1. This document provides guidelines for installing an electric heat tracing system on pipes. It describes components of a complete system and procedures for installing heating cables on pipes, elbows, supports, flanges, valves and pumps.
2. Key steps include laying out the cable according to piping layout, allowing extra cable for connections and splicing. Cable is attached to pipes using tape every 12 inches. Additional cable is required on valves, pumps and other areas with increased heat loss.
3. Instructions are given for testing cables upon receipt and completing installation by securing terminations.