and bridge ( both side)
18) Check Isolator at siding line provided with earthing heel and earth ,all Isolator(SS/SM)
handle provided with copper flexible bride with structure
19) Check Passenger shelters / metal fencing / any structure at stations / near/along track
- More than 20 m to 350 m –Bond , more than 350 m are earthed .
20) Check bonding in track circuit area earthing done every 100 m up to and beyond 50 m
of home signal on both side.
21) Check earth electrode are connected to girders of ROB, FOB , bridges, fencing,
platform shelters, sheds, neutral section, Isolator, yard etc. and also connected to
nearest traction rails by means of two distinctive connection
22) in addition to connection to the relevant structures/equipment etc.,
23) Check the bond for Painting ( Finish with double coat bituminous black paint)
24) Check the Size of MS bond is 40 X 6 mm and Bolt GI - M 16 – 50/38 , Flat washer,
spring washer, nut etc.,
25) Check in track circuited area bond placed below the ballast 150-200 mm and
provided with 2 -3 mm PVC sleeve to avoid contact with positive rail / triple
insulation if required
26) Check for tightness of bolt between 160 – 213 Nm
27) Check No sharp edges and bolted joints on bond
28) Check bolting edge of bond should butt /flush with mast properly / rail (bent properly)
29) Check the holes drilled on neural axis on the traction rail ( Use template)
30) For 60 kg Rail.80.95mm from bottom flange and 91.05mm from Rail head
31) For 52 kg Rail.75.59mm from bottom flange and 80.41mm from Rail head
32) Hole to be chamfered by suitable compression die
CHECK LIST FOR OHE BONDING AND EARTHING FOR INDIAN RAILWAY
2 | P a g e
In case of any doubt or corrections please mail to : v.gopal21@gmail.com
33) No Hole to be drilled 250 mm close to Fishplate, 170 mm to existing hole and 100 to
al. thermic welding/ FB welding
34) Check the bond is made as per the shape shown in RDSO drawing
35) Check that no bond is connected in signal ( Positive Rail) in track circuited area
36) TSS/SWS/FP
Check that all the traction rails shall be provided with rail bonds for a distance of 1000m
on both sides opposite to the FP and all the traction rails are cross bonded at a distance
of 300m, 500m, 750m & 1000m on both sides of the FP.
Check the earth electrodes provided at switching station shall be interconnected to
form a closed loop to form earthing ring. This ring, traction rail and the earth mat are
connected by means of two distinct connections of 50 mm x 6 mm MS flat
Check the designated terminal of the secondary of each potential, current and auxiliary
transformer , masts, structures, fencing uprights, and all outdoor equipment pedestals
including auxiliary transformer tank are connected to the earthing ring by means of two
separate and distinct connections and the metal casing of potential and current
transformers are connected to the mast/ structures by means of two separate and
distinct connections made with 50 mm x 6 mm MS flat
Check all fencing panels , metallic door panels and upright are connected to the
supporting uprights by two separate and distinct connections with 6 SWG G.I. wire.
Check the ground terminal of lightning arrester are connected directly to the earth
grid/ring by means of two separate and distinct connections made with 50 mm x 6 mm
MS flat earthing leads from the lightning arrester are brought to the earth grid/ring by
as short and straight path as possible
Check the metal casing of LT AC. and DC. distribution board, battery chargers, terminal
board, remote control equipment cabinets and other such equipment are connected to
the earthing ring by means of two separate and distinct connections made with 8 SWG
G.I. wire.
Check at TSS and SWS where power supply at 415 V/ 240 V, ac, 50 Hz, is taken from the
local supply authority and having neutral earth at some distant point in the premises of
the supply authority, the neutral of such supply are earthed by means of two separate
and distinct connections made with 6 SWG G.I. wire by connecting to an independent
earth electrode.
Check 52 kg/m rail with length of 13 m shall be buried near the track at the TSS /SWS
at a depth of one metre. Two separate and distinct connections shall be made the
earthing grid and the buried rail. The buried rail to be connected by means of two
separate and distinct connections made to the traction rail with 75 mm X 8 mm MS flat
Check when the FP is located separately away from the traction TSS, the buried rail
provided at the FP (where one terminal of the secondary winding of the traction power
transformer of the substation is grounded).One terminal of the secondary winding (25
kV winding) of each traction power transformer to be earthed directly by connecting it
to the earthing grid and to the buried rail by 75 mm x 8 mm MS flat.
Check the designated terminal of the secondary of each potential, current and auxiliary
transformer are connected to the earthing grid by means of two separate and distinct
earth connections and metallic frame work of all outdoor equipment such as
transformers, circuit breakers, interrupters and isolators, as well as steel structures are
connected to the earthing grid by means of two separate and distinct connections
CHECK LIST FOR OHE BONDING AND EARTHING FOR INDIAN RAILWAY
3 | P a g e
In case of any doubt or corrections please mail to : v.gopal21@gmail.com
37) Check Various size of flats and wires used at respective location
40 X 6 mm MS – OHE bonding and earthing
50 X 6 mm MS -25 kV System and equipment earthing in TSS and SWS including AT
75 X 8 mm MS -HV System, buried rail ,equipment and structure earthing in TSS
8 SWG GI wire - ACDB and DCDB, battery chargers, terminal board
6 SWG GI wire - Fencing panel and Local supply neutral
38) Check Painting
The exposed surfaces of earthing connections (MS flats) above ground level shall be
given two coats of painting to colour grass green
The bond connections on OHE shall be painted with two coats of black bituminous
paint
39) Check Maximum Value
Combined Earth value in OHM shall not be greater than TSS - 0.5, SSP/SP - 2, AT - 10,
Independent earth station- 10
40) Check Marking
Earth pit Shall be provided Box & Cover and the CE/IE Values to be stencilled with date
test & Earth pit No
41) Safety and Permission
A) Before starting the rail drilling work the following should be available
1. OHE bonding plan
2. Portable Rail drilling machine
3. Chamfering tool
4. Template for hole marking
5. Competent operator for drilling and chamfering
6. Helpers and whistle men
7. Necessary PPE , safety gadget, Flags and banners
8. Person with communication equipment at work spot and at both station on
either direction
B) The safety counselling to be done for the staff engaged to understand and follow
( Toolbox talk) the Safety rules and procedures like GR ,Joint Procedure order,
Circulars, Standing Instructions for safe working on track with block / caution
order including movement of trains
C) The EA engineer should be available at site and ensure necessary permits are
obtained and information is given to SMRs,SMs ( on either direction) and section
SSE/SE/JE Pway,S&T
D) The site should be cleaned before leaving
End of check sheet

More Related Content

What's hot

Safety management in electrification of railways
Safety management in electrification of railwaysSafety management in electrification of railways
Safety management in electrification of railwaysSuresh Sunny
 
Electric traction ankit
Electric traction ankitElectric traction ankit
Electric traction ankitAnkit Verma
 
Overhead Electrification
Overhead Electrification Overhead Electrification
Overhead Electrification Suresh Sunny
 
Safety management in electrification of railways
Safety management in electrification of railwaysSafety management in electrification of railways
Safety management in electrification of railwaysSuresh Sunny
 
Traction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptTraction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptAshish585772
 
Electric traction in railways
Electric traction in railwaysElectric traction in railways
Electric traction in railwayssuresh shindhe
 
Presentaion on Diesel Loco WDG4
Presentaion on Diesel Loco WDG4Presentaion on Diesel Loco WDG4
Presentaion on Diesel Loco WDG4Abhishek dayal
 
NWR summer training ppt
NWR summer training pptNWR summer training ppt
NWR summer training pptKaushu Deshwal
 
Electric Traction
Electric TractionElectric Traction
Electric TractionNawaz Nz
 
Railway coaching depot report
Railway coaching depot reportRailway coaching depot report
Railway coaching depot reportAshutosh Khaitan
 
Air conditioning in indian railways PEE
Air conditioning in indian railways PEEAir conditioning in indian railways PEE
Air conditioning in indian railways PEEirkportal
 
Railway summer training report electrical engineering
Railway summer training report electrical engineeringRailway summer training report electrical engineering
Railway summer training report electrical engineeringYogesh Jadoun
 
Ppt power grid design
Ppt power grid designPpt power grid design
Ppt power grid designsusanta das
 
Diesel locomotive
Diesel locomotiveDiesel locomotive
Diesel locomotiveCyber4Tech
 

What's hot (20)

Safety management in electrification of railways
Safety management in electrification of railwaysSafety management in electrification of railways
Safety management in electrification of railways
 
Electric traction ankit
Electric traction ankitElectric traction ankit
Electric traction ankit
 
Overhead Electrification
Overhead Electrification Overhead Electrification
Overhead Electrification
 
Safety management in electrification of railways
Safety management in electrification of railwaysSafety management in electrification of railways
Safety management in electrification of railways
 
Traction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptTraction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.ppt
 
Electric traction in railways
Electric traction in railwaysElectric traction in railways
Electric traction in railways
 
Electric traction
Electric tractionElectric traction
Electric traction
 
Presentaion on Diesel Loco WDG4
Presentaion on Diesel Loco WDG4Presentaion on Diesel Loco WDG4
Presentaion on Diesel Loco WDG4
 
NWR summer training ppt
NWR summer training pptNWR summer training ppt
NWR summer training ppt
 
Electric Traction
Electric TractionElectric Traction
Electric Traction
 
The diesel locomotive
The diesel locomotiveThe diesel locomotive
The diesel locomotive
 
Railway coaching depot report
Railway coaching depot reportRailway coaching depot report
Railway coaching depot report
 
Air conditioning in indian railways PEE
Air conditioning in indian railways PEEAir conditioning in indian railways PEE
Air conditioning in indian railways PEE
 
Busduct catalogue
Busduct catalogueBusduct catalogue
Busduct catalogue
 
HVDC TRANSMISSION
HVDC TRANSMISSIONHVDC TRANSMISSION
HVDC TRANSMISSION
 
final report
final reportfinal report
final report
 
vikanksh
vikankshvikanksh
vikanksh
 
Railway summer training report electrical engineering
Railway summer training report electrical engineeringRailway summer training report electrical engineering
Railway summer training report electrical engineering
 
Ppt power grid design
Ppt power grid designPpt power grid design
Ppt power grid design
 
Diesel locomotive
Diesel locomotiveDiesel locomotive
Diesel locomotive
 

Similar to VG check list for OHE bonding and earthing 002

Entership Presentation (1).pptx
Entership Presentation (1).pptxEntership Presentation (1).pptx
Entership Presentation (1).pptxmebremezgebe
 
Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvAlexander Decker
 
Grounding,Earthing,Bonding
Grounding,Earthing,BondingGrounding,Earthing,Bonding
Grounding,Earthing,BondingKo Winnwe
 
Nec and oesc-2
Nec and oesc-2Nec and oesc-2
Nec and oesc-2grantlerc
 
011 spec grounding and bonding
011 spec grounding and bonding011 spec grounding and bonding
011 spec grounding and bondingYash Bhardwaj
 
Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)Mahesh Chandra Manav
 
Flash butt welding
Flash butt weldingFlash butt welding
Flash butt weldingsabdou
 
HA no. 2 EE182LDaet_Valdez
HA no. 2 EE182LDaet_ValdezHA no. 2 EE182LDaet_Valdez
HA no. 2 EE182LDaet_ValdezPrudenceDaet
 
VG Railway S & T wiring check list rev 00
VG  Railway S & T wiring check list rev 00VG  Railway S & T wiring check list rev 00
VG Railway S & T wiring check list rev 00Varadharajalu Gopal
 
Maintenance of Track in Electrified Areas.pptx
Maintenance of Track in Electrified Areas.pptxMaintenance of Track in Electrified Areas.pptx
Maintenance of Track in Electrified Areas.pptxPUJARI4
 
Electrical layout of
Electrical layout ofElectrical layout of
Electrical layout ofBhakti Stm
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976Southern Railway
 
PB Weir Substation Earth End Clamps - CE22-BESI-L2 & CE20-ESI-E1
PB Weir Substation Earth End Clamps - CE22-BESI-L2 & CE20-ESI-E1PB Weir Substation Earth End Clamps - CE22-BESI-L2 & CE20-ESI-E1
PB Weir Substation Earth End Clamps - CE22-BESI-L2 & CE20-ESI-E1Thorne & Derrick International
 
tender6-7_040616.pdf
tender6-7_040616.pdftender6-7_040616.pdf
tender6-7_040616.pdfKSLDESIGN
 
VG check list for S & T cable laying
VG  check list for S & T cable laying VG  check list for S & T cable laying
VG check list for S & T cable laying Varadharajalu Gopal
 

Similar to VG check list for OHE bonding and earthing 002 (20)

Entership Presentation (1).pptx
Entership Presentation (1).pptxEntership Presentation (1).pptx
Entership Presentation (1).pptx
 
Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kv
 
ملزمة
ملزمةملزمة
ملزمة
 
Distribution system 2
Distribution system  2Distribution system  2
Distribution system 2
 
Grounding,Earthing,Bonding
Grounding,Earthing,BondingGrounding,Earthing,Bonding
Grounding,Earthing,Bonding
 
Nec and oesc-2
Nec and oesc-2Nec and oesc-2
Nec and oesc-2
 
011 spec grounding and bonding
011 spec grounding and bonding011 spec grounding and bonding
011 spec grounding and bonding
 
Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)
 
Flash butt welding
Flash butt weldingFlash butt welding
Flash butt welding
 
HA no. 2 EE182LDaet_Valdez
HA no. 2 EE182LDaet_ValdezHA no. 2 EE182LDaet_Valdez
HA no. 2 EE182LDaet_Valdez
 
VG Railway S & T wiring check list rev 00
VG  Railway S & T wiring check list rev 00VG  Railway S & T wiring check list rev 00
VG Railway S & T wiring check list rev 00
 
Maintenance of Track in Electrified Areas.pptx
Maintenance of Track in Electrified Areas.pptxMaintenance of Track in Electrified Areas.pptx
Maintenance of Track in Electrified Areas.pptx
 
Ccs for solar power pv plant
Ccs for solar power pv plantCcs for solar power pv plant
Ccs for solar power pv plant
 
Ccs for solar power pv plant
Ccs for solar power pv plantCcs for solar power pv plant
Ccs for solar power pv plant
 
Electrical layout of
Electrical layout ofElectrical layout of
Electrical layout of
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
 
PB Weir Substation Earth End Clamps - CE22-BESI-L2 & CE20-ESI-E1
PB Weir Substation Earth End Clamps - CE22-BESI-L2 & CE20-ESI-E1PB Weir Substation Earth End Clamps - CE22-BESI-L2 & CE20-ESI-E1
PB Weir Substation Earth End Clamps - CE22-BESI-L2 & CE20-ESI-E1
 
tender6-7_040616.pdf
tender6-7_040616.pdftender6-7_040616.pdf
tender6-7_040616.pdf
 
VG check list for S & T cable laying
VG  check list for S & T cable laying VG  check list for S & T cable laying
VG check list for S & T cable laying
 
Paper
PaperPaper
Paper
 

Recently uploaded

DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Quantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation ComputingQuantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation ComputingWSO2
 
Navigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseNavigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseWSO2
 
ChatGPT and Beyond - Elevating DevOps Productivity
ChatGPT and Beyond - Elevating DevOps ProductivityChatGPT and Beyond - Elevating DevOps Productivity
ChatGPT and Beyond - Elevating DevOps ProductivityVictorSzoltysek
 
Design Guidelines for Passkeys 2024.pptx
Design Guidelines for Passkeys 2024.pptxDesign Guidelines for Passkeys 2024.pptx
Design Guidelines for Passkeys 2024.pptxFIDO Alliance
 
Design and Development of a Provenance Capture Platform for Data Science
Design and Development of a Provenance Capture Platform for Data ScienceDesign and Development of a Provenance Capture Platform for Data Science
Design and Development of a Provenance Capture Platform for Data SciencePaolo Missier
 
API Governance and Monetization - The evolution of API governance
API Governance and Monetization -  The evolution of API governanceAPI Governance and Monetization -  The evolution of API governance
API Governance and Monetization - The evolution of API governanceWSO2
 
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)Samir Dash
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxRustici Software
 
UiPath manufacturing technology benefits and AI overview
UiPath manufacturing technology benefits and AI overviewUiPath manufacturing technology benefits and AI overview
UiPath manufacturing technology benefits and AI overviewDianaGray10
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2
 
Choreo: Empowering the Future of Enterprise Software Engineering
Choreo: Empowering the Future of Enterprise Software EngineeringChoreo: Empowering the Future of Enterprise Software Engineering
Choreo: Empowering the Future of Enterprise Software EngineeringWSO2
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Bhuvaneswari Subramani
 
Less Is More: Utilizing Ballerina to Architect a Cloud Data Platform
Less Is More: Utilizing Ballerina to Architect a Cloud Data PlatformLess Is More: Utilizing Ballerina to Architect a Cloud Data Platform
Less Is More: Utilizing Ballerina to Architect a Cloud Data PlatformWSO2
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Zilliz
 
TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...
TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...
TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...TrustArc
 
Decarbonising Commercial Real Estate: The Role of Operational Performance
Decarbonising Commercial Real Estate: The Role of Operational PerformanceDecarbonising Commercial Real Estate: The Role of Operational Performance
Decarbonising Commercial Real Estate: The Role of Operational PerformanceIES VE
 
JohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard37
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
JavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuideJavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuidePixlogix Infotech
 

Recently uploaded (20)

DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Quantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation ComputingQuantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation Computing
 
Navigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseNavigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern Enterprise
 
ChatGPT and Beyond - Elevating DevOps Productivity
ChatGPT and Beyond - Elevating DevOps ProductivityChatGPT and Beyond - Elevating DevOps Productivity
ChatGPT and Beyond - Elevating DevOps Productivity
 
Design Guidelines for Passkeys 2024.pptx
Design Guidelines for Passkeys 2024.pptxDesign Guidelines for Passkeys 2024.pptx
Design Guidelines for Passkeys 2024.pptx
 
Design and Development of a Provenance Capture Platform for Data Science
Design and Development of a Provenance Capture Platform for Data ScienceDesign and Development of a Provenance Capture Platform for Data Science
Design and Development of a Provenance Capture Platform for Data Science
 
API Governance and Monetization - The evolution of API governance
API Governance and Monetization -  The evolution of API governanceAPI Governance and Monetization -  The evolution of API governance
API Governance and Monetization - The evolution of API governance
 
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
UiPath manufacturing technology benefits and AI overview
UiPath manufacturing technology benefits and AI overviewUiPath manufacturing technology benefits and AI overview
UiPath manufacturing technology benefits and AI overview
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Choreo: Empowering the Future of Enterprise Software Engineering
Choreo: Empowering the Future of Enterprise Software EngineeringChoreo: Empowering the Future of Enterprise Software Engineering
Choreo: Empowering the Future of Enterprise Software Engineering
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 
Less Is More: Utilizing Ballerina to Architect a Cloud Data Platform
Less Is More: Utilizing Ballerina to Architect a Cloud Data PlatformLess Is More: Utilizing Ballerina to Architect a Cloud Data Platform
Less Is More: Utilizing Ballerina to Architect a Cloud Data Platform
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...
TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...
TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...
 
Decarbonising Commercial Real Estate: The Role of Operational Performance
Decarbonising Commercial Real Estate: The Role of Operational PerformanceDecarbonising Commercial Real Estate: The Role of Operational Performance
Decarbonising Commercial Real Estate: The Role of Operational Performance
 
JohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptx
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
JavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuideJavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate Guide
 

VG check list for OHE bonding and earthing 002

  • 1. CHECK LIST FOR OHE BONDING AND EARTHING FOR INDIAN RAILWAY 1 | P a g e In case of any doubt or corrections please mail to : v.gopal21@gmail.com 1) Check Structure bond on all type of masts and up rights of OHE 2) Check Longitudinal bond on fish plate joints of rails on all non-track circuited area 3) Check Cross bond-between rails (open route 3 per KM in non-track circuited area) 4) Check Cross bond between track on double line and yards ( negative rails in track circuited area) 5) Check Z bonding at insulated rail joint for staggering of polarity for DC track circuited area 6) Check “U’’ Bond (check / guard rails in bridges) 7) Check bonding for girders of ROB 8) Check bonding for FOB 9) Check bonding for Passengers Shelters in platforms provide proper embedding of bond on platforms and ensure cleat on coping of platform 10) Check bonding metal fencing 11) Check in major bridge for every 100 m hand rails to be connected to track by bond 12) Check at tunnel for earth wire to run through out 13) Check bond for metal pipeline along track if any 14) Check at Level crossings All the traction rails shall be provided with cross-bonds at only one location which shall be within five metres from either of the transverse edges (non-track circuited) 15) Check the Level crossing A frame, Lifting barrier base , lever mechanism provided with bond. 16) Check PTFE neutral section connected with structure and earthed 17) Check earthing for girders of ROB, FOB and bridge ( both side) 18) Check Isolator at siding line provided with earthing heel and earth ,all Isolator(SS/SM) handle provided with copper flexible bride with structure 19) Check Passenger shelters / metal fencing / any structure at stations / near/along track - More than 20 m to 350 m –Bond , more than 350 m are earthed . 20) Check bonding in track circuit area earthing done every 100 m up to and beyond 50 m of home signal on both side. 21) Check earth electrode are connected to girders of ROB, FOB , bridges, fencing, platform shelters, sheds, neutral section, Isolator, yard etc. and also connected to nearest traction rails by means of two distinctive connection 22) in addition to connection to the relevant structures/equipment etc., 23) Check the bond for Painting ( Finish with double coat bituminous black paint) 24) Check the Size of MS bond is 40 X 6 mm and Bolt GI - M 16 – 50/38 , Flat washer, spring washer, nut etc., 25) Check in track circuited area bond placed below the ballast 150-200 mm and provided with 2 -3 mm PVC sleeve to avoid contact with positive rail / triple insulation if required 26) Check for tightness of bolt between 160 – 213 Nm 27) Check No sharp edges and bolted joints on bond 28) Check bolting edge of bond should butt /flush with mast properly / rail (bent properly) 29) Check the holes drilled on neural axis on the traction rail ( Use template) 30) For 60 kg Rail.80.95mm from bottom flange and 91.05mm from Rail head 31) For 52 kg Rail.75.59mm from bottom flange and 80.41mm from Rail head 32) Hole to be chamfered by suitable compression die
  • 2. CHECK LIST FOR OHE BONDING AND EARTHING FOR INDIAN RAILWAY 2 | P a g e In case of any doubt or corrections please mail to : v.gopal21@gmail.com 33) No Hole to be drilled 250 mm close to Fishplate, 170 mm to existing hole and 100 to al. thermic welding/ FB welding 34) Check the bond is made as per the shape shown in RDSO drawing 35) Check that no bond is connected in signal ( Positive Rail) in track circuited area 36) TSS/SWS/FP Check that all the traction rails shall be provided with rail bonds for a distance of 1000m on both sides opposite to the FP and all the traction rails are cross bonded at a distance of 300m, 500m, 750m & 1000m on both sides of the FP. Check the earth electrodes provided at switching station shall be interconnected to form a closed loop to form earthing ring. This ring, traction rail and the earth mat are connected by means of two distinct connections of 50 mm x 6 mm MS flat Check the designated terminal of the secondary of each potential, current and auxiliary transformer , masts, structures, fencing uprights, and all outdoor equipment pedestals including auxiliary transformer tank are connected to the earthing ring by means of two separate and distinct connections and the metal casing of potential and current transformers are connected to the mast/ structures by means of two separate and distinct connections made with 50 mm x 6 mm MS flat Check all fencing panels , metallic door panels and upright are connected to the supporting uprights by two separate and distinct connections with 6 SWG G.I. wire. Check the ground terminal of lightning arrester are connected directly to the earth grid/ring by means of two separate and distinct connections made with 50 mm x 6 mm MS flat earthing leads from the lightning arrester are brought to the earth grid/ring by as short and straight path as possible Check the metal casing of LT AC. and DC. distribution board, battery chargers, terminal board, remote control equipment cabinets and other such equipment are connected to the earthing ring by means of two separate and distinct connections made with 8 SWG G.I. wire. Check at TSS and SWS where power supply at 415 V/ 240 V, ac, 50 Hz, is taken from the local supply authority and having neutral earth at some distant point in the premises of the supply authority, the neutral of such supply are earthed by means of two separate and distinct connections made with 6 SWG G.I. wire by connecting to an independent earth electrode. Check 52 kg/m rail with length of 13 m shall be buried near the track at the TSS /SWS at a depth of one metre. Two separate and distinct connections shall be made the earthing grid and the buried rail. The buried rail to be connected by means of two separate and distinct connections made to the traction rail with 75 mm X 8 mm MS flat Check when the FP is located separately away from the traction TSS, the buried rail provided at the FP (where one terminal of the secondary winding of the traction power transformer of the substation is grounded).One terminal of the secondary winding (25 kV winding) of each traction power transformer to be earthed directly by connecting it to the earthing grid and to the buried rail by 75 mm x 8 mm MS flat. Check the designated terminal of the secondary of each potential, current and auxiliary transformer are connected to the earthing grid by means of two separate and distinct earth connections and metallic frame work of all outdoor equipment such as transformers, circuit breakers, interrupters and isolators, as well as steel structures are connected to the earthing grid by means of two separate and distinct connections
  • 3. CHECK LIST FOR OHE BONDING AND EARTHING FOR INDIAN RAILWAY 3 | P a g e In case of any doubt or corrections please mail to : v.gopal21@gmail.com 37) Check Various size of flats and wires used at respective location 40 X 6 mm MS – OHE bonding and earthing 50 X 6 mm MS -25 kV System and equipment earthing in TSS and SWS including AT 75 X 8 mm MS -HV System, buried rail ,equipment and structure earthing in TSS 8 SWG GI wire - ACDB and DCDB, battery chargers, terminal board 6 SWG GI wire - Fencing panel and Local supply neutral 38) Check Painting The exposed surfaces of earthing connections (MS flats) above ground level shall be given two coats of painting to colour grass green The bond connections on OHE shall be painted with two coats of black bituminous paint 39) Check Maximum Value Combined Earth value in OHM shall not be greater than TSS - 0.5, SSP/SP - 2, AT - 10, Independent earth station- 10 40) Check Marking Earth pit Shall be provided Box & Cover and the CE/IE Values to be stencilled with date test & Earth pit No 41) Safety and Permission A) Before starting the rail drilling work the following should be available 1. OHE bonding plan 2. Portable Rail drilling machine 3. Chamfering tool 4. Template for hole marking 5. Competent operator for drilling and chamfering 6. Helpers and whistle men 7. Necessary PPE , safety gadget, Flags and banners 8. Person with communication equipment at work spot and at both station on either direction B) The safety counselling to be done for the staff engaged to understand and follow ( Toolbox talk) the Safety rules and procedures like GR ,Joint Procedure order, Circulars, Standing Instructions for safe working on track with block / caution order including movement of trains C) The EA engineer should be available at site and ensure necessary permits are obtained and information is given to SMRs,SMs ( on either direction) and section SSE/SE/JE Pway,S&T D) The site should be cleaned before leaving End of check sheet