1. MINISTRY OF PUBLIC WORK AND PUBLIC HOUSING
DIRECTORATE GENERAL OF HOUSING PROVISION
FEBRUARY 2016
KEMAYORAN
ATHLETE VILLAGES
TOWARDS ASIAN GAMES 2018
3. A. Kemayoran Athlete Villages
ZONE D10
Tower : 7 (24 & 32 lt)
Unit : 5.594
Spacious : 333.700 m2
Capacity : 11.188 persons
Build by : PUPR
ZONE C2
Tower : 3 (18 & 24 lt)
Unit : 1.930
Spacious : 135.000 m2
Capacity : 3.860 persons
Build by : PUPR
PROGRESS
• Procurement method: Design and Build
• Pre Qualification bidding Announcement January 12th 2016
• The entire contract is expected to be completed on March 9th 2016
• Construction will be completed by October 2017
ZONE C3
Tower : 5 (22 & 24 lt)
Unit : 3.969 (T.36)
Spacious : 80.200 m2
Capacity : 7.938 persons
Build by : Perumnas
TOTAL
Tower : 15
Unit : 11.493
Spacious : 611.612 m2
Capacity : 22.986 persons
Build by : PUPR and Perumnas
• The development of Athlete Village
consists of the buldings,
surrounding infrstructure and
utilities
4. A. Wisma Atlet Kemayoran
BLOK D10
Tower : 7 (24 & 32 lt)
Unit : 5.594
Luas : 333.700 m2
Penghuni : 11.188
Pelaksana : PUPR
BLOK C2
Tower : 3 (18 & 24 lt)
Unit : 1.930
Luas : 135.000 m2
Penghuni : 3.860
Pelaksana : PUPR
PROGRES PERSIAPAN
PEMBANGUNAN
• Sistem pengadaan Design and Build
• Pengumuman pra-kualifikasi lelang
tanggal 12 Januari 2016.
• Rencana kontrak tanggal 9 Maret 2016
• Rencana selesai konstruksi ≤ Oktober 2017
• Bangunan Wisma Atlet akan
dilaksanakan termasuk dengan penataan
lingkungannya.
BLOK C3
Tower : 5 (22 & 24 lt)
Unit : 3.969 (T.36)
Luas : 80.200 m2
Penghuni : 7.938
Pelaksana : Perumnas
TOTAL
Tower : 15
Unit : 11.493
Luas : 611.612 m2
Penghuni : 22.986
Pelaksana : PUPR dan
Perumnas
5. Zone Costructed By
Total Building
Area
Quantity of
Tower
Quantity of
Unit
Quantity of
Accupants
C2
Ministry of Public
Work and Public
Housing
135.000 3 1.930 3.860
C3 PERUMNAS 80.200 5 3.969 7.938
D10
Ministry of Public
Work and Public
Housing
333.700 7 5.594 11.188
Total 15 11.493 22.986
CAPACITY OF KEMAYORAN ATHLETE VILLAGE
5
*) note: 1 (one) unit occupied by 2 (two) persons
8. Athletes Village
Media Village
Block C2 & C3
Media Village
Block D10
Athletes Village
JIExpo
Block C2 & C3
Media Village
Block D10
Athletes Village
JIExpo
14. ATHLETES VILLAGE – D10
TRANSPORTATION
ZONE
FLAG PLAZA
HOSPITAL
RESIDENTIAL
ZONE
Recreation Park
750 seats
750 seats
750 seats
750 seats
DINNING HALL
On 3rd floor Open Space
(total 1500 seats)
750 seats
750 seats
Service
Access
Service
Access
Service
Access
DINNING HALL
On 3rd floor Open
Space
(total 3000 seats)
15. TRANSPORT
ZONE
FLAGS PLAZA RESIDENTIAL
ZONE
Rumah Sakit
(eksisting)
Sekolah Jubilee
(eksisting)
International / Transportation Zone
Meminjam sebagian lahan Rumah Sakit sbg Transport Zone
Halte
Busway
Angkot
LRT
16. +2.00
+2.00
+1.00
±0.00+2.00
+1.00
MESJID
LOKASI WTP
-4.00
TK & SD
SEKOLAH
RS MITRA KEMAYORAN
(eksisting)
SEKOLAH JUBILEE
(eksisting)
+4.00
+5.00
+6.00
+8.00
+3.00
±0.00
-1.00
-2.00
-3.00
POS DAMKAR
KELURAHAN
4.00
P L A Z A
±0.00
STASIUN LRT
+0.50
RAK SEPEDA
SHOWERS
GROUND TANK
LOBBY
±0.00
TOKO / WARUNG
±0.00
TOKO / WARUNG
±0.00
LIFT LOBBY
±0.00
TOKO / WARUNG
±0.00
SERVICE DOCK
-0.15
RAK SEPEDA
-0.15
SHOWERS
-0.05
TAMAN
-0.15
PARKIR SEPEDA
-0.15
AREA DUDUK
-0.30
AREA DUDUK
PARKIR SEPEDA MOTOR
-0.15
PARKIR MOBIL
+1.50
SERVICE DOCK
-0.15
SERVICE DOCK
-0.15
PARKIR MOBIL
+1.50
PARKIR SEPEDA MOTOR
-0.15
TOKO / WARUNG
±0.00
PARKIR SEPEDA
-0.15
TOKO / WARUNG
±0.00
TOKO / WARUNG
±0.00
TAMAN
-0.15
AREA DUDUK
-0.30
AREA DUDUK
LOBBY
±0.00
-0.15
DROP-OFF
SERVICE DOCK
-0.15
SERVICE DOCK
-0.15
RAK SEPEDA
-0.15
RAK SEPEDA
-0.15
SHOWERS
-0.05
SHOWERS
-0.05
LOBBY
±0.00
-0.15
DROP-OFF
PLAZA INTERNAL
PARKIR MOBIL
+1.50
PARKIR SEPEDA MOTOR
-0.15
TOKO / WARUNG
±0.00
TOKO / WARUNG
±0.00
TOKO / WARUNG
±0.00
LIFT LOBBY
±0.00
LIFT LOBBY
±0.00
MEP
Kotak Surat
MEP
Kotak Surat
MEP
Kotak Surat
TOKO / WARUNG
±0.00
TOKO / WARUNG
±0.00
TOKO / WARUNG
±0.00
PARKIR SEPEDA
-0.15
PARKIR SEPEDA
-0.15
SERVICE DOCK
-0.15
SERVICE DOCK
-0.15
PARKIR MOBIL
+1.50
PARKIR SEPEDA MOTOR
-0.15
LOBBY
±0.00
-0.15
DROP-OFF
LIFT LOBBY
±0.00
MEP
Kotak Surat
TAMAN
-0.15
PLAZA INTERNAL
TOKO / WARUNG
±0.00
TOKO / WARUNG
±0.00
TOKO / WARUNG
±0.00
TOKO / WARUNG
±0.00
TOKO / WARUNG
±0.00
TOKO / WARUNG
±0.00
PARKIR SEPEDA
-0.15
PARKIR SEPEDA
-0.15
TAMAN
-0.15
TAMAN
-0.15
LOBBY
±0.00
-0.15
DROP-OFF
SERVICE DOCK
-0.15
RAK SEPEDA
-0.15
SHOWERS
-0.05
RAK SEPEDA
-0.15
LOBBY
±0.00
-0.15
DROP-OFF
SERVICE DOCK
-0.15
SERVICE DOCK
-0.15
SERVICE DOCK
-0.15
LIFT LOBBY
±0.00
MEP
Kotak Surat
LIFT LOBBY
±0.00
MEP
Kotak Surat
PARKIR MOBIL
+1.50
PARKIR SEPEDA MOTOR
-0.15
PARKIR SEPEDA MOTOR
-0.15
PARKIR MOBIL
+1.50
LAGOON
KOLAM HIAS
R. PLN
TRAFO
PDTR
PDTM
CAP BANK
R. PLN
TRAFO
PDTR
PDTM
CAP BANK
R. PLN
TRAFO
PDTR
PDTM
CAP BANK
TRAFO
PDTR
PDTM
CAP BANK
R.PANEL Tower 1 & 2
R.PANEL Tower 3 & 4
R.PANEL Tower 5 & 6
R.PANEL Tower 7
R.KONTROL
±0.00
FCC
±0.00
FCC
±0.00
FCC
±0.00
FCC
±0.00
FCC
±0.00
FCC
±0.00
FCC
±0.00
-0.15
DROP-OFF
TRANSPORT
ZONE
25. APR-DES
1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 5 6 7 8 9 10 11 12
PROCUREMENT
a Pre Qualification Announcement
b Pre Qualification Evaluation
c Procurement
d Procurement selected
e Signing contract
CONSTRUCTION
a 18 Floor Building
b 24 Floor Building
c 32 Floor Building
2017
2016
ACTIVITIESNO
MARETFEBRUARIJANUARI
SCHEDULE
• Pre Qualification Announcement : January 12th 2016
Signing contract : March 9th 2016
Ground Breaking : March 15th 2016
PHO 18 floor,
MAY 2017
PHO 24 floor,
JULY 2017
PHO 32 floor,
OCT 2017
• Construction goals
18 Floor Building : May 2017 (14th
month)
24 Floor Building : July 2017 (16th
month)
32 Floor Building : October 2017 (18 month)
NO ACTIVITIES 2016
1 2 3 4 5 6 7 8 9 10 11 12
PROCUREMENT
a Procurement Process
b Signing Contract
CONSTRUCTION
5 floor Building
A. Kemayoran
B. Jakabaring
• 3 (three) tower already built on 2015
• Procurement process of 2 (two) remaining
tower on 2016
• Signing contract : February 11th 2016
• Construction time (8 month) : October 2016
26. APR-DES
1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 5 6 7 8 9 10 11 12
PELELANGAN
a Pengumuman PQ
b Evaluasi PQ dan Penetapan
c Pemilihan
d Penetapan Pemenang
e Penandatanganan Kontrak
PELAKSANAAN KONSTRUKSI
a Bangunan Rusun (Wisma Atlet) 18 lantai
b Bangunan Rusun (Wisma Atlet) 24 lantai
c Bangunan Rusun (Wisma Atlet) 32 lantai
2017
2016
KEGIATANNO
MARETFEBRUARIJANUARI
JADWAL PELAKSANAAN
• Pengumuman Pra-Kualifikasi (PQ) : 12 Januari 2016
Penandatanganan Kontrak : 9 Maret 2016
Ground Breaking : 15 Maret 2016
PHO 18 lantai,
MEI 2017
PHO 24 lantai,
JULI 2017
PHO 32 lantai,
OKT 2017
• Target Penyelesaian
Bangunan 18 lantai : Mei 2017 (14 bulan)
Bangunan 24 lantai : Juli 2017 (16 bulan)
Bangunan 32 lantai : Oktober 2017 (18bulan)
A. Kemayoran
B. Jakabaring
• Rusun Wisma Atlet telah terbangun:
3 (tiga) tower TA. 2015
• Proses Lelang 2 (dua) tower TA. 2016
Jan-Feb 2016
• Tandatangan Kontrak): 11 Februari 2016
• Konstruksi (8 bulan) : Oktober 2016
NO KEGIATAN 2016
1 2 3 4 5 6 7 8 9 10 11 12
PELELANGAN (2 tower) TA.2016
a Proses Pelelangan
b Penandatanganan Kontrak
PELAKSANAAN KONSTRUKSI
Bangunan Rusun (Wisma Atlet) 5 lantai