SlideShare a Scribd company logo
1 of 105
Download to read offline
ITEM 1.11
A PRELIMINARIES/GENERAL
CONDITIONS
A40 Contractor's general cost
items: Management and staff
Site administrative staff
Provide general site
supervision/administration
1 Project Manager; say 2
days/week for 14 weeks with
additional 2 days for
completion & handover 6.00 week 6000.00 0.00 0.00 0.00 0.00 0.00 600.00 218.64 1136.44 6,818.64
2 Labourer for manual
unloading of materials 10.00 week 4000.00 0.00 0.00 0.00 0.00 0.00 400.00 145.70 454.57 4,545.70
Subtotal for A ... 10000.00 0.00 0.00 0.00 0.00 0.00 1000.00 364.34 11,364.34
A PRELIMINARIES/GENERAL
CONDITIONS
A41 Contractor's general cost
items: Site accommodation
Temporary offices and the like
Hire of temporary
accommodation
3 Portaloo hire 14.00 nr/wk 0.00 0.00 77.00 0.00 0.00 0.00 7.70 2.80 6.25 87.50
Subtotal for A ... 0.00 0.00 77.00 0.00 0.00 0.00 7.70 2.80 87.50
Total for Item 1.11 10000.00 0.00 77.00 0.00 0.00 0.00 1007.70 367.14 11,451.84
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 1
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 1.23
Z PC SUMS
PC Sums associated with the
project
4 provide health & safety site
signage item 0.00 0.00 0.00 0.00 0.00 200.00 20.00 7.29 227.29 227.29
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 200.00 20.00 7.29 227.29
Total for Item 1.23 0.00 0.00 0.00 0.00 0.00 200.00 20.00 7.29 227.29
ITEM 1.27
A PRELIMINARIES/GENERAL
CONDITIONS
A44 Contractor's general cost
items: Temporary works
Scaffolding up to 10m high
Independent scaffolding
5 Erect and subsequently
dismantle 99.17 m2
0.00 0.00 0.00 0.00 1361.60 0.00 135.86 49.59 15.60 1,547.05
Subtotal for A ... 0.00 0.00 0.00 0.00 1361.60 0.00 135.86 49.59 1,547.05
Total for Item 1.27 0.00 0.00 0.00 0.00 1361.60 0.00 135.86 49.59 1,547.05
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 2
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 1.36
A PRELIMINARIES/GENERAL
CONDITIONS
A42 Contractor's general cost
items: Services and facilities
Provide the following services
and facilities
Rubbish disposal
6 Skips 2.00 nr 0.00 0.00 420.00 0.00 0.00 0.00 42.00 15.30 238.65 477.30
Subtotal for A ... 0.00 0.00 420.00 0.00 0.00 0.00 42.00 15.30 477.30
Total for Item 1.36 0.00 0.00 420.00 0.00 0.00 0.00 42.00 15.30 477.30
ITEM 2.1
Z PC SUMS
PC Sums associated with the
project
7 mechanical & electrical
disconnections & removals; no
details on survey drawings item 0.00 0.00 0.00 0.00 0.00 500.00 50.00 18.22 568.22 568.22
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 500.00 50.00 18.22 568.22
Total for Item 2.1 0.00 0.00 0.00 0.00 0.00 500.00 50.00 18.22 568.22
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 3
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 2.2
C EXISTING
SITE/BUILDINGS/SERVICES
C90 Alterations - spot items
Temporary screens
softwood framing with plywood
and polythene to one side only
8 clear away on completion of
works 4.66 m2
113.84 66.82 0.00 0.00 0.00 0.00 18.08 6.57 44.06 205.32
Subtotal for C Existing ... 113.84 66.82 0.00 0.00 0.00 0.00 18.08 6.57 205.32
Total for Item 2.2 113.84 66.82 0.00 0.00 0.00 0.00 18.08 6.57 205.32
ITEM 2.4
C EXISTING
SITE/BUILDINGS/SERVICES
C20 Demolition
Disconnect redundant services
and demolish individual
structures to
ground level; grub out slab and
foundations
Dispose of spoil off site;
disposal costs included within
rates
9 structure not exceeding 50
m3 19.33 m3
593.82 0.00 594.01 0.00 0.00 0.00 118.88 43.30 69.84 1,350.01
Subtotal for C Existing ... 593.82 0.00 594.01 0.00 0.00 0.00 118.88 43.30 1,350.01
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 4
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
Z PC SUMS
PC Sums associated with the
project
10 lift and salvage all paving within
the area of the new build; no
details on survey drawing item 0.00 0.00 0.00 0.00 0.00 125.00 12.50 4.55 142.05 142.05
11 cutting back vegetation to
facilitate access for extension;
no details on survey drawing item 0.00 0.00 0.00 0.00 0.00 335.00 33.50 12.21 380.71 380.71
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 460.00 46.00 16.76 522.76
Total for Item 2.4 593.82 0.00 594.01 0.00 0.00 460.00 164.88 60.06 1,872.77
ITEM 2.5
Z PC SUMS
PC Sums associated with the
project
12 strip out existing kitchen
units/worktops and dispose of
off-site; no details on survey
drawing item 0.00 0.00 0.00 0.00 0.00 335.00 33.50 12.21 380.71 380.71
13 provide temporary covering to
roof structure and protection to
floor coverings item 0.00 0.00 0.00 0.00 0.00 200.00 20.00 7.29 227.29 227.29
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 535.00 53.50 19.50 608.00
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 5
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
C EXISTING
SITE/BUILDINGS/SERVICES
C20 Demolition
Demolishing parts of concrete
structures
Plain concrete beds
14 150 mm thick 11.12 m2
161.68 0.00 157.57 0.00 0.00 0.00 31.91 11.68 32.63 362.85
C90 Alterations - spot items
Remove finishings
Floors
15 linoleum 11.12 m2
21.68 0.00 13.34 0.00 0.00 0.00 3.56 1.33 3.59 39.92
C20 Demolition
Pulling down - including removal
of debris
Demolish external brickwork
walls in cement mortar;
disposal of
debris off-site
16 2 x 102.5 mm thick skins
forming cavity wall 10.61 m2
336.12 0.00 133.69 0.00 0.00 0.00 47.00 17.08 50.32 533.90
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 6
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
C EXISTING
continued ...
C90 Alterations - spot items
Removing fittings and fixtures
Doors including frame;
dispose of debris off-site or set
aside for re-use
17 single door 4.00 nr 47.76 0.00 8.40 0.00 0.00 0.00 5.60 2.04 15.95 63.80
Windows; dispose of debris
off-site or set aside for re-use
18 casement window 1.15 m2
22.46 0.00 2.42 0.00 0.00 0.00 2.48 0.91 24.58 28.27
Removing plumbing and
engineering installations
Sanitary fittings, including
capping off service and waste
pipes and
bringing forward services
19 WC 1.00 nr 85.37 28.63 6.00 0.00 0.00 0.00 12.00 4.37 136.37 136.37
20 wash hand basin 1.00 nr 4.34 0.00 28.00 0.00 0.00 0.00 3.23 1.18 36.75 36.75
Remove finishings
Ceilings
21 plasterboard 2.31 m2
10.03 0.00 2.77 0.00 0.00 0.00 1.27 0.46 6.29 14.53
Walls, without backing
22 wallpaper 9.31 m2
17.13 0.00 2.79 0.00 0.00 0.00 1.96 0.74 2.43 22.62
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 7
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
C EXISTING
continued ...
C90 Alterations - continued ...
Coverings
Stripping and repairs to slate
and tile roofs
23 plain or interlocking tiles;
dispose of debris off-site 21.37 m2
166.90 0.00 12.82 0.00 0.00 0.00 17.95 6.62 9.56 204.30
Subtotal for C Existing ... 873.47 28.63 367.80 0.00 0.00 0.00 126.96 46.41 1,443.31
Total for Item 2.5 873.47 28.63 367.80 0.00 0.00 535.00 180.46 65.91 2,051.31
ITEM 3.1
R DISPOSAL SYSTEMS
R12 Drainage below ground
Excavation by machine
Trenches for drain pipes not
exceeding 200 mm nominal
size,
grading bottoms, earthwork
support and backfilling with
excavated
material; average depth
24 0.75 m 7.65 m 63.11 0.00 20.20 0.00 0.00 0.00 8.34 3.06 12.38 94.71
25 1.00 m 10.70 m 181.26 0.00 58.64 0.00 0.00 0.00 23.97 8.77 25.48 272.64
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 8
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
R DISPOSAL continued ...
R12 Drainage continued ...
Disposal of material arising from
drainage excavations
Excavated material; bulking
factor 1.25
26 loaded by hand from spoil
heaps 3.10 m3
55.49 0.00 93.00 0.00 0.00 0.00 14.85 5.43 54.44 168.76
Imported granular material
150 mm beds and side filling
to half height of pipes
Unplasticised PVC pipes and
fittings to BS 4660
110 mm pipes
27 in trenches 18.35 m 55.78 94.32 0.00 0.00 0.00 0.00 15.05 5.51 9.30 170.66
Extra for
28 long radius bends 2.00 nr 5.36 22.48 0.00 0.00 0.00 0.00 2.78 1.02 15.82 31.64
29 single junction 1.00 nr 3.75 16.43 0.00 0.00 0.00 0.00 2.02 0.74 22.94 22.94
30 slip coupler 3.00 nr 4.83 8.55 0.00 0.00 0.00 0.00 1.35 0.48 5.07 15.21
Accessories
31 back inlet bottle gulley 1.00 nr 29.50 46.38 0.00 0.00 0.00 0.00 7.59 2.76 86.23 86.23
32 bottle gulley 1.00 nr 29.50 32.02 0.00 0.00 0.00 0.00 6.15 2.24 69.91 69.91
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 9
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
R DISPOSAL continued ...
R12 Drainage continued ...
Testing drains
Water test
33 100 mm drains 18.35 m 22.94 0.00 0.00 0.00 0.00 0.00 2.39 0.92 1.43 26.24
Subtotal for R Disposal Systems 451.52 220.18 171.84 0.00 0.00 0.00 84.49 30.93 958.94
Total for Item 3.1 451.52 220.18 171.84 0.00 0.00 0.00 84.49 30.93 958.94
ITEM 3.7
Manholes
Unplasticised PVC inspection
chambers 450 mm diameter;
set in cement mortar 1:3,
depth to invert
34 1035 mm 1.00 nr 33.08 148.09 0.00 0.00 0.00 0.00 18.12 6.60 205.89 205.89
Total for Item 3.7 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 205.89
ITEM 3.8
Surface drainage systems
ACO Drain K100 channel with
galvanised steel lockable
grating
35 set in gound, bedded and
haunched in concrete 7.68 m 104.52 204.98 0.00 0.00 0.00 0.00 30.95 11.29 45.80 351.74
36 extra for end cap 2.00 nr 2.10 8.42 0.00 0.00 0.00 0.00 1.06 0.38 5.98 11.96
Total for Item 3.8 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 363.70
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 10
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 3.9
Soakaways
Modular soakaway crates
37 aquavoid light duty
soakaway crates 1.00 m3
44.70 172.50 0.00 0.00 0.00 0.00 21.72 7.91 246.83 246.83
Total for Item 3.9 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 246.83
ITEM 4.1
D20 Excavating and filling
Excavating by machine
Trenches, width over 0.30 m,
maximum depth not
exceeding
38 1.00 m 8.63 m3
185.80 0.00 60.67 0.00 0.00 0.00 24.68 8.98 32.46 280.13
Disposal
Off site to tip average 15 km
from site
39 loaded by hand from spoil
heaps 10.78 m3
192.96 0.00 323.40 0.00 0.00 0.00 51.64 18.76 54.43 586.76
Surface treatments
Compacting
40 bottom of excavation 12.33 m2
5.30 0.00 1.36 0.00 0.00 0.00 0.62 0.25 0.61 7.52
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 11
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
E IN SITU CONCRETE/LARGE
PRECAST CONCRETE
E10 Mixing/casting/curing
in-situ concrete
Ready mixed concrete
Plain in situ concrete 1:2:4 -
20 mm aggregate
41 foundations 7.71 m3
140.63 793.82 0.00 0.00 0.00 0.00 93.45 34.08 137.74 1,061.98
E41 Worked finishes/Cutting to
in situ concrete
Worked finishes
Tamping by mechanical
means
42 level 15.41 m2
10.02 0.00 2.62 0.00 0.00 0.00 1.23 0.46 0.93 14.33
Subtotal for E in Situ ... 719.11 1327.81 388.05 0.00 0.00 0.00 243.47 88.71 1,950.72
Total for Item 4.1 719.11 1327.81 388.05 0.00 0.00 0.00 243.47 88.71 1,950.72
ITEM 4.5
D20 Excavating and filling
Excavating by machine
To reduce levels, maximum
depth not exceeding
43 0.25 m 0.09 m3
1.94 0.00 0.63 0.00 0.00 0.00 0.26 0.09 32.42 2.92
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 12
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 4.5 continued ...
D20 Excavating continued ...
Disposal
Off site to tip average 15 km
from site
44 loaded by hand from spoil
heaps 0.11 m3
1.97 0.00 3.30 0.00 0.00 0.00 0.53 0.19 54.42 5.99
Surface treatments
Compacting
45 bottom of excavation 0.71 m2
0.31 0.00 0.08 0.00 0.00 0.00 0.04 0.01 0.60 0.43
E IN SITU CONCRETE/LARGE
PRECAST CONCRETE
E10 Mixing/casting/curing
in-situ concrete
Ready mixed concrete
46 beds, thickness not
exceeding 150 mm 0.09 m3
1.64 9.35 0.00 0.00 0.00 0.00 1.10 0.40 138.84 12.50
E41 Worked finishes/Cutting to
in situ concrete
Worked finishes
Tamping by mechanical
means
47 level 0.60 m2
0.39 0.00 0.10 0.00 0.00 0.00 0.05 0.02 0.93 0.56
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 13
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
E IN SITU CONCRETE/LARGE
PRECAST continued ...
E41 Worked finishes/Cutting to
in situ concrete continued ...
Worked finishes continued ...
Trowelling
48 level 0.60 m2
2.02 0.00 0.00 0.00 0.00 0.00 0.20 0.07 3.82 2.29
Subtotal for E in Situ ... 8.27 9.35 4.11 0.00 0.00 0.00 2.18 0.78 24.69
Total for Item 4.5 8.27 9.35 4.11 0.00 0.00 0.00 2.18 0.78 24.69
ITEM 5.1
D20 Excavating and filling
Excavating by machine
To reduce levels, maximum
depth not exceeding
49 1.00 m 12.97 m3
279.24 0.00 91.18 0.00 0.00 0.00 37.09 13.49 32.46 421.01
Disposal
Off site to tip average 15 km
from site
50 loaded by hand from spoil
heaps 16.21 m3
290.16 0.00 486.30 0.00 0.00 0.00 77.65 28.37 54.44 882.47
Surface treatments
Compacting
51 bottom of excavation 43.22 m2
18.58 0.00 4.75 0.00 0.00 0.00 2.16 0.86 0.61 26.36
Total for Item 5.1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,329.84
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 14
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 5.3 - 5.7
D20 Excavating and filling
Filling to excavations
Imported MOT Type 1 material
52 not exceeding 0.25 m 4.89 m3
81.71 207.34 8.26 0.00 0.00 0.00 29.73 10.81 69.09 337.85
Imported sand
53 not exceeding 0.25 m 0.98 m3
16.38 33.01 0.00 0.00 0.00 0.00 4.94 1.80 57.27 56.12
Surface treatments
Compacting
54 surface of filling 32.59 m2
14.01 0.00 3.58 0.00 0.00 0.00 1.63 0.65 0.61 19.88
J WATERPROOFING
J40 Flexible sheet tanking/
damp proof membranes
Tanking and damp proofing
Polythene medium weight
sheet underlay lapped 150
mm at joints
55 horizontally 44.50 m2
48.51 17.36 0.00 0.00 0.00 0.00 6.68 2.23 1.68 74.76
Subtotal for J Waterproofing 748.59 257.71 594.07 0.00 0.00 0.00 159.88 58.21 488.61
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 15
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
E IN SITU CONCRETE/LARGE
PRECAST CONCRETE
E10 Mixing/casting/curing
in-situ concrete
Ready mixed concrete
Plain in situ concrete 1:2:4 -
20 mm aggregate
56 slabs, thickness not
exceeding 150 mm 4.89 m3
174.87 503.47 0.00 0.00 0.00 0.00 67.82 24.74 157.65 770.91
E41 Worked finishes/Cutting to
in situ concrete
Worked finishes
Tamping by mechanical
means
57 level 32.59 m2
21.18 0.00 5.54 0.00 0.00 0.00 2.61 0.98 0.93 30.31
Subtotal for E in Situ ... 196.05 503.47 5.54 0.00 0.00 0.00 70.43 25.72 801.22
P BUILDING FABRIC SUNDRIES
P10 Sundry insulation/proofing
work/fire stops
Vapour barriers
Vapour barriers
58 Polythene vapour barrier 32.59 m2
58.99 11.41 0.00 0.00 0.00 0.00 7.17 2.61 2.46 80.17
Insulating boards
Celotex Insulation Fast-R
range
59 75 mm 32.59 m2
135.57 368.59 0.00 0.00 0.00 0.00 50.51 18.25 17.58 572.93
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 16
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
P BUILDING FABRIC continued ...
P10 Sundry insulation/proofing
work/fire stops continued ...
Insulating boards continued ...
Celotex Insulation T-Break
range
60 20 mm 4.47 m2
16.27 15.96 0.00 0.00 0.00 0.00 3.22 1.16 8.19 36.61
Subtotal for P Building Fabric ... 210.83 395.96 0.00 0.00 0.00 0.00 60.90 22.02 689.71
M SURFACE FINISHES
M10 Cement sand/Concrete
screeds/toppings
Cement and sand 1:3, work to
floors
Screeded beds, level and to
falls not exceeding 15 degrees
from
horizontal, over 300 mm wide
61 75 mm 32.59 m2
186.41 328.51 0.00 0.00 0.00 0.00 51.49 18.90 17.96 585.32
Subtotal for M Surface Finishes 186.41 328.51 0.00 0.00 0.00 0.00 51.49 18.90 585.32
Total for Item 5.3 - 5.7 1341.88 1485.65 599.61 0.00 0.00 0.00 342.70 124.85 2,564.86
ITEM 5.8
D20 Excavating and filling
Excavating by hand
To reduce levels, maximum
depth not exceeding
62 1.00 m 4.00 m3
70.76 0.00 0.00 0.00 0.00 0.00 7.08 2.60 20.11 80.44
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 17
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 5.8 continued ...
D20 Excavating continued ...
Disposal
Off site to tip average 15 km
from site
63 loaded by hand from spoil
heaps 5.00 m3
89.50 0.00 150.00 0.00 0.00 0.00 23.95 8.75 54.44 272.20
Surface treatments
Compacting
64 bottom of excavation 13.33 m2
5.73 0.00 1.47 0.00 0.00 0.00 0.67 0.27 0.61 8.13
Total for Item 5.8 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 360.77
ITEM 5.9
J WATERPROOFING
J40 Flexible sheet tanking/
damp proof membranes
Tanking and damp proofing
Polythene medium weight
sheet underlay lapped 150
mm at joints
65 horizontally 20.57 m2
22.42 8.02 0.00 0.00 0.00 0.00 3.09 1.03 1.68 34.56
Subtotal for J Waterproofing 188.41 8.02 151.47 0.00 0.00 0.00 34.79 12.65 34.56
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 18
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
E IN SITU CONCRETE/LARGE
PRECAST CONCRETE
E10 Mixing/casting/curing
in-situ concrete
Ready mixed concrete
Plain in situ concrete 1:2:4 -
20 mm aggregate
66 slabs, thickness not
exceeding 150 mm 2.00 m3
71.52 205.92 0.00 0.00 0.00 0.00 27.74 10.12 157.65 315.30
E41 Worked finishes/Cutting to
in situ concrete
Worked finishes
Tamping by mechanical
means
67 level 13.33 m2
8.66 0.00 2.27 0.00 0.00 0.00 1.07 0.40 0.93 12.40
Subtotal for E in Situ ... 80.18 205.92 2.27 0.00 0.00 0.00 28.81 10.52 327.70
P BUILDING FABRIC SUNDRIES
P10 Sundry insulation/proofing
work/fire stops
Vapour barriers
Vapour barriers
68 Polythene vapour barrier 13.33 m2
24.13 4.67 0.00 0.00 0.00 0.00 2.93 1.07 2.46 32.79
Insulating boards
Celotex Insulation Fast-R
range
69 75 mm 13.33 m2
55.45 150.76 0.00 0.00 0.00 0.00 20.66 7.46 17.58 234.34
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 19
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
P BUILDING FABRIC continued ...
P10 Sundry insulation/proofing
work/fire stops continued ...
Insulating boards continued ...
Celotex Insulation T-Break
range
70 20 mm 2.70 m2
9.83 9.64 0.00 0.00 0.00 0.00 1.94 0.70 8.19 22.11
Subtotal for P Building Fabric ... 89.41 165.07 0.00 0.00 0.00 0.00 25.53 9.23 289.24
M SURFACE FINISHES
M10 Cement sand/Concrete
screeds/toppings
Cement and sand 1:3, work to
floors
Screeded beds, level and to
falls not exceeding 15 degrees
from
horizontal, over 300 mm wide
71 75 mm 13.33 m2
76.25 134.37 0.00 0.00 0.00 0.00 21.06 7.73 17.96 239.41
Subtotal for M Surface Finishes 76.25 134.37 0.00 0.00 0.00 0.00 21.06 7.73 239.41
Total for Item 5.9 434.25 513.38 153.74 0.00 0.00 0.00 110.19 40.13 890.91
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 20
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 5.10
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Floor members
72 50 x 75mm 6.00 m 14.88 6.84 0.00 0.00 0.00 0.00 2.16 0.78 4.11 24.66
73 50 x 150mm 38.72 m 122.36 90.22 0.00 0.00 0.00 0.00 21.30 7.74 6.24 241.61
Solid bridging between joists
(measured over the joists)
74 50 x 150mm 5.87 m 37.10 14.44 0.00 0.00 0.00 0.00 5.17 1.88 9.98 58.58
Metalwork
Galvanised steel joist hangers
- built in
75 50 x 150mm 32.00 nr 64.96 41.28 0.00 0.00 0.00 0.00 10.56 3.84 3.77 120.64
Galvanised steel straps
76 heavy duty steel strap; once
bent; 1200 mm long 6.00 nr 37.92 26.64 0.00 0.00 0.00 0.00 6.48 2.34 12.23 73.38
Subtotal for G ... 277.22 179.42 0.00 0.00 0.00 0.00 45.67 16.58 518.87
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 21
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
K LININGS/SHEATHING/DRY
PARTITIONING
K20 Timber board
flooring/sheathing/linings/casings
Flooring
Chipboard Type C4 flooring
tongued and grooved all
edges, width
exceeding 300 mm, thickness
77 22mm 14.60 m2
105.56 93.44 0.00 0.00 0.00 0.00 19.86 7.30 15.49 226.15
Subtotal for K ... 105.56 93.44 0.00 0.00 0.00 0.00 19.86 7.30 226.15
P BUILDING FABRIC SUNDRIES
P10 Sundry insulation/proofing
work/fire stops
Insulating quilts
Acoustic insulating quilts
78 100 mm 14.60 m2
26.43 103.08 0.00 0.00 0.00 0.00 12.99 4.67 10.08 147.17
Subtotal for P Building Fabric ... 26.43 103.08 0.00 0.00 0.00 0.00 12.99 4.67 147.17
Total for Item 5.10 409.21 375.94 0.00 0.00 0.00 0.00 78.52 28.55 892.19
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 22
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 5.11
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Wall or partition members
79 50 x 75mm 4.25 m 13.43 4.59 0.00 0.00 0.00 0.00 1.79 0.68 4.82 20.49
Subtotal for G ... 13.43 4.59 0.00 0.00 0.00 0.00 1.79 0.68 20.49
Total for Item 5.11 13.43 4.59 0.00 0.00 0.00 0.00 1.79 0.68 20.49
ITEM 6.1
C EXISTING
SITE/BUILDINGS/SERVICES
C20 Demolition
Pulling down - including removal
of debris
Demolish external brickwork
walls in cement mortar;
disposal of
debris off-site
80 2 x 102.5 mm thick skins
forming cavity wall 3.00 m2
95.04 0.00 37.80 0.00 0.00 0.00 13.29 4.83 50.32 150.96
Subtotal for C Existing ... 95.04 0.00 37.80 0.00 0.00 0.00 13.29 4.83 150.96
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 23
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
F MASONRY
F31 Precast concrete
sills/lintels/copings/features
Lintels
Prestressed lintels 65 mm x
100 mm bedded
81 1200 mm 2.00 nr 16.86 22.60 0.00 0.00 0.00 0.00 3.94 1.44 22.42 44.84
F30 Accessories/Sundry items
for brick/block/stone walling
Closing cavities
Thermabate cavity closers
82 100 mm cavity 10.95 m 34.05 58.14 0.00 0.00 0.00 0.00 9.20 3.39 9.57 104.79
Proprietary items
Wall extension profiles, single
flange, plugging and screwing
83 100mm 21.10 m 81.45 100.86 0.00 0.00 0.00 0.00 18.15 6.54 9.81 206.99
Subtotal for F Masonry 132.36 181.60 0.00 0.00 0.00 0.00 31.29 11.37 356.62
Total for Item 6.1 227.40 181.60 37.80 0.00 0.00 0.00 44.58 16.20 507.58
ITEM 6.2
F MASONRY
F10 Brick/Block walling
Precast concrete dense
aggregate blocks to BS 6073
Walls, facework one side
84 100 mm solid; in gauged
mortar 1:3; below DPC level 23.09 m2
287.01 423.93 0.00 0.00 0.00 0.00 71.12 25.86 34.99 807.92
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 24
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
F MASONRY continued ...
F10 Brick/Block continued ...
Class B engineering bricks in
cement mortar 1:3
Walls
85 102.5 mm 4.87 m2
116.73 239.26 0.00 0.00 0.00 0.00 35.60 12.95 83.07 404.55
F30 Accessories/Sundry items
for brick/block/stone walling
Damp proof courses
Polythene
86 horizontal 100mm wide 41.11 m 18.09 4.52 0.00 0.00 0.00 0.00 2.47 0.82 0.63 25.90
Subtotal for F Masonry 421.83 667.71 0.00 0.00 0.00 0.00 109.19 39.63 1,238.37
Total for Item 6.2 421.83 667.71 0.00 0.00 0.00 0.00 109.19 39.63 1,238.37
ITEM 6.3
E IN SITU CONCRETE/LARGE
PRECAST CONCRETE
E10 Mixing/casting/curing
in-situ concrete
Ready mixed concrete
Plain in situ concrete 1:2:4 -
20 mm aggregate
87 filling to hollow walls 1.21 m3
64.90 125.77 0.00 0.00 0.00 0.00 19.07 6.95 179.08 216.69
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 25
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
E IN SITU CONCRETE/LARGE
PRECAST continued ...
E10 Mixing/casting/curing
in-situ concrete continued ...
Forming cavities
50 - 100 mm cavities in hollow
walls with 225 mm wall-ties at
5 per
m2 using
88 3 mm vertical-twist ties 67.71 m2
60.26 50.11 0.00 0.00 0.00 0.00 10.83 4.06 1.85 125.26
Subtotal for E in Situ ... 125.16 175.88 0.00 0.00 0.00 0.00 29.90 11.01 341.95
P BUILDING FABRIC SUNDRIES
P10 Sundry insulation/proofing
work/fire stops
Cavity wall Insulation
Slab insulation to masonry
walls
89 60 mm thick Celotex cavity
insulation 67.71 m2
270.84 635.80 0.00 0.00 0.00 0.00 90.73 33.18 15.22 1,030.55
Subtotal for P Building Fabric ... 270.84 635.80 0.00 0.00 0.00 0.00 90.73 33.18 1,030.55
Total for Item 6.3 396.00 811.68 0.00 0.00 0.00 0.00 120.63 44.19 1,372.50
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 26
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 6.4
F MASONRY
F10 Brick/Block walling
Precast concrete dense
aggregate blocks to BS 6073
Walls, facework one side
90 100 mm solid; in gauged
mortar 1:4; above DPC level 59.75 m2
742.69 1055.19 0.00 0.00 0.00 0.00 179.85 65.73 34.20 2,043.45
Subtotal for F Masonry 742.69 1055.19 0.00 0.00 0.00 0.00 179.85 65.73 2,043.45
Total for Item 6.4 742.69 1055.19 0.00 0.00 0.00 0.00 179.85 65.73 2,043.45
ITEM 6.5
F MASONRY
F10 Brick/Block walling
Facing bricks in gauged mortar
1:4
Walls, facework one side; PC
supply rate for bricks
£750/1000
91 102.5 mm 73.18 m2
1754.12 4432.51 0.00 0.00 0.00 0.00 618.37 225.39 96.07 7,030.40
Subtotal for F Masonry 1754.12 4432.51 0.00 0.00 0.00 0.00 618.37 225.39 7,030.40
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 27
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Dummy frames for brickwork
92 50 x 100mm 34.60 m 132.86 54.32 0.00 0.00 0.00 0.00 18.68 6.92 6.15 212.79
Subtotal for G ... 132.86 54.32 0.00 0.00 0.00 0.00 18.68 6.92 212.79
Total for Item 6.5 1886.98 4486.83 0.00 0.00 0.00 0.00 637.05 232.31 7,243.19
ITEM 6.6
F MASONRY
F30 Accessories/Sundry items
for brick/block/stone walling
Damp proof courses
Polythene
93 vertical 100mm wide 21.10 m 9.28 2.32 0.00 0.00 0.00 0.00 1.27 0.42 0.63 13.29
Subtotal for F Masonry 9.28 2.32 0.00 0.00 0.00 0.00 1.27 0.42 13.29
Total for Item 6.6 9.28 2.32 0.00 0.00 0.00 0.00 1.27 0.42 13.29
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 28
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 6.7
F MASONRY
F30 Accessories/Sundry items
for brick/block/stone walling
Closing cavities
Thermabate cavity closers
94 100 mm cavity 17.00 m 52.87 90.27 0.00 0.00 0.00 0.00 14.28 5.27 9.57 162.69
Subtotal for F Masonry 52.87 90.27 0.00 0.00 0.00 0.00 14.28 5.27 162.69
Total for Item 6.7 52.87 90.27 0.00 0.00 0.00 0.00 14.28 5.27 162.69
ITEM 6.8
F MASONRY
F30 Accessories/Sundry items
for brick/block/stone walling
Cavity trays
Polythene
95 horizontal exceeding 225
mm 5.09 m2
42.91 4.94 0.00 0.00 0.00 0.00 4.78 1.73 10.68 54.36
Stop Ends
96 lintel stop end 10.00 nr 8.90 7.40 0.00 0.00 0.00 0.00 1.60 0.60 1.85 18.50
Subtotal for F Masonry 51.81 12.34 0.00 0.00 0.00 0.00 6.38 2.33 72.86
Total for Item 6.8 51.81 12.34 0.00 0.00 0.00 0.00 6.38 2.33 72.86
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 29
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 6.9
F MASONRY
F30 Accessories/Sundry items
for brick/block/stone walling
Cavity trays
Type W Cavity weep ventilator
97 wall weep vent 25.00 nr 22.25 8.00 0.00 0.00 0.00 0.00 3.00 1.00 1.37 34.25
Subtotal for F Masonry 22.25 8.00 0.00 0.00 0.00 0.00 3.00 1.00 34.25
Total for Item 6.9 22.25 8.00 0.00 0.00 0.00 0.00 3.00 1.00 34.25
ITEM 6.10
L WINDOWS/DOORS/STAIRS
L10
Windows/rooflights/screens/louvres
Bedding and pointing frames
Pointing in mastic sealant
98 window frames 14.81 m 23.84 6.22 0.00 0.00 0.00 0.00 2.96 1.04 2.30 34.06
L20 Doors/shutters/hatches
Bedding and pointing frames
Pointing in mastic sealant
99 door frames 18.65 m 30.03 7.83 0.00 0.00 0.00 0.00 3.73 1.31 2.30 42.90
Subtotal for L Windows/Doors/Stairs 53.87 14.05 0.00 0.00 0.00 0.00 6.69 2.35 76.96
Total for Item 6.10 53.87 14.05 0.00 0.00 0.00 0.00 6.69 2.35 76.96
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 30
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 6.11
F MASONRY
F30 Accessories/Sundry items
for brick/block/stone walling
Galvanised steel lintels
Galvanised steel standard
lintels
100 2100mm 2.00 nr 20.42 100.18 0.00 0.00 0.00 0.00 12.06 4.40 68.53 137.06
Galvanised steel heavy duty
lintels
101 3900mm 1.00 nr 20.42 214.94 0.00 0.00 0.00 0.00 23.54 8.58 267.48 267.48
Galvanised steel eaves lintels
102 1200mm 1.00 nr 7.10 19.44 0.00 0.00 0.00 0.00 2.65 0.97 30.16 30.16
103 1350mm 1.00 nr 7.10 21.88 0.00 0.00 0.00 0.00 2.90 1.06 32.94 32.94
Subtotal for F Masonry 55.04 356.44 0.00 0.00 0.00 0.00 41.15 15.01 467.64
Total for Item 6.11 55.04 356.44 0.00 0.00 0.00 0.00 41.15 15.01 467.64
ITEM 6.12
F MASONRY
F10 Brick/Block walling
Facing bricks in gauged mortar
1:4
Flush bands
104 215 mm, brick on end 6.33 m 28.11 83.18 0.00 0.00 0.00 0.00 11.14 4.05 19.98 126.47
Subtotal for F Masonry 28.11 83.18 0.00 0.00 0.00 0.00 11.14 4.05 126.47
Total for Item 6.12 28.11 83.18 0.00 0.00 0.00 0.00 11.14 4.05 126.47
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 31
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 6.13
F MASONRY
F30 Accessories/Sundry items
for brick/block/stone walling
Closing cavities
Thermabate cavity closers
105 100 mm cavity 10.88 m 33.84 57.77 0.00 0.00 0.00 0.00 9.14 3.37 9.57 104.12
F31 Precast concrete
sills/lintels/copings/features
Copings
400 x 900 mm twice
weathered and throated
copings bedded
106 straight 10.88 m 178.65 412.03 0.00 0.00 0.00 0.00 59.08 21.54 61.70 671.30
Subtotal for F Masonry 212.49 469.80 0.00 0.00 0.00 0.00 68.22 24.91 775.42
H CLADDING/COVERING
H71 Lead sheet
coverings/flashings
Flashings, aprons
Code 4 lead, horizontal, 150
mm lapped joints, fixing with
lead clips
and wedges
107 300 mm girth 10.01 m 59.56 159.06 0.00 0.00 0.00 0.00 21.82 8.01 24.82 248.45
Subtotal for H Cladding/Covering 59.56 159.06 0.00 0.00 0.00 0.00 21.82 8.01 248.45
Total for Item 6.13 272.05 628.86 0.00 0.00 0.00 0.00 90.04 32.92 1,023.87
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 32
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 6.14
C EXISTING
SITE/BUILDINGS/SERVICES
C41
Repairing/renovating/conserving
masonry
Brickwork
Cut out
108 brickwork to allow for cavity
tray installation, make good
with new
facing bricks 0.75 m2
71.67 2.11 0.23 0.00 0.00 0.00 7.40 2.70 112.14 84.11
F30 Accessories/Sundry items
for brick/block/stone walling
Cavity trays
Polythene
109 horizontal exceeding 225
mm 1.50 m2
12.65 1.46 0.00 0.00 0.00 0.00 1.41 0.51 10.68 16.02
Type W Cavity weep ventilator
110 wall weep vent 14.00 nr 12.46 4.48 0.00 0.00 0.00 0.00 1.68 0.56 1.37 19.18
Subtotal for C Existing ... 96.78 8.05 0.23 0.00 0.00 0.00 10.49 3.77 119.31
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 33
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
H CLADDING/COVERING
H71 Lead sheet
coverings/flashings
Flashings, aprons
Code 4 lead, horizontal, 150
mm lapped joints, fixing with
lead clips
and wedges
111 300 mm girth 5.98 m 35.58 95.02 0.00 0.00 0.00 0.00 13.04 4.78 24.82 148.42
Subtotal for H Cladding/Covering 35.58 95.02 0.00 0.00 0.00 0.00 13.04 4.78 148.42
Total for Item 6.14 132.36 103.07 0.23 0.00 0.00 0.00 23.53 8.55 267.73
ITEM 6.15
F MASONRY
F31 Precast concrete
sills/lintels/copings/features
Padstones
Padstones bedded
112 400 x 100 x 150 mm 1.00 nr 6.21 15.86 0.00 0.00 0.00 0.00 2.21 0.80 25.08 25.08
113 250 x 100 x 150 mm 1.00 nr 6.21 14.48 0.00 0.00 0.00 0.00 2.07 0.75 23.51 23.51
114 50 x 280 x 218 mm 1.00 nr 6.21 14.48 0.00 0.00 0.00 0.00 2.07 0.75 23.51 23.51
Lintels
Prestressed lintels 65 mm x
100 mm bedded
115 750 mm 2.00 nr 16.86 15.86 0.00 0.00 0.00 0.00 3.28 1.20 18.60 37.20
Subtotal for F Masonry 35.49 60.68 0.00 0.00 0.00 0.00 9.63 3.50 109.30
Total for Item 6.15 35.49 60.68 0.00 0.00 0.00 0.00 9.63 3.50 109.30
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 34
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 6.16
F MASONRY
F10 Brick/Block walling
Precast concrete dense
aggregate blocks to BS 6073
Walls, facework one side
116 100 mm solid; in gauged
mortar 1:4; above DPC level 3.89 m2
48.35 68.70 0.00 0.00 0.00 0.00 11.71 4.28 34.20 133.04
Subtotal for F Masonry 48.35 68.70 0.00 0.00 0.00 0.00 11.71 4.28 133.04
Total for Item 6.16 48.35 68.70 0.00 0.00 0.00 0.00 11.71 4.28 133.04
ITEM 6.17
F MASONRY
F31 Precast concrete
sills/lintels/copings/features
Lintels
Prestressed lintels 65 mm x
100 mm bedded
117 1200 mm 2.00 nr 16.86 22.60 0.00 0.00 0.00 0.00 3.94 1.44 22.42 44.84
Subtotal for F Masonry 16.86 22.60 0.00 0.00 0.00 0.00 3.94 1.44 44.84
Total for Item 6.17 16.86 22.60 0.00 0.00 0.00 0.00 3.94 1.44 44.84
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 35
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 6.18
C EXISTING
SITE/BUILDINGS/SERVICES
C90 Alterations - spot items
Forming new window opening in
existing wall
Temporary support, close
cavity, make good reveals,
build in
standard lintel
118 through cavity wall 0.39 m2
61.77 27.44 6.26 0.00 0.00 0.00 9.55 3.48 278.21 108.50
Subtotal for C Existing ... 61.77 27.44 6.26 0.00 0.00 0.00 9.55 3.48 108.50
Total for Item 6.18 61.77 27.44 6.26 0.00 0.00 0.00 9.55 3.48 108.50
ITEM 6.19
C EXISTING
SITE/BUILDINGS/SERVICES
C41
Repairing/renovating/conserving
masonry
Brickwork
Cut out
119 brickwork to allow for new
meter box installation 0.25 m2
16.30 0.00 0.08 0.00 0.00 0.00 1.64 0.60 74.44 18.61
Subtotal for C Existing ... 16.30 0.00 0.08 0.00 0.00 0.00 1.64 0.60 18.61
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 36
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
F MASONRY
F30 Accessories/Sundry items
for brick/block/stone walling
Meter Boxes
120 recessed electric meter box 1.00 nr 5.53 20.46 0.00 0.00 0.00 0.00 2.60 0.95 29.54 29.54
Galvanised steel lintels
Single element lintels
121 750mm 1.00 nr 5.33 7.41 0.00 0.00 0.00 0.00 1.27 0.46 14.47 14.47
F30 Accessories/Sundry items
for brick/block/stone walling
Cavity trays
Polythene
122 horizontal exceeding 225
mm 0.28 m2
2.36 0.27 0.00 0.00 0.00 0.00 0.26 0.10 10.70 3.00
Type W Cavity weep ventilator
123 wall weep vent 3.00 nr 2.67 0.96 0.00 0.00 0.00 0.00 0.36 0.12 1.37 4.11
Subtotal for F Masonry 15.89 29.10 0.00 0.00 0.00 0.00 4.49 1.63 51.12
Total for Item 6.19 32.19 29.10 0.08 0.00 0.00 0.00 6.13 2.23 69.73
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 37
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 6.20
F MASONRY
F10 Brick/Block walling
Precast concrete dense
aggregate blocks to BS 6073
Walls, facework one side
124 100 mm solid; in gauged
mortar 1:4; above DPC level 0.78 m2
9.70 13.77 0.00 0.00 0.00 0.00 2.35 0.86 34.20 26.68
Forming cavities
50 - 100 mm cavities in hollow
walls with 225 mm wall-ties at
5 per
m2 using
125 3 mm vertical-twist ties 0.39 m2
0.35 0.29 0.00 0.00 0.00 0.00 0.06 0.02 1.84 0.72
Subtotal for F Masonry 10.05 14.06 0.00 0.00 0.00 0.00 2.41 0.88 27.40
P BUILDING FABRIC SUNDRIES
P10 Sundry insulation/proofing
work/fire stops
Cavity wall Insulation
Slab insulation to masonry
walls
126 60 mm thick Celotex cavity
insulation 0.39 m2
1.56 3.66 0.00 0.00 0.00 0.00 0.52 0.19 15.22 5.94
Subtotal for P Building Fabric ... 1.56 3.66 0.00 0.00 0.00 0.00 0.52 0.19 5.94
Total for Item 6.20 11.61 17.72 0.00 0.00 0.00 0.00 2.93 1.07 33.34
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 38
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 7.2
G STRUCTURAL/CARCASSING
METAL/TIMBER
G10 Structural steel framing
Framing, fabrication
Fabricated steelwork
127 columns 40 - 100 kg/m 0.41 tonne 0.00 563.70 0.00 0.00 0.00 0.00 56.37 20.54 1562.48 640.62
Erection on site
128 permanent erection 0.41 tonne 181.69 0.00 0.00 0.00 0.00 0.00 18.17 6.62 503.62 206.48
Surface treatments at
fabrication workshop
129 shot blasting & priming 6.97 m2
0.00 54.02 0.00 0.00 0.00 0.00 5.44 1.95 8.81 61.41
130 30 minute intumescent fire
paint 6.97 m2
0.00 90.89 0.00 0.00 0.00 0.00 9.06 3.28 14.81 103.23
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Boxing out steelwork
131 50 x 50mm 27.84 m 69.04 22.83 0.00 0.00 0.00 0.00 9.19 3.34 3.75 104.40
Subtotal for G ... 250.73 731.44 0.00 0.00 0.00 0.00 98.23 35.73 1,116.14
Total for Item 7.2 250.73 731.44 0.00 0.00 0.00 0.00 98.23 35.73 1,116.14
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 39
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 7.3
G STRUCTURAL/CARCASSING
METAL/TIMBER
G10 Structural steel framing
Framing, fabrication
Fabricated steelwork
132 beams less than 40 kg/m 0.08 tonne 0.00 133.50 0.00 0.00 0.00 0.00 13.35 4.86 1896.31 151.70
Fittings
133 general fiitings; plates, nuts,
bolts etc. 0.01 tonne 0.00 21.94 0.00 0.00 0.00 0.00 2.19 0.80 2492.91 24.93
Erection on site
134 permanent erection 0.08 tonne 35.45 0.00 0.00 0.00 0.00 0.00 3.55 1.29 503.60 40.29
Surface treatments at
fabrication workshop
135 shot blasting & priming 3.17 m2
0.00 24.57 0.00 0.00 0.00 0.00 2.47 0.89 8.81 27.93
136 30 minute intumescent fire
paint 3.17 m2
0.00 41.34 0.00 0.00 0.00 0.00 4.12 1.52 14.82 46.98
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Boxing out steelwork
137 50 x 50mm 9.64 m 23.91 7.90 0.00 0.00 0.00 0.00 3.18 1.16 3.75 36.15
Subtotal for G ... 59.36 229.25 0.00 0.00 0.00 0.00 28.86 10.52 327.98
Total for Item 7.3 59.36 229.25 0.00 0.00 0.00 0.00 28.86 10.52 327.98
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 40
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 7.5
G STRUCTURAL/CARCASSING
METAL/TIMBER
G10 Structural steel framing
Framing, fabrication
Fabricated steelwork
138 columns less than 40 kg/m 0.14 tonne 0.00 220.15 0.00 0.00 0.00 0.00 22.02 8.02 1787.01 250.18
Erection on site
139 permanent erection 0.14 tonne 62.04 0.00 0.00 0.00 0.00 0.00 6.20 2.26 503.61 70.51
Subtotal for G ... 62.04 220.15 0.00 0.00 0.00 0.00 28.22 10.28 320.69
Total for Item 7.5 62.04 220.15 0.00 0.00 0.00 0.00 28.22 10.28 320.69
ITEM 7.6
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Flat roof members
140 50 x 150mm 6.94 m 21.93 16.79 0.00 0.00 0.00 0.00 3.89 1.39 6.34 44.00
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 41
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
G STRUCTURAL/CARCASSING
METAL/TIMBER continued ...
G20 Carpentry/Timber
framing/First continued ...
Metalwork
Bolts & Timber Connectors
141 M12 bolt with nut; 130 mm
long 7.00 nr 7.91 6.02 0.00 0.00 0.00 0.00 1.40 0.49 2.26 15.82
Subtotal for G ... 29.84 22.81 0.00 0.00 0.00 0.00 5.29 1.88 59.82
Total for Item 7.6 29.84 22.81 0.00 0.00 0.00 0.00 5.29 1.88 59.82
ITEM 8.1
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Wall plates bedded
142 75 x 100mm 10.90 m 46.76 30.74 0.00 0.00 0.00 0.00 7.74 2.83 8.08 88.07
Metalwork
Galvanised steel straps
143 light duty wall plate strap;
once bent; 1200 mm long 18.00 nr 113.76 32.22 0.00 0.00 0.00 0.00 14.58 5.40 9.22 165.96
Subtotal for G ... 160.52 62.96 0.00 0.00 0.00 0.00 22.32 8.23 254.03
Total for Item 8.1 160.52 62.96 0.00 0.00 0.00 0.00 22.32 8.23 254.03
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 42
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 8.2
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Flat roof members
144 50 x 150mm 37.59 m 118.78 90.97 0.00 0.00 0.00 0.00 21.05 7.52 6.34 238.32
145 50 x 200mm 24.33 m 82.48 78.59 0.00 0.00 0.00 0.00 16.06 5.84 7.52 182.96
146 50 x 50mm angle fillets 34.96 m 70.97 25.87 0.00 0.00 0.00 0.00 9.79 3.50 3.15 110.12
147 sawn softwood firrings 61.92 m 195.67 315.17 0.00 0.00 0.00 0.00 51.39 18.58 9.38 580.81
Metalwork
Anchor bolts
148 M12 anchor bolt; 115 mm
long 28.00 nr 56.84 24.36 0.00 0.00 0.00 0.00 8.12 3.08 3.30 92.40
Bolts & Timber Connectors
149 M12 bolt with nut; 130 mm
long 31.00 nr 35.03 26.66 0.00 0.00 0.00 0.00 6.20 2.17 2.26 70.06
Galvanised steel straps
150 heavy duty steel strap; once
bent; 1200 mm long 6.00 nr 37.92 26.64 0.00 0.00 0.00 0.00 6.48 2.34 12.23 73.38
Speedy joist hangers
151 100mm 8.00 nr 30.72 5.92 0.00 0.00 0.00 0.00 3.68 1.36 5.21 41.68
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 43
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
G STRUCTURAL/CARCASSING
METAL/TIMBER continued ...
G20 Carpentry/Timber
framing/First continued ...
Metalwork continued ...
Speedy joist continued ...
152 50mm 44.00 nr 109.12 28.16 0.00 0.00 0.00 0.00 13.64 4.84 3.54 155.76
Subtotal for G ... 737.53 622.34 0.00 0.00 0.00 0.00 136.41 49.23 1,545.49
Total for Item 8.2 737.53 622.34 0.00 0.00 0.00 0.00 136.41 49.23 1,545.49
ITEM 8.3
K LININGS/SHEATHING/DRY
PARTITIONING
K20 Timber board
flooring/sheathing/linings/casings
Roof decking
WBP plywood
153 18mm WBP plywood
exceeding 300 mm wide 9.57 m2
79.91 68.71 0.00 0.00 0.00 0.00 14.83 5.45 17.65 168.91
Subtotal for K ... 79.91 68.71 0.00 0.00 0.00 0.00 14.83 5.45 168.91
Total for Item 8.3 79.91 68.71 0.00 0.00 0.00 0.00 14.83 5.45 168.91
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 44
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 8.4
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Flat roof members
154 50 x 100mm 24.68 m 94.77 39.98 0.00 0.00 0.00 0.00 13.57 4.94 6.21 153.26
Subtotal for G ... 94.77 39.98 0.00 0.00 0.00 0.00 13.57 4.94 153.26
Total for Item 8.4 94.77 39.98 0.00 0.00 0.00 0.00 13.57 4.94 153.26
ITEM 8.5
P BUILDING FABRIC SUNDRIES
P10 Sundry insulation/proofing
work/fire stops
Insulating quilts
Acoustic insulating quilts
155 100 mm 1.91 m2
3.46 13.48 0.00 0.00 0.00 0.00 1.70 0.61 10.08 19.25
Subtotal for P Building Fabric ... 3.46 13.48 0.00 0.00 0.00 0.00 1.70 0.61 19.25
Total for Item 8.5 3.46 13.48 0.00 0.00 0.00 0.00 1.70 0.61 19.25
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 45
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 8.6
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Flat roof members
156 50 x 150mm 10.67 m 33.72 25.82 0.00 0.00 0.00 0.00 5.98 2.13 6.34 67.65
Metalwork
Bolts & Timber Connectors
157 M12 bolt with nut; 130 mm
long 15.00 nr 16.95 12.90 0.00 0.00 0.00 0.00 3.00 1.05 2.26 33.90
Total for Item 8.6 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 101.55
ITEM 8.7
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Flat roof members
158 50 x 100mm 17.26 m 66.28 27.96 0.00 0.00 0.00 0.00 9.49 3.45 6.21 107.18
Subtotal for G ... 116.95 66.68 0.00 0.00 0.00 0.00 18.47 6.63 107.18
Total for Item 8.7 116.95 66.68 0.00 0.00 0.00 0.00 18.47 6.63 107.18
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 46
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 8.9
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Pitched roof members
159 50 x 150mm 111.32 m 477.56 271.62 0.00 0.00 0.00 0.00 74.58 27.83 7.65 851.60
160 50 x 225mm 17.70 m 75.93 64.07 0.00 0.00 0.00 0.00 13.98 5.13 8.99 159.12
Subtotal for G ... 553.49 335.69 0.00 0.00 0.00 0.00 88.56 32.96 1,010.72
Total for Item 8.9 553.49 335.69 0.00 0.00 0.00 0.00 88.56 32.96 1,010.72
ITEM 8.11
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Pitched roof members
161 50 x 150mm 36.30 m 155.73 88.57 0.00 0.00 0.00 0.00 24.32 9.08 7.65 277.70
Total for Item 8.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 277.70
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 47
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 8.12
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Pitched roof members
162 50 x 150mm 1.60 m 6.86 3.90 0.00 0.00 0.00 0.00 1.07 0.38 7.64 12.22
K LININGS/SHEATHING/DRY
PARTITIONING
K20 Timber board
flooring/sheathing/linings/casings
Flooring
Chipboard Type C4 flooring
tongued and grooved all
edges, width
exceeding 300 mm, thickness
163 22mm 14.19 m2
102.59 90.82 0.00 0.00 0.00 0.00 19.30 7.10 15.49 219.80
Subtotal for K ... 265.18 183.29 0.00 0.00 0.00 0.00 44.69 16.56 232.02
Total for Item 8.12 265.18 183.29 0.00 0.00 0.00 0.00 44.69 16.56 232.02
ITEM 8.13
P BUILDING FABRIC SUNDRIES
P10 Sundry insulation/proofing
work/fire stops
Insulating quilts
Thermal insulating quilts
164 170 mm Knauf Earthwool 14.19 m2
15.47 31.36 0.00 0.00 0.00 0.00 4.68 1.70 3.75 53.21
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 48
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
P BUILDING FABRIC continued ...
P10 Sundry insulation/proofing
work/fire stops continued ...
Insulating quilts continued ...
Thermal continued ...
165 100 mm Knauf Earthwool 14.19 m2
13.91 18.16 0.00 0.00 0.00 0.00 3.26 1.14 2.57 36.47
Subtotal for P Building Fabric ... 29.38 49.52 0.00 0.00 0.00 0.00 7.94 2.84 89.68
Total for Item 8.13 29.38 49.52 0.00 0.00 0.00 0.00 7.94 2.84 89.68
ITEM 8.14
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Pitched roof members
166 50 x 175mm C24 14.61 m 62.68 45.44 0.00 0.00 0.00 0.00 10.81 3.94 8.41 122.87
167 75 x 100mm 5.48 m 28.44 15.45 0.00 0.00 0.00 0.00 4.38 1.59 9.10 49.87
168 75 x 175mm 2.95 m 15.31 14.57 0.00 0.00 0.00 0.00 2.98 1.09 11.51 33.95
169 50 x 100mm 1.51 m 5.80 2.45 0.00 0.00 0.00 0.00 0.83 0.30 6.21 9.38
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 49
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
G STRUCTURAL/CARCASSING
METAL/TIMBER continued ...
G20 Carpentry/Timber
framing/First continued ...
Metalwork
Bolts & Timber Connectors
170 M12 bolt with nut; 130 mm
long 26.00 nr 29.38 22.36 0.00 0.00 0.00 0.00 5.20 1.82 2.26 58.76
Subtotal for G ... 141.61 100.27 0.00 0.00 0.00 0.00 24.20 8.74 274.83
Total for Item 8.14 141.61 100.27 0.00 0.00 0.00 0.00 24.20 8.74 274.83
ITEM 8.15
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Eaves and verge boarding
Impregnated wrought softwood
eaves and verge boarding,
width not exceeding 300 mm
171 32 x 225mm boards 12.75 m 66.17 118.83 0.00 0.00 0.00 0.00 18.49 6.76 16.49 210.25
Subtotal for G ... 66.17 118.83 0.00 0.00 0.00 0.00 18.49 6.76 210.25
Total for Item 8.15 66.17 118.83 0.00 0.00 0.00 0.00 18.49 6.76 210.25
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 50
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 8.16
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Pitched roof members
172 50 x 50mm plugged and
screwed 11.96 m 37.79 10.17 0.00 0.00 0.00 0.00 4.78 1.79 4.56 54.54
Eaves and verge boarding
WBP plywood
173 9mm Softwood plywood -
225mm wide 12.75 m 83.51 14.28 0.00 0.00 0.00 0.00 9.82 3.57 8.72 111.18
Subtotal for G ... 121.30 24.45 0.00 0.00 0.00 0.00 14.60 5.36 165.72
Total for Item 8.16 121.30 24.45 0.00 0.00 0.00 0.00 14.60 5.36 165.72
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 51
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 8.17
C EXISTING
SITE/BUILDINGS/SERVICES
C20 Demolition
Demolishing parts of timber
structures
Removing roof timbers
174 fascia or barge boards;
dispose of debris off-site 6.50 m 73.32 0.00 1.95 0.00 0.00 0.00 7.54 2.73 13.16 85.54
Subtotal for C Existing ... 73.32 0.00 1.95 0.00 0.00 0.00 7.54 2.73 85.54
Total for Item 8.17 73.32 0.00 1.95 0.00 0.00 0.00 7.54 2.73 85.54
ITEM 8.18
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Pitched roof members
175 50 x 125mm 13.06 m 50.15 29.25 0.00 0.00 0.00 0.00 7.97 2.87 6.91 90.24
176 50 x 100mm 5.60 m 21.50 9.07 0.00 0.00 0.00 0.00 3.08 1.12 6.21 34.78
Eaves and verge boarding
WBP plywood
177 12mm softwood WBP
plywood over 300mm wide 2.27 m2
38.95 11.33 0.00 0.00 0.00 0.00 5.04 1.84 25.18 57.16
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 52
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
G STRUCTURAL/CARCASSING
METAL/TIMBER continued ...
G20 Carpentry/Timber
framing/First continued ...
Eaves and verge continued ...
Impregnated wrought softwood
eaves and verge boarding,
width not exceeding 300 mm
178 32 x 225mm boards 3.54 m 18.37 32.99 0.00 0.00 0.00 0.00 5.13 1.88 16.49 58.37
Metalwork
Bolts & Timber Connectors
179 M12 bolt with nut; 130 mm
long 8.00 nr 9.04 6.88 0.00 0.00 0.00 0.00 1.60 0.56 2.26 18.08
Anchor bolts
180 M12 anchor bolt; 115 mm
long 16.00 nr 32.48 13.92 0.00 0.00 0.00 0.00 4.64 1.76 3.30 52.80
Subtotal for G ... 170.49 103.44 0.00 0.00 0.00 0.00 27.46 10.03 311.43
H CLADDING/COVERING
H60 Plain roof tiling
Sub-contract purchase
Clay plain tiles; Dreadnought
machine made smooth red or
other
equal and approved on 19 x
38mm treated battens and
breather membrane
181 roof coverings to 64mm lap 2.56 m2
0.00 0.00 0.00 0.00 173.16 0.00 17.31 6.30 76.86 196.76
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 53
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
H continued ...
H60 Plain roof continued ...
Sub-contract continued ...
Extra over for
182 double course at eaves 2.53 m 0.00 0.00 0.00 0.00 26.92 0.00 2.68 0.99 12.09 30.59
183 verges; single undercloak
course 1.01 m 0.00 0.00 0.00 0.00 9.39 0.00 0.94 0.34 10.57 10.68
H71 Lead sheet
coverings/flashings
Flashings, aprons
Code 4 lead, horizontal, 150
mm lapped joints, fixing with
lead clips
and wedges
184 300 mm girth 2.53 m 15.05 40.20 0.00 0.00 0.00 0.00 5.52 2.00 24.81 62.77
Code 4 lead, stepped, 150
mm lapped joints, fixing with
lead clips
and wedges
185 300 mm girth 1.01 m 12.01 17.60 0.00 0.00 0.00 0.00 2.96 1.08 33.32 33.65
Soakers and slates
Code 4 lead soakers (fixing by
slater or tiler)
186 175 x 165 mm 7.00 nr 4.97 9.03 0.00 0.00 0.00 0.00 1.40 0.49 2.27 15.89
Subtotal for H Cladding/Covering 32.03 66.83 0.00 0.00 209.47 0.00 30.81 11.20 350.34
Total for Item 8.18 202.52 170.27 0.00 0.00 209.47 0.00 58.27 21.23 661.77
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 54
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 9.5
H CLADDING/COVERING
H60 Plain roof tiling
Sub-contract purchase
Extra over for
187 valleys; cutting both sides 7.74 m 0.00 0.00 0.00 0.00 178.02 0.00 17.80 6.50 26.14 202.32
Subtotal for H Cladding/Covering 0.00 0.00 0.00 0.00 178.02 0.00 17.80 6.50 202.32
Total for Item 9.5 0.00 0.00 0.00 0.00 178.02 0.00 17.80 6.50 202.32
ITEM 9.6
Clay plain tiles; Dreadnought
machine made smooth red or
other
equal and approved on 19 x
38mm treated battens and
breather membrane
188 roof coverings to 64mm lap 42.21 m2
0.00 0.00 0.00 0.00 2855.08 0.00 285.34 103.84 76.86 3,244.26
Total for Item 9.6 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,244.26
ITEM 9.7
Extra over for
189 double course at eaves 12.64 m 0.00 0.00 0.00 0.00 134.49 0.00 13.40 4.93 12.09 152.82
Total for Item 9.7 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 152.82
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 55
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 9.8
H CLADDING/COVERING
H60 Plain roof tiling
Sub-contract purchase
Extra over for
190 bonnet hip tiles; cutting both
sides 14.25 m 0.00 0.00 0.00 0.00 1080.01 0.00 108.02 39.33 86.13 1,227.35
191 hip irons 2.00 nr 0.00 0.00 0.00 0.00 7.18 0.00 0.72 0.26 4.08 8.16
Subtotal for H Cladding/Covering 0.00 0.00 0.00 0.00 4076.76 0.00 407.48 148.36 1,235.51
Total for Item 9.8 0.00 0.00 0.00 0.00 4076.76 0.00 407.48 148.36 1,235.51
ITEM 9.11
H CLADDING/COVERING
H60 Plain roof tiling
Sub-contract purchase
Extra over for
192 ridge tiles 2.73 m 0.00 0.00 0.00 0.00 78.84 0.00 7.89 2.87 32.82 89.60
Subtotal for H Cladding/Covering 0.00 0.00 0.00 0.00 78.84 0.00 7.89 2.87 89.60
Total for Item 9.11 0.00 0.00 0.00 0.00 78.84 0.00 7.89 2.87 89.60
ITEM 10.1
J WATERPROOFING
J42 Built up roof coverings
Bauder Waterproof System
193 to timber or metal decking;
pitch not exceeding 5 degrees 9.57 m2
0.00 0.00 0.00 0.00 392.56 0.00 39.24 14.26 46.61 446.06
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 56
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
J WATERPROOFING continued ...
J42 Built up roof continued ...
Bauder Waterproof continued ...
194 kerb detail to Bauder
waterproof membrane, girth
not exceeding 400mm 24.59 m 0.00 0.00 0.00 0.00 1243.76 0.00 124.43 45.25 57.48 1,413.43
Tapered Insulation Board
Underlays
195 tapered PIR board;
mechanically fastened 9.57 m2
0.00 0.00 0.00 0.00 593.72 0.00 59.33 21.63 70.50 674.69
Subtotal for J Waterproofing 0.00 0.00 0.00 0.00 2230.04 0.00 223.00 81.14 2,534.18
Total for Item 10.1 0.00 0.00 0.00 0.00 2230.04 0.00 223.00 81.14 2,534.18
ITEM 10.4
H71 Lead sheet
coverings/flashings
Flashings, aprons
Code 4 lead, horizontal, 150
mm lapped joints, fixing with
lead clips
and wedges
196 300 mm girth 9.36 m 55.69 148.73 0.00 0.00 0.00 0.00 20.40 7.49 24.82 232.32
Total for Item 10.4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 232.32
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 57
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 10.5
H CLADDING/COVERING
H71 Lead sheet
coverings/flashings
Outlets
Code 4 lead, 150 mm lapped
joints, fixing with lead cleats
and brass
scews
197 600 mm girth 1.00 m 42.80 34.85 0.00 0.00 0.00 0.00 7.77 2.83 88.25 88.25
Subtotal for H Cladding/Covering 98.49 183.58 0.00 0.00 0.00 0.00 28.17 10.32 88.25
Total for Item 10.5 98.49 183.58 0.00 0.00 0.00 0.00 28.17 10.32 88.25
ITEM 10.6
C EXISTING
SITE/BUILDINGS/SERVICES
C90 Alterations - spot items
Coverings
Stripping and repairs to slate
and tile roofs
198 roofing felt or single ply
waterproofing membrane;
dispose of debris off-site 2.99 m2
14.26 0.00 1.79 0.00 0.00 0.00 1.61 0.57 6.10 18.24
Subtotal for C Existing ... 14.26 0.00 1.79 0.00 0.00 0.00 1.61 0.57 18.24
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 58
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
J WATERPROOFING
J42 Built up roof coverings
Bauder Waterproof System
199 to timber or metal decking;
pitch not exceeding 5 degrees 2.99 m2
0.00 0.00 0.00 0.00 122.65 0.00 12.26 4.46 46.61 139.36
200 kerb detail to Bauder
waterproof membrane, girth
not exceeding 400mm 12.28 m 0.00 0.00 0.00 0.00 621.12 0.00 62.14 22.60 57.48 705.85
Tapered Insulation Board
Underlays
201 tapered PIR board;
mechanically fastened 2.99 m2
0.00 0.00 0.00 0.00 185.50 0.00 18.54 6.76 70.50 210.80
H71 Lead sheet
coverings/flashings
Flashings, aprons
Code 4 lead, horizontal, 150
mm lapped joints, fixing with
lead clips
and wedges
202 300 mm girth 12.28 m 73.07 195.13 0.00 0.00 0.00 0.00 26.77 9.82 24.82 304.79
Subtotal for J Waterproofing 73.07 195.13 0.00 0.00 929.27 0.00 119.71 43.64 1,360.80
Total for Item 10.6 87.33 195.13 1.79 0.00 929.27 0.00 121.32 44.21 1,379.04
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 59
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 11.1
C EXISTING
SITE/BUILDINGS/SERVICES
C90 Alterations - spot items
Gutterwork
Remove gutters and supports,
dispose of debris off-site
203 cast iron 27.67 m 203.93 0.00 16.60 0.00 0.00 0.00 22.14 8.02 9.06 250.69
Rainwater pipework
Remove rainwater pipes and
supports, dispose of debris
off-site
204 cast iron rainwater stack 6.09 m 44.88 0.00 3.65 0.00 0.00 0.00 4.87 1.77 9.06 55.18
Subtotal for C Existing ... 248.81 0.00 20.25 0.00 0.00 0.00 27.01 9.79 305.87
Total for Item 11.1 248.81 0.00 20.25 0.00 0.00 0.00 27.01 9.79 305.87
ITEM 11.2
R DISPOSAL SYSTEMS
R10 Rainwater
pipework/gutters
Brett Martin Cascade rainwater
system
Gutters
205 112mm half round gutter 35.26 m 259.87 474.60 0.00 0.00 0.00 0.00 73.34 26.80 23.67 834.60
Subtotal for R Disposal Systems 259.87 474.60 0.00 0.00 0.00 0.00 73.34 26.80 834.60
Total for Item 11.2 259.87 474.60 0.00 0.00 0.00 0.00 73.34 26.80 834.60
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 60
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 11.3
R DISPOSAL SYSTEMS
R10 Rainwater
pipework/gutters
Brett Martin Cascade rainwater
system
Rainwater pipes
206 68mm round downpipes 11.29 m 83.21 243.41 0.00 0.00 0.00 0.00 32.63 11.85 32.87 371.10
Subtotal for R Disposal Systems 83.21 243.41 0.00 0.00 0.00 0.00 32.63 11.85 371.10
Total for Item 11.3 83.21 243.41 0.00 0.00 0.00 0.00 32.63 11.85 371.10
ITEM 11.4
R DISPOSAL SYSTEMS
R10 Rainwater
pipework/gutters
Brett Martin Cascade rainwater
system
Extra for
207 hopper head 2.00 nr 14.74 81.48 0.00 0.00 0.00 0.00 9.62 3.52 54.68 109.36
Subtotal for R Disposal Systems 14.74 81.48 0.00 0.00 0.00 0.00 9.62 3.52 109.36
Total for Item 11.4 14.74 81.48 0.00 0.00 0.00 0.00 9.62 3.52 109.36
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 61
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 11.5
R DISPOSAL SYSTEMS
R10 Rainwater
pipework/gutters
Brett Martin Cascade rainwater
system
Extra for
208 angles 5.00 nr 30.90 76.55 0.00 0.00 0.00 0.00 10.75 3.90 24.42 122.10
209 stopped ends 2.00 nr 5.70 15.50 0.00 0.00 0.00 0.00 2.12 0.78 12.05 24.10
210 outlets 4.00 nr 24.72 59.76 0.00 0.00 0.00 0.00 8.44 3.08 24.00 96.00
211 offset 4.00 nr 29.48 124.20 0.00 0.00 0.00 0.00 15.36 5.60 43.66 174.64
Subtotal for R Disposal Systems 90.80 276.01 0.00 0.00 0.00 0.00 36.67 13.36 416.84
Total for Item 11.5 90.80 276.01 0.00 0.00 0.00 0.00 36.67 13.36 416.84
ITEM 12.2
L WINDOWS/DOORS/STAIRS
L10
Windows/rooflights/screens/louvres
Supply & fix
212 Manufacturer quotation;
windows and doors; supply &
fix item 0.00 0.00 0.00 0.00 7525.00 0.00 752.50 274.18 8551.68 8,551.68
Subtotal for L Windows/Doors/Stairs 0.00 0.00 0.00 0.00 7525.00 0.00 752.50 274.18 8,551.68
Total for Item 12.2 0.00 0.00 0.00 0.00 7525.00 0.00 752.50 274.18 8,551.68
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 62
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 12.4
P BUILDING FABRIC SUNDRIES
P20 Unframed isolated
trims/skirtings/sundry items
Window boards
MDF with rounded nosing
213 25 x 219 mm 3.14 m 17.02 14.38 0.00 0.00 0.00 0.00 3.14 1.13 11.36 35.67
214 returned ends 8.00 nr 9.04 0.00 0.00 0.00 0.00 0.00 0.88 0.32 1.28 10.24
Subtotal for P Building Fabric ... 26.06 14.38 0.00 0.00 0.00 0.00 4.02 1.45 45.91
Total for Item 12.4 26.06 14.38 0.00 0.00 0.00 0.00 4.02 1.45 45.91
ITEM 12.5
L WINDOWS/DOORS/STAIRS
L10
Windows/rooflights/screens/louvres
Fixing only
215 Fix only softwood casement
windows 0.38 m2
15.69 0.00 0.00 0.00 0.00 0.00 1.57 0.57 46.93 17.83
Subtotal for L Windows/Doors/Stairs 15.69 0.00 0.00 0.00 0.00 0.00 1.57 0.57 17.83
Total for Item 12.5 15.69 0.00 0.00 0.00 0.00 0.00 1.57 0.57 17.83
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 63
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 13.1
L WINDOWS/DOORS/STAIRS
L10
Windows/rooflights/screens/louvres
Roof Lights
Monodraught diamond dome
sunpipe
216 300mm diameter 2.00 nr 135.48 471.46 0.00 0.00 0.00 0.00 60.70 22.12 344.88 689.76
Subtotal for L Windows/Doors/Stairs 135.48 471.46 0.00 0.00 0.00 0.00 60.70 22.12 689.76
Total for Item 13.1 135.48 471.46 0.00 0.00 0.00 0.00 60.70 22.12 689.76
ITEM 13.3
Z PC SUMS
PC Sums associated with the
project
217 supply of lantern lights from HLI
Building Products item 0.00 0.00 0.00 0.00 3228.00 0.00 322.80 117.62 3668.42 3,668.42
218 fixing of lantern lights including
wireways for electrical
connections item 0.00 0.00 0.00 400.00 0.00 0.00 40.00 14.57 454.57 454.57
Subtotal for Z Pc Sums 0.00 0.00 0.00 400.00 3228.00 0.00 362.80 132.19 4,122.99
Total for Item 13.3 0.00 0.00 0.00 400.00 3228.00 0.00 362.80 132.19 4,122.99
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 64
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 14.1
M SURFACE FINISHES
M20
Plastered/Rendered/Roughcast
coatings
Gypsum plasterboard to BS
1230
Fixing with screws to ceilings
219 12.5 mm Plain Wallboard
over 300 mm wide 57.77 m2
413.63 129.40 0.00 0.00 0.00 0.00 54.30 19.64 10.68 616.98
Subtotal for M Surface Finishes 413.63 129.40 0.00 0.00 0.00 0.00 54.30 19.64 616.98
Total for Item 14.1 413.63 129.40 0.00 0.00 0.00 0.00 54.30 19.64 616.98
ITEM 14.2
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Wall or partition members
220 50 x 50mm 47.97 m 118.97 39.34 0.00 0.00 0.00 0.00 15.83 5.76 3.75 179.89
Subtotal for G ... 118.97 39.34 0.00 0.00 0.00 0.00 15.83 5.76 179.89
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 65
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
M SURFACE FINISHES
M20
Plastered/Rendered/Roughcast
coatings
Gypsum plasterboard to BS
1230
Fixing with screws to ceilings
221 12.5 mm Plain Wallboard
over 300 mm wide 10.25 m2
73.39 22.96 0.00 0.00 0.00 0.00 9.64 3.49 10.68 109.47
Subtotal for M Surface Finishes 73.39 22.96 0.00 0.00 0.00 0.00 9.64 3.49 109.47
Total for Item 14.2 192.36 62.30 0.00 0.00 0.00 0.00 25.47 9.25 289.36
ITEM 14.3
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Wall or partition members
222 50 x 75mm 60.19 m 190.20 65.01 0.00 0.00 0.00 0.00 25.28 9.03 4.81 289.51
Subtotal for G ... 190.20 65.01 0.00 0.00 0.00 0.00 25.28 9.03 289.51
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 66
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
P BUILDING FABRIC SUNDRIES
P10 Sundry insulation/proofing
work/fire stops
Insulating quilts
Acoustic insulating quilts
223 50 mm 7.55 m2
11.93 25.07 0.00 0.00 0.00 0.00 3.70 1.36 5.57 42.05
Subtotal for P Building Fabric ... 11.93 25.07 0.00 0.00 0.00 0.00 3.70 1.36 42.05
M SURFACE FINISHES
M20
Plastered/Rendered/Roughcast
coatings
Gypsum plasterboard to BS
1230
Fixing with screws to timber or
steel stud framing
224 12.5 mm Plain Wallboard
over 300 mm wide 30.20 m2
195.09 67.65 0.00 0.00 0.00 0.00 26.27 9.66 9.89 298.68
Subtotal for M Surface Finishes 195.09 67.65 0.00 0.00 0.00 0.00 26.27 9.66 298.68
Total for Item 14.3 397.22 157.73 0.00 0.00 0.00 0.00 55.25 20.05 630.24
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 67
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 14.4
K LININGS/SHEATHING/DRY
PARTITIONING
K11 Rigid sheet
flooring/sheathing/linings/casings
Sheet linings and casings
Tile backer boards
225 12.5mm Wediboard 5.93 m2
49.52 142.97 0.00 0.00 0.00 0.00 19.27 7.00 36.89 218.76
Subtotal for K ... 49.52 142.97 0.00 0.00 0.00 0.00 19.27 7.00 218.76
Total for Item 14.4 49.52 142.97 0.00 0.00 0.00 0.00 19.27 7.00 218.76
ITEM 14.5
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Wall or partition members
226 38 x 50mm 52.80 m 166.85 39.60 0.00 0.00 0.00 0.00 20.59 7.39 4.44 234.43
Subtotal for G ... 166.85 39.60 0.00 0.00 0.00 0.00 20.59 7.39 234.43
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 68
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
M SURFACE FINISHES
M20
Plastered/Rendered/Roughcast
coatings
Gypsum plasterboard to BS
1230
Fixing with screws to timber or
steel stud framing
227 12.5 mm Plain Wallboard
over 300 mm wide 20.86 m2
134.76 46.73 0.00 0.00 0.00 0.00 18.15 6.68 9.89 206.31
Subtotal for M Surface Finishes 134.76 46.73 0.00 0.00 0.00 0.00 18.15 6.68 206.31
Total for Item 14.5 301.61 86.33 0.00 0.00 0.00 0.00 38.74 14.07 440.74
ITEM 14.6
M SURFACE FINISHES
M20
Plastered/Rendered/Roughcast
coatings
Retarded hemihydrate gypsum
("Thistle") plasters to BS 1191,
Class B
3 mm board finish on walls or
ceilings including scrimming
joints
228 over 300 mm wide 93.73 m2
589.56 66.55 0.00 0.00 0.00 0.00 65.61 24.37 7.96 746.09
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 69
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
M SURFACE continued ...
M20
Plastered/Rendered/Roughcast
coatings continued ...
Plastering sundries
Galvanised plaster beads
229 thin coat angle bead 52.55 m 64.11 22.07 0.00 0.00 0.00 0.00 8.41 3.15 1.86 97.74
Subtotal for M Surface Finishes 653.67 88.62 0.00 0.00 0.00 0.00 74.02 27.52 843.83
Total for Item 14.6 653.67 88.62 0.00 0.00 0.00 0.00 74.02 27.52 843.83
ITEM 14.8
M SURFACE FINISHES
M20
Plastered/Rendered/Roughcast
coatings
Retarded hemihydrate gypsum
("Thistle") plasters to BS 1191,
Class B
13 mm two coat plastering on
brick or block walls
230 over 300 mm wide 62.70 m2
1040.82 217.57 0.00 0.00 0.00 0.00 126.03 45.77 22.81 1,430.19
Subtotal for M Surface Finishes 1040.82 217.57 0.00 0.00 0.00 0.00 126.03 45.77 1,430.19
Total for Item 14.8 1040.82 217.57 0.00 0.00 0.00 0.00 126.03 45.77 1,430.19
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 70
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 14.10
M SURFACE FINISHES
M20
Plastered/Rendered/Roughcast
coatings
Gypsum plasterboard to BS
1230
Fixing with screws to ceilings
231 12.5 mm Plain Wallboard
over 300 mm wide 9.17 m2
65.66 20.54 0.00 0.00 0.00 0.00 8.62 3.12 10.68 97.94
Retarded hemihydrate gypsum
("Thistle") plasters to BS 1191,
Class B
3 mm board finish on walls or
ceilings including scrimming
joints
232 over 300 mm wide 9.17 m2
57.68 6.51 0.00 0.00 0.00 0.00 6.42 2.38 7.96 72.99
Subtotal for M Surface Finishes 123.34 27.05 0.00 0.00 0.00 0.00 15.04 5.50 170.93
Total for Item 14.10 123.34 27.05 0.00 0.00 0.00 0.00 15.04 5.50 170.93
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 71
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 15.1
L WINDOWS/DOORS/STAIRS
L20 Doors/shutters/hatches
Softwood door frames and
linings
Door lining sets
233 32 x 115mm internal door
lining with loose stops 3.00 nr 47.43 38.97 0.00 0.00 0.00 0.00 8.64 3.15 32.73 98.19
Subtotal for L Windows/Doors/Stairs 47.43 38.97 0.00 0.00 0.00 0.00 8.64 3.15 98.19
Total for Item 15.1 47.43 38.97 0.00 0.00 0.00 0.00 8.64 3.15 98.19
ITEM 15.2
Z PC SUMS
PC Sums associated with the
project
234 supply of internal doors, 4 nr @
£120 each item 0.00 0.00 0.00 0.00 0.00 480.00 0.00 15.90 495.90 495.90
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 480.00 0.00 15.90 495.90
L WINDOWS/DOORS/STAIRS
L20 Doors/shutters/hatches
Fixing
235 hang internal door in 1 pair of
butt hinges 4.00 nr 67.76 0.00 0.00 0.00 0.00 0.00 6.76 2.48 19.25 77.00
Subtotal for L Windows/Doors/Stairs 67.76 0.00 0.00 0.00 0.00 0.00 6.76 2.48 77.00
Total for Item 15.2 67.76 0.00 0.00 0.00 0.00 480.00 6.76 18.38 572.90
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 72
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 15.3
Z PC SUMS
PC Sums associated with the
project
236 supply of JEDO door lever
handles, 4 @ £17.49 each item 0.00 0.00 0.00 0.00 0.00 69.96 0.00 2.32 72.28 72.28
237 supply of JEDO satin thumb turn item 0.00 0.00 0.00 0.00 0.00 7.71 0.00 0.26 7.97 7.97
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 77.67 0.00 2.58 80.25
P BUILDING FABRIC SUNDRIES
P21 Ironmongery
Fixing only to softwood
Door handles
238 lever handles on rose 4.00 pair 32.52 0.00 0.00 0.00 0.00 0.00 3.24 1.20 9.24 36.96
Latches
239 thumb latches 1.00 nr 13.55 0.00 0.00 0.00 0.00 0.00 1.36 0.49 15.40 15.40
240 75mm mortice latch 3.00 nr 54.18 0.00 0.00 0.00 0.00 0.00 5.43 1.98 20.53 61.59
Butt hinges
241 100mm 4.00 pair 28.00 0.00 0.00 0.00 0.00 0.00 2.80 1.04 7.96 31.84
Subtotal for P Building Fabric ... 128.25 0.00 0.00 0.00 0.00 0.00 12.83 4.71 145.79
Total for Item 15.3 128.25 0.00 0.00 0.00 0.00 77.67 12.83 7.29 226.04
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 73
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 15.4
Z PC SUMS
PC Sums associated with the
project
242 additional ironmongery item 0.00 0.00 0.00 0.00 0.00 300.00 0.00 9.94 309.94 309.94
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 300.00 0.00 9.94 309.94
Total for Item 15.4 0.00 0.00 0.00 0.00 0.00 300.00 0.00 9.94 309.94
ITEM 15.5
Z PC SUMS
PC Sums associated with the
project
243 supply & fix new section of
staircase including mopstick
handrails item 0.00 0.00 0.00 0.00 0.00 500.00 0.00 16.56 516.56 516.56
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 500.00 0.00 16.56 516.56
Total for Item 15.5 0.00 0.00 0.00 0.00 0.00 500.00 0.00 16.56 516.56
ITEM 15.7
P BUILDING FABRIC SUNDRIES
P20 Unframed isolated
trims/skirtings/sundry items
Skirtings, picture rails,
architraves and the like
Wrought softwood skirtings
244 25 x 75 mm Torus 48.09 m 119.26 72.62 0.00 0.00 0.00 0.00 19.24 7.21 4.54 218.33
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 74
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
P BUILDING FABRIC continued ...
P20 Unframed isolated
continued ...
Skirtings, picture rails,
architraves and the continued ...
Wrought softwood architraves
245 19 x 75 mm chamfered 40.00 m 99.20 54.80 0.00 0.00 0.00 0.00 15.60 5.60 4.38 175.20
Subtotal for P Building Fabric ... 218.46 127.42 0.00 0.00 0.00 0.00 34.84 12.81 393.53
Total for Item 15.7 218.46 127.42 0.00 0.00 0.00 0.00 34.84 12.81 393.53
ITEM 15.8
Z PC SUMS
PC Sums associated with the
project
246 provide gas bottle enclosure;
supply & fix item 0.00 0.00 0.00 0.00 0.00 750.00 0.00 24.84 774.84 774.84
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 750.00 0.00 24.84 774.84
Total for Item 15.8 0.00 0.00 0.00 0.00 0.00 750.00 0.00 24.84 774.84
ITEM 15.8
Z PC SUMS
PC Sums associated with the
project
247 supply gas bottles and
switchover valve item 0.00 0.00 0.00 0.00 0.00 115.00 0.00 3.81 118.81 118.81
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 115.00 0.00 3.81 118.81
Total for Item 15.8 0.00 0.00 0.00 0.00 0.00 115.00 0.00 3.81 118.81
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 75
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 16.3
Z PC SUMS
PC Sums associated with the
project
248 sealant sub-contractor for 0.5
day item 0.00 0.00 0.00 0.00 250.00 0.00 0.00 8.28 258.28 258.28
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 250.00 0.00 0.00 8.28 258.28
Total for Item 16.3 0.00 0.00 0.00 0.00 250.00 0.00 0.00 8.28 258.28
ITEM 16.4
Z PC SUMS
PC Sums associated with the
project
249 Lamona Ceramic 1.5 bowl sink
including waste and taps item 0.00 0.00 0.00 0.00 0.00 346.50 0.00 11.48 357.98 357.98
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 346.50 0.00 11.48 357.98
N FURNITURE/EQUIPMENT
N13 Sanitary appliances/fittings
Fixing only equipment
Connections to service and
waste pipes not included
250 Sink units with waste and
overflow fittings, plug and
chain - fitted to sink units 1.00 nr 0.00 1.06 0.00 0.00 93.59 0.00 9.47 3.45 107.57 107.57
Subtotal for N Furniture/Equipment 0.00 1.06 0.00 0.00 93.59 0.00 9.47 3.45 107.57
Total for Item 16.4 0.00 1.06 0.00 0.00 93.59 346.50 9.47 14.93 465.55
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 76
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 16.5
Z PC SUMS
PC Sums associated with the
project
251 Lamona Ceramic single bowl
sink including waste and taps item 0.00 0.00 0.00 0.00 0.00 183.00 0.00 6.06 189.06 189.06
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 183.00 0.00 6.06 189.06
N FURNITURE/EQUIPMENT
N13 Sanitary appliances/fittings
Fixing only equipment
Connections to service and
waste pipes not included
252 Sink units with waste and
overflow fittings, plug and
chain - fitted to sink units 1.00 nr 0.00 1.06 0.00 0.00 93.59 0.00 9.47 3.45 107.57 107.57
Subtotal for N Furniture/Equipment 0.00 1.06 0.00 0.00 93.59 0.00 9.47 3.45 107.57
Total for Item 16.5 0.00 1.06 0.00 0.00 93.59 183.00 9.47 9.51 296.63
ITEM 16.6
Z PC SUMS
PC Sums associated with the
project
253 Supply ROCA Easy 900 x 900 x
80mm shower tray item 0.00 0.00 0.00 0.00 0.00 141.81 0.00 4.70 146.51 146.51
254 Supply ROCA shower waste to
suit above tray item 0.00 0.00 0.00 0.00 0.00 62.29 0.00 2.06 64.35 64.35
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 77
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
Z PC SUMS continued ...
PC Sums associated with the
project continued ...
255 Supply ROCA L90 shower mixer
valve item 0.00 0.00 0.00 0.00 0.00 197.61 0.00 6.55 204.16 204.16
256 Supply ROCA Raindream
circular shower head item 0.00 0.00 0.00 0.00 0.00 167.67 0.00 5.55 173.22 173.22
257 Supply ROCA 500mm support
arm item 0.00 0.00 0.00 0.00 0.00 41.67 0.00 1.38 43.05 43.05
258 Supply ROCA L90 basin mixer
tap item 0.00 0.00 0.00 0.00 0.00 172.91 0.00 5.73 178.64 178.64
259 Supply ROCA Nexo 500 corner
cloakroom basin item 0.00 0.00 0.00 0.00 0.00 94.34 0.00 3.12 97.46 97.46
260 Supply ROCA Nexo close
coupled WC item 0.00 0.00 0.00 0.00 0.00 216.71 0.00 7.18 223.89 223.89
261 Supply ROCA Nexo WC seat &
cover item 0.00 0.00 0.00 0.00 0.00 48.93 0.00 1.62 50.55 50.55
262 Supply Mira Beam 900mm pivot
shower door item 0.00 0.00 0.00 0.00 0.00 224.38 0.00 7.43 231.81 231.81
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 1368.32 0.00 45.32 1,413.64
N FURNITURE/EQUIPMENT
N13 Sanitary appliances/fittings
Fixing only equipment
Connections to service and
waste pipes not included
263 Shower tray 1.00 nr 0.00 0.00 0.00 0.00 101.72 0.00 10.17 3.71 115.60 115.60
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 78
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
N continued ...
N13 Sanitary continued ...
Fixing only continued ...
Connections to service and
waste pipes not continued ...
264 Shower mixer 1.00 nr 0.00 0.00 0.00 0.00 123.15 0.00 12.32 4.49 139.96 139.96
265 Shower screen 1.00 nr 0.00 0.00 0.00 0.00 158.48 0.00 15.85 5.77 180.10 180.10
266 Wash hand basin 1.00 nr 0.00 0.00 0.00 0.00 75.92 0.00 7.59 2.77 86.28 86.28
267 Vitreous china lavatory
basins with waste fitting,
plug, chain and
stay, bracket plugged to wall 1.00 nr 0.00 0.00 0.00 0.00 82.64 0.00 8.26 3.01 93.91 93.91
Subtotal for N Furniture/Equipment 0.00 0.00 0.00 0.00 541.91 0.00 54.19 19.75 615.85
Total for Item 16.6 0.00 0.00 0.00 0.00 541.91 1368.32 54.19 65.07 2,029.49
ITEM 16.7
R DISPOSAL SYSTEMS
R11 Foul drainage above
ground
Sub-contract purchase
268 32mm waste pipe including
elbows and branches 3.00 m 0.00 0.00 0.00 0.00 22.05 0.00 2.22 0.81 8.36 25.08
269 40mm waste pipe including
elbows and branches 9.00 m 0.00 0.00 0.00 0.00 78.30 0.00 7.83 2.88 9.89 89.01
270 110mm waste pipe including
elbows and branches 0.30 m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 79
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
R DISPOSAL continued ...
R11 Foul drainage above
ground continued ...
Sub-contract continued ...
271 two storey soil stack 1.00 nr 0.00 0.00 0.00 0.00 495.45 0.00 49.55 18.05 563.05 563.05
Subtotal for R Disposal Systems 0.00 0.00 0.00 0.00 595.80 0.00 59.60 21.74 677.14
Total for Item 16.7 0.00 0.00 0.00 0.00 595.80 0.00 59.60 21.74 677.14
ITEM 17.1
M SURFACE FINISHES
M40
Stone/Concrete/Quarry/Ceramic
tiling/Mosaic
Floor Tiles
Fixing with adhesive
272 over 300 mm wide; ASS
Daple stube panaria wood
effect tiles 200 x 905mm 50.54 m2
1590.49 2370.33 0.00 0.00 0.00 0.00 396.23 144.54 89.07 4,501.60
Floor & Wall Tiles
273 over 300 mm wide; Nettuno
noce Cisa Let Fontare tiles
333 x 333mm 22.19 m2
698.32 2775.75 0.00 0.00 0.00 0.00 347.50 126.48 177.92 3,948.04
Subtotal for M Surface Finishes 2288.81 5146.08 0.00 0.00 0.00 0.00 743.73 271.02 8,449.64
Total for Item 17.1 2288.81 5146.08 0.00 0.00 0.00 0.00 743.73 271.02 8,449.64
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 80
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 17.3
M SURFACE FINISHES
M40
Stone/Concrete/Quarry/Ceramic
tiling/Mosaic
Floor & Wall tiling accessories
Schulter Ditra matting
274 Ditra 25 matting over 300
mm wide 54.10 m2
144.99 472.83 0.00 0.00 0.00 0.00 61.67 22.72 12.98 702.22
Subtotal for M Surface Finishes 144.99 472.83 0.00 0.00 0.00 0.00 61.67 22.72 702.22
Total for Item 17.3 144.99 472.83 0.00 0.00 0.00 0.00 61.67 22.72 702.22
ITEM 18.1
M SURFACE FINISHES
M60 Painting/Clear finishing
General surfaces
Two coats of Dulex coloured
matt emulsion paint over 300
mm girth
275 smooth plaster 140.93 m2
528.49 135.29 0.00 0.00 0.00 0.00 66.24 23.96 5.35 753.98
Knot, prime, stop and paint
one undercoat and one coat of
satinwood finish paint on
joinery
276 over 300 mm girth 15.12 m2
54.13 24.80 0.00 0.00 0.00 0.00 7.86 2.87 5.93 89.66
277 isolated surfaces, not
exceeding 300 mm girth 93.09 m 133.12 50.27 0.00 0.00 0.00 0.00 18.62 6.52 2.24 208.52
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 81
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
M SURFACE continued ...
M60 continued ...
General surfaces, externally
Knot, prime, stop and paint
two undercoats and one coat
of gloss
finish paint on joinery
278 over 300 mm girth 3.20 m2
20.03 5.50 0.00 0.00 0.00 0.00 2.56 0.93 9.07 29.02
279 isolated surfaces, not
exceeding 300 mm girth 35.17 m 87.93 18.99 0.00 0.00 0.00 0.00 10.55 3.87 3.45 121.34
M52 Decorative papers/fabrics
Generally
Prepare, size and hang
wallpaper supplied by others
to
280 walls 51.22 m2
210.51 11.78 0.00 0.00 0.00 0.00 22.02 8.20 4.93 252.51
Subtotal for M Surface Finishes 1034.21 246.63 0.00 0.00 0.00 0.00 127.85 46.35 1,455.03
Total for Item 18.1 1034.21 246.63 0.00 0.00 0.00 0.00 127.85 46.35 1,455.03
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 82
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 19.1
M SURFACE FINISHES
M51 Edge fixed carpeting
Underlay
Latex carpet underlay to floors
level and to falls not exceeding
15 degrees from horizontal on
timber base
281 exceeding 300 m wide 28.45 m2
25.32 34.42 0.00 0.00 0.00 0.00 5.97 2.28 2.39 68.00
Fitted carpet
Medium duty tufted wool/nylon
carpet fixed with gripper rods
to floors level and to floors not
exceeding 15 degrees from
horizontal on timber base
282 exceeding 300 m wide 28.45 m2
162.73 652.93 0.00 0.00 0.00 0.00 81.65 29.59 32.58 926.90
Subtotal for M Surface Finishes 188.05 687.35 0.00 0.00 0.00 0.00 87.62 31.87 994.90
Total for Item 19.1 188.05 687.35 0.00 0.00 0.00 0.00 87.62 31.87 994.90
ITEM 21.1
Z PC SUMS
PC Sums associated with the
project
283 Supply of Kitchen & Utility units;
Ref Howdens quotation dated
1st April 2015 item 0.00 0.00 0.00 0.00 0.00 10226.35 0.00 338.00 10565.08 10,565.08
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 83
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
Z PC SUMS continued ...
PC Sums associated with the
project continued ...
284 Fitting of Kitchen, Utility units
and white goods item 0.00 0.00 0.00 0.00 0.00 2000.00 0.00 66.25 2066.25 2,066.25
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 12226.35 0.00 404.25 12,631.33
Total for Item 21.1 0.00 0.00 0.00 0.00 0.00 12226.35 0.00 404.25 12,631.33
ITEM 22.1
P BUILDING FABRIC SUNDRIES
P30 Trenches/Pipeways/Pits for
buried engineering services
Excavate by hand
Trenches to receive service
pipes, cables etc, grade
bottom, fill in and compact
and remove surplus -
earthwork support not included
- average depth not exceeding
285 1.00 m, electricity duct 2.06 m 48.06 3.09 0.52 0.00 0.00 0.00 5.17 1.87 28.50 58.71
Subtotal for P Building Fabric ... 48.06 3.09 0.52 0.00 0.00 0.00 5.17 1.87 58.71
Total for Item 22.1 48.06 3.09 0.52 0.00 0.00 0.00 5.17 1.87 58.71
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 84
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 22.2
P BUILDING FABRIC SUNDRIES
P30 Trenches/Pipeways/Pits for
buried engineering services
Excavate by hand
Trenches to receive service
pipes, cables etc, grade
bottom, fill in and compact
and remove surplus -
earthwork support not included
- average depth not exceeding
286 1.00 m, water service pipe 8.74 m 203.90 7.34 2.19 0.00 0.00 0.00 21.33 7.78 27.75 242.54
Subtotal for P Building Fabric ... 203.90 7.34 2.19 0.00 0.00 0.00 21.33 7.78 242.54
Total for Item 22.2 203.90 7.34 2.19 0.00 0.00 0.00 21.33 7.78 242.54
ITEM 22.3
Z PC SUMS
PC Sums associated with the
project
287 UK Power Networks quotation to
divert electricity supply item 0.00 0.00 0.00 0.00 0.00 864.00 0.00 28.62 892.62 892.62
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 864.00 0.00 28.62 892.62
Total for Item 22.3 0.00 0.00 0.00 0.00 0.00 864.00 0.00 28.62 892.62
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 85
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 22.4
D GROUNDWORK
D20 Excavating and filling
Filling to make up levels
Imported MOT Type 1 material
288 not exceeding 0.25 m 1.79 m3
29.91 78.76 0.00 0.00 0.00 0.00 10.87 3.96 68.99 123.49
Surface treatments
Compacting
289 surface of filling 17.83 m2
7.67 0.00 1.96 0.00 0.00 0.00 0.89 0.36 0.61 10.88
Subtotal for D Groundwork 37.58 78.76 1.96 0.00 0.00 0.00 11.76 4.32 134.37
Q
PAVING/PLANTING/FENCING/SITE
FURNITURE
Q25 Slab/Brick/Sett/Cobble
pavings
Plain PCC slab paving
Salvaged paving; 50 mm thick
slabs, 50 mm sand base, 6
mm straight joints both ways,
pointing in cement mortar
(1:3), level and to falls only,
slab size
290 450 x 450mm 17.83 m2
89.33 103.41 1.60 0.00 0.00 0.00 19.43 7.13 12.39 220.91
Subtotal for Q ... 89.33 103.41 1.60 0.00 0.00 0.00 19.43 7.13 220.91
Total for Item 22.4 126.91 182.17 3.56 0.00 0.00 0.00 31.19 11.45 355.28
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 86
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 23.1
Z PC SUMS
PC Sums associated with the
project
291 Thermo Floor quoation for the
supply & installation of under
floor heating item 0.00 0.00 0.00 0.00 0.00 2130.00 0.00 70.55 2200.55 2,200.55
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 2130.00 0.00 70.55 2,200.55
Total for Item 23.1 0.00 0.00 0.00 0.00 0.00 2130.00 0.00 70.55 2,200.55
ITEM 23.2
T MECHANICAL
HEATING/COOLING/REFRIGERATION
SYSTEMS
T73 Works associated with
Heating installations
Sub-contract purchase
292 Worcester Bosch boiler 1.00 nr 0.00 0.00 0.00 0.00 1529.22 0.00 152.92 55.72 1737.86 1,737.86
293 210L Megaflo hot water
cylinder 1.00 nr 0.00 0.00 0.00 0.00 1718.53 0.00 171.85 62.62 1953.00 1,953.00
Subtotal for T Mechanical ... 0.00 0.00 0.00 0.00 3247.75 0.00 324.77 118.34 3,690.86
Total for Item 23.2 0.00 0.00 0.00 0.00 3247.75 0.00 324.77 118.34 3,690.86
ITEM 23.6
S PIPED SUPPLY SYSTEMS
S10 Cold Water
Sub-contract purchase
294 cold water point 5.00 nr 0.00 0.00 0.00 0.00 720.95 0.00 72.10 26.25 163.86 819.30
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 87
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
S PIPED SUPPLY continued ...
S11 Hot water
Sub-contract purchase
295 hot water point 4.00 nr 0.00 0.00 0.00 0.00 987.04 0.00 98.72 35.96 280.43 1,121.72
Subtotal for S Piped Supply ... 0.00 0.00 0.00 0.00 1707.99 0.00 170.82 62.21 1,941.02
Total for Item 23.6 0.00 0.00 0.00 0.00 1707.99 0.00 170.82 62.21 1,941.02
ITEM 23.7
T MECHANICAL
HEATING/COOLING/REFRIGERATION
SYSTEMS
T73 Works associated with
Heating installations
Sub-contract purchase
296 central heating service point 5.00 nr 0.00 0.00 0.00 0.00 2475.40 0.00 247.55 90.20 562.63 2,813.15
297 500mm radiator with TRV 1.00 nr 0.00 0.00 0.00 0.00 154.68 0.00 15.47 5.64 175.79 175.79
298 1000mm radiator with TRV 2.00 nr 0.00 0.00 0.00 0.00 341.84 0.00 34.18 12.46 194.24 388.48
299 1600mm radiator with TRV 4.00 nr 0.00 0.00 0.00 0.00 940.08 0.00 94.00 34.24 267.08 1,068.32
300 Towel rail - fix only; supply of
towel rail taken elsewhere* 1.00 nr 0.00 0.00 0.00 0.00 86.09 0.00 8.61 3.14 97.84 97.84
Subtotal for T Mechanical ... 0.00 0.00 0.00 0.00 3998.09 0.00 399.81 145.68 4,543.58
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 88
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
Z PC SUMS
PC Sums associated with the
project
301 supply of towel rail item 0.00 0.00 0.00 0.00 0.00 400.00 0.00 13.25 413.25 413.25
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 400.00 0.00 13.25 413.25
Total for Item 23.7 0.00 0.00 0.00 0.00 3998.09 400.00 399.81 158.93 4,956.83
ITEM 23.8
S PIPED SUPPLY SYSTEMS
S10 Cold Water
Sub-contract purchase
302 scale inhibitor 1.00 nr 0.00 0.00 0.00 0.00 60.00 0.00 6.00 2.19 68.19 68.19
Subtotal for S Piped Supply ... 0.00 0.00 0.00 0.00 60.00 0.00 6.00 2.19 68.19
Total for Item 23.8 0.00 0.00 0.00 0.00 60.00 0.00 6.00 2.19 68.19
ITEM 24.1
V ELECTRICAL SUPPLY/POWER
LIGHTING SYSTEMS
V22 General Low Voltage
power
Sub-contract purchase
Complete supply & fix
installations
303 consumer unit 1.00 nr 0.00 0.00 0.00 0.00 488.03 0.00 48.80 17.78 554.61 554.61
304 earth bonding 1.00 nr 0.00 0.00 0.00 0.00 177.35 0.00 17.74 6.46 201.55 201.55
305 testing & commisioning 1.00 nr 0.00 0.00 0.00 0.00 88.20 0.00 8.82 3.21 100.23 100.23
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 89
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
V ELECTRICAL SUPPLY/POWER
LIGHTING SYSTEMS continued ...
V22 General Low Voltage
power continued ...
Sub-contract continued ...
Complete supply & fix
installations continued ...
306 2-Gang switched socket
outlet; White 19.00 nr 0.00 0.00 0.00 0.00 613.13 0.00 61.37 22.42 36.68 696.92
307 extractor fan 4.00 nr 0.00 0.00 0.00 0.00 234.40 0.00 23.44 8.56 66.60 266.40
308 boiler electrics 1.00 nr 0.00 0.00 0.00 0.00 486.52 0.00 48.65 17.73 552.90 552.90
309 non-illuminated fused spur 12.00 nr 0.00 0.00 0.00 0.00 435.24 0.00 43.56 15.84 41.22 494.64
V23 Smoke/Heat/Gas alarms
Smoke alarms
310 hard wired smoke alarm 3.00 nr 0.00 0.00 0.00 0.00 211.05 0.00 21.12 7.68 79.95 239.85
Heat alarms
311 hard wired heat alarm 1.00 nr 0.00 0.00 0.00 0.00 70.35 0.00 7.04 2.56 79.95 79.95
V24 Telecoms and Data
TV, FM/DAB service points
312 TV point 2.00 nr 0.00 0.00 0.00 0.00 57.96 0.00 5.80 2.12 32.94 65.88
Subtotal for V Electrical ... 0.00 0.00 0.00 0.00 2862.23 0.00 286.34 104.36 3,252.93
Total for Item 24.1 0.00 0.00 0.00 0.00 2862.23 0.00 286.34 104.36 3,252.93
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 90
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 24.23
V ELECTRICAL SUPPLY/POWER
LIGHTING SYSTEMS
V21 General lighting
Sub-contract purchase
Complete supply & fix
installations
313 bulkhead light 1.00 nr 0.00 0.00 0.00 0.00 66.13 0.00 6.61 2.41 75.15 75.15
314 downlighter 41.00 nr 0.00 0.00 0.00 0.00 1951.19 0.00 195.16 70.93 54.08 2,217.28
315 ceiling rose; White 2.00 nr 0.00 0.00 0.00 0.00 86.24 0.00 8.62 3.14 49.00 98.00
316 photocell floodlight 6.00 nr 0.00 0.00 0.00 0.00 966.66 0.00 96.66 35.22 183.09 1,098.54
317 1-Gang, 1-Way: Light switch:
White 8.00 nr 0.00 0.00 0.00 0.00 259.04 0.00 25.92 9.44 36.80 294.40
318 2-Gang, 2-Way: Light switch:
White 2.00 nr 0.00 0.00 0.00 0.00 132.98 0.00 13.30 4.86 75.57 151.14
319 1-Gang, 1-Way: Pull Cord
Light Switch: White 1.00 nr 0.00 0.00 0.00 0.00 31.31 0.00 3.13 1.14 35.58 35.58
Subtotal for V Electrical ... 0.00 0.00 0.00 0.00 3493.55 0.00 349.40 127.14 3,970.09
Total for Item 24.23 0.00 0.00 0.00 0.00 3493.55 0.00 349.40 127.14 3,970.09
ITEM 24.28
V ELECTRICAL SUPPLY/POWER
LIGHTING SYSTEMS
V50 Electric underfloor heating
Electric Under Floor heating to
320 wet rooms 3.56 m2
0.00 0.00 0.00 0.00 347.31 0.00 34.75 12.67 110.88 394.73
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 91
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
V ELECTRICAL SUPPLY/POWER
LIGHTING SYSTEMS continued ...
V50 Electric continued ...
Electric Under continued ...
321 programmable floor thermostat 1.00 nr 0.00 0.00 0.00 0.00 85.64 0.00 8.56 3.12 97.32 97.32
Subtotal for V Electrical ... 0.00 0.00 0.00 0.00 432.95 0.00 43.31 15.79 492.05
K LININGS/SHEATHING/DRY
PARTITIONING
K20 Timber board
flooring/sheathing/linings/casings
Flooring
Plywood, width exceeding 300
mm, thickness
322 9mm 3.56 m2
22.50 17.37 0.00 0.00 0.00 0.00 3.99 1.46 12.73 45.32
Subtotal for K ... 22.50 17.37 0.00 0.00 0.00 0.00 3.99 1.46 45.32
Total for Item 24.28 22.50 17.37 0.00 0.00 432.95 0.00 47.30 17.25 537.37
ITEM 27.1
Z PC SUMS
PC Sums associated with the
project
323 contingency sum item 0.00 0.00 0.00 0.00 0.00 7500.00 0.00 248.43 7748.43 7,748.43
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 7500.00 0.00 248.43 7,748.43
Total for Item 27.1 0.00 0.00 0.00 0.00 0.00 7500.00 0.00 248.43 7,748.43
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 92
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 28.1
C EXISTING
SITE/BUILDINGS/SERVICES
C90 Alterations - spot items
Remove finishings
Floors
324 carpeting 4.74 m2
11.33 0.00 7.11 0.00 0.00 0.00 1.85 0.66 4.42 20.95
Walls, without backing
325 ceramic wall tiles 21.67 m2
94.05 0.00 19.50 0.00 0.00 0.00 11.27 4.12 5.95 128.94
Removing fittings and fixtures
Timber mouldings
326 skirtings, architraves or dado
rail; dispose of debris off-site
or set
aside for re-use 13.78 m 29.90 0.00 4.13 0.00 0.00 0.00 3.45 1.24 2.81 38.72
Removing plumbing and
engineering installations
Sanitary fittings, including
capping off service and waste
pipes and
bringing forward services
327 WC 1.00 nr 85.37 28.63 6.00 0.00 0.00 0.00 12.00 4.37 136.37 136.37
328 wash hand basin 1.00 nr 4.34 0.00 28.00 0.00 0.00 0.00 3.23 1.18 36.75 36.75
329 bath 1.00 nr 127.94 38.52 30.00 0.00 0.00 0.00 19.65 7.16 223.27 223.27
Radiators
330 medium 1.00 nr 42.57 8.39 7.50 0.00 0.00 0.00 5.85 2.13 66.44 66.44
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 93
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
C EXISTING
continued ...
C20 Demolition
Demolishing parts of timber
structures
Softwood studded partitions;
dispose of debris off-site
331 plasterboard finish 0.75 m2
6.19 0.00 3.15 0.00 0.00 0.00 0.94 0.34 14.15 10.61
Subtotal for C Existing ... 401.69 75.54 105.39 0.00 0.00 0.00 58.24 21.20 662.05
Z PC SUMS
PC Sums associated with the
project
332 disconnect electrical installation
and make safe for proceeding
works item 0.00 0.00 0.00 0.00 0.00 125.00 0.00 4.14 129.14 129.14
Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 125.00 0.00 4.14 129.14
Total for Item 28.1 401.69 75.54 105.39 0.00 0.00 125.00 58.24 25.34 791.19
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 94
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
ITEM 28.2
P BUILDING FABRIC SUNDRIES
P31
Holes/Chases/Covers/Supports
for services
Chases
Vertical rough chases
333 50 x 50 mm 2.40 m 47.95 0.00 0.00 0.00 0.00 0.00 4.80 1.75 22.71 54.50
Subtotal for P Building Fabric ... 47.95 0.00 0.00 0.00 0.00 0.00 4.80 1.75 54.50
Total for Item 28.2 47.95 0.00 0.00 0.00 0.00 0.00 4.80 1.75 54.50
ITEM 28.3
G STRUCTURAL/CARCASSING
METAL/TIMBER
G20 Carpentry/Timber
framing/First fixing
Impregnated sawn softwood -
SC3 Grade
Wall or partition members
334 50 x 50mm 31.80 m 78.86 26.08 0.00 0.00 0.00 0.00 10.49 3.82 3.75 119.25
Subtotal for G ... 78.86 26.08 0.00 0.00 0.00 0.00 10.49 3.82 119.25
This content is © of Estimating Service 2015.
www.estimatingservice.co.uk Page 3 / 95
Qty Unit
Labour
Cost
Material
Cost
Plant
Cost
Sub Lab
Cost
Sub Pur
Cost
PC Sum
Cost
Profit
Cost
Prelims
Cost Rate
R Ext
£ p
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary Report

More Related Content

Viewers also liked

Manpower planning for a construction company
Manpower planning for a construction companyManpower planning for a construction company
Manpower planning for a construction companyRevati Bargale
 
Construction Cost Estimating - Quality Cost Estimating
Construction Cost Estimating - Quality Cost EstimatingConstruction Cost Estimating - Quality Cost Estimating
Construction Cost Estimating - Quality Cost EstimatingDoina Dobre, P.Eng, GSC
 
Manpower planning project
Manpower planning projectManpower planning project
Manpower planning projecthema_nt
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 

Viewers also liked (7)

Manpower planning for a construction company
Manpower planning for a construction companyManpower planning for a construction company
Manpower planning for a construction company
 
Manpower Planning
Manpower PlanningManpower Planning
Manpower Planning
 
Construction Cost Estimating - Quality Cost Estimating
Construction Cost Estimating - Quality Cost EstimatingConstruction Cost Estimating - Quality Cost Estimating
Construction Cost Estimating - Quality Cost Estimating
 
Manpower planning project
Manpower planning projectManpower planning project
Manpower planning project
 
Manpower Planning
Manpower PlanningManpower Planning
Manpower Planning
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 

Similar to Schedule of Works Cost Summary Report

[Name Sponged] Consulting Project
[Name Sponged] Consulting Project[Name Sponged] Consulting Project
[Name Sponged] Consulting ProjectRyan Elder
 
CIM report - final
CIM report - finalCIM report - final
CIM report - finalPraveen S R
 
Home Owner Sample
Home Owner SampleHome Owner Sample
Home Owner SampleHai Nguyen
 
Home Owner Sample
Home Owner SampleHome Owner Sample
Home Owner SampleHai Nguyen
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxFaisalGulzar19
 
Final plant layout
Final plant layoutFinal plant layout
Final plant layoutradit12
 
ZBC in commodities.ppt
ZBC in commodities.pptZBC in commodities.ppt
ZBC in commodities.pptSoulmananIndia
 
Architect Sample
Architect SampleArchitect Sample
Architect SampleHai Nguyen
 
Design improvements and costing analysis
Design improvements and costing analysisDesign improvements and costing analysis
Design improvements and costing analysisASHISH MENKUDALE
 
cost appraisal
cost appraisalcost appraisal
cost appraisalahmong4
 

Similar to Schedule of Works Cost Summary Report (20)

[Name Sponged] Consulting Project
[Name Sponged] Consulting Project[Name Sponged] Consulting Project
[Name Sponged] Consulting Project
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM Report
CIM ReportCIM Report
CIM Report
 
Home Owner Sample
Home Owner SampleHome Owner Sample
Home Owner Sample
 
Home Owner Sample
Home Owner SampleHome Owner Sample
Home Owner Sample
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
Final plant layout
Final plant layoutFinal plant layout
Final plant layout
 
ZBC in commodities.ppt
ZBC in commodities.pptZBC in commodities.ppt
ZBC in commodities.ppt
 
Architect Sample
Architect SampleArchitect Sample
Architect Sample
 
Quality analysis of hmc
Quality analysis of hmcQuality analysis of hmc
Quality analysis of hmc
 
Quality analysis of hmc
Quality analysis of hmcQuality analysis of hmc
Quality analysis of hmc
 
WEIGHTING TABLE
WEIGHTING TABLEWEIGHTING TABLE
WEIGHTING TABLE
 
3rd stage ppt black book
3rd stage ppt   black book3rd stage ppt   black book
3rd stage ppt black book
 
Airjet shiva
Airjet shivaAirjet shiva
Airjet shiva
 
Design improvements and costing analysis
Design improvements and costing analysisDesign improvements and costing analysis
Design improvements and costing analysis
 
FINAL VOLUME 2 20.12
FINAL VOLUME 2 20.12FINAL VOLUME 2 20.12
FINAL VOLUME 2 20.12
 
cost appraisal
cost appraisalcost appraisal
cost appraisal
 
Copy of Financial report
Copy of Financial reportCopy of Financial report
Copy of Financial report
 
De assignment
De assignmentDe assignment
De assignment
 

Schedule of Works Cost Summary Report

  • 1. ITEM 1.11 A PRELIMINARIES/GENERAL CONDITIONS A40 Contractor's general cost items: Management and staff Site administrative staff Provide general site supervision/administration 1 Project Manager; say 2 days/week for 14 weeks with additional 2 days for completion & handover 6.00 week 6000.00 0.00 0.00 0.00 0.00 0.00 600.00 218.64 1136.44 6,818.64 2 Labourer for manual unloading of materials 10.00 week 4000.00 0.00 0.00 0.00 0.00 0.00 400.00 145.70 454.57 4,545.70 Subtotal for A ... 10000.00 0.00 0.00 0.00 0.00 0.00 1000.00 364.34 11,364.34 A PRELIMINARIES/GENERAL CONDITIONS A41 Contractor's general cost items: Site accommodation Temporary offices and the like Hire of temporary accommodation 3 Portaloo hire 14.00 nr/wk 0.00 0.00 77.00 0.00 0.00 0.00 7.70 2.80 6.25 87.50 Subtotal for A ... 0.00 0.00 77.00 0.00 0.00 0.00 7.70 2.80 87.50 Total for Item 1.11 10000.00 0.00 77.00 0.00 0.00 0.00 1007.70 367.14 11,451.84 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 1 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 2. ITEM 1.23 Z PC SUMS PC Sums associated with the project 4 provide health & safety site signage item 0.00 0.00 0.00 0.00 0.00 200.00 20.00 7.29 227.29 227.29 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 200.00 20.00 7.29 227.29 Total for Item 1.23 0.00 0.00 0.00 0.00 0.00 200.00 20.00 7.29 227.29 ITEM 1.27 A PRELIMINARIES/GENERAL CONDITIONS A44 Contractor's general cost items: Temporary works Scaffolding up to 10m high Independent scaffolding 5 Erect and subsequently dismantle 99.17 m2 0.00 0.00 0.00 0.00 1361.60 0.00 135.86 49.59 15.60 1,547.05 Subtotal for A ... 0.00 0.00 0.00 0.00 1361.60 0.00 135.86 49.59 1,547.05 Total for Item 1.27 0.00 0.00 0.00 0.00 1361.60 0.00 135.86 49.59 1,547.05 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 2 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 3. ITEM 1.36 A PRELIMINARIES/GENERAL CONDITIONS A42 Contractor's general cost items: Services and facilities Provide the following services and facilities Rubbish disposal 6 Skips 2.00 nr 0.00 0.00 420.00 0.00 0.00 0.00 42.00 15.30 238.65 477.30 Subtotal for A ... 0.00 0.00 420.00 0.00 0.00 0.00 42.00 15.30 477.30 Total for Item 1.36 0.00 0.00 420.00 0.00 0.00 0.00 42.00 15.30 477.30 ITEM 2.1 Z PC SUMS PC Sums associated with the project 7 mechanical & electrical disconnections & removals; no details on survey drawings item 0.00 0.00 0.00 0.00 0.00 500.00 50.00 18.22 568.22 568.22 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 500.00 50.00 18.22 568.22 Total for Item 2.1 0.00 0.00 0.00 0.00 0.00 500.00 50.00 18.22 568.22 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 3 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 4. ITEM 2.2 C EXISTING SITE/BUILDINGS/SERVICES C90 Alterations - spot items Temporary screens softwood framing with plywood and polythene to one side only 8 clear away on completion of works 4.66 m2 113.84 66.82 0.00 0.00 0.00 0.00 18.08 6.57 44.06 205.32 Subtotal for C Existing ... 113.84 66.82 0.00 0.00 0.00 0.00 18.08 6.57 205.32 Total for Item 2.2 113.84 66.82 0.00 0.00 0.00 0.00 18.08 6.57 205.32 ITEM 2.4 C EXISTING SITE/BUILDINGS/SERVICES C20 Demolition Disconnect redundant services and demolish individual structures to ground level; grub out slab and foundations Dispose of spoil off site; disposal costs included within rates 9 structure not exceeding 50 m3 19.33 m3 593.82 0.00 594.01 0.00 0.00 0.00 118.88 43.30 69.84 1,350.01 Subtotal for C Existing ... 593.82 0.00 594.01 0.00 0.00 0.00 118.88 43.30 1,350.01 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 4 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 5. Z PC SUMS PC Sums associated with the project 10 lift and salvage all paving within the area of the new build; no details on survey drawing item 0.00 0.00 0.00 0.00 0.00 125.00 12.50 4.55 142.05 142.05 11 cutting back vegetation to facilitate access for extension; no details on survey drawing item 0.00 0.00 0.00 0.00 0.00 335.00 33.50 12.21 380.71 380.71 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 460.00 46.00 16.76 522.76 Total for Item 2.4 593.82 0.00 594.01 0.00 0.00 460.00 164.88 60.06 1,872.77 ITEM 2.5 Z PC SUMS PC Sums associated with the project 12 strip out existing kitchen units/worktops and dispose of off-site; no details on survey drawing item 0.00 0.00 0.00 0.00 0.00 335.00 33.50 12.21 380.71 380.71 13 provide temporary covering to roof structure and protection to floor coverings item 0.00 0.00 0.00 0.00 0.00 200.00 20.00 7.29 227.29 227.29 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 535.00 53.50 19.50 608.00 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 5 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 6. C EXISTING SITE/BUILDINGS/SERVICES C20 Demolition Demolishing parts of concrete structures Plain concrete beds 14 150 mm thick 11.12 m2 161.68 0.00 157.57 0.00 0.00 0.00 31.91 11.68 32.63 362.85 C90 Alterations - spot items Remove finishings Floors 15 linoleum 11.12 m2 21.68 0.00 13.34 0.00 0.00 0.00 3.56 1.33 3.59 39.92 C20 Demolition Pulling down - including removal of debris Demolish external brickwork walls in cement mortar; disposal of debris off-site 16 2 x 102.5 mm thick skins forming cavity wall 10.61 m2 336.12 0.00 133.69 0.00 0.00 0.00 47.00 17.08 50.32 533.90 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 6 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 7. C EXISTING continued ... C90 Alterations - spot items Removing fittings and fixtures Doors including frame; dispose of debris off-site or set aside for re-use 17 single door 4.00 nr 47.76 0.00 8.40 0.00 0.00 0.00 5.60 2.04 15.95 63.80 Windows; dispose of debris off-site or set aside for re-use 18 casement window 1.15 m2 22.46 0.00 2.42 0.00 0.00 0.00 2.48 0.91 24.58 28.27 Removing plumbing and engineering installations Sanitary fittings, including capping off service and waste pipes and bringing forward services 19 WC 1.00 nr 85.37 28.63 6.00 0.00 0.00 0.00 12.00 4.37 136.37 136.37 20 wash hand basin 1.00 nr 4.34 0.00 28.00 0.00 0.00 0.00 3.23 1.18 36.75 36.75 Remove finishings Ceilings 21 plasterboard 2.31 m2 10.03 0.00 2.77 0.00 0.00 0.00 1.27 0.46 6.29 14.53 Walls, without backing 22 wallpaper 9.31 m2 17.13 0.00 2.79 0.00 0.00 0.00 1.96 0.74 2.43 22.62 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 7 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 8. C EXISTING continued ... C90 Alterations - continued ... Coverings Stripping and repairs to slate and tile roofs 23 plain or interlocking tiles; dispose of debris off-site 21.37 m2 166.90 0.00 12.82 0.00 0.00 0.00 17.95 6.62 9.56 204.30 Subtotal for C Existing ... 873.47 28.63 367.80 0.00 0.00 0.00 126.96 46.41 1,443.31 Total for Item 2.5 873.47 28.63 367.80 0.00 0.00 535.00 180.46 65.91 2,051.31 ITEM 3.1 R DISPOSAL SYSTEMS R12 Drainage below ground Excavation by machine Trenches for drain pipes not exceeding 200 mm nominal size, grading bottoms, earthwork support and backfilling with excavated material; average depth 24 0.75 m 7.65 m 63.11 0.00 20.20 0.00 0.00 0.00 8.34 3.06 12.38 94.71 25 1.00 m 10.70 m 181.26 0.00 58.64 0.00 0.00 0.00 23.97 8.77 25.48 272.64 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 8 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 9. R DISPOSAL continued ... R12 Drainage continued ... Disposal of material arising from drainage excavations Excavated material; bulking factor 1.25 26 loaded by hand from spoil heaps 3.10 m3 55.49 0.00 93.00 0.00 0.00 0.00 14.85 5.43 54.44 168.76 Imported granular material 150 mm beds and side filling to half height of pipes Unplasticised PVC pipes and fittings to BS 4660 110 mm pipes 27 in trenches 18.35 m 55.78 94.32 0.00 0.00 0.00 0.00 15.05 5.51 9.30 170.66 Extra for 28 long radius bends 2.00 nr 5.36 22.48 0.00 0.00 0.00 0.00 2.78 1.02 15.82 31.64 29 single junction 1.00 nr 3.75 16.43 0.00 0.00 0.00 0.00 2.02 0.74 22.94 22.94 30 slip coupler 3.00 nr 4.83 8.55 0.00 0.00 0.00 0.00 1.35 0.48 5.07 15.21 Accessories 31 back inlet bottle gulley 1.00 nr 29.50 46.38 0.00 0.00 0.00 0.00 7.59 2.76 86.23 86.23 32 bottle gulley 1.00 nr 29.50 32.02 0.00 0.00 0.00 0.00 6.15 2.24 69.91 69.91 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 9 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 10. R DISPOSAL continued ... R12 Drainage continued ... Testing drains Water test 33 100 mm drains 18.35 m 22.94 0.00 0.00 0.00 0.00 0.00 2.39 0.92 1.43 26.24 Subtotal for R Disposal Systems 451.52 220.18 171.84 0.00 0.00 0.00 84.49 30.93 958.94 Total for Item 3.1 451.52 220.18 171.84 0.00 0.00 0.00 84.49 30.93 958.94 ITEM 3.7 Manholes Unplasticised PVC inspection chambers 450 mm diameter; set in cement mortar 1:3, depth to invert 34 1035 mm 1.00 nr 33.08 148.09 0.00 0.00 0.00 0.00 18.12 6.60 205.89 205.89 Total for Item 3.7 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 205.89 ITEM 3.8 Surface drainage systems ACO Drain K100 channel with galvanised steel lockable grating 35 set in gound, bedded and haunched in concrete 7.68 m 104.52 204.98 0.00 0.00 0.00 0.00 30.95 11.29 45.80 351.74 36 extra for end cap 2.00 nr 2.10 8.42 0.00 0.00 0.00 0.00 1.06 0.38 5.98 11.96 Total for Item 3.8 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 363.70 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 10 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 11. ITEM 3.9 Soakaways Modular soakaway crates 37 aquavoid light duty soakaway crates 1.00 m3 44.70 172.50 0.00 0.00 0.00 0.00 21.72 7.91 246.83 246.83 Total for Item 3.9 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 246.83 ITEM 4.1 D20 Excavating and filling Excavating by machine Trenches, width over 0.30 m, maximum depth not exceeding 38 1.00 m 8.63 m3 185.80 0.00 60.67 0.00 0.00 0.00 24.68 8.98 32.46 280.13 Disposal Off site to tip average 15 km from site 39 loaded by hand from spoil heaps 10.78 m3 192.96 0.00 323.40 0.00 0.00 0.00 51.64 18.76 54.43 586.76 Surface treatments Compacting 40 bottom of excavation 12.33 m2 5.30 0.00 1.36 0.00 0.00 0.00 0.62 0.25 0.61 7.52 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 11 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 12. E IN SITU CONCRETE/LARGE PRECAST CONCRETE E10 Mixing/casting/curing in-situ concrete Ready mixed concrete Plain in situ concrete 1:2:4 - 20 mm aggregate 41 foundations 7.71 m3 140.63 793.82 0.00 0.00 0.00 0.00 93.45 34.08 137.74 1,061.98 E41 Worked finishes/Cutting to in situ concrete Worked finishes Tamping by mechanical means 42 level 15.41 m2 10.02 0.00 2.62 0.00 0.00 0.00 1.23 0.46 0.93 14.33 Subtotal for E in Situ ... 719.11 1327.81 388.05 0.00 0.00 0.00 243.47 88.71 1,950.72 Total for Item 4.1 719.11 1327.81 388.05 0.00 0.00 0.00 243.47 88.71 1,950.72 ITEM 4.5 D20 Excavating and filling Excavating by machine To reduce levels, maximum depth not exceeding 43 0.25 m 0.09 m3 1.94 0.00 0.63 0.00 0.00 0.00 0.26 0.09 32.42 2.92 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 12 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 13. ITEM 4.5 continued ... D20 Excavating continued ... Disposal Off site to tip average 15 km from site 44 loaded by hand from spoil heaps 0.11 m3 1.97 0.00 3.30 0.00 0.00 0.00 0.53 0.19 54.42 5.99 Surface treatments Compacting 45 bottom of excavation 0.71 m2 0.31 0.00 0.08 0.00 0.00 0.00 0.04 0.01 0.60 0.43 E IN SITU CONCRETE/LARGE PRECAST CONCRETE E10 Mixing/casting/curing in-situ concrete Ready mixed concrete 46 beds, thickness not exceeding 150 mm 0.09 m3 1.64 9.35 0.00 0.00 0.00 0.00 1.10 0.40 138.84 12.50 E41 Worked finishes/Cutting to in situ concrete Worked finishes Tamping by mechanical means 47 level 0.60 m2 0.39 0.00 0.10 0.00 0.00 0.00 0.05 0.02 0.93 0.56 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 13 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 14. E IN SITU CONCRETE/LARGE PRECAST continued ... E41 Worked finishes/Cutting to in situ concrete continued ... Worked finishes continued ... Trowelling 48 level 0.60 m2 2.02 0.00 0.00 0.00 0.00 0.00 0.20 0.07 3.82 2.29 Subtotal for E in Situ ... 8.27 9.35 4.11 0.00 0.00 0.00 2.18 0.78 24.69 Total for Item 4.5 8.27 9.35 4.11 0.00 0.00 0.00 2.18 0.78 24.69 ITEM 5.1 D20 Excavating and filling Excavating by machine To reduce levels, maximum depth not exceeding 49 1.00 m 12.97 m3 279.24 0.00 91.18 0.00 0.00 0.00 37.09 13.49 32.46 421.01 Disposal Off site to tip average 15 km from site 50 loaded by hand from spoil heaps 16.21 m3 290.16 0.00 486.30 0.00 0.00 0.00 77.65 28.37 54.44 882.47 Surface treatments Compacting 51 bottom of excavation 43.22 m2 18.58 0.00 4.75 0.00 0.00 0.00 2.16 0.86 0.61 26.36 Total for Item 5.1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,329.84 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 14 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 15. ITEM 5.3 - 5.7 D20 Excavating and filling Filling to excavations Imported MOT Type 1 material 52 not exceeding 0.25 m 4.89 m3 81.71 207.34 8.26 0.00 0.00 0.00 29.73 10.81 69.09 337.85 Imported sand 53 not exceeding 0.25 m 0.98 m3 16.38 33.01 0.00 0.00 0.00 0.00 4.94 1.80 57.27 56.12 Surface treatments Compacting 54 surface of filling 32.59 m2 14.01 0.00 3.58 0.00 0.00 0.00 1.63 0.65 0.61 19.88 J WATERPROOFING J40 Flexible sheet tanking/ damp proof membranes Tanking and damp proofing Polythene medium weight sheet underlay lapped 150 mm at joints 55 horizontally 44.50 m2 48.51 17.36 0.00 0.00 0.00 0.00 6.68 2.23 1.68 74.76 Subtotal for J Waterproofing 748.59 257.71 594.07 0.00 0.00 0.00 159.88 58.21 488.61 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 15 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 16. E IN SITU CONCRETE/LARGE PRECAST CONCRETE E10 Mixing/casting/curing in-situ concrete Ready mixed concrete Plain in situ concrete 1:2:4 - 20 mm aggregate 56 slabs, thickness not exceeding 150 mm 4.89 m3 174.87 503.47 0.00 0.00 0.00 0.00 67.82 24.74 157.65 770.91 E41 Worked finishes/Cutting to in situ concrete Worked finishes Tamping by mechanical means 57 level 32.59 m2 21.18 0.00 5.54 0.00 0.00 0.00 2.61 0.98 0.93 30.31 Subtotal for E in Situ ... 196.05 503.47 5.54 0.00 0.00 0.00 70.43 25.72 801.22 P BUILDING FABRIC SUNDRIES P10 Sundry insulation/proofing work/fire stops Vapour barriers Vapour barriers 58 Polythene vapour barrier 32.59 m2 58.99 11.41 0.00 0.00 0.00 0.00 7.17 2.61 2.46 80.17 Insulating boards Celotex Insulation Fast-R range 59 75 mm 32.59 m2 135.57 368.59 0.00 0.00 0.00 0.00 50.51 18.25 17.58 572.93 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 16 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 17. P BUILDING FABRIC continued ... P10 Sundry insulation/proofing work/fire stops continued ... Insulating boards continued ... Celotex Insulation T-Break range 60 20 mm 4.47 m2 16.27 15.96 0.00 0.00 0.00 0.00 3.22 1.16 8.19 36.61 Subtotal for P Building Fabric ... 210.83 395.96 0.00 0.00 0.00 0.00 60.90 22.02 689.71 M SURFACE FINISHES M10 Cement sand/Concrete screeds/toppings Cement and sand 1:3, work to floors Screeded beds, level and to falls not exceeding 15 degrees from horizontal, over 300 mm wide 61 75 mm 32.59 m2 186.41 328.51 0.00 0.00 0.00 0.00 51.49 18.90 17.96 585.32 Subtotal for M Surface Finishes 186.41 328.51 0.00 0.00 0.00 0.00 51.49 18.90 585.32 Total for Item 5.3 - 5.7 1341.88 1485.65 599.61 0.00 0.00 0.00 342.70 124.85 2,564.86 ITEM 5.8 D20 Excavating and filling Excavating by hand To reduce levels, maximum depth not exceeding 62 1.00 m 4.00 m3 70.76 0.00 0.00 0.00 0.00 0.00 7.08 2.60 20.11 80.44 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 17 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 18. ITEM 5.8 continued ... D20 Excavating continued ... Disposal Off site to tip average 15 km from site 63 loaded by hand from spoil heaps 5.00 m3 89.50 0.00 150.00 0.00 0.00 0.00 23.95 8.75 54.44 272.20 Surface treatments Compacting 64 bottom of excavation 13.33 m2 5.73 0.00 1.47 0.00 0.00 0.00 0.67 0.27 0.61 8.13 Total for Item 5.8 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 360.77 ITEM 5.9 J WATERPROOFING J40 Flexible sheet tanking/ damp proof membranes Tanking and damp proofing Polythene medium weight sheet underlay lapped 150 mm at joints 65 horizontally 20.57 m2 22.42 8.02 0.00 0.00 0.00 0.00 3.09 1.03 1.68 34.56 Subtotal for J Waterproofing 188.41 8.02 151.47 0.00 0.00 0.00 34.79 12.65 34.56 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 18 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 19. E IN SITU CONCRETE/LARGE PRECAST CONCRETE E10 Mixing/casting/curing in-situ concrete Ready mixed concrete Plain in situ concrete 1:2:4 - 20 mm aggregate 66 slabs, thickness not exceeding 150 mm 2.00 m3 71.52 205.92 0.00 0.00 0.00 0.00 27.74 10.12 157.65 315.30 E41 Worked finishes/Cutting to in situ concrete Worked finishes Tamping by mechanical means 67 level 13.33 m2 8.66 0.00 2.27 0.00 0.00 0.00 1.07 0.40 0.93 12.40 Subtotal for E in Situ ... 80.18 205.92 2.27 0.00 0.00 0.00 28.81 10.52 327.70 P BUILDING FABRIC SUNDRIES P10 Sundry insulation/proofing work/fire stops Vapour barriers Vapour barriers 68 Polythene vapour barrier 13.33 m2 24.13 4.67 0.00 0.00 0.00 0.00 2.93 1.07 2.46 32.79 Insulating boards Celotex Insulation Fast-R range 69 75 mm 13.33 m2 55.45 150.76 0.00 0.00 0.00 0.00 20.66 7.46 17.58 234.34 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 19 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 20. P BUILDING FABRIC continued ... P10 Sundry insulation/proofing work/fire stops continued ... Insulating boards continued ... Celotex Insulation T-Break range 70 20 mm 2.70 m2 9.83 9.64 0.00 0.00 0.00 0.00 1.94 0.70 8.19 22.11 Subtotal for P Building Fabric ... 89.41 165.07 0.00 0.00 0.00 0.00 25.53 9.23 289.24 M SURFACE FINISHES M10 Cement sand/Concrete screeds/toppings Cement and sand 1:3, work to floors Screeded beds, level and to falls not exceeding 15 degrees from horizontal, over 300 mm wide 71 75 mm 13.33 m2 76.25 134.37 0.00 0.00 0.00 0.00 21.06 7.73 17.96 239.41 Subtotal for M Surface Finishes 76.25 134.37 0.00 0.00 0.00 0.00 21.06 7.73 239.41 Total for Item 5.9 434.25 513.38 153.74 0.00 0.00 0.00 110.19 40.13 890.91 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 20 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 21. ITEM 5.10 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Floor members 72 50 x 75mm 6.00 m 14.88 6.84 0.00 0.00 0.00 0.00 2.16 0.78 4.11 24.66 73 50 x 150mm 38.72 m 122.36 90.22 0.00 0.00 0.00 0.00 21.30 7.74 6.24 241.61 Solid bridging between joists (measured over the joists) 74 50 x 150mm 5.87 m 37.10 14.44 0.00 0.00 0.00 0.00 5.17 1.88 9.98 58.58 Metalwork Galvanised steel joist hangers - built in 75 50 x 150mm 32.00 nr 64.96 41.28 0.00 0.00 0.00 0.00 10.56 3.84 3.77 120.64 Galvanised steel straps 76 heavy duty steel strap; once bent; 1200 mm long 6.00 nr 37.92 26.64 0.00 0.00 0.00 0.00 6.48 2.34 12.23 73.38 Subtotal for G ... 277.22 179.42 0.00 0.00 0.00 0.00 45.67 16.58 518.87 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 21 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 22. K LININGS/SHEATHING/DRY PARTITIONING K20 Timber board flooring/sheathing/linings/casings Flooring Chipboard Type C4 flooring tongued and grooved all edges, width exceeding 300 mm, thickness 77 22mm 14.60 m2 105.56 93.44 0.00 0.00 0.00 0.00 19.86 7.30 15.49 226.15 Subtotal for K ... 105.56 93.44 0.00 0.00 0.00 0.00 19.86 7.30 226.15 P BUILDING FABRIC SUNDRIES P10 Sundry insulation/proofing work/fire stops Insulating quilts Acoustic insulating quilts 78 100 mm 14.60 m2 26.43 103.08 0.00 0.00 0.00 0.00 12.99 4.67 10.08 147.17 Subtotal for P Building Fabric ... 26.43 103.08 0.00 0.00 0.00 0.00 12.99 4.67 147.17 Total for Item 5.10 409.21 375.94 0.00 0.00 0.00 0.00 78.52 28.55 892.19 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 22 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 23. ITEM 5.11 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Wall or partition members 79 50 x 75mm 4.25 m 13.43 4.59 0.00 0.00 0.00 0.00 1.79 0.68 4.82 20.49 Subtotal for G ... 13.43 4.59 0.00 0.00 0.00 0.00 1.79 0.68 20.49 Total for Item 5.11 13.43 4.59 0.00 0.00 0.00 0.00 1.79 0.68 20.49 ITEM 6.1 C EXISTING SITE/BUILDINGS/SERVICES C20 Demolition Pulling down - including removal of debris Demolish external brickwork walls in cement mortar; disposal of debris off-site 80 2 x 102.5 mm thick skins forming cavity wall 3.00 m2 95.04 0.00 37.80 0.00 0.00 0.00 13.29 4.83 50.32 150.96 Subtotal for C Existing ... 95.04 0.00 37.80 0.00 0.00 0.00 13.29 4.83 150.96 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 23 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 24. F MASONRY F31 Precast concrete sills/lintels/copings/features Lintels Prestressed lintels 65 mm x 100 mm bedded 81 1200 mm 2.00 nr 16.86 22.60 0.00 0.00 0.00 0.00 3.94 1.44 22.42 44.84 F30 Accessories/Sundry items for brick/block/stone walling Closing cavities Thermabate cavity closers 82 100 mm cavity 10.95 m 34.05 58.14 0.00 0.00 0.00 0.00 9.20 3.39 9.57 104.79 Proprietary items Wall extension profiles, single flange, plugging and screwing 83 100mm 21.10 m 81.45 100.86 0.00 0.00 0.00 0.00 18.15 6.54 9.81 206.99 Subtotal for F Masonry 132.36 181.60 0.00 0.00 0.00 0.00 31.29 11.37 356.62 Total for Item 6.1 227.40 181.60 37.80 0.00 0.00 0.00 44.58 16.20 507.58 ITEM 6.2 F MASONRY F10 Brick/Block walling Precast concrete dense aggregate blocks to BS 6073 Walls, facework one side 84 100 mm solid; in gauged mortar 1:3; below DPC level 23.09 m2 287.01 423.93 0.00 0.00 0.00 0.00 71.12 25.86 34.99 807.92 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 24 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 25. F MASONRY continued ... F10 Brick/Block continued ... Class B engineering bricks in cement mortar 1:3 Walls 85 102.5 mm 4.87 m2 116.73 239.26 0.00 0.00 0.00 0.00 35.60 12.95 83.07 404.55 F30 Accessories/Sundry items for brick/block/stone walling Damp proof courses Polythene 86 horizontal 100mm wide 41.11 m 18.09 4.52 0.00 0.00 0.00 0.00 2.47 0.82 0.63 25.90 Subtotal for F Masonry 421.83 667.71 0.00 0.00 0.00 0.00 109.19 39.63 1,238.37 Total for Item 6.2 421.83 667.71 0.00 0.00 0.00 0.00 109.19 39.63 1,238.37 ITEM 6.3 E IN SITU CONCRETE/LARGE PRECAST CONCRETE E10 Mixing/casting/curing in-situ concrete Ready mixed concrete Plain in situ concrete 1:2:4 - 20 mm aggregate 87 filling to hollow walls 1.21 m3 64.90 125.77 0.00 0.00 0.00 0.00 19.07 6.95 179.08 216.69 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 25 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 26. E IN SITU CONCRETE/LARGE PRECAST continued ... E10 Mixing/casting/curing in-situ concrete continued ... Forming cavities 50 - 100 mm cavities in hollow walls with 225 mm wall-ties at 5 per m2 using 88 3 mm vertical-twist ties 67.71 m2 60.26 50.11 0.00 0.00 0.00 0.00 10.83 4.06 1.85 125.26 Subtotal for E in Situ ... 125.16 175.88 0.00 0.00 0.00 0.00 29.90 11.01 341.95 P BUILDING FABRIC SUNDRIES P10 Sundry insulation/proofing work/fire stops Cavity wall Insulation Slab insulation to masonry walls 89 60 mm thick Celotex cavity insulation 67.71 m2 270.84 635.80 0.00 0.00 0.00 0.00 90.73 33.18 15.22 1,030.55 Subtotal for P Building Fabric ... 270.84 635.80 0.00 0.00 0.00 0.00 90.73 33.18 1,030.55 Total for Item 6.3 396.00 811.68 0.00 0.00 0.00 0.00 120.63 44.19 1,372.50 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 26 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 27. ITEM 6.4 F MASONRY F10 Brick/Block walling Precast concrete dense aggregate blocks to BS 6073 Walls, facework one side 90 100 mm solid; in gauged mortar 1:4; above DPC level 59.75 m2 742.69 1055.19 0.00 0.00 0.00 0.00 179.85 65.73 34.20 2,043.45 Subtotal for F Masonry 742.69 1055.19 0.00 0.00 0.00 0.00 179.85 65.73 2,043.45 Total for Item 6.4 742.69 1055.19 0.00 0.00 0.00 0.00 179.85 65.73 2,043.45 ITEM 6.5 F MASONRY F10 Brick/Block walling Facing bricks in gauged mortar 1:4 Walls, facework one side; PC supply rate for bricks £750/1000 91 102.5 mm 73.18 m2 1754.12 4432.51 0.00 0.00 0.00 0.00 618.37 225.39 96.07 7,030.40 Subtotal for F Masonry 1754.12 4432.51 0.00 0.00 0.00 0.00 618.37 225.39 7,030.40 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 27 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 28. G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Dummy frames for brickwork 92 50 x 100mm 34.60 m 132.86 54.32 0.00 0.00 0.00 0.00 18.68 6.92 6.15 212.79 Subtotal for G ... 132.86 54.32 0.00 0.00 0.00 0.00 18.68 6.92 212.79 Total for Item 6.5 1886.98 4486.83 0.00 0.00 0.00 0.00 637.05 232.31 7,243.19 ITEM 6.6 F MASONRY F30 Accessories/Sundry items for brick/block/stone walling Damp proof courses Polythene 93 vertical 100mm wide 21.10 m 9.28 2.32 0.00 0.00 0.00 0.00 1.27 0.42 0.63 13.29 Subtotal for F Masonry 9.28 2.32 0.00 0.00 0.00 0.00 1.27 0.42 13.29 Total for Item 6.6 9.28 2.32 0.00 0.00 0.00 0.00 1.27 0.42 13.29 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 28 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 29. ITEM 6.7 F MASONRY F30 Accessories/Sundry items for brick/block/stone walling Closing cavities Thermabate cavity closers 94 100 mm cavity 17.00 m 52.87 90.27 0.00 0.00 0.00 0.00 14.28 5.27 9.57 162.69 Subtotal for F Masonry 52.87 90.27 0.00 0.00 0.00 0.00 14.28 5.27 162.69 Total for Item 6.7 52.87 90.27 0.00 0.00 0.00 0.00 14.28 5.27 162.69 ITEM 6.8 F MASONRY F30 Accessories/Sundry items for brick/block/stone walling Cavity trays Polythene 95 horizontal exceeding 225 mm 5.09 m2 42.91 4.94 0.00 0.00 0.00 0.00 4.78 1.73 10.68 54.36 Stop Ends 96 lintel stop end 10.00 nr 8.90 7.40 0.00 0.00 0.00 0.00 1.60 0.60 1.85 18.50 Subtotal for F Masonry 51.81 12.34 0.00 0.00 0.00 0.00 6.38 2.33 72.86 Total for Item 6.8 51.81 12.34 0.00 0.00 0.00 0.00 6.38 2.33 72.86 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 29 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 30. ITEM 6.9 F MASONRY F30 Accessories/Sundry items for brick/block/stone walling Cavity trays Type W Cavity weep ventilator 97 wall weep vent 25.00 nr 22.25 8.00 0.00 0.00 0.00 0.00 3.00 1.00 1.37 34.25 Subtotal for F Masonry 22.25 8.00 0.00 0.00 0.00 0.00 3.00 1.00 34.25 Total for Item 6.9 22.25 8.00 0.00 0.00 0.00 0.00 3.00 1.00 34.25 ITEM 6.10 L WINDOWS/DOORS/STAIRS L10 Windows/rooflights/screens/louvres Bedding and pointing frames Pointing in mastic sealant 98 window frames 14.81 m 23.84 6.22 0.00 0.00 0.00 0.00 2.96 1.04 2.30 34.06 L20 Doors/shutters/hatches Bedding and pointing frames Pointing in mastic sealant 99 door frames 18.65 m 30.03 7.83 0.00 0.00 0.00 0.00 3.73 1.31 2.30 42.90 Subtotal for L Windows/Doors/Stairs 53.87 14.05 0.00 0.00 0.00 0.00 6.69 2.35 76.96 Total for Item 6.10 53.87 14.05 0.00 0.00 0.00 0.00 6.69 2.35 76.96 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 30 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 31. ITEM 6.11 F MASONRY F30 Accessories/Sundry items for brick/block/stone walling Galvanised steel lintels Galvanised steel standard lintels 100 2100mm 2.00 nr 20.42 100.18 0.00 0.00 0.00 0.00 12.06 4.40 68.53 137.06 Galvanised steel heavy duty lintels 101 3900mm 1.00 nr 20.42 214.94 0.00 0.00 0.00 0.00 23.54 8.58 267.48 267.48 Galvanised steel eaves lintels 102 1200mm 1.00 nr 7.10 19.44 0.00 0.00 0.00 0.00 2.65 0.97 30.16 30.16 103 1350mm 1.00 nr 7.10 21.88 0.00 0.00 0.00 0.00 2.90 1.06 32.94 32.94 Subtotal for F Masonry 55.04 356.44 0.00 0.00 0.00 0.00 41.15 15.01 467.64 Total for Item 6.11 55.04 356.44 0.00 0.00 0.00 0.00 41.15 15.01 467.64 ITEM 6.12 F MASONRY F10 Brick/Block walling Facing bricks in gauged mortar 1:4 Flush bands 104 215 mm, brick on end 6.33 m 28.11 83.18 0.00 0.00 0.00 0.00 11.14 4.05 19.98 126.47 Subtotal for F Masonry 28.11 83.18 0.00 0.00 0.00 0.00 11.14 4.05 126.47 Total for Item 6.12 28.11 83.18 0.00 0.00 0.00 0.00 11.14 4.05 126.47 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 31 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 32. ITEM 6.13 F MASONRY F30 Accessories/Sundry items for brick/block/stone walling Closing cavities Thermabate cavity closers 105 100 mm cavity 10.88 m 33.84 57.77 0.00 0.00 0.00 0.00 9.14 3.37 9.57 104.12 F31 Precast concrete sills/lintels/copings/features Copings 400 x 900 mm twice weathered and throated copings bedded 106 straight 10.88 m 178.65 412.03 0.00 0.00 0.00 0.00 59.08 21.54 61.70 671.30 Subtotal for F Masonry 212.49 469.80 0.00 0.00 0.00 0.00 68.22 24.91 775.42 H CLADDING/COVERING H71 Lead sheet coverings/flashings Flashings, aprons Code 4 lead, horizontal, 150 mm lapped joints, fixing with lead clips and wedges 107 300 mm girth 10.01 m 59.56 159.06 0.00 0.00 0.00 0.00 21.82 8.01 24.82 248.45 Subtotal for H Cladding/Covering 59.56 159.06 0.00 0.00 0.00 0.00 21.82 8.01 248.45 Total for Item 6.13 272.05 628.86 0.00 0.00 0.00 0.00 90.04 32.92 1,023.87 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 32 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 33. ITEM 6.14 C EXISTING SITE/BUILDINGS/SERVICES C41 Repairing/renovating/conserving masonry Brickwork Cut out 108 brickwork to allow for cavity tray installation, make good with new facing bricks 0.75 m2 71.67 2.11 0.23 0.00 0.00 0.00 7.40 2.70 112.14 84.11 F30 Accessories/Sundry items for brick/block/stone walling Cavity trays Polythene 109 horizontal exceeding 225 mm 1.50 m2 12.65 1.46 0.00 0.00 0.00 0.00 1.41 0.51 10.68 16.02 Type W Cavity weep ventilator 110 wall weep vent 14.00 nr 12.46 4.48 0.00 0.00 0.00 0.00 1.68 0.56 1.37 19.18 Subtotal for C Existing ... 96.78 8.05 0.23 0.00 0.00 0.00 10.49 3.77 119.31 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 33 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 34. H CLADDING/COVERING H71 Lead sheet coverings/flashings Flashings, aprons Code 4 lead, horizontal, 150 mm lapped joints, fixing with lead clips and wedges 111 300 mm girth 5.98 m 35.58 95.02 0.00 0.00 0.00 0.00 13.04 4.78 24.82 148.42 Subtotal for H Cladding/Covering 35.58 95.02 0.00 0.00 0.00 0.00 13.04 4.78 148.42 Total for Item 6.14 132.36 103.07 0.23 0.00 0.00 0.00 23.53 8.55 267.73 ITEM 6.15 F MASONRY F31 Precast concrete sills/lintels/copings/features Padstones Padstones bedded 112 400 x 100 x 150 mm 1.00 nr 6.21 15.86 0.00 0.00 0.00 0.00 2.21 0.80 25.08 25.08 113 250 x 100 x 150 mm 1.00 nr 6.21 14.48 0.00 0.00 0.00 0.00 2.07 0.75 23.51 23.51 114 50 x 280 x 218 mm 1.00 nr 6.21 14.48 0.00 0.00 0.00 0.00 2.07 0.75 23.51 23.51 Lintels Prestressed lintels 65 mm x 100 mm bedded 115 750 mm 2.00 nr 16.86 15.86 0.00 0.00 0.00 0.00 3.28 1.20 18.60 37.20 Subtotal for F Masonry 35.49 60.68 0.00 0.00 0.00 0.00 9.63 3.50 109.30 Total for Item 6.15 35.49 60.68 0.00 0.00 0.00 0.00 9.63 3.50 109.30 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 34 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 35. ITEM 6.16 F MASONRY F10 Brick/Block walling Precast concrete dense aggregate blocks to BS 6073 Walls, facework one side 116 100 mm solid; in gauged mortar 1:4; above DPC level 3.89 m2 48.35 68.70 0.00 0.00 0.00 0.00 11.71 4.28 34.20 133.04 Subtotal for F Masonry 48.35 68.70 0.00 0.00 0.00 0.00 11.71 4.28 133.04 Total for Item 6.16 48.35 68.70 0.00 0.00 0.00 0.00 11.71 4.28 133.04 ITEM 6.17 F MASONRY F31 Precast concrete sills/lintels/copings/features Lintels Prestressed lintels 65 mm x 100 mm bedded 117 1200 mm 2.00 nr 16.86 22.60 0.00 0.00 0.00 0.00 3.94 1.44 22.42 44.84 Subtotal for F Masonry 16.86 22.60 0.00 0.00 0.00 0.00 3.94 1.44 44.84 Total for Item 6.17 16.86 22.60 0.00 0.00 0.00 0.00 3.94 1.44 44.84 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 35 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 36. ITEM 6.18 C EXISTING SITE/BUILDINGS/SERVICES C90 Alterations - spot items Forming new window opening in existing wall Temporary support, close cavity, make good reveals, build in standard lintel 118 through cavity wall 0.39 m2 61.77 27.44 6.26 0.00 0.00 0.00 9.55 3.48 278.21 108.50 Subtotal for C Existing ... 61.77 27.44 6.26 0.00 0.00 0.00 9.55 3.48 108.50 Total for Item 6.18 61.77 27.44 6.26 0.00 0.00 0.00 9.55 3.48 108.50 ITEM 6.19 C EXISTING SITE/BUILDINGS/SERVICES C41 Repairing/renovating/conserving masonry Brickwork Cut out 119 brickwork to allow for new meter box installation 0.25 m2 16.30 0.00 0.08 0.00 0.00 0.00 1.64 0.60 74.44 18.61 Subtotal for C Existing ... 16.30 0.00 0.08 0.00 0.00 0.00 1.64 0.60 18.61 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 36 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 37. F MASONRY F30 Accessories/Sundry items for brick/block/stone walling Meter Boxes 120 recessed electric meter box 1.00 nr 5.53 20.46 0.00 0.00 0.00 0.00 2.60 0.95 29.54 29.54 Galvanised steel lintels Single element lintels 121 750mm 1.00 nr 5.33 7.41 0.00 0.00 0.00 0.00 1.27 0.46 14.47 14.47 F30 Accessories/Sundry items for brick/block/stone walling Cavity trays Polythene 122 horizontal exceeding 225 mm 0.28 m2 2.36 0.27 0.00 0.00 0.00 0.00 0.26 0.10 10.70 3.00 Type W Cavity weep ventilator 123 wall weep vent 3.00 nr 2.67 0.96 0.00 0.00 0.00 0.00 0.36 0.12 1.37 4.11 Subtotal for F Masonry 15.89 29.10 0.00 0.00 0.00 0.00 4.49 1.63 51.12 Total for Item 6.19 32.19 29.10 0.08 0.00 0.00 0.00 6.13 2.23 69.73 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 37 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 38. ITEM 6.20 F MASONRY F10 Brick/Block walling Precast concrete dense aggregate blocks to BS 6073 Walls, facework one side 124 100 mm solid; in gauged mortar 1:4; above DPC level 0.78 m2 9.70 13.77 0.00 0.00 0.00 0.00 2.35 0.86 34.20 26.68 Forming cavities 50 - 100 mm cavities in hollow walls with 225 mm wall-ties at 5 per m2 using 125 3 mm vertical-twist ties 0.39 m2 0.35 0.29 0.00 0.00 0.00 0.00 0.06 0.02 1.84 0.72 Subtotal for F Masonry 10.05 14.06 0.00 0.00 0.00 0.00 2.41 0.88 27.40 P BUILDING FABRIC SUNDRIES P10 Sundry insulation/proofing work/fire stops Cavity wall Insulation Slab insulation to masonry walls 126 60 mm thick Celotex cavity insulation 0.39 m2 1.56 3.66 0.00 0.00 0.00 0.00 0.52 0.19 15.22 5.94 Subtotal for P Building Fabric ... 1.56 3.66 0.00 0.00 0.00 0.00 0.52 0.19 5.94 Total for Item 6.20 11.61 17.72 0.00 0.00 0.00 0.00 2.93 1.07 33.34 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 38 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 39. ITEM 7.2 G STRUCTURAL/CARCASSING METAL/TIMBER G10 Structural steel framing Framing, fabrication Fabricated steelwork 127 columns 40 - 100 kg/m 0.41 tonne 0.00 563.70 0.00 0.00 0.00 0.00 56.37 20.54 1562.48 640.62 Erection on site 128 permanent erection 0.41 tonne 181.69 0.00 0.00 0.00 0.00 0.00 18.17 6.62 503.62 206.48 Surface treatments at fabrication workshop 129 shot blasting & priming 6.97 m2 0.00 54.02 0.00 0.00 0.00 0.00 5.44 1.95 8.81 61.41 130 30 minute intumescent fire paint 6.97 m2 0.00 90.89 0.00 0.00 0.00 0.00 9.06 3.28 14.81 103.23 G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Boxing out steelwork 131 50 x 50mm 27.84 m 69.04 22.83 0.00 0.00 0.00 0.00 9.19 3.34 3.75 104.40 Subtotal for G ... 250.73 731.44 0.00 0.00 0.00 0.00 98.23 35.73 1,116.14 Total for Item 7.2 250.73 731.44 0.00 0.00 0.00 0.00 98.23 35.73 1,116.14 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 39 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 40. ITEM 7.3 G STRUCTURAL/CARCASSING METAL/TIMBER G10 Structural steel framing Framing, fabrication Fabricated steelwork 132 beams less than 40 kg/m 0.08 tonne 0.00 133.50 0.00 0.00 0.00 0.00 13.35 4.86 1896.31 151.70 Fittings 133 general fiitings; plates, nuts, bolts etc. 0.01 tonne 0.00 21.94 0.00 0.00 0.00 0.00 2.19 0.80 2492.91 24.93 Erection on site 134 permanent erection 0.08 tonne 35.45 0.00 0.00 0.00 0.00 0.00 3.55 1.29 503.60 40.29 Surface treatments at fabrication workshop 135 shot blasting & priming 3.17 m2 0.00 24.57 0.00 0.00 0.00 0.00 2.47 0.89 8.81 27.93 136 30 minute intumescent fire paint 3.17 m2 0.00 41.34 0.00 0.00 0.00 0.00 4.12 1.52 14.82 46.98 G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Boxing out steelwork 137 50 x 50mm 9.64 m 23.91 7.90 0.00 0.00 0.00 0.00 3.18 1.16 3.75 36.15 Subtotal for G ... 59.36 229.25 0.00 0.00 0.00 0.00 28.86 10.52 327.98 Total for Item 7.3 59.36 229.25 0.00 0.00 0.00 0.00 28.86 10.52 327.98 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 40 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 41. ITEM 7.5 G STRUCTURAL/CARCASSING METAL/TIMBER G10 Structural steel framing Framing, fabrication Fabricated steelwork 138 columns less than 40 kg/m 0.14 tonne 0.00 220.15 0.00 0.00 0.00 0.00 22.02 8.02 1787.01 250.18 Erection on site 139 permanent erection 0.14 tonne 62.04 0.00 0.00 0.00 0.00 0.00 6.20 2.26 503.61 70.51 Subtotal for G ... 62.04 220.15 0.00 0.00 0.00 0.00 28.22 10.28 320.69 Total for Item 7.5 62.04 220.15 0.00 0.00 0.00 0.00 28.22 10.28 320.69 ITEM 7.6 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Flat roof members 140 50 x 150mm 6.94 m 21.93 16.79 0.00 0.00 0.00 0.00 3.89 1.39 6.34 44.00 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 41 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 42. G STRUCTURAL/CARCASSING METAL/TIMBER continued ... G20 Carpentry/Timber framing/First continued ... Metalwork Bolts & Timber Connectors 141 M12 bolt with nut; 130 mm long 7.00 nr 7.91 6.02 0.00 0.00 0.00 0.00 1.40 0.49 2.26 15.82 Subtotal for G ... 29.84 22.81 0.00 0.00 0.00 0.00 5.29 1.88 59.82 Total for Item 7.6 29.84 22.81 0.00 0.00 0.00 0.00 5.29 1.88 59.82 ITEM 8.1 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Wall plates bedded 142 75 x 100mm 10.90 m 46.76 30.74 0.00 0.00 0.00 0.00 7.74 2.83 8.08 88.07 Metalwork Galvanised steel straps 143 light duty wall plate strap; once bent; 1200 mm long 18.00 nr 113.76 32.22 0.00 0.00 0.00 0.00 14.58 5.40 9.22 165.96 Subtotal for G ... 160.52 62.96 0.00 0.00 0.00 0.00 22.32 8.23 254.03 Total for Item 8.1 160.52 62.96 0.00 0.00 0.00 0.00 22.32 8.23 254.03 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 42 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 43. ITEM 8.2 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Flat roof members 144 50 x 150mm 37.59 m 118.78 90.97 0.00 0.00 0.00 0.00 21.05 7.52 6.34 238.32 145 50 x 200mm 24.33 m 82.48 78.59 0.00 0.00 0.00 0.00 16.06 5.84 7.52 182.96 146 50 x 50mm angle fillets 34.96 m 70.97 25.87 0.00 0.00 0.00 0.00 9.79 3.50 3.15 110.12 147 sawn softwood firrings 61.92 m 195.67 315.17 0.00 0.00 0.00 0.00 51.39 18.58 9.38 580.81 Metalwork Anchor bolts 148 M12 anchor bolt; 115 mm long 28.00 nr 56.84 24.36 0.00 0.00 0.00 0.00 8.12 3.08 3.30 92.40 Bolts & Timber Connectors 149 M12 bolt with nut; 130 mm long 31.00 nr 35.03 26.66 0.00 0.00 0.00 0.00 6.20 2.17 2.26 70.06 Galvanised steel straps 150 heavy duty steel strap; once bent; 1200 mm long 6.00 nr 37.92 26.64 0.00 0.00 0.00 0.00 6.48 2.34 12.23 73.38 Speedy joist hangers 151 100mm 8.00 nr 30.72 5.92 0.00 0.00 0.00 0.00 3.68 1.36 5.21 41.68 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 43 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 44. G STRUCTURAL/CARCASSING METAL/TIMBER continued ... G20 Carpentry/Timber framing/First continued ... Metalwork continued ... Speedy joist continued ... 152 50mm 44.00 nr 109.12 28.16 0.00 0.00 0.00 0.00 13.64 4.84 3.54 155.76 Subtotal for G ... 737.53 622.34 0.00 0.00 0.00 0.00 136.41 49.23 1,545.49 Total for Item 8.2 737.53 622.34 0.00 0.00 0.00 0.00 136.41 49.23 1,545.49 ITEM 8.3 K LININGS/SHEATHING/DRY PARTITIONING K20 Timber board flooring/sheathing/linings/casings Roof decking WBP plywood 153 18mm WBP plywood exceeding 300 mm wide 9.57 m2 79.91 68.71 0.00 0.00 0.00 0.00 14.83 5.45 17.65 168.91 Subtotal for K ... 79.91 68.71 0.00 0.00 0.00 0.00 14.83 5.45 168.91 Total for Item 8.3 79.91 68.71 0.00 0.00 0.00 0.00 14.83 5.45 168.91 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 44 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 45. ITEM 8.4 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Flat roof members 154 50 x 100mm 24.68 m 94.77 39.98 0.00 0.00 0.00 0.00 13.57 4.94 6.21 153.26 Subtotal for G ... 94.77 39.98 0.00 0.00 0.00 0.00 13.57 4.94 153.26 Total for Item 8.4 94.77 39.98 0.00 0.00 0.00 0.00 13.57 4.94 153.26 ITEM 8.5 P BUILDING FABRIC SUNDRIES P10 Sundry insulation/proofing work/fire stops Insulating quilts Acoustic insulating quilts 155 100 mm 1.91 m2 3.46 13.48 0.00 0.00 0.00 0.00 1.70 0.61 10.08 19.25 Subtotal for P Building Fabric ... 3.46 13.48 0.00 0.00 0.00 0.00 1.70 0.61 19.25 Total for Item 8.5 3.46 13.48 0.00 0.00 0.00 0.00 1.70 0.61 19.25 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 45 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 46. ITEM 8.6 G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Flat roof members 156 50 x 150mm 10.67 m 33.72 25.82 0.00 0.00 0.00 0.00 5.98 2.13 6.34 67.65 Metalwork Bolts & Timber Connectors 157 M12 bolt with nut; 130 mm long 15.00 nr 16.95 12.90 0.00 0.00 0.00 0.00 3.00 1.05 2.26 33.90 Total for Item 8.6 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 101.55 ITEM 8.7 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Flat roof members 158 50 x 100mm 17.26 m 66.28 27.96 0.00 0.00 0.00 0.00 9.49 3.45 6.21 107.18 Subtotal for G ... 116.95 66.68 0.00 0.00 0.00 0.00 18.47 6.63 107.18 Total for Item 8.7 116.95 66.68 0.00 0.00 0.00 0.00 18.47 6.63 107.18 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 46 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 47. ITEM 8.9 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Pitched roof members 159 50 x 150mm 111.32 m 477.56 271.62 0.00 0.00 0.00 0.00 74.58 27.83 7.65 851.60 160 50 x 225mm 17.70 m 75.93 64.07 0.00 0.00 0.00 0.00 13.98 5.13 8.99 159.12 Subtotal for G ... 553.49 335.69 0.00 0.00 0.00 0.00 88.56 32.96 1,010.72 Total for Item 8.9 553.49 335.69 0.00 0.00 0.00 0.00 88.56 32.96 1,010.72 ITEM 8.11 G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Pitched roof members 161 50 x 150mm 36.30 m 155.73 88.57 0.00 0.00 0.00 0.00 24.32 9.08 7.65 277.70 Total for Item 8.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 277.70 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 47 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 48. ITEM 8.12 G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Pitched roof members 162 50 x 150mm 1.60 m 6.86 3.90 0.00 0.00 0.00 0.00 1.07 0.38 7.64 12.22 K LININGS/SHEATHING/DRY PARTITIONING K20 Timber board flooring/sheathing/linings/casings Flooring Chipboard Type C4 flooring tongued and grooved all edges, width exceeding 300 mm, thickness 163 22mm 14.19 m2 102.59 90.82 0.00 0.00 0.00 0.00 19.30 7.10 15.49 219.80 Subtotal for K ... 265.18 183.29 0.00 0.00 0.00 0.00 44.69 16.56 232.02 Total for Item 8.12 265.18 183.29 0.00 0.00 0.00 0.00 44.69 16.56 232.02 ITEM 8.13 P BUILDING FABRIC SUNDRIES P10 Sundry insulation/proofing work/fire stops Insulating quilts Thermal insulating quilts 164 170 mm Knauf Earthwool 14.19 m2 15.47 31.36 0.00 0.00 0.00 0.00 4.68 1.70 3.75 53.21 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 48 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 49. P BUILDING FABRIC continued ... P10 Sundry insulation/proofing work/fire stops continued ... Insulating quilts continued ... Thermal continued ... 165 100 mm Knauf Earthwool 14.19 m2 13.91 18.16 0.00 0.00 0.00 0.00 3.26 1.14 2.57 36.47 Subtotal for P Building Fabric ... 29.38 49.52 0.00 0.00 0.00 0.00 7.94 2.84 89.68 Total for Item 8.13 29.38 49.52 0.00 0.00 0.00 0.00 7.94 2.84 89.68 ITEM 8.14 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Pitched roof members 166 50 x 175mm C24 14.61 m 62.68 45.44 0.00 0.00 0.00 0.00 10.81 3.94 8.41 122.87 167 75 x 100mm 5.48 m 28.44 15.45 0.00 0.00 0.00 0.00 4.38 1.59 9.10 49.87 168 75 x 175mm 2.95 m 15.31 14.57 0.00 0.00 0.00 0.00 2.98 1.09 11.51 33.95 169 50 x 100mm 1.51 m 5.80 2.45 0.00 0.00 0.00 0.00 0.83 0.30 6.21 9.38 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 49 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 50. G STRUCTURAL/CARCASSING METAL/TIMBER continued ... G20 Carpentry/Timber framing/First continued ... Metalwork Bolts & Timber Connectors 170 M12 bolt with nut; 130 mm long 26.00 nr 29.38 22.36 0.00 0.00 0.00 0.00 5.20 1.82 2.26 58.76 Subtotal for G ... 141.61 100.27 0.00 0.00 0.00 0.00 24.20 8.74 274.83 Total for Item 8.14 141.61 100.27 0.00 0.00 0.00 0.00 24.20 8.74 274.83 ITEM 8.15 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Eaves and verge boarding Impregnated wrought softwood eaves and verge boarding, width not exceeding 300 mm 171 32 x 225mm boards 12.75 m 66.17 118.83 0.00 0.00 0.00 0.00 18.49 6.76 16.49 210.25 Subtotal for G ... 66.17 118.83 0.00 0.00 0.00 0.00 18.49 6.76 210.25 Total for Item 8.15 66.17 118.83 0.00 0.00 0.00 0.00 18.49 6.76 210.25 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 50 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 51. ITEM 8.16 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Pitched roof members 172 50 x 50mm plugged and screwed 11.96 m 37.79 10.17 0.00 0.00 0.00 0.00 4.78 1.79 4.56 54.54 Eaves and verge boarding WBP plywood 173 9mm Softwood plywood - 225mm wide 12.75 m 83.51 14.28 0.00 0.00 0.00 0.00 9.82 3.57 8.72 111.18 Subtotal for G ... 121.30 24.45 0.00 0.00 0.00 0.00 14.60 5.36 165.72 Total for Item 8.16 121.30 24.45 0.00 0.00 0.00 0.00 14.60 5.36 165.72 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 51 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 52. ITEM 8.17 C EXISTING SITE/BUILDINGS/SERVICES C20 Demolition Demolishing parts of timber structures Removing roof timbers 174 fascia or barge boards; dispose of debris off-site 6.50 m 73.32 0.00 1.95 0.00 0.00 0.00 7.54 2.73 13.16 85.54 Subtotal for C Existing ... 73.32 0.00 1.95 0.00 0.00 0.00 7.54 2.73 85.54 Total for Item 8.17 73.32 0.00 1.95 0.00 0.00 0.00 7.54 2.73 85.54 ITEM 8.18 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Pitched roof members 175 50 x 125mm 13.06 m 50.15 29.25 0.00 0.00 0.00 0.00 7.97 2.87 6.91 90.24 176 50 x 100mm 5.60 m 21.50 9.07 0.00 0.00 0.00 0.00 3.08 1.12 6.21 34.78 Eaves and verge boarding WBP plywood 177 12mm softwood WBP plywood over 300mm wide 2.27 m2 38.95 11.33 0.00 0.00 0.00 0.00 5.04 1.84 25.18 57.16 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 52 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 53. G STRUCTURAL/CARCASSING METAL/TIMBER continued ... G20 Carpentry/Timber framing/First continued ... Eaves and verge continued ... Impregnated wrought softwood eaves and verge boarding, width not exceeding 300 mm 178 32 x 225mm boards 3.54 m 18.37 32.99 0.00 0.00 0.00 0.00 5.13 1.88 16.49 58.37 Metalwork Bolts & Timber Connectors 179 M12 bolt with nut; 130 mm long 8.00 nr 9.04 6.88 0.00 0.00 0.00 0.00 1.60 0.56 2.26 18.08 Anchor bolts 180 M12 anchor bolt; 115 mm long 16.00 nr 32.48 13.92 0.00 0.00 0.00 0.00 4.64 1.76 3.30 52.80 Subtotal for G ... 170.49 103.44 0.00 0.00 0.00 0.00 27.46 10.03 311.43 H CLADDING/COVERING H60 Plain roof tiling Sub-contract purchase Clay plain tiles; Dreadnought machine made smooth red or other equal and approved on 19 x 38mm treated battens and breather membrane 181 roof coverings to 64mm lap 2.56 m2 0.00 0.00 0.00 0.00 173.16 0.00 17.31 6.30 76.86 196.76 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 53 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 54. H continued ... H60 Plain roof continued ... Sub-contract continued ... Extra over for 182 double course at eaves 2.53 m 0.00 0.00 0.00 0.00 26.92 0.00 2.68 0.99 12.09 30.59 183 verges; single undercloak course 1.01 m 0.00 0.00 0.00 0.00 9.39 0.00 0.94 0.34 10.57 10.68 H71 Lead sheet coverings/flashings Flashings, aprons Code 4 lead, horizontal, 150 mm lapped joints, fixing with lead clips and wedges 184 300 mm girth 2.53 m 15.05 40.20 0.00 0.00 0.00 0.00 5.52 2.00 24.81 62.77 Code 4 lead, stepped, 150 mm lapped joints, fixing with lead clips and wedges 185 300 mm girth 1.01 m 12.01 17.60 0.00 0.00 0.00 0.00 2.96 1.08 33.32 33.65 Soakers and slates Code 4 lead soakers (fixing by slater or tiler) 186 175 x 165 mm 7.00 nr 4.97 9.03 0.00 0.00 0.00 0.00 1.40 0.49 2.27 15.89 Subtotal for H Cladding/Covering 32.03 66.83 0.00 0.00 209.47 0.00 30.81 11.20 350.34 Total for Item 8.18 202.52 170.27 0.00 0.00 209.47 0.00 58.27 21.23 661.77 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 54 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 55. ITEM 9.5 H CLADDING/COVERING H60 Plain roof tiling Sub-contract purchase Extra over for 187 valleys; cutting both sides 7.74 m 0.00 0.00 0.00 0.00 178.02 0.00 17.80 6.50 26.14 202.32 Subtotal for H Cladding/Covering 0.00 0.00 0.00 0.00 178.02 0.00 17.80 6.50 202.32 Total for Item 9.5 0.00 0.00 0.00 0.00 178.02 0.00 17.80 6.50 202.32 ITEM 9.6 Clay plain tiles; Dreadnought machine made smooth red or other equal and approved on 19 x 38mm treated battens and breather membrane 188 roof coverings to 64mm lap 42.21 m2 0.00 0.00 0.00 0.00 2855.08 0.00 285.34 103.84 76.86 3,244.26 Total for Item 9.6 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,244.26 ITEM 9.7 Extra over for 189 double course at eaves 12.64 m 0.00 0.00 0.00 0.00 134.49 0.00 13.40 4.93 12.09 152.82 Total for Item 9.7 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 152.82 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 55 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 56. ITEM 9.8 H CLADDING/COVERING H60 Plain roof tiling Sub-contract purchase Extra over for 190 bonnet hip tiles; cutting both sides 14.25 m 0.00 0.00 0.00 0.00 1080.01 0.00 108.02 39.33 86.13 1,227.35 191 hip irons 2.00 nr 0.00 0.00 0.00 0.00 7.18 0.00 0.72 0.26 4.08 8.16 Subtotal for H Cladding/Covering 0.00 0.00 0.00 0.00 4076.76 0.00 407.48 148.36 1,235.51 Total for Item 9.8 0.00 0.00 0.00 0.00 4076.76 0.00 407.48 148.36 1,235.51 ITEM 9.11 H CLADDING/COVERING H60 Plain roof tiling Sub-contract purchase Extra over for 192 ridge tiles 2.73 m 0.00 0.00 0.00 0.00 78.84 0.00 7.89 2.87 32.82 89.60 Subtotal for H Cladding/Covering 0.00 0.00 0.00 0.00 78.84 0.00 7.89 2.87 89.60 Total for Item 9.11 0.00 0.00 0.00 0.00 78.84 0.00 7.89 2.87 89.60 ITEM 10.1 J WATERPROOFING J42 Built up roof coverings Bauder Waterproof System 193 to timber or metal decking; pitch not exceeding 5 degrees 9.57 m2 0.00 0.00 0.00 0.00 392.56 0.00 39.24 14.26 46.61 446.06 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 56 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 57. J WATERPROOFING continued ... J42 Built up roof continued ... Bauder Waterproof continued ... 194 kerb detail to Bauder waterproof membrane, girth not exceeding 400mm 24.59 m 0.00 0.00 0.00 0.00 1243.76 0.00 124.43 45.25 57.48 1,413.43 Tapered Insulation Board Underlays 195 tapered PIR board; mechanically fastened 9.57 m2 0.00 0.00 0.00 0.00 593.72 0.00 59.33 21.63 70.50 674.69 Subtotal for J Waterproofing 0.00 0.00 0.00 0.00 2230.04 0.00 223.00 81.14 2,534.18 Total for Item 10.1 0.00 0.00 0.00 0.00 2230.04 0.00 223.00 81.14 2,534.18 ITEM 10.4 H71 Lead sheet coverings/flashings Flashings, aprons Code 4 lead, horizontal, 150 mm lapped joints, fixing with lead clips and wedges 196 300 mm girth 9.36 m 55.69 148.73 0.00 0.00 0.00 0.00 20.40 7.49 24.82 232.32 Total for Item 10.4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 232.32 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 57 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 58. ITEM 10.5 H CLADDING/COVERING H71 Lead sheet coverings/flashings Outlets Code 4 lead, 150 mm lapped joints, fixing with lead cleats and brass scews 197 600 mm girth 1.00 m 42.80 34.85 0.00 0.00 0.00 0.00 7.77 2.83 88.25 88.25 Subtotal for H Cladding/Covering 98.49 183.58 0.00 0.00 0.00 0.00 28.17 10.32 88.25 Total for Item 10.5 98.49 183.58 0.00 0.00 0.00 0.00 28.17 10.32 88.25 ITEM 10.6 C EXISTING SITE/BUILDINGS/SERVICES C90 Alterations - spot items Coverings Stripping and repairs to slate and tile roofs 198 roofing felt or single ply waterproofing membrane; dispose of debris off-site 2.99 m2 14.26 0.00 1.79 0.00 0.00 0.00 1.61 0.57 6.10 18.24 Subtotal for C Existing ... 14.26 0.00 1.79 0.00 0.00 0.00 1.61 0.57 18.24 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 58 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 59. J WATERPROOFING J42 Built up roof coverings Bauder Waterproof System 199 to timber or metal decking; pitch not exceeding 5 degrees 2.99 m2 0.00 0.00 0.00 0.00 122.65 0.00 12.26 4.46 46.61 139.36 200 kerb detail to Bauder waterproof membrane, girth not exceeding 400mm 12.28 m 0.00 0.00 0.00 0.00 621.12 0.00 62.14 22.60 57.48 705.85 Tapered Insulation Board Underlays 201 tapered PIR board; mechanically fastened 2.99 m2 0.00 0.00 0.00 0.00 185.50 0.00 18.54 6.76 70.50 210.80 H71 Lead sheet coverings/flashings Flashings, aprons Code 4 lead, horizontal, 150 mm lapped joints, fixing with lead clips and wedges 202 300 mm girth 12.28 m 73.07 195.13 0.00 0.00 0.00 0.00 26.77 9.82 24.82 304.79 Subtotal for J Waterproofing 73.07 195.13 0.00 0.00 929.27 0.00 119.71 43.64 1,360.80 Total for Item 10.6 87.33 195.13 1.79 0.00 929.27 0.00 121.32 44.21 1,379.04 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 59 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 60. ITEM 11.1 C EXISTING SITE/BUILDINGS/SERVICES C90 Alterations - spot items Gutterwork Remove gutters and supports, dispose of debris off-site 203 cast iron 27.67 m 203.93 0.00 16.60 0.00 0.00 0.00 22.14 8.02 9.06 250.69 Rainwater pipework Remove rainwater pipes and supports, dispose of debris off-site 204 cast iron rainwater stack 6.09 m 44.88 0.00 3.65 0.00 0.00 0.00 4.87 1.77 9.06 55.18 Subtotal for C Existing ... 248.81 0.00 20.25 0.00 0.00 0.00 27.01 9.79 305.87 Total for Item 11.1 248.81 0.00 20.25 0.00 0.00 0.00 27.01 9.79 305.87 ITEM 11.2 R DISPOSAL SYSTEMS R10 Rainwater pipework/gutters Brett Martin Cascade rainwater system Gutters 205 112mm half round gutter 35.26 m 259.87 474.60 0.00 0.00 0.00 0.00 73.34 26.80 23.67 834.60 Subtotal for R Disposal Systems 259.87 474.60 0.00 0.00 0.00 0.00 73.34 26.80 834.60 Total for Item 11.2 259.87 474.60 0.00 0.00 0.00 0.00 73.34 26.80 834.60 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 60 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 61. ITEM 11.3 R DISPOSAL SYSTEMS R10 Rainwater pipework/gutters Brett Martin Cascade rainwater system Rainwater pipes 206 68mm round downpipes 11.29 m 83.21 243.41 0.00 0.00 0.00 0.00 32.63 11.85 32.87 371.10 Subtotal for R Disposal Systems 83.21 243.41 0.00 0.00 0.00 0.00 32.63 11.85 371.10 Total for Item 11.3 83.21 243.41 0.00 0.00 0.00 0.00 32.63 11.85 371.10 ITEM 11.4 R DISPOSAL SYSTEMS R10 Rainwater pipework/gutters Brett Martin Cascade rainwater system Extra for 207 hopper head 2.00 nr 14.74 81.48 0.00 0.00 0.00 0.00 9.62 3.52 54.68 109.36 Subtotal for R Disposal Systems 14.74 81.48 0.00 0.00 0.00 0.00 9.62 3.52 109.36 Total for Item 11.4 14.74 81.48 0.00 0.00 0.00 0.00 9.62 3.52 109.36 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 61 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 62. ITEM 11.5 R DISPOSAL SYSTEMS R10 Rainwater pipework/gutters Brett Martin Cascade rainwater system Extra for 208 angles 5.00 nr 30.90 76.55 0.00 0.00 0.00 0.00 10.75 3.90 24.42 122.10 209 stopped ends 2.00 nr 5.70 15.50 0.00 0.00 0.00 0.00 2.12 0.78 12.05 24.10 210 outlets 4.00 nr 24.72 59.76 0.00 0.00 0.00 0.00 8.44 3.08 24.00 96.00 211 offset 4.00 nr 29.48 124.20 0.00 0.00 0.00 0.00 15.36 5.60 43.66 174.64 Subtotal for R Disposal Systems 90.80 276.01 0.00 0.00 0.00 0.00 36.67 13.36 416.84 Total for Item 11.5 90.80 276.01 0.00 0.00 0.00 0.00 36.67 13.36 416.84 ITEM 12.2 L WINDOWS/DOORS/STAIRS L10 Windows/rooflights/screens/louvres Supply & fix 212 Manufacturer quotation; windows and doors; supply & fix item 0.00 0.00 0.00 0.00 7525.00 0.00 752.50 274.18 8551.68 8,551.68 Subtotal for L Windows/Doors/Stairs 0.00 0.00 0.00 0.00 7525.00 0.00 752.50 274.18 8,551.68 Total for Item 12.2 0.00 0.00 0.00 0.00 7525.00 0.00 752.50 274.18 8,551.68 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 62 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 63. ITEM 12.4 P BUILDING FABRIC SUNDRIES P20 Unframed isolated trims/skirtings/sundry items Window boards MDF with rounded nosing 213 25 x 219 mm 3.14 m 17.02 14.38 0.00 0.00 0.00 0.00 3.14 1.13 11.36 35.67 214 returned ends 8.00 nr 9.04 0.00 0.00 0.00 0.00 0.00 0.88 0.32 1.28 10.24 Subtotal for P Building Fabric ... 26.06 14.38 0.00 0.00 0.00 0.00 4.02 1.45 45.91 Total for Item 12.4 26.06 14.38 0.00 0.00 0.00 0.00 4.02 1.45 45.91 ITEM 12.5 L WINDOWS/DOORS/STAIRS L10 Windows/rooflights/screens/louvres Fixing only 215 Fix only softwood casement windows 0.38 m2 15.69 0.00 0.00 0.00 0.00 0.00 1.57 0.57 46.93 17.83 Subtotal for L Windows/Doors/Stairs 15.69 0.00 0.00 0.00 0.00 0.00 1.57 0.57 17.83 Total for Item 12.5 15.69 0.00 0.00 0.00 0.00 0.00 1.57 0.57 17.83 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 63 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 64. ITEM 13.1 L WINDOWS/DOORS/STAIRS L10 Windows/rooflights/screens/louvres Roof Lights Monodraught diamond dome sunpipe 216 300mm diameter 2.00 nr 135.48 471.46 0.00 0.00 0.00 0.00 60.70 22.12 344.88 689.76 Subtotal for L Windows/Doors/Stairs 135.48 471.46 0.00 0.00 0.00 0.00 60.70 22.12 689.76 Total for Item 13.1 135.48 471.46 0.00 0.00 0.00 0.00 60.70 22.12 689.76 ITEM 13.3 Z PC SUMS PC Sums associated with the project 217 supply of lantern lights from HLI Building Products item 0.00 0.00 0.00 0.00 3228.00 0.00 322.80 117.62 3668.42 3,668.42 218 fixing of lantern lights including wireways for electrical connections item 0.00 0.00 0.00 400.00 0.00 0.00 40.00 14.57 454.57 454.57 Subtotal for Z Pc Sums 0.00 0.00 0.00 400.00 3228.00 0.00 362.80 132.19 4,122.99 Total for Item 13.3 0.00 0.00 0.00 400.00 3228.00 0.00 362.80 132.19 4,122.99 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 64 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 65. ITEM 14.1 M SURFACE FINISHES M20 Plastered/Rendered/Roughcast coatings Gypsum plasterboard to BS 1230 Fixing with screws to ceilings 219 12.5 mm Plain Wallboard over 300 mm wide 57.77 m2 413.63 129.40 0.00 0.00 0.00 0.00 54.30 19.64 10.68 616.98 Subtotal for M Surface Finishes 413.63 129.40 0.00 0.00 0.00 0.00 54.30 19.64 616.98 Total for Item 14.1 413.63 129.40 0.00 0.00 0.00 0.00 54.30 19.64 616.98 ITEM 14.2 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Wall or partition members 220 50 x 50mm 47.97 m 118.97 39.34 0.00 0.00 0.00 0.00 15.83 5.76 3.75 179.89 Subtotal for G ... 118.97 39.34 0.00 0.00 0.00 0.00 15.83 5.76 179.89 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 65 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 66. M SURFACE FINISHES M20 Plastered/Rendered/Roughcast coatings Gypsum plasterboard to BS 1230 Fixing with screws to ceilings 221 12.5 mm Plain Wallboard over 300 mm wide 10.25 m2 73.39 22.96 0.00 0.00 0.00 0.00 9.64 3.49 10.68 109.47 Subtotal for M Surface Finishes 73.39 22.96 0.00 0.00 0.00 0.00 9.64 3.49 109.47 Total for Item 14.2 192.36 62.30 0.00 0.00 0.00 0.00 25.47 9.25 289.36 ITEM 14.3 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Wall or partition members 222 50 x 75mm 60.19 m 190.20 65.01 0.00 0.00 0.00 0.00 25.28 9.03 4.81 289.51 Subtotal for G ... 190.20 65.01 0.00 0.00 0.00 0.00 25.28 9.03 289.51 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 66 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 67. P BUILDING FABRIC SUNDRIES P10 Sundry insulation/proofing work/fire stops Insulating quilts Acoustic insulating quilts 223 50 mm 7.55 m2 11.93 25.07 0.00 0.00 0.00 0.00 3.70 1.36 5.57 42.05 Subtotal for P Building Fabric ... 11.93 25.07 0.00 0.00 0.00 0.00 3.70 1.36 42.05 M SURFACE FINISHES M20 Plastered/Rendered/Roughcast coatings Gypsum plasterboard to BS 1230 Fixing with screws to timber or steel stud framing 224 12.5 mm Plain Wallboard over 300 mm wide 30.20 m2 195.09 67.65 0.00 0.00 0.00 0.00 26.27 9.66 9.89 298.68 Subtotal for M Surface Finishes 195.09 67.65 0.00 0.00 0.00 0.00 26.27 9.66 298.68 Total for Item 14.3 397.22 157.73 0.00 0.00 0.00 0.00 55.25 20.05 630.24 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 67 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 68. ITEM 14.4 K LININGS/SHEATHING/DRY PARTITIONING K11 Rigid sheet flooring/sheathing/linings/casings Sheet linings and casings Tile backer boards 225 12.5mm Wediboard 5.93 m2 49.52 142.97 0.00 0.00 0.00 0.00 19.27 7.00 36.89 218.76 Subtotal for K ... 49.52 142.97 0.00 0.00 0.00 0.00 19.27 7.00 218.76 Total for Item 14.4 49.52 142.97 0.00 0.00 0.00 0.00 19.27 7.00 218.76 ITEM 14.5 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Wall or partition members 226 38 x 50mm 52.80 m 166.85 39.60 0.00 0.00 0.00 0.00 20.59 7.39 4.44 234.43 Subtotal for G ... 166.85 39.60 0.00 0.00 0.00 0.00 20.59 7.39 234.43 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 68 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 69. M SURFACE FINISHES M20 Plastered/Rendered/Roughcast coatings Gypsum plasterboard to BS 1230 Fixing with screws to timber or steel stud framing 227 12.5 mm Plain Wallboard over 300 mm wide 20.86 m2 134.76 46.73 0.00 0.00 0.00 0.00 18.15 6.68 9.89 206.31 Subtotal for M Surface Finishes 134.76 46.73 0.00 0.00 0.00 0.00 18.15 6.68 206.31 Total for Item 14.5 301.61 86.33 0.00 0.00 0.00 0.00 38.74 14.07 440.74 ITEM 14.6 M SURFACE FINISHES M20 Plastered/Rendered/Roughcast coatings Retarded hemihydrate gypsum ("Thistle") plasters to BS 1191, Class B 3 mm board finish on walls or ceilings including scrimming joints 228 over 300 mm wide 93.73 m2 589.56 66.55 0.00 0.00 0.00 0.00 65.61 24.37 7.96 746.09 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 69 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 70. M SURFACE continued ... M20 Plastered/Rendered/Roughcast coatings continued ... Plastering sundries Galvanised plaster beads 229 thin coat angle bead 52.55 m 64.11 22.07 0.00 0.00 0.00 0.00 8.41 3.15 1.86 97.74 Subtotal for M Surface Finishes 653.67 88.62 0.00 0.00 0.00 0.00 74.02 27.52 843.83 Total for Item 14.6 653.67 88.62 0.00 0.00 0.00 0.00 74.02 27.52 843.83 ITEM 14.8 M SURFACE FINISHES M20 Plastered/Rendered/Roughcast coatings Retarded hemihydrate gypsum ("Thistle") plasters to BS 1191, Class B 13 mm two coat plastering on brick or block walls 230 over 300 mm wide 62.70 m2 1040.82 217.57 0.00 0.00 0.00 0.00 126.03 45.77 22.81 1,430.19 Subtotal for M Surface Finishes 1040.82 217.57 0.00 0.00 0.00 0.00 126.03 45.77 1,430.19 Total for Item 14.8 1040.82 217.57 0.00 0.00 0.00 0.00 126.03 45.77 1,430.19 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 70 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 71. ITEM 14.10 M SURFACE FINISHES M20 Plastered/Rendered/Roughcast coatings Gypsum plasterboard to BS 1230 Fixing with screws to ceilings 231 12.5 mm Plain Wallboard over 300 mm wide 9.17 m2 65.66 20.54 0.00 0.00 0.00 0.00 8.62 3.12 10.68 97.94 Retarded hemihydrate gypsum ("Thistle") plasters to BS 1191, Class B 3 mm board finish on walls or ceilings including scrimming joints 232 over 300 mm wide 9.17 m2 57.68 6.51 0.00 0.00 0.00 0.00 6.42 2.38 7.96 72.99 Subtotal for M Surface Finishes 123.34 27.05 0.00 0.00 0.00 0.00 15.04 5.50 170.93 Total for Item 14.10 123.34 27.05 0.00 0.00 0.00 0.00 15.04 5.50 170.93 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 71 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 72. ITEM 15.1 L WINDOWS/DOORS/STAIRS L20 Doors/shutters/hatches Softwood door frames and linings Door lining sets 233 32 x 115mm internal door lining with loose stops 3.00 nr 47.43 38.97 0.00 0.00 0.00 0.00 8.64 3.15 32.73 98.19 Subtotal for L Windows/Doors/Stairs 47.43 38.97 0.00 0.00 0.00 0.00 8.64 3.15 98.19 Total for Item 15.1 47.43 38.97 0.00 0.00 0.00 0.00 8.64 3.15 98.19 ITEM 15.2 Z PC SUMS PC Sums associated with the project 234 supply of internal doors, 4 nr @ £120 each item 0.00 0.00 0.00 0.00 0.00 480.00 0.00 15.90 495.90 495.90 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 480.00 0.00 15.90 495.90 L WINDOWS/DOORS/STAIRS L20 Doors/shutters/hatches Fixing 235 hang internal door in 1 pair of butt hinges 4.00 nr 67.76 0.00 0.00 0.00 0.00 0.00 6.76 2.48 19.25 77.00 Subtotal for L Windows/Doors/Stairs 67.76 0.00 0.00 0.00 0.00 0.00 6.76 2.48 77.00 Total for Item 15.2 67.76 0.00 0.00 0.00 0.00 480.00 6.76 18.38 572.90 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 72 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 73. ITEM 15.3 Z PC SUMS PC Sums associated with the project 236 supply of JEDO door lever handles, 4 @ £17.49 each item 0.00 0.00 0.00 0.00 0.00 69.96 0.00 2.32 72.28 72.28 237 supply of JEDO satin thumb turn item 0.00 0.00 0.00 0.00 0.00 7.71 0.00 0.26 7.97 7.97 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 77.67 0.00 2.58 80.25 P BUILDING FABRIC SUNDRIES P21 Ironmongery Fixing only to softwood Door handles 238 lever handles on rose 4.00 pair 32.52 0.00 0.00 0.00 0.00 0.00 3.24 1.20 9.24 36.96 Latches 239 thumb latches 1.00 nr 13.55 0.00 0.00 0.00 0.00 0.00 1.36 0.49 15.40 15.40 240 75mm mortice latch 3.00 nr 54.18 0.00 0.00 0.00 0.00 0.00 5.43 1.98 20.53 61.59 Butt hinges 241 100mm 4.00 pair 28.00 0.00 0.00 0.00 0.00 0.00 2.80 1.04 7.96 31.84 Subtotal for P Building Fabric ... 128.25 0.00 0.00 0.00 0.00 0.00 12.83 4.71 145.79 Total for Item 15.3 128.25 0.00 0.00 0.00 0.00 77.67 12.83 7.29 226.04 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 73 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 74. ITEM 15.4 Z PC SUMS PC Sums associated with the project 242 additional ironmongery item 0.00 0.00 0.00 0.00 0.00 300.00 0.00 9.94 309.94 309.94 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 300.00 0.00 9.94 309.94 Total for Item 15.4 0.00 0.00 0.00 0.00 0.00 300.00 0.00 9.94 309.94 ITEM 15.5 Z PC SUMS PC Sums associated with the project 243 supply & fix new section of staircase including mopstick handrails item 0.00 0.00 0.00 0.00 0.00 500.00 0.00 16.56 516.56 516.56 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 500.00 0.00 16.56 516.56 Total for Item 15.5 0.00 0.00 0.00 0.00 0.00 500.00 0.00 16.56 516.56 ITEM 15.7 P BUILDING FABRIC SUNDRIES P20 Unframed isolated trims/skirtings/sundry items Skirtings, picture rails, architraves and the like Wrought softwood skirtings 244 25 x 75 mm Torus 48.09 m 119.26 72.62 0.00 0.00 0.00 0.00 19.24 7.21 4.54 218.33 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 74 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 75. P BUILDING FABRIC continued ... P20 Unframed isolated continued ... Skirtings, picture rails, architraves and the continued ... Wrought softwood architraves 245 19 x 75 mm chamfered 40.00 m 99.20 54.80 0.00 0.00 0.00 0.00 15.60 5.60 4.38 175.20 Subtotal for P Building Fabric ... 218.46 127.42 0.00 0.00 0.00 0.00 34.84 12.81 393.53 Total for Item 15.7 218.46 127.42 0.00 0.00 0.00 0.00 34.84 12.81 393.53 ITEM 15.8 Z PC SUMS PC Sums associated with the project 246 provide gas bottle enclosure; supply & fix item 0.00 0.00 0.00 0.00 0.00 750.00 0.00 24.84 774.84 774.84 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 750.00 0.00 24.84 774.84 Total for Item 15.8 0.00 0.00 0.00 0.00 0.00 750.00 0.00 24.84 774.84 ITEM 15.8 Z PC SUMS PC Sums associated with the project 247 supply gas bottles and switchover valve item 0.00 0.00 0.00 0.00 0.00 115.00 0.00 3.81 118.81 118.81 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 115.00 0.00 3.81 118.81 Total for Item 15.8 0.00 0.00 0.00 0.00 0.00 115.00 0.00 3.81 118.81 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 75 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 76. ITEM 16.3 Z PC SUMS PC Sums associated with the project 248 sealant sub-contractor for 0.5 day item 0.00 0.00 0.00 0.00 250.00 0.00 0.00 8.28 258.28 258.28 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 250.00 0.00 0.00 8.28 258.28 Total for Item 16.3 0.00 0.00 0.00 0.00 250.00 0.00 0.00 8.28 258.28 ITEM 16.4 Z PC SUMS PC Sums associated with the project 249 Lamona Ceramic 1.5 bowl sink including waste and taps item 0.00 0.00 0.00 0.00 0.00 346.50 0.00 11.48 357.98 357.98 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 346.50 0.00 11.48 357.98 N FURNITURE/EQUIPMENT N13 Sanitary appliances/fittings Fixing only equipment Connections to service and waste pipes not included 250 Sink units with waste and overflow fittings, plug and chain - fitted to sink units 1.00 nr 0.00 1.06 0.00 0.00 93.59 0.00 9.47 3.45 107.57 107.57 Subtotal for N Furniture/Equipment 0.00 1.06 0.00 0.00 93.59 0.00 9.47 3.45 107.57 Total for Item 16.4 0.00 1.06 0.00 0.00 93.59 346.50 9.47 14.93 465.55 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 76 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 77. ITEM 16.5 Z PC SUMS PC Sums associated with the project 251 Lamona Ceramic single bowl sink including waste and taps item 0.00 0.00 0.00 0.00 0.00 183.00 0.00 6.06 189.06 189.06 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 183.00 0.00 6.06 189.06 N FURNITURE/EQUIPMENT N13 Sanitary appliances/fittings Fixing only equipment Connections to service and waste pipes not included 252 Sink units with waste and overflow fittings, plug and chain - fitted to sink units 1.00 nr 0.00 1.06 0.00 0.00 93.59 0.00 9.47 3.45 107.57 107.57 Subtotal for N Furniture/Equipment 0.00 1.06 0.00 0.00 93.59 0.00 9.47 3.45 107.57 Total for Item 16.5 0.00 1.06 0.00 0.00 93.59 183.00 9.47 9.51 296.63 ITEM 16.6 Z PC SUMS PC Sums associated with the project 253 Supply ROCA Easy 900 x 900 x 80mm shower tray item 0.00 0.00 0.00 0.00 0.00 141.81 0.00 4.70 146.51 146.51 254 Supply ROCA shower waste to suit above tray item 0.00 0.00 0.00 0.00 0.00 62.29 0.00 2.06 64.35 64.35 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 77 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 78. Z PC SUMS continued ... PC Sums associated with the project continued ... 255 Supply ROCA L90 shower mixer valve item 0.00 0.00 0.00 0.00 0.00 197.61 0.00 6.55 204.16 204.16 256 Supply ROCA Raindream circular shower head item 0.00 0.00 0.00 0.00 0.00 167.67 0.00 5.55 173.22 173.22 257 Supply ROCA 500mm support arm item 0.00 0.00 0.00 0.00 0.00 41.67 0.00 1.38 43.05 43.05 258 Supply ROCA L90 basin mixer tap item 0.00 0.00 0.00 0.00 0.00 172.91 0.00 5.73 178.64 178.64 259 Supply ROCA Nexo 500 corner cloakroom basin item 0.00 0.00 0.00 0.00 0.00 94.34 0.00 3.12 97.46 97.46 260 Supply ROCA Nexo close coupled WC item 0.00 0.00 0.00 0.00 0.00 216.71 0.00 7.18 223.89 223.89 261 Supply ROCA Nexo WC seat & cover item 0.00 0.00 0.00 0.00 0.00 48.93 0.00 1.62 50.55 50.55 262 Supply Mira Beam 900mm pivot shower door item 0.00 0.00 0.00 0.00 0.00 224.38 0.00 7.43 231.81 231.81 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 1368.32 0.00 45.32 1,413.64 N FURNITURE/EQUIPMENT N13 Sanitary appliances/fittings Fixing only equipment Connections to service and waste pipes not included 263 Shower tray 1.00 nr 0.00 0.00 0.00 0.00 101.72 0.00 10.17 3.71 115.60 115.60 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 78 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 79. N continued ... N13 Sanitary continued ... Fixing only continued ... Connections to service and waste pipes not continued ... 264 Shower mixer 1.00 nr 0.00 0.00 0.00 0.00 123.15 0.00 12.32 4.49 139.96 139.96 265 Shower screen 1.00 nr 0.00 0.00 0.00 0.00 158.48 0.00 15.85 5.77 180.10 180.10 266 Wash hand basin 1.00 nr 0.00 0.00 0.00 0.00 75.92 0.00 7.59 2.77 86.28 86.28 267 Vitreous china lavatory basins with waste fitting, plug, chain and stay, bracket plugged to wall 1.00 nr 0.00 0.00 0.00 0.00 82.64 0.00 8.26 3.01 93.91 93.91 Subtotal for N Furniture/Equipment 0.00 0.00 0.00 0.00 541.91 0.00 54.19 19.75 615.85 Total for Item 16.6 0.00 0.00 0.00 0.00 541.91 1368.32 54.19 65.07 2,029.49 ITEM 16.7 R DISPOSAL SYSTEMS R11 Foul drainage above ground Sub-contract purchase 268 32mm waste pipe including elbows and branches 3.00 m 0.00 0.00 0.00 0.00 22.05 0.00 2.22 0.81 8.36 25.08 269 40mm waste pipe including elbows and branches 9.00 m 0.00 0.00 0.00 0.00 78.30 0.00 7.83 2.88 9.89 89.01 270 110mm waste pipe including elbows and branches 0.30 m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 79 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 80. R DISPOSAL continued ... R11 Foul drainage above ground continued ... Sub-contract continued ... 271 two storey soil stack 1.00 nr 0.00 0.00 0.00 0.00 495.45 0.00 49.55 18.05 563.05 563.05 Subtotal for R Disposal Systems 0.00 0.00 0.00 0.00 595.80 0.00 59.60 21.74 677.14 Total for Item 16.7 0.00 0.00 0.00 0.00 595.80 0.00 59.60 21.74 677.14 ITEM 17.1 M SURFACE FINISHES M40 Stone/Concrete/Quarry/Ceramic tiling/Mosaic Floor Tiles Fixing with adhesive 272 over 300 mm wide; ASS Daple stube panaria wood effect tiles 200 x 905mm 50.54 m2 1590.49 2370.33 0.00 0.00 0.00 0.00 396.23 144.54 89.07 4,501.60 Floor & Wall Tiles 273 over 300 mm wide; Nettuno noce Cisa Let Fontare tiles 333 x 333mm 22.19 m2 698.32 2775.75 0.00 0.00 0.00 0.00 347.50 126.48 177.92 3,948.04 Subtotal for M Surface Finishes 2288.81 5146.08 0.00 0.00 0.00 0.00 743.73 271.02 8,449.64 Total for Item 17.1 2288.81 5146.08 0.00 0.00 0.00 0.00 743.73 271.02 8,449.64 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 80 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 81. ITEM 17.3 M SURFACE FINISHES M40 Stone/Concrete/Quarry/Ceramic tiling/Mosaic Floor & Wall tiling accessories Schulter Ditra matting 274 Ditra 25 matting over 300 mm wide 54.10 m2 144.99 472.83 0.00 0.00 0.00 0.00 61.67 22.72 12.98 702.22 Subtotal for M Surface Finishes 144.99 472.83 0.00 0.00 0.00 0.00 61.67 22.72 702.22 Total for Item 17.3 144.99 472.83 0.00 0.00 0.00 0.00 61.67 22.72 702.22 ITEM 18.1 M SURFACE FINISHES M60 Painting/Clear finishing General surfaces Two coats of Dulex coloured matt emulsion paint over 300 mm girth 275 smooth plaster 140.93 m2 528.49 135.29 0.00 0.00 0.00 0.00 66.24 23.96 5.35 753.98 Knot, prime, stop and paint one undercoat and one coat of satinwood finish paint on joinery 276 over 300 mm girth 15.12 m2 54.13 24.80 0.00 0.00 0.00 0.00 7.86 2.87 5.93 89.66 277 isolated surfaces, not exceeding 300 mm girth 93.09 m 133.12 50.27 0.00 0.00 0.00 0.00 18.62 6.52 2.24 208.52 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 81 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 82. M SURFACE continued ... M60 continued ... General surfaces, externally Knot, prime, stop and paint two undercoats and one coat of gloss finish paint on joinery 278 over 300 mm girth 3.20 m2 20.03 5.50 0.00 0.00 0.00 0.00 2.56 0.93 9.07 29.02 279 isolated surfaces, not exceeding 300 mm girth 35.17 m 87.93 18.99 0.00 0.00 0.00 0.00 10.55 3.87 3.45 121.34 M52 Decorative papers/fabrics Generally Prepare, size and hang wallpaper supplied by others to 280 walls 51.22 m2 210.51 11.78 0.00 0.00 0.00 0.00 22.02 8.20 4.93 252.51 Subtotal for M Surface Finishes 1034.21 246.63 0.00 0.00 0.00 0.00 127.85 46.35 1,455.03 Total for Item 18.1 1034.21 246.63 0.00 0.00 0.00 0.00 127.85 46.35 1,455.03 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 82 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 83. ITEM 19.1 M SURFACE FINISHES M51 Edge fixed carpeting Underlay Latex carpet underlay to floors level and to falls not exceeding 15 degrees from horizontal on timber base 281 exceeding 300 m wide 28.45 m2 25.32 34.42 0.00 0.00 0.00 0.00 5.97 2.28 2.39 68.00 Fitted carpet Medium duty tufted wool/nylon carpet fixed with gripper rods to floors level and to floors not exceeding 15 degrees from horizontal on timber base 282 exceeding 300 m wide 28.45 m2 162.73 652.93 0.00 0.00 0.00 0.00 81.65 29.59 32.58 926.90 Subtotal for M Surface Finishes 188.05 687.35 0.00 0.00 0.00 0.00 87.62 31.87 994.90 Total for Item 19.1 188.05 687.35 0.00 0.00 0.00 0.00 87.62 31.87 994.90 ITEM 21.1 Z PC SUMS PC Sums associated with the project 283 Supply of Kitchen & Utility units; Ref Howdens quotation dated 1st April 2015 item 0.00 0.00 0.00 0.00 0.00 10226.35 0.00 338.00 10565.08 10,565.08 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 83 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 84. Z PC SUMS continued ... PC Sums associated with the project continued ... 284 Fitting of Kitchen, Utility units and white goods item 0.00 0.00 0.00 0.00 0.00 2000.00 0.00 66.25 2066.25 2,066.25 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 12226.35 0.00 404.25 12,631.33 Total for Item 21.1 0.00 0.00 0.00 0.00 0.00 12226.35 0.00 404.25 12,631.33 ITEM 22.1 P BUILDING FABRIC SUNDRIES P30 Trenches/Pipeways/Pits for buried engineering services Excavate by hand Trenches to receive service pipes, cables etc, grade bottom, fill in and compact and remove surplus - earthwork support not included - average depth not exceeding 285 1.00 m, electricity duct 2.06 m 48.06 3.09 0.52 0.00 0.00 0.00 5.17 1.87 28.50 58.71 Subtotal for P Building Fabric ... 48.06 3.09 0.52 0.00 0.00 0.00 5.17 1.87 58.71 Total for Item 22.1 48.06 3.09 0.52 0.00 0.00 0.00 5.17 1.87 58.71 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 84 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 85. ITEM 22.2 P BUILDING FABRIC SUNDRIES P30 Trenches/Pipeways/Pits for buried engineering services Excavate by hand Trenches to receive service pipes, cables etc, grade bottom, fill in and compact and remove surplus - earthwork support not included - average depth not exceeding 286 1.00 m, water service pipe 8.74 m 203.90 7.34 2.19 0.00 0.00 0.00 21.33 7.78 27.75 242.54 Subtotal for P Building Fabric ... 203.90 7.34 2.19 0.00 0.00 0.00 21.33 7.78 242.54 Total for Item 22.2 203.90 7.34 2.19 0.00 0.00 0.00 21.33 7.78 242.54 ITEM 22.3 Z PC SUMS PC Sums associated with the project 287 UK Power Networks quotation to divert electricity supply item 0.00 0.00 0.00 0.00 0.00 864.00 0.00 28.62 892.62 892.62 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 864.00 0.00 28.62 892.62 Total for Item 22.3 0.00 0.00 0.00 0.00 0.00 864.00 0.00 28.62 892.62 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 85 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 86. ITEM 22.4 D GROUNDWORK D20 Excavating and filling Filling to make up levels Imported MOT Type 1 material 288 not exceeding 0.25 m 1.79 m3 29.91 78.76 0.00 0.00 0.00 0.00 10.87 3.96 68.99 123.49 Surface treatments Compacting 289 surface of filling 17.83 m2 7.67 0.00 1.96 0.00 0.00 0.00 0.89 0.36 0.61 10.88 Subtotal for D Groundwork 37.58 78.76 1.96 0.00 0.00 0.00 11.76 4.32 134.37 Q PAVING/PLANTING/FENCING/SITE FURNITURE Q25 Slab/Brick/Sett/Cobble pavings Plain PCC slab paving Salvaged paving; 50 mm thick slabs, 50 mm sand base, 6 mm straight joints both ways, pointing in cement mortar (1:3), level and to falls only, slab size 290 450 x 450mm 17.83 m2 89.33 103.41 1.60 0.00 0.00 0.00 19.43 7.13 12.39 220.91 Subtotal for Q ... 89.33 103.41 1.60 0.00 0.00 0.00 19.43 7.13 220.91 Total for Item 22.4 126.91 182.17 3.56 0.00 0.00 0.00 31.19 11.45 355.28 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 86 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 87. ITEM 23.1 Z PC SUMS PC Sums associated with the project 291 Thermo Floor quoation for the supply & installation of under floor heating item 0.00 0.00 0.00 0.00 0.00 2130.00 0.00 70.55 2200.55 2,200.55 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 2130.00 0.00 70.55 2,200.55 Total for Item 23.1 0.00 0.00 0.00 0.00 0.00 2130.00 0.00 70.55 2,200.55 ITEM 23.2 T MECHANICAL HEATING/COOLING/REFRIGERATION SYSTEMS T73 Works associated with Heating installations Sub-contract purchase 292 Worcester Bosch boiler 1.00 nr 0.00 0.00 0.00 0.00 1529.22 0.00 152.92 55.72 1737.86 1,737.86 293 210L Megaflo hot water cylinder 1.00 nr 0.00 0.00 0.00 0.00 1718.53 0.00 171.85 62.62 1953.00 1,953.00 Subtotal for T Mechanical ... 0.00 0.00 0.00 0.00 3247.75 0.00 324.77 118.34 3,690.86 Total for Item 23.2 0.00 0.00 0.00 0.00 3247.75 0.00 324.77 118.34 3,690.86 ITEM 23.6 S PIPED SUPPLY SYSTEMS S10 Cold Water Sub-contract purchase 294 cold water point 5.00 nr 0.00 0.00 0.00 0.00 720.95 0.00 72.10 26.25 163.86 819.30 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 87 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 88. S PIPED SUPPLY continued ... S11 Hot water Sub-contract purchase 295 hot water point 4.00 nr 0.00 0.00 0.00 0.00 987.04 0.00 98.72 35.96 280.43 1,121.72 Subtotal for S Piped Supply ... 0.00 0.00 0.00 0.00 1707.99 0.00 170.82 62.21 1,941.02 Total for Item 23.6 0.00 0.00 0.00 0.00 1707.99 0.00 170.82 62.21 1,941.02 ITEM 23.7 T MECHANICAL HEATING/COOLING/REFRIGERATION SYSTEMS T73 Works associated with Heating installations Sub-contract purchase 296 central heating service point 5.00 nr 0.00 0.00 0.00 0.00 2475.40 0.00 247.55 90.20 562.63 2,813.15 297 500mm radiator with TRV 1.00 nr 0.00 0.00 0.00 0.00 154.68 0.00 15.47 5.64 175.79 175.79 298 1000mm radiator with TRV 2.00 nr 0.00 0.00 0.00 0.00 341.84 0.00 34.18 12.46 194.24 388.48 299 1600mm radiator with TRV 4.00 nr 0.00 0.00 0.00 0.00 940.08 0.00 94.00 34.24 267.08 1,068.32 300 Towel rail - fix only; supply of towel rail taken elsewhere* 1.00 nr 0.00 0.00 0.00 0.00 86.09 0.00 8.61 3.14 97.84 97.84 Subtotal for T Mechanical ... 0.00 0.00 0.00 0.00 3998.09 0.00 399.81 145.68 4,543.58 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 88 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 89. Z PC SUMS PC Sums associated with the project 301 supply of towel rail item 0.00 0.00 0.00 0.00 0.00 400.00 0.00 13.25 413.25 413.25 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 400.00 0.00 13.25 413.25 Total for Item 23.7 0.00 0.00 0.00 0.00 3998.09 400.00 399.81 158.93 4,956.83 ITEM 23.8 S PIPED SUPPLY SYSTEMS S10 Cold Water Sub-contract purchase 302 scale inhibitor 1.00 nr 0.00 0.00 0.00 0.00 60.00 0.00 6.00 2.19 68.19 68.19 Subtotal for S Piped Supply ... 0.00 0.00 0.00 0.00 60.00 0.00 6.00 2.19 68.19 Total for Item 23.8 0.00 0.00 0.00 0.00 60.00 0.00 6.00 2.19 68.19 ITEM 24.1 V ELECTRICAL SUPPLY/POWER LIGHTING SYSTEMS V22 General Low Voltage power Sub-contract purchase Complete supply & fix installations 303 consumer unit 1.00 nr 0.00 0.00 0.00 0.00 488.03 0.00 48.80 17.78 554.61 554.61 304 earth bonding 1.00 nr 0.00 0.00 0.00 0.00 177.35 0.00 17.74 6.46 201.55 201.55 305 testing & commisioning 1.00 nr 0.00 0.00 0.00 0.00 88.20 0.00 8.82 3.21 100.23 100.23 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 89 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 90. V ELECTRICAL SUPPLY/POWER LIGHTING SYSTEMS continued ... V22 General Low Voltage power continued ... Sub-contract continued ... Complete supply & fix installations continued ... 306 2-Gang switched socket outlet; White 19.00 nr 0.00 0.00 0.00 0.00 613.13 0.00 61.37 22.42 36.68 696.92 307 extractor fan 4.00 nr 0.00 0.00 0.00 0.00 234.40 0.00 23.44 8.56 66.60 266.40 308 boiler electrics 1.00 nr 0.00 0.00 0.00 0.00 486.52 0.00 48.65 17.73 552.90 552.90 309 non-illuminated fused spur 12.00 nr 0.00 0.00 0.00 0.00 435.24 0.00 43.56 15.84 41.22 494.64 V23 Smoke/Heat/Gas alarms Smoke alarms 310 hard wired smoke alarm 3.00 nr 0.00 0.00 0.00 0.00 211.05 0.00 21.12 7.68 79.95 239.85 Heat alarms 311 hard wired heat alarm 1.00 nr 0.00 0.00 0.00 0.00 70.35 0.00 7.04 2.56 79.95 79.95 V24 Telecoms and Data TV, FM/DAB service points 312 TV point 2.00 nr 0.00 0.00 0.00 0.00 57.96 0.00 5.80 2.12 32.94 65.88 Subtotal for V Electrical ... 0.00 0.00 0.00 0.00 2862.23 0.00 286.34 104.36 3,252.93 Total for Item 24.1 0.00 0.00 0.00 0.00 2862.23 0.00 286.34 104.36 3,252.93 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 90 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 91. ITEM 24.23 V ELECTRICAL SUPPLY/POWER LIGHTING SYSTEMS V21 General lighting Sub-contract purchase Complete supply & fix installations 313 bulkhead light 1.00 nr 0.00 0.00 0.00 0.00 66.13 0.00 6.61 2.41 75.15 75.15 314 downlighter 41.00 nr 0.00 0.00 0.00 0.00 1951.19 0.00 195.16 70.93 54.08 2,217.28 315 ceiling rose; White 2.00 nr 0.00 0.00 0.00 0.00 86.24 0.00 8.62 3.14 49.00 98.00 316 photocell floodlight 6.00 nr 0.00 0.00 0.00 0.00 966.66 0.00 96.66 35.22 183.09 1,098.54 317 1-Gang, 1-Way: Light switch: White 8.00 nr 0.00 0.00 0.00 0.00 259.04 0.00 25.92 9.44 36.80 294.40 318 2-Gang, 2-Way: Light switch: White 2.00 nr 0.00 0.00 0.00 0.00 132.98 0.00 13.30 4.86 75.57 151.14 319 1-Gang, 1-Way: Pull Cord Light Switch: White 1.00 nr 0.00 0.00 0.00 0.00 31.31 0.00 3.13 1.14 35.58 35.58 Subtotal for V Electrical ... 0.00 0.00 0.00 0.00 3493.55 0.00 349.40 127.14 3,970.09 Total for Item 24.23 0.00 0.00 0.00 0.00 3493.55 0.00 349.40 127.14 3,970.09 ITEM 24.28 V ELECTRICAL SUPPLY/POWER LIGHTING SYSTEMS V50 Electric underfloor heating Electric Under Floor heating to 320 wet rooms 3.56 m2 0.00 0.00 0.00 0.00 347.31 0.00 34.75 12.67 110.88 394.73 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 91 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 92. V ELECTRICAL SUPPLY/POWER LIGHTING SYSTEMS continued ... V50 Electric continued ... Electric Under continued ... 321 programmable floor thermostat 1.00 nr 0.00 0.00 0.00 0.00 85.64 0.00 8.56 3.12 97.32 97.32 Subtotal for V Electrical ... 0.00 0.00 0.00 0.00 432.95 0.00 43.31 15.79 492.05 K LININGS/SHEATHING/DRY PARTITIONING K20 Timber board flooring/sheathing/linings/casings Flooring Plywood, width exceeding 300 mm, thickness 322 9mm 3.56 m2 22.50 17.37 0.00 0.00 0.00 0.00 3.99 1.46 12.73 45.32 Subtotal for K ... 22.50 17.37 0.00 0.00 0.00 0.00 3.99 1.46 45.32 Total for Item 24.28 22.50 17.37 0.00 0.00 432.95 0.00 47.30 17.25 537.37 ITEM 27.1 Z PC SUMS PC Sums associated with the project 323 contingency sum item 0.00 0.00 0.00 0.00 0.00 7500.00 0.00 248.43 7748.43 7,748.43 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 7500.00 0.00 248.43 7,748.43 Total for Item 27.1 0.00 0.00 0.00 0.00 0.00 7500.00 0.00 248.43 7,748.43 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 92 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 93. ITEM 28.1 C EXISTING SITE/BUILDINGS/SERVICES C90 Alterations - spot items Remove finishings Floors 324 carpeting 4.74 m2 11.33 0.00 7.11 0.00 0.00 0.00 1.85 0.66 4.42 20.95 Walls, without backing 325 ceramic wall tiles 21.67 m2 94.05 0.00 19.50 0.00 0.00 0.00 11.27 4.12 5.95 128.94 Removing fittings and fixtures Timber mouldings 326 skirtings, architraves or dado rail; dispose of debris off-site or set aside for re-use 13.78 m 29.90 0.00 4.13 0.00 0.00 0.00 3.45 1.24 2.81 38.72 Removing plumbing and engineering installations Sanitary fittings, including capping off service and waste pipes and bringing forward services 327 WC 1.00 nr 85.37 28.63 6.00 0.00 0.00 0.00 12.00 4.37 136.37 136.37 328 wash hand basin 1.00 nr 4.34 0.00 28.00 0.00 0.00 0.00 3.23 1.18 36.75 36.75 329 bath 1.00 nr 127.94 38.52 30.00 0.00 0.00 0.00 19.65 7.16 223.27 223.27 Radiators 330 medium 1.00 nr 42.57 8.39 7.50 0.00 0.00 0.00 5.85 2.13 66.44 66.44 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 93 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 94. C EXISTING continued ... C20 Demolition Demolishing parts of timber structures Softwood studded partitions; dispose of debris off-site 331 plasterboard finish 0.75 m2 6.19 0.00 3.15 0.00 0.00 0.00 0.94 0.34 14.15 10.61 Subtotal for C Existing ... 401.69 75.54 105.39 0.00 0.00 0.00 58.24 21.20 662.05 Z PC SUMS PC Sums associated with the project 332 disconnect electrical installation and make safe for proceeding works item 0.00 0.00 0.00 0.00 0.00 125.00 0.00 4.14 129.14 129.14 Subtotal for Z Pc Sums 0.00 0.00 0.00 0.00 0.00 125.00 0.00 4.14 129.14 Total for Item 28.1 401.69 75.54 105.39 0.00 0.00 125.00 58.24 25.34 791.19 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 94 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p
  • 95. ITEM 28.2 P BUILDING FABRIC SUNDRIES P31 Holes/Chases/Covers/Supports for services Chases Vertical rough chases 333 50 x 50 mm 2.40 m 47.95 0.00 0.00 0.00 0.00 0.00 4.80 1.75 22.71 54.50 Subtotal for P Building Fabric ... 47.95 0.00 0.00 0.00 0.00 0.00 4.80 1.75 54.50 Total for Item 28.2 47.95 0.00 0.00 0.00 0.00 0.00 4.80 1.75 54.50 ITEM 28.3 G STRUCTURAL/CARCASSING METAL/TIMBER G20 Carpentry/Timber framing/First fixing Impregnated sawn softwood - SC3 Grade Wall or partition members 334 50 x 50mm 31.80 m 78.86 26.08 0.00 0.00 0.00 0.00 10.49 3.82 3.75 119.25 Subtotal for G ... 78.86 26.08 0.00 0.00 0.00 0.00 10.49 3.82 119.25 This content is © of Estimating Service 2015. www.estimatingservice.co.uk Page 3 / 95 Qty Unit Labour Cost Material Cost Plant Cost Sub Lab Cost Sub Pur Cost PC Sum Cost Profit Cost Prelims Cost Rate R Ext £ p