SlideShare a Scribd company logo
1
Chaplin Station
Open Houses
February 24 & 27, 2014
2
Eglinton Crosstown LRT
 Project
 $4.9 B (2010$), funded by the Province of Ontario
 19 kilometres east-west LRT from Kennedy to
Jane/Black Creek, including 10 kilometers of tunnel
 Connections to Yonge-University-Spadina Subway,
Scarborough RT and GO Stouffville
 Up to 26 stations
3
Tunnelling Works 2014
4
Tunnelling Update
 TBM 1 is well underway with tunnelling; just recently bored
through our west headwall at Keele St.
 TBM 2, a twin machine, has been assembled and is
following closely behind
5
Tunnel Drive Sequence
2. Construct
Extraction Shaft
1. Construct Tunnel
Launch Shaft
6
Tunnel Drive Sequence
Install Jet Grout
Block “Headwalls”
from Surface
Commence Mining
Twin Tunnels
7
Tunnel Drive Sequence
Mine-Through Jet
Grout Blocks
8
Tunnel Drive Sequence
• Excavate Station and
Commence
Removing Concrete
Tunnel Liners
After Tunnel Contract:
•Install Station Sidewall
and Headwall Support of
Excavation
Finally:
•Station Box Fully
Excavated & Tunnel
Lining Removed (Not
shown)
9
Launch Shaft Tunnel Boring Machine
10
Tunnel Drive Works 2013
11
Tunnel Drive Works Current Status
 In 2013 the majority of tunnel works took place between
Black Creek Drive and the vicinity of Allen Road
 In 2014 work continues east of Allen Road
 Crews are starting the construction of headwalls and utility
relocation at future station sites along Eglinton Avenue
West
12
Tunnel Drive Works
 Headwalls: Temporary support walls for future excavation
of the LRT stations.
 Made of concrete and installed to the depth of the future
track level
 Two methods of installation used: Secant Pile Walls, Jet
Grout
 Machinery including drill rigs, grout tanks, diggers and other
equipment
13
Tunnel Drive Works
Secant pile wall : formed by
intersecting concrete piles
Jet grout wall : uses engineered
grout to form wall in situ
14
Jet Grout Headwalls
15
16
Grout Plant for Headwall Construction
Why a grout plant at Chaplin?
Headwalls for Chaplin required
Gilgorm adjacent to work site
Gilgorm to remain open one lane northbound
Allows efficient use of space
Other options examined included Vesta Drive and Eglinton
Gilgorm preferred because of:
reduced property impact
reduced footprint on Eglinton Ave.
17
 The site will be situated on Metrolinx-
owned property and occupy City of
Toronto roadway
 A fence will enclose the site to
demarcate the site from the public
roadway throughout the entire works
 The plant will service headwall
construction for Chaplin Station and
cross-passages at Vesta Dr and
Castle Knock Road
 The site is expected to be in place for
approximately 8-10 months
Grout Plant at Chaplin
18
Grout Plant at Chaplin
Advantages of jet grout
technique for headwall
installation:
Reduce requirement for
extensive utility relocation
Overall construction time
savings
19
Timeline
With appropriate permissions in place Metrolinx’ contractor will:
Begin to set up the grout plant
Install fencing and secure the perimeter
Install grout lines in the roadway
Test works
Begin Chaplin headwall construction works
Chaplin headwall construction is currently scheduled to
commence in March 2014
8-10 months anticipated
Headwall works at Avenue Road and Bathurst are currently
being reviewed
20
Chaplin Work Staging- South Setup
 Work is set up on the south side of Eglinton
 The work zone is separated from the ROW with concrete
barriers and fencing
 Unoccupied traffic lanes remain open on the north side of
Eglinton with one lane in each direction
 Through-traffic southbound on Chaplin at Eglinton will not
be permitted
 Southbound traffic must exit at Eglinton or choose an
alternate route
 Expected duration: Approximately 4 months
21
Chaplin Work Staging- North Setup
 A work site is set up on the north side of Eglinton
 The work zone is separated from the ROW with concrete
barriers and fencing
 Unoccupied traffic lanes remain open on the south side of
Eglinton with one lane in each direction
 Through-traffic northbound on Chaplin at Eglinton will not
be permitted
 Northbound traffic must exit at Eglinton or choose an
alternate route
 Expected duration: Approximately 4 months
 Latimer Avenue is closed to/from Eglinton during this phase
22
Chaplin Station
Plan View
23
Chaplin Station
Preliminary Station Concept
Looking West
24
Chaplin Station
Entrance Locations
Primary Entrance Secondary Entrance
Secondary Entrance
25
Next Steps
 Community Relations will outreach to specific condos and
apartment buildings to raise awareness of the site and
planned works
 Co-ordination with TTC will continue to ensure continued
bus service
 Co-ordination with local Fire Station also continues to
ensure service levels
26
www.metrolinx.com
Thank you

More Related Content

What's hot

Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
Crosstown TO
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
Crosstown TO
 
Caledonia station open house
Caledonia station open houseCaledonia station open house
Caledonia station open house
Crosstown TO
 
Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house
Crosstown TO
 
Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open house
Crosstown TO
 
Mount pleasant station open house
Mount pleasant station open house  Mount pleasant station open house
Mount pleasant station open house
Crosstown TO
 
Keelesdale station open house
Keelesdale station open houseKeelesdale station open house
Keelesdale station open house
Crosstown TO
 
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Crosstown TO
 
Mount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewMount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design Review
Crosstown TO
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
Crosstown TO
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
Crosstown TO
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015
Crosstown TO
 
Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house  Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house
Crosstown TO
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house
Crosstown TO
 
Public Open House - Finch West LRT
Public Open House - Finch West LRTPublic Open House - Finch West LRT
Public Open House - Finch West LRT
Crosstown TO
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
Crosstown TO
 
Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open House
Crosstown TO
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
Crosstown TO
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017
Crosstown TO
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
Crosstown TO
 

What's hot (20)

Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
Caledonia station open house
Caledonia station open houseCaledonia station open house
Caledonia station open house
 
Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house
 
Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open house
 
Mount pleasant station open house
Mount pleasant station open house  Mount pleasant station open house
Mount pleasant station open house
 
Keelesdale station open house
Keelesdale station open houseKeelesdale station open house
Keelesdale station open house
 
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...
 
Mount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewMount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design Review
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015
 
Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house  Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house
 
Public Open House - Finch West LRT
Public Open House - Finch West LRTPublic Open House - Finch West LRT
Public Open House - Finch West LRT
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 
Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open House
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
 

Viewers also liked

Science centre station open house
Science centre station open houseScience centre station open house
Science centre station open house
Crosstown TO
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
Crosstown TO
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
Crosstown TO
 
Imagine Eglinton Drawing Contest
Imagine Eglinton Drawing ContestImagine Eglinton Drawing Contest
Imagine Eglinton Drawing Contest
Crosstown TO
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
Crosstown TO
 
Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown Update
Crosstown TO
 
Chaplin Grout Plant and Headwall Construction
Chaplin Grout Plant and Headwall ConstructionChaplin Grout Plant and Headwall Construction
Chaplin Grout Plant and Headwall Construction
Crosstown TO
 
Station Design Update Meeting: East Open House
Station Design Update Meeting: East Open HouseStation Design Update Meeting: East Open House
Station Design Update Meeting: East Open House
Crosstown TO
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting Presentation
Crosstown TO
 
Cts tradeshow remarks
Cts tradeshow remarksCts tradeshow remarks
Cts tradeshow remarks
Crosstown TO
 
Kennedy Mobility Hub Presentation
Kennedy Mobility Hub PresentationKennedy Mobility Hub Presentation
Kennedy Mobility Hub Presentation
Crosstown TO
 

Viewers also liked (11)

Science centre station open house
Science centre station open houseScience centre station open house
Science centre station open house
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
 
Imagine Eglinton Drawing Contest
Imagine Eglinton Drawing ContestImagine Eglinton Drawing Contest
Imagine Eglinton Drawing Contest
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
 
Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown Update
 
Chaplin Grout Plant and Headwall Construction
Chaplin Grout Plant and Headwall ConstructionChaplin Grout Plant and Headwall Construction
Chaplin Grout Plant and Headwall Construction
 
Station Design Update Meeting: East Open House
Station Design Update Meeting: East Open HouseStation Design Update Meeting: East Open House
Station Design Update Meeting: East Open House
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting Presentation
 
Cts tradeshow remarks
Cts tradeshow remarksCts tradeshow remarks
Cts tradeshow remarks
 
Kennedy Mobility Hub Presentation
Kennedy Mobility Hub PresentationKennedy Mobility Hub Presentation
Kennedy Mobility Hub Presentation
 

Similar to Chaplin slide deck final

Chaplin Grout Plant and Headwall Construction Spring 2014
Chaplin Grout Plant and Headwall Construction Spring 2014Chaplin Grout Plant and Headwall Construction Spring 2014
Chaplin Grout Plant and Headwall Construction Spring 2014
Crosstown TO
 
Eglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House PresentationEglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House Presentation
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO
 
West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Crosstown TO
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
Crosstown TO
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 Slides
Crosstown TO
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5
Crosstown TO
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO
 
Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
Crosstown TO
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Crosstown TO
 

Similar to Chaplin slide deck final (20)

Chaplin Grout Plant and Headwall Construction Spring 2014
Chaplin Grout Plant and Headwall Construction Spring 2014Chaplin Grout Plant and Headwall Construction Spring 2014
Chaplin Grout Plant and Headwall Construction Spring 2014
 
Eglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House PresentationEglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House Presentation
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 Slides
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
 
Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
Crosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
Crosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
Crosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Crosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
Crosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Crosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
Crosstown TO
 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Dr. Vinod Kumar Kanvaria
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
adhitya5119
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
Israel Genealogy Research Association
 
How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17
Celine George
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
Celine George
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 
How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17
Celine George
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
Celine George
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
Priyankaranawat4
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
adhitya5119
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
David Douglas School District
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
amberjdewit93
 
DRUGS AND ITS classification slide share
DRUGS AND ITS classification slide shareDRUGS AND ITS classification slide share
DRUGS AND ITS classification slide share
taiba qazi
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
Dr. Mulla Adam Ali
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
Nguyen Thanh Tu Collection
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
AyyanKhan40
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
Scholarhat
 
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPLAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
RAHUL
 

Recently uploaded (20)

Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
 
How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 
How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
 
DRUGS AND ITS classification slide share
DRUGS AND ITS classification slide shareDRUGS AND ITS classification slide share
DRUGS AND ITS classification slide share
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
 
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPLAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
 

Chaplin slide deck final

  • 2. 2 Eglinton Crosstown LRT  Project  $4.9 B (2010$), funded by the Province of Ontario  19 kilometres east-west LRT from Kennedy to Jane/Black Creek, including 10 kilometers of tunnel  Connections to Yonge-University-Spadina Subway, Scarborough RT and GO Stouffville  Up to 26 stations
  • 4. 4 Tunnelling Update  TBM 1 is well underway with tunnelling; just recently bored through our west headwall at Keele St.  TBM 2, a twin machine, has been assembled and is following closely behind
  • 5. 5 Tunnel Drive Sequence 2. Construct Extraction Shaft 1. Construct Tunnel Launch Shaft
  • 6. 6 Tunnel Drive Sequence Install Jet Grout Block “Headwalls” from Surface Commence Mining Twin Tunnels
  • 8. 8 Tunnel Drive Sequence • Excavate Station and Commence Removing Concrete Tunnel Liners After Tunnel Contract: •Install Station Sidewall and Headwall Support of Excavation Finally: •Station Box Fully Excavated & Tunnel Lining Removed (Not shown)
  • 9. 9 Launch Shaft Tunnel Boring Machine
  • 11. 11 Tunnel Drive Works Current Status  In 2013 the majority of tunnel works took place between Black Creek Drive and the vicinity of Allen Road  In 2014 work continues east of Allen Road  Crews are starting the construction of headwalls and utility relocation at future station sites along Eglinton Avenue West
  • 12. 12 Tunnel Drive Works  Headwalls: Temporary support walls for future excavation of the LRT stations.  Made of concrete and installed to the depth of the future track level  Two methods of installation used: Secant Pile Walls, Jet Grout  Machinery including drill rigs, grout tanks, diggers and other equipment
  • 13. 13 Tunnel Drive Works Secant pile wall : formed by intersecting concrete piles Jet grout wall : uses engineered grout to form wall in situ
  • 15. 15
  • 16. 16 Grout Plant for Headwall Construction Why a grout plant at Chaplin? Headwalls for Chaplin required Gilgorm adjacent to work site Gilgorm to remain open one lane northbound Allows efficient use of space Other options examined included Vesta Drive and Eglinton Gilgorm preferred because of: reduced property impact reduced footprint on Eglinton Ave.
  • 17. 17  The site will be situated on Metrolinx- owned property and occupy City of Toronto roadway  A fence will enclose the site to demarcate the site from the public roadway throughout the entire works  The plant will service headwall construction for Chaplin Station and cross-passages at Vesta Dr and Castle Knock Road  The site is expected to be in place for approximately 8-10 months Grout Plant at Chaplin
  • 18. 18 Grout Plant at Chaplin Advantages of jet grout technique for headwall installation: Reduce requirement for extensive utility relocation Overall construction time savings
  • 19. 19 Timeline With appropriate permissions in place Metrolinx’ contractor will: Begin to set up the grout plant Install fencing and secure the perimeter Install grout lines in the roadway Test works Begin Chaplin headwall construction works Chaplin headwall construction is currently scheduled to commence in March 2014 8-10 months anticipated Headwall works at Avenue Road and Bathurst are currently being reviewed
  • 20. 20 Chaplin Work Staging- South Setup  Work is set up on the south side of Eglinton  The work zone is separated from the ROW with concrete barriers and fencing  Unoccupied traffic lanes remain open on the north side of Eglinton with one lane in each direction  Through-traffic southbound on Chaplin at Eglinton will not be permitted  Southbound traffic must exit at Eglinton or choose an alternate route  Expected duration: Approximately 4 months
  • 21. 21 Chaplin Work Staging- North Setup  A work site is set up on the north side of Eglinton  The work zone is separated from the ROW with concrete barriers and fencing  Unoccupied traffic lanes remain open on the south side of Eglinton with one lane in each direction  Through-traffic northbound on Chaplin at Eglinton will not be permitted  Northbound traffic must exit at Eglinton or choose an alternate route  Expected duration: Approximately 4 months  Latimer Avenue is closed to/from Eglinton during this phase
  • 24. 24 Chaplin Station Entrance Locations Primary Entrance Secondary Entrance Secondary Entrance
  • 25. 25 Next Steps  Community Relations will outreach to specific condos and apartment buildings to raise awareness of the site and planned works  Co-ordination with TTC will continue to ensure continued bus service  Co-ordination with local Fire Station also continues to ensure service levels