SlideShare a Scribd company logo
December 8, 2016
toronto.ca/king‐liberty‐bridge
Welcome
King Liberty Pedestrian / Cycling Bridge
Detail Design
Public Drop-in Event #1
150 East Liberty Street,
December 8, 2016. 6 p.m. – 8 p.m.
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
• Introduce the King‐Liberty 
Pedestrian/Bridge (the “Project”).
• Recap the results of the 
Environmental Assessment (EA) 
conducted in 2011.
• Provide an update on the work 
completed since the EA.
• Describe the general arrangement of 
the Project. 
• Seek input on various design 
elements of the Project.
Purpose of this Public Consultation
2
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
3
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
Project Area
4
The Project Area 
is situated within 
Liberty Village in 
the City of 
Toronto, bounded 
by King St West 
to the north west, 
GO Transit 
Corridor and 
Western Battery 
Rd to the south 
and Shaw St to 
the East. 
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
Project Background
• The Environmental Assessment (EA) was completed in November 2011. 
• Multiple alternative locations of the King‐Liberty Pedestrian / Cyclist Link were 
considered and assessed as part of the EA. 
• Once the preferred location was determined, various design alternatives were 
considered.
5
• A bridge with a 
combination of stairs and 
elevators for access was 
identified as the 
recommended preferred 
design.
• This is the early concept 
design from 2011. See later 
slides for current detailed 
design.
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
Project Background
The preferred design offer the following:
 Poses minimal impact to possible future multi‐use path 
on Douro St.
 Elevator eliminates the need for out‐of‐way travel and 
it is accessible for cyclists at all levels. 
 Requires the least amount of tree removal. 
 Poses minimal impacts to residential and commercial 
properties. 
 Poses no impacts to archaeological or heritage 
resources. 
 Poses no Impacts to Metrolinx / CN / CP rail 
operations.
6
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
7
Existing Conditions: Western Battery Rd
Facing North 
towards Douro St
Facing South towards 
Western Battery Rd
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
8
Tree Inventory: Western Battery Rd
The tree inventory study area includes the Project Area plus a 6m buffer. There are 24 
trees near the southern part of the bridge that may need removal, subject to final design.
Trees range from 4.5cm – 18cm Diameter at Breast Height.
Ironwood Red maple & Oak
White Pine
Spruce
Tree replacement opportunities are being reviewed and will be identified at Public Drop‐in Event # 2
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
9
Tree Inventory: Douro St
Manitoba Maples
Norway Maple
The tree inventory study area includes the Project Area plus a 6m buffer.  There are 7 trees
near the northern part of the bridge that may need removal, subject to final design. Trees 
range from 2cm ‐7cm Diameter at Breast Height.
Tree replacement opportunities are being reviewed and will be identified at Public Drop‐in Event # 2
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
10
Study Area – Land Ownership
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
Design Elements
11
Elements already 
determined
• Bridge location and 
configuration 
• Elevators at each end
• Stairs with bike channel
• 5m wide multi‐use bridge 
path
• Covered deck with 2m glass
• Lighting & safety 
• Elevator façade 
• Staircase & railing
• Exterior treatment (roof, 
cladding and façade)
• Landscaping and 
streetscaping
Photos are conceptual only
Options to be 
decided
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
12
General Arrangement – Street Level
NEW ELEVATOR
NEW PLAZA
NEW ELEVATOR
NEW PLAZAEXISTING
RAIL
CORRIDOR 
NEW STAIR
NEW STAIR
Landscaping options shown in later slides
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
13
General Arrangement - Bridge Level
NEW STAIR
NEW ELEVATOR
NEW STAIR
EXISTING
RAIL
CORRIDOR 
A
A
NEW ELEVATOR
Landscaping options shown in later slides
SECTION A‐A                                                
3m
5m
2m GLASS WALL
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
14
General Arrangement - Aerial View
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
Lighting
15
TYPICAL LED EXTERIOR LIGHTING
TO BE CONSIDERED AT PLAZAS
EXAMPLES OF STAIR LIGHTING AT BOTH
HIGH AND TREAD LEVELS
ARTIST CONCEPT OF BRIDGE LIGHTING
THE BRIDGE WILL BE ILLUMINATED WITH LED LIGHTS
ACROSS FULL SPAN,ON THE STAIRS, LANDINGS AND
WITHIN THE ELEVATORS
NIGHT VIEW
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
Safety
16
RAILINGS & HANDRAIL
ANTI-SLIP NOSING
CLOSED CIRCUIT SECURITY
CAMERAS
THESE REFERENCE IMAGES CAPTURE SPECIFIC SAFETY 
ELEMENTS THAT WILL BE INCLUDED IN THE FINAL DESIGN AT 
THE BRIDGE
EMERGENCY CALL
BUTTON
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
17
PRECEDENT
IMAGES
ELEVATION- E1
ELEVATION- E2
METAL FASCIA
BRICK
BRICK
GLASS
GLASS
BRICK
METAL FASCIA
THE ELEVATOR NODE WILL HOUSE A STANDARD SIZE 
ELEVATOR CAB WITH A GLASS ENCLOSED SHAFT.  
THE CAB IS LARGE ENOUGH TO CARRY 2 BICYCLES.
Elevator Façade Options
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
18
Glass Wall – W2
DOURO STREET ELEVATION
DOURO STREET ELEVATION
WEST BATTERY ELEVATION
WEST BATTERY ELEVATION
GLASS SIDE WALLS 
WITH INTEGRATED 
HANDRAILS
ROOF
OPEN
ROOF
SOLID SIDE WALLS 
WITH INTEGRATED 
HANDRAILS
OPEN
Staircase & Railing Options
Solid Wall – W1
SOUTH STAIR – W 1
NORTH STAIR – W 2
WEST BATTERY ELEVATION
PERSPECTIVE
VIEWS
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
19
Single Color - G1
Multi-Tinted - G2
MULTI‐TINTED GLASS
SINGLE COLOR GLASS
Bridge Deck Façade Treatments Options
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
Roof Treatment Options
20
SECTIONS OPTION
R2
R1CURVED METAL ROOF – R1
FLAT ROOF WITH SKYLIGHTS – R2
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
Roof Art Concepts
21
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
22
NEW ELEVATOR
NEW PLAZA
NEW ELEVATOR
NEW PLAZA
NEW STAIR
NEW STAIR
1 2 3 4 5 7
3
2
4
6 7
1
5
5
NORTH END SOUTH END
Here are images of some options that could be incorporated into the final design concept: 
Landscaping and Streetscaping Options
CYCLING IN  PLAZA PAVEMENTS PATTERNS BIKE STORAGE LED LIGHTING PLANTERS
6
BENCHES
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
23
Timeline & Next Steps
• Deadline for feedback on these materials: January 6, 2017
• Incorporate feedback: Early‐2017
• Continue detailed design work
• Public Drop‐in Event #2: Mid‐2017
• Incorporate feedback: Late‐2017
• Finalize the design for the Project: Late‐2017
• Proceed to construction: 2018
BelleRiverWind
toronto.ca/king‐liberty‐bridgeDecember 8, 2016
Thank You for Attending!
Please let us know what you think 
about this project by completing a 
feedback form.
Paper forms are available at the 
registration table or use the online 
feedback form on our 
web page: 
toronto.ca/king‐liberty‐bridge
Contact us:
Jason Diceman, 
Senior Public Consultation Coordinator, 
Tel: 416‐338‐2830 
jason.diceman@toronto.ca
24

More Related Content

What's hot

Construction of the highline
Construction of the highlineConstruction of the highline
Construction of the highline
turnitover
 
Simmons us 82 fm 989 txk 060909
Simmons   us 82 fm 989 txk 060909Simmons   us 82 fm 989 txk 060909
Simmons us 82 fm 989 txk 060909
Brian Bochner
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
Crosstown TO
 

What's hot (19)

John Street Open House Display Boards
John Street Open House Display BoardsJohn Street Open House Display Boards
John Street Open House Display Boards
 
East Don Trail - Design Concepts
East Don Trail - Design ConceptsEast Don Trail - Design Concepts
East Don Trail - Design Concepts
 
Design Review Panel Presentation - December 2014
Design Review Panel Presentation - December 2014Design Review Panel Presentation - December 2014
Design Review Panel Presentation - December 2014
 
Glen Road Pedestrian Bridge Environmental Assessment Study - PIC #1
Glen Road Pedestrian Bridge Environmental Assessment Study - PIC #1Glen Road Pedestrian Bridge Environmental Assessment Study - PIC #1
Glen Road Pedestrian Bridge Environmental Assessment Study - PIC #1
 
Reimagining yonge_street__pic_3_display_panels
Reimagining yonge_street__pic_3_display_panelsReimagining yonge_street__pic_3_display_panels
Reimagining yonge_street__pic_3_display_panels
 
John Street Corridor Improvements - Stakeholder Meeting Presentation
John Street Corridor Improvements - Stakeholder Meeting PresentationJohn Street Corridor Improvements - Stakeholder Meeting Presentation
John Street Corridor Improvements - Stakeholder Meeting Presentation
 
The Highline
 The Highline The Highline
The Highline
 
Presentation for public information centres
Presentation for public information centresPresentation for public information centres
Presentation for public information centres
 
Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)
 
Construction of the highline
Construction of the highlineConstruction of the highline
Construction of the highline
 
Oakwood Avenue Bump-outs (panels)
Oakwood Avenue Bump-outs (panels)Oakwood Avenue Bump-outs (panels)
Oakwood Avenue Bump-outs (panels)
 
Simmons us 82 fm 989 txk 060909
Simmons   us 82 fm 989 txk 060909Simmons   us 82 fm 989 txk 060909
Simmons us 82 fm 989 txk 060909
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
 
Oakwood Avenue Bump-outs (slides)
Oakwood Avenue Bump-outs (slides)Oakwood Avenue Bump-outs (slides)
Oakwood Avenue Bump-outs (slides)
 
Re imagining yonge street mcea study - pic 2 display panels low res
Re imagining yonge street mcea study - pic 2 display panels low resRe imagining yonge street mcea study - pic 2 display panels low res
Re imagining yonge street mcea study - pic 2 display panels low res
 
Buey Oil Well Permit
Buey Oil Well PermitBuey Oil Well Permit
Buey Oil Well Permit
 
Chaplin slide deck final
Chaplin slide deck finalChaplin slide deck final
Chaplin slide deck final
 
Tantallon tweaks slideshow2 a
Tantallon tweaks slideshow2 aTantallon tweaks slideshow2 a
Tantallon tweaks slideshow2 a
 
REimagining Yonge Street - Public Open House 1 Display Panels [may 25-16]
REimagining Yonge Street - Public Open House 1 Display Panels [may 25-16]REimagining Yonge Street - Public Open House 1 Display Panels [may 25-16]
REimagining Yonge Street - Public Open House 1 Display Panels [may 25-16]
 

Viewers also liked

SEAFARER’S CENTER PEDESTRIAN BRIDGE_PRESENTATION
SEAFARER’S CENTER PEDESTRIAN BRIDGE_PRESENTATIONSEAFARER’S CENTER PEDESTRIAN BRIDGE_PRESENTATION
SEAFARER’S CENTER PEDESTRIAN BRIDGE_PRESENTATION
Maha Al Soufi
 

Viewers also liked (16)

King Street Pilot Public Meeting
King Street Pilot Public MeetingKing Street Pilot Public Meeting
King Street Pilot Public Meeting
 
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
 
SmartTrack Presentation- Toronto Transit Network Planning
SmartTrack Presentation- Toronto Transit Network PlanningSmartTrack Presentation- Toronto Transit Network Planning
SmartTrack Presentation- Toronto Transit Network Planning
 
Design steps of foot bridge , stringer and cross girder
Design steps of foot bridge , stringer and cross girderDesign steps of foot bridge , stringer and cross girder
Design steps of foot bridge , stringer and cross girder
 
Design of Pedestrian Bridge
Design of Pedestrian BridgeDesign of Pedestrian Bridge
Design of Pedestrian Bridge
 
Foot bridge presentation
Foot bridge presentationFoot bridge presentation
Foot bridge presentation
 
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
 
Steeles Bridge EA PIC#2 powerpoint 04_01_2017
Steeles Bridge  EA PIC#2 powerpoint 04_01_2017Steeles Bridge  EA PIC#2 powerpoint 04_01_2017
Steeles Bridge EA PIC#2 powerpoint 04_01_2017
 
Moveable pedestrian bridge over the Göta Älv (Göteborg, Sweden)
Moveable pedestrian bridge over the Göta Älv (Göteborg, Sweden)Moveable pedestrian bridge over the Göta Älv (Göteborg, Sweden)
Moveable pedestrian bridge over the Göta Älv (Göteborg, Sweden)
 
Newington Road Pedestrian Bridge Replacement Project June 2014
Newington Road Pedestrian Bridge Replacement Project June 2014Newington Road Pedestrian Bridge Replacement Project June 2014
Newington Road Pedestrian Bridge Replacement Project June 2014
 
Lawrence Park PIC 3 slides
Lawrence Park PIC 3 slidesLawrence Park PIC 3 slides
Lawrence Park PIC 3 slides
 
SEAFARER’S CENTER PEDESTRIAN BRIDGE_PRESENTATION
SEAFARER’S CENTER PEDESTRIAN BRIDGE_PRESENTATIONSEAFARER’S CENTER PEDESTRIAN BRIDGE_PRESENTATION
SEAFARER’S CENTER PEDESTRIAN BRIDGE_PRESENTATION
 
14 04-09 complete streets overview
14 04-09 complete streets overview14 04-09 complete streets overview
14 04-09 complete streets overview
 
Suggested fine-tuning of bridge and park designs to best activate the Provide...
Suggested fine-tuning of bridge and park designs to best activate the Provide...Suggested fine-tuning of bridge and park designs to best activate the Provide...
Suggested fine-tuning of bridge and park designs to best activate the Provide...
 
Increase retention by 35% and avoid US$2.5 million penalties with a single so...
Increase retention by 35% and avoid US$2.5 million penalties with a single so...Increase retention by 35% and avoid US$2.5 million penalties with a single so...
Increase retention by 35% and avoid US$2.5 million penalties with a single so...
 
Data preprocessing
Data preprocessingData preprocessing
Data preprocessing
 

Similar to King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)

Dave Ruhl Project Portfolio
Dave Ruhl Project PortfolioDave Ruhl Project Portfolio
Dave Ruhl Project Portfolio
Dave Ruhl
 

Similar to King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels) (13)

TxDOT City of El Paso Quarterly Report 031715
TxDOT City of El Paso Quarterly Report 031715TxDOT City of El Paso Quarterly Report 031715
TxDOT City of El Paso Quarterly Report 031715
 
2014 ULI Sustainable Places Downtown Carrollton TOD
2014 ULI Sustainable Places Downtown Carrollton TOD2014 ULI Sustainable Places Downtown Carrollton TOD
2014 ULI Sustainable Places Downtown Carrollton TOD
 
Dave Ruhl Project Portfolio
Dave Ruhl Project PortfolioDave Ruhl Project Portfolio
Dave Ruhl Project Portfolio
 
Portfolio spreads
Portfolio spreadsPortfolio spreads
Portfolio spreads
 
Four Mile Run Joint Task Force Presentation
Four Mile Run Joint Task Force PresentationFour Mile Run Joint Task Force Presentation
Four Mile Run Joint Task Force Presentation
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_
 
Community Forum presentation - 31st January 2017
Community Forum presentation - 31st January 2017Community Forum presentation - 31st January 2017
Community Forum presentation - 31st January 2017
 
Removing Toronto's Expressway One Piece at a Time
Removing Toronto's Expressway One Piece at a TimeRemoving Toronto's Expressway One Piece at a Time
Removing Toronto's Expressway One Piece at a Time
 
Bangor Waterfront Park Plans by Shadley 12-2010
Bangor Waterfront Park Plans by Shadley 12-2010Bangor Waterfront Park Plans by Shadley 12-2010
Bangor Waterfront Park Plans by Shadley 12-2010
 
Six Points Reconfiguration - Community Update June, 2013 (Poster Boards)
Six Points Reconfiguration - Community Update June, 2013 (Poster Boards)Six Points Reconfiguration - Community Update June, 2013 (Poster Boards)
Six Points Reconfiguration - Community Update June, 2013 (Poster Boards)
 
Active18 agm-2013 public
Active18 agm-2013 publicActive18 agm-2013 public
Active18 agm-2013 public
 
Theodor Nicolas Master
Theodor Nicolas MasterTheodor Nicolas Master
Theodor Nicolas Master
 

More from Toronto Public Consultation Unit

More from Toronto Public Consultation Unit (20)

Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
SmartTrack Public Meeting Presentation
SmartTrack Public Meeting PresentationSmartTrack Public Meeting Presentation
SmartTrack Public Meeting Presentation
 
Waterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display PanelsWaterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display Panels
 
Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation
 
Sewer Outfall Project
Sewer Outfall ProjectSewer Outfall Project
Sewer Outfall Project
 
General information
General informationGeneral information
General information
 
Disinfection System
Disinfection SystemDisinfection System
Disinfection System
 
2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information 2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information
 
Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards
 
King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
 
Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
Swc public consultation_pres_170307_final
Swc public consultation_pres_170307_finalSwc public consultation_pres_170307_final
Swc public consultation_pres_170307_final
 
Downsview Water Service Improvement Study Boards
Downsview Water Service Improvement Study BoardsDownsview Water Service Improvement Study Boards
Downsview Water Service Improvement Study Boards
 
Downsview Water Service Improvement Study Maps
Downsview Water Service Improvement Study MapsDownsview Water Service Improvement Study Maps
Downsview Water Service Improvement Study Maps
 
Transit Network Plan Update and Financial Strategy
 Transit Network Plan Update and Financial Strategy Transit Network Plan Update and Financial Strategy
Transit Network Plan Update and Financial Strategy
 
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
 
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
 

Recently uploaded

一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
enbam
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
enbam
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
enbam
 
一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单
一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单
一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单
enbam
 

Recently uploaded (20)

Setting a new path to greater, shared prosperity
Setting a new path to greater, shared prosperitySetting a new path to greater, shared prosperity
Setting a new path to greater, shared prosperity
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
Creating an Effective Veteran Policy in Ukraine
Creating an Effective Veteran Policy in UkraineCreating an Effective Veteran Policy in Ukraine
Creating an Effective Veteran Policy in Ukraine
 
CrossWalksInspirations for Brockville***
CrossWalksInspirations for Brockville***CrossWalksInspirations for Brockville***
CrossWalksInspirations for Brockville***
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
 
OilChange: Big Oil Reality Check May 2024
OilChange: Big Oil Reality Check May 2024OilChange: Big Oil Reality Check May 2024
OilChange: Big Oil Reality Check May 2024
 
PPT Item # 2 -- Announcements Powerpoint
PPT Item # 2 -- Announcements PowerpointPPT Item # 2 -- Announcements Powerpoint
PPT Item # 2 -- Announcements Powerpoint
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 
Elderly Persons Midday Meal Program kurnool
Elderly Persons Midday Meal Program kurnoolElderly Persons Midday Meal Program kurnool
Elderly Persons Midday Meal Program kurnool
 
Hub Design Inspiration Graphics May 24 2024.pdf
Hub Design Inspiration Graphics May 24 2024.pdfHub Design Inspiration Graphics May 24 2024.pdf
Hub Design Inspiration Graphics May 24 2024.pdf
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
PPT Item # 4 - 525 Argo Avenue ARB Case # 926F
PPT Item # 4 - 525 Argo Avenue ARB Case # 926FPPT Item # 4 - 525 Argo Avenue ARB Case # 926F
PPT Item # 4 - 525 Argo Avenue ARB Case # 926F
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
Canadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key SlidesCanadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key Slides
 
07/03/2024 Publiekdomeindag - namiddag
07/03/2024 Publiekdomeindag - namiddag07/03/2024 Publiekdomeindag - namiddag
07/03/2024 Publiekdomeindag - namiddag
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
 
一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单
一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单
一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单
 
Counting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptxCounting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptx
 
How to Save a Place: How to Fund Your Preservation Project
How to Save a Place: How to Fund Your Preservation ProjectHow to Save a Place: How to Fund Your Preservation Project
How to Save a Place: How to Fund Your Preservation Project
 

King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)