Design of a cable stayed bridge between Stigberget and Slottsberget. The new bridge allows bicycle and pedestrian flow across the river and vessels flow along the river. The cross section of all the main elements, the connections and the open mechanism are defined.
2. Location: Constraints and Possibilities
Stigberget
Boat traffic
- Stena Line
- Älvsnabben
- Industrial
- Personal
Can connect
different heights
Clayey soil in the
bottom of the river
Slottsberget Lindholmen
3. Evaluation criteria
Enjoyable to walk across
Beautiful design
Comfortable to walk/stand on
Spectacular opening mechanism
Easy accessible for everyone
Low effort to maintain
High structural and material efficiency
Low disruption of traffic in building phase
Connect to multiple infrastructures
Short opening time
Height of the main span
Easy to build
Low cost to open the bridge
Low cost of non-structural maintenance
Separation of traffic in structure
Sustainable materials
Bridge should be/have:
MoreimportantLessimportant
4. Very high
Risk
High
Moderate
Failure of
auxiliary services
Low Project changes
Fail of opening
mechanism
Very low
Fire
Fail of non-
structural parts
Sabotage
Fail of the
structure
Consequence
Minor Small Moderate Severe Catastrophic
Risk analysis
Very high
Risk
High Project changes
Moderate
Failure of
auxiliary services
Low
Fail of opening
mechanism
Very low
Fail of non-
structural parts
Fire
Ship collision
Sabotage
Fail of the
structure
Consequence
Minor Small Moderate Severe Catastrophic
Doppler Effect Low
Trefoils Moderate
Cobras Moderate - High
the Trefoils
Very high
Risk
Project changes
High
Moderate
Failure of auxiliary
services
Fail of opening
mechanism
Low
Very low
Fail of non-
structural parts
Sabotage
Fire
Fail of the
structure
Consequence
Minor Small Moderate Severe Catastrophic
the Cobras
the Doppler Effect
Risk analysis
5. Cobras Trefoils Doppler Effect
Risk Moderate - High Moderate Low
Enjoyable to walk across Average Good Good
Beautiful design Average Good Good
Comfortable to walk/stand on Good Average Good
Spectacular opening
mechanism
Very Good Good Average
Other design criteria Bad Average Good
- WINNER? WINNER?
Conclusions
11. Structural behaviour
Loads:
5kN/m2 (crowd load) * 1,5
Self-Weight * 1,35
Closed position
Axial Stress:
Max Axial Force:
8200kN on the column and foundations
1200kN on the most critical cable
12. Structural behaviour
Open position
Loads:
5kN/m2 (crowd load) * 1,5
Self-Weight * 1,35
Max Axial Force:
9100kN on the column and foundations
1300kN on the most critical cable
Loads:
5kN/m2 (crowd load) on one arm
Self-Weight on all the arms
Max Bending Moment:
48 400kN on the base of
the tower
Axial Stress: Moment:
13. Buckling of the bridge deck
Dynamic behaviour due to pedestrians
Structural behaviour
14. 1,50 m
0,10 m 0,30 m
0,10 m 4,00 m
0,50 m
3,0 cm
2,0 cm
Bridge deck
Box beam in steel S450
Structural solution
Carbon fibre cables
ϕ 66 mm
Towers in steel S450:
30 metres high
Section - base Section - top
Deflection is dimensioning
- Open position worst case
- Allows for structural redundancy
16. Shear connection
Openable shear connection
Designed to hide the connection
Transmits shear between the two bridge decks
Slender deck important for visual impression
Design intention:
Structural solution
17. Structural solution
Rotation ring
Trunnion carrying
vertical load from pylon
Opening mechanism Gears that drive the opening
Ball bearings –
allows rotation and transfer
force from moment to column
Reinforced concrete support
18. 9100 kN
~10 000 kN
~ 10 000 kN
Foundations of the main towers
Reactions
Strut and tie
for bending
Structural solution
19. Way of production
• Build the foundations and towers
• Build the arms section by section in the open position
• Possible to build from only one place if the bridge can rotate during
construction
20. Functional qualities
Owner’s perspective:User’s perspective:
• Connects different places
and different heights
• Transports people both
across and along the river
• An eventful experience
when opening
• Unique concept which can
attract tourists and city residents
• Quick opening
• A new connection to enhance
public transportation
21. Development of solution
Critical issue:
Deflections in open position
- Worst case is imposed loads on only one arm
Max 400 people
Increase stiffness in cables?
or
Monitor number of
people on bridge?
22. Development of solution
Risk mitigation
• Structural redundancy
• Fire proof coating around carbon fibre cables
• ”Dolphin defence” against ship collision
Dolphins against ship collision
Lanterns for night time alert
Waiting area for ships going upstream
Waiting area for ships
going downstream
Structural redundancy in cables –
Effect from deflection governed
design
23. How many times will the bridge have to open?
During rush hour the
bridge needs to open
every 20 minutes
• Scheduled openings
• Signs to announce next opening
BRIDGE
WILL OPEN IN
13:1413:1313:1213:1113:1013:0913:0813:0713:0613:0513:0413:0313:0213:0113:0012:5912:5812:5712:5612:5612:55
Development of solution
24. Critical review
Disadvantages:Advantages:
• Connects four places instead of two
• An attraction for the city
• Structurally efficient
• Needs to open more frequently
• Expensive
• May be a regulations challenge
to allow people on the bridge
while moving
25. Further investigations
Dynamic loads
Emergency exits:
• Fire
• Fail of opening mechanism
• No electricity
Platforms near the foundations
in case of emergency
Pedestrian traffic may cause large vibrations
Constant cross section makes it vulnerable
to wind induced oscillation
Turbulence
Critical review
In our design process we have used the design intention as our original idea, the general intention of what is important to us when designing this bridge. In a general design task it is usually quite easy to get lost along the way and forget ones original idea. We have therefore chosen to go back to our original design intention which shows what we originally intended for this bridge.
Design Intention
Spectacular event;
Connects the city;
Widens the city centre.
Other characteristics:
Leisure/resting platforms;
Doesn’t disrupt river traffic;
45 seconds to open and 45 seconds to close
fk= 1 863 MPa, E=122 GPa
The forces are calculated for a moment of 55 000 kNm, which with a distance of 5.5 m between the corresponding reaction forces gives a resulting force of about 10 000 kN. In order to do this calculation more correctly, a lot of more information is needed. Crucial information is capacity and detailed structural behavior of the ball bearings and trunnion, and a knowledge of the area required inside the structure for inspection of the machinery.