1. 4 | P a g e
Attachment A – EPC Contract Power Plant Project Kaeng Khoi, Thailand
SCOPEOFPROJECT
TYPE OF CONTRACT Full turnkey Engineering, Procurement & Construction (EPC).
TYPE OF
CONFIGURATION
2 x KA26B – 2 (Multi Shaft) Output : 1,468 MW (2 blocks of ~760MW each)
COUNTRY Thailand, Saraburi Province
CUSTOMER Gulf Power Generation Client:Mitsui & Co
SUB-
CONTRACTORS
Civil Works – Sino-Thai Engineering & Construction PCL (STECON), McConnell Dowell
Mechanical Works – STECON MECHANICAL, Thailand.
Electrical Works – ALSTOM Power Thailand.
• The Power Plant constitutes of 2 Blocks of 2 GT combined cycle.
• The owner is Gulf Power Generation Company Limited.
• The scope is fully EPC and the NTP was awarded on 3rd December 2004.
• The civil works started 25 April 2005.
• PAC Block 1 was 01 March 07 with L/D 250,000 Euro/Day.
• PAC Block 1 includes all the common plant buildings and facilities.
• CONCRETE – 86500 m3 done against Original budget of 59000 m3, 150% on budget
• STEEL REINFORCEMENT – 8520 T against 4530 T , 188% on original budget
• UNDERGROUND [ PIPE WORK ALONE] - executed is 2.4 times the original budget . cost over run is 117,532914
THB against 48,218501 THB budget.
• STEEL STRUCTURE – 5340 T against 3440 T original budget, 155% on original budget
• CLADDING- 33000 m2 against 27000 m2 original budget , 122% on original budget.
My duration of service in this project
5 Months