SlideShare a Scribd company logo
1 of 60
Download to read offline
Challenges for the Design of Wind and Solar Power
Plant Grounding System for Personal Safety
Comparison of Copper and Copper Clad Steel Conductors for WPP
Grounding Application
IEEE PES 2016 General Meeting, Boston, MA, July 17-21, 2016.
Presentation by:
Andrew Cadmore , CEng MIET, Principal Electrical Design Engineer, RES Ltd
Abdou Sana, P.Eng, Ph.D, Electrical Engineering Specialist, RES-Americas
1
1- The Use of bare Copper Clad Steel (CSS) conductor, instead of
bare Copper (Cu) conductor, as the directly buried bare
horizontal ground electrode conductor laid in all MV cable
trenches is evaluated based on a WPP project design exercise
2
Typical 34.5kV MV Cable Trench Cross-Section View
2- Copper Clad Steel (CCS)
• Composite in which a concentric copper cladding is bonded to
a steel core to provide a strong “low cost” solution for
grounding conductors
• Available Stranded CCS conductors: 40% and 30% conductivity
relative to the same size of annealed soft-drawn copper
(relative conductivity of 100%).
• Sizing of CCS conductor should be based on an equivalent
short circuit capacity to that of annealed soft-drawn copper
3
4
• Claims on the benefits of CCS conductors as an alternative to
copper conductors:
– Cost savings compared to copper
– 8-12% lighter than copper conductors
– 105-108% higher fusing current compared to copper conductors
– Highly theft resistant
– Excellent fatigue properties
– Extremely strong and rugged, higher breaking strength than copper
conductors
– CCS requires no special handling compared to Copper
– CCS is compatible with standard copper connectors either pressure,
bolted or exothermic welded
– CCS conductors exhibit high corrosion resistance as tested in various
soils conditions
3- Comparative Study copper vs CCS for a typical WPP
• Analysis of the impedance profile resulting from a 3-
dimensional model of the grounding system for a large WPP
– Impedance profiles as seen from the main substation and using 3
types of conductors throughout the MV cable trenches are evaluated
and compared:
• Bare copper conductors
• Equivalent 30% conductivity CCS conductors
• Equivalent 40% conductivity CCS conductors
• Parametric analysis for each of these 3 grounding conductor
systems (Copper, CCS30% & CCS40%), with logarithmic varying
soil resistivity:
• 10 ohm.m uniform soil model (Typ. Shoreline windfarm)
• 100 ohm.m uniform soil model (Typ. low-land windfarm)
• 1,000 ohm.m uniform soil model (Typ. high-land windfarm)
• 10,000 ohm.m uniform soil model (Extreme rocky mountainous windfarm)
5
6
WPP example in WA State, USA, Design-built in 2010/2011:
• 1x 230kV/34.5kVSubstation
• 83 Wind Turbines (191MW)
• 2 Met Masts
• Approx. 5.7 mi x 3.5 mi
• 10- 34.5kV Collection Circuits
All UG, 5 different MV cable
sizes
• Equivalent Bare Grounding Conductor installed at the base of
all MV cable trenches:
– Size based on IEEE Std 80-2000 with:
• Prevailing maximum 34.5kV fault level, seen at the main substation: 20,383 Amps.
• Fault clearing time 0.133s
• Initial Temperature : 25°C
• Final Temperature: 350°C
– Results:
• 1/0 AWG stranded copper conductor, (106kcmil)
• 30% conductivity CCS conductor: 7x #6 AWG (184kcmil)
• 40% conductivity CCS conductor: 7x #7 AWG (146kcmil)
7
I rms current in kA
Amm
2 minimum Conductor cross section in mm2
Akcmil minimum Conductor cross section in kcmil
Tm Maximum allowable temperature in °C
Ta Ambient temperature in °C
Tr Reference temperature for material constants in °C
αo Thermal coefficient of resistivity at 0 °C in 1/°C
αr Thermal coefficient of resistivity at reference temperature Tr in 1/°C
ρr Resistivity of the ground conductor at reference temperature Tr in μΩ-cm
Ko 1/αo or (1/αr) – Tr in °C
tc duration of current in s
TCAP: Thermal capacity per unit volume of material in J/(cm3·°C) (see table)
αr and ρr to be evaluated at the same reference temperature of Tr °C .
(Tables provides data for αr and ρr at 20 °C).
8
Amm2 I
1
TCAP10
4

tc r r






ln
K0 Tm
K0 Ta







 A.kcmil I
197.4
TCAP
t.c .r .r






ln
K.0 T.m
K.0 T.a








Minimum Conductor Cross-section Area (IEEE Std 80 -2000)
9
a From ASTM standards.
b Copper-clad steel rods based on 0.254 mm (0.010 in) copper thickness.
c Stainless-clad steel rod based on 0.508 mm (0.020 in) No. 304 stainless steel thickness over No. 1020
steel core.
Description Material
conductivity
(%)
αr factor at
20 °C
(1/°C)
Ko at 0 °C
(0 °C)
Fusinga
temperature
Tm (°C)
ρr 20 °C
(μΩ·cm)
TCAP thermal
capacity
[J/(cm3
·°C)]
Copper, annealed soft-
drawn
100.0 0.003 93 234 1083 1.72 3.42
Copper, commercial
hard-drawn
97.0 0.003 81 242 1084 1.78 3.42
Copper-clad steel wire 40.0 0.003 78 245 1084 4.40 3.85
Copper-clad steel wire 30.0 0.003 78 245 1084 5.86 3.85
Copper-clad steel rodb
20.0 0.003 78 245 1084 8.62 3.85
Aluminum, EC grade 61.0 0.004 03 228 657 2.86 2.56
Aluminum, 5005 alloy 53.5 0.003 53 263 652 3.22 2.60
Aluminum, 6201 alloy 52.5 0.003 47 268 654 3.28 2.60
Aluminum-clad steel
wire
20.3 0.003 60 258 657 8.48 3.58
Steel, 1020 10.8 0.001 60 605 1510 15.90 3.28
Stainless-clad steel rodc
9.8 0.001 60 605 1400 17.50 4.44
Zinc-coated steel rod 8.6 0.003 20 293 419 20.10 3.93
Stainless steel, 304 2.4 0.001 30 749 1400 72.00 4.03
Ground Electrode Impedance Profile Studies Results
10
11
12
13
14
Ground Electrode Impedance Profile Studies Results – Table
4- Comments on Results
• Ground grid Impedance Zg, as seen at the Main Substation
(i.e. point of fault), increases for CCS relative to copper. Max
value 140.8% for the 30% CCS conductor, in a 10 ohm.m soil.
This results also in:
– Increase of GPR, Touch & Step Potential as seen at or near the point of
fault proportional to the increase in ground electrode impedance.
– Slightly larger Hot Zones
– Increased need for crushed rock at the WTG’s located closest to the
main sub.
For most in-land WPP (100 ohm.m soils), the various ground potential
values would all have increased by approximately 124.7%.
15
• The % deviation in Zg as seen at the Main Substation (i.e.point
of fault), decreases with CCS compared to Copper with an
increase in soil resistivity. This means that the:
– impact of CCS conductor becomes more comparable to Copper as the
soil resistivity increases in ohm.m value.
• The % deviation in Zg as seen at the farthest WTG or Met
Mast, from the Main Substation decreases with CCS compared
to Copper with an increase in the value of soil resistivity.
– This means that for transfer potentials, CSS conductors performs
better than Copper conductors due the increase in their internal
impedance.
• The difference in electrical performance between 30%CCS and
40% CCS conductor is not significant.
16
5- CONCLUSION
• Copper ground conductors offer better electrical
performance than CCS conductors.
– The difference in performance is though not so substantial (max
140.8% of increased GPR using CCS as compared to Copper during
extremely low soil resistivity conditions)
– In most cases this is manageable within the engineering design of
the windfarm grounding system.
• From an engineering design perspective, the impact of CCS
compared to Copper conductors are as follows:
– Possible need to install additional GPR control conductors, around
WTG’s, Junction Boxes or Met Masts to mitigate increased Touch &
Step Potential: Likelihood of having to install such additional
ground conductors is relatively low.
17
– Possible need to install crushed rock at more WTG’s, MV Junction
Boxes or Met Masts to mitigate increased Touch & Step Potential
– Possible need to undertake more detailed ground potential analysis
mitigate increased Touch & Step Potential.
– Increased likelihood that a project site will be subject to a “Hot”
Zone of Influence and an increase in the area size of that “Hot” Zone
of Influence. There is little that can be practically done to reduce the
size of the “Hot” Zone of Influence, beyond refining the desktop
design & analysis.
• The difference in electrical performance of 30% and 40%
conductivity CCS conductors is not significant,
– 40% CCS conductor product has a better protection of the inner
steel core against corrosion resulting from either soil chemistry, or
3rd party damage of the outer copper coating, and is recommended
over 30%CCS
18
Challenges for the Design of Wind and Solar Power
Plant Grounding System for Personal Safety
Applicability of Electrical Code (NESC/CEC) to WPP & Solar Power
Plant Grounding
IEEE PES 2016 General Meeting, Boston, MA, July 17‐21, 2016.
Presentation by:
Tracker Goree, Electrical Design Engineer, RES-Americas
Abdou Sana, P.Eng, Ph.D, Electrical Engineering Specialist, RES-Americas
1
2
Appx. 8 mi
Appx.7mi
• 1‐ Bare Ground Removal 
• 2‐ Mid Span Grounding
• 3‐ Redundant Path Requirements 
3
1‐ Bare Trench Ground Requirements
NESC Rule 354 D.2.a(3) 
“A separate conductor in contact with the earth and in close 
proximity to the cable, where such cable or cables also have a 
grounded sheath or shield not necessarily in contact with the 
earth. The sheath, shield or both as well as the separate 
conductor, shall be adequate for the expected magnitude and 
duration of the fault currents that may be imposed.” 
This means that to remove the bare ground conductor one 
needs to provide either of the following:
4
• Unjacketed Cable (Concentric neutrals are bare and in contact 
with the soil)
or
• Semi‐conductive jacketed concentric neutral.(Outer Jacket 
made from semi‐conductive material (appx. 100 ohm.m)
• Unjacketed concentric neutral cable is subject to corrosion
• Semi‐conductive jacketed cable are costly items. 
5
6
Ground Impedance Calculations were done using an interconnected model both including
and excluding the bare ground conductor.
Split Factor Calculations were done for each location both including and excluding the
bare ground conductor.
The GPR was calculated as a product of the short circuit current, split factor, and ground
resistance.
GPR = I_ShC * L_f * S_f * Rg
I_ShC = Actual Short-circuit current
L_f = Load Growth Factor =110%
S_f = Split factor (calculated)
Rg = Ground grid resistance
Touch and Step voltages were calculated based on simulation plots as a percentage of
the GPR.
Vtouch = Vtouch% * GPR
Vstep = Vsep% * GPR
7
8
Of the 42 locations evaluated: Roughly 50% of the locations considered were
unsafe without the use of crushed rock.
All Sites were safe when considered with the use of crushed rock.
This study was conducted using one median soil resistivity model with an average
of roughly 100 ohm-m.
If this resistivity is increased beyond 100 ohm-m what will be the effect?
Assumptions:
• Only the interconnected impedance was changed according to soil resistivity in the
calculation.
• Split factor and all other variables were considered to be the same for this exercise.
• Safety Criteria was held constant for this exercise.
9
10
0
100
200
300
400
500
600
700
800
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Touch Voltage
Average Soil Resistivity
Average Soil Resistivity Vs Touch Voltage
With Bare GND
Conductor
Without Bare GND
Conductor
Safety Criteria
Without Crushed
Rock
Safety Criteria With
Crushed Rock
Main Implications of Rule for Solar and WPP
• It has been shown in this case study that if the grounding conductor is removed the
split factor, the network impedance and subsequently the GPR will increase. This
increase in GPR will consequently increase touch and step voltages. The higher the
soil resistivity is the greater this increase will be.
• This increase may motivate the need for mitigation measures in order to achieve
safety and this will have an associated cost impact.
• From an NESC applicability standpoint. Rule 354-D.2.a(3) is restrictive in enforcing
unjacketed concentric neutral or semi conducting jacket in-lieu of the trench
ground, however the study proves that under certain soil conditions (low rho and low
SC current) and/or with the use of crushed rock, the safety criteria can be met
without the trench conductor or the semi-conducting jacket or unjacketed concentric
neutral.
• For med. to high rho value soil safety can be difficult to achieve without costly
mitigation. In addition many wind turbine manufacturers local grounding or lightning
protection requirements will be difficult to meet at reasonable cost. (namely those of
IEC 61400-24).
• Further Analysis is needed to determine the effects of soil structure on this
comparison and to evaluate the economics associated with the various code
compliant solutions.
11
2‐ Mid Span Grounding Requirements
NESC Rule 096C : Multi Grounded Systems 
“The neutral, which shall be of sufficient size and ampacity for 
the duty involved, shall be connected to a made or existing 
electrode at each transformer location and at a sufficient 
number of additional points with the made or existing 
electrodes to total not less than four grounds in each 1.6 km (1 
mi) of the entire line, not including grounds at individual 
services.” 
12
Mid Span Grounding Requirements
NESC Rule 354‐D.3.c : Random separation (<12in) between 
Insulating jacketed grounded neutral supply cables and 
communication cables 
“Grounded in accordance with Rule 314 except that the 
grounding interval required by Rule 96C shall be not less than 
eight in each 1.6 km (1 mile) of the random buried section, not 
including grounds at individual services” 
13
NESC Rule 96C when Applied to Wind Power Plant collection 
Systems:
‐ Distances in‐between WTG are less or slightly  greater than 
400m (1/4 mile)
‐ Feeders (home runs) length may >5miles  and Each additional 
grounding point is a an additional potential point of failure
‐ WPP and SPP MV collection systems are generally run as 
Balanced networks, with Delta/Wye MV/LV transformers, and 
are therefore not generally subject to standing Neutral load 
current flow.
14
Cable Shield/sheath Standing Voltages 
3 Phase – Cables Trefoil
Typical : d=2.2in; S=d; S/d~1
3 Phase – Cable Flat Formation
- Transposed Cross-bonded
(T&XB)
- Single Point Bonded (SPB)
Typical: d=2.2in; S=12in
Installation
IEEE Std 575‐2014
‐ Trefoil –Cables Touching (S/d=1) : E= 60V/1000m/1000A
‐ Flat ‐ Cable Transposed & Screen Cross‐Bonded (T&XB  ‐ S/d=5.5): 
E= 180V/1000m/1000A 
‐ Flat ‐ Single Point Bonded (SPB – S/d=5.5): E= 180V/1000m/1000A
Installation
Method
Installation
Configuration
Max Acceptable
Full-Load
Standing Sheath
Voltage
Max Continuous
Loading
Max Length for Max
Acceptable Sheath
Standing Voltage
NESC 096C
- 4xGnd/Mile
V/km/kA (V) (A) (ft) (ft)
300 11847
350 10155
400 8886
450 7898
500 7108
550 6462
600 5924
300 3949
350 3385
400 2962
450 2633
500 2369
550 2154
600 1975
300 1519
350 1302
400 1139
450 1013
500 911
550 828
600 759
Direct Buried
Direct Buried Flat - T&XB
Flat - SPBDirect Buried
Assumed per-unit sheath voltage values (IEEE 575-2014- Figure 1):
- Trefoil - Cables Touching: 60V/1000m/1000A
- Flat - Single Point Bonded (Flat-SPB): 180V/1000m/1000A
- Flat - Cable Transposed & Screen Cross-Bonded (Flat-T&XB): 180V/1000m/1000A for "Minor" Section Lengths
Maximum acceptable full-load standing sheath voltage (IEEE 575-2014 Annex C1):
- 65V for Trefoil or Flat formation Transposed and cross-bonded
- 25V for Flat formation and Shield Single Point Bonded SPB cable terminations
Sheath Induced Voltage Based on Loading In accordance with IEEE 575-2014 - Concentric Neutral Shielded Cable
60.000
180.000
180.000
65
65
25
1320
1320
1320
Continous Loading
Trefoil
18
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
11000
12000
300 350 400 450 500 550 600
Cable Section Length (ft)
Maximum Continuous Loading Current (Amp)
Maximum Cable Length for Sheath Induced Voltage <65V vs Loading 
In accordance with IEEE 575‐2014  ‐
Trefoil ‐
V_Sheath<65V
Flat ‐ T&XB ‐
V_Sheath<65V
Flat ‐ SPB ‐
V_Sheath<25V
NESC
4xGnd/Mile
Main Implications of Rule for Solar and WPP
‐ For cable in trefoil touching and cables in flat formation 
transposed and cross‐bonded: 
‐ Acceptable shield standing voltages of Max 65V can be achieved.
‐ Section lengths far greater than ¼ mile are acceptable without shield 
grounding for typical feeder maximum current loading of 600A. 
‐ Sections length without need for shield grounding are even greater for 
lower current loading <600A. 
‐ NESC rule 96C requires max 1320ft (1/4mile)
19
3‐ Redundant Ground Conductor for Substation 
Remote Ground Electrodes
36‐302 (3)(a) Ontario Safety Code 
“ … Two grounding conductors of a minimum of No. 2/0 AWG 
copper shall connect the ground electrode to the station 
equipment in such a way that should one grounding conductor 
or ground electrode be damaged, no single metal structure or 
equipment frame may become isolated;…” 
This Rule is enforced by the Ontario Electrical Safety Authority as 
follows:
20
• Each remote grounding station has to be connected to the 
substation by redundant paths which is either: 
– a double ground conductor (bare or OHG) or
– a looped ground connection to the substation through 2 or more 
circuits)
• If underground shielded cables (Concentric Neutral, tape 
shield etc..) are used, the cable shield shall not be considered 
a current return path (don’t count on it). 
• If OHL are used, the neutral cannot be considered a sufficient 
path for fault current return 
• In addition, the grounding system shall exhibit a GPR < 5000V 
and be safe (V_Step ≤ Safe V_Step;  and V_Touch ≤ Safe 
V_Touch)
21
• If any of the above conditions cannot be achieved, then the 
remote ground station and the substation have to be safe as 
standalone.
– Full short‐circuit applicable,
– No allowance for ground fault current split factor
– No allowance to consider an interconnected ground grid resistance
This rule is understandable for a substation with remote 
electrodes (counterpoise terminated by a ground rod). However,  
for WTG and Solar PP it’s a big challenge 
22
23
For Wind PP, any WTG grounding station is considered remote to 
the main substation and needs to comply with the above rule 
(safe as standalone), or use redundant ground conductors 
(double or looped ground or both)
A Typical WPP Plant Feeder Ground has to be doubled
Single Ground
Conductor System
Double Ground
Conductors 1
24
Fully looped or mixed lopped and double ground conductors may be used.  
Mix of Double and Looped
Ground Conductors
Looped Ground
Conductors
25
For Solar PP., each inverter station is considered remote to the 
main substation and needs to comply with the above rule (safe 
as standalone, or use redundant ground conductors (double or 
looped ground or both)
Main Implications of OSC Rule 36‐302 (3)(a) for Solar & WPP
• Extraordinary cost increase especially on difficult soils 
(500Ohm.m and above) up to 15,000$ per WTG
• Improved Personnel Safety ? 
– Safety is achieved with standard  calculations without need to apply 
this Rule
– UG and OH systems layout are such that the ground conductor 
cannot be severed without cutting the communication cable and 
hence cannot be unnoticed. The intent of redundancy is thus 
achieved through a careful and methodic trench and OHL layout.
– Even if the ground conductor is voluntarily severed without 
touching the communication system,  part of phase to ground 
current will still flow in the concentric neutral  and hence a split 
factor should be allowed to be applied for the standalone cases.
– Due to inductive coupling and outer jacket insulation the split 
factor component of the concentric neutral is more stable than that 
of the bare ground conductor. 
26
27
1
Challenges for the Design of Wind and Solar Power 
Plant Grounding System for Personal Safety
WPP Grounding System Design Challenges on High Resistivity Ground
IEEE PES 2016 General Meeting Boston MA July 17‐21 2016IEEE PES 2016 General Meeting, Boston, MA, July 17‐21, 2016.
Presentation by:Presentation by:
Andrew Cadmore CEng MIET, RES Ltd., Principal Electrical Design Engineer
Project 'A' Windfarm
2
Project  A  Windfarm,
Ontario, Canada (2010/11), ( / )
98.9MW (43x 2.3MW turbines) project ~60km north‐east of 
Thunder Bay. Project required 10.3km (49 spans) of new build 
d l i it 230kV t i i li f th P i t Ofdual circuit 230kV transmission line from the new Point Of 
Interconnection Switching Station (POI) to the new Windfarm 
230/34.5kV Main Substation (WF Sub). RES were responsible for230/34.5kV Main Substation (WF Sub). RES were responsible for 
all project electrical design works, inc. 230kV POI through to LV 
terminals at base of each wind turbine.
230kV Grid Connection
3
230kV Grid Connection
Existing
Remote Sub ‘B’Remote Sub  B
Sub
183km
New Windfarm 
230/34.5kV Sub
New POI 
230kV Sw.Sta.
10.3km
47km
Grid Point of
Interconnection
Existing
Remote Sub ‘C’
S bSub
230kV Transmission Line Design
4
230kV Transmission Line Design
OPGW 1
129mm²
OPGW 2
A1 C2A1
B1
C2
B2B1 B2
C1 A2
400mm²
ACSR
Soil Resistivity
5
Soil Resistivity
Electrical soil resistivity ‘ρ’ increased significantly between POI 
and WF Sub, as windfarm is located on the Canadian Granite 
Cap. Grounding analysis software was used to determine 
equivalent multi‐layer soil models along OHL route, terminal 
substations and throughout the windfarm collection systemsubstations and throughout the windfarm collection system.  
OEB/HONI Transmission Code design criteria required the 
connected facility grounding be designed for a ground return y g g g g
current of ‘Ig = 25kA’ (actual max 3.9kA) at the POI, reducing to 
10.7kA (actual max 3.2kA) at WF Sub. 
Wide Range of Soil Resistivity
6
Wide Range of Soil Resistivity
Project 'A'
Range of Electrical Soil Resistivity:
From 230kV POI Switching Station to Windfarm 230/34.5kV Main Substation
100,000
g /
Windfarm Median
10,000
istivity
WF 230/34.5kV SUB
200m from SUB
400m from SUB
600m from SUB
800mfrom SUB
1,000
Electrical Soil Resi
(ohm‐m)
800m from SUB
1000m from SUB
3300m from SUB
Midway SWY/SUB
900m from SWY
1,000
790m from SWY
600m from SWY
420m from SWY
140m from SWY
60m from SWY
100
0.1 1.0 10.0 100.0
Average Electrode Spacing
(m)
POI 230kV SWY
Ground Electrodes
7
Ground Electrodes
b d l d d d ‘ ’ hWF Sub stand‐alone ground grid design = ‘Rg = 29.79Ω’ even with 6x 100m 
vertical electrodes, reducing to ‘Zg+wf = 3.25 + j0.73Ω’ upon connection to 
windfarm grounding system. WF Sub grid required to be designed stand‐alone 
sufficient.
Grounding analysis software was used to model all ground electrode systems, g y g y ,
allowing full consideration of internal impedances.
RES specified installation of 2x low resistance OPGW sky wires and control ofRES specified installation of 2x low resistance OPGW sky wires, and control of 
OHL pole ground electrode ‘Rtg’ values, to reduce current split factor (Sf) as 
seen from both ends.
Rtg ≤95Ω ‐ except initial 7x poles out from POI Rtg ≤9Ω
Windfarm Sub Ground Grid
8
Windfarm Sub Ground Grid
-30
0 SOIL SURFACE
60
30
XIS(METERS)
90
ZAX
54
84
114
Y
AXIS
(M
ETE
120
-36
-6
24
TERS)
-30 0 30 60 90 120
XAXIS (METERS)
WF Sub Ground Grid – 3D View
XAXIS (METERS)
3-D View of Conductors
Windfarm Grounding System
9
Windfarm Grounding System
3000
00
-3000 WF Sub
-7500 -4500 -1500 1500 4500 7500
-6000
Windfarm Grounding System – Plan View
230kV T L Pole Ground Electrodes
10
230kV T.L. Pole Ground Electrodes
100
Project 'A'
230kV Terminal & Pole Earth Electrode Resistances
80
90
50
60
70
de Resistance
ms)
30
40
50
Earth Electrod
(ohm
10
20
0
0 5 10 15 20 25 30 35 40 45 50
Overhead Line Structure
(No.)
Earth Resistance (Design) Earth Resistance (Test)
POISw.Stn.
WF Sub
Ground Potential Rise
11
Ground Potential Rise
OESC GPR limit of ≤5kV was not practically achievable. 
Therefore, as an OESC permitted deviation, RES recommended p
the IEEE 367 value of 25kV be the max GPR limit. IEEE 80: 2000, 
Table C.1, covers many transmission line scenarios for calculation 
f ‘S ’ b did f h j ' ' i G diof ‘Sf’, but did not cater for the Project 'A' scenario. Grounding 
analysis software was used to analyse and calculate bespoke 
values of ‘S ’ allowing for: 2x parallel low resistance OPGWvalues of  Sf  allowing for: 2x parallel low resistance OPGW 
conductors; variable span lengths; variable pole ‘Rtg‘ values; 
variable soil resistivity ‘ρ’ along OHL route.
Standard v Optimised Design
12
Standard v Optimised Design
Applicable Standard and Code Requirements
If Rg Sf Ig GPR
Applicable Standard and Code Requirements
(A) (ohm) (%) (A) (V)
Ontario Electrical Safety Code (OESC) 24th Ed.: 2009 ‐ Rule 36‐304:
Standard GPR Limit
≤5,000
Ontario Electrical Safety Code (OESC) 24th Ed.: 2009 ‐ Rules 36‐304 & 2‐030:
E t d d GPR Li it P itt d d i ti ith itt OESA l
>5,000
Extended GPR Limit ‐ Permitted deviation with written OESA approval
,
IEEE 367: 1996 ‐ Clause 4.2 ‐ Possible high GPR under 'unusual circumstances' ≤25000
Calculation Methods
IEEE 80: 2000 ‐ Table C.1: 1x Transmission Line; 0x Distribution Lines 
1x 7x #10 AWG (36 8mm²) Alumoweld (ACS) Shield Wire R 2 94Ω/km @ 20°C
18.20% 1,941 57,837
1x 7x #10 AWG (36.8mm²) Alumoweld (ACS) Shield Wire: Rac = 2.94Ω/km @ 20°C
IEEE 80: 2000 ‐ Table C.1: 2x Transmission Lines; 0x Distribution Lines 
2x 7x #10 AWG (36.8mm²) Alumoweld (ACS) Shield Wire: Rac = 2.94Ω/km @ 20°C
10.00% 1,067 31,779
Calculated: 1x Single Circuit Transmission Line (Check against IEEE 80, Table C.1)
( ²) l ld ( ) h ld /k °
18.22% 1,943 57,88529.79
1x 7x #10 AWG (36.8mm²) Alumoweld (ACS) Shield Wire: Rac = 2.94Ω/km @ 20°C
8 % ,9 3 5 ,885
Calculated: 1x Dual Circuit Transmission Line
2x 7x #10 AWG (36.8mm²) Alumoweld (ACS) Shield Wire: Rac = 2.94Ω/km @ 20°C
13.10% 1,398 41,636
Calculated: 1x Dual Circuit Transmission Line ‐ Design approved by HONI & OESA
2x OPGW (129mm²) ACS/AA Shield Wire Rac 0 423Ω/km @ 20°C
5.82% 620 18,486
10,667
2x OPGW (129mm²) ACS/AA Shield Wire: Rac = 0.423Ω/km @ 20°C
Calculated: 1x Dual Circuit Transmission Line ‐ As‐Built approved by HONI & OESA
2x OPGW (129mm²) ACS/AA Shield Wire: Rac = 0.423Ω/km @ 20°C
21.40 6.17% 658 14,090
Design Validation
13
Design Validation
Following site testing of as‐built works, and using the same g g , g
grounding analysis software,  RES undertook validation checks of 
design calculations based on the as‐built ground electrode 
resistance test data taken from the terminal substations and 
each line pole. Both Design and As‐Built installation were 
accepted and approved by HONI & OESAaccepted and approved by HONI & OESA.
Design Validation
14
Design Validation
50%20000
Project 'A'
Current Split Factor Curve ‐ 230/34.5kV Windfarm Sub
29.821.43.25 3.30
40%
45%
50%
16000
18000
20000
25%
30%
35%
10000
12000
14000
t Split Factor
(%)
Potential Rise
(volts)
10%
15%
20%
4000
6000
8000
Curren
Ground 
(
0%
5%
10%
0
2000
4000
0.1 1.0 10.0 100.0
Earth Electrode Resistance  seen at Windfarm Main  Sub
(ohms)
OEB/HONI GPR [10.67kA] (Design) OEB/HONI GPR [10.67kA] (As‐Built) Max Actual GPR [3.16kA] (Design) Max Actual GPR [3.16kA] (As‐Built)
OESC 5000V (Design) Current Split Factor (Design) Current Split Factor (As‐Built) R Grid (Design)
R Grid (As‐Built) R Windfarm (Design) R Windfarm (As‐Built)
Conclusion
15
Conclusion
The grounding design criteria at Project 'A' WPP proved to be g g g j p
very challenging throughout, particularly at the 230kV terminal 
substations. However, in‐depth modelling and analysis of the 
230kV transmission line configuration, to accurately calculate 
ground fault current split factors, demonstrated: excellent 
correlation between IEEE 80 2000 Table C 1 values and analysiscorrelation between IEEE 80‐2000, Table C.1 values and analysis 
results; opportunity to improve on standard split factor values 
through in‐depth modelling of an enhanced OPGW conductor g p g
installation; very good validation of design values through 
extensive on‐site testing prior to approval and commissioning.
All helping to provide a confident design solution, for a very 
difficult grounding environment.

More Related Content

What's hot

Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable SizingLeonardo ENERGY
 
Cable sizing to withstand short circuit current
Cable sizing to withstand short circuit currentCable sizing to withstand short circuit current
Cable sizing to withstand short circuit currentLeonardo ENERGY
 
Design off grid solar PV system
Design off grid solar PV systemDesign off grid solar PV system
Design off grid solar PV systemRajesh Pindoriya
 
ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2Himmelstern
 
Flexible AC Transmission (FACTS)
Flexible AC Transmission (FACTS)Flexible AC Transmission (FACTS)
Flexible AC Transmission (FACTS)SHIMI S L
 
Low Voltage Circuit Breaker
Low Voltage Circuit BreakerLow Voltage Circuit Breaker
Low Voltage Circuit BreakerAbdul Haseeb
 
A STATCOM CONTROL SCHEME FOR POWER QUALITY IMPROVEMENT OF GRID CONNECTED TO W...
A STATCOM CONTROL SCHEME FOR POWER QUALITY IMPROVEMENT OF GRID CONNECTED TO W...A STATCOM CONTROL SCHEME FOR POWER QUALITY IMPROVEMENT OF GRID CONNECTED TO W...
A STATCOM CONTROL SCHEME FOR POWER QUALITY IMPROVEMENT OF GRID CONNECTED TO W...Power System Operation
 
PSCAD Final Report
PSCAD Final ReportPSCAD Final Report
PSCAD Final ReportJeff Ge
 
ETAP - Transformer mva sizing
ETAP - Transformer mva sizingETAP - Transformer mva sizing
ETAP - Transformer mva sizingHimmelstern
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION moiz89
 
Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...
Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...
Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...usman1441
 
substation automation
substation automationsubstation automation
substation automationMahbub Rashid
 
Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Sifan Welisa
 
Thyristor switched capacitor PPT
Thyristor switched capacitor PPTThyristor switched capacitor PPT
Thyristor switched capacitor PPTKLS' S GIT, BELGAUM
 

What's hot (20)

Microgrids
MicrogridsMicrogrids
Microgrids
 
Solar Power Plant Design and PV Syst
Solar Power Plant Design and PV SystSolar Power Plant Design and PV Syst
Solar Power Plant Design and PV Syst
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
 
IEEE substation design
IEEE substation designIEEE substation design
IEEE substation design
 
Cable sizing to withstand short circuit current
Cable sizing to withstand short circuit currentCable sizing to withstand short circuit current
Cable sizing to withstand short circuit current
 
Design off grid solar PV system
Design off grid solar PV systemDesign off grid solar PV system
Design off grid solar PV system
 
ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2
 
Flexible AC Transmission (FACTS)
Flexible AC Transmission (FACTS)Flexible AC Transmission (FACTS)
Flexible AC Transmission (FACTS)
 
Insulation coordination
Insulation coordinationInsulation coordination
Insulation coordination
 
Low Voltage Circuit Breaker
Low Voltage Circuit BreakerLow Voltage Circuit Breaker
Low Voltage Circuit Breaker
 
A STATCOM CONTROL SCHEME FOR POWER QUALITY IMPROVEMENT OF GRID CONNECTED TO W...
A STATCOM CONTROL SCHEME FOR POWER QUALITY IMPROVEMENT OF GRID CONNECTED TO W...A STATCOM CONTROL SCHEME FOR POWER QUALITY IMPROVEMENT OF GRID CONNECTED TO W...
A STATCOM CONTROL SCHEME FOR POWER QUALITY IMPROVEMENT OF GRID CONNECTED TO W...
 
Solar pv connected to grid
Solar pv connected to gridSolar pv connected to grid
Solar pv connected to grid
 
Facts
FactsFacts
Facts
 
PSCAD Final Report
PSCAD Final ReportPSCAD Final Report
PSCAD Final Report
 
ETAP - Transformer mva sizing
ETAP - Transformer mva sizingETAP - Transformer mva sizing
ETAP - Transformer mva sizing
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
 
Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...
Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...
Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...
 
substation automation
substation automationsubstation automation
substation automation
 
Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]
 
Thyristor switched capacitor PPT
Thyristor switched capacitor PPTThyristor switched capacitor PPT
Thyristor switched capacitor PPT
 

Similar to Ccs for solar power pv plant

CorrosionCathProtBasicDesignSATX
CorrosionCathProtBasicDesignSATXCorrosionCathProtBasicDesignSATX
CorrosionCathProtBasicDesignSATXStanley Worcester
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Audubon Engineering Company
 
Jmv Presentation Airport and JMV LPS LTD
Jmv Presentation Airport and JMV LPS LTDJmv Presentation Airport and JMV LPS LTD
Jmv Presentation Airport and JMV LPS LTDMahesh Chandra Manav
 
Corrosion Assessment – Half-Cell Potential Method for reinforced concrete
Corrosion Assessment – Half-Cell Potential Method for reinforced concreteCorrosion Assessment – Half-Cell Potential Method for reinforced concrete
Corrosion Assessment – Half-Cell Potential Method for reinforced concreteYash Shah
 
MAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONS
MAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONSMAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONS
MAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONSFluxtrol Inc.
 
Magnetism Circuit.ppt
Magnetism Circuit.pptMagnetism Circuit.ppt
Magnetism Circuit.pptELESAiteAshok
 
Exp4_Study of Various Types of Earthing (1).pptx
Exp4_Study of Various Types of Earthing (1).pptxExp4_Study of Various Types of Earthing (1).pptx
Exp4_Study of Various Types of Earthing (1).pptxpalanisekar
 
New generation of copper conductors for overhead lines
New generation of copper conductors for overhead linesNew generation of copper conductors for overhead lines
New generation of copper conductors for overhead linesLeonardo ENERGY
 
New generation of copper conductors for overhead lines
New generation of copper conductors for overhead linesNew generation of copper conductors for overhead lines
New generation of copper conductors for overhead linesLeonardo ENERGY
 
64132673-Cathodic-Protection- diseños-Design.ppt
64132673-Cathodic-Protection- diseños-Design.ppt64132673-Cathodic-Protection- diseños-Design.ppt
64132673-Cathodic-Protection- diseños-Design.pptomar681193
 
Medium strength high conductivity materials
Medium strength high conductivity materialsMedium strength high conductivity materials
Medium strength high conductivity materialsLeonardo ENERGY
 
Electrical Services & Cast Iron Earthing Pipe By Vaidehi E. Link, Maharashtra
Electrical Services & Cast Iron Earthing Pipe By Vaidehi E. Link, MaharashtraElectrical Services & Cast Iron Earthing Pipe By Vaidehi E. Link, Maharashtra
Electrical Services & Cast Iron Earthing Pipe By Vaidehi E. Link, MaharashtraIndiaMART InterMESH Limited
 
Steel grounding-design-guide-and-application-notes
Steel grounding-design-guide-and-application-notesSteel grounding-design-guide-and-application-notes
Steel grounding-design-guide-and-application-notesNick Wang
 
Micro-alloyed copper overhead line conductors - PowerGrid International Augus...
Micro-alloyed copper overhead line conductors - PowerGrid International Augus...Micro-alloyed copper overhead line conductors - PowerGrid International Augus...
Micro-alloyed copper overhead line conductors - PowerGrid International Augus...Leonardo ENERGY
 
MOSFET, SOI-FET and FIN-FET-ABU SYED KUET
MOSFET, SOI-FET and FIN-FET-ABU SYED KUETMOSFET, SOI-FET and FIN-FET-ABU SYED KUET
MOSFET, SOI-FET and FIN-FET-ABU SYED KUETA. S. M. Jannatul Islam
 
Impressed Current Cathodic Protection System Design ICCP
Impressed Current Cathodic Protection System Design ICCPImpressed Current Cathodic Protection System Design ICCP
Impressed Current Cathodic Protection System Design ICCPTauseef bin Abdul Rashid
 
Cathodic Protection For Oil Wells
Cathodic Protection For Oil WellsCathodic Protection For Oil Wells
Cathodic Protection For Oil WellsAbinash Padhy
 

Similar to Ccs for solar power pv plant (20)

CorrosionCathProtBasicDesignSATX
CorrosionCathProtBasicDesignSATXCorrosionCathProtBasicDesignSATX
CorrosionCathProtBasicDesignSATX
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
 
Jmv Presentation Airport and JMV LPS LTD
Jmv Presentation Airport and JMV LPS LTDJmv Presentation Airport and JMV LPS LTD
Jmv Presentation Airport and JMV LPS LTD
 
Corrosion Assessment – Half-Cell Potential Method for reinforced concrete
Corrosion Assessment – Half-Cell Potential Method for reinforced concreteCorrosion Assessment – Half-Cell Potential Method for reinforced concrete
Corrosion Assessment – Half-Cell Potential Method for reinforced concrete
 
MAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONS
MAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONSMAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONS
MAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONS
 
Magnetism Circuit.ppt
Magnetism Circuit.pptMagnetism Circuit.ppt
Magnetism Circuit.ppt
 
3-Cs Eucas 2015 Poster v2
3-Cs Eucas 2015 Poster v23-Cs Eucas 2015 Poster v2
3-Cs Eucas 2015 Poster v2
 
ملزمة
ملزمةملزمة
ملزمة
 
Exp4_Study of Various Types of Earthing (1).pptx
Exp4_Study of Various Types of Earthing (1).pptxExp4_Study of Various Types of Earthing (1).pptx
Exp4_Study of Various Types of Earthing (1).pptx
 
New generation of copper conductors for overhead lines
New generation of copper conductors for overhead linesNew generation of copper conductors for overhead lines
New generation of copper conductors for overhead lines
 
New generation of copper conductors for overhead lines
New generation of copper conductors for overhead linesNew generation of copper conductors for overhead lines
New generation of copper conductors for overhead lines
 
64132673-Cathodic-Protection- diseños-Design.ppt
64132673-Cathodic-Protection- diseños-Design.ppt64132673-Cathodic-Protection- diseños-Design.ppt
64132673-Cathodic-Protection- diseños-Design.ppt
 
Jmv presentation solar
Jmv  presentation solarJmv  presentation solar
Jmv presentation solar
 
Medium strength high conductivity materials
Medium strength high conductivity materialsMedium strength high conductivity materials
Medium strength high conductivity materials
 
Electrical Services & Cast Iron Earthing Pipe By Vaidehi E. Link, Maharashtra
Electrical Services & Cast Iron Earthing Pipe By Vaidehi E. Link, MaharashtraElectrical Services & Cast Iron Earthing Pipe By Vaidehi E. Link, Maharashtra
Electrical Services & Cast Iron Earthing Pipe By Vaidehi E. Link, Maharashtra
 
Steel grounding-design-guide-and-application-notes
Steel grounding-design-guide-and-application-notesSteel grounding-design-guide-and-application-notes
Steel grounding-design-guide-and-application-notes
 
Micro-alloyed copper overhead line conductors - PowerGrid International Augus...
Micro-alloyed copper overhead line conductors - PowerGrid International Augus...Micro-alloyed copper overhead line conductors - PowerGrid International Augus...
Micro-alloyed copper overhead line conductors - PowerGrid International Augus...
 
MOSFET, SOI-FET and FIN-FET-ABU SYED KUET
MOSFET, SOI-FET and FIN-FET-ABU SYED KUETMOSFET, SOI-FET and FIN-FET-ABU SYED KUET
MOSFET, SOI-FET and FIN-FET-ABU SYED KUET
 
Impressed Current Cathodic Protection System Design ICCP
Impressed Current Cathodic Protection System Design ICCPImpressed Current Cathodic Protection System Design ICCP
Impressed Current Cathodic Protection System Design ICCP
 
Cathodic Protection For Oil Wells
Cathodic Protection For Oil WellsCathodic Protection For Oil Wells
Cathodic Protection For Oil Wells
 

More from Mahesh Chandra Manav

The Ministry of Road Transport and Highways with Electric Vehicle Charging an...
The Ministry of Road Transport and Highways with Electric Vehicle Charging an...The Ministry of Road Transport and Highways with Electric Vehicle Charging an...
The Ministry of Road Transport and Highways with Electric Vehicle Charging an...Mahesh Chandra Manav
 
Building Automation,Networking & Communication Presentation by LVS 2022.pdf
Building Automation,Networking & Communication Presentation by LVS 2022.pdfBuilding Automation,Networking & Communication Presentation by LVS 2022.pdf
Building Automation,Networking & Communication Presentation by LVS 2022.pdfMahesh Chandra Manav
 
Indian railway&amp;metro rail,others electrical safety first periorty
Indian railway&amp;metro rail,others electrical safety first periortyIndian railway&amp;metro rail,others electrical safety first periorty
Indian railway&amp;metro rail,others electrical safety first periortyMahesh Chandra Manav
 
National green building code 2021 india kaya kool hey hum by link vue system
National green building code 2021 india  kaya kool hey hum by link vue systemNational green building code 2021 india  kaya kool hey hum by link vue system
National green building code 2021 india kaya kool hey hum by link vue systemMahesh Chandra Manav
 
Lightning it's not joke kills or destry only safety first
Lightning it's not joke kills or destry only safety firstLightning it's not joke kills or destry only safety first
Lightning it's not joke kills or destry only safety firstMahesh Chandra Manav
 
Electric vehicle charging information. by linkvue system
Electric vehicle charging   information. by linkvue systemElectric vehicle charging   information. by linkvue system
Electric vehicle charging information. by linkvue systemMahesh Chandra Manav
 
Solar power and our application (2)
Solar power and our application (2)Solar power and our application (2)
Solar power and our application (2)Mahesh Chandra Manav
 
Link vue system and solar pv power plant protection
Link vue system and solar pv power plant protectionLink vue system and solar pv power plant protection
Link vue system and solar pv power plant protectionMahesh Chandra Manav
 
Electrical Failure ,Short Circuit Reason Cables and Termination
Electrical Failure ,Short Circuit Reason Cables and TerminationElectrical Failure ,Short Circuit Reason Cables and Termination
Electrical Failure ,Short Circuit Reason Cables and TerminationMahesh Chandra Manav
 
High speed electric sky pods for passenger and cargo presentation by link vue
High speed electric sky pods for passenger and cargo presentation by link vueHigh speed electric sky pods for passenger and cargo presentation by link vue
High speed electric sky pods for passenger and cargo presentation by link vueMahesh Chandra Manav
 
Presentation for power plant 2021 by link vue system
Presentation for power plant 2021 by link vue systemPresentation for power plant 2021 by link vue system
Presentation for power plant 2021 by link vue systemMahesh Chandra Manav
 
Building management system from link vue system
Building management system  from link vue systemBuilding management system  from link vue system
Building management system from link vue systemMahesh Chandra Manav
 
Safe you and your team from corona virus 2021 by link vue system
Safe you and your team from corona virus 2021 by link vue  systemSafe you and your team from corona virus 2021 by link vue  system
Safe you and your team from corona virus 2021 by link vue systemMahesh Chandra Manav
 
Electric bus best public transport(hum safar)
Electric bus best public transport(hum safar)Electric bus best public transport(hum safar)
Electric bus best public transport(hum safar)Mahesh Chandra Manav
 
A green corridor carbon free road transportation india 2021
A green corridor carbon free road transportation india 2021A green corridor carbon free road transportation india 2021
A green corridor carbon free road transportation india 2021Mahesh Chandra Manav
 
India great intiative a carbon free silent road transportaion electric vehicle
India great intiative a carbon free silent road transportaion electric vehicleIndia great intiative a carbon free silent road transportaion electric vehicle
India great intiative a carbon free silent road transportaion electric vehicleMahesh Chandra Manav
 
Plug&Socket for All Equipment's&System from Link Vue
Plug&Socket for All Equipment's&System from Link VuePlug&Socket for All Equipment's&System from Link Vue
Plug&Socket for All Equipment's&System from Link VueMahesh Chandra Manav
 
Platform touch voltage protection membrane system and other railways buildin...
Platform touch voltage protection membrane system  and other railways buildin...Platform touch voltage protection membrane system  and other railways buildin...
Platform touch voltage protection membrane system and other railways buildin...Mahesh Chandra Manav
 
Aaab Khela HOBO a Dead Man Walking
Aaab Khela HOBO a Dead Man WalkingAaab Khela HOBO a Dead Man Walking
Aaab Khela HOBO a Dead Man WalkingMahesh Chandra Manav
 

More from Mahesh Chandra Manav (20)

The Ministry of Road Transport and Highways with Electric Vehicle Charging an...
The Ministry of Road Transport and Highways with Electric Vehicle Charging an...The Ministry of Road Transport and Highways with Electric Vehicle Charging an...
The Ministry of Road Transport and Highways with Electric Vehicle Charging an...
 
Building Automation,Networking & Communication Presentation by LVS 2022.pdf
Building Automation,Networking & Communication Presentation by LVS 2022.pdfBuilding Automation,Networking & Communication Presentation by LVS 2022.pdf
Building Automation,Networking & Communication Presentation by LVS 2022.pdf
 
Indian railway&amp;metro rail,others electrical safety first periorty
Indian railway&amp;metro rail,others electrical safety first periortyIndian railway&amp;metro rail,others electrical safety first periorty
Indian railway&amp;metro rail,others electrical safety first periorty
 
National green building code 2021 india kaya kool hey hum by link vue system
National green building code 2021 india  kaya kool hey hum by link vue systemNational green building code 2021 india  kaya kool hey hum by link vue system
National green building code 2021 india kaya kool hey hum by link vue system
 
Lightning it's not joke kills or destry only safety first
Lightning it's not joke kills or destry only safety firstLightning it's not joke kills or destry only safety first
Lightning it's not joke kills or destry only safety first
 
Electric vehicle charging information. by linkvue system
Electric vehicle charging   information. by linkvue systemElectric vehicle charging   information. by linkvue system
Electric vehicle charging information. by linkvue system
 
Solar power and our application (2)
Solar power and our application (2)Solar power and our application (2)
Solar power and our application (2)
 
Link vue system and solar pv power plant protection
Link vue system and solar pv power plant protectionLink vue system and solar pv power plant protection
Link vue system and solar pv power plant protection
 
Electrical Failure ,Short Circuit Reason Cables and Termination
Electrical Failure ,Short Circuit Reason Cables and TerminationElectrical Failure ,Short Circuit Reason Cables and Termination
Electrical Failure ,Short Circuit Reason Cables and Termination
 
High speed electric sky pods for passenger and cargo presentation by link vue
High speed electric sky pods for passenger and cargo presentation by link vueHigh speed electric sky pods for passenger and cargo presentation by link vue
High speed electric sky pods for passenger and cargo presentation by link vue
 
Presentation for power plant 2021 by link vue system
Presentation for power plant 2021 by link vue systemPresentation for power plant 2021 by link vue system
Presentation for power plant 2021 by link vue system
 
Building management system from link vue system
Building management system  from link vue systemBuilding management system  from link vue system
Building management system from link vue system
 
Safe you and your team from corona virus 2021 by link vue system
Safe you and your team from corona virus 2021 by link vue  systemSafe you and your team from corona virus 2021 by link vue  system
Safe you and your team from corona virus 2021 by link vue system
 
Electric bus best public transport(hum safar)
Electric bus best public transport(hum safar)Electric bus best public transport(hum safar)
Electric bus best public transport(hum safar)
 
War is not a Solution
War is not a SolutionWar is not a Solution
War is not a Solution
 
A green corridor carbon free road transportation india 2021
A green corridor carbon free road transportation india 2021A green corridor carbon free road transportation india 2021
A green corridor carbon free road transportation india 2021
 
India great intiative a carbon free silent road transportaion electric vehicle
India great intiative a carbon free silent road transportaion electric vehicleIndia great intiative a carbon free silent road transportaion electric vehicle
India great intiative a carbon free silent road transportaion electric vehicle
 
Plug&Socket for All Equipment's&System from Link Vue
Plug&Socket for All Equipment's&System from Link VuePlug&Socket for All Equipment's&System from Link Vue
Plug&Socket for All Equipment's&System from Link Vue
 
Platform touch voltage protection membrane system and other railways buildin...
Platform touch voltage protection membrane system  and other railways buildin...Platform touch voltage protection membrane system  and other railways buildin...
Platform touch voltage protection membrane system and other railways buildin...
 
Aaab Khela HOBO a Dead Man Walking
Aaab Khela HOBO a Dead Man WalkingAaab Khela HOBO a Dead Man Walking
Aaab Khela HOBO a Dead Man Walking
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 

Ccs for solar power pv plant