Brentcliffe-Victoria Park CLC Meeting Slide 1 Brentcliffe-Victoria Park CLC Meeting Slide 2 Brentcliffe-Victoria Park CLC Meeting Slide 3 Brentcliffe-Victoria Park CLC Meeting Slide 4 Brentcliffe-Victoria Park CLC Meeting Slide 5 Brentcliffe-Victoria Park CLC Meeting Slide 6 Brentcliffe-Victoria Park CLC Meeting Slide 7 Brentcliffe-Victoria Park CLC Meeting Slide 8 Brentcliffe-Victoria Park CLC Meeting Slide 9 Brentcliffe-Victoria Park CLC Meeting Slide 10 Brentcliffe-Victoria Park CLC Meeting Slide 11 Brentcliffe-Victoria Park CLC Meeting Slide 12 Brentcliffe-Victoria Park CLC Meeting Slide 13 Brentcliffe-Victoria Park CLC Meeting Slide 14 Brentcliffe-Victoria Park CLC Meeting Slide 15 Brentcliffe-Victoria Park CLC Meeting Slide 16 Brentcliffe-Victoria Park CLC Meeting Slide 17 Brentcliffe-Victoria Park CLC Meeting Slide 18 Brentcliffe-Victoria Park CLC Meeting Slide 19 Brentcliffe-Victoria Park CLC Meeting Slide 20
Upcoming SlideShare
What to Upload to SlideShare
Next
Download to read offline and view in fullscreen.

0 Likes

Share

Download to read offline

Brentcliffe-Victoria Park CLC Meeting

Download to read offline

Construction updates for stations and stops including: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O'Connor.

  • Be the first to like this

Brentcliffe-Victoria Park CLC Meeting

  1. 1. July 8, 2021 Eglinton Crosstown LRT Construction Liaison Meeting Brentcliffe Road to Victoria Park Avenue
  2. 2. Section One At-Grade: Brentcliffe Portal to Sunnybrook Park Stop
  3. 3. SECTION ONE AT-GRADE UPDATE 3 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021 Noise Barrier and Soil Nail Wall removal Brentcliffe – SE side August 2021 – September 2021 Brentcliffe Retaining Wall construction North side of Eglinton Ave, east of Brentcliffe Rd Ongoing through Summer 2021 Waterproofing West Don River Bridge Completed June 2021 • Shelter finishing activities • Handrail installation • Platform ramps & curbs • Electrical finishes Sunnybrook Park Stop • Largely completed June 2021 • • Ongoing through Summer 2021 • Multi-use path construction: backfill and compaction Landscaping works Serena Gundy Park – West of Leslie St. Ongoing through July 2021 Fall 2021 Concrete and road works Don Mills Rd & Eglinton Ave E Ongoing through 2021
  4. 4. EAST TESTING & COMMISSIONING 4 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021 • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  5. 5. RETAINING WALL CONSTRUCTION NORTH SIDE OF EGLINTON AVENUE EAST OF BRENTCLIFFE ROAD 5 • This retaining wall is required to hold the embankment created from the widened Eglinton Ave. • Retaining wall construction continues and is expected to be complete in late Summer 2021 • Monitoring of the slope continues and there have been no recent issues with the movement. Residents on Thursfield Crescent have full use of their backyards. • The City provided revised comments on the restoration design and approved planting trees in soil depths that are less than the by-law requirements, which means trees will be included in the restoration plan. • CTS has reviewed and incorporated the City’s comments; the final restoration plan is now with the City. CTS expects approval shortly. • CTS will share the restoration plan with Elected Officials and Thursfield residents upon completion. • CTS expects to begin the restoration works in Fall 2021.
  6. 6. FINAL ROAD RESTORATION BRENTCLIFFE – KENNEDY 6 • Final Road Restoration works will begin in Summer 2021 and last through Fall 2021 • The approximate timeline for road restoration of the At-Grade is: o Late July 2021: Sloane – Victoria Park o July – August 2021: Victoria Park – Birchmount o September – October 2021: Sloane – Leslie o October 2021: West of Leslie & east of Birchmount • More specific details regarding the dates and locations of road restoration works will be communicated to the public as they become available
  7. 7. NOISE BARRIER WALL AND SOIL NAIL WALL REMOVAL 7 • The noise barrier and soil nail walls, located on the south side of Eglinton Avenue East, east of Brentcliffe Rd., were erected in 2014 to facilitate the construction of the east portal. • As early as August 2021, CTS will begin removing the noise barrier wall and exposed segment of the soil nail wall. This work is expected to last approximately one (1) month • More detailed information about this work will be communicated to the residents before the work begins.
  8. 8. RAMP CONSTRUCTION, WEST OF LESLIE STREET MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK 8 • Excavation work is complete • Final backfilling activities are underway, and are expected to be completed in July 2021 • After backfilling activities are completed, installation of topsoil, sodding, and landscaping works will take place in Fall 2021as part of the final restoration plan Mid-July 2020 through July 2021
  9. 9. CONSTRUCTION PROGRESS PHOTOS 9 WATERPROOFING WEST DON RIVER BRIDGE BACKFILL LESLIE TRAIL
  10. 10. Science Centre Station
  11. 11. SCIENCE CENTRE STATION UPDATE 11 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021 Door Installation Main Entrance – retail space Completed June 2021 Finishing Activities: • Floor tiling, ceiling grid & tile installation, mechanical and electrical finishes, handrail installation Station Box Ongoing through July 2021 Finishing Activities: • Wall & floor tiling, ceiling grid & tile installation, electrical finishes, sliding door finishes, canopy Installation Bus Terminal Ongoing through July 2021 Finishing Activities: • Floor tiling, ceiling grid & tile installation, electrical finishes, sliding door finishes Main Entrance Ongoing through July 2021
  12. 12. EAST TESTING & COMMISSIONING 12 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021 • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  13. 13. SCIENCE CENTRE TRAFFIC CONFIGURATION 13 December 6, 2020 for approx. eight months
  14. 14. CONSTRUCTION PROGRESS PHOTOS 14 GLAZING CONCOURSE LEVEL STAIR RAILING INSTALLATION MAIN ENTRANCE
  15. 15. CONSTRUCTION PROGRESS PHOTOS 15 SIDEWALK RESTORATION SOUTH SIDE OF EGLINTON AT DON MILLS ROAD WIDENING DON MILLS INTERSECTION
  16. 16. Section Two At-Grade Aga Khan Park & Museum Stop to O’Connor Stop
  17. 17. SECTION TWO AT-GRADE UPDATE 17 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021 Waterproofing East Don River Bridge Completed June 2021 • Shelter finishing activities • Handrail installation • Platform ramps & curbs • Electrical finishes Aga Khan Park & Museum Stop • Largely completed June 2021 • • Ongoing through Summer 2021 • • Shelter finishing activities • Handrail installation • Platform ramps & curbs • Electrical finishes Sloane Stop • Largely completed June 2021 • • Ongoing through Summer 2021 • • Shelter finishing activities • Handrail installation • Platform ramps & curbs • Electrical finishes O’Connor Stop • Largely completed June 2021 • • Ongoing through Summer 2021 •
  18. 18. EAST TESTING & COMMISSIONING 18 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021 • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  19. 19. CONSTRUCTION PROGRESS PHOTOS 19 WATERPROOFING EAST DON RIVER BRIDGE EDGE TILE INSTALLATION WYNFORD STOP

Construction updates for stations and stops including: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O'Connor.