SlideShare a Scribd company logo
Failures in Construction Due to Ineffective Project
Management Information Systems
Essam Mohamed Lotffy, PMP, CCP
MEP-Construction Manager, Trojan Holding
P.O. Box 7856, Abu Dhabi
UAE
esam_mese@hotmail.com
Frank R. Parth, MS, MSSM, MBA, PMP
CEO Project Auditors
P.O. Box 80688, Rancho Santa Margarita, CA, USA
fparth@projectauditors.com
Introduction
“Companies risk $135 million for every $1 billion spent on a project, and new research
indicates that $75 million of that $135 million (56 percent) is put at risk by ineffective
communications, indicating a critical need for organizations to address communications
deficiencies at the enterprise level.”
The flow of information in projects can be a significant driver to project success, or to project failure. As
in all projects, there are different layers of communications and each requires its own approach, skills,
and tools. Communicating work directions to the construction crews is simply telling them what to do,
when to do it, and identifying other parallel work that may impact their own. The construction trades are
generally skilled enough they can determine for themselves how to do the job.
Communicating information to the owners or financers requires a completely different approach. Their
interests are in the overall project status, completion forecasts, and risks. Project managers in all fields
and perhaps more so in construction, are neither trained in effective communications nor do they have the
time to identify the detailed information needs of all stakeholders and create custom formats for each on.
So how do they approach communications? They use the default reports built into Primavera, Prism,
Aurora, or whatever the scheduling tool is.
Rather than spend precious time customizing the reports, project managers operate on the philosophy that
if some information is good, more is better. More dials, more color, more data on the screen to the point
where there is so much clutter on the dashboard that it is impossible to tell quickly the status of the
project.
Performing organizations should have, but virtually never do have, a pre-defined format for exactly what
data is presented and how it is shown. This lack of standards allows the project manager to selectively
report the project in the best light, glossing over schedule slippages, cost overruns, and increasing risks. If
the project is high priority or appears to be running into problems the situation is made worse by upper
management asking for more and more reports and more frequent updates without adding the resources
needed to implement the change reporting requirements.
The Project Information Management System (PMIS)
PMI describes the PMIS as follows: The project management information system … provides access to
tools, such as a scheduling tool, a work authorization system, a configuration management system, and
information collection and distribution system, or interfaces to other online automated systems. It consists
of the tools and techniques used to gather, integrate, and disseminate the outputs of project management
processes. It supports all aspects of the project from initiating through closing, and can include both
manual and automated systems.
A core competency for a project manager throughout a construction project is to assure that the proper
information is flowing to the stakeholders in the most effective and efficient manner possible. In the
middle of a construction project this is not a high priority for a typical construction project manager when
day to day work has to be juggled and arranged. He, or she, will simply utilize whatever approaches were
quickly decided on at the beginning of the project. To a person in this position, communicating with the
trades working on site is of much more immediate importance than a schedule update to higher level
management.
Unfortunately the performing organization often pays little more attention to the information being
presented them than the project manager does. Management tends to assume that the project manager is
giving them accurate, unbiased, and thorough information. This assumption continues until they become
aware of a major problem on the project that they feel they should have known about earlier. At this point
their trust in the project manager is lost and they will start demanding additional information, which
forces the project manager to spend more time communicating and less time managing.
A much better approach is to set up an effective project management information system (PMIS) at the
beginning of the project that the project manager can easily utilize and that gives the management in the
performing organization the information they need. If the PMIS is set as a standard then they are
receiving consistent information from all projects and that it provides them the early warning data they
need for effective decision making.
The PMIS, which can be managed centrally by the PMO for all projects or dedicated to a specific
program, should be both thorough and efficient. It should include not only regular status reports but all
documentation related to the project, keep them under configuration management, and make them
accessible to all who are authorized access to them. For a construction project this can include
architectural and engineering drawings as well as shop drawing control logs, procurement control logs,
subcontractors’ prequalification’s control logs, change control logs, RFI logs, etc.
Project management academics, theorists, and bloggers know what should be done. Experienced project
managers also know how to effectively communicate. But when a construction project is started out there
is little time or priority to setting up an effective PMIS. The project manager is willing to adopt whatever
the controlling organization already has in place. But unless there is an effective PMO to develop and
maintain the PMIS, it often does not exist. Management expects the project managers to know how to
communicate, but they are often much too busy to spend time developing the most efficient approach for
their project. There are other priorities.
The end result is that the existing PMIS is often not used effectively and communications on a project
ends up being very poor. Figure 1, shows a proper communications flow and should be the core element
of a successful project information system.
Figure (1)
The communications flow illustrated here demonstrates how the information is first identified and how it
is delivered to the project’s team members without any discrepancies. A single source of the information
should be identified and this will vary depending on the information being communicated. There should
be a single source of approval before information is distributed to avoid duplication or wasted efforts.
This avoids the common problem of different sources of information delivering different messages. The
same message should be delivered whether the information comes from schedule reports, Earned Value
reports, weekly budget reports, or status meetings.
“Ineffective communications is the primary contributor to project failure one third of the
time, and had a negative impact on project success more than half the time.”
Lack of Information Management System and collaboration
As mentioned in the previous part of this technical paper about Information management system and as
illustrated in Figure (1), we have to iterate again that performing organization and project manager
accordingly should ensure that all project stakeholders are using up to date information’s, By giving all
project team members the best quality information when they need it, team members become more
productive and are able to support project success without loss of control. A lack of availability of an
integrated information system with proper communication process will lead to the lack of the information
provided by it which consequently impact the project success and lead to its failure. A glaring example of
lack of information management system is that most of project team members use email to communicate
project updates and data like shop drawing control logs, procurement control logs, subcontractors’
prequalification’s control logs, RFI logs, etc., and the biggest complaint here is that project information
resides in each project team member’s email box, so if new information or updates relevant to any of the
aforementioned control logs exist there will not be any centralized view of the current information.
From the above it is obvious without a well defined communication process and project information
management system to regulate project information and communication this will contribute to project
failure. The following findings will show the effect of lack of projects’ information management system:
High-performing organizations (those completing an average of 80 percent or more of
projects on time, on budget and within goals) create formal communications plans for
nearly twice as many projects as their lower performing counterparts (which complete
fewer than 60 percent of projects on time, on budget, and within goals).”
It is also obvious that performing organizations lose significant amounts of money due to ineffective
communication. A missing or poorly designed information management system will affect the project
success and increase the risk and threats to the performing organization and their strategic plans.
Here a question arises about the relationship between the project’s information management system and
“Construction collaboration” terminology.
Effective construction collaboration between the project’s stakeholders and/or performing organization
team members provides a full sharing of project information and knowledge. Sharing information will
replace the project data held by individual team members with a centralized and robust storage of data
and information related to the project. The data can now be accessed by stakeholders with the appropriate
authorization level. The main feature of effective construction collaboration is the communication and
information management that it facilitates.
Establishing an effective project information management system
As mentioned in earlier sections, a project manager usually spends more effort to introduce a variety of
colored reports to top management to show-off his communications abilities without giving timely and
accurate reports that reflect how the project is progressing, neglecting the fact that all these silly reports
are consuming a lot of effort by the project’s team members which consequently impacts project progress
and ultimately can lead to project failure.
The fact is that any performing organization should have an effective project information management
system that provides a multi-project analysis and reporting capability to enable top management to
compare the project’s actual status to the baseline. An integrated and comprehensive project information
management system improves the project’s information flow and accuracy to eliminate redundant files
and poor data and consequently reduces time and effort being spent to obtain timely and accurate status.
Figure (2) shows a cause-effect diagram illustrating the requirement of having an Integrated Information
management system globally accessible across all stakeholders with regular updates and data.
Figure (2)
This diagram shows that the main challenge for any performing organization is to have a cohesive project
information management system that globally accessible by all project stakeholders with regular updates
to assure the project success. The objective is to have an effective communication process.
A PMIS is often thought of as just a software tool that the organization buys to track schedule. But it is
actually a system of tools and processes to collect data, analyze it, and communicate it. Schedule and cost
tracking tools are part of it, but so are the project manager’s weekly status updates, the IT infrastructure in
the organization, and the communications tools. If the project manager puts on a hard hat and walks the
construction site to collect information on current status, he’s collecting information that will be fed into
the software tools and analyzed to understand where the project is. The earned value management reports
are part of data analysis and reporting.
As in any system, the more effectively the tools and the manual process work together the more effective
the entire system is. A construction project manager that is using the desktop version of MS Project 2007
to manage a set of 5,000 activities will quickly find the tool is completely inadequate for the job. The
tools, processes, and approaches must be appropriate for the project’s size and complexity.
The PMIS is part of the project’s overall control approach. While the project manager should take
advantage of the tools available in the organization he should be most interested in making the PMIS as
effective as possible for the project. The Association for the Advancement of Cost Engineering (AACE)
in Recommended Practice RP60R-10 offers strong advice on how the project controls approach should be
designed and implemented. The right tools, data, and processes are crucial in successfully managing
projects.
Conclusion
The goal of this technical paper was to gain a better understanding of effectiveness of project
management information system (PMIS) in construction, and its contribution in adequate decision making
using proper information flow throughout the project stakeholders, which is a core competency for any
project manager. The study was tending to assure that the most significant approach is the setting up and
effective project management information system (PMIS) to avoid spending more time communicating
rather than managing. Every performing organization should have standards and per-defined format for
project data presentations to prevent project manager’s form implementing best light, glossing selectivity
reports.
About Authors:
Essam Lottfy PMP, CCP is a Construction Manager-MEP at Trojan general contracting in Abu Dhabi,
UAE. He received his BSc. degree in Electrical Engineering (Major) and Power Distribution (Minor)
through Zagazig University, Zagazig, Egypt since 2001. Pursued and achieved his certificates in Project
Management (PMP®) from PMI-USA since 2013, and certificate in Cost Management (CCP®) from
AACE International since june-2014. He does claim 13 years extensive hands on experience in various
aspects of projects and project management within maintenance, power distribution networks monitoring
and supervision and construction projects as well. During his employment tenure with his past employers
Suez Canal Electrical Distribution Company, United Engineering & Trading Company – ENTRACO,
and TROJAN General Contracting, he has successfully managed various projects, in addition enhancing
the process capabilities and organization performance as well. Essam Lotffy is actively pursuing potential
opportunities in the project management field, where a room of growth and opportunities for
advancement exists.
Frank Parth, MS, MSSM, MBA, PMP is the President of Project Auditors LLC, a past member of PMI’s Board of
Directors, and is currently on the core management team for PMI’s PMBOK Guide version 6. Mr. Parth brings 35
years experience in project and program management to his teaching and consulting work.
He had a first career designing satellite systems for the US government and in 1993 he set up a consultancy and
began consulting in program management and systems engineering. He has created PMOs for several Fortune 1000
companies and for companies internationally. He consults to clients in multiple industry sectors, including telecom,
construction, high tech, chemical processing, utilities, government, healthcare, mining, financial services, and
aerospace. He is currently supporting Saudi Arabia’s Saline Water Conversion Corporation in improving their
project management processes and in developing a PMO.
Mr. Parth teaches project management courses throughout the world and has taught over 4000 students worlwide in
preparing for the PMP certification exam. He is a guest lecturer at USC’s Marshall School of Business, the
University of California, Irvine, and at the American University of Sharjah (AUS) in the UAE, is an accomplished
international speaker, and does pro bono teaching of project management in Vietnam.
He has co-authored or contributed to multiple books in project management and has published numerous papers in
project management and systems engineering. He is actively involved with PMI, serving on local and national
committees and was PMI’s Project Manager for the Standard for Program Management, 2nd
edition published in
2008

More Related Content

What's hot

Paul Blumstein Resume vers 6j
Paul Blumstein Resume vers 6jPaul Blumstein Resume vers 6j
Paul Blumstein Resume vers 6j
Paul Blumstein, PMP®, PMI-RMP®, LSSGB
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
Glen Alleman
 
A Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementA Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project Management
Workfront
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project ManagementGoutama Bachtiar
 
Preempting ERP Project Failure
Preempting ERP Project FailurePreempting ERP Project Failure
Preempting ERP Project Failure
Rob Prinzo
 
Software Project Planning II
Software Project Planning IISoftware Project Planning II
Software Project Planning II
Gagan Deep
 
1Doug K. Brown PM 5-16-16 Res
1Doug K. Brown PM 5-16-16 Res1Doug K. Brown PM 5-16-16 Res
1Doug K. Brown PM 5-16-16 ResDoug Brown
 
Project management (A Basic Approach)
Project management (A Basic Approach)Project management (A Basic Approach)
Project management (A Basic Approach)
Jed Concepcion
 
Software Project Planning III
Software Project Planning IIISoftware Project Planning III
Software Project Planning III
Gagan Deep
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
Glen Alleman
 
Five immutable principles
Five immutable principlesFive immutable principles
Five immutable principles
Glen Alleman
 
What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?
Glen Alleman
 
Probabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisProbabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost Analysis
Glen Alleman
 
Callinan resume
Callinan resumeCallinan resume
Callinan resume
Jill Callinan
 
Project management IT Project Management
Project management IT Project Management Project management IT Project Management
Project management IT Project Management
Amanda Haddad
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
Glen Alleman
 
Brownfields agile draft v11
Brownfields agile draft v11Brownfields agile draft v11
Brownfields agile draft v11
tony1234
 
School district gets an a+ in primavera people soft integration by doing thei...
School district gets an a+ in primavera people soft integration by doing thei...School district gets an a+ in primavera people soft integration by doing thei...
School district gets an a+ in primavera people soft integration by doing thei...
p6academy
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
Glen Alleman
 
Lec#1
Lec#1Lec#1
Lec#1
Yasir Khan
 

What's hot (20)

Paul Blumstein Resume vers 6j
Paul Blumstein Resume vers 6jPaul Blumstein Resume vers 6j
Paul Blumstein Resume vers 6j
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
A Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementA Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project Management
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project Management
 
Preempting ERP Project Failure
Preempting ERP Project FailurePreempting ERP Project Failure
Preempting ERP Project Failure
 
Software Project Planning II
Software Project Planning IISoftware Project Planning II
Software Project Planning II
 
1Doug K. Brown PM 5-16-16 Res
1Doug K. Brown PM 5-16-16 Res1Doug K. Brown PM 5-16-16 Res
1Doug K. Brown PM 5-16-16 Res
 
Project management (A Basic Approach)
Project management (A Basic Approach)Project management (A Basic Approach)
Project management (A Basic Approach)
 
Software Project Planning III
Software Project Planning IIISoftware Project Planning III
Software Project Planning III
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
Five immutable principles
Five immutable principlesFive immutable principles
Five immutable principles
 
What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?
 
Probabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisProbabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost Analysis
 
Callinan resume
Callinan resumeCallinan resume
Callinan resume
 
Project management IT Project Management
Project management IT Project Management Project management IT Project Management
Project management IT Project Management
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 
Brownfields agile draft v11
Brownfields agile draft v11Brownfields agile draft v11
Brownfields agile draft v11
 
School district gets an a+ in primavera people soft integration by doing thei...
School district gets an a+ in primavera people soft integration by doing thei...School district gets an a+ in primavera people soft integration by doing thei...
School district gets an a+ in primavera people soft integration by doing thei...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
Lec#1
Lec#1Lec#1
Lec#1
 

Viewers also liked

Project management information system
Project management information systemProject management information system
Project management information system
Pradeep Patel, PMP®
 
project management information system
project management information systemproject management information system
project management information system
Aswin prakash i , Xantus Technologies
 
The project management information system
The project management information systemThe project management information system
The project management information systemDavinder Singh
 
Project Management an Introduction
Project Management an IntroductionProject Management an Introduction
Project Management an Introduction
Muhammad Asim Rashid PMP®, Six Sigma GB, MBA
 
Building a Project Management Information System with SharePoint
Building a Project Management Information System with SharePointBuilding a Project Management Information System with SharePoint
Building a Project Management Information System with SharePoint
ASPE, Inc.
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
Craig Brown
 
College Stationery Management System VB 6.0 and Microsoft Access Project
College Stationery Management System VB 6.0  and Microsoft Access ProjectCollege Stationery Management System VB 6.0  and Microsoft Access Project
College Stationery Management System VB 6.0 and Microsoft Access Project
Tushar Soni
 
Introduction and objectives of the project
Introduction and objectives of the projectIntroduction and objectives of the project
Introduction and objectives of the projectrihan696
 
School management system
School management systemSchool management system
School management systemasd143
 
Chapter 2-Realated literature and Studies
Chapter 2-Realated literature and StudiesChapter 2-Realated literature and Studies
Chapter 2-Realated literature and Studies
Mercy Daracan
 

Viewers also liked (10)

Project management information system
Project management information systemProject management information system
Project management information system
 
project management information system
project management information systemproject management information system
project management information system
 
The project management information system
The project management information systemThe project management information system
The project management information system
 
Project Management an Introduction
Project Management an IntroductionProject Management an Introduction
Project Management an Introduction
 
Building a Project Management Information System with SharePoint
Building a Project Management Information System with SharePointBuilding a Project Management Information System with SharePoint
Building a Project Management Information System with SharePoint
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
College Stationery Management System VB 6.0 and Microsoft Access Project
College Stationery Management System VB 6.0  and Microsoft Access ProjectCollege Stationery Management System VB 6.0  and Microsoft Access Project
College Stationery Management System VB 6.0 and Microsoft Access Project
 
Introduction and objectives of the project
Introduction and objectives of the projectIntroduction and objectives of the project
Introduction and objectives of the project
 
School management system
School management systemSchool management system
School management system
 
Chapter 2-Realated literature and Studies
Chapter 2-Realated literature and StudiesChapter 2-Realated literature and Studies
Chapter 2-Realated literature and Studies
 

Similar to Failures in construction due to ineffective project management information systems

The project management information system
The project management information systemThe project management information system
The project management information systemDavinder Singh
 
COMMUNICATION, COLLABORATION, AND TEAMWORK ARE INCREASINGLY IMPORTANT FOR THE...
COMMUNICATION, COLLABORATION, AND TEAMWORK ARE INCREASINGLY IMPORTANT FOR THE...COMMUNICATION, COLLABORATION, AND TEAMWORK ARE INCREASINGLY IMPORTANT FOR THE...
COMMUNICATION, COLLABORATION, AND TEAMWORK ARE INCREASINGLY IMPORTANT FOR THE...
Hirak Kocharee
 
Improving IT Project Communication
Improving IT Project CommunicationImproving IT Project Communication
Improving IT Project Communication
arshriz
 
Communications Management Plan Templatewww.ProjectManagementDo.docx
Communications Management Plan Templatewww.ProjectManagementDo.docxCommunications Management Plan Templatewww.ProjectManagementDo.docx
Communications Management Plan Templatewww.ProjectManagementDo.docx
clarebernice
 
Implementation of Enterpriseapplicationby Dennis Smith.docx
Implementation of Enterpriseapplicationby Dennis Smith.docxImplementation of Enterpriseapplicationby Dennis Smith.docx
Implementation of Enterpriseapplicationby Dennis Smith.docx
wilcockiris
 
Prajwal Bhattarai - Role and Importance of Project Management Information sys...
Prajwal Bhattarai - Role and Importance of Project Management Information sys...Prajwal Bhattarai - Role and Importance of Project Management Information sys...
Prajwal Bhattarai - Role and Importance of Project Management Information sys...
Prajwal Bhattarai
 
Communications Management PlanProject NameTable of Contents.docx
Communications Management PlanProject NameTable of Contents.docxCommunications Management PlanProject NameTable of Contents.docx
Communications Management PlanProject NameTable of Contents.docx
clarebernice
 
Cooper Untech10 IT Program Mgmt Final
Cooper Untech10 IT Program Mgmt FinalCooper Untech10 IT Program Mgmt Final
Cooper Untech10 IT Program Mgmt Final
Bonnie Cooper
 
Self Hosted Project Management Software for Hassle.pdf
Self Hosted Project Management Software for Hassle.pdfSelf Hosted Project Management Software for Hassle.pdf
Self Hosted Project Management Software for Hassle.pdf
Orangescrum
 
How Project Management Leads to Better Outcomes
How Project Management Leads to Better OutcomesHow Project Management Leads to Better Outcomes
How Project Management Leads to Better Outcomes
Allison Reznick
 
Managing it personnel and projects
Managing it personnel and projectsManaging it personnel and projects
Managing it personnel and projects
Mr. Pramit Kumar Sah
 
Is PPM Enough?
Is PPM Enough?Is PPM Enough?
Is PPM Enough?
Digite Inc
 
Issue Management in Complex IT Integration Programs.pdf
Issue Management in Complex IT Integration Programs.pdfIssue Management in Complex IT Integration Programs.pdf
Issue Management in Complex IT Integration Programs.pdf
Ceyhun Jay Tugcu
 
ERP For Project Focused Organizations
ERP For Project Focused OrganizationsERP For Project Focused Organizations
ERP For Project Focused Organizations
arjencornelisse
 
computer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for morecomputer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for more
kimchibhendalbhai070
 
Communication management
Communication management Communication management
Communication management
ammara2010
 
Final Project Report on Information Systems Project Management
Final Project Report on Information Systems Project ManagementFinal Project Report on Information Systems Project Management
Final Project Report on Information Systems Project Management
Abbas Ahmed
 
Nine keys to successful delegation in Project Management
Nine keys to successful delegation in Project ManagementNine keys to successful delegation in Project Management
Nine keys to successful delegation in Project Management
mrinalsingh385
 
project-management-office-critical-to-successful-project-completion- cuneiform
project-management-office-critical-to-successful-project-completion- cuneiformproject-management-office-critical-to-successful-project-completion- cuneiform
project-management-office-critical-to-successful-project-completion- cuneiform
Cuneiform Consulting Pvt Ltd.
 
Not All Collaboration Solutions are Built the Same
Not All Collaboration Solutions are Built the Same Not All Collaboration Solutions are Built the Same
Not All Collaboration Solutions are Built the Same
Phil Auguste
 

Similar to Failures in construction due to ineffective project management information systems (20)

The project management information system
The project management information systemThe project management information system
The project management information system
 
COMMUNICATION, COLLABORATION, AND TEAMWORK ARE INCREASINGLY IMPORTANT FOR THE...
COMMUNICATION, COLLABORATION, AND TEAMWORK ARE INCREASINGLY IMPORTANT FOR THE...COMMUNICATION, COLLABORATION, AND TEAMWORK ARE INCREASINGLY IMPORTANT FOR THE...
COMMUNICATION, COLLABORATION, AND TEAMWORK ARE INCREASINGLY IMPORTANT FOR THE...
 
Improving IT Project Communication
Improving IT Project CommunicationImproving IT Project Communication
Improving IT Project Communication
 
Communications Management Plan Templatewww.ProjectManagementDo.docx
Communications Management Plan Templatewww.ProjectManagementDo.docxCommunications Management Plan Templatewww.ProjectManagementDo.docx
Communications Management Plan Templatewww.ProjectManagementDo.docx
 
Implementation of Enterpriseapplicationby Dennis Smith.docx
Implementation of Enterpriseapplicationby Dennis Smith.docxImplementation of Enterpriseapplicationby Dennis Smith.docx
Implementation of Enterpriseapplicationby Dennis Smith.docx
 
Prajwal Bhattarai - Role and Importance of Project Management Information sys...
Prajwal Bhattarai - Role and Importance of Project Management Information sys...Prajwal Bhattarai - Role and Importance of Project Management Information sys...
Prajwal Bhattarai - Role and Importance of Project Management Information sys...
 
Communications Management PlanProject NameTable of Contents.docx
Communications Management PlanProject NameTable of Contents.docxCommunications Management PlanProject NameTable of Contents.docx
Communications Management PlanProject NameTable of Contents.docx
 
Cooper Untech10 IT Program Mgmt Final
Cooper Untech10 IT Program Mgmt FinalCooper Untech10 IT Program Mgmt Final
Cooper Untech10 IT Program Mgmt Final
 
Self Hosted Project Management Software for Hassle.pdf
Self Hosted Project Management Software for Hassle.pdfSelf Hosted Project Management Software for Hassle.pdf
Self Hosted Project Management Software for Hassle.pdf
 
How Project Management Leads to Better Outcomes
How Project Management Leads to Better OutcomesHow Project Management Leads to Better Outcomes
How Project Management Leads to Better Outcomes
 
Managing it personnel and projects
Managing it personnel and projectsManaging it personnel and projects
Managing it personnel and projects
 
Is PPM Enough?
Is PPM Enough?Is PPM Enough?
Is PPM Enough?
 
Issue Management in Complex IT Integration Programs.pdf
Issue Management in Complex IT Integration Programs.pdfIssue Management in Complex IT Integration Programs.pdf
Issue Management in Complex IT Integration Programs.pdf
 
ERP For Project Focused Organizations
ERP For Project Focused OrganizationsERP For Project Focused Organizations
ERP For Project Focused Organizations
 
computer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for morecomputer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for more
 
Communication management
Communication management Communication management
Communication management
 
Final Project Report on Information Systems Project Management
Final Project Report on Information Systems Project ManagementFinal Project Report on Information Systems Project Management
Final Project Report on Information Systems Project Management
 
Nine keys to successful delegation in Project Management
Nine keys to successful delegation in Project ManagementNine keys to successful delegation in Project Management
Nine keys to successful delegation in Project Management
 
project-management-office-critical-to-successful-project-completion- cuneiform
project-management-office-critical-to-successful-project-completion- cuneiformproject-management-office-critical-to-successful-project-completion- cuneiform
project-management-office-critical-to-successful-project-completion- cuneiform
 
Not All Collaboration Solutions are Built the Same
Not All Collaboration Solutions are Built the Same Not All Collaboration Solutions are Built the Same
Not All Collaboration Solutions are Built the Same
 

More from Essam Lotffy, PMP®, CCP®

Introduction to quality management
Introduction to quality managementIntroduction to quality management
Introduction to quality management
Essam Lotffy, PMP®, CCP®
 
Common contract types
Common contract typesCommon contract types
Common contract types
Essam Lotffy, PMP®, CCP®
 
Pmp selective process data flow
Pmp selective process data flowPmp selective process data flow
Pmp selective process data flow
Essam Lotffy, PMP®, CCP®
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
Essam Lotffy, PMP®, CCP®
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
Essam Lotffy, PMP®, CCP®
 
Sample cosntructability report Template
Sample cosntructability report Template Sample cosntructability report Template
Sample cosntructability report Template
Essam Lotffy, PMP®, CCP®
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
Essam Lotffy, PMP®, CCP®
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plans
Essam Lotffy, PMP®, CCP®
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projects
Essam Lotffy, PMP®, CCP®
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
Essam Lotffy, PMP®, CCP®
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
Essam Lotffy, PMP®, CCP®
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
Essam Lotffy, PMP®, CCP®
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
Essam Lotffy, PMP®, CCP®
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
Essam Lotffy, PMP®, CCP®
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
Essam Lotffy, PMP®, CCP®
 
Effect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEffect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo success
Essam Lotffy, PMP®, CCP®
 
A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period
Essam Lotffy, PMP®, CCP®
 

More from Essam Lotffy, PMP®, CCP® (17)

Introduction to quality management
Introduction to quality managementIntroduction to quality management
Introduction to quality management
 
Common contract types
Common contract typesCommon contract types
Common contract types
 
Pmp selective process data flow
Pmp selective process data flowPmp selective process data flow
Pmp selective process data flow
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
 
Sample cosntructability report Template
Sample cosntructability report Template Sample cosntructability report Template
Sample cosntructability report Template
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plans
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projects
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Effect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEffect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo success
 
A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period
 

Recently uploaded

TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
Tata Consultancy Services
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
ssuserf63bd7
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
Amir H. Fassihi
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
juniourjohnstone
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
akaash13
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
William (Bill) H. Bender, FCSI
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
CIOWomenMagazine
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 

Recently uploaded (9)

TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 

Failures in construction due to ineffective project management information systems

  • 1. Failures in Construction Due to Ineffective Project Management Information Systems Essam Mohamed Lotffy, PMP, CCP MEP-Construction Manager, Trojan Holding P.O. Box 7856, Abu Dhabi UAE esam_mese@hotmail.com Frank R. Parth, MS, MSSM, MBA, PMP CEO Project Auditors P.O. Box 80688, Rancho Santa Margarita, CA, USA fparth@projectauditors.com Introduction “Companies risk $135 million for every $1 billion spent on a project, and new research indicates that $75 million of that $135 million (56 percent) is put at risk by ineffective communications, indicating a critical need for organizations to address communications deficiencies at the enterprise level.” The flow of information in projects can be a significant driver to project success, or to project failure. As in all projects, there are different layers of communications and each requires its own approach, skills, and tools. Communicating work directions to the construction crews is simply telling them what to do, when to do it, and identifying other parallel work that may impact their own. The construction trades are generally skilled enough they can determine for themselves how to do the job. Communicating information to the owners or financers requires a completely different approach. Their interests are in the overall project status, completion forecasts, and risks. Project managers in all fields and perhaps more so in construction, are neither trained in effective communications nor do they have the time to identify the detailed information needs of all stakeholders and create custom formats for each on. So how do they approach communications? They use the default reports built into Primavera, Prism, Aurora, or whatever the scheduling tool is. Rather than spend precious time customizing the reports, project managers operate on the philosophy that if some information is good, more is better. More dials, more color, more data on the screen to the point where there is so much clutter on the dashboard that it is impossible to tell quickly the status of the project. Performing organizations should have, but virtually never do have, a pre-defined format for exactly what data is presented and how it is shown. This lack of standards allows the project manager to selectively report the project in the best light, glossing over schedule slippages, cost overruns, and increasing risks. If the project is high priority or appears to be running into problems the situation is made worse by upper management asking for more and more reports and more frequent updates without adding the resources needed to implement the change reporting requirements.
  • 2. The Project Information Management System (PMIS) PMI describes the PMIS as follows: The project management information system … provides access to tools, such as a scheduling tool, a work authorization system, a configuration management system, and information collection and distribution system, or interfaces to other online automated systems. It consists of the tools and techniques used to gather, integrate, and disseminate the outputs of project management processes. It supports all aspects of the project from initiating through closing, and can include both manual and automated systems. A core competency for a project manager throughout a construction project is to assure that the proper information is flowing to the stakeholders in the most effective and efficient manner possible. In the middle of a construction project this is not a high priority for a typical construction project manager when day to day work has to be juggled and arranged. He, or she, will simply utilize whatever approaches were quickly decided on at the beginning of the project. To a person in this position, communicating with the trades working on site is of much more immediate importance than a schedule update to higher level management. Unfortunately the performing organization often pays little more attention to the information being presented them than the project manager does. Management tends to assume that the project manager is giving them accurate, unbiased, and thorough information. This assumption continues until they become aware of a major problem on the project that they feel they should have known about earlier. At this point their trust in the project manager is lost and they will start demanding additional information, which forces the project manager to spend more time communicating and less time managing. A much better approach is to set up an effective project management information system (PMIS) at the beginning of the project that the project manager can easily utilize and that gives the management in the performing organization the information they need. If the PMIS is set as a standard then they are receiving consistent information from all projects and that it provides them the early warning data they need for effective decision making. The PMIS, which can be managed centrally by the PMO for all projects or dedicated to a specific program, should be both thorough and efficient. It should include not only regular status reports but all documentation related to the project, keep them under configuration management, and make them accessible to all who are authorized access to them. For a construction project this can include architectural and engineering drawings as well as shop drawing control logs, procurement control logs, subcontractors’ prequalification’s control logs, change control logs, RFI logs, etc. Project management academics, theorists, and bloggers know what should be done. Experienced project managers also know how to effectively communicate. But when a construction project is started out there is little time or priority to setting up an effective PMIS. The project manager is willing to adopt whatever the controlling organization already has in place. But unless there is an effective PMO to develop and maintain the PMIS, it often does not exist. Management expects the project managers to know how to communicate, but they are often much too busy to spend time developing the most efficient approach for their project. There are other priorities. The end result is that the existing PMIS is often not used effectively and communications on a project ends up being very poor. Figure 1, shows a proper communications flow and should be the core element of a successful project information system.
  • 3. Figure (1) The communications flow illustrated here demonstrates how the information is first identified and how it is delivered to the project’s team members without any discrepancies. A single source of the information should be identified and this will vary depending on the information being communicated. There should be a single source of approval before information is distributed to avoid duplication or wasted efforts. This avoids the common problem of different sources of information delivering different messages. The same message should be delivered whether the information comes from schedule reports, Earned Value reports, weekly budget reports, or status meetings. “Ineffective communications is the primary contributor to project failure one third of the time, and had a negative impact on project success more than half the time.”
  • 4. Lack of Information Management System and collaboration As mentioned in the previous part of this technical paper about Information management system and as illustrated in Figure (1), we have to iterate again that performing organization and project manager accordingly should ensure that all project stakeholders are using up to date information’s, By giving all project team members the best quality information when they need it, team members become more productive and are able to support project success without loss of control. A lack of availability of an integrated information system with proper communication process will lead to the lack of the information provided by it which consequently impact the project success and lead to its failure. A glaring example of lack of information management system is that most of project team members use email to communicate project updates and data like shop drawing control logs, procurement control logs, subcontractors’ prequalification’s control logs, RFI logs, etc., and the biggest complaint here is that project information resides in each project team member’s email box, so if new information or updates relevant to any of the aforementioned control logs exist there will not be any centralized view of the current information. From the above it is obvious without a well defined communication process and project information management system to regulate project information and communication this will contribute to project failure. The following findings will show the effect of lack of projects’ information management system: High-performing organizations (those completing an average of 80 percent or more of projects on time, on budget and within goals) create formal communications plans for nearly twice as many projects as their lower performing counterparts (which complete fewer than 60 percent of projects on time, on budget, and within goals).” It is also obvious that performing organizations lose significant amounts of money due to ineffective communication. A missing or poorly designed information management system will affect the project success and increase the risk and threats to the performing organization and their strategic plans. Here a question arises about the relationship between the project’s information management system and “Construction collaboration” terminology. Effective construction collaboration between the project’s stakeholders and/or performing organization team members provides a full sharing of project information and knowledge. Sharing information will replace the project data held by individual team members with a centralized and robust storage of data and information related to the project. The data can now be accessed by stakeholders with the appropriate authorization level. The main feature of effective construction collaboration is the communication and information management that it facilitates. Establishing an effective project information management system As mentioned in earlier sections, a project manager usually spends more effort to introduce a variety of colored reports to top management to show-off his communications abilities without giving timely and accurate reports that reflect how the project is progressing, neglecting the fact that all these silly reports
  • 5. are consuming a lot of effort by the project’s team members which consequently impacts project progress and ultimately can lead to project failure. The fact is that any performing organization should have an effective project information management system that provides a multi-project analysis and reporting capability to enable top management to compare the project’s actual status to the baseline. An integrated and comprehensive project information management system improves the project’s information flow and accuracy to eliminate redundant files and poor data and consequently reduces time and effort being spent to obtain timely and accurate status. Figure (2) shows a cause-effect diagram illustrating the requirement of having an Integrated Information management system globally accessible across all stakeholders with regular updates and data. Figure (2) This diagram shows that the main challenge for any performing organization is to have a cohesive project information management system that globally accessible by all project stakeholders with regular updates to assure the project success. The objective is to have an effective communication process. A PMIS is often thought of as just a software tool that the organization buys to track schedule. But it is actually a system of tools and processes to collect data, analyze it, and communicate it. Schedule and cost
  • 6. tracking tools are part of it, but so are the project manager’s weekly status updates, the IT infrastructure in the organization, and the communications tools. If the project manager puts on a hard hat and walks the construction site to collect information on current status, he’s collecting information that will be fed into the software tools and analyzed to understand where the project is. The earned value management reports are part of data analysis and reporting. As in any system, the more effectively the tools and the manual process work together the more effective the entire system is. A construction project manager that is using the desktop version of MS Project 2007 to manage a set of 5,000 activities will quickly find the tool is completely inadequate for the job. The tools, processes, and approaches must be appropriate for the project’s size and complexity. The PMIS is part of the project’s overall control approach. While the project manager should take advantage of the tools available in the organization he should be most interested in making the PMIS as effective as possible for the project. The Association for the Advancement of Cost Engineering (AACE) in Recommended Practice RP60R-10 offers strong advice on how the project controls approach should be designed and implemented. The right tools, data, and processes are crucial in successfully managing projects. Conclusion The goal of this technical paper was to gain a better understanding of effectiveness of project management information system (PMIS) in construction, and its contribution in adequate decision making using proper information flow throughout the project stakeholders, which is a core competency for any project manager. The study was tending to assure that the most significant approach is the setting up and effective project management information system (PMIS) to avoid spending more time communicating rather than managing. Every performing organization should have standards and per-defined format for project data presentations to prevent project manager’s form implementing best light, glossing selectivity reports.
  • 7. About Authors: Essam Lottfy PMP, CCP is a Construction Manager-MEP at Trojan general contracting in Abu Dhabi, UAE. He received his BSc. degree in Electrical Engineering (Major) and Power Distribution (Minor) through Zagazig University, Zagazig, Egypt since 2001. Pursued and achieved his certificates in Project Management (PMP®) from PMI-USA since 2013, and certificate in Cost Management (CCP®) from AACE International since june-2014. He does claim 13 years extensive hands on experience in various aspects of projects and project management within maintenance, power distribution networks monitoring and supervision and construction projects as well. During his employment tenure with his past employers Suez Canal Electrical Distribution Company, United Engineering & Trading Company – ENTRACO, and TROJAN General Contracting, he has successfully managed various projects, in addition enhancing the process capabilities and organization performance as well. Essam Lotffy is actively pursuing potential opportunities in the project management field, where a room of growth and opportunities for advancement exists.
  • 8. Frank Parth, MS, MSSM, MBA, PMP is the President of Project Auditors LLC, a past member of PMI’s Board of Directors, and is currently on the core management team for PMI’s PMBOK Guide version 6. Mr. Parth brings 35 years experience in project and program management to his teaching and consulting work. He had a first career designing satellite systems for the US government and in 1993 he set up a consultancy and began consulting in program management and systems engineering. He has created PMOs for several Fortune 1000 companies and for companies internationally. He consults to clients in multiple industry sectors, including telecom, construction, high tech, chemical processing, utilities, government, healthcare, mining, financial services, and aerospace. He is currently supporting Saudi Arabia’s Saline Water Conversion Corporation in improving their project management processes and in developing a PMO. Mr. Parth teaches project management courses throughout the world and has taught over 4000 students worlwide in preparing for the PMP certification exam. He is a guest lecturer at USC’s Marshall School of Business, the University of California, Irvine, and at the American University of Sharjah (AUS) in the UAE, is an accomplished international speaker, and does pro bono teaching of project management in Vietnam. He has co-authored or contributed to multiple books in project management and has published numerous papers in project management and systems engineering. He is actively involved with PMI, serving on local and national committees and was PMI’s Project Manager for the Standard for Program Management, 2nd edition published in 2008