SlideShare a Scribd company logo
1 of 28
FORMWORK AND ITS TYPES
NAME : PRADUMN BALAJI SURYAKAR
GUIDED BY: DR. S. S. KORANNE
CLASS: S.E. CIVIL
ROLL NO.: BE17F01F049
CONTENTS
 INTRODUCTION
 REQUIREMENTS
 INDIAN STANDARDS ON FORM WORK
 LOADS ON FORM WORK
 TYPES OF FORM WORK
INTRODUCTION
 Formwork (shuttering) in concrete construction is used as a mould for a structure in
which fresh concrete is poured only to harden subsequently. Types of concrete
formwork construction depends on formwork material and type of structural element.
 Classification – wooden, plywood, steel, combined wood-steel, reinforced concrete,
plain concrete.
 The construction of formwork takes time and involves expenditure upto 20 to 25% of
the cost of the structure or even more.
 Timber is the most common material used for formwork. The disadvantage with timber
formwork is that it will warp, swell and shrink. Application of water impermeable cost
to the surface of wood mitigates these defects.
 The operation of removing the formwork is known as stripping. Stripped formwork can
be reused. Reusable forms are known as panel forms and non-usable are called
stationary forms.
REQUIREMENTS
 It should be strong enough to withstand all types of dead and live loads.
 It should be rigidly constructed and efficiently propped and braced both horizontally
and vertically, so as to retain its shape.
 The joints in the formwork should be tight against leakage of cement grout.
 Construction of formwork should permit removal of various parts in desired sequences
without damage to the concrete.
 It should rest on firm base.
 The material of the formwork should be cheap, easily available and should be suitable
for reuse.
 The formwork should be set accurately to the desired line and levels should have plane
surface.
 It should be as light as possible.
 The material of the formwork should not warp or get distorted when exposed to the
elements.
ECONOMY IN FORM WORK
 The plan of the building should imply minimum number of variations in the size of
rooms, floor area etc. so as to permit reuse of the formwork repeatedly.
 Design should be perfect to use slender sections only in a most economical way.
 Minimum sawing and cutting of wooden pieces should be made to enable reuse of the
material a number of times. The quantity of surface finish depends on the quality of the
formwork.
 Fibre glass made of precast concrete and aluminium are used in cast-in-situ
construction such as slabs or members involving curved surfaces.
INDIAN STANDARDS ON FORM WORK
 General – Form work shall conform shape, lines, dimensions.
 Cleaning and treatment of forms – All rubbish, particularly chippings, shavings
and sawdust shall be removed from interior of the forms before concrete is
placed.
 Camber – Desirable to give forms an upward camber to ensure that the beams
do not have a sag.
 Tolerances – Form work shall be so constructed that the internal dimensions
are within the permissible tolerance specified by the designer.
 Stripping time
S.
No.
Description of structural member Time Period
1 Walls, columns and vertical sides of beams 1 to 2 days
2 Slabs (props left under) 3 days
3 Beam soffits (props left under) 7 days
4
Removal of props to slabs
(a) For slabs spanning upto 4.5 m 7 days
(b) For slabs spanning over 4.5 m 14 days
5
Removal of props to beams and arches
(a) Spanning upto 6 m 14 days
(b) spanning over 6 m 21 days
TYPES OF FORMWORK
Timber Formwork
 Timber for formwork should satisfy the following requirement – It should be,
 well seasoned
 light in weight
 easily workable with nails without splitting
 free from loose knots
 Timber used for shuttering for exposed concrete work should have smooth and
even surface on all faces which come in contact with concrete.
Normal sizes of members for timber formwork:
Sheeting for slabs, beam, column
side and beam bottom
25 mm to 40mm thick
Joints, ledges 50 x 70 mm to 50 x 150 mm
Posts 75 x 100mm to 100 x 100 mm
Advantages of using timber forms:
 Timber Shuttering is easy to construct for any shape, size and height.
 It is economical for Small projects.
 It can easily be made into any shape or size.
 It can be constructed using locally available timber.
 It is light weight as compared to steel or aluminum Shuttering.
Plywood Formwork
 Resin bonded plywood sheets are attached to timber frames to make up
panels of required sizes.
 It is possible to have smooth finish in which case on cost in surface finishing is
there.
 By use of large size panels it is possible to effect saving in the labour cost of
fixing and dismantling.
 Number of reuses are more as compared with timber shuttering. For
estimation purpose, number of reuses can be taken as 20 to 25.
Steel Formwork
 This consist of panels fabricated out of thin steel plates stiffened along the edges by
small steel angles.
 The panel units can be held together through the use of suitable clamps or bolts and
nuts.
 The panels can be fabricated in large number in any desired modular shape or size.
 Steel forms are largely used in large projects or in situation where large number reuses
of the shuttering is possible.
 This type of shuttering is considered most suitable for circular or curved structures.
Steel forms compared with timber formwork:
 Steel forms are stronger, durable and have longer life than timber formwork and their
reuses are more in number.
 Steel forms can be installed and dismantled with greater ease and speed.
 The quality of exposed concrete surface by using steel forms is good and such surfaces
need no further treatment.
 Steel formwork does not absorb moisture from concrete.
 Steel formwork does not shrink or warp.
Aluminium Form work
 Aluminium formwork is similar in many respects similar to those made of
steel.
 Aluminium forms are lighter than steel forms due to low density and this is
their primary advantage when compared to steel.
 The shuttering is economical if large numbers of repeating usage are made in
construction.
 The disadvantage is that no alteration is possible once the formwork is
constructed.
Plastic Formwork
Plastic form work is a lightweight modular, interlocking system and can be used
more than 100 times
 Advantage of Plastic Form work:-
 It is light weight shuttering hence requires less handling cost.
 It can be used for large section.
 If carefully transported and used, multiple reuses are possible making it highly
economical.
Fabric Formwork
 Fabric formwork is emerging
technology in shuttering industry for
construction of irregular shape and
complex member.
 The flexibility of this material makes it
possible to produce concrete at any
shape.
Coffor Formwork
 Coffor is a stay in place formwork
system.
 Coffor remains in place after concrete
is poured and acts as reinforcement.
 Coffor is transported to the site
prefabricated from the factory.
 This type of shuttering can be used for
any type of structure like houses,
multistory buildings etc.
Wall Form work
 Wall formwork used for concreting of
shear or RCC wall in dams, wing
walls, basement rcc walls etc.
 Wall shuttering made up of vertically
arranged upright timbers (bearers) to
which plywood sheeting boards are
nailed at the inner side.
 The upright timbers are diagonally
braced with the help of boards at both
sides.
Beam Form work
 Beam is the most important member in
RCC framed structure.
 Beam formwork has prefabricated form
work includes sheeting bottom and side
sheeting panels.
 The individual parts of form-work are
manufactured based on the beam size.
Foundation Form work
 Foundation formworks designed
according to foundation type.
 Shuttering design for foundation
depends on foundation type like
footing, combined footing, raft.
 There is a difference in the design for
individual foundations, and shuttering
for strip foundations.
Column Formwork
 Formwork arrangement for column
may differ on the basis of column
outline like rectangular, circular, and
hexagonal or any other shape.
 The sheeting of column shuttering is
constructed according to the column
dimensions.
 The panels are placed in a foot rim,
anchored in soil with the help of bolts.
REFERENCE
 https://theconstructor.org/building/formwork-shuttering/types-of-formwork-
shuttering/3767/
 https://civildigital.com/formwork-construction-types-applications-shuttering/
 Building Construction book by Dr.B.C.Punmia
THANK YOU

More Related Content

What's hot

What's hot (20)

Building methods and construction technology 1
Building methods and construction technology 1Building methods and construction technology 1
Building methods and construction technology 1
 
Types of bonds
Types of bondsTypes of bonds
Types of bonds
 
Details of roofs and floors
Details of roofs and floorsDetails of roofs and floors
Details of roofs and floors
 
Brick masonry ppt
Brick masonry pptBrick masonry ppt
Brick masonry ppt
 
Buiding construction (part ii)
Buiding construction (part ii)Buiding construction (part ii)
Buiding construction (part ii)
 
Timber ppt-1
Timber ppt-1Timber ppt-1
Timber ppt-1
 
PRESENTATION ON CONCRETE
PRESENTATION ON CONCRETEPRESENTATION ON CONCRETE
PRESENTATION ON CONCRETE
 
Framed structures
Framed structures Framed structures
Framed structures
 
Laminated boards
Laminated boardsLaminated boards
Laminated boards
 
Reinforced Concrete
Reinforced ConcreteReinforced Concrete
Reinforced Concrete
 
Components of building - Building Materials and Construction
Components of building - Building Materials and ConstructionComponents of building - Building Materials and Construction
Components of building - Building Materials and Construction
 
FORMWORK.pptx
FORMWORK.pptxFORMWORK.pptx
FORMWORK.pptx
 
Building construction 1
Building construction 1Building construction 1
Building construction 1
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Design
 
types of Flooring in construction
types of Flooring in constructiontypes of Flooring in construction
types of Flooring in construction
 
Brick Masonry
Brick MasonryBrick Masonry
Brick Masonry
 
Masonry
MasonryMasonry
Masonry
 
Tiles
TilesTiles
Tiles
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 
Footing and Its Types
Footing and Its TypesFooting and Its Types
Footing and Its Types
 

Similar to Formwork Types Guide for Concrete Construction

Types of Formwork & Materials.pptx
Types of Formwork & Materials.pptxTypes of Formwork & Materials.pptx
Types of Formwork & Materials.pptxMr Amol Ghogare
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineeringFazal-E- Jalal
 
Formwork For Structural Member.pptx
Formwork For Structural Member.pptxFormwork For Structural Member.pptx
Formwork For Structural Member.pptxMr Amol Ghogare
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdfFaizanSolanki
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2Gali Suresh
 
types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdfReigerRoyal
 
Ct formwork presentation
Ct formwork presentationCt formwork presentation
Ct formwork presentationbee_by
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shutteringKishor Ade
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction FormworkAnkit Singhai
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction purvi golecha
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork adarshkaushik6
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
Uses of Materials- Town Planning
Uses of Materials- Town PlanningUses of Materials- Town Planning
Uses of Materials- Town PlanningFaisal Rasool
 

Similar to Formwork Types Guide for Concrete Construction (20)

Types of Formwork & Materials.pptx
Types of Formwork & Materials.pptxTypes of Formwork & Materials.pptx
Types of Formwork & Materials.pptx
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineering
 
Formwork For Structural Member.pptx
Formwork For Structural Member.pptxFormwork For Structural Member.pptx
Formwork For Structural Member.pptx
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
 
Shuttering materials
Shuttering materialsShuttering materials
Shuttering materials
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2
 
Temporary Works (Form Work)
Temporary Works (Form Work)Temporary Works (Form Work)
Temporary Works (Form Work)
 
types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdf
 
Ct formwork presentation
Ct formwork presentationCt formwork presentation
Ct formwork presentation
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Formwork
FormworkFormwork
Formwork
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction Formwork
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork
 
Formwork
FormworkFormwork
Formwork
 
Formwork 151220193813
Formwork 151220193813Formwork 151220193813
Formwork 151220193813
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Uses of Materials- Town Planning
Uses of Materials- Town PlanningUses of Materials- Town Planning
Uses of Materials- Town Planning
 

Recently uploaded

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 

Formwork Types Guide for Concrete Construction

  • 1. FORMWORK AND ITS TYPES NAME : PRADUMN BALAJI SURYAKAR GUIDED BY: DR. S. S. KORANNE CLASS: S.E. CIVIL ROLL NO.: BE17F01F049
  • 2. CONTENTS  INTRODUCTION  REQUIREMENTS  INDIAN STANDARDS ON FORM WORK  LOADS ON FORM WORK  TYPES OF FORM WORK
  • 3. INTRODUCTION  Formwork (shuttering) in concrete construction is used as a mould for a structure in which fresh concrete is poured only to harden subsequently. Types of concrete formwork construction depends on formwork material and type of structural element.  Classification – wooden, plywood, steel, combined wood-steel, reinforced concrete, plain concrete.  The construction of formwork takes time and involves expenditure upto 20 to 25% of the cost of the structure or even more.
  • 4.  Timber is the most common material used for formwork. The disadvantage with timber formwork is that it will warp, swell and shrink. Application of water impermeable cost to the surface of wood mitigates these defects.  The operation of removing the formwork is known as stripping. Stripped formwork can be reused. Reusable forms are known as panel forms and non-usable are called stationary forms.
  • 5. REQUIREMENTS  It should be strong enough to withstand all types of dead and live loads.  It should be rigidly constructed and efficiently propped and braced both horizontally and vertically, so as to retain its shape.  The joints in the formwork should be tight against leakage of cement grout.  Construction of formwork should permit removal of various parts in desired sequences without damage to the concrete.  It should rest on firm base.
  • 6.  The material of the formwork should be cheap, easily available and should be suitable for reuse.  The formwork should be set accurately to the desired line and levels should have plane surface.  It should be as light as possible.  The material of the formwork should not warp or get distorted when exposed to the elements.
  • 7. ECONOMY IN FORM WORK  The plan of the building should imply minimum number of variations in the size of rooms, floor area etc. so as to permit reuse of the formwork repeatedly.  Design should be perfect to use slender sections only in a most economical way.  Minimum sawing and cutting of wooden pieces should be made to enable reuse of the material a number of times. The quantity of surface finish depends on the quality of the formwork.  Fibre glass made of precast concrete and aluminium are used in cast-in-situ construction such as slabs or members involving curved surfaces.
  • 8. INDIAN STANDARDS ON FORM WORK  General – Form work shall conform shape, lines, dimensions.  Cleaning and treatment of forms – All rubbish, particularly chippings, shavings and sawdust shall be removed from interior of the forms before concrete is placed.  Camber – Desirable to give forms an upward camber to ensure that the beams do not have a sag.  Tolerances – Form work shall be so constructed that the internal dimensions are within the permissible tolerance specified by the designer.
  • 9.  Stripping time S. No. Description of structural member Time Period 1 Walls, columns and vertical sides of beams 1 to 2 days 2 Slabs (props left under) 3 days 3 Beam soffits (props left under) 7 days 4 Removal of props to slabs (a) For slabs spanning upto 4.5 m 7 days (b) For slabs spanning over 4.5 m 14 days 5 Removal of props to beams and arches (a) Spanning upto 6 m 14 days (b) spanning over 6 m 21 days
  • 11. Timber Formwork  Timber for formwork should satisfy the following requirement – It should be,  well seasoned  light in weight  easily workable with nails without splitting  free from loose knots  Timber used for shuttering for exposed concrete work should have smooth and even surface on all faces which come in contact with concrete.
  • 12.
  • 13. Normal sizes of members for timber formwork: Sheeting for slabs, beam, column side and beam bottom 25 mm to 40mm thick Joints, ledges 50 x 70 mm to 50 x 150 mm Posts 75 x 100mm to 100 x 100 mm
  • 14. Advantages of using timber forms:  Timber Shuttering is easy to construct for any shape, size and height.  It is economical for Small projects.  It can easily be made into any shape or size.  It can be constructed using locally available timber.  It is light weight as compared to steel or aluminum Shuttering.
  • 15. Plywood Formwork  Resin bonded plywood sheets are attached to timber frames to make up panels of required sizes.  It is possible to have smooth finish in which case on cost in surface finishing is there.  By use of large size panels it is possible to effect saving in the labour cost of fixing and dismantling.  Number of reuses are more as compared with timber shuttering. For estimation purpose, number of reuses can be taken as 20 to 25.
  • 16.
  • 17. Steel Formwork  This consist of panels fabricated out of thin steel plates stiffened along the edges by small steel angles.  The panel units can be held together through the use of suitable clamps or bolts and nuts.  The panels can be fabricated in large number in any desired modular shape or size.  Steel forms are largely used in large projects or in situation where large number reuses of the shuttering is possible.  This type of shuttering is considered most suitable for circular or curved structures.
  • 18.
  • 19. Steel forms compared with timber formwork:  Steel forms are stronger, durable and have longer life than timber formwork and their reuses are more in number.  Steel forms can be installed and dismantled with greater ease and speed.  The quality of exposed concrete surface by using steel forms is good and such surfaces need no further treatment.  Steel formwork does not absorb moisture from concrete.  Steel formwork does not shrink or warp.
  • 20. Aluminium Form work  Aluminium formwork is similar in many respects similar to those made of steel.  Aluminium forms are lighter than steel forms due to low density and this is their primary advantage when compared to steel.  The shuttering is economical if large numbers of repeating usage are made in construction.  The disadvantage is that no alteration is possible once the formwork is constructed.
  • 21.
  • 22. Plastic Formwork Plastic form work is a lightweight modular, interlocking system and can be used more than 100 times  Advantage of Plastic Form work:-  It is light weight shuttering hence requires less handling cost.  It can be used for large section.  If carefully transported and used, multiple reuses are possible making it highly economical.
  • 23.
  • 24. Fabric Formwork  Fabric formwork is emerging technology in shuttering industry for construction of irregular shape and complex member.  The flexibility of this material makes it possible to produce concrete at any shape. Coffor Formwork  Coffor is a stay in place formwork system.  Coffor remains in place after concrete is poured and acts as reinforcement.  Coffor is transported to the site prefabricated from the factory.  This type of shuttering can be used for any type of structure like houses, multistory buildings etc.
  • 25. Wall Form work  Wall formwork used for concreting of shear or RCC wall in dams, wing walls, basement rcc walls etc.  Wall shuttering made up of vertically arranged upright timbers (bearers) to which plywood sheeting boards are nailed at the inner side.  The upright timbers are diagonally braced with the help of boards at both sides. Beam Form work  Beam is the most important member in RCC framed structure.  Beam formwork has prefabricated form work includes sheeting bottom and side sheeting panels.  The individual parts of form-work are manufactured based on the beam size.
  • 26. Foundation Form work  Foundation formworks designed according to foundation type.  Shuttering design for foundation depends on foundation type like footing, combined footing, raft.  There is a difference in the design for individual foundations, and shuttering for strip foundations. Column Formwork  Formwork arrangement for column may differ on the basis of column outline like rectangular, circular, and hexagonal or any other shape.  The sheeting of column shuttering is constructed according to the column dimensions.  The panels are placed in a foot rim, anchored in soil with the help of bolts.