1. Amitabha Chattopadhyay
Construction Manager
Currentprojects
15 MMPTA IOCL Paradip refinery , India Oil Corporation , Paradip, Odisha
Core skills
Excellent knowledge of Large LNG Tanks (11 nos) with respect to
multidiscipline activities related to the project for Rasgas, Qatar Gas
&Petronet (I st& I Ind phase) including expansion.
Strong coordination and supervisory skills, particularly in complex project
and/or technical structures.
Knowledge of all phases of construction operations relating to
engineering, construction and field activities.
Professional summary
Graduate in Civil Engineering having 24 years of experience in the field of construction Management,
Project Management, Engineering & project coordination including but not limited to the pre-commissioning
of large grass root LNG with Re-gasification, LPG, Petrochemicals (Ethylene- Naphtha cracker), Textiles,
Plant Buildings, Automobile and Power plant in India, Qatar and Singapore with client as IOCL, Exxon
Mobil, RAS-Gas, Qatar Gas, ONGC , Petronet LNG & PETRONAS-IOCL LPG in the role of increasing
responsibility.
Achieved appreciation of excellence from ONGC ,Dahej,India
Professional qualifications/registration(s)
OHSAS 18001:2007 & Lead Auditor ISO 9001:2008
Education
Bachelor Degree in Engineering (Civil ) from Institution of Engineers(India)
Memberships/affiliations
Associate Member of Institution of Engineers
Languages
English,Hindi & Bengali
Employmenthistory
Foster Wheeler India Pvt Ltd., Senior Principal Engineer,Civil &Structural, (2009 – Present)
Ishikawajima-Harima Heavy Industries Corporation (I.H.I), Japan. Construction Superintendent,(2001 –
2008)
Toyo Engineering India Ltd., Civil Engineer (2000 – 2001)
Haldia Petrochemical Ltd., Civil Engineer(1997 – 2000)
Gherzi Eastern Ltd ,Civil Engineer (1995 – 1997)
Simplex Concrete Piles India Ltd, Assistant Engineer (1990 – 1995)
Resident Construction Manager role performed successfully till handing over to client for ONGC
Petro addition Limited (OPAL) at Dahej, India.
Having excellent knowledge of large LNG tanks (11 nos) with respect to Civil,structural and
mechanical activities related to the project for Rasgas, Qatar Gas &Petronet (I st& I Ind phase)
including expansion.
Executing of underground tunnelling job within 52 existing underground services including
hydrogen line successfully and safely for Singapore parallel train.
Achieved the appreciation from Exxon Mobil,Singapore parallel train project in 2009
2. Representative projects
Deputy Construction manager, IOCL Paradip Refinery
Petrochemical /Foster Wheeler India Pvt Ltd., Paradip Refinery Project, Paradip ,India
Having a track record as successful completion of overall construction management from construction
phase till system handover.
Petrochemical Facility / Foster Wheeler India Pvt Ltd, ONGC-FETC Project,Dahej,India
Resident Construction manager.
Leading a team of 10 packages as LSTK contracts for Demountable Flare blow down, Demin plant, cooling
towers, ETP, & road bridge over Santa creek, plant buildings, Storm water outfall discharge to the sea ,
secured land fill for the most hazardous substances for disposal and as an Engineering In-charge for piping
contract and OWS,CRWS line.
Responsible to manage INR 1265 cores
Compliance to the HSE requirements through reviewing the reports and administratively
implemented by job safety analysis, toolbox, Management meetings & safety walk around,
near miss reporting and review of accident/ incident reports .
Direct coordination with clients for areas of responsibility,
Strong coordination and supervisory skills, particularly in complex project and/or
technical structures.
Knowledge of all phases of construction operations relating to engineering,
construction and field activities.
Direct involvement in quality assurance, ITP and review of quality deficiency and resolving the
problems.
Assigned the roles and responsibility to the team members for daily basis supervisions and
review their reports and corrective actions advices.
Direct coordination with H.O.related to Engineering, Construction, Contract& change orders to
take final decision to go ahead the site works.
Assigned with authority a role to make suitable correspondences and review of all other
contractual correspondences
Review of schedule and resources to expedite the job assigned.
Final review of job procedures, QAP,ITP,change order,
Decisive action to sort out the site issues.
Attending to monthly/weekly review meeting with client, contractors.
Analysing major scope of work at site as per contract, inter-discipline coordination, interfacing
issues between EPC contractors.
Review of Contractor’s time extension request and recommendation to IOCL.
Appraising of project/construction status to client back to HQ
Monitoring and Supervision of construction activities at site and ensuring construction
activities are being carried out as per approved drawings, documents and work procedures,
system hook up and commissioning.
Participation in technical issues to sort out.
Worked as Engineer-in-charge for conventional packages contract.
Participation in brain storming discussion to find out the way to improve the progress at site.
3. Final bill certification and project close out
.LNG Facility / Ishikawajima-Harima Heavy Industries Corporation (I.H.I), Japan.
Petronet LNG Expansion Project(148000 M3
X 4 nos), Dahej, India
Qatar Gas II LNG Tanks Project (140000 M3
X 5 nos),Qatar
Ras-Gas LNG tanks, (2nos), Qatar
Worked asan in-charge of all civil and structural activities and with respect to the mechanical job
as plate fabrication, erection, bending etc .for tank having inner concrete wall dia 81 m and 40 M
of height as a coordinator.
Supervised the piling works, special post-tension cryogenic concrete wall, heavy concrete
foundation and dome roof.
LPG Facility / Toyo Engineering India Ltd. Indian Oil Petronas (LPG storage,loading and unloading terminal),
Worked with Toyo engineering India ltd for the construction of LPG process plant supervising
LPG tanks, piling work, LPG bullet (mounded) steel structure, pipe racks, equipment
foundations and concerned plant service buildings
Worked with Toyo Engineering corporation ,Japan and Toyo Engineering India ltd. wherein I
was looking after execution of construction supervision for precast driven piles, load tests,
Overall responsible for coordination, liaising and project management at site in accordance with terms and
condition of contract.Responsible to certify the completion of work. Scrutinize the contractor’s records,
approval for execution and HSE plan. To examine the waiver/change over items.To certify the close out
report for infrastructure development project. In addition to that I am direct involved with Site inspection and
construction of civil and structural job for buildings, open sheds roads, drainage ,outfall structure to
river/Sea and huge earthwork for infrastructure development project. Resolve contractor’s raised queries
with technical support group. Responsible for witness the tests also as required.
Responsible to manage INR 941cores
Managing a team of engineer/supervisors, supporting staffs and site office, overall
responsible for quality and HSE.
Appraising of project/construction status to client back to HQ.
Planning, Progress Monitoring/ Supervision of construction activities of Contractors at site
Preparation and submission of progress reports to client.
Review and approval of construction procedures and methodology.
Ensuring all site construction activities being carried out as per agreed schedule and meeting
the governing standards.
Review of contractor’s resources and Schedules.
Progress measurement, scrutinise, surveillance on all project related activities and work
certification of bills for payment.
Carrying out quality and safety audit.
Petrochemical / Foster Wheeler India Pvt Ltd. Singapore Parallel Train
Direct supervision as daily basis including engineering coordination
Construction of pipe tunnel crossing the main city road in Singapore refining project. Related
to civil and steel structure for pipe racks, vessels, stair/ladders. Review and check relevant
documents along with drawings. Directinvolved as field engineering as well as supervision as
a team leader of 4 local site Engineers.
Expediting the tunnelling across the main road wherein 52 underground services including
hydrogen and oxygen line wereexisting and declared as most high risk zone.
4. heavy equipment foundations like tall towers, flare stacks, fractionators, exchangers, cold
box, vessels, compressors foundation, heaters, pipe racks cable trench and plant buildings
and roads. Apart from this I was assigned as a chief of painting and thermal insulation work.
Project type/company
Paradip Refinery Project, India Oil Corporatio,Delhi India
ONGC-FETC Project,Dahej,India ,ONGC India.
Singapore Parallel Train., Exxon Mobil, Singapore
Petronet LNG Expansion Project(148000 M3
X 4 nos), Dahej, India,
Qatar Gas II LNG Tanks Project (140000 M3
X 5 nos),Qatar, QATAR Gas
Ras-Gas LNG tanks (2nos), Qatar, QATAR Gas
Publications and presentations
Nil.