SlideShare a Scribd company logo
1 of 56
International Burch university                 Course : Building Construction Technology I
Architecture department                                                Date : xx / xx / xxxx
Sarajevo




                           Building Construction Technology I


  Professor : Prof.dr.Nerman Rustempasic
  Assistant : M.Sc. Ahmed El Sayed
   For the different construction activities like
       Brick work above 5 ft
       Surface finishing works like plastering, painting, walling etc.
       Renovation, repair and alteration works.
       Roof and slab pouring

    Some temporary nature supports and structures are required like

       Formwork     (Supporting Structure)
       Scaf foldings (arrangement for working plate forms)
       Shoring      (supporting method for unsafe structure)
       Underpinning (Method of strengthening an existing
                      structure’s footing)
Definitions
    Its is an artificial support provided below and around the precast or cast insitue
        concrete work
   Definition
   Qualities of formwork
   Types of formwork
   Formwork detail for different structural members
   Removal of formwork
   Maintenance of formwork
   Cost of formwork
   Advantages of steel form work
   Its is an artificial support provided below and around the
    precast or cast insitue concrete work.

   Formwork is commonly made of
       Steel
       wood

   Formwork construction & casting is of prime importance in
    concrete industry. It share a significant amount of concrete
    cost.
   It should be water tight

   It should be strong

   It can be reusable

   Its contact surface should be uniform

   It should be according to the size of member.
   Formwork are mainly of two types
       Steel formwork
       Wooden formwork

   Steel formwork is made of
       steel sheets
       Angle Iron
       Tee Iron

   Wooden formwork consists of
       Props
       Planks battens
       Ledgers
       sheeting
 In concrete construction formwork is commonly
  provided for the following structural members.
 Foundations
 Wall
 Column
 Slabs & beams
 Stairs
 Wall foundations
 It consists of
     Plywood   Sheeting
     Struts
 Column
  Foundations
 It consists of
     Side Supports
     Side Planks

     Cleats
                      Cleats

                      Side Support
                                     Side Planks
Vertical Posts

   It consists of
       Timber sheeting
       Vertical posts          Struts
       Horizontal members
       Rackers
       Stakes
       Wedges
   Af ter completing
    one side of
    formwork
    reinforcement is
    provided at the
    place then the
    second side
    formwork is
    provided.
   It consists of the
    following
     Side   & End Planks
     Yoke

     Nut   & Bolts
   Two end & two side
    planks are joined by
    the yokes and bolts.
   It consists of
       Sole plates
       Wedges
       Props
       Head tree
       Planks
       Batten
       Ledgers
   Beam formwork rests
    on head tree
   Slab form work rests
    on battens and joists
   If prop height are more
    than 8’ provide
    horizontal braces.
   It consists of            Riser Planks
     Vertical   & inclined
      posts
     Inclined members



     Wooden     Planks or
      sheeting
     Stringer

     Riser Planks
Time of formwork removal depends on the
  following factors
2. Type of Cement
    • Rapid hardening cements require lesser time as
       compared to OPC (Ordinary Portland Cement)
3. Ratio of concrete mix
    • Rich ratio concrete gain strength earlier as
       compared to weak ratio concrete.
4. Weather condition
    1. Hydration process accelerates in hot weather
       conditions as compared to cold and humid
       weather conditions.
Sr.                                                  OPC               Rapid
No                                              (Ordinary Portland   Hardening
         Structural Member                           Cement)
                                                                      Cement
1     Beam sides, walls & Columns                  2-3 Days           2 Days
2     Slab (Vertical Supports remains intact)       4 Days            3 Days
3     Slab (Complete Formwork removal)              10 Days           5 Days
4     Beams (Removal of Sheeting, Props             8 Days            5 Days
      remains intact)

5     Beams & Arches (Complete                      14 Days           5-8 Days
      formwork removal) (up to 6 m span)

6     Beams & Arches (Complete                      21 Days          8-10 Days
      formwork removal) (more than 6 m span)
   Due to continuous use wooden planks & steel plates
    surfaces become uneven and require maintenance.
   For wooden formwork use cardboard or plastic fiber
    board. Bolt hole places must also be repaired.
   For steel formwork plates must be leveled by mallet
    and loose corners must be welded.
   For normal works cost of formwork is about
    30%-40% of the concrete cost.
   For special works cost of formwork is about
    50%-60% of the concrete cost.
   Formwork cost is controlled by the following
    factors
       Formwork Material cost
       Formwork erecting cost
       Formwork removal cost
       Formwork jointing cost (Nails and Cables)
       Labor charges.
 It can be used for a no. of times.
 It is non absorbent.

 Smooth finish surface obtained.

 No shrinkage of formwork occurs.

 Easy to use.

 Its volume is less

 Its strength is more.
Definitions
    It’s a temporary structure to provide a platform at different levels of a building for
        workers and Materials.
    Following are the types of scaffolds
    1.   Single Scaffolds
    2.   Double Scaffolds
    3.   Ladder Scaffolds
    4.   Cantilever Scaffolds
    5.   Suspended Scaffolds
    6.   Steel or Tubular Scaffolds
   Scaffold
     It is the temporary support system provided for the
      construction & maintenance purposes.
     It consists of supports and a working platform for
      workers and Materials.
   Scaffolding
     Method   of construction of scaffolds is called
      scaffolding.
   It consists of
     Standards (v posts)
      (10 cm)
     Putlogs (7.5 x 7.5)
     Ledgers (
                            1.2 m
     Wooden boards
     Braces
    Used for ordinary
      buildings
   It consists of
     Two rows of standards.
     15 cm, 1.5 m

     Shores are provided.



   Used for superior
    works
   It consists of

     Brackets  for
      Plate form.
   It consists of
     Cantilever
     Struts
     Standards
     Putlogs
     Plate forms

   It is used above
    ground level
   It consists of
     Ropes
     Working platforms
    Ropes can be raised
      Manually or
      mechanically
    Used for light
      construction and
      finishing works of
      multistory buildings.
   It consists of
     Steel tubes (1-1/2” – 2-1/2” diameter)
     Coupler or Clamps (to hold pipes in different
      positions)
     Prop nuts (to hold single pipes)

     Bolts, Nuts & washers

     Wedge & Clip
   Double Coupler
      It joins ledgers and standards.
   Swivel Coupler
      Composed of two single couplers and used to join two scaffolds at any
        angle.
   Putlog Coupler
      Used to join putlogs with transom.
   Base Plate
      Used at the base of the standards.
   Split joint Pin
      It’s a connection fitting used to join scaffold tubes.
   Reveal Pin
      It fit in to the end of a tube to form an adjustable strut.
   Putlog end
      A flat plate used at the end of a scaffold to convert it in to a putlog.
   http://www.advancescaffold.com/international-st
Definitions
    It is the method of providing temporary support (shores) to an unsafe structure.
   Definition
     Itis the method of providing temporary support
      (shores) to an unsafe structure.
   Types of Shoring
     Horizontal shoring or flying shoring
     Vertical shoring or dead shoring

     Inclined Shoring or flying shoring
   It consists of
     Horizontal
      beam or strut
     Wall plates
     Cleats
     Straining
      beams
   Used to
    support two
    adjacent
    buildings.
   It consists of
     Dead
      shores
     Sole plates

     Needles

     Props

   Used for
    rebuilding of
    walls.
   It consists of
     Rackers
     Needles
     Cleats
     Braces
     Sole   plate
   Used to
    strengthen a
    wall.
8. formworks and scaffoldings
8. formworks and scaffoldings
8. formworks and scaffoldings
8. formworks and scaffoldings
8. formworks and scaffoldings
8. formworks and scaffoldings

More Related Content

What's hot

Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
Hamdija Velagic
 

What's hot (20)

Formwork
FormworkFormwork
Formwork
 
Formwork
FormworkFormwork
Formwork
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Formwork
FormworkFormwork
Formwork
 
Foundation
FoundationFoundation
Foundation
 
Plastering
PlasteringPlastering
Plastering
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Roof structures and Types of roofs
Roof structures and Types of roofsRoof structures and Types of roofs
Roof structures and Types of roofs
 
Beams and columns
Beams and columns Beams and columns
Beams and columns
 
Concrete
ConcreteConcrete
Concrete
 
Masonry
MasonryMasonry
Masonry
 
Types of foundation and their uses
Types of foundation and their usesTypes of foundation and their uses
Types of foundation and their uses
 
FORMWORK, SCAFFOLDING, CENTERING
FORMWORK, SCAFFOLDING, CENTERINGFORMWORK, SCAFFOLDING, CENTERING
FORMWORK, SCAFFOLDING, CENTERING
 
Foundation
FoundationFoundation
Foundation
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Mat or raft foundation
Mat or raft foundationMat or raft foundation
Mat or raft foundation
 
Shoring
ShoringShoring
Shoring
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
 
Staircase
StaircaseStaircase
Staircase
 

Viewers also liked

Introduction to Arch Week 14
Introduction to Arch Week 14Introduction to Arch Week 14
Introduction to Arch Week 14
Hamdija Velagic
 
Building Construction 7. construction site
Building Construction 7. construction siteBuilding Construction 7. construction site
Building Construction 7. construction site
Hamdija Velagic
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materials
Hamdija Velagic
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
Hamdija Velagic
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
Hamdija Velagic
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
Hamdija Velagic
 
Intro to Architecture Week 5 [compatibility mode]
Intro to Architecture Week 5 [compatibility mode]Intro to Architecture Week 5 [compatibility mode]
Intro to Architecture Week 5 [compatibility mode]
Hamdija Velagic
 
Introduction to Arch Week 11
Introduction to Arch Week 11Introduction to Arch Week 11
Introduction to Arch Week 11
Hamdija Velagic
 
Introduction to Arch Week 13
Introduction to Arch Week 13Introduction to Arch Week 13
Introduction to Arch Week 13
Hamdija Velagic
 
Building Construction Class 2. definitions
Building Construction Class 2. definitionsBuilding Construction Class 2. definitions
Building Construction Class 2. definitions
Hamdija Velagic
 
Architecture form space order
Architecture form space orderArchitecture form space order
Architecture form space order
Hamdija Velagic
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
Ashish Parihar
 
Building Construction 4. tender offer
Building Construction 4. tender offerBuilding Construction 4. tender offer
Building Construction 4. tender offer
Hamdija Velagic
 
Building Construction and Tech. 3. Responsibilities of participants
Building Construction and Tech. 3. Responsibilities of participantsBuilding Construction and Tech. 3. Responsibilities of participants
Building Construction and Tech. 3. Responsibilities of participants
Hamdija Velagic
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - site
Hamdija Velagic
 
Building Construction 6. intro to building materials
Building Construction 6. intro to building materialsBuilding Construction 6. intro to building materials
Building Construction 6. intro to building materials
Hamdija Velagic
 
8. formwork and scaffolding
8. formwork and scaffolding8. formwork and scaffolding
8. formwork and scaffolding
Hamdija Velagic
 
Introduction to Arch List of potential questions
Introduction to Arch List of potential questionsIntroduction to Arch List of potential questions
Introduction to Arch List of potential questions
Hamdija Velagic
 
Intro to Arch Week 4 [compatibility mode]
Intro to Arch Week 4 [compatibility mode]Intro to Arch Week 4 [compatibility mode]
Intro to Arch Week 4 [compatibility mode]
Hamdija Velagic
 

Viewers also liked (20)

Introduction to Arch Week 14
Introduction to Arch Week 14Introduction to Arch Week 14
Introduction to Arch Week 14
 
Building Construction 7. construction site
Building Construction 7. construction siteBuilding Construction 7. construction site
Building Construction 7. construction site
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materials
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
 
Intro to Architecture Week 5 [compatibility mode]
Intro to Architecture Week 5 [compatibility mode]Intro to Architecture Week 5 [compatibility mode]
Intro to Architecture Week 5 [compatibility mode]
 
Introduction to Arch Week 11
Introduction to Arch Week 11Introduction to Arch Week 11
Introduction to Arch Week 11
 
Introduction to Arch Week 13
Introduction to Arch Week 13Introduction to Arch Week 13
Introduction to Arch Week 13
 
Building Construction Class 2. definitions
Building Construction Class 2. definitionsBuilding Construction Class 2. definitions
Building Construction Class 2. definitions
 
Architecture form space order
Architecture form space orderArchitecture form space order
Architecture form space order
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
Building Construction 4. tender offer
Building Construction 4. tender offerBuilding Construction 4. tender offer
Building Construction 4. tender offer
 
Building Construction and Tech. 3. Responsibilities of participants
Building Construction and Tech. 3. Responsibilities of participantsBuilding Construction and Tech. 3. Responsibilities of participants
Building Construction and Tech. 3. Responsibilities of participants
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - site
 
Building Construction 6. intro to building materials
Building Construction 6. intro to building materialsBuilding Construction 6. intro to building materials
Building Construction 6. intro to building materials
 
8. formwork and scaffolding
8. formwork and scaffolding8. formwork and scaffolding
8. formwork and scaffolding
 
Into. to Arch Week 2
Into. to Arch Week 2Into. to Arch Week 2
Into. to Arch Week 2
 
Introduction to Arch List of potential questions
Introduction to Arch List of potential questionsIntroduction to Arch List of potential questions
Introduction to Arch List of potential questions
 
Intro to Arch Week 4 [compatibility mode]
Intro to Arch Week 4 [compatibility mode]Intro to Arch Week 4 [compatibility mode]
Intro to Arch Week 4 [compatibility mode]
 

Similar to 8. formworks and scaffoldings

8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
FaizanSolanki
 
various types of scffolding and formwork with underpining
various types of scffolding and formwork with underpiningvarious types of scffolding and formwork with underpining
various types of scffolding and formwork with underpining
kuldeep361335
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
FaizanSolanki
 
Framing Floors, And Walls
Framing Floors, And WallsFraming Floors, And Walls
Framing Floors, And Walls
vizithum
 

Similar to 8. formworks and scaffoldings (20)

8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
 
formwork.pdf
formwork.pdfformwork.pdf
formwork.pdf
 
various types of scffolding and formwork with underpining
various types of scffolding and formwork with underpiningvarious types of scffolding and formwork with underpining
various types of scffolding and formwork with underpining
 
Formwork
FormworkFormwork
Formwork
 
Formwork
FormworkFormwork
Formwork
 
Temporary Works (Form Work)
Temporary Works (Form Work)Temporary Works (Form Work)
Temporary Works (Form Work)
 
FormWork
FormWork FormWork
FormWork
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
 
Formwork
FormworkFormwork
Formwork
 
Formwork
FormworkFormwork
Formwork
 
Form Work
Form Work Form Work
Form Work
 
Formwork
FormworkFormwork
Formwork
 
From work & shuttering
From work & shutteringFrom work & shuttering
From work & shuttering
 
FORMWORK.pptx
FORMWORK.pptxFORMWORK.pptx
FORMWORK.pptx
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Place and Fix Reinforcement Materials Intro (2023 Edit).pptx
Place and Fix Reinforcement Materials Intro (2023 Edit).pptxPlace and Fix Reinforcement Materials Intro (2023 Edit).pptx
Place and Fix Reinforcement Materials Intro (2023 Edit).pptx
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
 
Timber Structure.pdf
Timber Structure.pdfTimber Structure.pdf
Timber Structure.pdf
 
Framing Floors, And Walls
Framing Floors, And WallsFraming Floors, And Walls
Framing Floors, And Walls
 
form work - Building construction necessities
form work - Building construction necessities  form work - Building construction necessities
form work - Building construction necessities
 

More from Hamdija Velagic

New Intro to Architecture Week 4
New Intro to Architecture Week 4New Intro to Architecture Week 4
New Intro to Architecture Week 4
Hamdija Velagic
 
Building Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionBuilding Construction 2. rules and definition in construction
Building Construction 2. rules and definition in construction
Hamdija Velagic
 
Building Construction 3. responsibilities of participants
Building Construction 3. responsibilities of participantsBuilding Construction 3. responsibilities of participants
Building Construction 3. responsibilities of participants
Hamdija Velagic
 
Building Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionBuilding Construction 2. rules and definition in construction
Building Construction 2. rules and definition in construction
Hamdija Velagic
 
1. Introduction to Project Management
1. Introduction to Project Management1. Introduction to Project Management
1. Introduction to Project Management
Hamdija Velagic
 

More from Hamdija Velagic (6)

New Intro to Architecture Week 4
New Intro to Architecture Week 4New Intro to Architecture Week 4
New Intro to Architecture Week 4
 
Building Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionBuilding Construction 2. rules and definition in construction
Building Construction 2. rules and definition in construction
 
Building Construction 3. responsibilities of participants
Building Construction 3. responsibilities of participantsBuilding Construction 3. responsibilities of participants
Building Construction 3. responsibilities of participants
 
Building Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionBuilding Construction 2. rules and definition in construction
Building Construction 2. rules and definition in construction
 
Into. to Arch Week 3
Into. to Arch Week 3Into. to Arch Week 3
Into. to Arch Week 3
 
1. Introduction to Project Management
1. Introduction to Project Management1. Introduction to Project Management
1. Introduction to Project Management
 

Recently uploaded

!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
DUBAI (+971)581248768 BUY ABORTION PILLS IN ABU dhabi...Qatar
 
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
instagramfab782445
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Abortion pills in Kuwait Cytotec pills in Kuwait
 

Recently uploaded (20)

Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Power point presentation on enterprise performance management
Power point presentation on enterprise performance managementPower point presentation on enterprise performance management
Power point presentation on enterprise performance management
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From Seosmmearth
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Cracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareCracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' Slideshare
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 

8. formworks and scaffoldings

  • 1. International Burch university Course : Building Construction Technology I Architecture department Date : xx / xx / xxxx Sarajevo Building Construction Technology I Professor : Prof.dr.Nerman Rustempasic Assistant : M.Sc. Ahmed El Sayed
  • 2. For the different construction activities like  Brick work above 5 ft  Surface finishing works like plastering, painting, walling etc.  Renovation, repair and alteration works.  Roof and slab pouring Some temporary nature supports and structures are required like  Formwork (Supporting Structure)  Scaf foldings (arrangement for working plate forms)  Shoring (supporting method for unsafe structure)  Underpinning (Method of strengthening an existing structure’s footing)
  • 3. Definitions Its is an artificial support provided below and around the precast or cast insitue concrete work
  • 4. Definition  Qualities of formwork  Types of formwork  Formwork detail for different structural members  Removal of formwork  Maintenance of formwork  Cost of formwork  Advantages of steel form work
  • 5. Its is an artificial support provided below and around the precast or cast insitue concrete work.  Formwork is commonly made of  Steel  wood  Formwork construction & casting is of prime importance in concrete industry. It share a significant amount of concrete cost.
  • 6. It should be water tight  It should be strong  It can be reusable  Its contact surface should be uniform  It should be according to the size of member.
  • 7. Formwork are mainly of two types  Steel formwork  Wooden formwork  Steel formwork is made of  steel sheets  Angle Iron  Tee Iron  Wooden formwork consists of  Props  Planks battens  Ledgers  sheeting
  • 8.  In concrete construction formwork is commonly provided for the following structural members.  Foundations  Wall  Column  Slabs & beams  Stairs
  • 9.  Wall foundations  It consists of  Plywood Sheeting  Struts
  • 10.  Column Foundations  It consists of  Side Supports  Side Planks  Cleats Cleats Side Support Side Planks
  • 11. Vertical Posts  It consists of  Timber sheeting  Vertical posts Struts  Horizontal members  Rackers  Stakes  Wedges  Af ter completing one side of formwork reinforcement is provided at the place then the second side formwork is provided.
  • 12. It consists of the following  Side & End Planks  Yoke  Nut & Bolts  Two end & two side planks are joined by the yokes and bolts.
  • 13.
  • 14.
  • 15. It consists of  Sole plates  Wedges  Props  Head tree  Planks  Batten  Ledgers  Beam formwork rests on head tree  Slab form work rests on battens and joists  If prop height are more than 8’ provide horizontal braces.
  • 16.
  • 17. It consists of Riser Planks  Vertical & inclined posts  Inclined members  Wooden Planks or sheeting  Stringer  Riser Planks
  • 18.
  • 19. Time of formwork removal depends on the following factors 2. Type of Cement • Rapid hardening cements require lesser time as compared to OPC (Ordinary Portland Cement) 3. Ratio of concrete mix • Rich ratio concrete gain strength earlier as compared to weak ratio concrete. 4. Weather condition 1. Hydration process accelerates in hot weather conditions as compared to cold and humid weather conditions.
  • 20. Sr. OPC Rapid No (Ordinary Portland Hardening Structural Member Cement) Cement 1 Beam sides, walls & Columns 2-3 Days 2 Days 2 Slab (Vertical Supports remains intact) 4 Days 3 Days 3 Slab (Complete Formwork removal) 10 Days 5 Days 4 Beams (Removal of Sheeting, Props 8 Days 5 Days remains intact) 5 Beams & Arches (Complete 14 Days 5-8 Days formwork removal) (up to 6 m span) 6 Beams & Arches (Complete 21 Days 8-10 Days formwork removal) (more than 6 m span)
  • 21. Due to continuous use wooden planks & steel plates surfaces become uneven and require maintenance.  For wooden formwork use cardboard or plastic fiber board. Bolt hole places must also be repaired.  For steel formwork plates must be leveled by mallet and loose corners must be welded.
  • 22. For normal works cost of formwork is about 30%-40% of the concrete cost.  For special works cost of formwork is about 50%-60% of the concrete cost.  Formwork cost is controlled by the following factors  Formwork Material cost  Formwork erecting cost  Formwork removal cost  Formwork jointing cost (Nails and Cables)  Labor charges.
  • 23.  It can be used for a no. of times.  It is non absorbent.  Smooth finish surface obtained.  No shrinkage of formwork occurs.  Easy to use.  Its volume is less  Its strength is more.
  • 24. Definitions It’s a temporary structure to provide a platform at different levels of a building for workers and Materials.
  • 25. Following are the types of scaffolds 1. Single Scaffolds 2. Double Scaffolds 3. Ladder Scaffolds 4. Cantilever Scaffolds 5. Suspended Scaffolds 6. Steel or Tubular Scaffolds
  • 26. Scaffold  It is the temporary support system provided for the construction & maintenance purposes.  It consists of supports and a working platform for workers and Materials.  Scaffolding  Method of construction of scaffolds is called scaffolding.
  • 27. It consists of  Standards (v posts) (10 cm)  Putlogs (7.5 x 7.5)  Ledgers ( 1.2 m  Wooden boards  Braces Used for ordinary buildings
  • 28.
  • 29. It consists of  Two rows of standards.  15 cm, 1.5 m  Shores are provided.  Used for superior works
  • 30.
  • 31. It consists of  Brackets for Plate form.
  • 32. It consists of  Cantilever  Struts  Standards  Putlogs  Plate forms  It is used above ground level
  • 33. It consists of  Ropes  Working platforms Ropes can be raised Manually or mechanically Used for light construction and finishing works of multistory buildings.
  • 34. It consists of  Steel tubes (1-1/2” – 2-1/2” diameter)  Coupler or Clamps (to hold pipes in different positions)  Prop nuts (to hold single pipes)  Bolts, Nuts & washers  Wedge & Clip
  • 35.
  • 36.
  • 37. Double Coupler  It joins ledgers and standards.  Swivel Coupler  Composed of two single couplers and used to join two scaffolds at any angle.  Putlog Coupler  Used to join putlogs with transom.  Base Plate  Used at the base of the standards.  Split joint Pin  It’s a connection fitting used to join scaffold tubes.  Reveal Pin  It fit in to the end of a tube to form an adjustable strut.  Putlog end  A flat plate used at the end of a scaffold to convert it in to a putlog.
  • 38.
  • 39.
  • 40.
  • 41.
  • 42. http://www.advancescaffold.com/international-st
  • 43. Definitions It is the method of providing temporary support (shores) to an unsafe structure.
  • 44. Definition  Itis the method of providing temporary support (shores) to an unsafe structure.  Types of Shoring  Horizontal shoring or flying shoring  Vertical shoring or dead shoring  Inclined Shoring or flying shoring
  • 45. It consists of  Horizontal beam or strut  Wall plates  Cleats  Straining beams  Used to support two adjacent buildings.
  • 46.
  • 47.
  • 48. It consists of  Dead shores  Sole plates  Needles  Props  Used for rebuilding of walls.
  • 49.
  • 50. It consists of  Rackers  Needles  Cleats  Braces  Sole plate  Used to strengthen a wall.