SlideShare a Scribd company logo
Prepared By Site Construction TeamPrepared By Site Construction Team
Project data
Location : ------------------------------------------
Plot no. : ------------------------------------------
Plot Area : ------------------------------------------
Usage : -------------------------------------------
Measure Of Use : -------------------------------------------
Total BUA : -------------------------------------------
Retail area : ------------------------------------------
Number Of Parking : ------------------------------------------
Project phases : -------------------------------------------
Purpose:Purpose:
This presentation outlines the Brief Of
procedures to cover the installation of
Electrical, mechanical, plumbing, fire
protection & low current Systems for the
entire project as detailed in MEP scope of
works and the required shop drawingsrequired shop drawings.
Sequence of construction:Sequence of construction:
Major MEP Activities & Criteria Of Super- vision Distribution:Major MEP Activities & Criteria Of Super- vision Distribution:
The project is planned to be treated as Previous Illustration,The project is planned to be treated as Previous Illustration,
with dedicated teams to mentioned above.with dedicated teams to mentioned above.
 
The Expected Critical Activities are:The Expected Critical Activities are:
 
• The Shop drawing firstly will start for the Podium level which follow asThe Shop drawing firstly will start for the Podium level which follow as
C7 to C8 to C9.C7 to C8 to C9.
• Typical floor shop drawing for Tower C7,C8,C9 (as per latestTypical floor shop drawing for Tower C7,C8,C9 (as per latest
architectural received from main contractor).architectural received from main contractor).
• The Above shop drawing will used for Slab opening & ConduitsThe Above shop drawing will used for Slab opening & Conduits
required for Electrical Services in Slab.required for Electrical Services in Slab.
• Authority Approval for all MEP shop drawings.Authority Approval for all MEP shop drawings.
• Embedded Items Installation during Slab Casting.Embedded Items Installation during Slab Casting.
• H/L services above false ceiling.H/L services above false ceiling.
• MEP Work in Plant Room & Roof.MEP Work in Plant Room & Roof.
• Low Current Service.Low Current Service.
Major MEP Activities Sequence:Major MEP Activities Sequence:
• MEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/HorizontalsMEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/Horizontals
(Column/Slab).(Column/Slab).
• MEP 2nd Fix - Stage 1: High Level MEP Works above False CeilingMEP 2nd Fix - Stage 1: High Level MEP Works above False Ceiling
i) Fixing supports, installation of Firefighting, Chilled Water piping,i) Fixing supports, installation of Firefighting, Chilled Water piping,
drainage pipes, water supply(hot & cold), rain water, cable ladders, G.Idrainage pipes, water supply(hot & cold), rain water, cable ladders, G.I
Conduiting, AC ductingConduiting, AC ducting
ii) Pressure tests and insulationsii) Pressure tests and insulations
iii) Installation of FCUs, water heaters.iii) Installation of FCUs, water heaters.
• MEP 2nd Fix - Stage 2: Clearance for False Ceiling PeopleMEP 2nd Fix - Stage 2: Clearance for False Ceiling People
i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures,i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures,
fire stopping and identification works etc.fire stopping and identification works etc.
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Required Shop Drawings illustrated as perRequired Shop Drawings illustrated as per
attached list”attached list”

More Related Content

What's hot

Certificado Udemy - Android
Certificado Udemy - Android Certificado Udemy - Android
Certificado Udemy - Android
Rodolfo G.Luna Freire
 
Lifting Rules Example - DNV.pdf
Lifting Rules Example - DNV.pdfLifting Rules Example - DNV.pdf
Lifting Rules Example - DNV.pdf
limkanghai
 
Building Construction Analysis Report
Building Construction Analysis ReportBuilding Construction Analysis Report
Building Construction Analysis ReportDaniel Yap
 
Elevador - dados técnicos
Elevador - dados técnicosElevador - dados técnicos
Elevador - dados técnicos
Carlos Elson Cunha
 
Buildng construction report
Buildng construction reportBuildng construction report
Buildng construction report
Clara Lee
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project PresentationWayne Holley
 
excel pour mur en beton arme (dimensionnement) - télécharger l'excel : http:/...
excel pour mur en beton arme (dimensionnement) - télécharger l'excel : http:/...excel pour mur en beton arme (dimensionnement) - télécharger l'excel : http:/...
excel pour mur en beton arme (dimensionnement) - télécharger l'excel : http:/...
Hani sami joga
 
Tableau de dosage
Tableau   de   dosageTableau   de   dosage
Tableau de dosage
Abdoul Fatré Kienou
 
Project 01 - Experiencing Construction
Project 01 - Experiencing ConstructionProject 01 - Experiencing Construction
Project 01 - Experiencing Construction
Lek Yuen
 
Ogc1 généralités sur l'ost dans le gc
Ogc1  généralités sur l'ost dans le gcOgc1  généralités sur l'ost dans le gc
Ogc1 généralités sur l'ost dans le gc
IRBarry
 
Bonner House - Set.pdf
Bonner House - Set.pdfBonner House - Set.pdf
Bonner House - Set.pdf
Canberra Institute of technology
 
EMIN SG - Sistemas de Celdas Atlantis
EMIN SG - Sistemas de Celdas AtlantisEMIN SG - Sistemas de Celdas Atlantis
EMIN SG - Sistemas de Celdas Atlantis
EMIN Sistemas Geotecnicos
 
PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methods
Halim Rahman
 
01 Construction Code of Practice - Method of Statement
01 Construction Code of Practice - Method of Statement01 Construction Code of Practice - Method of Statement
01 Construction Code of Practice - Method of StatementSopheap Chek
 
Sachpazis: Raft Foundation Analysis & Design BS8110:part 1-1997_plain slab w...
Sachpazis: Raft Foundation Analysis & Design  BS8110:part 1-1997_plain slab w...Sachpazis: Raft Foundation Analysis & Design  BS8110:part 1-1997_plain slab w...
Sachpazis: Raft Foundation Analysis & Design BS8110:part 1-1997_plain slab w...
Dr.Costas Sachpazis
 
Open House LifeStyle, Setor Marista - Goiânia.
Open House LifeStyle, Setor Marista - Goiânia.Open House LifeStyle, Setor Marista - Goiânia.
Open House LifeStyle, Setor Marista - Goiânia.
Cristiano Campos
 
Ogc6 préparation et aménagement des chantiers 1
Ogc6 préparation et aménagement des chantiers 1Ogc6 préparation et aménagement des chantiers 1
Ogc6 préparation et aménagement des chantiers 1
IRBarry
 
Maîtrise du temps unitaire bâtiment télécharger : http://goo.gl/wfk89F
Maîtrise du temps unitaire bâtiment télécharger : http://goo.gl/wfk89FMaîtrise du temps unitaire bâtiment télécharger : http://goo.gl/wfk89F
Maîtrise du temps unitaire bâtiment télécharger : http://goo.gl/wfk89F
Hani sami joga
 

What's hot (20)

Certificado Udemy - Android
Certificado Udemy - Android Certificado Udemy - Android
Certificado Udemy - Android
 
Lifting Rules Example - DNV.pdf
Lifting Rules Example - DNV.pdfLifting Rules Example - DNV.pdf
Lifting Rules Example - DNV.pdf
 
Building Construction Analysis Report
Building Construction Analysis ReportBuilding Construction Analysis Report
Building Construction Analysis Report
 
Elevador - dados técnicos
Elevador - dados técnicosElevador - dados técnicos
Elevador - dados técnicos
 
Buildng construction report
Buildng construction reportBuildng construction report
Buildng construction report
 
METHOD STATEMENT
METHOD STATEMENTMETHOD STATEMENT
METHOD STATEMENT
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 
excel pour mur en beton arme (dimensionnement) - télécharger l'excel : http:/...
excel pour mur en beton arme (dimensionnement) - télécharger l'excel : http:/...excel pour mur en beton arme (dimensionnement) - télécharger l'excel : http:/...
excel pour mur en beton arme (dimensionnement) - télécharger l'excel : http:/...
 
Tableau de dosage
Tableau   de   dosageTableau   de   dosage
Tableau de dosage
 
Project 01 - Experiencing Construction
Project 01 - Experiencing ConstructionProject 01 - Experiencing Construction
Project 01 - Experiencing Construction
 
Ogc1 généralités sur l'ost dans le gc
Ogc1  généralités sur l'ost dans le gcOgc1  généralités sur l'ost dans le gc
Ogc1 généralités sur l'ost dans le gc
 
Bonner House - Set.pdf
Bonner House - Set.pdfBonner House - Set.pdf
Bonner House - Set.pdf
 
EMIN SG - Sistemas de Celdas Atlantis
EMIN SG - Sistemas de Celdas AtlantisEMIN SG - Sistemas de Celdas Atlantis
EMIN SG - Sistemas de Celdas Atlantis
 
PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methods
 
01 Construction Code of Practice - Method of Statement
01 Construction Code of Practice - Method of Statement01 Construction Code of Practice - Method of Statement
01 Construction Code of Practice - Method of Statement
 
Sachpazis: Raft Foundation Analysis & Design BS8110:part 1-1997_plain slab w...
Sachpazis: Raft Foundation Analysis & Design  BS8110:part 1-1997_plain slab w...Sachpazis: Raft Foundation Analysis & Design  BS8110:part 1-1997_plain slab w...
Sachpazis: Raft Foundation Analysis & Design BS8110:part 1-1997_plain slab w...
 
Open House LifeStyle, Setor Marista - Goiânia.
Open House LifeStyle, Setor Marista - Goiânia.Open House LifeStyle, Setor Marista - Goiânia.
Open House LifeStyle, Setor Marista - Goiânia.
 
Ogc6 préparation et aménagement des chantiers 1
Ogc6 préparation et aménagement des chantiers 1Ogc6 préparation et aménagement des chantiers 1
Ogc6 préparation et aménagement des chantiers 1
 
02 tableaux aciers
02 tableaux aciers02 tableaux aciers
02 tableaux aciers
 
Maîtrise du temps unitaire bâtiment télécharger : http://goo.gl/wfk89F
Maîtrise du temps unitaire bâtiment télécharger : http://goo.gl/wfk89FMaîtrise du temps unitaire bâtiment télécharger : http://goo.gl/wfk89F
Maîtrise du temps unitaire bâtiment télécharger : http://goo.gl/wfk89F
 

Similar to Sample cosntructability report Template

DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSDAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
Islam Nassef
 
Case Study of Phased Array UT for B31.1 Piping
Case Study of Phased Array UT for B31.1 PipingCase Study of Phased Array UT for B31.1 Piping
Case Study of Phased Array UT for B31.1 Piping
William Jensen
 
eng.ahmad fathi C.V
eng.ahmad fathi C.Veng.ahmad fathi C.V
eng.ahmad fathi C.Vahmad fathi
 
Design basis report on-14.11.2016
Design basis report  on-14.11.2016Design basis report  on-14.11.2016
Design basis report on-14.11.2016
bhavesh raysoni
 
Cost estimate presentation (1).pptx
Cost estimate presentation (1).pptxCost estimate presentation (1).pptx
Cost estimate presentation (1).pptx
PradeepKumar504728
 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
IrfanAwan25
 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
IrfanAwan25
 
Analysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case studyAnalysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case study
IRJET Journal
 
Colt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptxColt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptx
IrfanAwan25
 
Calculation note 29 11-2014
Calculation note 29 11-2014Calculation note 29 11-2014
Calculation note 29 11-2014
Khaled Eid
 
I03504063072
I03504063072I03504063072
I03504063072
theijes
 
FORENSIC ANALYSIS OF COLLAPSE OF SURFSIDE CONDMINIMUM, MIAMI
FORENSIC ANALYSIS OF COLLAPSE OF SURFSIDE CONDMINIMUM, MIAMIFORENSIC ANALYSIS OF COLLAPSE OF SURFSIDE CONDMINIMUM, MIAMI
FORENSIC ANALYSIS OF COLLAPSE OF SURFSIDE CONDMINIMUM, MIAMI
IRJET Journal
 
IJ Presentation, Slide 01 to 30.pptx
IJ Presentation, Slide 01 to 30.pptxIJ Presentation, Slide 01 to 30.pptx
IJ Presentation, Slide 01 to 30.pptx
AGNELVVARKEY
 
Stress Analysis in District Cooling Projects
Stress Analysis in District Cooling ProjectsStress Analysis in District Cooling Projects
Stress Analysis in District Cooling Projects
Amer Abdul Aziz
 
Telecommunication infrastructure services
Telecommunication infrastructure servicesTelecommunication infrastructure services
Telecommunication infrastructure services
essafi
 
Engineering & Design - April
Engineering & Design - April Engineering & Design - April
Engineering & Design - April
Piping Technology & Products, Inc.
 
Heat Load Calculation
Heat Load CalculationHeat Load Calculation
Heat Load Calculation
cihuy3
 

Similar to Sample cosntructability report Template (20)

DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSDAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
 
Case Study of Phased Array UT for B31.1 Piping
Case Study of Phased Array UT for B31.1 PipingCase Study of Phased Array UT for B31.1 Piping
Case Study of Phased Array UT for B31.1 Piping
 
CV Piping Designer & Supervisor
CV Piping Designer & SupervisorCV Piping Designer & Supervisor
CV Piping Designer & Supervisor
 
eng.ahmad fathi C.V
eng.ahmad fathi C.Veng.ahmad fathi C.V
eng.ahmad fathi C.V
 
Design basis report on-14.11.2016
Design basis report  on-14.11.2016Design basis report  on-14.11.2016
Design basis report on-14.11.2016
 
Cost estimate presentation (1).pptx
Cost estimate presentation (1).pptxCost estimate presentation (1).pptx
Cost estimate presentation (1).pptx
 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
 
Analysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case studyAnalysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case study
 
MCV
MCVMCV
MCV
 
Colt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptxColt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptx
 
Calculation note 29 11-2014
Calculation note 29 11-2014Calculation note 29 11-2014
Calculation note 29 11-2014
 
I03504063072
I03504063072I03504063072
I03504063072
 
FORENSIC ANALYSIS OF COLLAPSE OF SURFSIDE CONDMINIMUM, MIAMI
FORENSIC ANALYSIS OF COLLAPSE OF SURFSIDE CONDMINIMUM, MIAMIFORENSIC ANALYSIS OF COLLAPSE OF SURFSIDE CONDMINIMUM, MIAMI
FORENSIC ANALYSIS OF COLLAPSE OF SURFSIDE CONDMINIMUM, MIAMI
 
IJ Presentation, Slide 01 to 30.pptx
IJ Presentation, Slide 01 to 30.pptxIJ Presentation, Slide 01 to 30.pptx
IJ Presentation, Slide 01 to 30.pptx
 
Stress Analysis in District Cooling Projects
Stress Analysis in District Cooling ProjectsStress Analysis in District Cooling Projects
Stress Analysis in District Cooling Projects
 
Telecommunication infrastructure services
Telecommunication infrastructure servicesTelecommunication infrastructure services
Telecommunication infrastructure services
 
Engineering & Design - April
Engineering & Design - April Engineering & Design - April
Engineering & Design - April
 
Heat Load Calculation
Heat Load CalculationHeat Load Calculation
Heat Load Calculation
 
Ahmed Fahmy_CV
Ahmed Fahmy_CVAhmed Fahmy_CV
Ahmed Fahmy_CV
 

More from Essam Lotffy, PMP®, CCP®

Introduction to quality management
Introduction to quality managementIntroduction to quality management
Introduction to quality management
Essam Lotffy, PMP®, CCP®
 
Common contract types
Common contract typesCommon contract types
Common contract types
Essam Lotffy, PMP®, CCP®
 
Pmp selective process data flow
Pmp selective process data flowPmp selective process data flow
Pmp selective process data flow
Essam Lotffy, PMP®, CCP®
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
Essam Lotffy, PMP®, CCP®
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
Essam Lotffy, PMP®, CCP®
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
Essam Lotffy, PMP®, CCP®
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plans
Essam Lotffy, PMP®, CCP®
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projects
Essam Lotffy, PMP®, CCP®
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
Essam Lotffy, PMP®, CCP®
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
Essam Lotffy, PMP®, CCP®
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
Essam Lotffy, PMP®, CCP®
 
Failure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.finalFailure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.final
Essam Lotffy, PMP®, CCP®
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
Essam Lotffy, PMP®, CCP®
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
Essam Lotffy, PMP®, CCP®
 
Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...
Essam Lotffy, PMP®, CCP®
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
Essam Lotffy, PMP®, CCP®
 
Effect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEffect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo success
Essam Lotffy, PMP®, CCP®
 
A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period
Essam Lotffy, PMP®, CCP®
 

More from Essam Lotffy, PMP®, CCP® (18)

Introduction to quality management
Introduction to quality managementIntroduction to quality management
Introduction to quality management
 
Common contract types
Common contract typesCommon contract types
Common contract types
 
Pmp selective process data flow
Pmp selective process data flowPmp selective process data flow
Pmp selective process data flow
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plans
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projects
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Failure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.finalFailure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.final
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
 
Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Effect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEffect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo success
 
A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period
 

Recently uploaded

Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
ssuserf63bd7
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
akaash13
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
Amir H. Fassihi
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
William (Bill) H. Bender, FCSI
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
CIOWomenMagazine
 
TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
Tata Consultancy Services
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
juniourjohnstone
 

Recently uploaded (9)

Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
 
TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
 

Sample cosntructability report Template

  • 1. Prepared By Site Construction TeamPrepared By Site Construction Team
  • 2. Project data Location : ------------------------------------------ Plot no. : ------------------------------------------ Plot Area : ------------------------------------------ Usage : ------------------------------------------- Measure Of Use : ------------------------------------------- Total BUA : ------------------------------------------- Retail area : ------------------------------------------ Number Of Parking : ------------------------------------------ Project phases : -------------------------------------------
  • 3. Purpose:Purpose: This presentation outlines the Brief Of procedures to cover the installation of Electrical, mechanical, plumbing, fire protection & low current Systems for the entire project as detailed in MEP scope of works and the required shop drawingsrequired shop drawings.
  • 5. Major MEP Activities & Criteria Of Super- vision Distribution:Major MEP Activities & Criteria Of Super- vision Distribution: The project is planned to be treated as Previous Illustration,The project is planned to be treated as Previous Illustration, with dedicated teams to mentioned above.with dedicated teams to mentioned above.   The Expected Critical Activities are:The Expected Critical Activities are:   • The Shop drawing firstly will start for the Podium level which follow asThe Shop drawing firstly will start for the Podium level which follow as C7 to C8 to C9.C7 to C8 to C9. • Typical floor shop drawing for Tower C7,C8,C9 (as per latestTypical floor shop drawing for Tower C7,C8,C9 (as per latest architectural received from main contractor).architectural received from main contractor). • The Above shop drawing will used for Slab opening & ConduitsThe Above shop drawing will used for Slab opening & Conduits required for Electrical Services in Slab.required for Electrical Services in Slab. • Authority Approval for all MEP shop drawings.Authority Approval for all MEP shop drawings. • Embedded Items Installation during Slab Casting.Embedded Items Installation during Slab Casting. • H/L services above false ceiling.H/L services above false ceiling. • MEP Work in Plant Room & Roof.MEP Work in Plant Room & Roof. • Low Current Service.Low Current Service.
  • 6. Major MEP Activities Sequence:Major MEP Activities Sequence: • MEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/HorizontalsMEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/Horizontals (Column/Slab).(Column/Slab). • MEP 2nd Fix - Stage 1: High Level MEP Works above False CeilingMEP 2nd Fix - Stage 1: High Level MEP Works above False Ceiling i) Fixing supports, installation of Firefighting, Chilled Water piping,i) Fixing supports, installation of Firefighting, Chilled Water piping, drainage pipes, water supply(hot & cold), rain water, cable ladders, G.Idrainage pipes, water supply(hot & cold), rain water, cable ladders, G.I Conduiting, AC ductingConduiting, AC ducting ii) Pressure tests and insulationsii) Pressure tests and insulations iii) Installation of FCUs, water heaters.iii) Installation of FCUs, water heaters. • MEP 2nd Fix - Stage 2: Clearance for False Ceiling PeopleMEP 2nd Fix - Stage 2: Clearance for False Ceiling People i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures,i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures, fire stopping and identification works etc.fire stopping and identification works etc.
  • 7. Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 8. Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 9. Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 10. Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 11. Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 12. Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 13. Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 14. Required Shop Drawings illustrated as perRequired Shop Drawings illustrated as per attached list”attached list”