1. NATARAJAN SIVAKUMAR
Tel.: +97474736977 (M) E-mail: nsivakumar14@yahoo.com
Job Objective
Assignments in Inspection, Quality Control & Assurance (Architectural, Civil and Structural Construction) with a
high growth oriented organization in Oil & Gas sector and Infrastructure projects.
Brief Overview
A B.Tech in Civil Engineering with 18 years experience in Construction, Inspection and Testing in the field of
QA/QC in Architectural, civil and structural works for the Industrial, Refinery, Petrochemical, Power station,
Residential and commercial Buildings.
Career Highlights
• Since Oct 2009 to till date with Punj Lloyd, Doha, Qatar
Project Title: QSTec Polysilicon Project-Phase-I.
Owner: Qatar Solar Technologies (QS Tec)
Consultant: Project Management Consultant (CH2M-HILL).
Position held in the project: Civil QA/QC-Engineer
Duration: Feb 2013 to till date
JOB RESPONSIBLE
A QA/QC Civil Engineer in charged for civil works. My responsibility is to Check and review the plans &
specifications for the proper construction & quality implementation at job site, perform inspection to
ensure that all installed materials are within the standard in conformance to applicable drawings &
specs., conduct final inspection prior to proceed concrete pouring and other succeeding work activities
that requires step by step inspection as per inspection and testing procedures (ITP), render monitoring
and surveillance on site to control the quality of work being implemented by the constructors.
Civil work activities for Construction of Admin building, Canteen building, First Aid Medical, Mosque,
CER building, 3 nos Substation building, Reactor building, Convertor building, processing building,
Control room building, Compressor building, Chiller water building, RO plant building, Waste water
treatment plant, 6 Nos ERoom, Main truck gate house, Security building, Driver rest room, Scale room,
6 Nos Tank ring wall foundation, Cooling tower wall construction, , Evaporation bond.
Responsible for the constructions and finishing works of buildings including Stream generation plant
foundation, Air compressor foundation, Diesel storage supply & Foundation, fire water pump house,
Domestic waste storage, Bulk chemical storage, Intermediate pumping station for sanitary sewage,
Maintenance workshop, Tank farm, Chemical dosing foundation, Side stream filter foundation,
Page 1 of 7
2. Emergency vents crubber package, Off gas treatment area, Heavy equipment foundation, Pipe rock
foundation, Drainage Chanel, Strom water manhole with RCC pipe connection, Fire water wall
chamber, ERC & IRC duct bank road crossing, Light pole foundation, Cable trench wall with also
include all painting works of structures for Concrete surface, underground and above the ground level.
Witness for the required test associated to the project specification and constructions, such as Field
density Test (FDT), Leak/Pressure test hot & cold water, Wet and Dry film test for painting works.
Responsible for the acceptance and rejection of scheduled RFIs, attending joint inspection with the
contractors for approval.
Reports non-conforming activities, propose rectification strategy and follow-up on remedial works
• Project Title: New Doha International Airport.
Owner: NDIA
Consultant: Overseas Bechtel Incorporated (OBI)
Position held in the project: Civil QC-Inspector
Duration: Oct 2009 to Jan 2013
JOB RESPONSIBLE
Preparing Method Statement, ITP, Material approvals for the construction of 5 Nos Oil storage
tank, Dyke wall, 230 mm thickness Asphalt Paving works, 40 Kmtr Fuel hydrant pipeline, 230
Nos fuel hydrant pits, 24 Nos valve chamber, Administration building, Fuel deposit office
building, 3 Nos Laboratory building, Fuel loading & Unloading bay, 2 Nos Fuel station with
building, 5 Nos Substation building
Conduct pre-inspection for ongoing/ progress civil works activities in daily basis.
Preparing RFI and Coordinate with the clients for final inspection, acceptance and approval.
Preparing QA/QC documents, work progress and daily inspection report.
Submit daily and Monthly Quality performance monitoring reports base on the project
schedule.
Review and coordinate for Technical Query with Drawings inconsistency to engineering
Department, follow up materials inquiry & approval and other related QA/QC matter.
Attend weekly Departmental meeting with the clients and sub-contractors.
Ensure there are no ambiguity in the agreed standards to be achieved, i.e. workmanship,
benchmarks, material samples etc.
Regular reporting of progress and performance to QA/QC Manager and others as instructed.
Provide an inspection service to ensure that workmanship and materials are as specified by
the Client.
Resolve quality issues in a pragmatic manner at the earliest opportunity, to the maximum
benefit of the business.
Witness testing of concrete cubes/materials with test laboratory
Ensures that all test results are verified to meet contract requirements
Monitor’s material storage area and takes necessary measures to prevent damage
Page 2 of 7
3. Reports non-conforming activities, propose rectification strategy and follow-up on remedial
works
• Jun 2009 t0 Sept 2009 Integral Service Co W.L.L, Kuwait
Project Title: Replacement/Installation of IRT Pipeline.
Owner: KNPC
Position held in the project: Civil QC-Inspector
Duration: Jun 2009 to Sept 2009
JOB RESPONSIBLE
Responsible for daily activities related to QC civil Road open crossing, Pipe installation,
Providing protection slab, Back filling & Compaction, Casting pipe support at site, Pipe rack
foundation, Water proofing work.
Monitoring and inspecting of all the civil works. Execution of construction activities as
specified, co-ordination of inspection and testing activities on the site.
Implementation and construction of works, Closing NCR and Surveillance with Client
Inspection and checking for concrete Slump test, earth works, finishing works of foundation
and asphalt works.
Check the works in their area of responsibility for compliance with the specifications.
Respond to request for inspection / approval in a timely manner.
• Feb2008 to Feb 2009 date with DAELIM, Kuwait
Project Title: Replacement of 9 Crude oil filling Pipeline.
Owner: KOC
PMC: Flour International
Position held in the project: Civil QC-Inspector
Duration: Feb 2008 to Feb 2009
JOB RESPONSIBLE
Responsible for the Quality control and Civil inspection in all aspect for the Implementation
and construction Substation, Control room building, Valve pits, Drain pits, sump pits, Car park
shelter, Asphalt Road works, Construction of Gatch road, Pipe support, Valve support,
Platform support, Linear soak way chanel, Fencing work, Pipeline trenching, Cable line, Back
filling and compaction, Road crossing E&I duct bank, RCC barrier panel and Grouting works.
Coordinates all site inspections with construction supervisors and vendors.
Conducts and documents punch list and exception lists. Monitors and controls status of punch
listed items.
Also include to my task to review all QC related documents such as Project Specifications,
Material Submittals, Technical Data Sheets, Inspection and Test Plans, Method Statements,
etc.
Page 3 of 7
4. Ensure the subcontractors are in compliance with their own quality systems.
Ensure all method of statements and inspection test plans are being progressed as planned.
Prepare non conformance / compliance reports and follow-up for close out.
Maintain quality control records and inspection records.
Reports non-conforming activities, propose rectification strategy and follow-up on remedial
works.
Ensures that quality records, acceptance certificates, completion certificates for specific
systems and building/ areas are prepared and collated in accordance with the project and
contract requirements.
Performs other job-related duties as assigned by QA/QC Manager
• Nov 2007 to Jan 2008 with Al Ganim Sepam, Kuwait
Project Title: Demolishing and Reconstruction of Building .
Owner: Good Food
Position held in the project: Civil Supervisor
Duration: Nov 2007 to Jan 2008
JOB RESPONSIBLE
Responsible for removed equipment, Machinery and unwanted material as per the project layout plan.
As per the construction drawing followed Lift wall construction, concrete block work, Dry wall partition,
Plastering, Wooden, Aluminum, Rolling shutter Doors and window installation, Internal Architectural
painting works, Carpet tile, Ceramic floor & wall tiles and Granite stone installation, Access ramp
construction, External cladding works, Stainless steel hand rail installation works.
Material intended with project procurement team, Monitoring and supervising the project.
Material, Equipment, Tools and manpower control the project site.
Day to day work meet the project schedule and reporting to the Planning department and Project
manager.
• Nov 2005 to Oct 2007 with HEISCO, Kuwait
Project Title: Heaters and Boilers Safety Up Gradation & Emission control.
Owner: KNPC
Position held in the project: Civil Supervisor
Duration: Nov 2005 to Apr 2006
Responsible for the Joint inspection with Sub contractor’s inspector for the materials and
construction and offering approvals with Client for the construction of Blast proof building,
Cable room (Basement floor), Local equipment room, HVAC room, Battery room and UPS
room for Supervision of RCC structural concrete, Concrete block masonry, Plastering,
Painting, False ceiling, False flooring, Paving Concrete, Battery room Acid proof tiles laying,
Mosaic flooring laying, Marble laying, Grouting work and Hand rail fixing etc.
Page 4 of 7
5. Project Title: Modification of Tank vapor system and crude filling piping work in SEK GC’s
Owner: Kuwait Oil Company
Consultant: AMEC
Position held in the project: Civil Supervisor
Duration: May 2006 to Oct 2007
Responsible for preparation of inspection reports and co-ordination with clients to get approval
for the construction of 7nos Oil Storage Tank Foundation, Installation pre-cast Pipe Supports,
Radial Stairway Foundation, Tank Apron, 7nos Substation Buildings Construction of UPS &
Battery room, Oil Storage Tank Bund wall construction work etc.
Nov’02 to Oct’05 with Aban Constructions Pvt. Ltd. Chennai, India
• Inspection of construction activities & Preparation of all QC related documents, coordination with clients
for Inspections & Approvals, Inspection of Subcontractor works etc., for the following projects in oil and
gas industry as detailed below:
Project Title: Laying of 12” Ф inter connection cross country pipeline
Owner: Gas Authority of India Ltd.
Consultant: Macon India Ltd.
Position held in the project: Asst Engineer
- Responsible for Inspection of Pipeline rote survey, Preparation of inspection reports, Co-
ordination with consultant for the Construction of Pavement, RCC road, Pipe sleepers, Pipe
supports, Valve pit, Fencing etc.
Project Title: Laying of 75 KM 28” Ф cross country Pipeline from Mundra to Panipat, Gujarat.
Owner: Indian Oil Corporation Ltd
Consultant: Engineers India Limited
Position held in the project: Asst Engineer
- Responsible for Inspection of Survey, and co-ordination with consultant for getting inspection approvals
for the Construction of valve pits, pipe sleepers, pipe supports, Anchor block, Trenching, Back filling,
Road crossing, Control room and structural works and fencing etc.
Project Title: Replacement of common user shore pipelines from Manifold to Marketing storage,
Owner: Mumbai Port Trust
Consultant: Kvaerner Engineers and Consultants Pvt Ltd Singapore.
Position held in the project: Asst Engineer
- Responsible for Survey, Right of way, Preparation of construction drawings, Quantity survey,
construction of pipe supports, pipe sleepers, valve pits, anchor blocks, structural works,
fencing, trenching, sand bedding and back filling for the laying of 24” Ф black oil, 20” Ф high
speed diesel, and 20” Ф superior kerosene pipelines each 7.8 Kilometer.
Page 5 of 7
6. Project Title: Laying of 120 Km 12” Ф LP Gas Cross country pipeline from Vizak to Secundrabad.
Owner: Gas Authority of India Ltd.
Consultant: Engineers India Ltd.
Position held in the project: Asst Engineer
- Responsible for Pipeline route survey, Right of way preparation, Preparation of Inspection
Rep[orts, co-ordination with consultant, Construction of Pipe sleepers, Pipe supports, RCC
blast proof wall, Road crossing (By thrust Boring), Laying of WBM roads, Control room
buildings at each terminal, fencing and painting of piping.
Apr 1999 to Oct 2002 with Nest Builders, Nagapattinam.
Project Title: Construction of commercial complex.
Owner: Sivasakthi Super market
Position held in the project: Site Engineer
- Responsible for Planning, Marking, Estimation and Execution of RCC framed structures, Brick work,
Plastering, Tiles laying, pavement and car park for the M/S Sivasakthi Super market
Project Title: Construction of College Buildings.
Owner: G.S.Pillai College of Engineering.
Position held in the project: Site Engineer
- Responsibility includes Construction of college buildings includes Planing, Quality control and
execution of RCC framed structures, Machinery foundation, Asphalt Road and Compound wall
construction.
Project Title: Construction of commercial and Residential Buildings in Nagapattinam.
Position held in the project: Trainee Engineer
- Responsibility includes Estimation, Quantity surveying, Execution of Survey and Construction
of Single and Double storied Residential flats and Commercial complex at various locations
Education
Diploma in Civil Engineering from Valivalam Desikar Polytechnic, Nagapattinam.
B.Tech Civil in Rajasthan Vidyapeeth University
IT Skills
Auto CAD 2000, MS-Office Applications.
Personal Details
Permanent Address : No-6 Kumaran Nagar, East kudiyana street, Thirupalathurai,
Papanasam (Post & Talk), Thanjavur (dist) Pin:614205
Tamilnadu, India. Telephone - +91 4374224223
Passport Number : Z1845868 valid up to 22nd
Aug 2019
Date of Birth : 14th
April, 1977
Page 6 of 7
7. Languages Known : Arabic, English, Hindi, Tamil & Malayalam
Driving Licenses
I having Driving Licenses from state of Qatar valid up to 08 Oct 2018
I having Indian Driving Licenses No.6820140006086 Valid up to 13 April 2027
Page 7 of 7