Brentcliffe-Victoria Park CLC Meeting

July 8, 2021
Eglinton Crosstown LRT
Construction Liaison Meeting
Brentcliffe Road to Victoria Park Avenue
Section One At-Grade:
Brentcliffe Portal to Sunnybrook Park Stop
SECTION ONE AT-GRADE UPDATE
3
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021
Noise Barrier and Soil Nail Wall removal Brentcliffe – SE side August 2021 – September 2021
Brentcliffe Retaining Wall construction
North side of Eglinton Ave, east of
Brentcliffe Rd
Ongoing through Summer 2021
Waterproofing West Don River Bridge Completed June 2021
• Shelter finishing activities
• Handrail installation
• Platform ramps & curbs
• Electrical finishes
Sunnybrook Park Stop
• Largely completed June 2021
•
• Ongoing through Summer 2021
•
Multi-use path construction: backfill and
compaction
Landscaping works
Serena Gundy Park – West of Leslie St.
Ongoing through July 2021
Fall 2021
Concrete and road works Don Mills Rd & Eglinton Ave E Ongoing through 2021
EAST TESTING & COMMISSIONING
4
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
RETAINING WALL CONSTRUCTION
NORTH SIDE OF EGLINTON AVENUE
EAST OF BRENTCLIFFE ROAD
5
• This retaining wall is required to hold the embankment created from
the widened Eglinton Ave.
• Retaining wall construction continues and is expected to be
complete in late Summer 2021
• Monitoring of the slope continues and there have been no recent
issues with the movement. Residents on Thursfield Crescent have full
use of their backyards.
• The City provided revised comments on the restoration design and approved planting trees in soil depths
that are less than the by-law requirements, which means trees will be included in the restoration plan.
• CTS has reviewed and incorporated the City’s comments; the final restoration plan is now with the City. CTS
expects approval shortly.
• CTS will share the restoration plan with Elected Officials and Thursfield residents upon completion.
• CTS expects to begin the restoration works in Fall 2021.
FINAL ROAD RESTORATION
BRENTCLIFFE – KENNEDY
6
• Final Road Restoration works will begin in Summer 2021 and last through Fall 2021
• The approximate timeline for road restoration of the At-Grade is:
o Late July 2021: Sloane – Victoria Park
o July – August 2021: Victoria Park – Birchmount
o September – October 2021: Sloane – Leslie
o October 2021: West of Leslie & east of Birchmount
• More specific details regarding the dates and locations of road restoration works will
be communicated to the public as they become available
NOISE BARRIER WALL AND SOIL NAIL WALL REMOVAL
7
• The noise barrier and soil nail walls, located on
the south side of Eglinton Avenue East, east of
Brentcliffe Rd., were erected in 2014 to facilitate
the construction of the east portal.
• As early as August 2021, CTS will begin
removing the noise barrier wall and exposed
segment of the soil nail wall. This work is
expected to last approximately one (1) month
• More detailed information about this work will
be communicated to the residents before the
work begins.
RAMP CONSTRUCTION, WEST OF LESLIE STREET
MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK
8
• Excavation work is complete
• Final backfilling activities are underway, and are expected to be completed in July 2021
• After backfilling activities are completed, installation of topsoil, sodding, and landscaping works will take place in
Fall 2021as part of the final restoration plan
Mid-July 2020 through July 2021
CONSTRUCTION PROGRESS PHOTOS
9
WATERPROOFING
WEST DON RIVER BRIDGE
BACKFILL
LESLIE TRAIL
Science Centre Station
SCIENCE CENTRE STATION UPDATE
11
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021
Door Installation Main Entrance – retail space Completed June 2021
Finishing Activities:
• Floor tiling, ceiling grid & tile
installation, mechanical and electrical
finishes, handrail installation
Station Box Ongoing through July 2021
Finishing Activities:
• Wall & floor tiling, ceiling grid & tile
installation, electrical finishes, sliding
door finishes, canopy Installation
Bus Terminal Ongoing through July 2021
Finishing Activities:
• Floor tiling, ceiling grid & tile
installation, electrical finishes, sliding
door finishes
Main Entrance Ongoing through July 2021
EAST TESTING & COMMISSIONING
12
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
SCIENCE CENTRE TRAFFIC CONFIGURATION
13
December 6, 2020 for approx. eight months
CONSTRUCTION PROGRESS PHOTOS
14
GLAZING
CONCOURSE LEVEL
STAIR RAILING INSTALLATION
MAIN ENTRANCE
CONSTRUCTION PROGRESS PHOTOS
15
SIDEWALK RESTORATION
SOUTH SIDE OF EGLINTON AT DON MILLS
ROAD WIDENING
DON MILLS INTERSECTION
Section Two At-Grade
Aga Khan Park & Museum Stop to O’Connor Stop
SECTION TWO AT-GRADE UPDATE
17
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021
Waterproofing East Don River Bridge Completed June 2021
• Shelter finishing activities
• Handrail installation
• Platform ramps & curbs
• Electrical finishes
Aga Khan Park & Museum Stop
• Largely completed June 2021
•
• Ongoing through Summer 2021
•
• Shelter finishing activities
• Handrail installation
• Platform ramps & curbs
• Electrical finishes
Sloane Stop
• Largely completed June 2021
•
• Ongoing through Summer 2021
•
• Shelter finishing activities
• Handrail installation
• Platform ramps & curbs
• Electrical finishes
O’Connor Stop
• Largely completed June 2021
•
• Ongoing through Summer 2021
•
EAST TESTING & COMMISSIONING
18
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
CONSTRUCTION PROGRESS PHOTOS
19
WATERPROOFING
EAST DON RIVER BRIDGE
EDGE TILE INSTALLATION
WYNFORD STOP
Brentcliffe-Victoria Park CLC Meeting
1 of 20

Recommended

Brentcliffe-Victoria Park CLC Meeting by
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
5.6K views20 slides
Pharmacy to Kennedy CLC meeting by
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meetingCrosstown TO
5.1K views16 slides
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021 by
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021 Crosstown TO
2.4K views21 slides
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting by
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
3.3K views17 slides
Brentcliffe - Victoria Park Construction Liaison Committee Meeting by
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
6.6K views18 slides
CLC: Leaside and Laird - Sept 13 2021 by
CLC: Leaside and Laird - Sept 13 2021 CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 Crosstown TO
5.4K views14 slides

More Related Content

What's hot

Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022 by
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Crosstown TO
7.9K views15 slides
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ... by
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...Crosstown TO
193 views18 slides
Brentcliffe - Victoria Park Construction Liaison Committee Meeting by
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
4.3K views28 slides
Cedarvale & Forest Hill Construction Update (September 29, 2021) by
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Crosstown TO
4.3K views12 slides
Avenue & Chaplin CLC - Construction Update: November 4, 2020 by
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Crosstown TO
1.8K views15 slides
Fairbank-Oakwood Construction Update - November 2021 by
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Crosstown TO
2.6K views14 slides

What's hot(20)

Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022 by Crosstown TO
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Crosstown TO7.9K views
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ... by Crosstown TO
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Crosstown TO193 views
Brentcliffe - Victoria Park Construction Liaison Committee Meeting by Crosstown TO
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO4.3K views
Cedarvale & Forest Hill Construction Update (September 29, 2021) by Crosstown TO
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Crosstown TO4.3K views
Avenue & Chaplin CLC - Construction Update: November 4, 2020 by Crosstown TO
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Crosstown TO1.8K views
Fairbank-Oakwood Construction Update - November 2021 by Crosstown TO
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
Crosstown TO2.6K views
Avenue & Chaplin CLC - Construction Update: January 5, 2022 by Crosstown TO
Avenue & Chaplin CLC - Construction Update: January 5, 2022Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022
Crosstown TO4.6K views
Pharmacy to Kennedy Construction Liaison Committee Meeting by Crosstown TO
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
Crosstown TO2.2K views
Fairbank-Oakwood Construction Update - September 2021 by Crosstown TO
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
Crosstown TO3.2K views
Leaside laird clc - november 9, 2020 by Crosstown TO
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
Crosstown TO2.3K views
CLC pharmacy to Kennedy (Nov24) by Crosstown TO
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)
Crosstown TO3.6K views
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020) by Crosstown TO
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO1.6K views
Eastern Works Open House by Crosstown TO
Eastern Works Open House Eastern Works Open House
Eastern Works Open House
Crosstown TO17.6K views
Pharmacy to Kennedy - November meeting by Crosstown TO
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
Crosstown TO423 views
Final central east open house oct282020 by Crosstown TO
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
Crosstown TO3.7K views
Chaplin & Avenue Construction Liaison Committee Meeting by Crosstown TO
Chaplin & Avenue Construction Liaison Committee MeetingChaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee Meeting
Crosstown TO2.4K views
CLC Pharmacy to Kennedy January by Crosstown TO
CLC Pharmacy to Kennedy JanuaryCLC Pharmacy to Kennedy January
CLC Pharmacy to Kennedy January
Crosstown TO3.8K views
Brentcliffe to Victoria Park - March 4, 2021 by Crosstown TO
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021
Crosstown TO4.3K views
Eastern Virtual Open House Deck by Crosstown TO
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House Deck
Crosstown TO4K views
Western Works CLC - Construction Update: January 18, 2022 by Crosstown TO
Western Works CLC - Construction Update: January 18, 2022Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022
Crosstown TO7.1K views

Similar to Brentcliffe-Victoria Park CLC Meeting

Pharmacy to Kennedy CLC - November by
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November Crosstown TO
4.6K views18 slides
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 by
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Crosstown TO
3.3K views18 slides
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020) by
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
3.4K views18 slides
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020) by
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
3.2K views18 slides
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf by
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCrosstown TO
458 views16 slides
Brentcliffe to Victoria Park - CLC construction update January 2021 by
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Crosstown TO
1.7K views17 slides

Similar to Brentcliffe-Victoria Park CLC Meeting(20)

Pharmacy to Kennedy CLC - November by Crosstown TO
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
Crosstown TO4.6K views
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 by Crosstown TO
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Crosstown TO3.3K views
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020) by Crosstown TO
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO3.4K views
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020) by Crosstown TO
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO3.2K views
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf by Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
Crosstown TO458 views
Brentcliffe to Victoria Park - CLC construction update January 2021 by Crosstown TO
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021
Crosstown TO1.7K views
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf by Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
Crosstown TO3.8K views
Avenue & Chaplin CLC - Construction Update: September 1, 2021 by Crosstown TO
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Crosstown TO3.6K views
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf by Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
Crosstown TO376 views
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting by Crosstown TO
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Crosstown TO1.9K views
Avenue & Chaplin CLC - Construction Update: November 3, 2021 by Crosstown TO
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Crosstown TO3.5K views
Avenue & Chaplin CLC - Construction Update: July 7, 2021 by Crosstown TO
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Crosstown TO2.5K views
Avenue & Chaplin CLC - Construction Update: May 5, 2021 by Crosstown TO
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Crosstown TO1.8K views
Avenue & Chaplin CLC - Construction Update: September 9, 2020 by Crosstown TO
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Crosstown TO1.8K views
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx by Crosstown TO
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
Crosstown TO5.7K views
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf by Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
Crosstown TO1.9K views
Pharmacy to Kennedy Construction Liaison Meeting - July 2020 by Crosstown TO
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Crosstown TO2.7K views
Avenue & Chaplin CLC - Construction Update: July 8, 2020 by Crosstown TO
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Crosstown TO2.3K views
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx by Crosstown TO
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Crosstown TO19 views
Fairbank-Oakwood Construction Update - July 2021 by Crosstown TO
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021
Crosstown TO2.5K views

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf by
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
36 views22 slides
Western Works CLC - May 16, 2023 by
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
147 views23 slides
Western Works CLC - March, 21 2023 by
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
143 views23 slides
Leaside-Laird CLC - May 8, 2023.pdf by
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
919 views15 slides
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf by
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
1.5K views11 slides
Chaplin-Avenue CLC - May 3 2023 Updated.pptx by
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
985 views14 slides

More from Crosstown TO(20)

Western Works CLC - January 17, 2023.pdf by Crosstown TO
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
Crosstown TO36 views
Western Works CLC - May 16, 2023 by Crosstown TO
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
Crosstown TO147 views
Western Works CLC - March, 21 2023 by Crosstown TO
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
Crosstown TO143 views
Leaside-Laird CLC - May 8, 2023.pdf by Crosstown TO
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
Crosstown TO919 views
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf by Crosstown TO
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Crosstown TO1.5K views
Chaplin-Avenue CLC - May 3 2023 Updated.pptx by Crosstown TO
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Crosstown TO985 views
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx by Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
Crosstown TO1.1K views
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx by Crosstown TO
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Crosstown TO1.5K views
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx by Crosstown TO
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
Crosstown TO1.8K views
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx by Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO2K views
Chaplin-Avenue CLC - March 1, 2023.pptx by Crosstown TO
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
Crosstown TO1.7K views
Leaside-Laird CLC - March 13, 2023.pdf by Crosstown TO
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
Crosstown TO6.1K views
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx by Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO171 views
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf by Crosstown TO
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Crosstown TO3.6K views
Chaplin-Avenue CLC - November 2 2022 compressed.pptx by Crosstown TO
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Crosstown TO1.4K views
Chaplin-Avenue CLC - January 11 2023 (002).pptx by Crosstown TO
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Crosstown TO2.5K views
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx by Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
Crosstown TO3.2K views
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf by Crosstown TO
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Crosstown TO4.8K views
Leaside-Laird CLC - January 9, 2023.pdf by Crosstown TO
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
Crosstown TO3K views
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf by Crosstown TO
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
Crosstown TO192 views

Recently uploaded

Creating a Culture of Security by
Creating a Culture of SecurityCreating a Culture of Security
Creating a Culture of SecurityTechSoup
10 views14 slides
Delroy Corinaldi - Future of Ageing 2023 by
Delroy Corinaldi - Future of Ageing 2023Delroy Corinaldi - Future of Ageing 2023
Delroy Corinaldi - Future of Ageing 2023ILCUK
32 views8 slides
Project Nexus Regional Rail by
Project Nexus Regional RailProject Nexus Regional Rail
Project Nexus Regional RailLee Haber
7 views32 slides
Mapping location and co-location of industries at the neighborhood level - A... by
Mapping location and co-location of industries at the neighborhood level  - A...Mapping location and co-location of industries at the neighborhood level  - A...
Mapping location and co-location of industries at the neighborhood level - A...OECD CFE
7 views19 slides
University of Cambridge: COP28 briefing by
University of Cambridge: COP28 briefingUniversity of Cambridge: COP28 briefing
University of Cambridge: COP28 briefingEnergy for One World
16 views33 slides
David Sinclair - Future of Ageing 2023 by
David Sinclair - Future of Ageing 2023David Sinclair - Future of Ageing 2023
David Sinclair - Future of Ageing 2023ILCUK
40 views12 slides

Recently uploaded(20)

Creating a Culture of Security by TechSoup
Creating a Culture of SecurityCreating a Culture of Security
Creating a Culture of Security
TechSoup 10 views
Delroy Corinaldi - Future of Ageing 2023 by ILCUK
Delroy Corinaldi - Future of Ageing 2023Delroy Corinaldi - Future of Ageing 2023
Delroy Corinaldi - Future of Ageing 2023
ILCUK32 views
Project Nexus Regional Rail by Lee Haber
Project Nexus Regional RailProject Nexus Regional Rail
Project Nexus Regional Rail
Lee Haber7 views
Mapping location and co-location of industries at the neighborhood level - A... by OECD CFE
Mapping location and co-location of industries at the neighborhood level  - A...Mapping location and co-location of industries at the neighborhood level  - A...
Mapping location and co-location of industries at the neighborhood level - A...
OECD CFE7 views
David Sinclair - Future of Ageing 2023 by ILCUK
David Sinclair - Future of Ageing 2023David Sinclair - Future of Ageing 2023
David Sinclair - Future of Ageing 2023
ILCUK40 views
The National Security Framework of Spain by Miguel A. Amutio
The National Security Framework of SpainThe National Security Framework of Spain
The National Security Framework of Spain
Miguel A. Amutio38 views
MMF Newsletter March 2022.pdf by mmpcofficial
MMF Newsletter March 2022.pdfMMF Newsletter March 2022.pdf
MMF Newsletter March 2022.pdf
mmpcofficial22 views
Assets of Community Value: From a Local Council Perspective by Scribe
 Assets of Community Value: From a Local Council Perspective Assets of Community Value: From a Local Council Perspective
Assets of Community Value: From a Local Council Perspective
Scribe 29 views
Professor Stephen Harridge and Tom Addison - Future of Ageing 2023 by ILCUK
Professor Stephen Harridge and Tom Addison - Future of Ageing 2023Professor Stephen Harridge and Tom Addison - Future of Ageing 2023
Professor Stephen Harridge and Tom Addison - Future of Ageing 2023
ILCUK32 views
Andreas Schleicher Global Launch of PISA - Presentation - 5 December 2023 by EduSkills OECD
Andreas Schleicher Global Launch of PISA - Presentation - 5 December 2023Andreas Schleicher Global Launch of PISA - Presentation - 5 December 2023
Andreas Schleicher Global Launch of PISA - Presentation - 5 December 2023
EduSkills OECD90 views
COP28: Example of Formation of Negotiated Texts: Global StockTake by Energy for One World
COP28: Example of  Formation of Negotiated Texts: Global StockTakeCOP28: Example of  Formation of Negotiated Texts: Global StockTake
COP28: Example of Formation of Negotiated Texts: Global StockTake
Arunima Himawan - Future of Ageing 2023 by ILCUK
Arunima Himawan - Future of Ageing 2023Arunima Himawan - Future of Ageing 2023
Arunima Himawan - Future of Ageing 2023
ILCUK6 views

Brentcliffe-Victoria Park CLC Meeting

  • 1. July 8, 2021 Eglinton Crosstown LRT Construction Liaison Meeting Brentcliffe Road to Victoria Park Avenue
  • 2. Section One At-Grade: Brentcliffe Portal to Sunnybrook Park Stop
  • 3. SECTION ONE AT-GRADE UPDATE 3 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021 Noise Barrier and Soil Nail Wall removal Brentcliffe – SE side August 2021 – September 2021 Brentcliffe Retaining Wall construction North side of Eglinton Ave, east of Brentcliffe Rd Ongoing through Summer 2021 Waterproofing West Don River Bridge Completed June 2021 • Shelter finishing activities • Handrail installation • Platform ramps & curbs • Electrical finishes Sunnybrook Park Stop • Largely completed June 2021 • • Ongoing through Summer 2021 • Multi-use path construction: backfill and compaction Landscaping works Serena Gundy Park – West of Leslie St. Ongoing through July 2021 Fall 2021 Concrete and road works Don Mills Rd & Eglinton Ave E Ongoing through 2021
  • 4. EAST TESTING & COMMISSIONING 4 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021 • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 5. RETAINING WALL CONSTRUCTION NORTH SIDE OF EGLINTON AVENUE EAST OF BRENTCLIFFE ROAD 5 • This retaining wall is required to hold the embankment created from the widened Eglinton Ave. • Retaining wall construction continues and is expected to be complete in late Summer 2021 • Monitoring of the slope continues and there have been no recent issues with the movement. Residents on Thursfield Crescent have full use of their backyards. • The City provided revised comments on the restoration design and approved planting trees in soil depths that are less than the by-law requirements, which means trees will be included in the restoration plan. • CTS has reviewed and incorporated the City’s comments; the final restoration plan is now with the City. CTS expects approval shortly. • CTS will share the restoration plan with Elected Officials and Thursfield residents upon completion. • CTS expects to begin the restoration works in Fall 2021.
  • 6. FINAL ROAD RESTORATION BRENTCLIFFE – KENNEDY 6 • Final Road Restoration works will begin in Summer 2021 and last through Fall 2021 • The approximate timeline for road restoration of the At-Grade is: o Late July 2021: Sloane – Victoria Park o July – August 2021: Victoria Park – Birchmount o September – October 2021: Sloane – Leslie o October 2021: West of Leslie & east of Birchmount • More specific details regarding the dates and locations of road restoration works will be communicated to the public as they become available
  • 7. NOISE BARRIER WALL AND SOIL NAIL WALL REMOVAL 7 • The noise barrier and soil nail walls, located on the south side of Eglinton Avenue East, east of Brentcliffe Rd., were erected in 2014 to facilitate the construction of the east portal. • As early as August 2021, CTS will begin removing the noise barrier wall and exposed segment of the soil nail wall. This work is expected to last approximately one (1) month • More detailed information about this work will be communicated to the residents before the work begins.
  • 8. RAMP CONSTRUCTION, WEST OF LESLIE STREET MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK 8 • Excavation work is complete • Final backfilling activities are underway, and are expected to be completed in July 2021 • After backfilling activities are completed, installation of topsoil, sodding, and landscaping works will take place in Fall 2021as part of the final restoration plan Mid-July 2020 through July 2021
  • 9. CONSTRUCTION PROGRESS PHOTOS 9 WATERPROOFING WEST DON RIVER BRIDGE BACKFILL LESLIE TRAIL
  • 11. SCIENCE CENTRE STATION UPDATE 11 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021 Door Installation Main Entrance – retail space Completed June 2021 Finishing Activities: • Floor tiling, ceiling grid & tile installation, mechanical and electrical finishes, handrail installation Station Box Ongoing through July 2021 Finishing Activities: • Wall & floor tiling, ceiling grid & tile installation, electrical finishes, sliding door finishes, canopy Installation Bus Terminal Ongoing through July 2021 Finishing Activities: • Floor tiling, ceiling grid & tile installation, electrical finishes, sliding door finishes Main Entrance Ongoing through July 2021
  • 12. EAST TESTING & COMMISSIONING 12 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021 • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 13. SCIENCE CENTRE TRAFFIC CONFIGURATION 13 December 6, 2020 for approx. eight months
  • 14. CONSTRUCTION PROGRESS PHOTOS 14 GLAZING CONCOURSE LEVEL STAIR RAILING INSTALLATION MAIN ENTRANCE
  • 15. CONSTRUCTION PROGRESS PHOTOS 15 SIDEWALK RESTORATION SOUTH SIDE OF EGLINTON AT DON MILLS ROAD WIDENING DON MILLS INTERSECTION
  • 16. Section Two At-Grade Aga Khan Park & Museum Stop to O’Connor Stop
  • 17. SECTION TWO AT-GRADE UPDATE 17 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021 Waterproofing East Don River Bridge Completed June 2021 • Shelter finishing activities • Handrail installation • Platform ramps & curbs • Electrical finishes Aga Khan Park & Museum Stop • Largely completed June 2021 • • Ongoing through Summer 2021 • • Shelter finishing activities • Handrail installation • Platform ramps & curbs • Electrical finishes Sloane Stop • Largely completed June 2021 • • Ongoing through Summer 2021 • • Shelter finishing activities • Handrail installation • Platform ramps & curbs • Electrical finishes O’Connor Stop • Largely completed June 2021 • • Ongoing through Summer 2021 •
  • 18. EAST TESTING & COMMISSIONING 18 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021 • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 19. CONSTRUCTION PROGRESS PHOTOS 19 WATERPROOFING EAST DON RIVER BRIDGE EDGE TILE INSTALLATION WYNFORD STOP