2. MEMBERS OF GROUP B
MAYBELLE WANG SZE KHER 0327553
WENDY TEO SIEW YEN 0328242
ERVINNA ANAK ENDELA @ ENDELLA 0327508
AISHATH HUSSAIN 0320429
CHUANG JING 0322934
JACKSON TING SHII HANG 0324326
KONG ZHEN CHUNG 0319528
LAU CHIN SHENG 0317899
LEONG KARR KHEI 0324362
YONG SING YEW 0318766
ELLIOT PANG TIU SENG 0319438
GOH MING HANN WILLIAM 0317949
HAZIM BIN ABDUL AZIZ 0315773
3. Job Title : Proposed 1 Block of 3 Storey Nursing
Home.
BUILDING TO BE ANALYSED
4. NURSING HOME
Client : Synod Diocese Malaysia Barat
Project : Cadangan Pembangunan 1 Blok 3
Tingkat Rumah Kebajikan (“Nursing”)
Location : Lot No. PT. 3720, Jalan Besar, Kg.
Baru Sungai Buloh, Seksyen U19,
40160 Shah Alam, Selangor Darul
Ehsan.
PROJECT INFO
5.
6. • Contract Sum : RM 2,997,700
• Date of Commencement : 14th June 2004
• Date of Completion : 13th December 2005
• Deflect Liability : 18 Months
• LAD
TNB Substation (14th August 2005) RM 1,000 per day
Building Works (13th December 2005) RM 1,000 per day
• Work Programme : 7 days upon the receive of this
letter.
• Period of Interim Certificate : once in a month. Thirty
(30) days from the date of the architects certificate.
• Period of Delay : 3 Months
CONTRACT DETAILS
20. Total Circulation : 639.75m2
Total Ancillary : 459.75m2
Total Usable : 1117.78m2
Total Internal Division : 92.55m2
SUMMARY OF NET FLOOR AREA FROM
GROUND FLOOR TO UPPER FLOOR
29. GROSS FLOOR AREA : m2 TENDER DATE :
Convert unit from BQ to required unit.
E.g.
Concrete given in m2 (Quantity x height of slab)
Reinforcement given in m2 (Quantity x weightage)
Formwork given in m (Quantity x thickness)
30. GROSS FLOOR AREA : m2 TENDER DATE :
Identify the internal door from plan.
Get the total surface area of the
door. (Area measured over frames)
31. 4. Fittings and Furnishings P.C. Sums
39100.00 16.00 - - - Allowed
5. Services
5.A. Sanitary Appliances 79899.98 32.69 495 No. 161.41 - -
5.B. Plumbing Installation 170000.00 69.56 - - - 170000.00
5.C. Refuse Disposal - - - - - -
5.D. Air conditioning and 15000.00 6.14 - Tm3 15000.00
Ventilation System
5.E. Electrical Installation 365000.00 149.35 - - - 365000.00
5.F. Fire Protection Installation 124000.00 50.74 - - - 124000.00
5.G. Lift and Conveyor Installation 120000.00 49.10 - - - 120000.00
5.H. Communication Installation - - - - - -
5.J Special Installation - - - - - -
5.K. Builder's Profit and Attendance - - - - - -
on Services
5.L. Builder's Work in Connection - - - - - -
with Services
Group Element Total : 873899.98 357.57 794000.00
Sub - total excluding External Works, 2340000.00 957.45
Priliminaries and Contingencies
Ironmongeries: RM 33,100
Signages: RM 6,000
32. 4. Fittings and Furnishings P.C. Sums
39100.00 16.00 - - - Allowed
5. Services
5.A. Sanitary Appliances 79899.98 32.69 495 No. 161.41 - -
5.B. Plumbing Installation 170000.00 69.56 - - - 170000.00
5.C. Refuse Disposal - - - - - -
5.D. Air conditioning and 15000.00 6.14 - Tm3 15000.00
Ventilation System
5.E. Electrical Installation 365000.00 149.35 - - - 365000.00
5.F. Fire Protection Installation 124000.00 50.74 - - - 124000.00
5.G. Lift and Conveyor Installation 120000.00 49.10 - - - 120000.00
5.H. Communication Installation - - - - - -
5.J Special Installation - - - - - -
5.K. Builder's Profit and Attendance - - - - - -
on Services
5.L. Builder's Work in Connection - - - - - -
with Services
Group Element Total : 873899.98 357.57 794000.00
Sub - total excluding External Works, 2340000.00 957.45
Priliminaries and Contingencies
Extracted from Bill No.3-Building Works
Extracted from items under P.C Sum Prices for services only under P.C Sum
33. 6. External Works
6.A. Site Work 119169.50 48.76
6.B. Drainage 167744.50 68.64
6.C. External Services 17086.00 6.99
6.D. Ancillary Buildings 7000.00 2.86
6.E. Recreational Facilities - -
Group Element Total : 311000.00 127.25
Preliminaries 141000.00 57.69
TOTAL ( less
Contingencies ) 2792000.00
•Exclude Dayworks Bill total RM35700.00
•Exclude Provisional Sum for future
expansion of addition floor total RM 20000.00
Amount of items categorized under site
works + Landscaping (P.C Sum)
Amount of items categorized under
drainage + Septic tank & pump sump (P.C
Sum)
Extracted from Contract Bill
37. The Purpose of Form 3
It describes the various components in each
element including the types and quality of
material used
This form provides a brief picture of the building
standards and quality and this information is
important for cost comparison purposes