SlideShare a Scribd company logo
1 of 25
SAFETY IN ERECTION OF
STRUCTURAL STEELWORK
AKASH TILOKANI
121420006
College Of Engineering , Pune
Forerunners in technical education
References
• IS 7205: 1974 – Code of Safety for Erection of
Structural Steel Work
• SP 70: 2001 – Handbook on Construction
Safety Practices
College Of Engineering , Pune
Forerunners in technical education
Aspects: Clause 9.1 (SP:70-2001) and
Clause 2.1 (IS:7205-1974)
College Of Engineering , Pune
Forerunners in technical education
Scheme
College Of Engineering , Pune
Forerunners in technical education
General Provisions
• Contained in IS 7205-1974, Clause 5 and its sub
clauses
• Before a man is engaged in some work, he should
be given thorough medical check up.
• The erection gang should have adequate supply of
bolts, washers, rivets, pins, etc., of correct size.
• When fitter, riveters, etc., can work from a
planked floor or a planked area, the work can be
done safely and more expeditiously. When this is
not feasible scaffolding or floats should be used.
College Of Engineering , Pune
Forerunners in technical education
Continued…
• When the men can work safely from the steel structure
itself, this is preferable to hanging platforms or
scaffolds, as it eliminates additional operations, which
in turn, reduces the hazard of an accident.
• The men should be taught to clean their shoes of mud,
grease, oil, snow, ice or other slippery material before
climbing ladder or going on steel or a planked floor, so
that they will not slip or drag slippery material for other
to slip on.
• Men should avoid carrying tools or other material when
using a ladder, they should use a hand rope to raise and
lower such material.
College Of Engineering , Pune
Forerunners in technical education
Continued…
• When a number of trusses or deep girders are
loaded in one car or a truck, all but one being
lifted should be tied back unless they have
been tied or braced to prevent their falling over
and endangering men while unloading.
• If a piece is laterally unstable when picked at
its center, use of a balance beam is advisable ,
unless a pair of bridled slings can be placed far
enough for them to be safe lifting points.
College Of Engineering , Pune
Forerunners in technical education
Erection Equipments
• Contained in respective clauses of SP:70-2001 and IS:7205-1974.
1. Cranes
• No crane should be used unless a competent person has inspected
and tested it and furnished a certificate specifying the maximum
working load.
• Access to and egress from the operator’s stand should be safe from
any position of the crane.
• Cranes should not be used to pull out fixed objects with a slanting
pull, drag objects or move vehicles.
• Before being put into use for the first time, jib cranes with variable
radius should undergo tests of stability and all movements.
• Jib cranes should not be operated in the proximity to the electric
power lines.
College Of Engineering , Pune
Forerunners in technical education
Continued …1
2. Hoists
• Hoists must be enclosed at ground level by substantial enclosures
and gates at least by 2 m high and the enclosures should be extended
to accommodate the engine or motor.
• Gates of the same height of 2 m must be provided at all landing
stages.
• The complete hoist way throughout its height shall preferably be
enclosed with a wire mesh in order to contain the accidentally
dislodged material from the hoist platform.
• There must be only one operating position for the hoist and the
driver must be trained in the job and able to see the platform
throughout the travel.
• Every hoist must be fitted with an automatic device which will
support the platform in the event of any failure of the ropes or gear.
• Every hoist must be checked or inspected once in the week.
College Of Engineering , Pune
Forerunners in technical education
Continued…2
3. Wire ropes
• Wire ropes should be visually inspected daily or
at the start of shifts – Idea of thorough inspection.
• One rope lay: Refers to the axial wire rope length
for one wire rope strand to completely wrap
around the wire rope assembly.
• Wires should be stocked for the machines which
are in continuous service.
• Signs of rope deterioration and guidelines of
replacement are as follows
College Of Engineering , Pune
Forerunners in technical education
Continued…3
Signs of deterioration Causes of Replacement
Reduction of rope diameter
(a) Loss of core support
(b) Corrosion
(c) Worn out wires
For Rope Dia Reduction more than
Up to 80 mm 4 mm
95 mm to 130 mm 8 mm
145 mm to 190 mm 12 mm
Broken outside wires (a) 12 randomly distributed broken wires in
ORL
(b) 4 broken wires in one strand in ORL
Wear of individual wires Wear of 1/3rd of the original diameter of
outside individual wires
Corroded, broken, cracked, bent or
worn at end
Any of these conditions indicate replacement
Severe crushing, cutting and
unstranding
When such faults result in distortion of rope
structure
College Of Engineering , Pune
Forerunners in technical education
Columns
• Contained in SP:70-2001, Clause 9.3 and its sub
clauses.
• Get the first four columns of a bay facing
diagonally opposite to one another grouted soon
after bracing of the steelwork and its aligning and
plumbing the portion of steel structure.
• For levelling, aligning and plumbing of columns,
screed bars or level pads shall be provided.
College Of Engineering , Pune
Forerunners in technical education
Continued…
• Stabilize the erected anchored columns by
fastening temporary wire guys till four column
square is completely braced, levelled and
plumbed.
• Filled in pits must be either manually rammed or
rolled over by a heavy roller and sleepers should
be laid over the area.
• Safety nets shall be provided within two stories or
10 m below the height of the work which is
performed.
College Of Engineering , Pune
Forerunners in technical education
Riveting Operations
• Contained in IS 7205:1974, Clause 5.26 and its Sub
clauses
• Rivets covered with slippery materials should not be used
in fabrication work. Care shall be taken while handling
rivets so that they do not fall, strike or cause injury to
men and material below.
• Rivet heating equipment should be as near as possible to
the place of work. A pail of water should always be ready
for quenching the fire, if it develops.
• Rivets, bolts and the like should be kept in the boxes at
working area to prevent falling down on men or
equipments.
College Of Engineering , Pune
Forerunners in technical education
Slinging Operations
• While using multi legged slings each sling or leg should be
loaded evenly and the slings should be of sufficient length
to avoid a wide angle between legs.
• Only properly tested and marked lifting tackle of adequate
strength should be used.
• Allowances should be made for the weight of tackles.
• Load shall be free from any obstructions before it is lifted.
Hands should be taken away from the sling and the slinging
person should stand clear of the load4
• Crane hook should be centrally placed over the load to
prevent the slipping and swinging of the load when it is
raised.
College Of Engineering , Pune
Forerunners in technical education
Erection of Bridge Girders
• Contained in IS:7205-1974, Clause 6.1 and its sub clauses
• Careful inspection of machinery required for the purpose
and check for its capacity is needed.
• Care to protect the edges of members getting marked or
distorted, in the event of use of chains for lashing.
• Temporary bracings shall be provided to care of temporary
stresses from erection equipments or other loads.
• Provisions for lateral forces and wind loads as per the local
conditions.
College Of Engineering , Pune
Forerunners in technical education
Continued...
• Joints shall normally be made by filling not less than
50% of the holes with service bolts and barrel drifts
in the ratio 4:1. The service bolts are to be fully
tightened up as soon as the joint is assembled.
• In the event of emergency arising, such as the
structure in danger of being carried away by floods
before the riveting can be completed, the joints shall
be made secure by filling 40% of the holes with
cylindrical drifts and an equal number with service
bolts fully tightened up.
College Of Engineering , Pune
Forerunners in technical education
Occupational Safety and Health
Administration Provisions
• Safety for erection of structural steel is contained
in code 1926 and sub part R of OSHA.
• Provisions are related to;
1. Site layout, site specific erection plan and
construction sequence
2. Hoisting and Rigging
3. Structural steel stability requirements
4. Falling object protection
5. Fall Protection
College Of Engineering , Pune
Forerunners in technical education
College Of Engineering , Pune
Forerunners in technical education
College Of Engineering , Pune
Forerunners in technical education
College Of Engineering , Pune
Forerunners in technical education
College Of Engineering , Pune
Forerunners in technical education
College Of Engineering , Pune
Forerunners in technical education
College Of Engineering , Pune
Forerunners in technical education
College Of Engineering , Pune
Forerunners in technical education

More Related Content

What's hot

Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequenceRanjith Kumar
 
Basic Scaffolding Awareness
Basic Scaffolding AwarenessBasic Scaffolding Awareness
Basic Scaffolding Awarenessedale07
 
Construction safety management_Construction Management (2180611) (Semester-8)...
Construction safety management_Construction Management (2180611) (Semester-8)...Construction safety management_Construction Management (2180611) (Semester-8)...
Construction safety management_Construction Management (2180611) (Semester-8)...A Makwana
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction Mereia Kali
 
underwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptxunderwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptxJayachandran68
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolitionManthan Vaghasiya
 
Lifting Sling Safety
Lifting Sling SafetyLifting Sling Safety
Lifting Sling SafetyHvacmach
 
demolition techniques
demolition techniquesdemolition techniques
demolition techniquesbholu sharma
 
Health and Safety in Construction PPT
Health and Safety in Construction  PPTHealth and Safety in Construction  PPT
Health and Safety in Construction PPTLuke D'Arcy
 
SCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingSCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingWilliam York
 
Liftingproedure
LiftingproedureLiftingproedure
LiftingproedureZhai Rull
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training PresentationFAIZ FAREED
 
Construction site safety
Construction site safetyConstruction site safety
Construction site safetyDebajit Roy
 
Construction safety pocket guide osha3252
Construction safety pocket guide osha3252Construction safety pocket guide osha3252
Construction safety pocket guide osha3252zul husni
 

What's hot (20)

Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequence
 
Basic Scaffolding Awareness
Basic Scaffolding AwarenessBasic Scaffolding Awareness
Basic Scaffolding Awareness
 
Construction safety management_Construction Management (2180611) (Semester-8)...
Construction safety management_Construction Management (2180611) (Semester-8)...Construction safety management_Construction Management (2180611) (Semester-8)...
Construction safety management_Construction Management (2180611) (Semester-8)...
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
072 Method Statement
072 Method Statement072 Method Statement
072 Method Statement
 
Scaffolds ppt construction
Scaffolds ppt constructionScaffolds ppt construction
Scaffolds ppt construction
 
underwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptxunderwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptx
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolition
 
Rigging and lifting
Rigging and liftingRigging and lifting
Rigging and lifting
 
Lifting Sling Safety
Lifting Sling SafetyLifting Sling Safety
Lifting Sling Safety
 
demolition techniques
demolition techniquesdemolition techniques
demolition techniques
 
Lifting tools
Lifting toolsLifting tools
Lifting tools
 
Health and Safety in Construction PPT
Health and Safety in Construction  PPTHealth and Safety in Construction  PPT
Health and Safety in Construction PPT
 
SCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingSCAFFOLDING Safety Training
SCAFFOLDING Safety Training
 
Liftingproedure
LiftingproedureLiftingproedure
Liftingproedure
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training Presentation
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
Construction site safety
Construction site safetyConstruction site safety
Construction site safety
 
Wrs rigging practice
Wrs rigging practiceWrs rigging practice
Wrs rigging practice
 
Construction safety pocket guide osha3252
Construction safety pocket guide osha3252Construction safety pocket guide osha3252
Construction safety pocket guide osha3252
 

Viewers also liked

Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel StructureGaurang Kakadiya
 
Subpart R - Steel Erection
Subpart R -  Steel ErectionSubpart R -  Steel Erection
Subpart R - Steel ErectionFFSafety
 
Some common defects in steel structural erection at site
Some common defects in steel structural erection at site Some common defects in steel structural erection at site
Some common defects in steel structural erection at site PRABIR DATTA
 
Equipments for erection and compaction
Equipments for erection and compactionEquipments for erection and compaction
Equipments for erection and compactionPrasanthi Nelloor
 
Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga BridgeAshish Kumar Yadav
 
Job Safety Analysis
Job Safety AnalysisJob Safety Analysis
Job Safety AnalysisPraxiom
 
NEW CROSBY PRODUCTS
NEW CROSBY PRODUCTSNEW CROSBY PRODUCTS
NEW CROSBY PRODUCTSAndre Visser
 
Deterioration Modelling of Structural Members Subjected to Cyclic Loading Usi...
Deterioration Modelling of Structural Members Subjected to Cyclic Loading Usi...Deterioration Modelling of Structural Members Subjected to Cyclic Loading Usi...
Deterioration Modelling of Structural Members Subjected to Cyclic Loading Usi...openseesdays
 
Job safety Analysis
Job safety Analysis Job safety Analysis
Job safety Analysis Deepu Rajan
 
Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872Karthik Madhavan
 
Construction joints
Construction jointsConstruction joints
Construction jointsDaniia Roxio
 
Summer internship in Jaypee Group
Summer internship in Jaypee GroupSummer internship in Jaypee Group
Summer internship in Jaypee GroupAbhimanyu Saraswat
 
Expansion Joint
Expansion JointExpansion Joint
Expansion Jointdibz10
 
Pedoman quality control
Pedoman quality controlPedoman quality control
Pedoman quality controlJoni Iswanto
 

Viewers also liked (20)

Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
 
Subpart R - Steel Erection
Subpart R -  Steel ErectionSubpart R -  Steel Erection
Subpart R - Steel Erection
 
Pages from MPR
Pages from MPRPages from MPR
Pages from MPR
 
Some common defects in steel structural erection at site
Some common defects in steel structural erection at site Some common defects in steel structural erection at site
Some common defects in steel structural erection at site
 
Equipments for erection and compaction
Equipments for erection and compactionEquipments for erection and compaction
Equipments for erection and compaction
 
Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga Bridge
 
Operating practices
Operating practicesOperating practices
Operating practices
 
Job Hazard Analysis
Job Hazard AnalysisJob Hazard Analysis
Job Hazard Analysis
 
Job Safety Analysis
Job Safety AnalysisJob Safety Analysis
Job Safety Analysis
 
Steel truss ppt
Steel truss pptSteel truss ppt
Steel truss ppt
 
NEW CROSBY PRODUCTS
NEW CROSBY PRODUCTSNEW CROSBY PRODUCTS
NEW CROSBY PRODUCTS
 
Deterioration Modelling of Structural Members Subjected to Cyclic Loading Usi...
Deterioration Modelling of Structural Members Subjected to Cyclic Loading Usi...Deterioration Modelling of Structural Members Subjected to Cyclic Loading Usi...
Deterioration Modelling of Structural Members Subjected to Cyclic Loading Usi...
 
Safe_Erections_Web
Safe_Erections_WebSafe_Erections_Web
Safe_Erections_Web
 
Job safety Analysis
Job safety Analysis Job safety Analysis
Job safety Analysis
 
Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872
 
Construction joints
Construction jointsConstruction joints
Construction joints
 
Keselamatankerja
KeselamatankerjaKeselamatankerja
Keselamatankerja
 
Summer internship in Jaypee Group
Summer internship in Jaypee GroupSummer internship in Jaypee Group
Summer internship in Jaypee Group
 
Expansion Joint
Expansion JointExpansion Joint
Expansion Joint
 
Pedoman quality control
Pedoman quality controlPedoman quality control
Pedoman quality control
 

Similar to Safety in Erection of Steel Structures

Hoisting and Rigging Safety
Hoisting and Rigging SafetyHoisting and Rigging Safety
Hoisting and Rigging SafetyNickHawkins19
 
الروافع البرجيه واخطارها والتعامل معها. ومكوناتها
الروافع البرجيه واخطارها والتعامل معها. ومكوناتهاالروافع البرجيه واخطارها والتعامل معها. ومكوناتها
الروافع البرجيه واخطارها والتعامل معها. ومكوناتهاOsamaAbdelbaset2
 
UNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdfUNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdfPinakRay1
 
Mobile crane safety rules
Mobile crane safety rulesMobile crane safety rules
Mobile crane safety rulesytcrane
 
Scaffolding safety procedures and its types
Scaffolding safety procedures and its typesScaffolding safety procedures and its types
Scaffolding safety procedures and its typesabhisheksharma12001
 
Module 3.pptx
Module 3.pptxModule 3.pptx
Module 3.pptxShijo25
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfssuseref23d3
 
Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekRoseGaming1
 
PRESENTATION BY HANS HAMMAN-DROP RAISE
PRESENTATION BY HANS HAMMAN-DROP RAISEPRESENTATION BY HANS HAMMAN-DROP RAISE
PRESENTATION BY HANS HAMMAN-DROP RAISEHANS HAMMAN
 

Similar to Safety in Erection of Steel Structures (20)

safety while prestressed concrete
safety while prestressed concretesafety while prestressed concrete
safety while prestressed concrete
 
UTA_AST-Rigging.pptx
UTA_AST-Rigging.pptxUTA_AST-Rigging.pptx
UTA_AST-Rigging.pptx
 
Hoisting and Rigging Safety
Hoisting and Rigging SafetyHoisting and Rigging Safety
Hoisting and Rigging Safety
 
Safety.pptx
Safety.pptxSafety.pptx
Safety.pptx
 
safe lift EMERSON EDUARDO RODRIGUES
safe lift EMERSON EDUARDO RODRIGUESsafe lift EMERSON EDUARDO RODRIGUES
safe lift EMERSON EDUARDO RODRIGUES
 
Rigger safety .pdf
Rigger safety                        .pdfRigger safety                        .pdf
Rigger safety .pdf
 
Rigging Course .pdf
Rigging Course                       .pdfRigging Course                       .pdf
Rigging Course .pdf
 
الروافع البرجيه واخطارها والتعامل معها. ومكوناتها
الروافع البرجيه واخطارها والتعامل معها. ومكوناتهاالروافع البرجيه واخطارها والتعامل معها. ومكوناتها
الروافع البرجيه واخطارها والتعامل معها. ومكوناتها
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
Scaffold Safety (2).ppt
Scaffold Safety (2).pptScaffold Safety (2).ppt
Scaffold Safety (2).ppt
 
Overhead Crane Operators by
Overhead  Crane Operators byOverhead  Crane Operators by
Overhead Crane Operators by
 
UNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdfUNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdf
 
Mobile crane safety rules
Mobile crane safety rulesMobile crane safety rules
Mobile crane safety rules
 
Scaffolding safety procedures and its types
Scaffolding safety procedures and its typesScaffolding safety procedures and its types
Scaffolding safety procedures and its types
 
Module 3.pptx
Module 3.pptxModule 3.pptx
Module 3.pptx
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
 
Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhek
 
PRESENTATION BY HANS HAMMAN-DROP RAISE
PRESENTATION BY HANS HAMMAN-DROP RAISEPRESENTATION BY HANS HAMMAN-DROP RAISE
PRESENTATION BY HANS HAMMAN-DROP RAISE
 
Crane Rigging Safety by HF & C
Crane Rigging Safety by HF & CCrane Rigging Safety by HF & C
Crane Rigging Safety by HF & C
 
osha3252.pdf
osha3252.pdfosha3252.pdf
osha3252.pdf
 

More from Akash Tilokani

Glass Reinforced Plastic Waste
Glass Reinforced Plastic WasteGlass Reinforced Plastic Waste
Glass Reinforced Plastic WasteAkash Tilokani
 
Reactive Powder Concrete
Reactive Powder ConcreteReactive Powder Concrete
Reactive Powder ConcreteAkash Tilokani
 
Pile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm WallsPile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm WallsAkash Tilokani
 
Workers’ compensation in construction
Workers’ compensation in constructionWorkers’ compensation in construction
Workers’ compensation in constructionAkash Tilokani
 

More from Akash Tilokani (7)

Design of slabs 1
Design of slabs 1Design of slabs 1
Design of slabs 1
 
Glass Reinforced Plastic Waste
Glass Reinforced Plastic WasteGlass Reinforced Plastic Waste
Glass Reinforced Plastic Waste
 
Reactive Powder Concrete
Reactive Powder ConcreteReactive Powder Concrete
Reactive Powder Concrete
 
Pile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm WallsPile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm Walls
 
Compensation (HRM)
Compensation (HRM)Compensation (HRM)
Compensation (HRM)
 
Workers’ compensation in construction
Workers’ compensation in constructionWorkers’ compensation in construction
Workers’ compensation in construction
 
FDI in Infrastructure
FDI in InfrastructureFDI in Infrastructure
FDI in Infrastructure
 

Recently uploaded

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 

Recently uploaded (20)

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 

Safety in Erection of Steel Structures

  • 1. SAFETY IN ERECTION OF STRUCTURAL STEELWORK AKASH TILOKANI 121420006 College Of Engineering , Pune Forerunners in technical education
  • 2. References • IS 7205: 1974 – Code of Safety for Erection of Structural Steel Work • SP 70: 2001 – Handbook on Construction Safety Practices College Of Engineering , Pune Forerunners in technical education
  • 3. Aspects: Clause 9.1 (SP:70-2001) and Clause 2.1 (IS:7205-1974) College Of Engineering , Pune Forerunners in technical education
  • 4. Scheme College Of Engineering , Pune Forerunners in technical education
  • 5. General Provisions • Contained in IS 7205-1974, Clause 5 and its sub clauses • Before a man is engaged in some work, he should be given thorough medical check up. • The erection gang should have adequate supply of bolts, washers, rivets, pins, etc., of correct size. • When fitter, riveters, etc., can work from a planked floor or a planked area, the work can be done safely and more expeditiously. When this is not feasible scaffolding or floats should be used. College Of Engineering , Pune Forerunners in technical education
  • 6. Continued… • When the men can work safely from the steel structure itself, this is preferable to hanging platforms or scaffolds, as it eliminates additional operations, which in turn, reduces the hazard of an accident. • The men should be taught to clean their shoes of mud, grease, oil, snow, ice or other slippery material before climbing ladder or going on steel or a planked floor, so that they will not slip or drag slippery material for other to slip on. • Men should avoid carrying tools or other material when using a ladder, they should use a hand rope to raise and lower such material. College Of Engineering , Pune Forerunners in technical education
  • 7. Continued… • When a number of trusses or deep girders are loaded in one car or a truck, all but one being lifted should be tied back unless they have been tied or braced to prevent their falling over and endangering men while unloading. • If a piece is laterally unstable when picked at its center, use of a balance beam is advisable , unless a pair of bridled slings can be placed far enough for them to be safe lifting points. College Of Engineering , Pune Forerunners in technical education
  • 8. Erection Equipments • Contained in respective clauses of SP:70-2001 and IS:7205-1974. 1. Cranes • No crane should be used unless a competent person has inspected and tested it and furnished a certificate specifying the maximum working load. • Access to and egress from the operator’s stand should be safe from any position of the crane. • Cranes should not be used to pull out fixed objects with a slanting pull, drag objects or move vehicles. • Before being put into use for the first time, jib cranes with variable radius should undergo tests of stability and all movements. • Jib cranes should not be operated in the proximity to the electric power lines. College Of Engineering , Pune Forerunners in technical education
  • 9. Continued …1 2. Hoists • Hoists must be enclosed at ground level by substantial enclosures and gates at least by 2 m high and the enclosures should be extended to accommodate the engine or motor. • Gates of the same height of 2 m must be provided at all landing stages. • The complete hoist way throughout its height shall preferably be enclosed with a wire mesh in order to contain the accidentally dislodged material from the hoist platform. • There must be only one operating position for the hoist and the driver must be trained in the job and able to see the platform throughout the travel. • Every hoist must be fitted with an automatic device which will support the platform in the event of any failure of the ropes or gear. • Every hoist must be checked or inspected once in the week. College Of Engineering , Pune Forerunners in technical education
  • 10. Continued…2 3. Wire ropes • Wire ropes should be visually inspected daily or at the start of shifts – Idea of thorough inspection. • One rope lay: Refers to the axial wire rope length for one wire rope strand to completely wrap around the wire rope assembly. • Wires should be stocked for the machines which are in continuous service. • Signs of rope deterioration and guidelines of replacement are as follows College Of Engineering , Pune Forerunners in technical education
  • 11. Continued…3 Signs of deterioration Causes of Replacement Reduction of rope diameter (a) Loss of core support (b) Corrosion (c) Worn out wires For Rope Dia Reduction more than Up to 80 mm 4 mm 95 mm to 130 mm 8 mm 145 mm to 190 mm 12 mm Broken outside wires (a) 12 randomly distributed broken wires in ORL (b) 4 broken wires in one strand in ORL Wear of individual wires Wear of 1/3rd of the original diameter of outside individual wires Corroded, broken, cracked, bent or worn at end Any of these conditions indicate replacement Severe crushing, cutting and unstranding When such faults result in distortion of rope structure College Of Engineering , Pune Forerunners in technical education
  • 12. Columns • Contained in SP:70-2001, Clause 9.3 and its sub clauses. • Get the first four columns of a bay facing diagonally opposite to one another grouted soon after bracing of the steelwork and its aligning and plumbing the portion of steel structure. • For levelling, aligning and plumbing of columns, screed bars or level pads shall be provided. College Of Engineering , Pune Forerunners in technical education
  • 13. Continued… • Stabilize the erected anchored columns by fastening temporary wire guys till four column square is completely braced, levelled and plumbed. • Filled in pits must be either manually rammed or rolled over by a heavy roller and sleepers should be laid over the area. • Safety nets shall be provided within two stories or 10 m below the height of the work which is performed. College Of Engineering , Pune Forerunners in technical education
  • 14. Riveting Operations • Contained in IS 7205:1974, Clause 5.26 and its Sub clauses • Rivets covered with slippery materials should not be used in fabrication work. Care shall be taken while handling rivets so that they do not fall, strike or cause injury to men and material below. • Rivet heating equipment should be as near as possible to the place of work. A pail of water should always be ready for quenching the fire, if it develops. • Rivets, bolts and the like should be kept in the boxes at working area to prevent falling down on men or equipments. College Of Engineering , Pune Forerunners in technical education
  • 15. Slinging Operations • While using multi legged slings each sling or leg should be loaded evenly and the slings should be of sufficient length to avoid a wide angle between legs. • Only properly tested and marked lifting tackle of adequate strength should be used. • Allowances should be made for the weight of tackles. • Load shall be free from any obstructions before it is lifted. Hands should be taken away from the sling and the slinging person should stand clear of the load4 • Crane hook should be centrally placed over the load to prevent the slipping and swinging of the load when it is raised. College Of Engineering , Pune Forerunners in technical education
  • 16. Erection of Bridge Girders • Contained in IS:7205-1974, Clause 6.1 and its sub clauses • Careful inspection of machinery required for the purpose and check for its capacity is needed. • Care to protect the edges of members getting marked or distorted, in the event of use of chains for lashing. • Temporary bracings shall be provided to care of temporary stresses from erection equipments or other loads. • Provisions for lateral forces and wind loads as per the local conditions. College Of Engineering , Pune Forerunners in technical education
  • 17. Continued... • Joints shall normally be made by filling not less than 50% of the holes with service bolts and barrel drifts in the ratio 4:1. The service bolts are to be fully tightened up as soon as the joint is assembled. • In the event of emergency arising, such as the structure in danger of being carried away by floods before the riveting can be completed, the joints shall be made secure by filling 40% of the holes with cylindrical drifts and an equal number with service bolts fully tightened up. College Of Engineering , Pune Forerunners in technical education
  • 18. Occupational Safety and Health Administration Provisions • Safety for erection of structural steel is contained in code 1926 and sub part R of OSHA. • Provisions are related to; 1. Site layout, site specific erection plan and construction sequence 2. Hoisting and Rigging 3. Structural steel stability requirements 4. Falling object protection 5. Fall Protection College Of Engineering , Pune Forerunners in technical education
  • 19. College Of Engineering , Pune Forerunners in technical education
  • 20. College Of Engineering , Pune Forerunners in technical education
  • 21. College Of Engineering , Pune Forerunners in technical education
  • 22. College Of Engineering , Pune Forerunners in technical education
  • 23. College Of Engineering , Pune Forerunners in technical education
  • 24. College Of Engineering , Pune Forerunners in technical education
  • 25. College Of Engineering , Pune Forerunners in technical education