SlideShare a Scribd company logo
Contracts Management
Principles & Practices
According to FIDIC
By : Essam Mohamed Lotfi, PMP, CCP
• Having a brief of FIDIC
• Understand the steps and stages of Contract Management
Using FIDIC.
• Understand the Role of PM during construction project to
protect the organization Business case.
• Founded in 1913
• Expanded in 1945 to include 40 national associations
• Published first Conditions of Contract in 1957
• In 2004 has 64 member associations
• Headquarters in Switzerland
• Web Site : www.fidic.org
• Conditions of Contract for Construction (Red
Book)
• Conditions of Contract for Plant & Design
Build (Yellow Book)
• Conditions of Contract for EPC Turnkey
Projects (Silver Book)
• Short Form of Contracts (Green Book)
14.3 Contractor
submits
Statement to the
Employer
14.6 Employer
gives Contractor
notice of amount
considered due
14.7 Employer
makes the
payment to the
Contractor
<56d
<28d
Employer verifies the draft final statement, Contractor
submits information
14.11 Contractor submits
draft final statement to the
Employer
14.11 Contractor
submits Final Statement
and the 14.12 discharge
14.7 employer
makes payment
<42d
Each of the
monthly (or
otherwise)
interim
payments
The final
payment
DAB: the persons so named in the contract or other persons appointed
under sub-clause (appointment of the dispute adjudication board)
• The several documents forming the Contract are to be taken as
mutually explanatory of one another, but in case of ambiguities or
discrepancies the same shall be explained and adjusted by the
Engineer who shall thereupon issue to the Contractor instructions
thereon and in such event, unless otherwise provided in the Contract,
the priority of the documents forming the Contract shall be as follows:
(1) The Contract Agreement (if completed);
(2) The Letter of Acceptance;
(3) The Tender;
(4) Part II of these Conditions;
(5) Part I of these Conditions; and
(6) Any other document forming part of the Contract.
• Cl.1.9 Drawings
• Cl.2.1 Site
• Cl.4.7 Setting Out
• Cl.4.12 Unforeseeable
• Cl.4.24 Fossils
• Cl.7.4 Testing
• Cl.8.4 EoT
• Cl.8.4 Adverse Climatic
Conditions
• Cl.13.7 Legislation
• Cl.13.8 Changes in Cost
• Cl.14.8 Delayed
payments
• Cl.19.4 Force Majeure
• Cl.13.1 Right to vary
– Prior to issue of TO
certificate
• Cl.13.2 Value Engineering
– Development risk with
Contractor
– Savings 50/50
CLAIMS & CONTRACTUAL
PROCEDURES
 Majority of construction projects worldwide are
administered by the FIDIC forms of contract.
 FIDIC recognises delay and related costs and has
provisions related thereto. For example;
 Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition)
 Clauses 44 & 53 (FIDIC 1987 Edition)
 Unforeseeable ground conditions
 Delayed drawings
 Delayed payment
 Lack of possession of site
 Consequence of risk
 Suspension
 Force Majeure
 Clause 20.1
o Sets out Contractor procedure
o Condition Precedent
o Not later than 28 days
o Sets out Engineer procedure
 Contractor gives notice
 Within 28 days
 Contractor keeps contemporary records
o Engineer may monitor
o Engineer may instruct further records
 Fully detailed claim
o Supporting documents
 Within 42 days of event
 Crucial for determination of claim
 Records for any future dispute
 Contractor obliged to keep records
 Procedure for this work
 Employer & Engineer to agree Engineer’s
actions
 Cl.20.1 continuing procedure
 After 42 days:
o Claim submission is considered interim
o Further monthly claims
 Final claim with 28 days of end of effects
Fidic contracts management introduction

More Related Content

What's hot

Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
Kai Yun Pang
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
CNC
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
Gattupalli Naresh, PMP
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Project Controls Expo
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
Arvind Solanki
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
M Maged Hegazy, LLM, MBA, CCP, P3O
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
SN Panigrahi, PMP
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Moustafa Ismail Abu Dief
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
Hani Saad
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
ssuserb337ce1
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
Adrias TAN
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
dhiraj.gaur
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
Moustafa Ismail Abu Dief
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
claimsconsultancy
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
Farhan Moosa
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPT
KEVINMISTRY8
 
Contract management
Contract managementContract management

What's hot (20)

Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPT
 
Contract management
Contract managementContract management
Contract management
 

Similar to Fidic contracts management introduction

CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
Bahzad5
 
Fidic.pptx
Fidic.pptxFidic.pptx
Fidic.pptx
Zeeshan Yousaf
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
DonaAlisyahSiregar
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptx
Aditya Mane
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreement
abdmuhaiminyunus
 
17 10 16
17 10 1617 10 16
17 10 16
Suhaib Jibran
 
CIOB Complex Projects Contract 2013 and FIDIC: A Comparison
CIOB Complex Projects Contract 2013 and FIDIC: A ComparisonCIOB Complex Projects Contract 2013 and FIDIC: A Comparison
CIOB Complex Projects Contract 2013 and FIDIC: A Comparison
Francis Ho
 
ICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract managementICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract management
drmujahidkhan85
 
Psscoc 2008 db contract
Psscoc 2008 db contractPsscoc 2008 db contract
Psscoc 2008 db contract
Vance Ang
 
Disputes ans Arbitration..
Disputes ans Arbitration..Disputes ans Arbitration..
Disputes ans Arbitration..
Rajesh Prasad
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
BayuDarma4
 
FIDIC 2019
FIDIC 2019FIDIC 2019
New York City Department of Buildings Filing rep course_203
New York City Department of Buildings Filing rep course_203New York City Department of Buildings Filing rep course_203
New York City Department of Buildings Filing rep course_203
Safe Rise
 
FIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdfFIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdf
sajidkhan82714
 
12953021.ppt
12953021.ppt12953021.ppt
12953021.ppt
Amith Soyza
 
FIDIC intro author eng. mohammed fadlalla
FIDIC intro  author eng. mohammed fadlallaFIDIC intro  author eng. mohammed fadlalla
FIDIC intro author eng. mohammed fadlalla
Mohammed Fadlalla ,PMP ®
 
TOPIC6.pdf
TOPIC6.pdfTOPIC6.pdf
TOPIC6.pdf
HASMANIRA
 
Construction Contract PPT.ppt
Construction Contract PPT.pptConstruction Contract PPT.ppt
Construction Contract PPT.ppt
MohammedAbdu46
 
NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012
Ola Odejayi
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 Newsletter
SeanGibbs12
 

Similar to Fidic contracts management introduction (20)

CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
 
Fidic.pptx
Fidic.pptxFidic.pptx
Fidic.pptx
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptx
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreement
 
17 10 16
17 10 1617 10 16
17 10 16
 
CIOB Complex Projects Contract 2013 and FIDIC: A Comparison
CIOB Complex Projects Contract 2013 and FIDIC: A ComparisonCIOB Complex Projects Contract 2013 and FIDIC: A Comparison
CIOB Complex Projects Contract 2013 and FIDIC: A Comparison
 
ICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract managementICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract management
 
Psscoc 2008 db contract
Psscoc 2008 db contractPsscoc 2008 db contract
Psscoc 2008 db contract
 
Disputes ans Arbitration..
Disputes ans Arbitration..Disputes ans Arbitration..
Disputes ans Arbitration..
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
FIDIC 2019
FIDIC 2019FIDIC 2019
FIDIC 2019
 
New York City Department of Buildings Filing rep course_203
New York City Department of Buildings Filing rep course_203New York City Department of Buildings Filing rep course_203
New York City Department of Buildings Filing rep course_203
 
FIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdfFIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdf
 
12953021.ppt
12953021.ppt12953021.ppt
12953021.ppt
 
FIDIC intro author eng. mohammed fadlalla
FIDIC intro  author eng. mohammed fadlallaFIDIC intro  author eng. mohammed fadlalla
FIDIC intro author eng. mohammed fadlalla
 
TOPIC6.pdf
TOPIC6.pdfTOPIC6.pdf
TOPIC6.pdf
 
Construction Contract PPT.ppt
Construction Contract PPT.pptConstruction Contract PPT.ppt
Construction Contract PPT.ppt
 
NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 Newsletter
 

More from Essam Lotffy, PMP®, CCP®

Introduction to quality management
Introduction to quality managementIntroduction to quality management
Introduction to quality management
Essam Lotffy, PMP®, CCP®
 
Common contract types
Common contract typesCommon contract types
Common contract types
Essam Lotffy, PMP®, CCP®
 
Pmp selective process data flow
Pmp selective process data flowPmp selective process data flow
Pmp selective process data flow
Essam Lotffy, PMP®, CCP®
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
Essam Lotffy, PMP®, CCP®
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
Essam Lotffy, PMP®, CCP®
 
Sample cosntructability report Template
Sample cosntructability report Template Sample cosntructability report Template
Sample cosntructability report Template
Essam Lotffy, PMP®, CCP®
 
Introduction to cost management &amp; control in construction projects
Introduction to cost management &amp; control in construction projectsIntroduction to cost management &amp; control in construction projects
Introduction to cost management &amp; control in construction projects
Essam Lotffy, PMP®, CCP®
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plans
Essam Lotffy, PMP®, CCP®
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projects
Essam Lotffy, PMP®, CCP®
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
Essam Lotffy, PMP®, CCP®
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
Essam Lotffy, PMP®, CCP®
 
Failure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.finalFailure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.final
Essam Lotffy, PMP®, CCP®
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
Essam Lotffy, PMP®, CCP®
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
Essam Lotffy, PMP®, CCP®
 
Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...
Essam Lotffy, PMP®, CCP®
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
Essam Lotffy, PMP®, CCP®
 
Effect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEffect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo success
Essam Lotffy, PMP®, CCP®
 
A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period
Essam Lotffy, PMP®, CCP®
 

More from Essam Lotffy, PMP®, CCP® (18)

Introduction to quality management
Introduction to quality managementIntroduction to quality management
Introduction to quality management
 
Common contract types
Common contract typesCommon contract types
Common contract types
 
Pmp selective process data flow
Pmp selective process data flowPmp selective process data flow
Pmp selective process data flow
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
 
Sample cosntructability report Template
Sample cosntructability report Template Sample cosntructability report Template
Sample cosntructability report Template
 
Introduction to cost management &amp; control in construction projects
Introduction to cost management &amp; control in construction projectsIntroduction to cost management &amp; control in construction projects
Introduction to cost management &amp; control in construction projects
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plans
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projects
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Failure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.finalFailure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.final
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
 
Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Effect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEffect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo success
 
A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period
 

Recently uploaded

Maximize Your Efficiency with This Comprehensive Project Management Platform ...
Maximize Your Efficiency with This Comprehensive Project Management Platform ...Maximize Your Efficiency with This Comprehensive Project Management Platform ...
Maximize Your Efficiency with This Comprehensive Project Management Platform ...
SOFTTECHHUB
 
From Concept to reality : Implementing Lean Managements DMAIC Methodology for...
From Concept to reality : Implementing Lean Managements DMAIC Methodology for...From Concept to reality : Implementing Lean Managements DMAIC Methodology for...
From Concept to reality : Implementing Lean Managements DMAIC Methodology for...
Rokibul Hasan
 
Small Business Management An Entrepreneur’s Guidebook 8th edition by Byrd tes...
Small Business Management An Entrepreneur’s Guidebook 8th edition by Byrd tes...Small Business Management An Entrepreneur’s Guidebook 8th edition by Byrd tes...
Small Business Management An Entrepreneur’s Guidebook 8th edition by Byrd tes...
ssuserf63bd7
 
一比一原版(philau毕业证书)美国费城大学毕业证如何办理
一比一原版(philau毕业证书)美国费城大学毕业证如何办理一比一原版(philau毕业证书)美国费城大学毕业证如何办理
一比一原版(philau毕业证书)美国费城大学毕业证如何办理
nozaxy
 
Neal Elbaum Shares Top 5 Trends Shaping the Logistics Industry in 2024
Neal Elbaum Shares Top 5 Trends Shaping the Logistics Industry in 2024Neal Elbaum Shares Top 5 Trends Shaping the Logistics Industry in 2024
Neal Elbaum Shares Top 5 Trends Shaping the Logistics Industry in 2024
Neal Elbaum
 
9 Ways Managers Kill Morale (and What to Do Instead)
9 Ways Managers Kill Morale (and What to Do Instead)9 Ways Managers Kill Morale (and What to Do Instead)
9 Ways Managers Kill Morale (and What to Do Instead)
experienceprosarah
 
Customer Relationship Managemenet’s Impact on Customer Satisfaction and Perfo...
Customer Relationship Managemenet’s Impact on Customer Satisfaction and Perfo...Customer Relationship Managemenet’s Impact on Customer Satisfaction and Perfo...
Customer Relationship Managemenet’s Impact on Customer Satisfaction and Perfo...
Istanbul Beykent University (İstanbul Beykent Üniversitesi)
 
m249-saw PMI To familiarize the soldier with the M249 Squad Automatic Weapon ...
m249-saw PMI To familiarize the soldier with the M249 Squad Automatic Weapon ...m249-saw PMI To familiarize the soldier with the M249 Squad Automatic Weapon ...
m249-saw PMI To familiarize the soldier with the M249 Squad Automatic Weapon ...
LinghuaKong2
 
A comprehensive-study-of-biparjoy-cyclone-disaster-management-in-gujarat-a-ca...
A comprehensive-study-of-biparjoy-cyclone-disaster-management-in-gujarat-a-ca...A comprehensive-study-of-biparjoy-cyclone-disaster-management-in-gujarat-a-ca...
A comprehensive-study-of-biparjoy-cyclone-disaster-management-in-gujarat-a-ca...
Samirsinh Parmar
 

Recently uploaded (9)

Maximize Your Efficiency with This Comprehensive Project Management Platform ...
Maximize Your Efficiency with This Comprehensive Project Management Platform ...Maximize Your Efficiency with This Comprehensive Project Management Platform ...
Maximize Your Efficiency with This Comprehensive Project Management Platform ...
 
From Concept to reality : Implementing Lean Managements DMAIC Methodology for...
From Concept to reality : Implementing Lean Managements DMAIC Methodology for...From Concept to reality : Implementing Lean Managements DMAIC Methodology for...
From Concept to reality : Implementing Lean Managements DMAIC Methodology for...
 
Small Business Management An Entrepreneur’s Guidebook 8th edition by Byrd tes...
Small Business Management An Entrepreneur’s Guidebook 8th edition by Byrd tes...Small Business Management An Entrepreneur’s Guidebook 8th edition by Byrd tes...
Small Business Management An Entrepreneur’s Guidebook 8th edition by Byrd tes...
 
一比一原版(philau毕业证书)美国费城大学毕业证如何办理
一比一原版(philau毕业证书)美国费城大学毕业证如何办理一比一原版(philau毕业证书)美国费城大学毕业证如何办理
一比一原版(philau毕业证书)美国费城大学毕业证如何办理
 
Neal Elbaum Shares Top 5 Trends Shaping the Logistics Industry in 2024
Neal Elbaum Shares Top 5 Trends Shaping the Logistics Industry in 2024Neal Elbaum Shares Top 5 Trends Shaping the Logistics Industry in 2024
Neal Elbaum Shares Top 5 Trends Shaping the Logistics Industry in 2024
 
9 Ways Managers Kill Morale (and What to Do Instead)
9 Ways Managers Kill Morale (and What to Do Instead)9 Ways Managers Kill Morale (and What to Do Instead)
9 Ways Managers Kill Morale (and What to Do Instead)
 
Customer Relationship Managemenet’s Impact on Customer Satisfaction and Perfo...
Customer Relationship Managemenet’s Impact on Customer Satisfaction and Perfo...Customer Relationship Managemenet’s Impact on Customer Satisfaction and Perfo...
Customer Relationship Managemenet’s Impact on Customer Satisfaction and Perfo...
 
m249-saw PMI To familiarize the soldier with the M249 Squad Automatic Weapon ...
m249-saw PMI To familiarize the soldier with the M249 Squad Automatic Weapon ...m249-saw PMI To familiarize the soldier with the M249 Squad Automatic Weapon ...
m249-saw PMI To familiarize the soldier with the M249 Squad Automatic Weapon ...
 
A comprehensive-study-of-biparjoy-cyclone-disaster-management-in-gujarat-a-ca...
A comprehensive-study-of-biparjoy-cyclone-disaster-management-in-gujarat-a-ca...A comprehensive-study-of-biparjoy-cyclone-disaster-management-in-gujarat-a-ca...
A comprehensive-study-of-biparjoy-cyclone-disaster-management-in-gujarat-a-ca...
 

Fidic contracts management introduction

  • 1. Contracts Management Principles & Practices According to FIDIC By : Essam Mohamed Lotfi, PMP, CCP
  • 2. • Having a brief of FIDIC • Understand the steps and stages of Contract Management Using FIDIC. • Understand the Role of PM during construction project to protect the organization Business case.
  • 3. • Founded in 1913 • Expanded in 1945 to include 40 national associations • Published first Conditions of Contract in 1957 • In 2004 has 64 member associations • Headquarters in Switzerland • Web Site : www.fidic.org
  • 4. • Conditions of Contract for Construction (Red Book) • Conditions of Contract for Plant & Design Build (Yellow Book) • Conditions of Contract for EPC Turnkey Projects (Silver Book) • Short Form of Contracts (Green Book)
  • 5.
  • 6.
  • 7.
  • 8. 14.3 Contractor submits Statement to the Employer 14.6 Employer gives Contractor notice of amount considered due 14.7 Employer makes the payment to the Contractor <56d <28d Employer verifies the draft final statement, Contractor submits information 14.11 Contractor submits draft final statement to the Employer 14.11 Contractor submits Final Statement and the 14.12 discharge 14.7 employer makes payment <42d Each of the monthly (or otherwise) interim payments The final payment
  • 9. DAB: the persons so named in the contract or other persons appointed under sub-clause (appointment of the dispute adjudication board)
  • 10. • The several documents forming the Contract are to be taken as mutually explanatory of one another, but in case of ambiguities or discrepancies the same shall be explained and adjusted by the Engineer who shall thereupon issue to the Contractor instructions thereon and in such event, unless otherwise provided in the Contract, the priority of the documents forming the Contract shall be as follows: (1) The Contract Agreement (if completed); (2) The Letter of Acceptance; (3) The Tender; (4) Part II of these Conditions; (5) Part I of these Conditions; and (6) Any other document forming part of the Contract.
  • 11. • Cl.1.9 Drawings • Cl.2.1 Site • Cl.4.7 Setting Out • Cl.4.12 Unforeseeable • Cl.4.24 Fossils • Cl.7.4 Testing • Cl.8.4 EoT • Cl.8.4 Adverse Climatic Conditions • Cl.13.7 Legislation • Cl.13.8 Changes in Cost • Cl.14.8 Delayed payments • Cl.19.4 Force Majeure
  • 12. • Cl.13.1 Right to vary – Prior to issue of TO certificate • Cl.13.2 Value Engineering – Development risk with Contractor – Savings 50/50
  • 14.  Majority of construction projects worldwide are administered by the FIDIC forms of contract.  FIDIC recognises delay and related costs and has provisions related thereto. For example;  Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition)  Clauses 44 & 53 (FIDIC 1987 Edition)
  • 15.  Unforeseeable ground conditions  Delayed drawings  Delayed payment  Lack of possession of site  Consequence of risk  Suspension  Force Majeure
  • 16.  Clause 20.1 o Sets out Contractor procedure o Condition Precedent o Not later than 28 days o Sets out Engineer procedure
  • 17.  Contractor gives notice  Within 28 days  Contractor keeps contemporary records o Engineer may monitor o Engineer may instruct further records  Fully detailed claim o Supporting documents  Within 42 days of event
  • 18.  Crucial for determination of claim  Records for any future dispute  Contractor obliged to keep records  Procedure for this work  Employer & Engineer to agree Engineer’s actions
  • 19.  Cl.20.1 continuing procedure  After 42 days: o Claim submission is considered interim o Further monthly claims  Final claim with 28 days of end of effects