SlideShare a Scribd company logo
1
UV
Disinfection
System
Detailed Design
Ashbridges Bay
Treatment Plant
2
• Meeting Objective
• Project Background
• Project Implementation
• Design Criteria
• UV Disinfection Facility
• UV Supplier Selection
• Effluent Discharge Management
• Capital / Project Schedule
Agenda
2
3
Presentation of the UV Disinfection Facility detailed
design prior to Tendering and Construction
Meeting Objective
3
4
Project Background
• Improved ABTP discharge treated effluent
quality
• Discontinue use of the Seawall Gates
• Improved nearshore water quality at ABTP
• Eliminate chlorination by-products during
normal operation
• Eliminate residual chlorine during by-pass
• Increased ABTP process reliability and
operational flexibility
• Connect to the new outfall
4
5
Project Objective
• Design and construct an UV disinfection facility that meets all
regulations
Success Factors
• Elimination of residual chlorine discharge to the lake
• Discontinue the use of the seawall gates
• Improvement of the nearshore water quality
• Meeting EA commitments
Project Implementation
5
6
• Effluent flows
– 818 MLD (rated capacity)
– 2,000 MLD
– 3,300 MLD
• Effluent UV disinfection (normal operation)
• Effluent chlorination / dechlorination (by-pass mode)
Design Criteria
6
7
Project Overview
Seawall
Substation
Upgrades and
New Standby
Generators
Plant Water
Pumping Station
Upgrades
New
Disinfection
Building
New Bypass
Water Tower
Elimination
New Outfall
(by others)
7
8
New Disinfection Building
8
9
Disinfection Building Overview
Architectural 3D
Ground Floor Plan
9
10
Disinfection Building Overview
Architectural 3D
Second Floor Plan
10
11
Disinfection Building Overview
Architectural 3D
Third Floor Plan
11
12
Disinfection Building Overview
• Combination of Green Roof / Cool Roof
• Solar Wall
Green Roof
Architectural 3D
Roof Plan
12
13
UV Facility
UV
Equipment
UV Channel
13
14
Sodium hypochlorite
Sodium bisulfite
Chemical Storage and Dosing System
14
15
Energy Conservation Measures
• Green Roof
• Solar Wall
• Heat recovery to reduce operational cost
• Occupied/ unoccupied control (light and heat)
• VFDs provided to all fans & pumps
• Heat reclaim for domestic water heating
• Ultra high efficiency and high efficiency motors and
lighting
• Mechanical control system linked to ABTP central
computer system
• Environmentally friendly refrigerants in air-
conditioning system
• Variable Refrigerant Flow (VRF) in air-conditioning
system
15
16
UV Equipment Competitive Pre-Selection
Monetary Criteria
• Equipment capital cost
• Facility capital cost
• Operating cost
Non-Monetary Criteria
• Vendor experience
• Performance guarantee
• Service capabilities
• Replacement parts
• Reference facilities
16
17
• Highest score
• Lower energy consumption
• Lower number of lamps
UV Pre-selected Supplier – TrojanUV
Lamp Technology
Number of
Lamps
Required
Power Draw
Low Pressure – High Output 4,720 1,180 kW
Medium Pressure – High Output 1,680 4,300 kW
New Low Pressure – Very High Output 1,408 1,280 kW
17
18
Discharge To Lake 2017 – 2020 (during UV facility
construction)
By-Pass
Disinfection
Existing Outfall
and Seawall Gates
18
19
Discharge to Lake 2020 to 2023 (UV operation during
new outfall construction)
By-Pass
Disinfection
Existing Outfall
and Seawall Gates
UV Disinfection
UV
19
20
Discharge to Lake 2023 (UV and new outfall)
By-Pass
Disinfection
UV Disinfection
UV
New 3,923 MLD
Outfall
20
21
Cost and Project Schedule
Total Project Cost (2019 CAD) $220M
Total Estimated Construction Duration 3 years
2017 2018 2019 2020 2021 2022 2023
100%
Detailed
Design
Start
Construction
UV
Operation
Old Outfall
UV
Operation
New
Outfall
Design Construction Operation
Tender
21
22
Conclusions
• Meeting EA requirements and applicable regulations
• Eliminate effluent chlorination (during normal operation
with UV)
• Improve effluent quality and near shore lake water quality
22
23
Thank you
23

More Related Content

What's hot

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Fairfax County
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Fairfax County
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
Toronto Public Consultation Unit
 
Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation
Fairfax County
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
Fairfax County
 
Land Subdivisions University Course
Land Subdivisions University CourseLand Subdivisions University Course
Land Subdivisions University Course
NettlemanU
 
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Fairfax County
 
Waterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display PanelsWaterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display Panels
Toronto Public Consultation Unit
 
Road Salt Regional Perspective: New York State Success Stories
Road Salt Regional Perspective: New York State Success StoriesRoad Salt Regional Perspective: New York State Success Stories
Road Salt Regional Perspective: New York State Success Stories
Cary Institute of Ecosystem Studies
 
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1
Fairfax County
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
Fairfax County
 
SmartTrack Presentation- Toronto Transit Network Planning
SmartTrack Presentation- Toronto Transit Network PlanningSmartTrack Presentation- Toronto Transit Network Planning
SmartTrack Presentation- Toronto Transit Network Planning
Toronto Public Consultation Unit
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
VDOT Northern Virginia
 
LTCP meeting 11-16-05
LTCP meeting 11-16-05LTCP meeting 11-16-05
LTCP meeting 11-16-05HartTWI
 
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementLong Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Fairfax County
 
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Fairfax County
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectascemiami-dade
 
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationLittle Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station Rehabilitation
Fairfax County
 
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowMark Oberschmidt
 

What's hot (20)

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
 
Land Subdivisions University Course
Land Subdivisions University CourseLand Subdivisions University Course
Land Subdivisions University Course
 
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
 
Waterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display PanelsWaterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display Panels
 
Road Salt Regional Perspective: New York State Success Stories
Road Salt Regional Perspective: New York State Success StoriesRoad Salt Regional Perspective: New York State Success Stories
Road Salt Regional Perspective: New York State Success Stories
 
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
 
SmartTrack Presentation- Toronto Transit Network Planning
SmartTrack Presentation- Toronto Transit Network PlanningSmartTrack Presentation- Toronto Transit Network Planning
SmartTrack Presentation- Toronto Transit Network Planning
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
 
LTCP meeting 11-16-05
LTCP meeting 11-16-05LTCP meeting 11-16-05
LTCP meeting 11-16-05
 
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementLong Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
 
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
 
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationLittle Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station Rehabilitation
 
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
 

Similar to Disinfection System

Global Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyGlobal Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea Technology
Conference_Presentations
 
Overview of Water cycles, wastewater treatment processes, wastewater plant en...
Overview of Water cycles, wastewater treatment processes, wastewater plant en...Overview of Water cycles, wastewater treatment processes, wastewater plant en...
Overview of Water cycles, wastewater treatment processes, wastewater plant en...
AEP Ohio
 
Optimizing Existing Rooftop Unit Energy Efficiency
Optimizing Existing Rooftop Unit Energy EfficiencyOptimizing Existing Rooftop Unit Energy Efficiency
Optimizing Existing Rooftop Unit Energy Efficiency
Center for Energy and Environment
 
Velocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology ForumVelocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology ForumJohn Glenning
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
DeanGarratt
 
The role of AnMBR LEtm Anaerobic MBR in environmental improvements at the Gle...
The role of AnMBR LEtm Anaerobic MBR in environmental improvements at the Gle...The role of AnMBR LEtm Anaerobic MBR in environmental improvements at the Gle...
The role of AnMBR LEtm Anaerobic MBR in environmental improvements at the Gle...
BerghofKevin
 
Capstone turbine corporation e-finity distributed generation
Capstone turbine corporation  e-finity distributed generation Capstone turbine corporation  e-finity distributed generation
Capstone turbine corporation e-finity distributed generation TNenergy
 
Design2Occupancy Services LLP Company Profile
Design2Occupancy Services LLP Company ProfileDesign2Occupancy Services LLP Company Profile
Design2Occupancy Services LLP Company Profile
Ayush Maheshwari
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
DeanDallwitz
 
Parmenter, Brady, Presentation
Parmenter, Brady, PresentationParmenter, Brady, Presentation
Parmenter, Brady, PresentationBrady Parmenter
 
Closer Look At Infrastructure Sustainability - Engineering Perspective - Infr...
Closer Look At Infrastructure Sustainability - Engineering Perspective - Infr...Closer Look At Infrastructure Sustainability - Engineering Perspective - Infr...
Closer Look At Infrastructure Sustainability - Engineering Perspective - Infr...
Loay Ghazaleh MBA, BSc Civil Eng.
 
Utilizing Online TOC Monitoring to Control Industrial Water Quality
Utilizing Online TOC Monitoring to Control Industrial Water QualityUtilizing Online TOC Monitoring to Control Industrial Water Quality
Utilizing Online TOC Monitoring to Control Industrial Water QualityMuhammad Naeem Ashraf
 
Met council Environmental Services - overview of wastewater treatment
Met council Environmental Services - overview of wastewater treatment Met council Environmental Services - overview of wastewater treatment
Met council Environmental Services - overview of wastewater treatment
Amanda Bilek
 
automating coating process
automating coating processautomating coating process
automating coating process
Vu Nguyen
 
Hestia Energy - Levin Igloo Retrofit
Hestia Energy - Levin Igloo Retrofit Hestia Energy - Levin Igloo Retrofit
Hestia Energy - Levin Igloo Retrofit
Peter Zhou
 
case-study-sustainable-mixed-use-development-in-historic-urban-areas (2).pptx
case-study-sustainable-mixed-use-development-in-historic-urban-areas (2).pptxcase-study-sustainable-mixed-use-development-in-historic-urban-areas (2).pptx
case-study-sustainable-mixed-use-development-in-historic-urban-areas (2).pptx
amatulwasey
 
Power-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion PaperPower-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion Paper
Bowen
 
Storm water harvestin_Anamrita khan_2013
Storm water harvestin_Anamrita khan_2013Storm water harvestin_Anamrita khan_2013
Storm water harvestin_Anamrita khan_2013
India Water Portal
 

Similar to Disinfection System (20)

Global Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyGlobal Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea Technology
 
Project review
Project reviewProject review
Project review
 
Overview of Water cycles, wastewater treatment processes, wastewater plant en...
Overview of Water cycles, wastewater treatment processes, wastewater plant en...Overview of Water cycles, wastewater treatment processes, wastewater plant en...
Overview of Water cycles, wastewater treatment processes, wastewater plant en...
 
Optimizing Existing Rooftop Unit Energy Efficiency
Optimizing Existing Rooftop Unit Energy EfficiencyOptimizing Existing Rooftop Unit Energy Efficiency
Optimizing Existing Rooftop Unit Energy Efficiency
 
Velocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology ForumVelocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology Forum
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
 
The role of AnMBR LEtm Anaerobic MBR in environmental improvements at the Gle...
The role of AnMBR LEtm Anaerobic MBR in environmental improvements at the Gle...The role of AnMBR LEtm Anaerobic MBR in environmental improvements at the Gle...
The role of AnMBR LEtm Anaerobic MBR in environmental improvements at the Gle...
 
Capstone turbine corporation e-finity distributed generation
Capstone turbine corporation  e-finity distributed generation Capstone turbine corporation  e-finity distributed generation
Capstone turbine corporation e-finity distributed generation
 
Design2Occupancy Services LLP Company Profile
Design2Occupancy Services LLP Company ProfileDesign2Occupancy Services LLP Company Profile
Design2Occupancy Services LLP Company Profile
 
annalee-1207
annalee-1207annalee-1207
annalee-1207
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
 
Parmenter, Brady, Presentation
Parmenter, Brady, PresentationParmenter, Brady, Presentation
Parmenter, Brady, Presentation
 
Closer Look At Infrastructure Sustainability - Engineering Perspective - Infr...
Closer Look At Infrastructure Sustainability - Engineering Perspective - Infr...Closer Look At Infrastructure Sustainability - Engineering Perspective - Infr...
Closer Look At Infrastructure Sustainability - Engineering Perspective - Infr...
 
Utilizing Online TOC Monitoring to Control Industrial Water Quality
Utilizing Online TOC Monitoring to Control Industrial Water QualityUtilizing Online TOC Monitoring to Control Industrial Water Quality
Utilizing Online TOC Monitoring to Control Industrial Water Quality
 
Met council Environmental Services - overview of wastewater treatment
Met council Environmental Services - overview of wastewater treatment Met council Environmental Services - overview of wastewater treatment
Met council Environmental Services - overview of wastewater treatment
 
automating coating process
automating coating processautomating coating process
automating coating process
 
Hestia Energy - Levin Igloo Retrofit
Hestia Energy - Levin Igloo Retrofit Hestia Energy - Levin Igloo Retrofit
Hestia Energy - Levin Igloo Retrofit
 
case-study-sustainable-mixed-use-development-in-historic-urban-areas (2).pptx
case-study-sustainable-mixed-use-development-in-historic-urban-areas (2).pptxcase-study-sustainable-mixed-use-development-in-historic-urban-areas (2).pptx
case-study-sustainable-mixed-use-development-in-historic-urban-areas (2).pptx
 
Power-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion PaperPower-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion Paper
 
Storm water harvestin_Anamrita khan_2013
Storm water harvestin_Anamrita khan_2013Storm water harvestin_Anamrita khan_2013
Storm water harvestin_Anamrita khan_2013
 

More from Toronto Public Consultation Unit

King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
Toronto Public Consultation Unit
 
Sewer Outfall Project
Sewer Outfall ProjectSewer Outfall Project
Sewer Outfall Project
Toronto Public Consultation Unit
 
General information
General informationGeneral information
2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information 2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information
Toronto Public Consultation Unit
 
Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards
Toronto Public Consultation Unit
 
2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final
Toronto Public Consultation Unit
 
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Toronto Public Consultation Unit
 
Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing
Toronto Public Consultation Unit
 
FG Gardiner New Simcoe Ramp - display boards
FG Gardiner   New Simcoe Ramp - display boardsFG Gardiner   New Simcoe Ramp - display boards
FG Gardiner New Simcoe Ramp - display boards
Toronto Public Consultation Unit
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
Toronto Public Consultation Unit
 
Swc public consultation_pres_170307_final
Swc public consultation_pres_170307_finalSwc public consultation_pres_170307_final
Swc public consultation_pres_170307_final
Toronto Public Consultation Unit
 
King Street Pilot Public Meeting
King Street Pilot Public MeetingKing Street Pilot Public Meeting
King Street Pilot Public Meeting
Toronto Public Consultation Unit
 
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
Toronto Public Consultation Unit
 
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Toronto Public Consultation Unit
 
Downsview Water Service Improvement Study Boards
Downsview Water Service Improvement Study BoardsDownsview Water Service Improvement Study Boards
Downsview Water Service Improvement Study Boards
Toronto Public Consultation Unit
 
Downsview Water Service Improvement Study Maps
Downsview Water Service Improvement Study MapsDownsview Water Service Improvement Study Maps
Downsview Water Service Improvement Study Maps
Toronto Public Consultation Unit
 
Transit Network Plan Update and Financial Strategy
 Transit Network Plan Update and Financial Strategy Transit Network Plan Update and Financial Strategy
Transit Network Plan Update and Financial Strategy
Toronto Public Consultation Unit
 
King-Liberty Pedestrian / Cycling Bridge
King-Liberty Pedestrian / Cycling Bridge King-Liberty Pedestrian / Cycling Bridge
King-Liberty Pedestrian / Cycling Bridge
Toronto Public Consultation Unit
 
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Toronto Public Consultation Unit
 
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Toronto Public Consultation Unit
 

More from Toronto Public Consultation Unit (20)

King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
 
Sewer Outfall Project
Sewer Outfall ProjectSewer Outfall Project
Sewer Outfall Project
 
General information
General informationGeneral information
General information
 
2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information 2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information
 
Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards
 
2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final
 
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
 
Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing
 
FG Gardiner New Simcoe Ramp - display boards
FG Gardiner   New Simcoe Ramp - display boardsFG Gardiner   New Simcoe Ramp - display boards
FG Gardiner New Simcoe Ramp - display boards
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
Swc public consultation_pres_170307_final
Swc public consultation_pres_170307_finalSwc public consultation_pres_170307_final
Swc public consultation_pres_170307_final
 
King Street Pilot Public Meeting
King Street Pilot Public MeetingKing Street Pilot Public Meeting
King Street Pilot Public Meeting
 
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
 
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
 
Downsview Water Service Improvement Study Boards
Downsview Water Service Improvement Study BoardsDownsview Water Service Improvement Study Boards
Downsview Water Service Improvement Study Boards
 
Downsview Water Service Improvement Study Maps
Downsview Water Service Improvement Study MapsDownsview Water Service Improvement Study Maps
Downsview Water Service Improvement Study Maps
 
Transit Network Plan Update and Financial Strategy
 Transit Network Plan Update and Financial Strategy Transit Network Plan Update and Financial Strategy
Transit Network Plan Update and Financial Strategy
 
King-Liberty Pedestrian / Cycling Bridge
King-Liberty Pedestrian / Cycling Bridge King-Liberty Pedestrian / Cycling Bridge
King-Liberty Pedestrian / Cycling Bridge
 
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
 
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
 

Recently uploaded

PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
ahcitycouncil
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
GrantManagementInsti
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
ILC- UK
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
ahcitycouncil
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
ARCResearch
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
ClaudioTebaldi2
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
SERUDS INDIA
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
ahcitycouncil
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
JSchaus & Associates
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
ehbuaw
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Congressional Budget Office
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
850fcj96
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
ehbuaw
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
Antti Rautiainen
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
ahcitycouncil
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
Paul Smith
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
Get Government Grants
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
Mohammed325561
 

Recently uploaded (20)

PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
 

Disinfection System

  • 2. 2 • Meeting Objective • Project Background • Project Implementation • Design Criteria • UV Disinfection Facility • UV Supplier Selection • Effluent Discharge Management • Capital / Project Schedule Agenda 2
  • 3. 3 Presentation of the UV Disinfection Facility detailed design prior to Tendering and Construction Meeting Objective 3
  • 4. 4 Project Background • Improved ABTP discharge treated effluent quality • Discontinue use of the Seawall Gates • Improved nearshore water quality at ABTP • Eliminate chlorination by-products during normal operation • Eliminate residual chlorine during by-pass • Increased ABTP process reliability and operational flexibility • Connect to the new outfall 4
  • 5. 5 Project Objective • Design and construct an UV disinfection facility that meets all regulations Success Factors • Elimination of residual chlorine discharge to the lake • Discontinue the use of the seawall gates • Improvement of the nearshore water quality • Meeting EA commitments Project Implementation 5
  • 6. 6 • Effluent flows – 818 MLD (rated capacity) – 2,000 MLD – 3,300 MLD • Effluent UV disinfection (normal operation) • Effluent chlorination / dechlorination (by-pass mode) Design Criteria 6
  • 7. 7 Project Overview Seawall Substation Upgrades and New Standby Generators Plant Water Pumping Station Upgrades New Disinfection Building New Bypass Water Tower Elimination New Outfall (by others) 7
  • 12. 12 Disinfection Building Overview • Combination of Green Roof / Cool Roof • Solar Wall Green Roof Architectural 3D Roof Plan 12
  • 14. 14 Sodium hypochlorite Sodium bisulfite Chemical Storage and Dosing System 14
  • 15. 15 Energy Conservation Measures • Green Roof • Solar Wall • Heat recovery to reduce operational cost • Occupied/ unoccupied control (light and heat) • VFDs provided to all fans & pumps • Heat reclaim for domestic water heating • Ultra high efficiency and high efficiency motors and lighting • Mechanical control system linked to ABTP central computer system • Environmentally friendly refrigerants in air- conditioning system • Variable Refrigerant Flow (VRF) in air-conditioning system 15
  • 16. 16 UV Equipment Competitive Pre-Selection Monetary Criteria • Equipment capital cost • Facility capital cost • Operating cost Non-Monetary Criteria • Vendor experience • Performance guarantee • Service capabilities • Replacement parts • Reference facilities 16
  • 17. 17 • Highest score • Lower energy consumption • Lower number of lamps UV Pre-selected Supplier – TrojanUV Lamp Technology Number of Lamps Required Power Draw Low Pressure – High Output 4,720 1,180 kW Medium Pressure – High Output 1,680 4,300 kW New Low Pressure – Very High Output 1,408 1,280 kW 17
  • 18. 18 Discharge To Lake 2017 – 2020 (during UV facility construction) By-Pass Disinfection Existing Outfall and Seawall Gates 18
  • 19. 19 Discharge to Lake 2020 to 2023 (UV operation during new outfall construction) By-Pass Disinfection Existing Outfall and Seawall Gates UV Disinfection UV 19
  • 20. 20 Discharge to Lake 2023 (UV and new outfall) By-Pass Disinfection UV Disinfection UV New 3,923 MLD Outfall 20
  • 21. 21 Cost and Project Schedule Total Project Cost (2019 CAD) $220M Total Estimated Construction Duration 3 years 2017 2018 2019 2020 2021 2022 2023 100% Detailed Design Start Construction UV Operation Old Outfall UV Operation New Outfall Design Construction Operation Tender 21
  • 22. 22 Conclusions • Meeting EA requirements and applicable regulations • Eliminate effluent chlorination (during normal operation with UV) • Improve effluent quality and near shore lake water quality 22