Prepared By Site Construction TeamPrepared By Site Construction Team
Project data
Location : ------------------------------------------
Plot no. : ------------------------------------------
Plot Area : ------------------------------------------
Usage : -------------------------------------------
Measure Of Use : -------------------------------------------
Total BUA : -------------------------------------------
Retail area : ------------------------------------------
Number Of Parking : ------------------------------------------
Project phases : -------------------------------------------
Purpose:Purpose:
This presentation outlines the Brief Of
procedures to cover the installation of
Electrical, mechanical, plumbing, fire
protection & low current Systems for the
entire project as detailed in MEP scope of
works and the required shop drawingsrequired shop drawings.
Sequence of construction:Sequence of construction:
Major MEP Activities & Criteria Of Super- vision Distribution:Major MEP Activities & Criteria Of Super- vision Distribution:
The project is planned to be treated as Previous Illustration,The project is planned to be treated as Previous Illustration,
with dedicated teams to mentioned above.with dedicated teams to mentioned above.
 
The Expected Critical Activities are:The Expected Critical Activities are:
 
• The Shop drawing firstly will start for the Podium level which follow asThe Shop drawing firstly will start for the Podium level which follow as
C7 to C8 to C9.C7 to C8 to C9.
• Typical floor shop drawing for Tower C7,C8,C9 (as per latestTypical floor shop drawing for Tower C7,C8,C9 (as per latest
architectural received from main contractor).architectural received from main contractor).
• The Above shop drawing will used for Slab opening & ConduitsThe Above shop drawing will used for Slab opening & Conduits
required for Electrical Services in Slab.required for Electrical Services in Slab.
• Authority Approval for all MEP shop drawings.Authority Approval for all MEP shop drawings.
• Embedded Items Installation during Slab Casting.Embedded Items Installation during Slab Casting.
• H/L services above false ceiling.H/L services above false ceiling.
• MEP Work in Plant Room & Roof.MEP Work in Plant Room & Roof.
• Low Current Service.Low Current Service.
Major MEP Activities Sequence:Major MEP Activities Sequence:
• MEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/HorizontalsMEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/Horizontals
(Column/Slab).(Column/Slab).
• MEP 2nd Fix - Stage 1: High Level MEP Works above False CeilingMEP 2nd Fix - Stage 1: High Level MEP Works above False Ceiling
i) Fixing supports, installation of Firefighting, Chilled Water piping,i) Fixing supports, installation of Firefighting, Chilled Water piping,
drainage pipes, water supply(hot & cold), rain water, cable ladders, G.Idrainage pipes, water supply(hot & cold), rain water, cable ladders, G.I
Conduiting, AC ductingConduiting, AC ducting
ii) Pressure tests and insulationsii) Pressure tests and insulations
iii) Installation of FCUs, water heaters.iii) Installation of FCUs, water heaters.
• MEP 2nd Fix - Stage 2: Clearance for False Ceiling PeopleMEP 2nd Fix - Stage 2: Clearance for False Ceiling People
i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures,i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures,
fire stopping and identification works etc.fire stopping and identification works etc.
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Detailed Constructability of MEP Disciplines:Detailed Constructability of MEP Disciplines:
Required Shop Drawings illustrated as perRequired Shop Drawings illustrated as per
attached list”attached list”

Sample cosntructability report Template

  • 1.
    Prepared By SiteConstruction TeamPrepared By Site Construction Team
  • 2.
    Project data Location :------------------------------------------ Plot no. : ------------------------------------------ Plot Area : ------------------------------------------ Usage : ------------------------------------------- Measure Of Use : ------------------------------------------- Total BUA : ------------------------------------------- Retail area : ------------------------------------------ Number Of Parking : ------------------------------------------ Project phases : -------------------------------------------
  • 3.
    Purpose:Purpose: This presentation outlinesthe Brief Of procedures to cover the installation of Electrical, mechanical, plumbing, fire protection & low current Systems for the entire project as detailed in MEP scope of works and the required shop drawingsrequired shop drawings.
  • 4.
  • 5.
    Major MEP Activities& Criteria Of Super- vision Distribution:Major MEP Activities & Criteria Of Super- vision Distribution: The project is planned to be treated as Previous Illustration,The project is planned to be treated as Previous Illustration, with dedicated teams to mentioned above.with dedicated teams to mentioned above.   The Expected Critical Activities are:The Expected Critical Activities are:   • The Shop drawing firstly will start for the Podium level which follow asThe Shop drawing firstly will start for the Podium level which follow as C7 to C8 to C9.C7 to C8 to C9. • Typical floor shop drawing for Tower C7,C8,C9 (as per latestTypical floor shop drawing for Tower C7,C8,C9 (as per latest architectural received from main contractor).architectural received from main contractor). • The Above shop drawing will used for Slab opening & ConduitsThe Above shop drawing will used for Slab opening & Conduits required for Electrical Services in Slab.required for Electrical Services in Slab. • Authority Approval for all MEP shop drawings.Authority Approval for all MEP shop drawings. • Embedded Items Installation during Slab Casting.Embedded Items Installation during Slab Casting. • H/L services above false ceiling.H/L services above false ceiling. • MEP Work in Plant Room & Roof.MEP Work in Plant Room & Roof. • Low Current Service.Low Current Service.
  • 6.
    Major MEP ActivitiesSequence:Major MEP Activities Sequence: • MEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/HorizontalsMEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/Horizontals (Column/Slab).(Column/Slab). • MEP 2nd Fix - Stage 1: High Level MEP Works above False CeilingMEP 2nd Fix - Stage 1: High Level MEP Works above False Ceiling i) Fixing supports, installation of Firefighting, Chilled Water piping,i) Fixing supports, installation of Firefighting, Chilled Water piping, drainage pipes, water supply(hot & cold), rain water, cable ladders, G.Idrainage pipes, water supply(hot & cold), rain water, cable ladders, G.I Conduiting, AC ductingConduiting, AC ducting ii) Pressure tests and insulationsii) Pressure tests and insulations iii) Installation of FCUs, water heaters.iii) Installation of FCUs, water heaters. • MEP 2nd Fix - Stage 2: Clearance for False Ceiling PeopleMEP 2nd Fix - Stage 2: Clearance for False Ceiling People i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures,i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures, fire stopping and identification works etc.fire stopping and identification works etc.
  • 7.
    Detailed Constructability ofMEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 8.
    Detailed Constructability ofMEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 9.
    Detailed Constructability ofMEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 10.
    Detailed Constructability ofMEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 11.
    Detailed Constructability ofMEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 12.
    Detailed Constructability ofMEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 13.
    Detailed Constructability ofMEP Disciplines:Detailed Constructability of MEP Disciplines:
  • 14.
    Required Shop Drawingsillustrated as perRequired Shop Drawings illustrated as per attached list”attached list”